Cherwell Creek Coal Pty Ltd v BHP Queensland Coal Investments Pty Ltd & Ors (No 23) [2020] QLC 18
LAND COURT OF QUEENSLAND
CITATION: Cherwell Creek Coal Pty Ltd v BHP Queensland Coal
Investments Pty Ltd & Ors (No 23) [2020] QLC 18
PARTIES: Cherwell Creek Coal Pty Ltd
(ACN 063 763 002)
(applicant)
V
BHP Queensland Coal Investments Pty Ltd
(ACN 098 876 825)
QCT Resources Pty Ltd
(ACN 010 808 705)
BHP Coal Pty Ltd
(ACN 010 595 721)
QCT Mining Pty Ltd
(ACN 010 487 840)
Mitsubishi Development Pty Ltd
(ACN 009 779 873)
QCT Investment Pty Ltd
(ACN 010 487 831)
Umal Consolidated Pty Ltd
(ACN 000 767 386)
(respondents)
FILE NO: MRA1332-08
DIVISION: General division
PROCEEDING: General application
DELIVERED ON: 3 June 2020
DELIVERED AT: Brisbane
HEARD ON: 15 May 2020
HEARD AT: Brisbane
PRESIDENT: FY Kingham
DECISION: I will grant Cherwell Creek leave to rely on the revised
Fifth Amended Annexure A, except for the proposed
amendment to paragraph 17.
I will grant Cherwell Creek leave to amend paragraph
-- 1 of 14 --
2
17 to particularise its claim for compensation by stating
the amount or amounts claimed and how they have been
calculated, including by reference to the special value
claim should it wish to maintain that claim.
I will hear from the parties about costs and the form of
orders to give effect to these reasons and to readjust the
trial timetable for the remaining pre-trial steps.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – PLEADINGS – where the Court
had made orders that any amendments to pleadings were
limited to those required to bring them into conformity with
expert evidence – where the applicant sought to file
pleadings beyond this scope – where the respondent
opposed leave being granted to file the amended pleadings –
where the applicant submitted that the amendments do not
raise any new claims and more clearly articulate their
interpretation of the relevant statute – where the respondents
submitted that the amendments are a significant departure
from the previous formulation of the applicant’s claim –
where the Court granted leave to allow all proposed
amendments except paragraph 17, which failed to
adequately particularise the amount of compensation sought
and how that was calculated
Land Court Act 2000 s 7(b)
Land Court Rules 2000 r 4
Mineral Resources Act 1989 s 334ZJ
Uniform Civil Procedure Rules 1999 r 5, r 155(1)
Allianz Australia Insurance Ltd v Mashaghati [2018] 1 Qd
R 429 [101]; [2017] QCA 127, applied
Aon Risk Services Australia Ltd v Australian National
University (2009) 239 CLR 175; [2009] HCA 27, applied
Australian Securities and Investments Commission v Rich
(2009) 236 FLR 1; [2009] NSWSC 1229, applied
Cherwell Creek Coal Pty Ltd v BHP Queensland Coal
Investments Pty Ltd & Ors (No 6) [2017] QLAC 1, cited
Graham & Linda Huddy Nominees Pty Ltd & Anor v Byrne
& Ors [2016] QSC 221, applied
Harris v Australand Apartments No. 6 Pty Ltd [2011] QSC
204, applied
Sellars v Adelaide Petroleum NL (1994) 179 CLR 221;
[1994] HCA 4, applied
APPEARANCES: N Owens SC, with J Redwood and L Sheptooha (instructed
-- 2 of 14 --
3
by Holding Redlich) for the applicant
S Doyle QC, with A Stumer and S Webster (instructed by
Allens) for the respondent
[1] The lengthy history of this statutory claim for compensation is well documented in
previous decisions and is evident from Cherwell Creek’s application for leave to
deliver a Fifth Amended Annexure A,1 the equivalent of its Statement of Claim in
this proceeding.
[2] The claim is in the final stages of pre-trial preparation. Although the parties have
filed pleadings, the position of the parties has long been that the pleadings would be
refined in light of the expert evidence prepared for the trial.2 For that reason, I
granted the parties leave to amend their pleadings for consistency with the expert
evidence.3 Unless otherwise ordered, I ordered that no party could file further
amended pleadings.4
[3] Cherwell Creek’s proposed amended pleading was out of time and, it accepts, some
of its proposed amendments go beyond the scope of the Court’s leave, hence this
application.
