Chapel of Angels Pty Ltd v Hennessy Building Pty Ltd & Anor [2019] QCA 229 (2019) 2 QR 334
SUPREME COURT OF QUEENSLAND
CITATION: Chapel of Angels Pty Ltd v Hennessy Building Pty Ltd &
Anor [2019] QCA 229
PARTIES: CHAPEL OF ANGELS PTY LTD
ACN 154 237 867
(applicant)
v
HENNESSY BUILDING PTY LTD ACN 117 587 998 IN
ITS OWN CAPACITY AND AS TRUSTEE FOR THE
HENNESSEY FAMILY TRUST
ABN 45 515 151 376
(first respondent)
JOHN PAUL HENNESSY
(second respondent)
FILE NO/S: Appeal No 4767 of 2019
DC No 4124 of 2014
DIVISION: Court of Appeal
PROCEEDING: Application for Stay of Execution
ORIGINATING
COURT: District Court at Brisbane – [2018] QDC 218 (Porter QC DCJ)
DELIVERED ON: 25 October 2019
DELIVERED AT: Brisbane
HEARING DATE: 17 October 2019
JUDGE: Morrison JA
ORDERS: Upon the first respondent, by its Counsel, undertaking that
any amounts recovered by the first respondent pursuant to
execution of a judgment for costs will be held in the trust
account of Axia Litigation Lawyers pending further order
of the Court of Appeal:
1. The application is dismissed.
2. The applicant is to pay the first respondent’s costs of
the application.
CATCHWORDS: APPEAL AND NEW TRIAL – PROCEDURE –
QUEENSLAND – STAY OF ORDERS – where the parties
fell into dispute about various aspects of a building contract
between them – where proceedings in the District Court
resulted in orders being made which included the payment of
the respondents’ costs of the proceedings – where the applicant
has brought an application for the stay of an order for the
applicant to pay 75 per cent of the respondents’ costs of the
proceedings, including reserved costs, to be assessed on the
-- 1 of 8 --
2
standard basis for costs incurred up to 23 May 2018 and
thereafter on the indemnity basis – whether the appeal has
a reasonable chance of success – whether the allowing of a stay
would be prejudicial to either of the parties if granted
COUNSEL: M J Ohlson (sol) for the applicant
P A Travis for the respondent
SOLICITORS: Ohlsons Lawyers and Barristers for the applicant
Axia Litigation Lawyers for the respondent
[1] MORRISON JA: In December 2012 Chapel of Angels Pty Ltd entered into a
building contract with Hennessy Building Pty Ltd for the construction of a building
constituting a chapel and a storeroom, and other associated works.
[2] The parties fell into dispute about various aspects and Chapel of Angels retook
possession of the site and refused to pay any further sums. It initiated proceedings in
the District Court seeking relief, including restitution of all the monies paid under the
contract, based on the fact that Hennessy Building did not hold the necessary
contractor’s licence under the Queensland Building Services Authority Act 1991 (Qld)
and the Queensland Building Services Authority Regulation 2003 (Qld)1 to construct
the chapel, that being a Class 9(b) Type B building, namely one with a rise of two
storeys.
[3] Hennessy Building contested the licence issue on grounds that do not presently
matter, but also counterclaimed for reasonable remuneration under s 42(4) of the
QBSA Act or alternatively on the basis of a quantum meruit.
[4] On 12 November 2018 the trial judge found that:2
(a) Hennessy Building did not hold the requisite licence to build the chapel and
surrounding works, which was done in contravention of s 42(1) of the QBSA Act;3
(b) therefore Chapel of Angels was entitled to recover all payments made under
the building contract;4
(c) however, Hennessy Building nonetheless held a “Carpentry” licence and a
“Builder – low rise” licence;5
(d) Hennessy Building was entitled to recover reasonable remuneration for work
done: (i) if that was within the scope of any licence held by it, without being
limited by s 42(4) of the QBSA Act; and (ii) if that was unlicensed work limited
under s 42(4) of the QBSA Act;6
(e) Hennessy Building’s carpentry licence authorised a substantial part of the
chapel works;7
1 To which I shall refer as the QBSA Act and QBSA Regulation, respectively.
2 Chapel of Angels Pty Ltd v Hennessy Builder Pty Ltd & Anor [2018] QDC 218. I note that the name
in the reasons below and the reported case is incorrect; the company is Hennessy Building Pty Ltd.
3 Reasons below at [111]. Nor did the principal of Hennessy Building.
4 Reasons below at [127].
5 Under Part 4, ss 1 and 2(2) (Builder – low rise), and Part 16, ss 1 and 2 (Carpentry) of the QBSA Regulations.
6 Reasons below at [133](a) and [134]. In this respect his Honour relied upon Dart Holdings Pty Ltd v
Total Concept Group Pty Ltd [2012] QSC 158 at [40].
