Allen v G Developments Pty Ltd & Anor [2019] QCA 287
SUPREME COURT OF QUEENSLAND
CITATION: Allen v G Developments Pty Ltd & Anor [2019] QCA 287
PARTIES: JOHN ALLEN (AS TRUSTEE FOR THE BUNDAMBA
TRUST)
(appellant)
v
G DEVELOPMENTS PTY LTD
ACN 116 332 220
(first respondent)
GARRICK GRAHAME BULL
(second respondent)
RICHARD JAMES GARNER
(third respondent)
ALEXANDER SCOTT HAGAN
(fourth respondent)
DALIBOR STEVANOVIC
(fifth respondent)
FILE NO/S: Appeal No 6416 of 2019
SC No 11245 of 2016
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
ORIGINATING
COURT: Supreme Court at Brisbane – [2019] QSC 107 (Bradley J)
DELIVERED ON: 6 December 2019
DELIVERED AT: Brisbane
HEARING DATE: 29 October 2019
JUDGES: Morrison and Philippides JJA and Mullins AJA
ORDERS: 1. Appeal allowed.
2. Paragraphs 2 and 6 of the orders made by Bradley J on
24 May 2019 are set aside.
3. The first and second respondents must pay the
appellant the sum of $1,972,220.52.
4. The first and second respondents must pay the
appellant’s costs of the proceeding below on and from
18 August 2018.
5. The first and second respondents must pay the
appellant’s costs of the appeal.
6. The costs of the application for security for costs filed
on 26 July 2019 are the respondents’ costs in the appeal.
-- 1 of 14 --
2
CATCHWORDS: CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS –
INTERPRETATION OF MISCELLANEOUS CONTRACTS
AND OTHER MATTERS – where the appellant loaned
$1 million to the respondent pursuant to a loan deed to enable
the respondent to complete the purchase and development of
land – where the loan deed embodied a transaction between
commercial parties – where the loan deed contained an express
covenant in clause 4(a) by the borrower to pay interest of
25 per cent per annum payable on the expiration of the
minimum period, which was the earlier of one year after the
date of drawdown or project completion date – where the loan
deed allowed for the variation of the rate of interest after the
expiration of the minimum period – where the principal was
repayable on or before the first anniversary of the drawdown
of the loan – where the appellant asserted that clause 4(a)
should be construed as providing for interest to continue to
accrue if default were made in repayment of the principal –
where the respondent asserted that clause 4(a) provided for the
maximum interest payable under the loan to be $250,000,
irrespective of when the principal was repaid – where the loan
deed must be construed as a whole and to avoid commercial
nonsense – where clause 4(a) should be construed as
incorporating an express obligation to pay interest after the
first year of the loan when default was made in repayment of
the principal
Electricity Generation Corporation v Woodside Energy Ltd
(2014) 251 CLR 640; [2014] HCA 7, cited
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd
(2015) 256 CLR 104; [2015] HCA 37, considered
COUNSEL: S J Lee with J J T Dudley for the appellant
M D Martin QC, with P G Jeffery, for the first and second
respondents
SOLICITORS: HWL Ebsworth Lawyers for the appellant
Evans Lawyers for the first and second respondents
[1] MORRISON JA: I have read the reasons of Mullins AJA and agree with those
reasons and the orders her Honour proposes.
[2] PHILIPPIDES JA: I agree with Mullins AJA.
[3] MULLINS AJA: Mr Allen who was the plaintiff at first instance appeals against the
decision of the learned primary judge on the construction of the loan deed dated
20 January 2010 between Mr Allen as trustee of the Bundamba Trust as the lender
and Radical Developments Pty Ltd and the first respondent G Developments Pty Ltd
as the borrower: Allen v G Developments Pty Ltd [2019] QSC 107 (the reasons).
Mr Allen appeals specifically against the dismissal of the proceeding and the order
that he pay the first respondent’s costs and the costs of Mr Bull (the second
-- 2 of 14 --
3
respondent) of the claim against them, on and from 18 August 2018, to be assessed
on the standard basis. In lieu of those orders, Mr Allen seeks the following orders:
a. the first and second respondents pay the appellant the sum of $2,132,344.42 plus
ongoing interest on $709,327.98 calculated at 25% per annum from and including
30 October 2019 until the Court of Appeal’s judgment, or $485.84 per day;
b. the first and second respondents pay the costs of the appellant of and incidental to
the proceedings below on and from 18 August 2018, to be assessed on the
standard basis;
c. the first and second respondents pay the costs of the appellant of and incidental to
this appeal;
d. the sum of $89,049.99 which was paid to the appellant on or about 17 May 2019
be set off against the total amount due to the appellant pursuant to sub paragraphs
a, b and c above.