[4] The principles enunciated in Aon Risk Services Australia Ltd v Australian National
University5 apply to the application. Questions of prejudice and delay are central
considerations, including whether the amendments will unnecessarily delay
proceedings, particularly where proposed amendments raise a new claim.6
[5] Cherwell Creek argues there will be no impact on the commencement of the trial. It
is not due to start until 20 August 2020. It has made this application well in advance
of trial and the amendments objected to do not have significant consequences for
pre-trial preparation. The amendments do not represent a substantial reformulation
of its claim. They more clearly articulate Cherwell Creek’s case in the context of its
interpretation of Chapter 12, Part 4 of the Mineral Resources Act 1989, which
governs this claim. They do not raise any new claim.
1 After oral argument, Cherwell Creek revised its proposed amendments to deal with some matters
clarified at the hearing, which reduced the number of matters in contention.
2 Cherwell Creek Coal Pty Ltd v BHP Queensland Coal Investments Pty Ltd & Ors (No 6) [2017]
QLAC 1.
3 Orders made by this Court in the present matter on 17 September 2019.
4 Orders made by this Court in the present matter on 14 November 2019.
5 (2009) 239 CLR 175; [2009] HCA 27.
6 Ibid [5].
-- 3 of 14 --
4
[6] BMA opposed the Court granting leave with respect to many of the amendments.
Some refinements to the proposed pleading made after oral argument substantially
reduced the scope of the dispute. However, BMA maintains that those amendments
it still objects to involve a significant departure from the way in which Cherwell
Creek previously formulated its case, with consequences for expert and lay
evidence, costs thrown away, and delay or disruption to the trial.
[7] I will address the objections maintained by BMA under the following headings:
1. The construction of s 334ZJ and the counterfactuals;
2. The special value case;
3. Particularisation of the claim for compensation; and
4. Other amendments.
The construction of s 334ZJ and the counterfactuals
[8] Although BMA identified the amendments falling in this category as discrete issues,
they are related, and it is convenient to address them together.
[9] The first issue arises in this way. BMA objects to amendments that change the
terminology used in a number of allegations. In some paragraphs of the proposed
pleading, Cherwell Creek wishes to replace an assertion that a certain thing “would”
have happened to an assertion that it “could” have done so.7 It says this is consistent
with, and more clearly articulates, its interpretation of s 334ZJ. BMA says to
introduce the “possibility” rather than the “probability” of a counterfactual
occurring has significant implications for the expert evidence, which has only been
prepared on the latter, not the former, basis.
[10] The second issue relates to the counterfactuals involving Cherwell Creek selling its
rights in coal resource; in either May 2008 or July 2012. BMA says Cherwell Creek
has “walked away from” the counterfactuals. The effect of the proposed
amendments8 is that Cherwell Creek cannot recover compensation for loss of the
opportunity to sell its interests in the resource in either May 2008 or July 2012,
because it has not pleaded it would have done so.
7 Proposed paragraphs 4 (chapeau), 4(b)-(l), 10(f)-(i), (10)(l)-(n).
8 Proposed paragraphs 4(k)(i)-(iii), 13(a)-(b), 14(a)-(b), 17(a)-(b).
-- 4 of 14 --
5
[11] Cherwell Creek says it has not walked away from the counterfactuals. It argues the
amendments make clear the role and relevance of the counterfactuals within the
statutory scheme and valuation exercise. Further, the Court must read the
amendments to which BMA objects in the context of the pleading as a whole.
[12] The central provision is s 334ZJ of the MRA. Section 334ZJ(1) permits Cherwell
Creek to apply to this Court “for an order for the payment of compensation for the
loss of its opportunity, because of the enactment of this part, to commercialise the
MDLA364 coal resource.”
[13] Pursuant to s 334ZJ(4), on that application, this Court must:
(a) decide whether any compensation should be payable; and
(b) if it decides compensation should be payable –
(i) decide the amount of compensation; and
(ii) make an order for payment of the amount…
[14] In making a decision under s 334ZJ(4), s 334ZJ(5) requires the Court to “have
regard to the likelihood that, had this part not been enacted, Cherwell Creek, alone
or in conjunction with another person, would have been able to commercialise the
MDLA364 coal resource, having regard to” a number of stated criteria.
