Bulkbuild Pty Ltd v Fortuna Well Pty Ltd & Ors [2019] QSC 173 [2019] 30 QLR
SUPREME COURT OF QUEENSLAND
CITATION: Bulkbuild Pty Ltd v Fortuna Well Pty Ltd & Ors [2019] QSC
173
PARTIES: BULKBUILD PTY LTD ACN 136 952 102
(plaintiff)
v
FORTUNA WELL PTY LTD ACN 169 357 233 AS
TRUSTEE OF THE FORTUNA WELL FAMILY
TRUST UNDER INSTRUMENT 715956160
(first defendant)
ANTHONY MARK FENDT
(second defendant)
PROJECT & RETAIL MANAGEMENT PTY LTD ACN
010 935 645
(third defendant)
FILE NO/S: BS No 5640 of 2019
DIVISION: Trial Division
PROCEEDING: Application
DELIVERED ON: 16 July 2019
DELIVERED AT: Brisbane
HEARING DATE: 26 June 2019
JUDGE: Bowskill J
ORDER: There will be an order that the proceeding against the
first defendant is stayed, and the matter is referred to
arbitration pursuant to s 8 of the Commercial Arbitration
Act 2013 (Qld).
I will give the parties the opportunity to consider these
reasons, and make further submissions if they wish to, in
relation to the second and third defendants’ stay
application and the court’s power to make directions. I
will also hear the parties in relation to costs.
CATCHWORDS: ARBITRATION – THE ARBITRATION AGREEMENT
AND REFERENCE – ARBITRATION AGREEMENT AS A
DEFENCE AND AS A GROUND FOR STAY OF
PROCEEDINGS – STAY OF PROCEEDINGS – POWER OF
COURT TO STAY – GENERALLY – where the plaintiff
contractor claims that the first defendant principal breached the
design and construction contract between them by failing to
-- 1 of 12 --
2
pay for the work performed – where the contract included a
dispute resolution clause that constituted an arbitration
agreement under s 7 of the Commercial Arbitration Act 2013
(Qld) – where the first defendant applies for an order that the
proceeding be stayed until the dispute resolution clause is
complied with – where the plaintiff claims that the arbitration
agreement is “incapable of being performed” – whether the
court must refer the parties to arbitration, and therefore
necessarily grant the stay, under s 8 of the Commercial
Arbitration Act 2013
ARBITRATION – THE ARBITRATION AGREEMENT
AND REFERENCE – HOW MATTERS MAY BE
REFERRED – GENERALLY – where the second and third
defendants were the superintendent at varying times under the
contract between the plaintiff and first defendant – where the
second and third defendants also apply for a stay of the
proceedings against them – whether the second and third
defendants are each a “party” to the arbitration agreement
under the Commercial Arbitration Act – whether the second
and third defendants are claiming (or defending) “through or
under” the first defendant – alternatively, whether the court has
discretionary power to grant the stay, and should exercise this
discretion
Commercial Arbitration Act 2013 (Qld) ss 5, 6, 7, 8, 24B
Broken Hill City Council v Unique Urban Built Pty Ltd
[2018] NSWSC 825
Casaceli v Natuzzi SpA (2012) 292 ALR 143
CPB Contractors Pty Ltd v Celsus Pty Ltd [2017] FCA 1620;
(2017) 353 ALR 84
Flint Ink NZ Ltd v Huhtamaki Australia Pty Ltd (2014) 44
VR 64; (2014) 289 FLR 30
John Holland Pty Ltd v Kellogg Brown & Root Pty Ltd
[2015] NSWSC 451
Novawest Contracting Pty Ltd v Brimbank City Council
[2015] VSC 679
Pipeline Services WA Pty Ltd v ATCO Gas Australia Pty Ltd
[2014] WASC 10
Recyclers of Australia Pty Ltd v Hettinga Equipment Inc
(2000) 100 FCR 420; (2000) 175 ALR 725
Rinehart v Hancock Prospecting Pty Ltd [2019] HCA 13;
(2019) 366 ALR 635
Sembawang Engineers and Constructors Pte Ltd v Covec
(Singapore) Pte Ltd [2008] SGHC 229
Tanning Research Laboratories Inc v O’Brien (1990) 169
CLR 332
COUNSEL: P Somers for the plaintiff
M J Drysdale for the first defendant
-- 2 of 12 --
3
J R Moore (sol) for the second and third defendants
SOLICITORS: Romans & Romans Lawyers for the plaintiff
Clinton Mohr Lawyers for the first defendant
Thynne & Macartney for the second and third defendants
First defendant’s stay application