[4] The primary judge ordered the first and second respondents to pay Mr Allen’s costs
of his claim against them up to and including 17 August 2018, to be assessed on the
standard basis, and there is no appeal against that order.
The loan deed
[5] The background to the making of the loan is set out at [2]-[12] of the reasons:
“[2] The first defendant G Developments Pty Ltd is part of a group
of companies involved in the building of residential
development projects. From its incorporation in 2005, the
second defendant Garrick Grahame Bull has been the sole
director.
[3] Since 12 January 2006, G Developments has held a licence in
the class Builder – Low Rise issued under the Queensland
Building and Construction Commission Act 1991 (Qld). In that
period, it has undertaken 1,466 residential construction jobs,
with a total value over $334 million. There are no conditions on
its licence. It has not been the subject of any tribunal direction
orders, disciplinary action or orders, recorded convictions,
exclusions, bans, disqualifications, infringement notices or
demerit points. It has received two directions to rectify
structural work. It has complied with each.
[4] On 15 May 2009, G Developments entered into a written
contract to purchase land at 10 Creek Street, Bundamba. The
land was considered a potential development site, suitable for
the construction of 20 strata title units. The contract specified
a purchase price of $1,050,000, and was subject to finance.
[5] Between 15 May 2009 and early January 2010,
G Developments was unable to obtain finance to complete the
purchase of the land. Over that period, G Developments paid
deposits totalling $80,000 to the seller and, it appears, the
purchase price was adjusted by agreement to become
$1.07 million.
-- 3 of 14 --
4
[6] In early 2010, Mr Bull approached the third defendant Richard
James Garner about arranging funding for the land purchase and
also for the associated development project. At the time
Mr Garner was a finance broker and property marketer, with
experience in sourcing funds for projects like that proposed for
the Bundamba land.
[7] On 14 January 2010, Radical Developments Pty Ltd was
incorporated, with Mr Garner, the fourth defendant Alexander
Scott Hagan, and the fifth defendant Dalibor Stevanovic as its
directors. Mr Garner and Mr Stevanovic each held 50 ordinary
shares and Mr Hagan held 33 ordinary shares in the company.
[8] Also on 14 January 2010, G Developments and Radical
Developments ‘agreed to subscribe to interests in a joint venture
in relation to the development, management and operation’ of
the project for the Bundamba land. The two companies entered
into a written joint venture agreement dated 14 January 2010 to
‘record the nature of their relationship, rights and obligations.’
[9] By the joint venture agreement, G Developments and Radical
Developments agreed to cause to be advanced ‘all moneys
required to establish the Project, estimated at $1,100,000’,
which approximated the balance purchase price and associated
settlement costs; and to ‘jointly seek funding on behalf of the
venture in the sum of $3,600,000’, the then estimated cost of
developing the project. No fee was to be charged by either joint
venturer for any services rendered to the project, unless
mutually agreed. G Developments was appointed the ‘Project
Manager.’
[10] Mr Bull’s evidence, which was not contested, is that: the
contribution to the project by Radical Developments and its
directors was to comprise sourcing the funding to complete the
purchase of the land, organising construction funding, and
selling the units in the project; and G Developments’
contribution was to be organising the sub-division of the land
and building the units.
[11] On about 20 January 2010, the plaintiff John Allen loaned
$1 million to Radical Developments and G Developments.
According to Mr Bull, whose evidence I accept in this respect,
Mr Garner had arranged the loan from Mr Allen.
[12] Mr Allen drew the loan money from funds he held as trustee of
the Bundamba Trust. The Bundamba Trust is a unit trust
governed by a deed made on 15 January 2010, the day after
Radical Developments was incorporated and the joint venture
agreement was signed.” (footnote omitted)
[6] Radical Developments was deregistered on 8 June 2014 and therefore can be ignored
for the purpose of the appeal. The second respondent is one of the guarantors under
the loan deed. The purpose of the loan set out in recital A of the loan deed was to
-- 4 of 14 --
5
enable the borrower to complete the purchase and/or development of identified land
at Bundamba.