[15] The Court’s task, therefore, is to make two decisions: whether compensation is
payable and, if so, the amount. The nature of those decisions may be equated to
questions of causation and valuation.
[16] A claim for damages for loss of opportunity raises difficult issues about what must
be proved, and to what standard, to establish causation and to assess quantum (or
value).9 For this statutory claim, s 334ZJ uses the phrase “loss of opportunity”
which invites reference to the case law on these issues for claims in contract, tort or
under other statutory regimes. However, those difficult issues must be resolved as a
matter of statutory interpretation. What needs to be proved, and to what standard,
may differ depending on which decision the Court is making pursuant to s 334ZJ(4).
[17] Cherwell Creek argues the distinction between the decisions on causation and
valuation is important. It accepts its current pleading does not draw the distinction,
and the role the counterfactuals play in those decisions, clearly enough.
9 Sellars v Adelaide Petroleum NL (1994) 179 CLR 221; [1994] HCA 4 [38]-[40].
-- 5 of 14 --
6
[18] Cherwell Creek proposes to amend its pleading through paragraph 3A to make it
explicit that it need only prove that, as a result of the commencement of Chapter 12,
Part 4, it has lost a valuable commercial opportunity to commercialise the coal
resource, which it would have done by taking specified steps. That relates to its
intention to commercialise the resource.
[19] In paragraph 4, it proposes to plead the means by which it could have
commercialised the resource. That includes, in paragraph 4(l), “continuing the
extraction and selling of coal…until the earlier of production of the coal becoming
cash flow negative or upon a sale of its interest in the mine.” That assertion relates
to its ability to commercialise the resource.
[20] The effect of paragraph 4(l), if allowed, is that Cherwell Creek will no longer assert
that it would have sold its interests on either of the two dates formerly pleaded.
[21] It is clear from both the proposed amendments and Cherwell Creek’s submissions
that it asserts the dates for the possible sale relate to questions of valuation, not
causation. It says it need not plead nor prove that it would have sold on either of the
dates, to recover compensation assessed by reference to hypothetical sales on those
dates.
[22] BMA argues there is no basis for recovering compensation assessed by reference to
a sale on a particular date unless Cherwell Creek establishes that, but for the
commencement of Chapter 12, Part 4, it would have sold or sought to sell its
interests on that date.
[23] The purpose of pleadings is to expose the issues that must be determined at trial.
Cherwell Creek’s proposed amendments expose a significant dispute between the
parties about the requirements for recovering compensation pursuant to s 334ZJ.
The correct interpretation is a complex question best decided after full argument at
trial. I am not satisfied Cherwell Creek’s interpretation is so untenable that it should
be rejected in a summary way on an application to amend a pleading.
[24] There is, though, the question of the implications of the proposed pleading for the
evidence.
-- 6 of 14 --
7
[25] BMA relied on an affidavit by its solicitor, Mr Hurford, in support of its submission
that the amendments would involve significant revision of the expert evidence.10
Most of the further work identified by Mr Hurford related to an issue since resolved
by Cherwell Creek’s revisions to the proposed pleading made after oral argument.
This clarified that Cherwell Creek maintained that MDLA364 would have been
granted, either as a matter of statutory implication or as a matter of fact. That means
the further work asserted in paragraphs 14 to 27 of Mr Hurford’s affidavit will not
be required.
[26] Mr Hurford also referred to expert reports which considered hypothetical sales on
the pleaded dates.11 However, the parties’ time and expense in obtaining those
reports will not be wasted if the proposed amendments are allowed.
[27] Cherwell Creek has maintained its reliance on hypothetical sales in May 2008 or
July 2012, as they relate to a decision on value. The proposed pleading
particularises statutory criteria the Court must consider by reference to those expert
reports. It is sufficiently obvious from the proposed pleading that Cherwell Creek
does not assert a sale at any other time. That is now on the record. Cherwell Creek
says it will not need to or seek to lead further evidence in support of its proposed
amendments,12 and the parties need not develop any new counterfactual scenario.13
[28] I am not satisfied the change to the way in which the counterfactuals sales are
pleaded, as they pertain to either causation or value, has any serious consequence
for the expert evidence.
