Delta Pty Ltd v Mechanical and Construction Insurance Pty Ltd [2019] QCA 62 [2019] 3 Qd R 438
SUPREME COURT OF QUEENSLAND
CITATION: Delta Pty Ltd v Mechanical and Construction Insurance Pty
Ltd [2019] QCA 62
PARTIES: DELTA PTY LTD
ACN 007 069 794
(appellant)
v
MECHANICAL AND CONSTRUCTION INSURANCE
PTY LTD
ACN 106 907 055
(respondent)
FILE NO: Appeal No 8520 of 2017
SC No 8800 of 2012
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
ORIGINATING
COURT: Supreme Court at Brisbane – [2018] 1 Qd R 564 (Dalton J)
DELIVERED ON: 12 April 2019
DELIVERED AT: Brisbane
HEARING
DATES: 21 March 2018; 22 March 2018
JUDGES: Fraser and McMurdo JJA and Flanagan J
ORDERS: The appeal is dismissed with costs.
CATCHWORDS: INSURANCE – THE POLICY – CLAIMS GENERALLY –
REFUSAL – OTHER MATTERS – where the appellant and
a third party subcontractor settled claims between them
concerning breaches of subcontract by way of an assignment
by the subcontractor to the appellant of rights under a policy
of insurance issued by the respondent – where the appellant as
the assignee insured claimed indemnification from the
respondent for losses suffered in connection with breaches of
subcontract by the subcontractor – whether the subcontractor
was legally liable so as to engage the insurance policy –
whether the settlement between the appellant and the
subcontractor was reasonable – whether the losses claimed by
the appellant were insured by the policy
INSURANCE – THE POLICY – THE INSURED – where the
appellant claimed as an insured in its own right an indemnity
under a policy of insurance issued by the respondent – whether
the appellant was insured under the relevant policy – whether
the losses claimed by the appellant were insured by the policy
-- 1 of 49 --
2
Civil Proceedings Act 2011 (Qld), s 58
Insurance Contracts Act 1984 (Cth), s 54
Limitation of Actions Act 1974 (Qld), s 10(1)(a)
Uniform Civil Procedure Rules 1999 (Qld), r 150(1)(k)
Allianz Australia Insurance Ltd v BlueScope Steel Ltd (2014)
87 NSWLR 332; [2014] NSWCA 276, cited
Associated Forest Holdings Pty Ltd v Gordian Runoff Ltd
[2015] TASFC 6, followed
Australasian Correctional Services Pty Ltd v AIG Australia
Ltd [2018] FCA 2043, cited
Barrie Toepfer Earthmoving and Land Management Pty Ltd v
CGU Insurance Ltd [2016] NSWCA 67, applied
Bayer Australia Pty Ltd v Kemcon Pty Ltd (1991)
6 ANZ Ins Cas 61-026, cited
Blakeley & Ors v CGU Insurance Ltd (2017) 53 VR 733;
[2017] VSCA 378, cited
BNP Paribas v Pacific Carriers Ltd [2005] NSWCA 72,
distinguished
Cacciolla v Fire & All Risks Insurance Co Ltd [1971]
1 NSWLR 691, applied
Campbell v Director of Prosecutions for the Commonwealth
of Australia [1995] 2 VR 654; [1995] VicRp 82, cited
CGU Insurance Ltd v One.Tel Ltd (In liq) (2014) 242 CLR 174;
[2010] HCA 26, cited
Cigna Insurance Asia Pacific Ltd v Packer (2000) 23 WAR 159;
[2000] WASCA 415, followed
Corti v Rodwell [1985] VR 287; [1985] VicRp 26, applied
Distillers Co Bio-Chemicals (Aust) Pty Ltd v Ajax Insurance
Co Ltd (1974) 130 CLR 1; [1974] HCA 3, applied
Globe Church Incorporated v Allianz Australia Insurance Ltd
[2019] NSWCA 27, followed
Graham Evans & Co (Qld) Pty Ltd v Vanguard Insurance Co
Ltd (1986) 4 ANZ Ins Cas 60-689, cited
Guardian Assurance Co Ltd v Underwood Constructions Pty
Ltd (1974) 48 ALJR 307, distinguished
Keeley v Horton [2016] QCA 253, explained
Hunter v Stronghold Insurance (Australia) Ltd [1995] VicSC 5,
not followed
Maxwell v Highway Hauliers Pty Ltd (2014) 252 CLR 590;
[2014] HCA 33, cited
McCann v Switzerland Insurance Australia Ltd (2000) 203
CLR 579; [2000] HCA 65, applied
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd
(2015) 256 CLR 104; [2015] HCA 37, applied
Penrith City Council v Government Insurance Office of New
South Wales (1991) 24 NSWLR 564, not followed
Rail Corporation New South Wales v Fluor Australia Pty Ltd
[2009] NSWCA 344, cited
Ranicar v Frigmobile Pty Ltd [1983] Tas R 113; (1983)
2 ANZ Ins Cas 60-525; [1983] TASRp 13, cited
Vero Insurance Ltd v Baycorp Advantage Ltd (2005)
-- 2 of 49 --
3
13 ANZ Ins Cas 61-630; [2004] NSWCA 390, cited
Wallaby Grip Ltd v QBE Insurance (Australia) Ltd (2010)
240 CLR 444; [2010] HCA 9, applied
COUNSEL: J Gleeson QC, with B Jellis, for the appellant
D A Savage QC, with S R Lumb, for the respondent
SOLICITORS: Thomson Geer for the appellant
TurksLegal for the respondent
[1] FRASER JA: The issues in this appeal concern the question whether a policy of
insurance issued by the respondent (“Mecon”) covers claims made by the appellant
(“Delta”) arising out of breach of contract by Delta’s subcontractor, Team Rock
Anchors Pty Ltd (“TRA”).
[2] In May 2006 the Queensland Investment Corporation contracted with Delta for it to
undertake an excavation on the Corporation’s land at 175 Albert Street, Brisbane, in
preparation for the construction of a high rise building. In or about September 2006
Watpac contracted with Queensland Investment Corporation to carry out the
construction work, the contract between Queensland Investment Corporation and
Delta was replaced by a contract between Watpac and Delta, and Delta entered into
a subcontract with TRA for it to complete that part of Delta’s contract work which
comprised the installation of rock anchors.
[3] The function of the rock anchors installed by TRA was to secure the four retaining
walls (designated as SW1, SW2, SW3 and SW4) constructed in the excavation,
thereby protecting workers and material within the excavation and neighbouring
buildings and roads. The rock anchors’ design included bundles of thick wire strands,
varying in length up to 20 metres. They were to be placed in holes drilled through
concrete piles around the perimeter of the construction site and fixed in place by
injections of grout to bind the last few metres of the strands to the subsoil. The trial
judge described TRA’s work as “woeful”; the great majority of the rock anchors were
not in accordance with the shop drawings, there were insufficient strands in the
bundles, the strands were not long enough, they were not grouted into position
properly at their ends, and they were not capable of performing as designed.1
[4] Delta argues that TRA’s defective work impacted upon all four retaining walls in a
way that amounted to property loss, liability for which is insured under the Mecon
policy. That is in issue. It is sufficient at this point to refer to the trial judge’s
description of consequences of TRA’s breaches:
“Survey monitoring points were located around the perimeter of the
site on top of the retaining walls. By May they showed unacceptable
movement of one wall, SW1. The Superintendent appointed pursuant
to the contract between Watpac and Delta issued a direction to Delta
on 3 May 2007 to backfill against SW1 and install a further two rows
of rock anchors in that wall. That was done, but movement of SW1
continued. On 28 June 2007 the Superintendent issued a further
instruction to Delta in relation to the SW1 wall. Lastly, on 24 July
2007 the Superintendent instructed Delta to backfill the entire
excavation and essentially start excavating again, testing and replacing
1 Delta Pty Ltd v Team Rock Anchors Pty Ltd & Anor [2018] 1 Qd R 564 (“Reasons”) at [6].
-- 3 of 49 --
4
defective anchors as the re-excavation proceeded. Delta complied
with all these directions.”2
[5] In 2012 Delta sued TRA for damages for, inter alia, breach of subcontract. TRA
brought a third party claim against Mecon claiming an indemnity pursuant to the
insurance policy under which TRA was a named insured. That claim was
discontinued when TRA could not supply security for Mecon’s costs. In May 2016
Delta compromised its claim against TRA by a settlement deed, which included an
assignment to Delta of TRA’s rights under the policy.
[6] The proceedings thereafter involved only claims by Delta against Mecon. The claims
which remain in issue are:
(a) A claim by Delta as assignee of TRA’s claimed right to an indemnity of
the “Settlement Amount” under the settlement deed of $2,581,179.18 or,
alternatively, an amount assessed by the court.
(b) In the alternative to (a), a claim by Delta as an insured under the policy
for the costs incurred in undertaking temporary protective repairs, in an
amount of $1,478,000.
[7] After a trial, judgment was given for Mecon against Delta.
The claim by Delta as assignee of TRA
[8] Delta, as assignee of TRA, claimed an indemnity against TRA’s liability to Delta
under the public liability cover in cl 5 of s 2 of the policy. Clause 5 provides:
“5.00 In accordance with the terms, exclusions and conditions of the
Policy MECON will provide indemnity for all amounts which
you become legally liable to pay in compensation of Personal
Injury or Property Loss that happens within the Territorial
Limits during the Period of Insurance as a result of an
Occurrence which arises in connection with your Business.
With MECON’s prior written permission, and included within
the applicable limits of Indemnity, MECON will also pay:
5.01 legal charges, expenses and costs incurred by you; and
5.02 legal costs for your representation at any coroner’s inquest; and
5.03 costs incurred by you for temporary protective repairs
undertaken to prevent any immediate threat of Property Loss or
Personal Injury.”
“Occurrence” is defined to mean “an event, including the continued or repeated
exposure of persons or property to conditions that are generally the same, which you
could not have expected and did not intend to happen”. The word “Event” is defined
to mean “a single event of loss or damage”.
[9] It is not in issue that TRA assigned its claim for an indemnity under the Mecon policy
to Delta. What is in issue is whether TRA was entitled to such an indemnity. Delta’s
case upon that issue is that the settlement deed rendered TRA “legally liable” to pay
2 Reasons at [7].
-- 4 of 49 --
5
the Settlement Amount “in compensation of … Property Loss” that happened as
a result of an Occurrence.
[10] The settlement deed commences with recitals which include reference to TRA being
entitled to a grant of indemnity and Mecon having improperly declined to grant
indemnity to TRA under the policy in connection with the “Delta Claim”. (“Delta
Claim” is defined to mean “Delta’s claims against TRA which are the subject of the
Proceeding and which are more particularly described in the pleadings in the
Proceeding”.) Recital F states that, “Delta TRA and Jones3 have agreed to enter into
this Deed under which … TRA agrees to assign to Delta certain of TRA’s rights under
the Mecon Policy on the terms set out below.”
[11] Clauses 2 and 3 provide:
“2.1 Subject to clause 2.2, and without any admission as to liability,
TRA hereby agrees to settle the Delta Claim upon the basis that:
(a) TRA agrees to pay to Delta the amount of $2,581,179.18,
in full and final settlement of the Proceeding including
the Delta Claim and the TRA Counterclaim (the
Settlement Amount) upon demand; and
(b) there be no order as to costs.
2.2 TRA remains, and shall remain, liable to Delta for the
Settlement Amount, but TRA's liability in respect of the
Settlement Amount is limited to the amount actually recovered
by Delta under the Mecon Policy as assignee of TRA.
2.3 TRA acknowledges that Delta's agreement to clause 2.2 is in
reliance upon TRA's representations as to TRA's current
financial position to the effect that TRA lacks the financial
capacity to meet any substantial part of TRA's liability to pay
the Settlement Amount.
…
3.1 By this Deed, TRA agrees to assign the Mecon Claim to Delta
for the sum of $1.00 (Purchase Amount).
3.2 TRA and Jones shall provide reasonable assistance to Delta in
relation to the exercise of Delta's rights under the Mecon Policy
as assignee of TRA.”
“Mecon Claim” is defined to mean “the whole of TRA’s beneficial interest in the
Mecon Policy including all rights and entitlements to obtain indemnity and to recover
under the Mecon Policy in respect of TRA’s liability to Delta for and in respect of the
Delta Claim.”
[12] A footnote referred to in cl 2.1(a) of the settlement deed after the Settlement Amount
figure of $2,581,179.18 states:
“Being the total amount claimed in paragraph 16 of the Claim
($2,831,179.18) less $250,000 on account of TRA’s counterclaim.”
3 Mr Jones, a former director of TRA, was the second defendant in the proceeding, but Delta released
and discharged him and consented to the claim against him being dismissed.
-- 5 of 49 --
6
[13] I understood it to be common ground that, in circumstances in which Mecon had
denied liability to indemnify TRA, TRA was entitled to an indemnity if it proved that
the settlement deed rendered TRA legally liable to pay the Settlement Amount,
TRA’s assumption of that liability was reasonable,4 and TRA was liable to pay that
amount “in compensation of … Property Loss” and otherwise satisfied the terms of
cl 5.00.5 During the hearing of the appeal, senior counsel for Delta argued that it was
sufficient for Delta to prove in this proceeding that TRA was liable for damages for
breach of its subcontract. Upon that premise Delta argued that, in circumstances in
which Delta clearly proved that TRA breached its subcontract in ways that caused
Delta loss and the real issue concerned only the quantum of that loss, it was not
necessary for Delta to prove that the settlement deed rendered TRA liable to pay the
Settlement Amount; the only relevance of the settlement deed was submitted to be
that it crystallised the amount of TRA’s liability for its breach of the subcontract.6
That argument is inconsistent with the way in which Delta argued its case at trial.
Mecon did not contend that the new argument should not be considered in this appeal,
presumably upon the footing that it involves only the proper construction of the policy.
[14] The trial judge referred to the general rule articulated in BNP Paribas v Pacific
Carriers Ltd7 by Giles JA (Sheller JA agreeing)8:
“At least where the insurer has breached the contract by denying
liability, the weight of authority in the indemnity cases is that the
insured can recover the amount of a reasonable settlement from the
insurer; prominent cases are Edwards v Insurance Office of Australia
Ltd (1933) 34 SR 88; General Omnibus Co Ltd v London General
Insurance Co Ltd (1936) IR 596; and Distillers Co Biochemicals (Aust)
Pty Ltd v Ajax Insurance Co Ltd (1974) 130 CLR 1. This is consistent
with the reasoning in Unity Insurance Brokers Pty Ltd v Rocco
Pezzano Pty Ltd in that, on the application of principles concerning
causation and remoteness in assessment of damages, settlement will
commonly be causally related to the insurer’s breach and a natural and
reasonably contemplated result of the breach. As McHugh J said in
Unity Insurance Brokers Pty Ltd v Rocco Pezzano Pty Ltd at [33], “As
a general rule, a contract breaker must be taken to have reasonably
contemplated that its breach may force the innocent party into
litigation with third parties and that the innocent party may conclude
that it is in its best interest to compromise the third party’s claim”.”
4 There was no challenge to the trial judges’ statement of the test of reasonableness quoted in [36] of
these reasons.
5 The evidence at the trial established that TRA was liable to Delta and that does not seem to have been
in issue. For that reason, and because of the way in which the appeal was conducted, it is not necessary
to consider the question whether an insured in TRA’s position who claims an indemnity (rather than
damages for breach of the policy) is obliged to prove that it was liable to the plaintiff where the insurer
has not repudiated the policy: see Hurlock v Council of the Shire of Johnstone [2002] QCA 256 at [28]
– [31], but note the reference to competing views in Vero Insurance Ltd v Baycorp Advantage Ltd
(2005) 13 ANZ Ins Cas 61-630; [2004] NSWCA 390 at [48]. Many other decisions on the point are
discussed in K Sutherland “An Uneasy Compromise; An Analysis of the Effect of a Settlement
Reached by an Insured with a Third Party Claimant vis-a-vis his or her Insurer” (1998) 9 ILJ 1 and
Traves “In what circumstances is an insurer bound by a judgment or settlement against its insured?”
(2015) 26 ILJ 209. See also Weir Services Australia v AXA Corporate Solutions Assurance [2018]
NSWCA 100 at [2] (Meagher JA), [17] – [22] (White JA), [62] – [64] (Barratt AJA).
6 Transcript 21 March 2018 at T1-57 to T1-58.
7 [2005] NSWCA 72 at [187].
8 [2005] NSWCA 72 at [88].
-- 6 of 49 --
7
The trial judge also referred to the following passage in Handley JA’s reasons:9
“Where a contract of indemnity is repudiated the innocent party, who
is faced with an adverse claim, is in the difficult position having to
litigate the issues on two fronts instead of none. In such circumstances
a settlement of the adverse claim, if reasonable, will crystallise the loss
for which the innocent party is entitled to indemnity. See Edwards v
Insurance Office of Australia Ltd (1933) 34 SR (NSW) 88. Such
settlement is within the notional reasonable contemplation of the
parties and a result of the breach. As I read Unity Insurance Brokers
Pty Ltd v Rocco Pezzano Pty Ltd (1998) 192 CLR 603 (Unity Brokers)
all judgments support this conclusion. McHugh J (612-4) and Gummow J
(625) refer to Edwards v Insurance Office of Australia Ltd with approval.”