[1] The plaintiff (as contractor) and the first defendant (as principal) entered into a contract
for the design and construction of serviced apartments at Windsor. The plaintiff contends
the first defendant has breached the contract, by failing to pay for work performed under
the contract. By this proceeding, commenced on 28 May 2019, the plaintiff seeks to
recover just over $4.3 million damages for that breach, or alternatively to recover that
amount on a quantum meruit basis. The second and third defendants were, at varying
times, the superintendent under the contract. The plaintiff also claims damages against
them for negligence in relation to, inter alia, the issue of payment certificates and the
treatment of variations.
[2] The contract included a dispute resolution clause, in the following terms:
“41 Dispute resolution
41.1 Notice of dispute
If a difference or dispute (together called a ‘dispute’) between the parties
arises in connection with the subject matter of the Contract, including a
dispute concerning:
(a) a Superintendent’s direction; or
(b) a claim:
(i) in tort;
(ii) under statute;
(iii) for restitution based on unjust enrichment or other quantum
meruit; or
(iv) for rectification or frustration,
or like claim available under the law governing the Contract,
then either party shall, by hand or by registered post, give the other and the
Superintendent a written notice of dispute adequately identifying and
providing details of the dispute.
-- 3 of 12 --
4
Notwithstanding the existence of a dispute, the parties shall, subject to clauses
38 and 39 and subclause 41.4, continue to perform the Contract.
41.2 Conference
Within 14 days after receiving a notice of dispute, the parties shall confer at
least once to resolve the dispute or to agree on methods of doing so. At every
such conference each party shall be represented by a person having authority
to agree to such resolution or methods. All aspects of every such conference
except the fact of occurrence shall be privileged.
If the dispute has not been resolved within 28 days of service of the notice of
dispute, that dispute shall be and is hereby referred to arbitration.
41.3 Arbitration
If within a further 14 days the parties have not agreed upon an arbitrator, the
arbitrator shall be nominated by the person in Item 37(a). The arbitration shall
be conducted in accordance with the rules in Item 37(b).
The arbitration shall be held at the location stated in Item 37(d).
41.4 Summary relief
Nothing herein shall prejudice the right of a party to institute proceedings to
enforce payment due under the Contract or to seek injunctive relief or urgent
declaratory relief.”1
[3] It is uncontroversial that this clause constitutes an “arbitration agreement” within the
meaning of s 7 of the Commercial Arbitration Act 2013 (Qld). Section 7 provides, in
part:
“(1) An arbitration agreement is an agreement by the parties to submit to
arbitration all or certain disputes which have arisen or which may arise
between them in respect of a defined legal relationship, whether
contractual or not.
(2) An arbitration agreement may be in the form of an arbitration clause in
a contract or in the form of a separate agreement. …”
[4] Although the contract is said to have been terminated on or about 27 or 28 March 2019,2
it is also uncontroversial that an arbitration agreement is independent of the underlying
1 Affidavit of Mr Mohr, filed 12 June 2019, at pp 67-68 of ex CMM-1.
2 Affidavit of Mr Mohr, filed 12 June 2019, at [5] and [6].
-- 4 of 12 --
5
contract in which it is contained and therefore that the enforceability of the arbitration
agreement survives the termination of the contract it relates to.3
[5] The first defendant applies for an order that the proceeding “be stayed until there has
been compliance with the dispute resolution procedures contained in clause 41” of the
contract.