[7] The relevant provisions of the loan deed are set out at [16] of the reasons. Clause 4
of the loan deed deals with interest:
“(a) The Borrower covenants that the Borrower will pay interest on
the Secured Monies computed at the rate of twenty five percent
per annum and payable on the date referred to in Item 8 of the
Schedule being on one year from the date of drawdown or
project completion whichever is earlier (hereinafter called ‘the
due date’) (hereinafter called (‘the date of first payment’) at
the fixed rate namely the rate referred to in Item 5 of the
Schedule (hereinafter called ‘the fixed rate’).
(b) The parties further agree if the Secured Monies is repaid at any
time prior to the first anniversary date of the initial drawdown,
a minimum payment of twenty-five percent of the loan amount
is payable as interest. The parties agree that the total payment
incorporates a penalty amount in compensation for the
opportunity costs of the lenders entering into this agreement and
is fair and reasonable in the circumstances.
(c) At the expiration of the period referred to in Item 6 of the
Schedule (hereinafter called ‘the minimum period’) the
Lender may at its discretion at any time and from time to time
thereafter give notice in writing to the Borrower varying the
rates of interest payable hereunder and may in such notice
prescribe a new rate. The new rate of interest so prescribed shall
become effective from the date of the notice and thereupon the
Borrower shall be liable under the covenants to pay interest at
the new rate and this Deed shall be deemed to be varied
accordingly.”
[8] Clause 5 of the loan deed deals with repayments:
“(a) The Borrower covenants that the Borrower will repay the Loan
Amount and any other monies owing to the Lender pursuant to
the provisions hereof on or before the date referred to in Item 7
of the Schedule (hereinafter called ‘the repayment date’)
(b) The Borrower further covenants that the Borrower will repay
the Principal Sum forthwith upon written demand being made
at any time after the happening of any of the following events:
(i) Default being made by the Borrower in the due or
punctual payment of any monies which comprise part of
the secured monies or in the due or punctual observance
or performance of any other obligation on the part of the
Borrower under this Deed:
[Other events of default which do not affect the construction
of the loan deed are then listed]
…
-- 5 of 14 --
6
(c) It is hereby agreed and declared that all monies received by the
Lender in reduction of the secured monies shall be applied by
the Lender firstly in reduction of any interest due but unpaid and
secondly in reduction of the remainder of the secured monies”
[9] The only other provision of the loan deed that contains a covenant by the borrower to
make certain payments of costs and expenses is clause 6:
“The Borrower covenants to pay all costs, charges and expenses
including legal and other professional fees, stamp duty and registration
fees paid or payable by the Lender for or in relation to the preparation
execution stamping and registration of this Deed or the obtaining of
any advice which the Lender reasonably requires in consequence of
the happening of any of the events referred to in Clause 5(b) hereof,
the exercise or attempted exercise of any of the rights powers and
privileges of the Lender hereunder.”
[10] The term “Principal Sum” is defined in clause 1(b) of the loan deed to mean “in
relation to any day, the difference between the total of all amounts which have been
lent by the Lender to the Borrower pursuant to Clause 3 hereof as at 5:00pm on that
day and the total of all amounts which have been repaid by the Borrower to the Lender
hereunder as at 5:00pm on that day”. The term “Secured Monies” is defined in
clause 1(c) of the loan deed to mean “all monies which are or which hereafter may
become owing or payable by the Borrower to the Lender or under or pursuant to this
Deed”. These definitions are specified to apply “unless contrary intention appears”.
[11] The schedule to the loan deed sets out the “Items” that are referred to in the loan deed.
Item 8 which is referred to in clause 4(a) and has the description “THE MONTHLY
INSTALMENT” reads “NIL”. Item 3 purports to be “THE DATE OF FIRST
REPAYMENT” and is incomplete, as it specifies “ day of 2011 or date
of practical completion of project whichever is earlier”, but there is also no reference
to Item 3 in the clauses of the loan deed.
[12] The subject matter of Item 5 is “THE FIXED RATE” and it specifies:
“Twenty five percent (25% per annum) with a minimum payment of
25% of the loan amount if the loan amount is paid back within
365 days.”