[29] The remaining argument on these amendments arises from the change in
terminology from “would” to “could.” BMA says this change from assessing
probabilities (it would occur) to assessing possibilities (it could occur) has
significant implications for the expert evidence. Mr Hurford did not address this in
his affidavit. During argument, BMA referred to the joint expert report of the
environmental experts (Mr Hansen for Cherwell Creek and Mr Smith for BMA).
BMA argues they have each set out their view on the likely timetable for obtaining
10 Affidavit of Stephen James Hurford, filed on 12 May 2020.
11 Ibid [30].
12 T 1-5 line 46 to 1-6 line 3.
13 T1-8 line 1 to line 7.
-- 7 of 14 --
8
environmental approvals,14 “but neither has sought to address the mere possibility
that environmental approvals could have been obtained so as to enable the grant of a
mining lease by July 2010.”15
[30] That example does not persuade me the proposed amendments will have significant
consequences for the evidence. The authors of the report, who include Mr Thatcher
and Mr Ritchie, address the work involved, the likely timing and the risks involved
in environmental regulatory processes prior to the grant of a mining lease, and, after
grant, prior to construction. There are some areas of disagreement about timeframes,
and whether certain discrete regulatory processes would have been triggered, but the
disagreements are limited, concisely stated and the reasons for disagreement appear,
on my brief review of this report, to be explained clearly enough.
[31] The joint expert report, and the oral evidence counsel will adduce from the experts
at trial, is relevant evidence for a live issue in the proceedings: the likelihood of
Cherwell Creek securing the grant of a mining lease by July 2010. However, the
experts could not express their opinion on that assertion, whether as a matter of
possibility or probability. That is for the Court to decide. The experts’ role is to
assist the Court to make that decision, by drawing on their expert knowledge and
experience, and advising what environmental processes may apply, the steps
involved in securing those environmental approvals, and the risks and time involved
in each of those steps.
[32] It should not matter to the experts, and their evidence should not differ, whether the
Court must be satisfied of a grant by July 2010 as a matter of probability or
possibility, and for what purpose (i.e. in determining causation or assessing value).
The Special Value case
[33] Cherwell Creek proposes to add a reference to special value in the pleadings in two
respects. First, it proposes to include it in paragraph 16A as one of the “other
relevant matters” the Court must consider pursuant to s 334Z(5)(h). Second, in
paragraph 17, it claims compensation is to be “assessed having regard to any special
value to BMA.”
14 Joint Expert Report of Robert Thatcher, Peter Hansen, Peter Smith and Douglas Ritchie dated 2
April 2020, Appendix 9.
15 Further Submissions for the Respondents: Applicant’s Application Filed on 1 May 2020 for Leave to
File Fifth Amended Annexure A filed 26 May 2020 [25].
-- 8 of 14 --
9
[34] BMA objects to Cherwell Creek introducing what it says is a new claim. Cherwell
Creek says there is no surprise to BMA, given the expert report of Dr Rudenno,
which BMA relied on when seeking leave to amend its Defence to introduce the
Caval Ridge allegations. It complained then that Cherwell Creek wanted to run a
special value case against it, while opposing proposed amendments to BMA’s
Defence to assert a special loss claim in defence.
[35] I accept that BMA cannot claim to be taken by surprise that Cherwell Creek now
proposes to plead in paragraph 16A that special value to BMA is a “relevant matter”
for s 334ZJ(5)(h).
[36] BMA says it will need to investigate and may wish to lead further lay evidence
about whether BMA would have bought EPC545 from Cherwell Creek.16 This will
involve time and expense and there may be an interlocutory dispute about whether
without prejudice privilege regarding some negotiations between the parties has
been waived.
[37] Cherwell Creek has not pleaded that BMA would have bought EPC545 from
Cherwell Creek and says it need not do so. In any case, Cherwell Creek says it will
not oppose BMA leading further lay evidence on the topic and any dispute about
without prejudice discussions between the parties can be dealt with before trial.
[38] I accept there would be limited consequences for the evidence if paragraph 16A is
allowed. However, the proposed amendment to paragraph 17 to include a special
value claim demands further consideration and I will turn to that now.
Particularisation of the claim for compensation
[39] Paragraph 17 pleads Cherwell Creek’s claim for compensation. The current
pleading quantifies loss (and the claimed compensation) in alternative scenarios.