[6] The first defendant argues that, by operation of s 8 of the Commercial Arbitration Act,
the court must grant the stay. Alternatively, if s 8 does not apply, the first defendant
seeks to invoke the court’s inherent jurisdiction to stay the proceeding until the dispute
resolution provisions under clause 41 of the contract have been complied with.
[7] For the following reasons, I find that s 8 of the Commercial Arbitration Act does apply,
such that the court must refer the parties to arbitration. It follows that it is appropriate to
stay the proceeding as against the first defendant.
[8] Section 8 of the Commercial Arbitration Act provides:
“8 Arbitration agreement and substantive claim before court (cf
Model Law Art 8)
(1) A court before which an action is brought in a matter which is the
subject of an arbitration agreement must, if a party so requests not
later than when submitting the party’s first statement on the
substance of the dispute, refer the parties to arbitration unless it
finds that the agreement is null and void, inoperative or incapable
of being performed.
(2) Where an action referred to in subsection (1) has been brought,
arbitral proceedings may nevertheless be commenced or
continued, and an award may be made, while the issue is pending
before the court.”
[9] This provision differs markedly from the provision which formerly applied, s 53 of the
Commercial Arbitration Act 1990 (Qld), which conferred a discretion on the court to stay
the proceedings if satisfied “there is no sufficient reason why the matter should not be
referred to arbitration in accordance with the agreement” (s 53(1)(a)). The 1990 Act was
repealed by the 2013 Act (see s 41).4
[10] By the enactment of the Commercial Arbitration Act 2013, the Queensland Parliament
adopted the United Nations Commission on International Trade Law (UNCITRAL)
Model Law on International Commercial Arbitration (as adopted in June 1985, and
3 See Pipeline Services WA Pty Ltd v ATCO Gas Australia Pty Ltd [2014] WASC 10 at [42] and [47] per Martin
CJ, and the authorities there referred to.
4 See Pipeline Services WA Pty Ltd v ATCO Gas Australia Pty Ltd [2014] WASC 10 at [32] per Martin CJ; and
John Holland Pty Ltd v Kellogg Brown & Root Pty Ltd [2015] NSWSC 451 at [74].
-- 5 of 12 --
6
amended in July 2006) with some adaptations for application to domestic arbitrations in
Queensland.5 As recorded in the note within part 1A of the 2013 Act, the Act closely
follows commercial arbitration legislation enacted in other Australian jurisdictions “to
ensure the greatest possible harmonisation across Australian jurisdictions”. The
paramount object of the Act is “to facilitate the fair and final resolution of commercial
disputes by impartial arbitral tribunals without unnecessary delay or expense” (s
1AC(1)). Section 2A(1) of the Act provides that, in the interpretation of the Act, “regard
is to be had to the need to promote, so far as practicable, uniformity between the
application of this Act to domestic commercial arbitrations and the application of
provisions of the Model Law …” and s 2A(3) provides that in interpreting the Act,
reference may be made to the documents relating to the Model Law.
[11] Relevantly, the explanatory notes to article 8 of the Model Law (on which s 8 of the 2013
Act is based) provide as follows:
“Articles 8 and 9 deal with two important aspects of the complex relationship
between the arbitration agreement and the resort to courts. Modelled on article
II (3) of the New York Convention, article 8 (1) of the Model Law places any
court under an obligation to refer the parties to arbitration if the court is seized
with a claim on the same subject-matter unless it finds that the arbitration
agreement is null and void, inoperative or incapable of being performed. The
referral is dependent on a request, which a party may make not later than
when submitting its first statement on the substance of the dispute. …”
[12] There is no discretion under s 8(1) of the 2013 Act. If the action brought by the plaintiff
is in a matter which is the subject of an arbitration agreement, unless the court finds that
the arbitration agreement is null and void, inoperative or incapable of being performed,
the court must refer the parties to arbitration.6
[13] It is not in issue between the parties that this proceeding is an action “in a matter which
is the subject of an arbitration agreement”. The first defendant’s request, under s 8, has
been made at an appropriate time, that is, before and certainly “not later than when
submitting the party’s first statement on the substance of the dispute”. Those
circumstances being met, the court must refer the parties to arbitration unless it finds that
the arbitration agreement is null and void, inoperative or incapable of being performed.