[13] Item 6 deals with “THE MINIMUM PERIOD” and specifies “One year or project
completion date whichever is earlier”.
[14] Item 7 contains “THE REPAYMENT DATE” and the date of “20 th day of January
2011” is inserted.
The primary judge’s construction of clause 4(a)
[15] The primary judge referred at [33] of the reasons to the general rule at common law
that “interest is not payable on a debt or a loan in the absence of express agreement
or some course of dealing or custom to that effect” which is referred to in F A Pidgeon
& Son Pty Ltd v Daneshurst Investments Pty Ltd [1986] 1 Qd R 448, 451. The
primary judge then set out the basic elements of an agreement to pay interest at [34]
of the reasons:
-- 6 of 14 --
7
“There are four basic elements of an agreement to pay interest: first,
the agreement that interest will accrue on the principal sum advanced;
second, the rate at which the interest is to be calculated; third, the rests
at which the interest is to accrue; and finally, the date(s) on which the
accrued interest is to be paid.” (footnote omitted)
[16] The primary judge noted at [37] of the reasons that, if the cross reference to Item 8 in
clause 4(a) was an error, it was not of any significance, and then stated:
“The parties described the relevant date expressly in cl 4(a) as ‘one
year from the date of drawdown or project completion whichever is
earlier’. It follows that G Development’s obligation to pay interest at
the agreed rate was to be performed one year from the drawdown date
or on project completion, if that occurred before the one year period
elapsed.”
[17] As there were no specified rests at which interest was accrued, the primary judge
noted at [39] of the reasons “that the agreement appears to be for simple interest on
the amount outstanding at the 25 per cent per annum rate calculated to the date of first
repayment (which is also the due date)”, and referred to the authorities set out in
El Khoury v Harsany [2018] NSWSC 1774 at [48]-[49] for the proposition that
a contractual provision which prescribes interest payable at a particular percentage
rate per annum imposes an obligation to pay simple interest.
[18] The primary judge noted at [44] of the reasons the effect of the first sentence of
clause 4(b) as:
“By this clause, the parties expressly contemplate that the Secured
Monies might be repaid by G Developments within one year (i.e.
‘prior to the first anniversary date of the initial drawdown’). They
agreed that, if this were to occur – whether because drawdown of the
loan occurs after 20 January 2010 or because the project is completed
before 20 January 2011 –then G Developments would make
‘a minimum payment of twenty-five percent of the loan amount … as
interest’.”
[19] The primary judge observed at [47] of the reasons that “nothing in cl 4(b) alters the
date for payment of interest, which remains that specified in cl 4(a)”.
[20] It was common ground at the trial that Mr Allen did not exercise the discretion
conferred by clause 4(c) to give a notice varying “the rates of interest payable
hereunder” and prescribing “a new rate”. The primary judge then set out at [51] of
the reasons Mr Allen’s contention for construction of clause 4(a):
“For Mr Allen it is contended that the parties’ reference in cl 4(c) to a
notice ‘varying the rates of interest payable hereunder’ infers that the
parties agreed by cl 4(a) that, in the absence of such a notice,
G Developments would pay interest on any part of the loan
outstanding after 20 January 2011 at the rate of 25 per cent per annum.
It is said that the language in cl 4(c) cannot be given any sensible
operation unless another provision (inferentially cl 4(a)) operates to
make interest payable at 25 per cent per annum after 20 January 2011
in the absence of a notice under cl 4(c).”
-- 7 of 14 --
8
[21] The primary judge concluded at [54] of the reasons that clause 4(c) of the loan deed
allowed for the variation of the rate of interest by notice, but the date for payment of
interest was not varied, no additional date for payment of interest was agreed, and the
liability to pay interest remained that “under the covenants” elsewhere in the loan
deed, where the only specific covenant to pay interest was in clause 4(a). The primary
judge then gave an example in [55] and [56] of the reasons how the variation of the
rate of interest would have worked, if the project completion date were to occur before
20 January 2011. The example was on the basis that the project completion date
occurred on 20 July 2010, so that the fixed interest of the $250,000 would be payable
on that date, but the loan amount of $1m would not be repayable until 20 January
2011. In that example, clause 4(c) would permit Mr Allen to give a notice varying
the interest rate and, if it was set above 25 per cent, the first respondent had an
incentive to repay the loan amount of $1m earlier than 20 January 2011, because
otherwise interest could then be calculated at the higher rate for the period from the
date of the notice up to 20 January 2011 during which the $1m remained outstanding
(less the sum of $250,000 that had already been paid). The primary judge therefore
observed at [57] of the reasons that “the language in cl 4(c) may be given sensible
effect without any additional interest accruing at 25 per cent per annum after the
repayment date of 20 January 2011”.