[15] Delta’s argument is not inconsistent with those passages, but the present point was
not in issue in BNP Paribas v Pacific Carriers Ltd. The reasoning in that case is not
applicable for two reasons. First, Handley JA and Giles JA analysed the issues with
reference to principles applicable in a claim for damages for the insurer’s breach of
the insurance contract, whereas Delta’s claim as assignee is for an indemnity to
which, at the time of the assignment, TRA is alleged to have been entitled pursuant
to the policy terms. Secondly, the contractual indemnity in BNP Paribas v Pacific
Carriers Ltd was in respect of any “liability loss or damage of whatsoever nature”,10
the scope of which is markedly broader than the indemnity in cl 5.00 of the Mecon
policy for “all amounts which you become legally liable to pay in compensation of
… Property Loss”.
[16] In an English case reported in 1928, Hood’s Trustees v Southern Union General
Insurance Company of Australasia Ltd,11 the Court of Appeal (Lord Hanworth MR,
Lawrence and Russell LJJ agreeing) approved Tomlin J’s conclusions that the right
to indemnity under a policy covering “any liability for compensation … for accidental
bodily injury …”12 arose upon the happening of an accident and was a chose in action
that vested in the insured’s trustee in bankruptcy before judgment was given against
the insured.13 Tomlin J considered that there was no substantial difference between
that case and another case in which a judgment against the insured had been obtained
before an insured went into liquidation.
[17] That decision might have supplied some support for Delta’s new argument (although
it did not concern the expression “legally liable”), but forty years later in Post Office
v Norwich Union,14 the majority of the Court of Appeal reached the opposite
conclusion with reference to a policy which obliged the insurer to “indemnify the
insured against all sums which the insured shall become legally liable to pay as
compensation in respect of loss of or damage to property”. Clause 5.00 of the Mecon
policy expresses the indemnity more narrowly, but the difference is not material for
the point under discussion. Denning MR concluded that the insured acquired a right
to sue for the money only when his liability to the plaintiff had been “ascertained and
determined to exist, either by judgment of the court or by an award in arbitration or
9 [2005] NSWCA 72 at [13].
10 [2005] NSWCA 72 at [108].
11 [1928] Ch 793.
12 [1928] Ch 793 at 794.
13 [1928] Ch 793 at 801-802.
14 [1967] 2 QB 363.
-- 7 of 49 --
8
by agreement” and until that was done, the right to indemnity did not arise.15
Similarly, Salmon LJ observed:16
“It is quite true that if Potters in the end are shown to have been legally
liable for the damage resulting from the accident to the cable, their
liability in law dates from the moment when the accident occurred and
the damage was suffered. But whether or not there is any legal liability
and, if so, the amount due from Potters to the Post Office can, in my
view, only be finally ascertained either by agreement between Potters
and the Post Office or by an action or arbitration between Potters and
the Post Office. It is quite unheard of in practice for any assured to
sue his insurers in a money claim when the actual loss against which
he wishes to be indemnified has not been ascertained. I have never
heard of such an action and there is nothing in law that makes such an
action possible.”
[18] The same construction of the expression “legally liable” in materially indistinguishable
policy provisions has repeatedly been adopted: Cacciola v Fire & All Risks Insurance
Co Ltd,17 Distillers Co Bio-Chemicals (Aust) Pty Ltd v Ajax Insurance Co Ltd,18 Corti
v Rodwell,19 Vero Insurance Ltd v Baycorp Advantage Ltd,20 Allianz Australia
Insurance Ltd v Bluescope Steel Ltd,21 and Australasian Correctional Services Pty
Ltd v AIG Australia Ltd.22 Thus, for example:
(a) In Distillers Co,23 Stephen J adopted Salmon LJ’s analysis in Post Office
v Norwich Union and accepted that the insured had not become “legally
liable for any sum by way of damages” for the purposes of the policy.
Menzies J’s reasons proceeded upon the same premise that liability to
indemnify the insured would arise only upon judgment or, in the case of
an insurer breaching the contract by denying liability and refusing to
defend or settle, the insured making a reasonable settlement.24
(b) In Cacciola, Jacobs JA (Moffitt JA and Taylor AJA agreeing) observed
of a similar policy that it “does not indemnify against a possible future
liability, but against an ascertained enforceable liability... In the
circumstances of this case, it seems to me that nothing before the signing
of the judgment results in what could be described as a legal liability by
way of damages within the meaning of the policy.”25
(c) In Corti v Rodwell,26 Tadgell J discussed a policy providing an
indemnity “in respect of all sums which the said Associations … might
15 [1967] 2 QB 363 at 373-374.
16 [1967] 2 QB 363 at 377-378.
17 [1971] 1 NSWLR 691 at 695.
18 (1974) 130 CLR 1 at 25-26.
19 [1985] VR 287 at 289.
20 (2005) 13 ANZ Ins Cas 61-630; [2004] NSWCA 390 at [1], [48], [89].
21 (2014) 87 NSWLR 332; [2014] NSWCA 276 at [78], [267]-[270].
22 [2018] FCA 2043 at [15].
23 (1974) 130 CLR 1 at 25-26.
24 (1974) 130 CLR 1 at 9, in the course of a discussion about General Omnibus Co v London General
Insurance Co [1936] IR 596. The present point was not considered by the third member of the Court,
Gibbs CJ.
25 [1971] 1 NSWLR 691 at 695.
26 [1985] VR 287 at 289.
-- 8 of 49 --
9
become legally liable to pay for compensation in respect of bodily injury
…”:
“There is certainly authority for the view, which cannot now be
doubted, that under a policy of insurance providing indemnity
to the insured in respect of all sums for which the insured
becomes legally liable by way of compensation (or damages) no
obligation can arise before a legal liability of the insured is
established. The expression “legally liable” in this context means,
in broad terms, “held liable”. Such a legal liability might be
established by judgment, arbitral award or agreement, including
an agreement of compromise. Counsel for the company relied on
The Distillers Company Bio-Chemicals (Australia) Pty Ltd v
Ajax Insurance Co Ltd (1974) 130 CLR 1, esp. at pp. 25-6, in the
judgment of Stephen J, and cases there cited; and Cacciola v
Fire & All Risks Insurance Co Ltd [1971] 1 NSWLR 691, at p. 695.”
[19] Different forms of liability cover may indemnify the insured against a liability for
breach of contract proved for the first time in proceedings against the insurer for the
indemnity, but the cases I have mentioned are powerful support for the view that,
upon the proper construction of the Mecon policy, cl 5.00 comprehends only
a liability under a judgment, an award, or an agreement of the kind I have mentioned.
[20] Under appeal ground 11, Delta also argues that if TRA’s assumption of liability under
the settlement deed for the Settlement Amount was not reasonable Delta as assignee
was entitled to recover the amount which the Court finds would have been
a reasonable settlement. That argument is submitted to find support in Giles JA’s
conclusion in BNP Paribas v Pacific Carriers Ltd that, if the settlement amount was
unreasonably high the plaintiff could recover the amount for which the third party’s
claim could have been settled. The trial judge distinguished that case upon the ground
that it did not concern insurance against a liability to pay, but a letter of indemnity
under which the plaintiff was required to prove only loss or damage.27 Delta argued
that Giles JA’s analysis was referrable to a legal liability arising by way of
a settlement even though the indemnity extended beyond that. My conclusion that
the trial judge correctly distinguished BNP Paribas v Pacific Carriers Ltd is
explained in [15] of these reasons.
[21] Upon the proper construction of the Mecon policy, Delta as assignee could not
succeed in its claim for an indemnity if it did not establish that the settlement deed
rendered TRA liable to pay the Settlement Amount.
Did the settlement deed render TRA legally liable to pay the Settlement Amount?
[22] Grounds 1 and 2 of Delta’s notice of appeal contend that the trial judge’s conclusion
that the settlement deed did not render TRA “legally liable” for the Settlement
Amount was based upon an erroneous construction of the settlement deed.
[23] The trial judge considered that there was substance behind Mecon’s argument that
the demand required by cl 2.1(a) was not proved; there never would be such a demand
27 Reasons at [163]. The trial judge distinguished Unity Insurance Brokers Pty Ltd v Rocco Pezzano Pty
Ltd (1998) 192 CLR 603 and Rail Corporation New South Wales v Fluor Australia Pty Ltd & Anor
[2009] NSWCA 344 upon the same ground.
-- 9 of 49 --
10
because under cl 2.2 TRA’s only liability was for any amount actually recovered by
Delta as assignee of TRA, any such recovery would result from a judgment in the
proceeding, the judgment sum would be payable and paid to Delta rather than TRA,
so that there would never be any funds in TRA’s hands and it would never become
liable to pay those funds to Delta. The trial judge considered that although cl 2.2, to
which cl 2.1(a) is subject, purports only to limit the liability of TRA, in fact no
liability would ever arise. The trial judge accepted Mecon’s argument that the only
legal liability in terms of cl 5 of s 2 of the policy upon which Delta relied was the
liability said to be established by the settlement deed, but that the settlement deed did
not establish any such liability.
[24] An assignment with an associated compromise in a settlement deed made after an
insurer has wrongly rejected an insured’s claim under a liability policy has been
described in the United States of America as a “Damron Assignment”.28 Former
Justice Derrington referred to this kind of agreement in an article: 29
“The Damron Assignment is one where, the insurer having wrongly
rejected the insured’s claim to indemnity against liability to a third
party claimant, the insured compromises the third party claim by
assigning to the claimant the insured’s rights against the insurer in full
discharge of the claim. The agreement to discharge the claim in
consideration of the assignment may be part of a single transaction in
which the parties will also have compromised the issue of liability and
quantum of damages; or the latter compromise may be distinct from
and antecedent to the discharge agreement.” (footnotes omitted)
[25] After noting that cases in the United States of America and Canada had rejected
arguments that, although the Damron Assignment might produce a liability in the
insured for the purposes of a liability policy, there was no loss for the insurer to indemnify
because the contract assignment discharged the same liability,30 Derrington J
articulated a justification for that result based in the common intention of the parties
to the contract of assignment:
“In this way, it is found that the parties intended that there be
agreement as to the extent of liability of the insured to the claimant as
a necessary antecedent to the next step, that is, the discharge of that
liability in consideration of the grant of the assignment. This is both
logical and consistent with the result intended by the parties.”31
The trial judge considered that this justification was unavailable to Delta because the
settlement deed did not discharge or limit TRA’s liability in consideration for the
assignment.32
[26] The trial judge concluded that although it might be speculated that the parties intended
to fix the amount of liability as between them and make it appear that TRA assumed
a liability in that amount, the deed did not create any liability in TRA.33
28 Named after Damron v Sledge (1969) 460 P.2d 997.
29 See Derrington, “The Damron Assignment”, (1995) 7 Insurance Law Journal 65.
30 Ibid, p 65.
31 Ibid, p 67.
32 Reasons [152].
33 Ibid.
-- 10 of 49 --
11
[27] Delta contends and Mecon disputes that: cl 2.1(a) created an immediate and
continuing liability to pay and cl 2.2 operated only upon recovery by Delta under the
policy and, at that time, it limited TRA’s liability for any shortfall below the
Settlement Amount; alternatively, the limit imposed in the second part of cl 2.2 should
be regarded as being practically ineffective and as preserving the liability created by
cl 2.1, thereby giving effect to the purpose of the settlement deed that TRA is and
shall remain liable to Delta; notwithstanding the absence of demand by Delta, the
deed created an existing liability; and, alternatively, even if the obligation crystallised
only upon the contingency of Delta recovering under the policy pursuant to cl 2.2, the
deed created a liability to pay the Settlement Amount, being a liability falling within
the expression “liable to pay” in cl 5 of s 2 of the policy. In the course of oral
argument Delta submitted that the second part of cl 2.2 should be construed only as
a limit upon Delta’s entitlement to enforce TRA’s liability.
[28] Considered in isolation, the literal meaning of the second part of cl 2.2 justifies
Mecon’s construction of the deed. That construction would give effect to the
expectation that cognate words have congruent meanings, which is particularly
significant here because the words “liable” and “liability” are used in the same
sentence in a short deed drawn with legal assistance.
[29] Other considerations support a different construction of the deed. The introductory
part of cl 2.1 is so expressed as to render TRA’s agreement in cl 2.1(a) subject to both
its liability for the Settlement Amount in the first part of cl 2.2 and the limitation in
the second part of that clause. An ambiguity arises from the conflict within cl 2.2
between TRA’s present and future liability to pay the Settlement Amount and that
same liability being limited in the way described in that clause. In contradistinction
to the expression “subject to” in the introductory part of cl 2.1, the second part of
cl 2.2 is introduced by the word “but”. That does not require the limitation to be
construed as detracting from TRA’s liability, particularly in light of the emphatic
expression in cl 2.2 that TRA “remains, and shall remain, liable for the Settlement
Amount” and the acknowledgment in the immediately following provision, cl 2.3, of
TRA’s “liability to pay the Settlement Amount”.
[30] Importantly, recital F, cl 3.1, and the definition of “Mecon claim” reveal that a
fundamental object of the settlement deed was the assignment by TRA to Delta of
TRA’s right to an indemnity under the Mecon policy in respect of TRA’s liability to
Delta for the “Delta Claim”. It would defeat that fundamental object to construe the
second part of cl 2.2 as qualifying out of existence the liability which is so
emphatically expressed in the first part of cl 2.2 and acknowledged in cl 2.3. In Mount
Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd34 French CJ, Nettle and
Gordon JJ referred to principles applied in construing commercial contracts,
including that the meaning of the contract is to be determined objectively by reference
to its text, context and purpose, it is necessary to ask what a reasonable business
person would have understood the terms to mean, and that requires consideration of
the contractual language, the circumstances addressed by it, and the commercial
purposes or objects to be secured by it. Their honours confirmed that:
“Unless a contrary intention is indicated in the contract, a court is
entitled to approach the task of giving a commercial contract an
interpretation on the assumption “that the parties … intended to
34 (2015) 256 CLR 104 at [46]-[51].
-- 11 of 49 --
12
produce a commercial result”. Put another way, a commercial contract
should be construed so as to avoid it “making commercial nonsense or
working commercial inconvenience.””35
[31] Mecon submitted that TRA may have wished to avoid being rendered legally liable
for the Settlement Amount so as to avoid any risk to the maintenance of its building
licence on account of potential insolvency. That is not a significant consideration in
circumstances in which Mecon did not develop an argument that such a risk in fact
existed in the particular circumstances of this case and it did not refer to any evidence
that either party knew of or adverted to such a risk. As to the reference in cl 2.1(a) of
the settlement deed to TRA agreeing to pay the Settlement Amount “upon demand”,
the matters already mentioned, particularly the first part of cl 2.2, justify Delta’s
submission that TRA’s liability arose immediately upon execution of the deed
without the necessity for any demand.36
[32] Giving effect to the expressed objects of the deed, the repeated acknowledgments in
it of TRA’s liability to pay the Settlement Amount, and the reference in cl 2.3 to
TRA’s represented lack of financial capacity to meet any substantial part of that
liability as the explanation for Delta’s agreement to cl 2.2, the deed should be
construed as rendering TRA unconditionally liable to Delta for the Settlement
Amount and as precluding Delta from enforcing that liability except by and to the
extent of any recovery by Delta as the assignee of TRA’s right to an indemnity under
the Mecon policy.
[33] In principle an insured may be legally liable to pay a sum of money for the purposes
of a claim by the insured’s assignee upon the liability insurance even though the
liability is not enforceable against the insured: see CGU Insurance Ltd v One.Tel Ltd
(In liq)37 and Blakeley & Ors v CGU Insurance Ltd.38 As Mecon submitted, those
decisions were concerned with liability under a consent judgment rather than under
a contract, but the principle is applicable in both kinds of cases. My conclusion is
that upon the proper construction of cl 5.00 in s 2 of the Mecon Policy, the settlement
deed rendered TRA “legally liable” to pay Delta the Settlement Amount of
$2,581,179.18.
[34] Finally in this respect, I note that application of conventional principles of contractual
construction produces a result that is broadly analogous to the justification for
upholding the Damron Assignment described earlier in these reasons. However the
American jurisprudence differs in important respects from Australian law and I have
not taken it into account.
Did Delta prove that the Settlement Amount was reasonable?
[35] Appeal ground 6 contends that the trial judge erred in finding that the Settlement
Amount was not reasonable.
[36] The trial judge explained the content of the reasonableness requirement in terms that
are not controversial in this appeal:
35 (2015) 256 CLR 104 at [51]. Citations omitted.
36 In this respect, TRA’s liability is analogous with the liability of a debtor under a loan payable on
request: Leveraged Equities Ltd v Goodridge (2011) 274 ALR 655 at [221]; Ogilvie v Adams [1981]
VR 1041 at 1043.
37 (2010) 242 CLR 174 at [42]-[46].
38 (2017) 53 VR 733; [2017] VSCA 378 at [183]-[197].
-- 12 of 49 --
13
“To establish a liability, a settlement “must not only be reasonable but
also bona fide”. [Vero Insurance Ltd v Baycorp Advantage Ltd [2004]
NSWCA 390, [68]]. The question of reasonableness is to be determined,
“based on a reasonable assessment of the risk faced by [the insurer] if
the [third party] claims were to proceed to trial and judgment” [CGU
Insurance Limited v AMP Financial Planning Pty Ltd (2007) 235 CLR 1,
[24]]. The settlement “must reflect the plaintiff’s true prospects of
success if the proceedings had been conducted with care and skill … .”