Proposed paragraph 17 does not do that. It pleads that compensation is to be
“assessed having regard to” a number of matters: the values assigned to each
counterfactual, and the special value case. BMA says this leaves it not knowing
what case it must meet.
16 Affidavit of Stephen James Hurford, filed 12 May 2020 [35]-[37].
-- 9 of 14 --
10
[40] Cherwell Creek argues that the statutory task before the Court is “one of informed
estimation in identifying a fair and appropriate amount of compensation for the
legislative expropriation of [its] rights… for the benefit of BMA.” This involves “an
evaluative judgment rather an inflexible, mechanical application of any single
metric.”17
[41] That may well be so, but it does not answer the complaint that its claim is
inadequately particularised.
[42] Paragraph 17 does not plead an amount, or alternative amounts, that Cherwell Creek
claims by way of compensation. Instead, it says compensation should be assessed
“having regard to” specified matters. Nor does paragraph 17 plead the extent of the
loss Cherwell Creek should be compensated for on the possibilities relating to the
counterfactuals.18 Further, this paragraph introduces a further degree of uncertainty
by introducing a special value claim.
[43] BMA argues that any special value to BMA is not within the ambit of s 334ZJ, but
that is a matter for trial. The difficulty I have with the pleading is that Cherwell
Creek fails to quantify its claim for compensation, as a whole, given the asserted
special value.
[44] In its submissions, Cherwell Creek says its special value claim is relevant to the
market value of property (the rights in EPC545) that has a special potential for
appropriate purchasers, in this case BMA.19 This seems to be consistent with the
approach taken by Dr Rudenno in his 2016 report.20 He did not purport to assess
special value, but relied on BMA’s submissions as evidence of special value, which
supported his argument that his valuation, arrived at using a different methodology,
was reasonable.
[45] However, proposed paragraph 17 separates out special value from the assessments
of fair market value otherwise particularised in paragraph 17. It is not clear whether
Cherwell Creek proposed to argue the amount pleaded for special value is
17 Outline of Submissions on behalf of Cherwell Creek, filed 8 May 2020 [27].
18 Graham & Linda Huddy Nominees Pty Ltd & Anor v Byrne & Ors [2016] QSC 221 [51].
19 Above n 16 [29]; Cherwell Creek’s Reply to Respondent’s Further Submissions filed 26 May 2020,
filed 28 May 2020 [15].
20 Expert Report of Victor Rudenno dated 15 February 2016 [65]-[66].
-- 10 of 14 --
11
encompassed by or in addition to the amounts pleaded in relation to the assessments
of the value of the counterfactuals.
[46] This further obscures Cherwell Creek’s case on the value of its lost opportunity to
commercialise the coal resource.
[47] A properly pleaded claim ensures the basic requirement of procedural fairness, that
the opposite party has the opportunity of meeting the case against it.21 BMA has
good cause to complain it does not know what Cherwell Creek’s case now is on the
decision about valuation.
[48] If this were a damages claim, Cherwell Creek would have to state what amount it
claims by way of damages,22 and how it calculates that claim.23 The Court must
decide compensation in accordance with s 334ZJ, but that requires an assessment of
the loss to be compensated. I see no reason to adopt a different approach to pleading
this claim than applies to a damages claim.
Other amendments
[49] I turn now to two other amendments not addressed above.
[50] First, it proposes to change the date by which it asserts Cherwell Creek would have
applied for a mining lease from “in or about September 2008” to “in or about
December 2008.” Cherwell Creek says the proposed amendments to paragraphs 4(e)
and (f) bring the pleading into conformity with the evidence of Mr Wallin.
[51] Mr Hurford identified some potential implications for expert evidence in his
affidavit.24 All but one of these are individual reports, many of which precede Mr
Wallin’s summary of evidence. Mr Hurford did not explain the implications for
their evidence of the proposed change of date.
[52] Mr Hurford also referred to one joint expert report, by Mr Smith and Mr Hanson,
which deals with the environmental approval process. However, as Cherwell Creek
observes, the change in dates is consistent with the statement in the report that
21 Australian Securities and Investments Commission v Rich (2009) 236 FLR 1 [158]–[169]; [2009]
NSWSC 1229.