[22] Even though the primary judge had recorded at [15] of the reasons that the loan deed
was prepared by the lawyers and accountants based in the Australian Capital Territory
who were advising Mr Allen, it was apparent that another document had been adapted
for the loan deed which resulted in the primary judge observing at [58]-[59] of the
reasons:
“[58] The Loan Deed includes a number of provisions, definitions and
items that are not necessary for the transaction it records. These
appear to be the ghosts of a different transaction – one that
included the payment of a ‘monthly instalment’ from a specified
‘date of first repayment’ with a ‘fixed rate’ of interest for ‘the
minimum period’ and a mechanism to vary ‘the fixed rate’ after
the expiry of ‘the minimum period’.
[59] For such a transaction: cl 4(a) could have provided for a
monthly payment of interest until the loan was repaid in full;
cl 4(b) would have provided for a minimum amount of interest,
in the event of early repayment; and cl 4(c) would have provided
for the fixed rate of interest to be varied by notice at the end of
the minimum period.”
[23] The primary judge’s approach to the construction of clause 4(a) of the loan deed was
set out at [60]-[62] of the reasons:
“[60] The parties could have quite easily adapted cl 4(a) and item 8 to
provide for interest to continue to accrue at ‘the fixed rate’ and
to be paid at regular specified dates after 20 January 2011.
Similarly, a provision could have been included in cl 5 to
provide for a specific rate of interest to apply in the event of
default. That such courses were not taken supports a conclusion
that the parties did not agree for interest to be paid after the
anniversary of the drawdown (or project completion, if that
-- 8 of 14 --
9
occurred earlier) at the 25 per cent per annum rate or at any
agreed rate.
[61] The parties’ use of the words ‘being one year from the date of
drawdown or project completion whichever is earlier
(hereinafter called ‘the due date’)’ in cl 4(a) and the nomination
of ‘NIL’ for ‘the monthly instalment’ dates in item 8 are
consistent with each other. They manifest an intention that, for
the present loan transaction, there would be only a single
payment date in cl 4(a), rather than the series of monthly dates
that might have been nominated in item 8.
[62] The absence of a provision for the calculation or payment of
interest after 20 January 2011, even in the event of default, also
tells against the submissions on behalf of Mr Allen that cl 4(a)
should be construed to impose on G Developments an
obligation to pay interest at 25 per cent per annum after that
date.” (footnote omitted)
[24] It was noted at [63] of the reasons that no case was made that clause 4(a) and Item 8
were affected by mistake and no claim was brought for rectification of the loan deed.
[25] The primary judge made the following observations at [68] of the reasons to support
the conclusion at [69] of the reasons that clause 4(a) was a covenant by the first
respondent to pay Mr Allen interest on all monies payable under the loan deed on the
first anniversary of the drawdown date (or on earlier project completion) at the rate
of 25 per cent per annum and was not a covenant to pay interest (of any rate) on any
outstanding sum on any other date:
“The express terms of the Loan Deed show the parties expected the
project to be financed, built, sold and completed in 12 months or
earlier. Such optimism is neither unusual nor unlikely at the
commencement of a commercial property development. The rate of
interest fixed in the Loan Deed is higher than the rate charged by banks
or other mainstream lenders at the time the Loan Deed was executed.
From the lender’s perspective, the higher rate may reflect a higher risk
attached to the lending. From the borrower’s perspective, it may
reflect the short-term nature of the borrowing and the inability to
obtain funds elsewhere. These circumstances are not determinative,
but they also reinforce a conclusion that by the Loan Deed the parties
agreed that G Developments would pay Mr Allen interest at 25 per
cent for a maximum fixed period of borrowing; and they did not agree
that interest would be paid at that rate indefinitely.”
[26] The primary judge concluded at [70] of the reasons that the first respondent was
obliged to pay Mr Allen pursuant to the loan deed a total of $1.25m on or before
20 January 2011. The first respondent defaulted in the payment of $1.25m on or
before 20 January 2011. By the conclusion of the trial before the primary judge, the
first respondent had paid a total of $1.25m to Mr Allen.