[14] The plaintiff does not contend the agreement is null and void, or inoperative, but argues
the arbitration agreement is “incapable of being performed” for the purposes of s 8
because the plaintiff’s respective claims against the first defendant, on the one hand, and
5 As part of an integrated statutory framework for international and domestic arbitration in each State and
Territory in Australia: Rinehart v Hancock Prospecting Pty Ltd [2019] HCA 13; (2019) 366 ALR 635 at [13].
6 See John Holland Pty Ltd v Kellogg Brown & Root Pty Ltd [2015] NSWSC 451 at [65], [74], [87] and [132]
per Hammerschlag J; Novawest Contracting Pty Ltd v Brimbank City Council [2015] VSC 679 at [19]-[21]
per Vickery J; CPB Contractors Pty Ltd v Celsus Pty Ltd [2017] FCA 1620; (2017) 353 ALR 84 at [43] per
Lee J; and Broken Hill City Council v Unique Urban Built Pty Ltd [2018] NSWSC 825 at [18] per
Hammerschlag J.
-- 6 of 12 --
7
the second and third defendants, on the other, will require the court to determine a number
of similar factual matters, and there is a risk that if the claim against the first defendant
is determined at arbitration, and the claim against the second and third defendants is
determined by a court, the two different forums may reach different factual conclusions.
It is on the basis of that risk of different factual findings that the plaintiff contends the
arbitration agreement is “incapable of being performed”.
[15] I do not accept that argument. The meaning of “incapable of being performed” in a
provision such as s 8 is discussed in Novawest Contracting Pty Ltd v Brimbank City
Council [2015] VSC 679 at [22]-[30] and in Broken Hill City Council v Unique Urban
Built Pty Ltd [2018] NSWSC 825 at [33]-[58]. In both cases, reference is made to a
decision of the High Court of Singapore in Sembawang Engineers and Constructors Pte
Ltd v Covec (Singapore) Pte Ltd [2008] SGHC 229 in which the following was said in
relation to the term “incapable of being performed” (at [42]):
“[T]his term would relate to the capability or incapability of parties to perform
an arbitration agreement. In Mustill & Boyd, Commercial Arbitration, it is
stated the expression would suggest ‘something more than mere difficulty or
inconvenience or delay in performing the arbitration’ (at p 465). There has
to be ‘some obstacle which cannot be overcome even if the parties are ready,
able and willing to perform the agreement’ (id at p 465). In Margaret L
Moses, The Principles and Practice of International Commercial Arbitration
(Cambridge University Press, 2008), some examples of situations where an
arbitration agreement has become incapable of being performed are given. It
is stated (id at pp 32-33):
‘An arbitration agreement could be incapable of being performed, if,
for example, there was contradictory language in the main contract
indicating the parties intended to litigate. Moreover, if the parties had
chosen a specific arbitrator in the agreement, who was, at the time of
the dispute, deceased or unavailable, the arbitration agreement could
not be effectuated. In addition, if the place of arbitration was no longer
available because of political upheaval, this could render the arbitration
agreement incapable of being performed. If the arbitration agreement
was itself too vague, confusing or contradictory, it could prevent the
arbitration from taking place.’”7
[16] Mere inconvenience, such as might arise if the claims against the second and third
defendants were permitted to be actively pursued in the court, at the same time as the
7 In the Broken Hill City Council case at [32]-[34] reference is also made to the observations of Kaplan J on the
meaning of “incapable of being performed” in the decision of the Hong Kong Court of First Instance in Lucky-
Goldster International (HK) Ltd v NG Moo Kee Engineering Ltd [1993] HKCFI 14 at [14], which again was
in terms that it applies to a case where the arbitration cannot “be effectively set in motion”.