[BNP Paribas, above, [17]] The insured is “required to have regard to
the proper interests of the insurer and [can] not claim indemnity under
the policy in respect of amounts payable under a settlement which
[does] not reflect, by its terms, a reasonable evaluation of the prospects
of a successful defence to a third party’s claim.” [The Distillers Company
Bio-Chemicals (Australia) Pty Ltd v Ajax Insurance Co Ltd (1973-
1974) 130 CLR 1, 32]. Monies paid for an ulterior purpose, that is
a purpose “extraneous to the risks insured against”, will mean that
there is not such a bona fide settlement of a liability [Distillers Bio-
Chemicals, above, pp 32-33]. In the Distillers Bio-Chemicals case,
Gibbs J gave examples of extraneous reasons which might motivate
an insured to settle: monies paid to avoid adverse publicity or to
relieve a parent company of its part in liability for a dangerous product
[Distillers Bio-Chemicals, above, p 32]. It is not that such matters
make the settlement unreasonable generally: they may provide
sensible commercial reasons to settle. But in terms of the rule
currently under discussion, these extraneous motives mean that the
settlement is not reasonable because it is not a bona fide or accurate
measure of liability in the action.”39
[37] Delta led no evidence about the legal advice, process, reasoning or negotiation which
led Delta to agree to the settlement. TRA did not waive legal professional privilege.
Mr Jones gave evidence in Delta’s case that he was closely involved in the process of
settlement,40 but the trial judge found that he was “coy” about those topics.41 The trial
judge accepted that the dearth of evidence upon those matters was not fatal and went
on to consider Delta’s case that the proved facts showed that it had sufficiently good
prospects of success in its action against TRA to make the Settlement Amount reasonable.
[38] As to TRA’s liability, Mecon’s own case was that “TRA made no attempt to comply
with the Subcontract”.42 It gave detailed particulars of the deficiencies in TRA’s
work in support of a defence that Delta’s claim as assignee was excluded by general
condition 10.08 of the policy, which required TRA and its employees to take all
reasonable steps to prevent incurring any loss, damage or liability. Each of the two
directors of TRA gave evidence which made it plain that, once “short anchors” were
extracted during the engineering investigation commenced as a result of the
movement of SW1, they knew that TRA’s work had been seriously deficient.43 It
was put to the directors during cross-examination (but denied) that they knew of the
deficiencies in TRA’s work at a much earlier time. The brief outline of the trial
judge’s findings in [3] – [4] of these reasons also suggests that when the settlement
39 Reasons at [142].
40 T6-64.
41 Reasons at [153].
42 Defence, para 13.
43 Mr Jones at T6-62–64; Mr Sandford T7-32-34.
-- 13 of 49 --
14
deed was executed Delta and TRA must have understood that TRA had breached its
subcontract in ways that caused Delta substantial loss. Other findings made by the
trial judge44 support the same view: there were serious deficiencies in TRA’s work of
installing the rock anchors; TRA falsified many of the required quality assurance
records; it was almost inconceivable that the workers installing anchors would not
have realised it was probable that they would not be able to perform the design
function; and TRA’s work was so bad that it might have endangered the life of
workers within the excavation and in adjacent properties. Mr Jones’ accepted evidence
was that, in circumstances in which the excavation of “short anchors” made it clear
that TRA “had clearly not done the right thing, and I wanted our first major project
not to be the one where our reputation was destroyed”, TRA stayed on the job and
assisted in the installation of remedial rock anchors for the next year or so working
free of charge under strict direction and supervision of Delta and others on site.45
[39] Mecon referred to allegations TRA pleaded when it was a defendant to the effect that
there were other causes of the movement in SW1, for which TRA was not responsible
and for which TRA was entitled to make a claim under the subcontract with Delta46
and that Delta contributed to the claimed loss in various ways.47 Mecon argued that,
particularly having regard to Delta’s failure to adduce evidence upon those matters in
circumstances in which it is to be expected that Delta easily could adduce such
evidence, Delta failed to prove that $1.837 million was a reasonable amount for that
part of Delta’s claim against TRA for the purposes of the settlement deed.48 Those
pleas are expressed in very general terms, with repeated references to further
particulars being provided once disclosure has been completed and TRA and
Mr Jones had obtained expert advice. Notwithstanding TRA’s pleas, the evidence
and findings adverted to in [38] of these reasons made it reasonable for TRA to settle
upon the basis that it would be found solely responsible for Delta’s losses.
[40] In these circumstances, TRA’s assumption of liability for the Settlement Amount
should be assessed upon the footing that it was reasonable for TRA to settle upon the
basis that it inevitably would be found liable for serious and extensive breaches of
subcontract which caused Delta substantial loss. Understandably, the trial judge’s
discussion of the reasonableness of the settlement focussed upon the evidence relating
to the quantum of Delta’s claim.
[41] When the settlement deed was executed, paragraph 16 of Delta’s statement of claim
against TRA claimed $2,831,179.18 for damages for breach of the subcontract. In
summary, the components of that claim comprised:
(a) An “incidental costs claim” of about $162,000, comprising $142,012.83
for “flight, travel and accommodation expenses of Delta staff engaged in
performing rectification works” and $20,000.00 for “Direct cost of
experts engaged to investigate and advise in relation to remedial works”.
(b) A “log of costs claim” of $1,885,218.39 for “direct unrecovered cost for
rectification works undertaken by Delta”.
44 Reasons at [16].
45 T6-62; Reasons at [156] and footnote 12.
46 Defence, para 22: AB 2173.
47 Defence para 23: AB 2173-2175.
48 Transcript 22 March 2018 at 1-4 to 1-8.
-- 14 of 49 --
15
(c) The “Watpac claim” of about $1 million, for “Shortfall in payments
under Contract due to TRA’s breaches…” This was claimed to be an
amount paid by Delta to Watpac on account of Delta’s liability arising
out of TRA’s breach of subcontract (after the deduction of $168,717.82,
described as the proportion of the subcontract sum not paid by Delta to
TRA). (In Delta’s claim against Mecon, the amount of the Watpac claim
was reduced to $720,577.70.)
[42] In final submissions at trial Delta contended, and appeal ground 7 contends, that the
reasonableness of TRA’s agreement in the settlement deed to assume liability for the
Settlement Amount could be demonstrated with reference to the following table:
Total claim by Delta against TRA as at the date of settlement $2,831,179.18
Interest accrued on the claim from the accrual of the cause of
action to date of settlement
(alternatively, from date of the issue of Delta’s proceedings
against TRA to the date of settlement ($731,040.60)
$2,379,390.90
Delta’s legal costs payable by TRA as at the date of settlement
(approx.)
$500,000
SUB-TOTAL $5,710,570.08
Likely further costs of TRA if it proceeded to trial $500,000
Likely further costs of Delta, payable by TRA if it proceeded to
trial and Delta’s claim substantially succeeded
$500,000
TOTAL $6,710,570.08
TRA’s counterclaim, interest on Delta’s claim and costs
[43] In light of the lengthy period that elapsed from when the subcontract work was done
until TRA and Delta entered into the settlement deed, TRA’s exposure to costs and
especially interest is a very significant factor in the assessment of the reasonableness
of the settlement. The trial judge acknowledged that the Settlement Amount made no
allowance for interest or costs and that the costs of running the claim against TRA
might have been considerable, but as against those matters the trial judge took into
account that the settlement also made no allowance for TRA’s claim for payment
under the rock anchor contract on Albert Street in circumstances in which TRA had
convinced Delta to allow it to stay on site and redo the work under supervision
without cost.49 The trial judge referred to TRA’s counterclaim for $550,286 on that
ground, the insufficiency of the evidence to enable an assessment of the merits of the
counterclaim and interest on it, and mentioned that the settlement went against TRA
in that Delta was left with the right to keep more than $64,000 of bank guarantees
under the subcontract.50 The trial judge also observed that nothing was said in the
footnote to the deed about those matters.51
49 Reasons at [156] and footnote 112.
50 Reasons at [156].
51 Reasons at [157].
-- 15 of 49 --
16
[44] Mecon relied upon the doubts expressed by the trial judge about the reasonableness
of the amount allowed in the settlement deed for TRA’s counterclaim. It emphasised
that the settlement deed made an allowance of only $250,000 for the counterclaim52
and that TRA otherwise paid the entirety of Delta’s claim (excluding interest and
costs). It developed detailed arguments in support of its contention that the amounts
allowed for TRA’s counterclaims were inadequate or not proved to be adequate.53 It
argued that Delta had no right to be compensated for its claimed loss and to refuse to
pay TRA in circumstances in which Delta ultimately received what TRA contracted
to provide.
[45] If TRA accepted an unreasonably small amount on account of its counterclaim that
might support an inference that it was in a relatively weak bargaining position. But
this aspect of the trial judge’s analysis proceeded upon the different premise that, for
the purpose of assessing the reasonableness of the settlement of Delta’s claim, TRA’s
counterclaim could be offset against its exposure to an award of interest and costs.
That approach may have been suggested by the fact that the settlement deed allowed
a set-off against Delta’s claim of $250,000 for one aspect of TRA’s counterclaim.
Unfortunately, Delta did not submit at the trial, as it did in this appeal, that the
$250,000 set-off was relevant only in so far as it reduced the amount for which TRA
assumed a legal liability for the purposes of cl 5.00 of the policy.
[46] Subject to the terms of the policy TRA was entitled to an indemnity from Mecon for
the reasonable amount which TRA became legally liable to pay Delta as compensation of
Property Loss, whether or not TRA was entitled to payments from Delta for the
subcontract price or under a contract on a different project. TRA’s counterclaim was
unrelated to its alleged liability for Property Loss in relation to which Delta claimed
as assignee to be entitled to an indemnity. It follows that any inadequacy in the set-
off for the counterclaim in the deed is not relevant to the issue whether the settlement
amount is reasonable. As between Mecon and TRA (and thus Delta claiming as the
assignee of TRA), if at the time of the settlement the Settlement Amount was a reasonable
estimate of the measure of TRA’s liability to Delta for damages, interest and costs,
the settlement could not be rendered unreasonable by the circumstance that TRA
might have made a better bargain in its own interests in relation to its counterclaim.
The log of costs and incidental costs claims
[47] In relation to the log of costs claim, the trial judge observed that the evidence adduced
by Delta “accounted for around $1.885 million of the claim Delta made against
TRA”.54 The relevant evidence was given by an engineer employed by Delta,
Mr Welsh, who, the trial judge accepted, had carefully compiled a log of those costs
which he considered reflected the cost to Delta of TRA’s breach of contract.55 The
trial judge accepted that Mr Welsh was “responsible, honest and intelligent”.56 The
log of costs tallied the costs Delta incurred from when it became evident that issues
with the SW1 wall would take the job outside budget parameters.57 Mr Welsh wrote
it up daily; it recorded Delta’s costs in complying with the Superintendent’s directions
to stabilise SW1 and later to backfill the entire site and to re-excavate, test and replace
52 This was for a claim by TRA on a different project. No allowance was made for the counterclaim for
payment under the sub-contact.
53 Respondent’s outline of submissions paras 29-32.
54 Reasons at [155].
55 Ibid.
56 Reasons at [8].
57 Reasons at [9].
-- 16 of 49 --
17
the anchors; the process lasted from May 2007 until about April 2008 and the total
amount of costs in the schedule was about $4.1 million.58
[48] Delta made a claim against its insurer, HSB Engineering Insurance Ltd, for the
amount in the log of costs and the amount of a claim of nearly $2.5 million made by
Watpac against Delta. Ultimately, after Delta sued HSB, they reached a compromise
in December 2010 by which HSB was to pay Delta $2,309,143.32, all of which was
referrable to the log of costs.59 Delta claimed against Mecon the same loss it had
claimed against TRA. The log of costs claim was for the total amount of the log of
costs after deduction of the amount recovered from HSB,60 but the trial judge noted
that the resulting amount is $1,837,826.43 rather than the claimed amount of
$1,885,218.61 After the trial judge analysed the Watpac Claim and found that it was
not supported by the evidence, the trial judge concluded that on the face of it, the
Settlement Amount was “$1 million higher than any loss Delta has managed to prove
in this proceeding and real questions arise, but cannot be resolved, as to the
counterclaim for payment by TRA.”62
[49] Mecon submitted that Delta had not proved an entitlement to recover about
$1.837 million from TRA on account of the log of costs claim.63 It was not obliged
to do so. The present issue instead concerns the reasonableness of that amount as
a measurement of the quantum of this claim in the settlement. Mecon argued that
a basis for discounting the costs was that Delta charged the costs of its machinery, as
well as external costs of subcontractors and the like, and no account was taken of the
fact whether the workers or the machinery would have been otherwise employed in
a different capacity.64 Mecon did not refer the court to any evidence supporting such
a contention or any particularisation of it by TRA in its defence to Delta’s claim.
Mecon also did not seek to contradict the submission for Delta that no question about
this was asked of Mr Welsh.
[50] That and other possible arguments suggest theoretical bases for challenging Delta’s
claim. It does not follow that TRA failed to prove that it was reasonable for it to settle
upon the basis that $1.837 million was a reasonable estimate of the measure of TRA’s
liability for Delta’s log of costs claim. A legitimate purpose of the settlement was to
avoid the very considerable expense of a thorough investigation into Delta’s claim
(including an audit of the log of costs) which TRA would incur if it continued to
litigate. Upon the evidence and the trial judge’s findings already mentioned -
particularly the findings that Delta incurred unrecovered rectification costs of about
$1.8 million as a result of serious deficiencies in its subcontract work, Delta’s
evidence accounted for about that amount of its claim against TRA, and the
Settlement Amount was $1 million higher than any loss Delta “managed to prove”65
- $1.837 million was a reasonable estimate of the measure of TRA’s liability for
Delta’s log of costs claim for the purposes of TRA entering into the settlement deed.
The appeal should be considered upon that footing.
58 Reasons at [10].
59 Reasons at [59].
60 The appropriateness of this deduction is not in issue.
61 Reasons at [68]. No explanation was given for the difference. These reasons proceed upon the footing
that the correct figure is $1,837,826.43.
62 Reasons at [157].
63 Transcript 21 March 2018 at 1-80.
64 Transcript 22 March 2018 at 1-10.
65 Reasons at [157].
-- 17 of 49 --
18
[51] The trial judge did not mention what I have called “the incidental costs claim” in the
course of discussing the question whether the settlement was shown to be reasonable,
presumably because of the relatively modest amount of that claim, but the trial judge
found in a different section of her reasons that the incidental costs claim was
conceptually the same as the log of costs claim and could have been included within it.66
[52] Accordingly, I would accept that Delta proved that, for the purpose of settling with
TRA, about $2 million was a reasonable measure of TRA’s liability for the total
amount of Delta’s log of costs claim (about $1.837 million) and its incidental costs
claim ($162,000).
Extraneous circumstances may have influenced the settlement
[53] Mecon referred to the trial judge’s remarks about the possibility that extraneous
circumstances might have inclined TRA to agree to a higher Settlement Amount than
the merits of the litigation alone warranted67 and the absence of evidence that
Mr Jones of TRA and employees of Delta could have given about such matters.
[54] Under appeal grounds 10(a) and (b), Delta argued that to the extent that the trial
judge’s conclusion was influenced by the finding that extraneous factors likely
influenced the settlement, that was an error because Mecon did not plead any such
point, as would have been required by the Uniform Civil Procedure Rules 1999 (Qld),
r 150(1)(k), and it was not suggested to Mr Jones in cross-examination. Under appeal
ground 10(c), Delta also argued that the Settlement Amount is objectively reasonable
in any event. Delta argues that the prospects of success in its claim were so high, and
that there was such a significant compromise by Delta in abandoning any claim for
interest and costs, that the Settlement Amount was demonstrably reasonable for those
reasons alone. Under appeal ground 10(d), Delta submitted that upon that case the
extraneous circumstances were irrelevant and it was unnecessary for it to adduce
evidence of the negotiations for the settlement or the legal advice TRA received.68
[55] The extraneous reasons which the trial judge considered likely inclined TRA to agree
to a higher Settlement Amount than was warranted by the merits of litigation were
that: firstly, in circumstances in which TRA lacked financial capacity to meet Delta’s
claim, it was faced with a claim by Delta and Mecon refused to indemnify it, TRA’s
attempt to sue Mecon was defeated because TRA could not provide security for costs,
it could not afford to pay its daily legal fees, and by the settlement deed TRA
effectively rid itself of Delta’s claim against it;69 and secondly, Mr Jones, who was
involved in negotiating the settlement gave evidence of his concern that he might lose
his BSA licence as a result of any verdict in the litigation, he was sued personally as
a second defendant, he did not have the financial resources to meet the claim and his
honesty and professionalism would certainly have been in issue in any proceedings,
but his liability to Delta was extinguished by the deed and the proceeding was
discontinued against him.70
[56] The trial judge noted that Delta bore the onus of proof but it adduced little evidence
about how those extraneous matters influenced the settlement negotiation, little
66 Reasons at [69] – [70].
67 Reasons at [158]-[160].
68 Delta could not adduce TRA’s legal advice in any event because TRA did not waive privilege.
69 Reasons at [158].
70 Reasons at [159].
-- 18 of 49 --
19
evidence about TRA’s counterclaim, and no evidence of the negotiation process. The
trial judge could not make definitive findings about these matters for lack of evidence
but doubt raised about those matters contributed to the trial judge not being persuaded
that the settlement was reasonable.71
[57] There are a number of reasons why the extraneous matters to which the trial judge
referred are not significant in relation to the log of costs and incidental costs claims.
First, the trial judge did not find that there were in fact any such extraneous matters
which influenced the Settlement Amount. Secondly, although the trial judge did not
in terms confine the relevance of those remarks to the assessment of the Watpac
claim, that may be what the trial judge had in mind. In that respect, the trial judge
referred to the extraneous circumstances immediately after finding that the Settlement
Amount was $1 million higher than any loss Delta had managed to prove in this
proceeding (a reference to Delta’s log of costs claim of about $1.837 million) and the
reasons do not convey that a paucity of evidence about the possible influence of the
extraneous circumstances detracted from that or the other findings in favour of Delta
upon that claim. Thirdly, the extraneous circumstances and the absence of evidence
of the reasoning and negotiation process were potentially relevant in the trial judge’s
analysis only because, in the trial judge’s view, Delta proved a total loss of only about
$1.837 million as against the Settlement Amount of $2,581,179.18; but that conclusion
resulted from the trial judge not including any allowance for interest or costs because
of a possible inadequacy in the amount allowed for TRA’s counterclaim, reasoning
which I respectfully do not adopt.