[27] There were other issues to be determined by the primary judge, as a result of further
dealings between the parties after 20 January 2011. There is no challenge to the
findings made by the primary judge in relation to the claims that were determined in
the proceeding arising from the subsequent dealings between the parties.
-- 9 of 14 --
10
Approach to the construction of the loan deed
[28] The loan deed must be construed as an agreement between commercial parties, as set
out at [25] of the reasons:
“The transaction between the parties to the Loan Deed was
commercial in nature. It follows that: the terms of the Loan Deed are
to be understood as a reasonable business person would have
understood them; the commercial purpose or objects to be achieved
are to inform such an understanding; an appreciation of the purpose or
objects is facilitated by understanding the genesis of the transaction,
the background, the context and the market in which the parties are
operating; and the court is entitled to assume the parties intended to
produce a commercial result which makes commercial sense: Electricity
Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640
at 656-7 [35].” (footnote inserted)
[29] The principles relevant to the construction of commercial contracts were summarised
in the joint judgment of French CJ and Nettle and Gordon JJ in Mount Bruce Mining
Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104 at [46]-[51]. That
judgment endorsed the principles referred to in Electricity Generation Corporation v
Woodside Energy Ltd (2014) 251 CLR 640 at [35], noting at [51]:
“Other principles are relevant in the construction of commercial
contracts. Unless a contrary intention is indicated in the contract,
a court is entitled to approach the task of giving a commercial contract
an interpretation on the assumption ‘that the parties … intended to
produce a commercial result’. Put another way, a commercial contract
should be construed so as to avoid it ‘making commercial nonsense or
working commercial inconvenience.” (footnotes omitted)
[30] The fact the loan deed may have been based on a precedent document that contained
extensive provisions that were not necessary for the transaction between the parties
does not alter the approach to the construction of the loan deed as embodying the
transaction between commercial parties.
Is there an obligation to pay interest after the first year of the loan?
[31] The short point of construction that was determined against the appellant by the
primary judge was that the loan deed only required the first respondent to pay interest
for the first year of the loan and that, if there were default in repayment of the loan,
no interest would accrue thereafter, irrespective of the length of the default period.
The appellant submits that the sum of $250,000 is the minimum interest payable on
the loan in accordance with clause 4(b) and Item 5 of the schedule, even if the loan
were repaid before one year from the date of drawdown. The respondents submit that
the sum of $250,000 is the maximum amount payable for interest on the loan under
the deed by virtue of clause 4(a), irrespective of when the principal was repaid or
whether default was made in the repayment of the principal.
[32] The appellant’s submissions are summarised as follows. The phrase “twenty five per
cent per annum” in clause 4(a) and Item 5 of the schedule suggests that interest will
continue to be payable until the loan amount is repaid in full, calculated at the rate of
25 per cent per annum, as otherwise the words “per annum” would be surplusage.
-- 10 of 14 --
11
Clause 4(a) describes the repayment date for interest not only as the “due date”, but
also “the date of first payment”. The phrase “the date of first payment” and the words
“first anniversary date” in clause 4(b) are phrases that connote that interest continues
to accrue under the loan deed after the one year period referred to in clause 4(a). To
the extent the primary judge treated “per annum” in clause 4(a) as merely the way the
money was measured and dismissed the significance of the words “the date of first
payment”, his Honour was in error. It is also relevant that clause 4(a) provides that
interest is payable on the “Secured Monies” which includes amounts that may become
payable under the loan deed, other than the loan amount. Clause 4(c) would have no
work to do, if the only obligation to pay interest under clause 4(a) were limited to the
interest calculated at 25 per cent per annum for the first year of the loan. Clause 5(c)
of the deed would have no work to do, unless interest continued to accrue where the
principal were not repaid on 20 January 2011. There would be no point in stipulating
that repayment was applied first to interest rather than principal, if interest did not
continue to accrue on the principal after 20 January 2011 that had not been repaid by
that date.