7 Reasons below at [156](a).
-- 2 of 8 --
3
(f) the car park and external works were within Hennessy Building’s licence, and
the contrary was not put by Chapel of Angels;8
(g) his Honour accepted the expert report of Mr Carey9 as to the costs of the
construction as no objection was made to its admission, no competing expert
evidence was adduced, and his Honour rejected such attacks as were made on
Mr Carey’s credibility and his report;10
(h) based on Mr Carey’s report the reasonable remuneration for work that came
under the licences was $636,462.67 (ex GST);11
(i) the GST inclusive sum for the licensed work was $700,108.20;12
(j) based on Mr Carey’s report the reasonable remuneration for the unlicensed
work, calculated under s 42(4) of the QBSA Act, was $27,635.46 (ex GST);13
under s 42(4)(a) and (c) that sum could only be recovered if it was not more
than the amount paid by Hennessy Building in carrying that work out, and not
more than any amount agreed for that work; as neither of those things had been
proven, no amount could be recovered for the unlicensed work;14 and
(k) the net sum payable to Hennessy Building was the difference between
$700,108.20 and the $632,615.32 paid under the contract, which was
recovered; the net was $67,492.88.15
[5] Having made all relevant findings in the first decision, the learned trial judge heard
the parties as to the form of orders and pronounced those orders on 11 December
2018.16 Order No. 2 was that Chapel of Angels pay $85,989.86 to Hennessy Building,
being the sum referred to in paragraph [4](k) above with interest added. Order No. 6
ordered Chapel of Angels to pay 75 per cent of Hennessy Building’s costs of the
proceedings, including reserved costs, to be assessed on the standard basis for costs
incurred up to 23 May 2018 and thereafter on the indemnity basis.
[6] The stay sought on this application is only in respect of Order No. 6, the judgment
sum under Order No. 2 having already been paid to Hennessy Building.
Legal principles
[7] In order to succeed in the grant of a stay the applicant must show that the circumstances
indicate that the grant is an appropriate one. That involves a consideration of:17
(a) whether there is a good arguable case on the appeal; in other words, the
likelihood of success in the appeal;
(b) the prejudice to the applicant if the stay is not ordered; and
(c) any competing prejudice to the respondents in the event that a stay is granted.
8 Reasons below at [156](b).
9 A quantity surveyor.
10 Reasons below at [140]-[154], [157].
11 Reasons below at [158]-[160].
12 Reasons below at [166].
13 Reasons below at [161]-[162].
14 Reasons below at [164]-[165].
15 Reasons below at [171]-[172].
16 Chapel of Angels Pty Ltd v Hennessy Builder Pty Ltd & Anor [2018] QDC 248.
17 Elphick v MMI General Insurance Ltd [2002] QCA 347 at [4] and [8].
-- 3 of 8 --
4
[8] A stay should not be granted unless the applicant establishes a sufficient basis to
outweigh the considerations that the judgment should not be treated as merely
provisional, and courts generally should not be disposed to delay the enforcement of
court orders. The fundamental justification for staying judicial orders pending an
appeal is to ensure that the orders which might ultimately be made by the courts are
fully effective. Where the court is able to make a preliminary assessment of the
strength of the case, the prospects of success on appeal might be significant and would
favour refusal of a stay if they were not.18
Discussion
[9] Before turning to the merits of the grounds urged by Chapel of Angels two
preliminary matters need to be explored.
[10] First, the application for leave to appeal was filed on 3 May 2019, four months outside
the time limited for appeal.19 Consequently, Chapel of Angels needs an extension of
time within which to bring the application for leave to appeal. There are real difficulties
about that.
[11] The evidence from Chapel of Angels is that:20
(a) before the orders were made, on 4 December 2018 it was given legal advice by
its lawyers at the trial21 that it should not appeal, as an appeal posed too much
of a risk, it made no financial sense; however, if Chapel of Angels wished to
pursue an appeal the lawyers would assist; further, it should pursue the former
lawyers for negligence;22
(b) Chapel of Angels debated the advice, stipulating grounds why it was not
100 per cent confident it should not appeal, and seeking further advice so that
it could “make an informed decision as [to] whether to appeal or not”;23
(c) the lawyers responded with reasons why there should be no appeal: (i) the
findings of credit would not assist Chapel of Angels; (ii) appeal courts are
loathe to interfere unless there is a significant error in law or fact; (iii) Counsel
felt there were “some prospects” but that the risk may be too high; (iv) even
though s 42(4) “curbs the amount that can be claimed from an unlicenced
builder, the quantum meruit doctrine is a common law principal (sic), which
allows some discression (sic) by the trial judge”; (v) even if the judge found
some facts in your favour, the amount would have to be quantified and weighed
up against the cost; (vi) there was a risk that the result may be a retrial; (vii)
there were “some prospects” but the risk “is just too great”; and (viii) if Chapel
of Angels decided to appeal the lawyers would “fight tooth and nail to secure
the best possible outcome”;24 and
(d) based on what it had been advised, that understood as being that the prospects
on appeal were poor, on 6 December 2018 Chapel of Angels decided not to appeal.25