[58] The trial judge’s conclusions upon this topic were that, “Enough doubt was cast on
the reasonableness of the settlement to call for these matters to be explained” and in
the absence of an explanation “the doubts raised contribute to my not being actually
persuaded that the settlement was reasonable”.72 Those doubts are not relevant upon
Delta’s case that the Settlement Amount was proved to be much less than an objectively
reasonable estimate of the measure of TRA’s liability for the log of costs and incidental
costs claims alone: Rail Corporation New South Wales v Fluor Australia Pty Ltd.73
Reasonableness of the Settlement Amount
[59] Delta argued that the objective reasonableness of the settlement amount was
established by the evidence and findings about the log of costs claim and the
incidental expenses claim when regard is had to the amount of interest on those claims
and costs likely to be awarded in favour of Delta.
[60] For those claims, interest should be calculated upon the total amount of about
$2 million up to the date of the settlement deed of 24 May 2016. Delta explained that
the figures for interest in the table upon which it relies (see [39] of these reasons)
were calculated using the “interest calculator” on the “Queensland Courts” website,
which uses the pre-judgment interest rates applied by the Registrar when giving
default judgments, such rates being set by practice directions under s 47 of the Supreme
Court Act 1995 (Qld) (prior to 1 September 2012) and s 58 of the Civil Proceedings
Act 2011(Qld) (from 1 September 2012). When exercising the discretionary power
to grant pre-judgment interest under s 58 of the Civil Proceedings Act 2011 (Qld),
judges commonly use those interest rates, although particular considerations might
71 Reasons at [160].
72 Reasons at [160].
73 [2009] NSWCA 344 at [109]-[110].
-- 19 of 49 --
20
result in the use of other rates in some circumstances. It would seem reasonable for
TRA to have assessed its exposure to interest using the “interest calculator”.
[61] Section 58 of the Civil Proceedings Act empowers the court to order the inclusion of
interest in a judgment at the rate the court considers appropriate for all or part of the
amount of the judgment, and for all and part of the period between the date when the
cause of action arose and the date of judgment. Delta submitted that the discretion
was commonly exercised to award interest from the date of accrual of the cause of
action. The discretion is exercised in that way in some cases, but the case cited by
Delta, Keeley v Horton,74 does not suggest that a plaintiff has a prima facie
entitlement to interest from that date in a case of this kind, where the cause of action
accrues before any loss is incurred by the plaintiff. Interest might instead be awarded
from the date when the plaintiff sustained the loss where that date is subsequent to
the accrual to the cause of action. That accords with the underlying philosophy that
interest is awarded by way of compensation for a plaintiff being kept out of the plaintiff’s
money.75 Another approach, which is less generous to plaintiffs, is to award interest
from the date of commencement of proceedings; that approach might be adopted, for
example, where the plaintiff unreasonably delays in the prosecution of the claim. In
relation to those three different starting points for the calculation of interest:
(a) Delta’s calculation ([42] of these reasons) adopts a date in November
2006 as the date when Delta’s cause of action against TRA accrued. Mecon
contended that this date was not correct. I will adopt as the date of accrual of
the cause of action 3 May 2007, when the superintendent directed Delta
to backfill against the SW1 wall and install a further two rows of rock
anchors in it.76 Interest calculated from that date is about $1.587 million,
resulting in an amount for claim and interest (about $3.587 million)
which exceeds the Settlement Amount by more than $1 million.
(b) According to the log of costs, Delta incurred the total cost of about
$4.1 million between 11 April 2007 and 4 April 2008. Adopting 1 April
2008 as the date from which interest is calculated77 the amount for
interest is about $1.41 million, resulting in a claim with interest (about
$3.41 million) which exceeds the Settlement Amount by about $900,000.
(c) Interest from the date of commencement of Delta’s claim against TRA
(21 September 2012) amounts to $513,470 making the total amount for
the claim and interest (about $2.51 million) which is about $70,000 less
than the Settlement Amount.
[62] As to costs, Delta adduced evidence that up to the date of the settlement deed it had
incurred costs of about $450,000 to $500,000.78 Mecon made two points in response
to Delta’s argument that a reasonable amount for Delta’s legal costs up to the date of
the settlement was about $500,000. First, Mecon argued that a reasonable settlement
would have contemplated costs on the standard basis rather than the indemnity basis,
74 [2016] QCA 253 at [7].
75 Haines v Bendall (1991) 172 CLR 60 at 66.
76 This date seems likely to be much too favourable to Mecon. Many of the breaches of contract involved
in the installation of the variety of deficient rock anchors occurred long before the first instruction was issued.
77 Interest might instead be calculated, more generously to Delta, upon items or groups of items from the
dates between 11 April 2007 and 4 April 2008 when the costs for such items were incurred. I note also that
Delta did not argue that interest should be calculated (in relation to the log of costs claim) upon about
$4.1 million until 23 November 2009, about $3.3 million from 24 November 2009 until 1 December
2010, about $1.83 million from 1 December 2010 until 18 April 2013: see [47] and [48] of these reasons.
78 T6-7 (Welsh).
-- 20 of 49 --
21
and a “broad-brush allowance” for costs on the standard basis would be in a range of
$225,000 to $250,000. For present purposes that may be accepted as a guide.
Secondly, Mecon argued that it could not be assumed that all of the costs were
attributable to Delta’s claim against TRA. That is so but, as Delta submitted, a party
in TRA’s position would not be required or able to carry out some precise calculation
of Delta’s costs. Given the nature of Delta’s claim and the period of the litigation, it
may readily be concluded that a reasonable compromise of Delta’s claim would
include an amount for costs which exceeded at least $150,000.
[63] Upon each of the three bases of calculating interest in [61] of these reasons, the total
amount for the log of costs claim, interest, and costs, exceeds the Settlement Amount
of $2,581,179.18. Upon the first and second bases for calculating interest, the total
amount for the log of costs claim, interests, and costs exceeds the settlement amount
by more than $1 million.
[64] From the perspective of a reasonable insured at the time of the settlement deed, it was
foreseeable that after a trial a less generous basis of calculating interest might be
adopted and that Delta might not recover costs on all parts of its claim. On the other
hand, it was also foreseeable that it would recover much more than $150,000 for costs
up to the date of the settlement deed. The appropriate conclusion is that when the
settlement deed was negotiated the Settlement Amount was a reasonable compromise
even if regard is had only to the log of costs claim, the incidental costs claim, interest
and costs. One factor in particular weighs heavily in favour of that conclusion; there
was a real prospect that TRA would be held liable for the log of costs claim alone in
an amount which, with interest and costs, would exceed the Settlement Amount by
more than a million dollars.79 It is also relevant that the future costs of defending
Delta’s claims and Delta’s costs of running them inevitably would be very substantial.
As the trial judge noted, Delta’s costs of running its claim against TRA “might have
been considerable”.80 Upon the current hypothesis that Mecon is liable to indemnify
TRA, that is another factor which suggests that a settlement upon the terms of the
deed was reasonable from Mecon’s perspective.
[65] I conclude that, even if no allowance is made for the Watpac claim, the Settlement
Amount was an objectively reasonable amount for the purposes of a settlement that
rendered TRA legally liable to Delta such as to attract the indemnity in cl 5.00 of the
Mecon policy. That conclusion assumes, of course, that TRA’s legal liability for the
total amount of the log of costs and incidental costs claims is insured as compensation
of Property Loss under cl 5.00: that issue is considered separately.
The Watpac claim
[66] In light of that conclusion it is not strictly necessary to consider TRA’s potential
liability for the Watpac claim, but I will explain my conclusion that it was reasonable
for TRA to take into account when settling with Delta at least that TRA was exposed
to a potentially significant liability for the Watpac claim.
79 Mecon did not submit that there had been unexplained and significant delay by Delta in prosecuting
its claim against TRA of a kind which might justify a deferral of the commencement date for interest
until the commencement of proceedings: See Interchase Corporation Limited (in Liq) v Grosvenor Hill (Qld)
Pty Ltd (No 3) [2003] 1 Qd R 26; [2001] QCA 191 at [61]-[63] (McPherson JA, McMurdo P and
Thomas JA agreeing).
80 Reasons at [156].
-- 21 of 49 --
22
[67] The trial judge found that there was no basis in the evidence for the Watpac claim,
which Delta ultimately quantified at $720,755.81 The trial judge recorded that Delta’s
case at trial was that, were it not for TRA’s defective installation of ground anchors,
Watpac would have paid Delta $720,557 under their contract. That figure was
calculated by deducting the amounts which QIC and Watpac paid Delta during the
course of the job and under a 2010 settlement deed from the contract price shown on
the original contract between Delta and QIC.82 The trial judge considered that to be
“a most unrealistic equation”,83 having regard to the existence of claims under that
contract which had no relationship with TRA’s work. The trial judge summarised the
evidence on that topic as follows:
“[41] Delta’s claims for payment from QIC and then Watpac were
processed according to the Building and Construction Industry
Payments Act, ie., via payment claims and payment schedules.
There were variations to the work that affected the amount that
was to be paid under the contract. There were claims for
variations made by Delta on Watpac before work on the rock
anchors began, and claims that had nothing to do with the rock
anchors. Some claims were agreed between Delta and Watpac,
and some were disputed. Indeed, there were some claims which
were in dispute between Delta and QIC before the novation.
There were about 35 claims for variation by the time Mr Welsh
arrived on the job.
[42] Before the ground anchor work began, Watpac had alleged that
Delta was delaying the works, and indeed delaying the critical
path of the works. Watpac’s claims in relation to that issue were
worth a significant amount of money. The date of practical
completion for Delta’s works was originally 22 January 2007.
Liquidated damages were in the amount of $7,500 per day up to
a maximum of $200,000. The rock anchors were a relatively
small part of the work Delta contracted to do; the rock anchor
contract was worth only $450,000. As part of the novation of
the contract, the date for practical completion of Delta’s works
was adjusted out to 15 February 2007, but the works were
nowhere near complete at that time. On 26 February 2007
Watpac issued a notice to Delta asking why it should not take
the work out of its hands because its programming showed it
would complete its contract 57 days after the date for practical
completion (then 9 March 2007).
[43] At the time the certificate of practical completion issued for
Delta’s work under its contract with Watpac there were
outstanding claims between Watpac and Delta. There were
claims made by Delta against Watpac, including for payment
for works done under the contract at that point.”84
[68] The December 2010 settlement deed between Watpac and Delta referred to Watpac’s
claims against Delta in the recitals and also recited that Watpac and Delta had agreed
81 Reasons at [155].
82 Reasons at [85].
83 Reasons at [86].
84 Reasons at [41]. Footnotes omitted.
-- 22 of 49 --
23
to settle the rectification ground anchor claim and the final sum payable under the
excavation contract on the terms of the deed. Relevantly, by the deed: Delta and
Watpac released each other from liability in relation to the rectification ground anchor
claim (cl 1.1), Delta and Watpac agreed that the total sum payable by Watpac to Delta
under the excavation contract was $3,773,020.60 [plus GST] and that Watpac had to
the date of the deed paid Delta $3,326,021.36 [plus GST] of that total sum (cl 2.1.1
and cl 2.1.2), Watpac was obliged to pay Delta the balance amount of $446,999.24
[plus GST] within 14 days of Delta executing the deed (cl 2.2), and Watpac and Delta
agreed that the deed contained everything the parties had agreed in relation to the
subject matter it dealt with (cl 3.3). The deed also recited that Watpac had notified
Delta of claims against Delta described as “the Regent building damage claim” and
the “the Regent building ground anchor compensation claim”. Under the deed Delta
agreed that it indemnified and must continue to indemnify Watpac from any liability
in relation to those claims (cl 1.5), which were originated in claims by the owners and
occupants of the Regent Theatre building adjacent to the project made against QIC,
and then by QIC against Watpac (cl 4.1, definitions).
[69] There is no suggestion that Delta had any claim against Watpac in relation to the
rectification ground anchor claim. Watpac’s release of Delta from liability in relation
to that claim would not preclude Delta from contending in proceedings against TRA
that the amount Delta received from Watpac under their contract had been reduced
by a substantial amount attributable to Watpac’s rectification ground anchor claim
against Delta.
[70] Mr Welsh gave evidence that the sum of about $1.2 million “is the balance of the
amount of contract works that otherwise would have been paid to Delta, had it not
been for the ground anchor issue and the prolongation of the works on the project …
So the amount that was outstanding – so the $1.2 million – was money that Delta
otherwise would have been entitled to under our total contract value for contract
works that were performed. But it wasn’t paid and was considered offset against
Watpac’s losses and their claims to Delta Group for the ground anchor issue and the
losses that they had incurred. So that $1.2 million was ultimately reduced by the
amount that was paid [to Delta] under the Watpac settlement in 2010.”85 The trial
judge accepted Delta’s submission that Mr Welsh was not challenged upon that
evidence, but observed that he was cross-examined to elicit the matters summarised
in [41] – [43] of the reasons. The trial judge also noted that Delta did not attempt to
adduce any evidence about how the disputes and agreements between Delta and
Watpac during the course of their contract affected the amount to be paid under it.86
The trial judge also referred to concessions and other evidence about the same matters
and held that Mr Welsh’s evidence was not reliable “as meaning that, but for the
faulty installation of the rock anchors, Delta was entitled to the very amount stated
on its contract with QIC.”87
[71] Appeal ground 9(b) challenges that finding upon the grounds that the trial judge
accepted that Mr Welsh was a reasonable, honest and intelligent witness, there was
no direct challenge to this evidence in cross-examination, and the trial judge
erroneously refused to admit evidence of the payment claims and schedules between
Delta and Watpac that corroborated his evidence.88 Appeal grounds 8 and 9(c)
85 Reasons at [86].
86 Reasons at [44].
87 Reasons at [87].
88 Appeal ground 9(b).
-- 23 of 49 --
24
contend that the trial judge applied the wrong test in finding that “the Settlement
Amount was $1 million higher than any loss Delta has managed to prove in this
proceeding”89 and in finding that the settlement between Delta and TRA was
unreasonable in relation to Delta’s claim for $720,555, because the test required an
assessment of the reasonableness of the settlement on the material available at the
time for settlement rather than proof of the actual loss that would have been
established at the trial of the settled claim.90 Appeal ground 9(a) contends that the
trial judge should have given more weight to Mr Welsh’s evidence.91
[72] The matters mentioned in [67] of these reasons justified the trial judge in being
sceptical about the manner in which the Watpac claim was pleaded in Delta’s claim
against TRA. On the other hand, the trial judge found that Watpac did suffer costs
and delay because of TRA’s breaches of its subcontract with Delta92 and that Watpac
made claims against Delta for the claimed extra costs:93
(a) In October 2007 Watpac claimed $737,615 against Delta “for the costs
associated with the rectification works of the damaged shoring walls,
which included, about $75,000 for “repair to services Regent Laneway”,
about $95,000 for Additional Two Rows of Anchors”, and about
$580,000 for “Fill Site and Retest Anchors”.
In relation to the last item, the trial judge referred to the following
evidence given by Mr Welsh. Watpac incurred part of those costs to
a contractor, Queensland Pre-Stressing, Watpac engaged to test TRA’s
ground anchors. Part of those costs were for Watpac’s own site
personnel for whom there was no productive work because Watpac could
not progress its work whilst the excavation was being back filled.94
(That evidence is consistent with the narrative in Watpac’s claim,95
which includes hundreds of supporting documents, including invoices by
Queensland Pre-Stressing to Watpac and Queensland Pre-Stressing daily
site reports.96) Mr Welsh verified substantial components of the claim,
said that Watpac would not have incurred the costs but for Delta’s late
completion which was attributable to the lateral wall movement caused
by the defective ground anchors, and said that Watpac had no
responsibility for the ground anchors being faulty.97
(b) In May 2008 Watpac delivered a revised claim against Delta,98
increasing the claim to $2,477,259.78, of which $1,775,920.23 was for
“fill site and retest anchors”. Supporting documentation for the claim
was again included.99 Mr Welsh also supported this claim.
(c) Watpac’s final claim of that kind against Delta was dated 1 August 2008
and it claimed $2,480,998.43, of which the claim for “fill site and retest
89 Reasons at [157].
90 Appeal grounds 8, 9(c).
91 Appeal ground 9(a).
92 Reasons at [35].
93 T6-7 referred to in reasons [45]-[48].
94 T5-46, Reasons at [45].
95 Ex 10 AB 1158 at 1159(4), 1225.
96 AB 1262-1324.
97 T5-46 - 5-48.
98 Ex 52 AB 1326.
99 AB 1327-1438.
-- 24 of 49 --
25
anchors” comprised $1,779,171.23. Mr Welsh did not give evidence
about this claim, which made only a relatively slight adjustment to the
May 2008 claim.
[73] In the context of the findings mentioned in [3], [4] and [38] of these reasons, those
findings are themselves sufficient to suggest that, from the perspective of TRA at the
time when it settled with Delta, TRA was exposed to an apparently credible and
substantial claim by Delta that it was liable to Watpac as a result of TRA’s breaches
of its subcontract. Upon the trial judge’s findings, Delta did not prove enough to
enable a reliable estimate to be made of the measure of Delta’s liability to Watpac,
but it nonetheless must have appeared to TRA that it was potentially substantial.