[33] The first and second respondents’ submissions are summarised as follows. There is
nothing in clause 4(a) and Item 5 of the schedule which suggests interest would
continue to be payable until the loan amount was repaid in full. The fixed rate referred
to in Item 5 is the rate of 25 per cent which is payable even if the loan were repaid
earlier than 12 months from the date of drawdown. Reference to “per annum” does
not suggest that interest is payable every year until the loan is repaid. It was a one
year loan and the appropriate interest rate was 25 per cent for that year, so the words
“per annum” are not surplusage. The mere reference to “the due date” or “the date of
first payment” does not mean that interest is payable after the initial period of
12 months. In fact, the defined terms in clause 4(a) of “the due date” and “the date
of first payment” can be ignored, as those terms are not repeated in the deed. The
plain meaning of clause 4(a) is the borrower will pay interest limited to 25 per cent
of the loan amount of $1m payable one year from the date of drawdown or project
completion, whichever is earlier, and there is no covenant to pay any interest on any
later date. There was no room for application of clause 4(c) to the transaction
embodied in the deed, as clause 4(c) applied to a loan where interest was payable after
the first year of the loan and was one of the provisions that fell within the primary
judge’s description of “the ghosts of a different transaction”. There was no such
obligation imposed under the deed in respect of the repayment of the loan made by
the appellant to the first respondent.
[34] In the circumstances where the loan was procured to be made by the appellant to the
first respondent where the first respondent had been unable to obtain finance to
complete the purchase of the land for the development proposed by the joint venture,
the respondents’ construction of clause 4(a) that denies the lender the right to claim
interest on the amount of the loan outstanding when the borrower defaulted in
repaying the loan on the first anniversary of the loan (when the project was still
incomplete at that time) does not suggest an agreement between commercial parties.
It would take the clearest language in a commercial agreement to deny the lender the
right to pursue the borrower for interest on the principal outstanding, after default in
repayment of the principal was made. For the reasons that follow, the proper
construction of clause 4(a) is that it includes a covenant to pay interest at the fixed
rate in Item 5 of the schedule, if the loan was not repaid within one year of the date
of drawdown. Clause 4(a) should be read and construed, as if the word “and” were
inserted before, and the word “thereafter” was inserted after, the words “at the fixed
-- 11 of 14 --
12
rate”. Clause 4(a) contains the covenant to pay interest up to one year from the date
of drawdown and a covenant to pay interest at the fixed rate after the expiry of that
year. Although it is awkward that clause 4(a) should be read by inserting those words,
it would be more awkward to construe clause 4(a), as if the words “at the fixed rate
namely the rate referred to in Item 5 of the Schedule” and the content of Item 5 simply
repeated the obligation earlier set out in clause 4(a) to pay interest up to one year from
the date of drawdown and were therefore effectively meaningless.
[35] Clause 4 has three paragraphs that deal with the payment of interest. Clause 4(a)
contains the covenant to pay interest. Clause 4(b) deals with the specific circumstance
of the minimum payment of interest that was required, if the secured monies were
repaid at any time prior to the first anniversary date of the initial drawdown.
Clause 4(c) allows for the variation of the rate of interest after the expiration of the
period referred to in Item 6 of the schedule that is defined as the minimum period and
which was the earlier of one year (after the date of drawdown) or project completion
date.
[36] Clause 4 must be construed in the context of the loan deed as a whole and as
embodying a transaction between commercial parties and to avoid commercial
nonsense. Pursuant to clause 2.1(f) of the loan deed, a schedule to the deed forms
part of the deed. That means that the contents of the schedule which are the items
that are incorporated by reference into the loan deed must be considered in construing
the deed. If the appellant’s contention that clause 4(a) makes no reference to the
payment of interest after the expiry of the earlier of one year from the date of
drawdown or project completion were correct, it leaves no reason for the specification
of the fixed rate in Item 5. If the only interest that were payable was that calculated
at 25 per cent of the loan amount for one year, there would be no purpose in
identifying the fixed rate in clause 4(a) as shown in Item 5 of the schedule. The plain
meaning of Item 5 is for the purpose of specifying the interest rate that applies, if the
loan were not repaid within 365 days or if there were other amounts outstanding under
the loan (such as costs and expenses chargeable to the borrower under clause 6 of the
loan deed). There would otherwise be little point in specifying in Item 5 as to what
the fixed rate of interest was, if interest did not accrue after the first year. Similarly,
clause 4(c) refers to the minimum period specified in Item 6 of the schedule which
can be either one year or the project completion date (whichever is the earlier) before
which the interest rate could be varied. That one year could be the minimum period
also suggests that it was anticipated by the parties that the obligation to pay interest
at the fixed rate would continue after that period of one year. The fact that the primary
judge by an example could show that clause 4(c) could be given effect, if the project
were completed before the first anniversary of the drawdown of the loan, does not
displace that clause 4(c) by its terms was intended to operate also at the expiration of
one year from the drawdown of the loan.