22 UCPR r 155(1).
23 Harris v Australand Apartments No. 6 Pty Ltd [2011] QSC 204 [10].
24 Above n 15, [29].
-- 11 of 14 --
12
Cherwell Creek could have submitted a mining lease application in late 2008.25
Further, the experts link timing to the date of grant of an environmental approval,
which involves a different application process, not the date on which Cherwell
Creek would have applied for a mining lease.26
[53] I am not satisfied the proposed change has serious consequences for the expert
evidence.
[54] Second, is the “other relevant matter” pleaded by paragraph 16A(c):
…other matters known, as at the date of the Land Court’s decision under
section 334ZJ(4) of the Act, about the likelihood that the MDLA 364
resource could have been developed and commercialised by the applicant
having regard to the contents of the expert reports relied on by the applicant
addressing the staututory criteria in paragraphs 8-14 above.
[55] BMA says this expands the scope of relevant matters to anything contained in an
expert report and would prevent it from objecting to any part of an expert report on
the ground of relevance. I accept Cherwell Creek’s submission that is not so. The
reference point for the Court’s state of knowledge is the date of its decision,
preserving BMA’s ability to object to evidence on the ground of relevance before or
during the trial.
Conclusion
[56] In exercising its jurisdiction, the Court must act according to the substantial merits
of the case without regard to legal technicalities and forms or the practice of other
courts.27 However, where the rules of the Court do not provide for a matter, the
Uniform Civil Procedure Rules 1999 apply, with necessary changes.28 The purpose
of those rules is to facilitate the just and expeditious resolution of the real issues at a
minimum of expense. The Court must apply them with the objective of avoiding
undue delay, expense and technicality and to facilitate the purpose of the rules.29
[57] Most of the amendments BMA objected to better articulate Cherwell Creek’s
interpretation of s 334ZJ. That interpretation is not so untenable that the
25 Joint Expert Report of Robert Thatcher, Peter Hansen, Peter Smith and Douglas Ritchie dated 2
April 2020, para 3.3(a).
26 Above, para 3.7.
27 Land Court Act 2000 s 7(b).
28 Land Court Rules 2000 r 4.
29 UCPR r 5.
-- 12 of 14 --
13
amendments should be refused. Further, they serve the purpose of pleadings, that is,
to expose the issues for the trial.
[58] The timing of the application is explained by the considerable work the parties were
required to do to bring the pleadings into conformity with the voluminous expert
evidence. I accept it was also an appropriate time for the parties to revisit the precise
formulation of their case.
[59] Cherwell Creek has not raised any new claims and the implications for the evidence
are limited. Cherwell Creek’s revisions to the proposed pleading mean that most of
the further work on the evidence, identified by BMA, will not be necessary. This
materially reduces the risk of the trial being delayed.
[60] There may be some further cost involved in BMA reconsidering its lay evidence on
special value, and there may be further interlocutory disputes about privilege and
waiver. The parties will also have to revisit the timetable for pre-trial steps
regarding the remaining pleadings. In particular, the parties will need to revisit the
particulars previously provided by Cherwell Creek.
[61] I am not persuaded there is a substantial risk that the trial will be delayed if the
proposed amendments are allowed.
[62] A just resolution of proceedings is the paramount objective and factors of speed and
efficiency “must not detract from a proper opportunity being given to the parties to
put their case.”30
[63] Given my conclusions about the effect and implications for evidence of the
proposed amendments, I consider the Aon principles favour granting leave to
Cherwell Creek to rely on all proposed amendments except those to paragraph 17.
[64] I will not give leave to Cherwell Creek to amend paragraph 17 as proposed because
it fails to particularise its claim. I will grant Cherwell Creek an extension of time in
which to deliver a revised paragraph 17 that states the amount or amounts sought by
way of compensation, and how they are calculated, including by reference to the
special value claim should it wish to maintain that claim.
30 Allianz Australia Insurance Ltd v Mashaghati [2018] 1 Qd R 429 [101]; [2017] QCA 127.
-- 13 of 14 --
14
[65] I will hear from the parties about costs and the form of orders to give effect to these
reasons and to readjust the trial timetable for the remaining pre-trial steps.
-- 14 of 14 --
Official source: https://www.sclqld.org.au/caselaw/QLC/2020/018