[74] The prospect that, after the completion of interlocutory steps and a trial, TRA would
be held liable for a substantial amount in relation to the Watpac claim is an additional
ground for finding that the Settlement Amount was objectively reasonable,
notwithstanding the trial judge’s inability to estimate the potential amount of that
liability. In view of that conclusion and my conclusions in relation to the log of costs
and incidental costs claims, it is not necessary further to consider Delta’s grounds of
appeal relating to the Watpac claim.
Was TRA liable to pay an amount in compensation of Property Loss?
[75] The trial judge rejected Delta’s claim for the additional reason that TRA’s claimed
legal liability under the settlement deed to pay the Settlement Amount was not a legal
liability to pay “in compensation of …. Property Loss” as a result of an Occurrence within
the meaning of cl 5 of s 2 of the policy. “Property Loss” is defined to mean:
“(a) physical loss, damage or destruction of tangible property
including resultant loss of use of such property and/or,
(b) loss of use of tangible property that arises from an Occurrence,
provided that this loss of use does not result from:
(i) delay or lack of performance of any contract or agreement
by you or by others on your behalf, or
(ii) a design defect or your failure to comply with a Project
specification.”
[76] The trial judge held that there was no such “Property Loss”:
“Delta did not lose any property by reason of the defective installation
of the ground anchors. No property belonging to Delta was damaged
or destroyed. It suffered economic loss, the starting point for
assessment of which is Mr Welsh’s schedule of loss: costs and
expenses. It was not the pleaded case that Delta suffered Property
Loss, as defined, and no attempt was made either to characterise the
Delta claim against TRA in this way or to dissect out parts of it which
could be characterised in this way.”100
[77] Appeal grounds 3 and 4 contend that the trial judge erroneously construed the
definition of Property Loss as concerning property belonging to Delta and by making
the finding that Delta did not own the property when that was not pleaded or
100 Reasons at [164].
-- 25 of 49 --
26
contended for by Mecon and as a result Delta was denied the opportunity to address
the court on that matter. Appeal ground 5 contends that the trial judge erred in holding
that the wall movement was not Property Loss, and in particular that the trial judge
did not give sufficient weight to the evidence of Mr Ervin (a civil engineer called by
Mecon) that SW1 was failing to perform its function of limiting deflections of
adjoining land, the trial judge should have held that there was property loss in the
form of a physical alteration or change that impaired the value or usefulness of the
thing said to have been damaged, the trial judge did not give sufficient weight to
evidence of Dr Baigent whose evidence was not challenged by Mecon in cross-
examination or in submissions, and the trial judge erroneously relied on an irrelevant
finding that QIC was the owner of the retaining walls.
[78] Delta argues that the lateral movement of the retaining walls of the excavation (the
“Wall Movement”) pleaded by Delta and admitted by Mecon falls within paragraph (a) of
the definition of Property Loss, upon the basis that “physical loss” or “damage”
comprehends a physical alteration or change that impairs the value or usefulness of
the thing said to have been damaged: Ranicar v Frigmobile Pty Ltd,101 Graham Evans
& Co (Qld) Pty Ltd v Vanguard Insurance Co Ltd,102 Bayer Australia Pty Ltd v
Kemcon Pty Ltd,103 and Guardian Assurance Co Ltd v Underwood Constructions Pty
Ltd.104 Mr Ervin gave evidence that the purpose or utility of the retaining wall is to
support the excavation until the permanent structure is completed so as to prevent
collapse and to limit deflections to avoid adjacent facilities being impacted by the
construction. The retaining walls failed because they failed to sustain the required
load. Unchallenged evidence by Dr Baigent (a civil engineer called by Delta) was to
similar effect. Dr Baigent gave evidence that by May 2007 the retaining walls had
suffered significant lateral movement, and he described the retaining walls as having
failed and said that there was “no alternative” but to backfill the entire excavation to
protect against collapse.
[79] Mr Ervin agreed that retaining wall SW1 was “not performing as it should” and he
gave evidence that SW1 continued to fulfil its primary function of preventing collapse
of excavation although it failed to perform its secondary function of limiting
deflections of adjoining land. Delta argued that the trial judge’s reasons did not
explain why the loss of functionality of SW1, which threatened the integrity of the
excavation, was not property damage, whether the function was characterised as
a primary or secondary. Delta argued that the trial judge erred in holding105 that the
failure of SW1 to prevent adjoining earth moving itself was not damage of tangible
property. In reliance upon Guardian Assurance Co Ltd v Underwood Constructions
Pty Ltd106 Delta also argued that the excavation itself amounted to property, so that
damage to it resulting from the loss of functionality in SW1 would amount to Property
Loss, and that costs incurred in fulfilling a contractual obligation to prevent liability
to a third party might fall within an indemnity against liability. Delta submits that the
trial judge did not take into account the fact that the entire excavation had to be refilled
because of a concern that the retaining walls would suffer further lateral movement.
101 (1983) 2 ANZ Ins Cas 60-525.
102 (1986) 4 ANZ Ins Cas 60-689.
103 (1991) 6 ANZ Ins Cas 61-026.
104 (1974) 48 ALJR 307.
105 Reasons at [98].
106 (1974) 48 ALJR 307 at 309.
-- 26 of 49 --
27
[80] Delta submits that during the period of nearly 12 months when the excavation was
backfilled and then re-excavated there was a loss of the “use of” the Retaining Walls
falling within the definition of Property Loss. Mecon’s argument is submitted to be
inconsistent with its admission of Delta’s allegation that “the Retaining Walls”
underwent significant lateral movement and with Dr Baigent’s evidence that the
whole of the remedial works were required to ensure the excavation was stable and
safe. Delta argued that the only reason the retaining walls needed to be saved by the
work, the cost of which was claimed from TRA, was because they were impaired in
a way which amounted to Property Loss.
[81] Mecon objected that Delta should not be permitted on appeal to depart from its
pleaded case: Delta did not plead that the Property Loss was the loss of functionality
of the retaining walls, or one or more of them, but that the Wall Movement (defined
as “significant lateral movement” of the Retaining Walls) was the Property Loss, and
it pleaded only that SW1 and SW2, rather than all four retaining walls, underwent
“the Wall Movement” as a result of TRA’s breach of contract. Mecon argued that
upon the evidence there was no loss of functionality in relation to any of the four
walls. The design of the retaining walls catered for movement, which therefore could
not amount to physical loss, damage or destruction of tangible property. Delta’s
relevant claim was for costs of, amongst other things, backfilling against each of the
four walls and removing the backfill. Most of that work could not be related to the
claimed loss of functionality of SW1 and SW2, and the trial judge found that only
SW1 moved unacceptably. Delta failed to establish that TRA was legally liable to
pay to Delta the Settlement Amount “in compensation of” the pleaded wall movement
(or the argued loss of functionality) of SW1.
[82] The trial judge did not find that it is a condition of cl 5.00 that the legal liability be
owed to the owner of the property alleged to have been damaged. The trial judge
merely referred to the fact that Delta did not own the allegedly damaged property,
thereby excluding ownership of the property by Delta as a ground upon which it could
be concluded that TRA was liable to pay Delta an amount “in compensation of” the
allegedly damaged property.
[83] There is substance in Mecon’s pleading points. Delta did not seek to amend its
pleading and it did not argue that Mecon had acquiesced in the litigation of issues
outside the pleadings. Of the four “Retaining Walls” mentioned in Delta’s statement
of claim only SW1 and SW2 are alleged to have undergone “significant lateral
movement” (“the Wall Movement”) as a result of TRA’s breach of contract.107
Mecon admitted that allegation. Delta did not plead and Mecon did not admit that
the claimed Property Loss was a loss of use or functionality in any retaining wall, that
the “significant lateral movement” caused any damage to the Retaining Walls
themselves, or that they were lost or damaged in any other way, or that the Property
Loss comprised the movement of retained soil or a threat to the excavation.
[84] Delta’s statement of claim against TRA relevantly pleaded as follows:
(a) Delta engaged TRA to install anchors and whalers to secure “the
Retaining Walls”.108
107 Third amended statement of claim, para 12; Further and Better Particulars of the statement of claim,
para 2(a): AB 1997.
108 Third amended statement of claim para 7: AB 1913.
-- 27 of 49 --
28
(b) In breach of the terms of the subcontract, TRA failed to install anchors
fit for the purpose of securing the Retaining Walls.109
(c) TRA’s breaches of the subcontract caused the Retaining Walls (SW1 and
SW2) to undergo significant lateral movement (“the Wall Movement”).
(d) The Wall Movement (SW1 and SW2) caused damage to the Site
(175 Albert Street, Brisbane) and surrounds (described as damage to
a road surface above SW1 wall with damage to underground services,
settlement and cracking of Elizabeth Street road surface above SW2
wall, and settlement and cracking of parts of the Regent Theatre adjacent
to the Site).110
(e) As a result of that Wall Movement, on 3 May 2007 Delta was directed
by the contract superintendent to backfill against the SW1 wall and
install a further two rows of rock anchors in it, on 28 June 2007 to
undertake emergency works to secure the stabilising beam to wall SW1,
and on 23 and 24 July 2007 to backfill the entire excavation to permit all
anchors to be tested and defective anchors to be replaced while
preventing further wall movement.111
(f) That work delayed practical completion under Delta’s contract with
Watpac.112
(g) As a result of TRA’s breach of the subcontract, Delta suffered loss and
damage, particulars of which are set out in schedule to paragraph 16 of
Delta’s statement of claim.
Mecon admitted (a) – (c).
[85] In relation to (d) of [84], paragraph 13 of Delta’s statement of claim pleads that the
“Wall Movement caused damage to the Site113 and surrounds as follows –
“(a) Settlement and cracking to laneway roads surface above SW1
wall with damage to underground surfaces (including water
main and stormwater piping damage);
(b) Settlement and cracking of Elizabeth Street road surface above
SW2 wall;
(c) Settlement and cracking of the west wall, internal walls and
structure of the Regent Theatre adjacent to the Site.”
Contrary to a submission by Delta, that plea did not put Mecon on notice of a claim
that, in addition to the specifically pleaded movement of SW1 and SW2 and whatever
damage at the Site is comprehended within (a) – (c), there was some unidentified
damage at the “Site” of a kind which Delta described in argument in this appeal.
Ultimately, Delta did not rely upon a case that (a) – (c) comprehended any significant
damage at the Site apart from the pleaded movement of SW1 and SW2.
109 Third amended statement of claim para 11(a): AB 1915.
110 Third amended statement of claim para 13: AB 1916.
111 Third amended statement of claim para 14: AB 1916.
112 Third amended statement of claim para 15: AB 1917.
113 The “Site” is defined by reference to the address at which Delta contracted to undertake excavation
works: Third amended statement of claim para 4: AB 1912.
-- 28 of 49 --
29
[86] After TRA and Delta settled, Delta pleaded against Mecon that the Wall Movement
(by definition confined to SW1 and SW 2) and damage to the Site and surrounds was
both an “Occurrence” and “Property Loss” in terms of cl 5.00.114 As to the surrounds,
Delta submitted that its log of costs included some (but not many) items of costs for
damage to adjacent structures, but Delta did not litigate a case that distinguished those
items from the mass of the items in the log of costs and it did not contend that the
Settlement Amount could be regarded as reasonable if its claim was confined to the
total cost of those items. As to the Site, for the reasons given in the preceding
paragraph, Delta’s pleaded case was ultimately confined to the contention that the
movement of SW1 and SW2 itself amounted to damage and Property Loss.
[87] Some of Delta’s arguments assumed that the “Retaining Walls” comprehended the
whole retaining system, including the retaining walls and the rock anchors.115
Understandably, the experts’ evidence did not always draw the distinction between
the retaining walls and the rock anchors which were designed to secure the retaining
walls, but Delta’s pleading clearly made that distinction. The trial judge cannot be
said to have erred by analysing Delta’s claim upon that basis.
[88] The grounds of appeal do not challenge the trial judge’s findings that some movement
of the retaining walls was acceptable and only SW1 moved unacceptably.116 Upon
the findings, the movement of SW1 (and the unpleaded movement of retained soil
and threat to the excavation) resulted directly from the failure of the anchors to fulfil
their design function. The postulated threat to the excavation was not in truth that
a failure in the retaining wall would damage the excavation; it was that the
deficiencies in the ground anchors would result in damage to the retaining wall and
the excavation. The only defect was in the construction of the rock anchors. There
was no physical change in the retaining wall that impaired its value or usefulness such
as occurred in the cases cited by Delta. It was not pleaded or found that SW1 or any
wall did not itself remain wholly intact and capable of fulfilling its designed purpose.
The trial judge’s findings to the contrary are not susceptible of challenge: after the
unacceptable movement was detected in SW1, the retaining walls were buttressed and
supported by the backfilling of soil and then with properly installed rock anchors,
after which the walls fulfilled their function; although at some point the walls “may
have been imperilled or stressed”,117 the walls were saved by timely steps being taken
and they were not lost; and there was no evidence that the walls were damaged in the
process of backfilling and re-excavation.118 As the trial judge concluded, movement
of any retaining wall was not damage independently of damage to the wall or some
other tangible property, and the “significant lateral movement” caused by TRA’s
breaches of the subcontract was not of itself capable of amounting to Property Loss
within (a) of the definition in the policy.119
[89] Furthermore, cl 5.00 of the policy applies in relation to Property Loss “as a result of
an Occurrence”. As the trial judge observed,120 a case that the Wall Movement of
SW1 was itself property damage would require Delta to postulate a different
114 Third amended statement of claim paras 77, 78 and 79(c): AB 1926.
115 Transcript 21 March 2018 at 1-38.
116 Reasons at [19].
117 The trial judge did not find that the walls were in fact imperilled or stressed and the findings mentioned
in [91] of these reasons are to the contrary in relation to the walls other than SW1.
118 Reasons at [96].
119 Reasons at [93].
120 Reasons at [99].
-- 29 of 49 --
30
Occurrence, such as its installation of the deficient SW1 ground anchors, but that was
not Delta’s pleaded case.
[90] Delta’s argument fails for another reason. It is not necessary to attempt a comprehensive
exposition of the meaning of the expression “compensation of…Property Loss” in
cl 5.00, but in relation to damage to property which is repaired the compensation
would appear not to extend beyond the cost of the repair and perhaps any residual
loss in the value of the damaged property. The buttressing and supporting of the four
retaining walls by the backfilling of soil and proper installation of rock anchors was
required to compensate Delta for the consequence of TRA’s breach of contract that
in relation to all four retaining walls the rock anchors did not meet the specification.
The damages claimed by Delta were for the economic loss it suffered as a result of
that breach of contract. Even if, contrary to my conclusion, the movement of SW1
itself amounts to damage to property or Delta can rely upon the argued loss of
function in SW1, the vast majority of the claimed damages could not be regarded as
compensation of any such damage to SW1 alone. The trial judge was not asked to
determine and did not determine what amount would be a reasonable estimate of the
measure of TRA’s liability to Delta for such compensation. Unsurprisingly, Delta
did not contend that the Settlement Amount was a reasonable estimate of the measure
of TRA’s liability upon that basis.
[91] Delta argued that there was a causal nexus between that functional impairment of
SW1 and TRA’s liability to Delta for the log of costs claim. A causal nexus is insufficient
to justify a conclusion that the claimed costs are compensation of Property Loss
within the meaning of cl 5.00. Delta also argued that upon the expert evidence and
the evidence of Mr Welsh to the effect that it was necessary to fill the whole
excavation as a result of what was found upon investigation of the four retaining
walls, TRA’s liability arose from an impairment in the function of all four retaining
walls. This case was not pleaded and, as I have mentioned, the notice of appeal does
not challenge the trial judge’s finding that the only unacceptable movement was in
SW1; and such findings as were made about SW3 and SW4 do not support
a conclusion that there was such a loss of functionality in those walls (as well as in
SW1 and SW2 or in the retaining system considered as a whole) as to suggest that
TRA’s liability for the cost of filling the whole excavation could be regarded as
compensation of that postulated loss of functionality. The trial judge generally
preferred Mr Ervin’s evidence to Dr Baigent’s evidence.121 The trial judge recorded
Mr Ervin’s evidence about SW3 and SW4 that, “No significant movement was
observed on these walls, and therefore it is not possible to say whether the anchors,
as installed, were adequately performing their intended function.”122 He explained
the instruction to backfill against SW1 on 3 May 2007 as resulting from the observed
increasing movement of SW1, in circumstances in which the consequences of
a collapse of part or all of that wall would have been considerable.123 Although
Dr Baigent noted that the possibility of failure of SW1 “and the other walls” would
have been of great concern if the defective nature of the anchors had been known,
that remark was made in the context of a reference to the support of SW1 being
“severely compromised by the defective anchor installation” and he also noted that
SW2, SW3 and SW4 did not fail although they did have defective anchors.124 In
relation to the 24 July 2007 direction which required backfilling of the whole site, the
121 Reasons at [13].
122 Reasons at [20].
123 Reasons at [21].
124 Reasons at [22].
-- 30 of 49 --
31
trial judge referred to Mr Welsh’s evidence that, following investigations which
revealed that the TRA anchors were short, testing of SW2, SW3 and SW4 also
produced anomalies and Delta did not have the confidence of Watpac or QIC.125 The
trial judge referred also to Mr Welsh’s evidence that the filling of the site was
occasioned by concern about the SW1 wall and not any proved instability in SW3 or
SW4.126 The evidence which the trial judge accepted justified the finding that the
only unacceptable movement was in SW1.
[92] In summary:
(a) Upon the pleaded case that the Occurrence and the Property Loss was
the excessive movement of SW1 and SW2 and damage to the Site and
surrounds resulting from that movement, Delta’s claim under cl 5.00
fails because:
(i) The movement in those walls was not Property Loss within the
meaning of the policy.