[37] Although it is common ground that clause 4(c) does not itself impose an obligation
to pay interest, but provides the mechanism for varying the rate of interest payable
under the loan deed at the expiration of one year or the project completion date,
whichever is the earlier, clause 4(c) is consistent only with there being an obligation
under another provision for the payment of interest after the expiration of the
minimum period. That assists in construing clause 4(a) as imposing that obligation.
[38] It is apparent that there must be some words omitted from clause 4(a) as there are no
connecting words between the rest of clause 4(a) and the closing words of “at the
-- 12 of 14 --
13
fixed rate namely the rate referred to in Item 5 of the Schedule (hereinafter called ‘the
fixed rate’)”. Clause 4(a) contains a covenant that interest on the secured monies at
the rate of 25 per cent per annum will be payable one year from the date of drawdown
or project completion (whichever was the earlier), but the closing words of clause 4(a)
in conjunction with the balance of the clause can be construed as also containing a
covenant by the borrower to pay interest on the secured monies at the fixed rate
referred to in Item 5 after the first year. It is not essential that rests be stipulated for
the calculation of interest after the first year, because as the primary judge noted at
[39] of the reasons that is otherwise an agreement to pay simple interest. The
obligation to pay interest after the first year was in respect of the secured monies that
remained outstanding. The loan deed specified when the interest for the first year
was payable, but there was no express provision as to when interest that continued to
accrue on the secured monies payable. In the absence of such provision, a demand
was required for payment of that interest. It is not in issue between the parties that
demand was made for the payment of the interest that continued to accrue after the
first year of the loan.
[39] The loan deed was poorly drafted and that gave rise to respectable arguments both for
and against the question of whether interest was payable on the principal sum after
the first year of the loan. There are more indications in the terms of the deed, the
purpose of the loan and the commercial nature of the transaction that favour the
construction of clause 4(a) as containing a covenant to pay interest on the principal
sum that remained outstanding after the first year of the loan than not.
[40] The appellant also made submissions based on what was alleged to be subsequent
conduct of the parties in relation to the meaning of clause 4(a) of the loan deed. The
appellant had not relied on the alleged subsequent conduct of the parties for the
purpose of the construction of the deed before the primary judge. The respondent
opposed consideration of this argument on the basis that it was not something which
the parties specifically addressed in evidence before the primary judge, but that, in
any event, the subsequent conduct of the parties could not assist in the construction
of the deed. In view of the conclusion that I have reached as to the proper construction
of clause 4(a) without regard to the subsequent conduct of the parties, it is
unnecessary to deal with the appellant’s submissions based on alleged subsequent
conduct or the respondent’s opposition to the consideration of those submissions.
Order
[41] The respondents had filed an application for security for costs of the appeal that was
resolved by the appellant’s providing security. The question of the costs of that
application are outstanding. The appellant proposed that the costs of that application
be costs in the appeal or the respondents’ costs in the appeal. The respondents’
preference was for an order that the costs of that application be the respondents’ costs
in the appeal. As the appellant did not provide security until after the application for
security for costs of the appeal was filed, the appropriate order is that those costs be
the respondent’s costs in the appeal. In view of the appellant’s success in the appeal,
the effect of that order is that the respondents will not recover their costs of the
security for costs application. It is still appropriate to make the order, as it means that
the appellant will not recover its costs of the security for costs application.
[42] The orders which should be made are as follows:
1. Appeal allowed.
-- 13 of 14 --
14
2. Paragraphs 2 and 6 of the orders made by Bradley J on 24 May 2019 are set
aside.
3. The first and second respondents must pay the appellant the sum of
$1,972,220.52.
4. The first and second respondents must pay the appellant’s costs of the
proceeding below on and from 18 August 2018.
5. The first and second respondents must pay the appellant’s costs of the appeal.
6. The costs of the application for security for costs filed on 26 July 2019 are the
respondents’ costs in the appeal.
-- 14 of 14 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2019/287