18 Cook’s Construction Pty Ltd v Stork Food Systems Australasia Pty Ltd [2008] 2 Qd R 453.
19 Taking that to be from when the orders were made on 11 December 2018.
20 Affidavit of Ms Peek, paragraphs 3-11.
21 Three solicitors and Counsel.
22 Exhibit SP3 to Ms Peek’s affidavit.
23 Exhibit SP4 to Ms Peek’s affidavit.
24 Exhibit SP5 to Ms Peek’s affidavit.
25 Affidavit of Ms Peek, paragraph 10.
-- 4 of 8 --
5
[12] The fact that a deliberate decision not to appeal has been made on legal advice
presents a very significant obstacle to the grant of an extension of time within which
to apply for leave to appeal.26 Where such a deliberate decision has been made “an
extension of time to allow an appeal would only be granted where it was demonstrably
necessary to prevent a substantial injustice”.27
[13] Secondly, as was conceded on behalf of Chapel of Angels during argument, a number
of matters now sought to be raised on the proposed appeal were not agitated at the
trial. That presents a significant hurdle to a grant of leave to appeal.
[14] The main points to be urged in the proposed appeal are that:
(a) the work was unlicensed because Hennessy Building did not work under the
guidance of a builder holding a licence for that class of building, i.e Class 9(b)
Type B;
(b) Hennessy Building’s carpenter licence was not an appropriate licence to carry
out most of the works and surrounds;
(c) Mr Carey’s report quantifies the building work on a quantum meruit basis, and
not under s 42(4); and
(d) the reasonable remuneration awarded at the trial was based on a quantum
meruit instead of an assessment under s 42(4) of the QBSA Act.
[15] The licence point contends that the carpenter and builder-low rise licences do not
authorise Hennessy Building to build the chapel (a Class 9(b) Type B building) and
therefore Hennessy Building’s work had to be done under the guidance of another
appropriately licensed builder. This was said to flow from s 42(1) of the QBSA Act
when read in conjunction with the definitions of “building work” and “building” in
Schedule 2 of the QBSA Act.
[16] The first thing to observe, as was accepted by the solicitor for Chapel of Angels, is
this is a point not raised below. Assuming it is a straight point of law,28 it is not
obvious to me that it is correct.
[17] Section 42 of the QBSA Act provides as follows:
“(1) A person must not carry out, or undertake to carry out, building
work unless that person holds a contractor’s licence of the
appropriate class under this Act.”
[18] The definitions of “building” and “building work” do not, in my view, add anything
relevant. Nothing in s 42(1) compels the construction that underlies the contention.
It provides that a builder who carries out building work must hold an appropriate
contractor’s licence. That focuses on the licence held by the person who carries the
work. It says nothing as to a requirement that there be an overarching licensed builder.
[19] No matter how the contention was expressed during the hearing it always came back
to the simple proposition that Hennessy Building was not licensed to construct the
26 Baguley v Lifestyle Homes Mackay Pty Ltd [2015] QCA 75 at [14]-[16].
27 Spencer v Hutson [2007] QCA 178 at [31].
28 If it a question dependant on facts then there is an even greater hurdle to overcome before the point
can be raised: see Water Board v Moustakis (1988) 180 CLR 491 at 497-498.
-- 5 of 8 --
6
chapel. At the trial Chapel of Angels succeeded on that issue.29 Having contravened
s 42(1) of the QBSA Act, the question was whether Hennessy Building could recover
anything, and if so, what. That is where s 42(4) is relevant, as it governs what can be
recovered when s 42(1) is contravened.
[20] Chapel of Angels accepts that the construction adopted in Dart Holdings Pty Ltd v
Total Concept Group Pty Ltd is correct.30 That means its contentions are advanced
on the basis that “the limitations as to the amount which can be claimed, consistently
with s 42(4), applies only to the building work for which the contractor did not have
the appropriate licence … [and] would not affect the defendant’s entitlement to be
paid, upon a restitutionary basis, for the work which it lawfully performed under its
licence.”