(ii) The notice of appeal does not challenge the finding that only SW1
moved unacceptably and Delta’s unpleaded challenge to that
finding would not succeed.
(iii) The postulated Property Loss did not result from the Occurrence
but from conduct not alleged to be an Occurrence, namely, TRA’s
breach of contract in installing rock anchors for all four retaining
walls that were not in accordance with the specification and were
incapable of securing SW1.
(iv) Delta did not prove that the Settlement Amount was reasonable as
compensation of that Property Loss.
(b) Delta did not plead that a loss in functionality of a retaining wall, movement
in retained soil, or a threat to the excavation, was the Property Loss.
(c) If, contrary to my conclusion, Delta should be permitted to argue such a
case, then its case in that respect is confined by the pleadings to SW1
and SW2 and it fails for the reasons given in sub-paragraphs (ii) – (iv) of
paragraph (a).
Delta’s claim as an insured
[93] The claim by Delta as an insured which remains in issue in this appeal is its claim for
the costs of temporary protective repairs under cl 5.03 in s 2 of the policy. Clause 5.03
is reproduced in [8] of these reasons. This claim by Delta was for the cost of
complying with the superintendent’s directions, firstly, to place fill beside SW1, and
thereafter to backfill the whole site and subsequently to remove that backfill. The
total amount of the claim is $1.478 million.127 Taking into account the situation of
cl 5.03 in s 2 of the policy and in cl 5 (concerning liability), the trial judge construed
cl 5.03 as relating only to costs incurred to prevent or minimise Property Loss for
which an insured could have become legally liable.128 The trial judge observed that
the fact that Delta never became legally liable to pay any compensation for Property
125 Reasons at [29].
126 Reasons at [31].
127 Reasons at [11], [104].
128 Reasons at [105], referring to [102] and Astrazeneca Insurance Co v XL Insurance [2013] 1 Ll Rep 290
(see [144]).
-- 31 of 49 --
32
Loss was not conclusive, because the relevant costs would be incurred in cases of an
immediate threat before it would be possible to determine who might be legally liable
for the costs, the aim of incurring the costs under cl 5.03 being to prevent the
occurrence of Property Loss.
[94] The trial judge accepted submissions that the only works undertaken by Delta to
prevent “immediate threat of Property Loss” were the works of placing earth against
SW1, the subsequent works resulting not from an immediate threat, but because the
testing of rock anchors after SW1 was buttressed revealed that the anchors had not
been installed in accordance with the shop drawings and Watpac lost faith in TRA’s
work.129 The subsequent re-excavation was not undertaken to prevent an immediate
threat of property loss and was not the removal of work installed to prevent such
a threat; that work was an integral part of the work required by the terms of the Delta
and TRA contracts.130 The trial judge concluded that the amount of any claim
available to Delta under cl 5.03 would be the costs incurred before 24 July 2007,
which were claimed in an amount of $245,285.12.131 Taking into account a finding
that Mr Welsh “understood his role to put Delta’s best foot forward”,132 that
subsequent reviews of his log of costs reduced the amount claimed, some parts of the
attribution of costs were in some respect arbitrary, Mr Welsh was at a disadvantage
in recording work before he arrived on site in the last week of June 2007 and for the
period before he arrived he relied solely on documentary records, the trial judge
discounted the categories of claim for which the costs were incurred by Delta itself
rather than invoices received by Delta by 15 per cent, yielding total costs assessed by
the trial judge of $220,106.133
[95] Delta submitted that it was an insured covered by cl 5.03. The submission requires
reference to two provisions:
(a) In the schedule of cover the “insured” is described as follows:
“Team Post Tensioning Pty Ltd134
principals and subcontractors who are not
otherwise insured”
(b) A glossary of terms in the policy defines “you/your” as meaning “anyone
insured by the Policy”. That is followed by a provision applicable “For
Section Two only”, that ““you/your” also includes … (b) any principal
but only for the principal’s liability that arises out of the work performed
by you for that principal”. That is followed by a proviso which it is not
relevant for present purposes.
Is Delta an insured under the schedule of cover?
[96] The trial judge accepted that Delta was TRA’s “principal” within the description of
an insured in the schedule of cover135 and rejected Delta’s submission that s 45(1) of
the Insurance Contracts Act 1984 (Cth) would operate to render void the requirement
129 Reasons at [110].
130 Ibid.
131 Ibid.
132 Reasons at [114].
133 Ibid.
134 The trial proceeded upon the agreed basis that TRA was to be treated as though it were a named insured.
135 Reasons at [74].
-- 32 of 49 --
33
that a principal or subcontractor did not otherwise have insurance.136 In relation to
the phrase “who are not otherwise insured” the trial judge found that Delta had at least
two insurance policies relevant to the loss it suffered on the Albert Street project and
that Delta had failed to satisfy the onus, which the trial judge held lay upon Delta, of
proving it had no other insurance.137 None of those conclusions are challenged by
the notice of appeal.
[97] Ground 12 of the notice of appeal challenges the trial judge’s construction that the
phrase “who are not otherwise insured” applies both to principals who are not
otherwise insured and to subcontractors who are not otherwise insured. The trial
judge considered that there was no sensible reason why the phrase would only apply
to subcontractors and the application of the phrase to both principals and
subcontractors fulfilled a sensible purpose of extending cover to losses related to the
contractor’s work which otherwise were not covered by insurance.138
[98] Delta contends that the trial judge should have held that upon the proper construction
of the definition of “insured” in the policy, the phrase “not otherwise insured” related
only to subcontractors and not to principals. It argues that the description of the
insured in the schedule of cover is ambiguous because of the absence of punctuation
and the ambiguity should be construed contra proferentem against Mecon. In
addition, Delta cites Campbell v Director of Prosecutions for the Commonwealth of
Australia139 as support for the application of what was submitted to be an ordinary
rule of grammar that words of relation prima facie refer to their nearest antecedent (in
this case, “subcontractors”). Mecon submits that the trial judge’s construction is
correct for the reasons given by the trial judge and because Delta’s construction would
make the extended definition of “you/your” redundant in so far as it applies to
principals. Delta replies that little weight should be given to the redundancy because
it results from a contrast between a memorandum of insurance adapted for the
particular case and the standard form policy wording.
[99] The schedule of cover does not wear the appearance of a document that would be
expected to apply grammatical conventions of the kind identified by Delta. In
Campbell v Director of Prosecutions for the Commonwealth of Australia140 McDonald J
referred to in Re Godfrey,141 in which Poole J quoted a statement by Pollock CB in
Eastern Counties and London and Blackwall Railway Co v Marriage142 that “…the
antecedent really referred to is often to be made out by good sense of the hearer or
reader, rather than by the position of a word in the sentence” and “[the] judicial
exposition of any document ought to be the reasonable one, and not emphatically the
grammatical one.” McDonald J also referred to Lord Chelmsford’s statement in
Eastern Counties and London and Blackwall Railway Co143 that “[E]very relative
ought to be referred, not perhaps to the next antecedent, “which will make sense with
the context,” but to that to which the context appears properly to attract it.” In deciding
whether the words “who are not otherwise insured” properly refer to “principals and
sub-contractors” or only to “sub-contractors” it is necessary to bear in mind that the
136 Reasons at [76], citing Lambert Leasing Inc v QBE Insurance (Australia) Ltd [2016] NSWCA 254 and
referring to s 45(2) of that Act.
137 Reasons at [77]-[78].
138 Reasons at [75].
139 [1995] 2 VR 654.
140 [1995] 2 VR 654 at 665-666.
141 [1921] SASR 148 at 152.
142 (1860) 9 HLC 32 at 37.
143 (1860) 9 HLC 32 at 74.
-- 33 of 49 --
34
Mecon policy is a commercial contract and should be given a businesslike interpretation:
McCann v Switzerland Insurance Australia Ltd.144 Even allowing for a “liberal
approach” in favour of insureds in a case of ambiguity,145 Delta’s arguments do not suggest
any error in the commercial construction of the policy preferred by the trial judge,
a construction which derives additional support from Mecon’s argument from redundancy.
[100] In relation to the extended definition of “you/your” in the glossary of terms, the trial
judge found that Delta was a principal within the phrase “any principal” at the
beginning of (b).146 The trial judge therefore accepted that Delta was covered by that
extended definition of insured, “but only for the principal’s liability that arises out of
the work performed by you for that principal”.147 The trial judge concluded that the
cost of providing temporary protective repairs could not be characterised as Delta’s
liability so that the extended definition of “you/your” relevantly operated only in
relation to cl 5.00 and cl 5.01 and not cl 5.03.148
[101] That conclusion is challenged by ground 13 of the notice of appeal. It contends that
the trial judge failed to determine whether or not Delta was entitled to the costs of
temporary protective repairs pursuant to cl 5.03 of the Policy and, having regard to
the matters set out in the paragraphs [104]-[105] of the trial judges’ reasons (see [93]
of these reasons) ought to have held that Delta was entitled to the costs of temporary
protective repairs. The first contention is incorrect. The trial judge determined that
Delta was not entitled to the costs of temporary protective repairs pursuant to cl 5.03.
[102] As to the second contention, Delta argues that the trial judge adopted an unreasonable
construction of the policy, at odds with its purpose, in concluding that the costs
incurred by Delta for temporary protective works were not the “principal’s liability”
within the meaning of cl 5.03.149 It submits that it is commercially absurd to construe
the policy so that Delta should be covered under cl 5.01 but not under cl 5.03 in the
event that it acted reasonably and proactively incurred costs in preventing Property
Loss or Personal Injury. Delta relies upon the purposive approach adopted in
Guardian Assurance Co Ltd v Underwood Constructions Pty Ltd.150 Mecon submits
that the trial judge’s construction is correct, that cl 5.03 concerns costs incurred by
the named insured rather a liability, and in any event costs incurred by Delta cannot
be characterised as a liability.
[103] I would affirm the trial judge’s conclusion. Clause 5.03 provides an indemnity for
certain costs incurred by the insured to prevent “any” immediate threat of Property
Loss or Personal Injury. Upon one view that involves no reference to any legal
liability. The trial judge preferred a different construction; taking into account the
contextual influence of cl 5.00, the trial judge construed cl 5.03 as applying only
where an insured could subsequently become legally liable for the described costs.
On either construction cl 5.03 covers costs in respect of which the insured has no legal
liability when the costs are incurred and is never rendered legally liable for them. That
describes the position of Delta upon findings not challenged on appeal.151 Whichever
construction is preferred the language of the subordinate clause in (b) of the extended
144 (2000) 203 CLR 579 at [22].
145 Ibid, at 602, citing Johnston v American Home Assurance Co (1998) 192 CLR 266 at 274 [19].
146 Reasons at [81].
147 Ibid.
148 Reasons at [118].
149 Delta’s outline of submissions, para 57 and Delta’s outline of submissions in reply, para 34.
150 (1974) 48 ALJR 307.
151 Reasons at [90].
-- 34 of 49 --
35
definition is inapt to extend an indemnity under cl 5.03 to Delta as a principal. As
Mecon submitted, the costs it incurred could not be characterised as a liability.
[104] The insurance policy considered in Guardian Assurance Co Ltd v Underwood
Constructions Pty Ltd named the plaintiff as the insured. Its entitlement to an
indemnity was not governed by a provision similar to the extended definition in the
Mecon policy. Even if TRA, as a named insured, would be entitled to an indemnity
upon the reasoning in Guardian if it carried out the described work to avoid threatened
damage that would result in it incurring an insured liability, it does not follow that it
is uncommercial for the indemnity under the extension of the insurance to TRA’s
principal to be construed in accordance with the terms of that extension. The presence
of the subordinate clause in (b) in a definition which applies only for s 2 might itself
be thought to be antithetical to an assumption that its purpose is to extend to principals
the same breadth of coverage under s 2 of the policy as that section provides to the
named insured.
Notice of contention
[105] Against the possibility that Delta might establish one of its grounds of appeal Mecon
filed a notice contending that the trial judge should have made other findings that
support the rejection of each of Delta’s claims.
Delta’s claim as assignee under cl 5.00 of the policy
[106] In relation to Delta’s claim as assignee under cl 5.00 of the policy, Mecon advances
four contentions in relation to matters which the trial judge found it not necessary to
decide.
[107] First, Mecon contends that Delta failed to establish that any Property Loss happened
as a result of an “Occurrence”. The policy definitions of “Occurrence” and “Event”
are set out in paragraph [8] of these reasons. I earlier mentioned that Delta’s statement
of claim characterised the Wall Movement as both the Occurrence and the Property
Loss. It also characterised the Wall Movement as the “Event (as defined)”.152 In
Delta’s final submissions at the trial, however, it submitted that the word “event” in
the definition of “Occurrence” was not the “Event” defined in the policy.153 It
submitted that the Occurrence was TRA’s breach of the subcontract causing the Wall
Movement.154 Bearing in mind the requirement in cl 5.00 that the Property Loss be
caused by the Occurrence, the contention that the Wall Movement was caused by
TRA’s breach could not form part of an “Occurrence” as defined (see [8] of these reasons).
[108] Mecon contended that the Wall Movement could not be an Occurrence because the
evidence established that TRA’s employees could have expected it to happen. This
argument invoked the provision in the extended definition of “you/your” in the policy
that, “For Section Two only, “you/your” also includes … (a) any of your directors,
executive officers or Employees while acting within the scope of their duties in such
capacity”.
[109] As Delta submitted, however, another paragraph of the same definition provides:
“For Section Two, where “you” comprises more than one entity or
person, each of the entities or persons shall be considered as a separate
152 Third amended statement of claim para 77.
153 Plaintiff’s closing submissions para 41.
154 Plaintiff’s closing submissions para 39.
-- 35 of 49 --
36
and distinct insured and the word “you” shall be considered as applying to
each entity or person in the same manner as if a separate policy, with
the exception of any limit of indemnity, had been issued to each.”
[110] The definitions are in a glossary which contains definitions of terms that are used in
different parts of the policy. The extended definition of “you/your” applies only for
s 2. It does not allow the word “you” in the definition of “Occurrence” to be read as
encompassing, not only the named insured, but also the named insured’s employees.
There is also substance in Delta’s argument that Mecon’s construction would deprive
the policy of much of its utility as insurance against negligent breaches of contract.
Mecon’s contention should be rejected for those reasons. It is not necessary to
consider Delta’s additional arguments upon this issue.155
[111] Mecon’s second contention is that the settlement deed did not assign to Delta any
right of indemnity in favour of TRA to recover the Settlement Amount under the
policy. Mecon did not advance written or oral argument in support of this contention
and the appeal was argued upon the assumption that there was such an assignment.
[112] Mecon’s third contention is that it was not liable to indemnify TRA by reason of its
breach of or non-compliance with cl 10.08 of the policy. The policy relevantly
provides:
“10.00 Each condition reflects a reasonable requirement of you as a
condition or precedent to receiving Insurance under the Policy.
If you fail to observe these conditions, and such failure
increases Mecon’s exposure to a claim or directly or indirectly
exacerbates or causes loss, damage or legal liability, Mecon
may reduce, or avoid paying, any claim submitted by you.
…
10.08 Risk Management
Without exception, you and your Employees must:
…
(d) take all reasonable steps to prevent incurring any loss, damage
or liability.”
[113] Mecon argued that upon the proper construction of cl 10 Delta bore the onus of
establishing that it satisfied cl 10.08(d).
[114] In Wallaby Grip Ltd v QBE Insurance (Australia) Ltd156 the High Court referred with
approval to the statement by Jordan CJ (delivering the judgment of the court) in Kodak
(Australasia) Pty Ltd v Retail Traders Mutual Indemnity Insurance Association157 that
“the question of where the onus lies must in every case depend primarily upon the
nature of the condition and the provisions of the policy”. In Kodak, a policy regulating
employers’ rights of indemnity against workers’ claims conferred a right of indemnity
against the insurer for sums for which it shall be liable to pay compensation, subject
to the due and proper observance and fulfilment by the employer of various conditions
including a reasonable precautions clause. Chief Justice Jordan stated that the clause
was “expressed as a condition to which the existence of an obligation to indemnity is
155 Appellant’s outline of submissions in reply paras 46 – 49.
156 (2010) 240 CLR 444 at 457 [28].
157 (1942) SR (NSW) 231 at 237.
-- 36 of 49 --
37
made subject” and “must therefore be presumed to be intended to operate as
a condition unless it is incapable of so operating.”158 Because the condition was not
capable of operating as a condition precedent to the existence of the policy or as
a condition concurrent with the accrual of a liability to indemnify, it could operate as
a condition of the existence of liability only as a condition precedent to the liability
being accrued or as a condition subsequent which discharged an accrued liability.159
Chief Justice Jordan reasoned that because the reasonable precautions clause referred
to a want of care referrable to an act or omission by the insured antecedent to the
injury, it must be treated “as a condition to be fulfilled by the insured which is
precedent to the accrual of liability to indemnify on the part of the insurer”.160 Chief
Justice Jordan thereafter applied “the ordinary rule” that, “as to any provisions which
are merely conditions precedent to the accrual of liability of the insurer according to
the terms of the policy treated as a binding document … the insured must allege, and
if the matter is put in issue prove, the performance by him of all conditions precedent
… a plaintiff seeking to enforce an obligation qualified by a general exception which
is applicable to all cases must negative the exception; but if the obligation is general
and qualified only by particular exceptions, a person seeking to rely on an exception
must prove himself within it.”161 Accordingly, it was held in Kodak that, because the
reasonable precautions clause was a condition precedent, the plaintiff was obliged to
prove compliance with it.
[115] In Barrie Toepfer Earthmoving and Land Management Pty Ltd v CGU Insurance
Ltd162 Meagher JA (Ward JA and Sackville AJA agreeing) referred to Kodak and
Wallaby Grip in the course of holding that the insurers were obliged to allege and
prove a breach of a reasonable precautions clause and causation. In that case, the
general insuring clause provided that, “Subject to the terms conditions and exclusions
of this policy … We agree to provide indemnity …”. An introductory clause to conditions,
which included a reasonable precautions clause, provided that the insurer “may refuse
to pay a claim, or may reduce the amount payable under a claim to the extent that
Your breach of any condition of this policy causes or contributes to loss, damage or
liability or prejudices Our interest or rights, in respect of that claim.” Meagher JA
observed that the right to refuse to pay or to reduce a claim arose where there was
“loss, damage or liability” to which the policy would otherwise entitle the insured to
an indemnity.163 After referring to the statement by the High Court in Wallaby
Grip164 that the difference between an exception and a limitation as to the amount
payable under an indemnity was that “an exception may prevent an insurer’s liability
from arising, whereas a limitation … operates after the obligation to indemnify has
arisen and upon the amount payable pursuant to it” and that the “legal burden of proof
arises from the principle: [h]e who alleges must prove” so that the “incidence of the
legal burden of proof can therefore be tested by answering the question: [w]hat does
each party need to allege?”,165 Meagher JA observed that the insurer’s liability to
indemnify arose upon the insured’s claim that its liability to a third party was caused
by the use of its motor vehicle; it followed that, subject to the application of an
exclusion or a breach of a condition which was causative or all or part of that liability,
158 Ibid at 234-238.
159 Ibid at 235.
160 Ibid.
161 Ibid. Citations omitted.
162 [2016] NSWCA 67 at [37] – [50].
163 [2016] NSWCA 67 at [48].
164 (2010) 240 CLR 444 at 459 [35].
165 Ibid at [35] and [36] (quoting observations by Hobhouse J in The Torenia [1983] 2 Lloyd’s Rep 210).
-- 37 of 49 --
38
the insurer’s liability to indemnify arose. Meagher JA therefore concluded that to
justify a refusal to pay all or part of the claim by reference to the reasonable
precautions clause the insurers were obliged to allege and prove breach of the
condition and causation.166
[116] The first sentence of cl 10.00 of the Mecon policy, if considered alone, is similar to
the condition considered in Kodak, to which the existence of an obligation to
indemnify was made subject. The second sentence of cl 10.00, read in the context of
the general insuring provision in cl 5.00, is not materially distinguishable from the
provisions construed by Meagher JA in Barrie Toepfer Earthmoving and Land
Management. Reading cl 10.00 as a whole, and particularly having regard to the
directly operative provision that “Mecon may reduce, or avoid paying, any claims
submitted by you”, I construe cl 10.00 not as imposing a condition precedent to the
accrual of liability to indemnify or as a general exception to such a liability applicable
to all cases, but as a particular exception to Mecon’s liability to indemnify under the
general insuring clauses. It follows that the onus lay upon Mecon to plead and prove
the breach of the reasonable precautions clause upon which Mecon relied to deny an
indemnity. That conclusion accords with many decisions which, so far as the reasons
reveal, concerned reasonable precautions clauses that were not expressed as
conditions to which the obligation to indemnify was made subject.167
[117] Upon the question whether Mecon had proved a breach of the reasonable precautions
clause, Mecon relied upon its written submissions at the trial. Mecon contended at
trial, and again on appeal, both that TRA by its directors and TRA’s “Employees”
(a reference to the employees on site) did not comply with cl 10.08(d). It also
submitted that, because of the impact of oral evidence in relation to this issue, if the
Court upheld Delta’s grounds of appeal and rejected Mecon’s other grounds in the
notice of contention the court might find it necessary to remit the matter to the trial
judge to make findings and give a consequential judgment. Delta argued that no
remitter was required because, taking into account Mecon’s failure to put necessary
propositions to the witnesses called by Delta, Mecon had not established an arguable
case for the application of the reasonable precautions clause.
[118] As to the employees, Delta argues that the expression “you” in cl 10.00 does not
comprehend employees. The definition for s 2 of “you/your”, which includes “(a)
any of your directors, executive officers or Employees while acting within the scope
of their duties in such capacity”, is submitted to be “self-defeating” for the purposes
of Mecon’s argument. It is submitted that cl 10.00 should be understood in the
context of a commercial purpose that the insured not lose cover because of unknown
and unauthorised conduct by its employees. Delta argues that the clause is at least
ambiguous and should be construed contra proferentum.
[119] It is not necessary for Mecon’s purposes that the word “you” in cl 10.00 should be
construed as comprehending Delta’s employees. Clause 10.08 unambiguously obliged
both TRA and its employees to comply with the obligations described in the sub-
paragraphs. If the employees did not comply and the non-compliance increased Mecon’s
exposure to a claim or directly or indirectly exacerbated or caused loss damage or
legal liability, cl 10.00 entitled Mecon to reduce or avoid paying any claim by TRA.
166 [2016] NSWCA 67 at [50].
167 See, for example, Legal and General Assurance Society Ltd v Commonwealth and Precision Cranes
and Hoists Pty Ltd [1985] 3 ANZ Ins Cas 60 – 621 and Bedford v James [1986] 2 Qd R 300 at 308.
-- 38 of 49 --
39
[120] Delta argued168 that Mecon did not comply with its obligations169 to plead as against
the employees the subjective knowledge necessary to establish the defence in cl 10.08.
[121] To establish a breach of cl 10.08(d) Mecon was obliged to prove that TRA (or its
employee) deliberately did or omitted to do an act knowing that it exposed TRA to
a risk of incurring loss, damage or liability by a resulting danger that was recognised
by the person (TRA or the employee) who knowingly did or omitted to do the act,
such that the conduct of TRA (or its employee) should be characterised as reckless.170
[122] In this respect, Mecon pleaded:171
(a) The risk of a lateral wall movement and consequential damage to
property at the Site and at its surrounds if the ground anchors were not
installed in accordance with the design requirements, including anchor
length and load capacity (“the Risk”) was “an obvious risk to any person
experienced in drilling and installing temporary or permanent rock
anchors”.
(b) TRA caused to be installed ground anchors at the Site during the relevant
period.
(c) Numerous of the original anchors were shorter (many substantially
shorter) than their design length and did not perform as designed.
(d) For a period of time there was made available to TRA’s drilling team on
Site only 14 metres of rod for drilling holes for the original anchors, that
limited the drilling depth to approximately 13 metres notwithstanding
that the design length was 18 metres and greater.
(e) One of the drilling supervisors, Mr Mogg, informed TRA by Mr Sanford
that only 14 metres of rod were on the Site at the relevant time and the
workmen could only drill to about 13 metres, and TRA by Mr Sanford
was also informed by Mr Mogg that about 10 holes were short and
anchors had been installed.
(f) TRA took no action in relation to either of those matters.
(g) The employees knew that the original anchors which were shorter than
the design length were in fact shorter than their design length. Particulars
of that alleged knowledge were given, including that the installed length
was a matter of observable fact to the installer of the anchors, the design
provided for the length of the cable to be installed, and the installer’s job
was to cut the coil of cable to the design length.
(h) Quality Assurance records were not compiled by TRA or its employees
in relation to the installation of the anchors in the initial construction
period and were first prepared in about April 2007 after movement of the
168 Plaintiff’s closing submissions paras 100 – 101.
169 Uniform Civil Procedure Rules 1999 (Qld), r 150(1)(k).
170 Fraser v BN Furnman Productions (Ltd) [1967] 3 All ER 57 at 60 – 61; the act or omission “must be
at least reckless, that is to say, made with actual recognition by the insured … that a danger exists, and
not caring whether or not it is averted”; Albion Insurance Co Pty Ltd v Body Corporate Strata Plan
No 430 [1983] 2 VR 339 at 342 – 3; Gold Coast Bakeries (Queensland) Pty Ltd v Heat & Control Pty
Ltd [1992] 1 Qd R 162 at 172 (approving Fraser v BN Furnman and referring to the need for the insurer
to prove that the insured was “negligent towards the insurer by courting the risk”).
171 Further amended defence paras 124 – 145, 158 – 159.
-- 39 of 49 --
40
SW1 wall at the Site had been reported and numerous of those records
did not record actual details but were reconstructed having regard to the plans.
(i) By reason of the pleaded matters, TRA and the Employees failed to take
all reasonable steps to prevent the incurring of the loss, damage and
liability alleged by Delta and failed to comply with or satisfy cl 10.08(d).
[123] Mecon did not prove (e). For present purposes the significant allegations are summarised
in (a), (c), (g) and (i). Although (a) does not use the word “knew”, in context it
conveys a case that TRA’s employees knew of the risk of the alleged wall movement
and consequential damage. Mecon sufficiently pleaded its argued case that the
employees failed to comply with cl 10.08(d) because they knowingly installed
numerous rock anchors which were shorter (many substantially shorter) than the
design length, in circumstances in which they knew of the resulting risk of lateral wall
movement and consequential damage from the installation of ground anchors not
being installed in accordance with the design requirement for anchor length.
[124] Mecon proved that case. As Delta submitted in a different context (concerning the
alleged breach of a clause by the conduct of TRA’s directors, Mr Jones and
Mr Sanford) there was unchallenged evidence that TRA’s employees on the site,
including Mr Mogg, were experienced in installing rock anchors.172 Mr Ervin gave
evidence173 that it was “almost inconceivable that the workers installing the anchors
would not have known of the shorter than design length anchors … or realised that it
was probable such anchors would not be able to perform their design function”, and
that TRA’s installation of the anchors was “extremely poor practice … which might
have endangered the lives of workers within the excavation and in adjacent
properties”. At the trial Delta argued that this was speculation which had no factual
basis in the evidence. However the trial judge accepted evidence of the remarkably
extensive and gross character of TRA’s breaches of contract; “[I]n the top two rows
of anchors on SW1, 18 failed when tested, including nine of which anchors were part
of the initial remedial works … all but four of the 85 anchors removed from SW1
were less than their design lengths and in many instances were significantly shorter:
67 of the 85 anchors were less than 75% of their design length and some anchors were
as little as 30-40% of their design length”.174
[125] Delta argued that the subjective knowledge of a worker at the base of an excavation
at a particular time was not an area of specialised knowledge. It was not suggested
to Mr Ervin, however, that his expertise did not extend to knowledge of the
competencies of employees, such as Mr Mogg, who were responsible for supervising
the installation of rock anchors. But even if Mr Ervin’s opinion is put to one side, the
findings about the extent and character of the breaches of the subcontract readily
justify an inference that the experienced employees responsible for the installation of
the rock anchors, particularly Mr Mogg, must have appreciated that the very extensive
departure from the design of the rock anchors resulted in risk that they would not
perform their design function of restraining the retaining walls against the loads
placed upon them by the retained soil.
172 Mr Jones at T7-26, Mr Sanford at T7-28 to T7-29, T7-38 to T7-39 (in which Mr Sanford made it clear
that Mr Mogg must have known that the anchors the installation of which he supervised were “short
anchors”, including “6-metre anchors out of a so called 20-metre anchor hole”.
173 Reasons at [18].
174 Reasons at [16].
-- 40 of 49 --
41
[126] Delta argued that the subjective knowledge of the employees required to establish that
they recklessly courted the risk could not be determined on the basis of inferences. The
seriousness of such a finding does require a court to be satisfied that it is clearly
proved, and it is not sufficient to produce “inexact proofs in definite testimony, or
indirect inferences”.175 That does not exclude a strong circumstantial case. There is
no evidence to rebut the inference I have described, which directly arises from the
trial judge’s findings and uncontentious evidence.
[127] Delta argues that Mecon did not sufficiently plead or prove that the alleged breach of
cl 10.08(d) increased Mecon’s exposure to a claim or directly or indirectly exacerbated or
caused loss, damage or legal liability, as required by cl 10.00. It was not in issue that
TRA’s breaches of the subcontract caused the SW1 wall to undergo significant lateral
movement and consequential damage to the Site and surrounds. It was Delta’s own
case that this was Property Loss for which TRA became legally liable to compensate
Delta, in respect of which Mecon was required to indemnify TRA under cl 5.00.
Acceptance of Mecon’s case that TRA’s employee courted the risk of that same
Property Loss therefore establishes that the breach of cl 10.08(d) exposed Mecon to
TRA’s claim under the policy.
[128] For these reasons I would hold that Mecon established an entitlement to avoid paying
TRA’s claim.
[129] In relation to TRA’s directors, Mecon pleaded (in addition to the matters in [122] of
these reasons) that:176
(a) Each of Mr Sanford and Mr Jones was aware of the Risk.
(b) Mr Sanford and Mr Jones did not supervise the drilling and installation
of the anchors or engage a qualified engineer to supervise the installation
and tensioning of the anchors or verify the anchor load capacities, and
TRA knew that Delta had not engaged a qualified engineer for those
purposes.
(c) TRA did not perform a lift-off test of the anchors after seven days as
required by the engineering drawings.
[130] In cross-examination Mr Jones accepted a series of propositions. He was a qualified
engineer. It was obvious to him that a consequence of incorrect installation of ground
anchors would be the lateral movement of the wall. There was a clear risk that the
lateral movement of the wall would damage surrounding sites, property and people.
It was important to take precautions against such an obvious risk. One such
precaution was paying attention to the design engineers. TRA’s primary function was
to install the rock anchors, the purpose of which, was noted on the design engineer’s
drawings, as being to hold up the retaining wall. TRA’s function included providing
the shop drawings to achieve the design engineer’s design. It was part of TRA’s role
to have a system that adequately supervised the installation, to keep adequate records,
to have adequate equipment and to have adequate supervision. Adequate equipment
was necessary to test the functionality of the ground anchors when installed and
a monojack was not adequate for that purpose. A system which did not preserve the
records of actual drilling was inadequate. A system under which Mr Jones signed the
quality assurance records on a single day, 9 April 2007, in the face of a demand and
175 Briginshaw v Briginshaw (1938) 60 CLR 336 at 361 – 362.
176 Further amended defence paras 124 – 145, 158 – 159.
-- 41 of 49 --
42
without referring to relevant documents was insufficient. That potentially fell far
short of what might be expected of a prudent rock anchor specialist to perform.
[131] Contrary to the submission for Mecon, that evidence did not prove that TRA
contravened cl 10.08(d). The admissions of negligence by Mr Jones were not accompanied
by any admission that he knew of the conduct of TRA’s employees amounting to
serious and extensive breaches of the subcontract. Mecon did not submit that the
evidence at the trial proved the pleaded allegations that Mr Mogg informed
Mr Sanford of the alleged facts that the drilling rods on site at the relevant times were
too short, that workmen could only drill to about 13 metres, and that anchors had been
installed in about 10 holes that were too short. Mecon otherwise did not plead that
Mr Sanford or Mr Jones knew of any of the breaches of the subcontract which TRA
had committed by its on-site employees. Mecon argued that there was a question not
determined by the trial judge whether Mr Jones signed the records knowing that they
were false, but no such contention was pleaded or put to him. Mecon also referred to
its pleaded allegation that the equipment on site was inapt to permit the installation
of the required lengths of rock anchors, but Mecon did not adduce evidence which
proves that allegation or that either of TRA’s directors knew it to be so.
[132] In short, the directors lacked the knowledge of the breaches of the subcontract which
was a critical element of proof that they deliberately adopted a course of action or
inaction whilst realising the risks of lateral wall movement and consequential damage
resulting from such breaches. Mecon’s claim that TRA, by its directors, breached
cl 10.08(d) could not succeed for that reason.
[133] Mecon’s fourth contention in relation to Delta’s claim as assignee is that Mecon is
not liable to indemnify TRA because of the operation of cl 8.13 of the policy. In s 2
of the policy, cl 8 provides (under the heading “Section Two Exclusions”) that:
“8.00 The Policy does not insure any legal liability for:
…
8.13 Specific Types of Project
Personal Injury or Property Loss directly or indirectly resulting
from:
(a) excavations deeper than 10 metres;
…
unless specified to the contrary in the Schedule and then solely
to the extent specified.
(Note: The Proposal Form contains questions relating to the
foregoing types of project and/or risk.)”
[134] Mecon argued that, having regard to the context supplied by cl 5.00, the expression
“legal liability” in cl 8.00 should be construed as a reference to “all amounts which
you become legally liable to pay in compensation of … Property Loss”. Mecon argued
that, because the work at the Site required an excavation deeper than 10 metres, the
insurance in cl 5.00 did not comprehend TRA’s liability to Delta which was the
subject of Delta’s claim as assignee. Mecon argued that cl 8.13 was concerned with
the nature of the project or work undertaken by the insured in respect of which the
relevant Property Loss directly or indirectly results, rather than a stage which the work
had reached. Mecon submitted that this construction was suggested by the “Note”,
which indicated that the scope of indemnity did not apply where an insured undertook
-- 42 of 49 --
43
a project or work of the kind described in cl 8.13 and the content of the items set out
in subclauses (a) to (k) of that clause, and in particular:
“(f) jetty, pier, wharf, marina or breakwater construction or work in,
on or over a permanent body of water;
(g) demolition over 10 metres in height, other than internal non-
structural demolition;
…
(i) work in or around an airport or aircraft landing area;”
It is submitted that the obvious intent of the clause was to exclude the insurer’s
liability where any claimed Property Loss occurred in the undertaking of the
particular work or identified project.
[135] Delta’s argument is to the effect that there must be a causal relationship between the
depth of the excavation and the Property Loss.