[21] Hennessy Building’s Builder-low rise licence included class 9 buildings but excluded
Type B buildings from its scope of works.31 The carpentry licence covered the
following scope of work:32
“2 Scope of work
(1) Construct and erect timber and steel wall framing and roof
structures.
(2) Construct and erect non-load bearing internal partition walls.
(3) Install windows and doors including framing.
(4) Erect ceiling and subfloor framing.
(5) Install timber and sheet flooring.
(6) Install exterior cladding, fascias and soffits.
(7) Install metal roofing.
(8) Construct timber stairs.
(9) Fix internal linings, panelling and mouldings.
(10) Install door and window locks and furniture.
(11) Restore and renovate doors, windows and frames.
(12) Install fitments.
(13) Concreting to simple forms, including install formwork,
reinforcement and concrete.
(14) Erect and strip formwork, including slip form and jump form
formwork.
(15) Incidental work of another class.”
[22] Mr Carey’s report dealt with the issue of what was within the carpenter licence, and
what was not.33 Having set out the scope of works above, he opined that “… on the
29 Reasons below at [111].
30 [2012] QSC 158 at [40]; Transcript T 1-64 line 28.
31 QBSA Regulation, Part 4, s 2.
32 QBSA Regulation, Part 16, s 2.
33 Report, section 3, pages 5-6.
-- 6 of 8 --
7
chapel the only work he was not entitled to undertake was the structural steel and
blockwork”. No contrary expert report was tendered at the trial, and, as the learned
trial judge noted, no evidence was led by Chapel of Angels as to the correct
restitutionary measure.34
[23] In the course of cross-examination it was revealed that: (i) Mr Carey’s experience as
an expert in building cases spanned some 10 years; (ii) he had particular expertise
working over 10 years for a builder that specialised in churches; and (iii) he had
inspected the chapel itself.35 The cross-examination did not challenge his expertise,
nor his opinion as to what was within and outside the licence,36 nor his verification
of the reasonableness of all the invoices. As indicated above, the learned trial judge
specifically rejected the five grounds of criticism levelled at Mr Carey’s evidence.37
[24] More particularly, there was no challenge to: (i) the correctness of including the car
park, and external works; (ii) the implicit assumption in Mr Carey’s report that the
car park and external works did not constitute unlicensed work under s 42(1) of the
QBSA Act; in fact, as his Honour found, there was no submission to the contrary
below;38 (iii) the costs of those works, and the reasonableness of them, or (iv) that
they were done by subcontractors to Hennessy Building.
[25] Those matters suggest that the prospects of successfully challenging the learned trial
judge’s calculation of the reasonable remuneration are not compelling. When combined
with the fact that the delay in seeking leave to appeal was the product of a deliberate
decision based on legal advice, the prospects of success on the appeal do not look
promising.
[26] However, even if that were not right, there are compelling discretionary reasons to
refuse a stay.
[27] First, the only order sought to be stayed is that relating to the costs ordered to be paid
by Chapel of Angels. A costs statement has been given and Chapel of Angels has
delivered the requisite notice disputing the costs. Consequently the process of
assessment has to be undertaken before the costs can be certified, and before they can
be enforced. Both sides agree that no assessor has been appointed, and that the
process will not be finalised by the date set for the hearing of the appeal. Even if, as
seems unlikely, the entire process is closer to finalisation by the appeal, the question
of a stay can be agitated then.
[28] Secondly, Mr Travis of Counsel, appearing for Hennessy Building, proffered an
undertaking to the Court to the effect that if anything is recovered in respect of the
costs ordered, that money will be placed in the solicitor’s trust account pending
further order of the Court. Thus the money would be preserved for recovery in the
event the appeal is successful.
[29] For all these reasons, upon the undertaking proffered by Mr Travis on his client’s
behalf, the application for a stay should be refused. In the circumstances there is no
34 Reasons below at [140].
35 Trial transcript T 8-45, 46, 47, 59.
36 There was a finding below that the carpentry licence authorised “a substantial part of the Chapel
works”: [156](b). It was accepted on this hearing that it had not been put to Mr Carey that he was
wrong about the split between licensed and unlicensed work: Transcript T 1-48 lines 10-22.
37 Reasons below at [142]-[154].
38 Reasons below at [156](a).
-- 7 of 8 --
8
reason to refuse an order that the costs of the application be paid by Chapel of Angels.
I therefore order:
Upon the first respondent, by its Counsel, undertaking that any amounts
recovered by the first respondent pursuant to execution of a judgment for costs
will be held in the trust account of Axia Litigation Lawyers pending further
order of the Court of Appeal:
1. The application is dismissed.
2. The applicant is to pay the first respondent’s costs of the application.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2019/229