[136] There is no ambiguity in the requirement in cl 8.13(a) that the Property Loss directly
or indirectly result from excavation deeper than 10 metres. There is no requirement
that the Property Loss be directly or indirectly caused by the depth of the excavation
exceeding 10 metres. The described relationship is instead between an excavation of
the specified depth and the Property Loss; the policy does not insure any legal liability
for Property Loss directly or indirectly resulting from an excavation deeper than 10 metres.
[137] Mecon argued that it had established the necessary causal link between an excavation
deeper than 10 metres and the claimed Property Loss: the failure of the SW1 retaining
wall to limit deflections of adjoining land – the argued loss of functionality of that
wall – continued after that wall exceeded the 10 metre depth and all of the directions
to rectify, and the costs claimed for rectifications, occurred after that time.
[138] Delta argued that those facts did not detract from a conclusion that the failure of SW1
occurred before the excavation reached a depth of 10 metres. Delta relied upon
Dr Baigent’s evidence that his review of Mr Ervin’s further supplementary report
resulted in an opinion that “the depth of excavation, and whether or not it exceeded
10m in depth, did not have any effect on the integrity and stability of the SW1
wall.”177 Delta also relied upon statements by Mr Ervin that the wall was being
compromised at times before early March 2007, it was failing by 1 March 2007 when
the depth was in the region of 4.7-7.9 metres, and there was what Delta characterised
as “clear evidence that the retaining wall was damaged before the excavation reached
10 metres and that the depth of excavation had no direct or indirect cause on the fact
that the Property Loss occurred”; Delta quoted Mr Ervin’s evidence that because the
retaining wall “has moved more than you would’ve expected at this point in time, the
wall is behaving in an unexpected manner” and that upon a model of the progressive
excavation “you would not expect, by a depth of 8 metres or 7 metres or whatever it
was at that point in time, to be indicating displacements of this order.”178
[139] As I have mentioned, the trial judge preferred Mr Ervin’s evidence to the evidence of
Dr Baigent. The quoted part of Mr Ervin’s evidence was to the effect that the movement
of the wall at depths before 10 metres was unexpected and a cause for serious concern
in an excavation the depth of which was to exceed 18 metres. However Mr Ervin did
not express any conclusion to the effect that the increasing depth of the excavation to
177 Plaintiff’s closing submissions para 111.
178 Plaintiff’s closing submissions para 113.
-- 43 of 49 --
44
and beyond 10 metres was not causally related to the threat to the excavation posed
by the deficiencies in TRA’s rock anchors.
[140] The proximate cause of the alleged Property Loss was TRA’s breach of contract in
installing rock anchors that did not comply with the subcontract, but it is obvious
enough (and it was confirmed by the engineers’ evidence179) that the excavation was
an indirect cause of that Property Loss. If the SW1 wall moved laterally before the
depth of the excavation reached 10 metres it may be concluded that Property Loss
then indirectly resulted from an excavation that was not 10 metres deep. But that
does not deny that once the excavation reached that depth TRA’s legal liability was
to pay compensation “of” the alleged Property Loss that indirectly resulted from
excavation deeper than 10 metres. Delta’s argument to the contrary is simply another
way of putting the argument, which I do not accept, that the clause requires a causal
relation between the Property Loss and the depth of the excavation.
[141] In any event, uncontentious evidence demonstrates that the Property Loss in relation
to which TRA became legally liable to Delta was incurred after the excavation
exceeded 10 metres. The depth of the excavation at SW1 exceeded 10 metres no later
than 27 March 2007.180 The earliest date of rectification work claimed by Delta was
11 April 2007. The earliest direction by the superintendent for Delta to carry out
work was made on 3 May 2007. It follows that the excavation deeper than 10 metres
indirectly resulted in the relevant Property Loss. That conclusion is not falsified by
the circumstance that some Property Loss of similar character might have occurred
before the excavation reached a depth of 10 metres.
[142] Delta relies upon a defence under s 54 of the Insurance Contracts Act 1984 (Cth).
Section 54 provides:
“54 Insurer may not refuse to pay claims in certain circumstances
(1) Subject to this section, where the effect of a contract of
insurance would, but for this section, be that the insurer may
refuse to pay a claim, either in whole or in part, by reason of
some act of the insured or of some other person, being an act
that occurred after the contract was entered into but not being
an act in respect of which subsection (2) applies, the insurer may
not refuse to pay the claim by reason only of that act but the
insurer’s liability in respect of the claim is reduced by the
amount that fairly represents the extent to which the insurer’s
interests were prejudiced as a result of that act.
(2) Subject to the succeeding provisions of this section, where the
act could reasonably be regarded as being capable of causing or
contributing to a loss in respect of which insurance cover is
provided by the contract, the insurer may refuse to pay the claim.
(3) Where the insured proves that no part of the loss that gave rise
to the claim was caused by the act, the insurer may not refuse to
pay the claim by reason only of the act.
(4) Where the insured proves that some part of the loss that gave
rise to the claim was not caused by the act, the insurer may not
179 For example, in Mr Ervin’s supplementary Report paras 6.0 – 6.9.
180 Second report of Mr Ervin para 5.3. AB1910.5.
-- 44 of 49 --
45
refuse to pay the claim, so far as it concerns that part of the loss,
by reason only of the act.
(5) Where:
(a) the act was necessary to protect the safety of a person or
to preserve property; or
(b) it was not reasonably possible for the insured or other
person not to do the act;
the insurer may not refuse to pay the claim by reason only of the act.
(6) A reference in this section to an act includes a reference to:
(a) an omission; and
(b) an act or omission that has the effect of altering the state
or condition of the subject-matter of the contract or of
allowing the state or condition of that subject-matter to alter.”
[143] For the proposition that s 54(1) was engaged in this case Delta relied upon Maxwell
v Highway Hauliers Pty Ltd.181 In that case, a provision in the policy that no
indemnity was provided for vehicle accidents unless the vehicle was being operated
by a driver who had a prescribed profile score in a psychology test approved by the
insurers. The High Court concluded that the fact that relevant vehicles were operated
at the time of accident by an untested driver was “by reason of some act … that
occurred after the contract was entered into” within s 54(1), being an omission of the
insured to ensure that each vehicle was operated by a driver who had undertaken the
prescribed test. In this case, the equivalent act occurring after the policy was entered
into was the creation of an excavation deeper than 10 metres.
[144] It is therefore necessary to address the question whether that act was one in respect of
which s 54(2) applied. That was not an issue in Maxwell v Highway Hauliers Pty Ltd. For
the reasons in [139] – [141], the excavation to beyond 10 metres depth “could
reasonably be regarded as being capable of causing or contributing to a loss in respect
of which insurance cover is provided by the contract”. Section 52(2) therefore
permitted the insurer to refuse the claim. Delta did not plead the elements of s 54(3)
or s 54(4) and it did not contend that it had satisfied its onus of proving those elements.
Delta’s claim as insured under cl 5.03
[145] In relation to Delta’s claim as insured under cl 5.03, Mecon advanced five contentions.
[146] First, Mecon contended that Delta’s claim under cl 5.03 was time barred under
s 10(1)(a) of the Limitation of Actions Act 1974 (Qld). Under s 10(1)(a) an action
founded on a simple contract (which includes the Mecon policy) should not be
brought after the expiration of six years from the date on which the cause of action
arose. It is not an issue that all of the costs claimed by Delta under cl 5.03 were
incurred more than six years before the commencement of the proceeding. The issue
is whether the cause of action arose when Delta incurred those costs or at the later
time (within the six year period) when Mecon refused to indemnify Delta.
181 (2014) 252 CLR 590.
-- 45 of 49 --
46
[147] The trial judge referred to a difference amongst the authorities as to whether a cause
of action against an insurer arose when loss within the policy was suffered (Callaghan
v Dominion Insurance Co Ltd,182 Cigna Insurance Asia Pacific Ltd v Packer,183 and
Commonwealth v Vero Insurance Ltd184) or whether a refusal by the insurer to
indemnify is a prerequisite to the accrual of a cause of action (Hunter v Stronghold
Insurance (Australia) Ltd185and Penrith City Council v Government Insurance Office
of New South Wales186). The trial judge referred also to observations of Professor
Carter in Indemnities against Breach of Contract187 which supported the first view:
“… the promise of the insurer is to indemnify against loss … it is, therefore, the
suffering of a loss which puts the insurer in breach of contract”. The trial judge
considered that reasoning was contrary to accepted principles of contract law; the
insured was entitled to an indemnity when loss was suffered, but the insurer was not
in breach at that time.188 Delta relied upon the trial judge’s reasoning. Mecon
submitted that the authorities compelled the contrary conclusion.
[148] In my respectful opinion, Professor Carter’s analysis is persuasive. Mecon’s
obligation under the relevant part of cl 5 was to pay costs incurred by Delta for the
repairs described in cl 5.03. Delta did not plead or submit that any other provision of
the policy, express or implied, qualified or imposed any condition upon that
obligation to indemnify Delta. It follows that Mecon’s obligation to pay Delta the
costs described in cl 5.03 arose at the time when Delta incurred those costs, so that
Delta’s cause of action arose at that time. It is not necessary to elaborate upon that
brief analysis: reasoning and conclusions to much the same effect were reached in
materially indistinguishable circumstances in two decisions of intermediate appellant
courts, Cigna Insurance Asia Pacific Ltd v Packer189 and Associated Forest Holdings
Pty Ltd v Gordian Runoff Ltd.190 Delta did not argue that those decisions were plainly
wrong or identify any basis for such an argument. That being so, it is sufficient that
I express my conclusion that I am not persuaded that either decision is plainly wrong.
[149] I note also that since the appeal was argued the New South Wales Court of Appeal,
by majority, has followed Cigna and Associated Forest Holdings in relation to
a policy provision which is also materially indistinguishable from the present case:
Globe Church Incorporated v Allianz Australia Insurance Ltd.191 The policy in issue
in that case included an obligation by the insurer, in circumstances giving rise to an
indemnity under the main cover, to pay certain additional costs including (in cl 3.1.3)
costs necessarily and reasonably incurred in respect of the temporary protection and
safety of Property insured pending repair or replacement.192 The question of principle
as to the accrual of a cause of action proved to be determinative for the majority’s
conclusion that those costs fell outside the limitation period.193
[150] I would uphold Mecon’s contention that Delta’s claim under cl 5.03 was time barred.
182 [1997] 2 Lloyd’s Rep 541 and the cases there cited.
183 (2000) 23 WAR 159.
184 (2012) 291 ALR 563 (obiter).
185 [1995] VicSC 5.
186 (1991) 24 NSWLR 564 (Giles J).
187 Paper presented at the 25th Annual Banking and Financial Services Law and Practice Conference, p 435.
188 Reasons at [107] – [108].
189 (2000) 23 WAR 159.
190 [2015] TASFC 6.
191 [2019] NSWCA 27 (Bathurst CJ, Beazley P and Ward JA; Meagher and Leeming JJA, dissenting).
192 Ibid at [38].
193 See [2019] NSWCA 27 at [120], [122] – [125].
-- 46 of 49 --
47
[151] Mecon’s second contention in relation to Delta’s claim as insured under cl 5.03 is that
Mecon was not liable to indemnify Delta because of the operation of cl 8.13 of the
policy. Clause 8.13 must be read together with cl 8.00 (see [133] of these reasons).
I have concluded that cl 8.13(a) is engaged, but Delta’s claim under cl 5.03 is not
a claim for insurance against “any legal liability for … Property Loss”. If, however,
the indemnity in cl 5.03 is promised only where an insured could subsequently
become entitled to an indemnity under cl 5.00 against a legal liability for the described
costs (see [103] of these reasons), then the effect of cl 8.00 and cl 8.13 would be that
Delta could not make a claim under cl 5.03. I am inclined to prefer the alternative
view that, the policy being ambiguous in this respect, the indemnity under cl 5.03
does not depend upon proof of that additional element. In circumstances in which it
is not strictly necessary to decide this point and the parties did not make submissions
about the proper construction of cl 8.00 and cl 8.13 in this respect, I refrain from
expressing any conclusion about the issue.
[152] Mecon’s third contention under the present heading is that Delta was compensated
for the claimed costs by its receipt of $2,309,142.32 from its insurer, HSB
Engineering Insurance Ltd in respect of costs subsequently claimed by Delta in the
proceeding. In this respect, the trial judge concluded that Delta had been paid for the
claim under cl 5.03 that it now made against Mecon; the trial judge added that Delta
was paid “at least $709,143 and quite possibly $2,309,142.32 in relation to its costs
of work protecting SW1 (and perhaps the site generally) incurred before 5 August
2007.”194
[153] Delta accepted that it could not now recover the sum of $709,143 from Mecon
because that was specifically addressed to part of the costs of the temporary protective
works, but it argued that there was no basis for a finding that the further payment
from HSB was attributable to that cost as distinct from other losses sustained by Delta
as recorded in the log of costs.195 Mecon replied that Delta’s submissions were based
on the incorrect premise that Mecon had the burden of establishing both that Delta
received further insurance monies and that they were attributable to what Delta
claimed as temporary protective repairs. In Mecon’s submission, Delta had the onus
of proving its loss, which included proof that the monies it received from HSB were
not attributable to temporary protective repairs. Mecon also argues, in the alternative,
that the balance of any proven amount of temporary protective repairs over and above
the specified sum of $709,143.32 (the balance being claimed by Delta to be
$768,551.00) should be reduced by about 46.5 per cent (being the proportion that the
sum of $1.6 million bears to the total sum claimed against HSB of $4,146,969.75 less
the first payment by HSB to Delta of $709,143.32.) Delta made submissions in
reply196 but it did not contradict Mecon’s submissions.
[154] It is not necessary to consider those arguments. Delta’s concession that it cannot
claim again the $709,143 it received from HSB has the consequence that, if Mecon is
liable to Delta for the claim under cl 5.03, Delta is not entitled to recover anything for
that claim in light of the trial judge’s finding that the quantum of any claim Delta
might have under cl 5.03 is $220,106.197 As noted earlier, no ground of appeal
challenges that finding.
194 Reasons at [119].
195 Appellant’s outline of submissions para 61.
196 Appellant’s outline of submissions in reply paras 83 – 84.
197 Reasons at [114].
-- 47 of 49 --
48
[155] Mecon’s fourth contention is that any claimed costs incurred after 31 October 2007
were not recoverable because they were incurred outside the period of insurance. In
Mecon’s written submissions in support of this contention, it extended the relevant
date; it submitted that Delta had no entitlement to recover costs after 3 November
2007.198 Delta did not contest the submission that the period of insurance expired at
that time. The issue is whether, as Mecon submits, Delta had no entitlement to
recover costs incurred after that date. Delta argued that under cl 5.03 it is the
immediate threat of Property Loss rather than the “costs incurred” that must occur
during the period of insurance. It submitted that Mecon’s construction was commercially
absurd because it would mean that the more significant was an event of Property Loss
the less likely it was that the insured would be indemnified for all of the costs of
preventing the threat. Delta’s argument has the effect of treating the insurance in
cl 5.03 as an insurance against a liability which has arisen within the period of
insurance albeit that the liability is met after the period of insurance. The fact that
Mecon’s obligations under that clause is to pay costs incurred, not to meet a liability,
favours Mecon’s construction. However I refrain from deciding this point because it
is not strictly necessary to do so and the parties’ arguments about it were not
developed in any detail.
[156] Mecon’s final contention is that any costs claimed in respect of Delta’s employees
and its machinery were not recoverable because such costs would have been incurred
in any event and were not “costs incurred by” Delta pursuant to cl 5.03. The effect
of Mecon’s argument is that Delta did not prove that it incurred the claimed costs
because of its failure to prove that the employees and machinery could have been
engaged in remunerative work were they not required to be engaged in the rectification
work.
[157] However, the effect of the trial judge’s findings199 is that $220,106 was the amount
of “the actual cost to Delta of these works”. Mecon did not identify a basis for setting
aside that finding of fact and it did not contradict Delta’s contention that Mecon did
not plead that “internal costs” expended on the temporary protective works were not
recoverable under cl 5.03. This contention should not be accepted.
Proposed order
[158] The appeal should be dismissed with costs.
[159] McMURDO JA: I agree with Fraser JA that the appeal should be dismissed with
costs and, subject to one question, I agree with his reasons.
[160] That question arose under Delta’s alternative claim for payment as an insured, rather
than as an assignee of the insured. The trial judge said that there were two
independent reasons for rejecting a claim on this basis. The first was that Delta was
a principal who was “otherwise insured”, so that it was not an “insured” as that term
was defined for the policy in the schedule of cover. I agree with the trial judge and
Fraser JA that the words “who are not otherwise insured” applied to both
subcontractors and principals of TRA. For that reason, the trial judge was correct in
dismissing the alternative claim.
[161] The second reason came from the definition of “you/your” in a glossary of terms in
the policy. The term was there defined to mean “anyone insured by the Policy” with
198 Respondent’s outline of submissions of support of notice of contention para 44 (last sentence).
199 Reasons at [114].
-- 48 of 49 --
49
the further definition that “you/your” also included “… (b) any principal but only for
the principal’s liability that arises out of the work performed by you for that principal”.
[162] I agree, as the primary judge said,200 that having regard to the location of cl 5.03
within the policy, the clause related only to costs incurred to prevent or minimise
Property Loss for which Delta could have become legally liable. However, in the
context of cl 5.03, I would interpret “the principal’s liability” in paragraph (b) of the
definition of “you/your”, as a reference to the principal’s potential liability, the
prevention or minimisation of which was the purpose of temporary protective repairs
undertaken by the principal. In that way I respectfully disagree with the trial judge201
and with Fraser JA.202
[163] FLANAGAN J: I agree with the orders proposed by Fraser JA and with his Honour’s
reasons.
200 Reasons at [105].
201 Reasons at [118].
202 At [103] above.
-- 49 of 49 --