-- 7 of 12 --
8
arbitration of the claim against the first defendant, does not render the arbitration
agreement “incapable of being performed”.
[17] However, for reasons I will address under the next heading, that inconvenience does
support the exercise of the discretion to stay the proceeding against the second and third
defendants.
[18] Apart from this argument, the plaintiff contended that clause 41, in particular sub-clause
41.4, preserves its right to bring this proceeding in the court and prosecute it, without
having it referred to arbitration. At one stage, counsel for the plaintiff articulated this in
terms of the parties having “contracted around” s 8. I reject this argument also. Whatever
the scope of clause 41.4 might be (that is, whether it extends to a claim to recover money
such as in this proceeding, or is limited to enforcing payment certificates), s 8 of the
Commercial Arbitration Act is clear in its terms. Where the circumstances apply, and
the arbitration agreement is not found to be null and void, inoperative or incapable of
being performed, the court must refer the parties to arbitration. The plaintiff accepts the
circumstances set out in s 8 apply (relevantly, that this proceeding is an action brought
in a matter which is the subject of an arbitration agreement, and the first defendant has
made its referral request at an appropriate time); and I have rejected its argument that the
agreement is incapable of being performed. Accordingly, the referral must be made.
[19] The balance of the plaintiff’s submissions concerned discretionary considerations, on the
assumption (which I find is incorrect) that the court retains a discretion whether or not to
refer the matter to arbitration. It is accordingly unnecessary to address those matters.
[20] Although the Act does not expressly provide for the proceeding to be stayed as a
consequence of a referral to arbitration under s 8, such an order necessarily follows.8
[21] The appropriate order to make, in relation to the first defendant’s application, is therefore
that the proceeding against the first defendant is stayed, and the matter is referred to
arbitration pursuant to s 8 of the Commercial Arbitration Act 2013.
[22] For completeness, I note that counsel for the plaintiff raised an issue about the scope of
any arbitration, following a referral (in terms of whether it would be limited to the matters
in respect of which notices of dispute have been given, or extend to all matters of dispute
between the parties).9 Counsel for the first defendant confirmed that the first defendant
wanted all issues between the plaintiff and the first defendant to be dealt with in the
arbitration,10 and there appears to be no reason why that could not occur.
8 See John Holland Pty Ltd v Kellogg Brown & Root Pty Ltd [2015] NSWSC 451 at [133]; see also Novawest
Contracting Pty Ltd v Brimbank City Council [2015] VSC 679 at [20], where Vickery J says that under the
Victorian equivalent of s 8 [in identical terms] “it is mandatory for the Court to stay proceedings that are
commenced in contradiction to an arbitration agreement”.
9 T 1-36.
10 T 1-43.
-- 8 of 12 --
9
Second and third defendants
[23] The second and third defendants supported the application by the first defendant, but did
not initially bring their own application for a stay of the proceedings against them. An
oral application was made during the hearing; formalised by the filing of an application
on 26 June 2019.
[24] In the Commercial Arbitration Act 2013 “party” means a party to an arbitration
agreement and includes “any person claiming through or under a party to the arbitration
agreement” (s 2(1)).
[25] When read with s 8, this definition enables a person claiming through or under a party to
an arbitration agreement to be referred to arbitration, even if they themselves are not a
party to the agreement.11
[26] The second and third defendants are not parties to the arbitration agreement. But they
would appear to be persons “claiming through or under a party to the arbitration
agreement”. As the High Court recently affirmed,12 the leading authority as to the
meaning of “through or under” in this context is the decision in Tanning Research
Laboratories Inc v O’Brien (1990) 169 CLR 332. In Tanning at 342 Brennan and
Dawson JJ said:
“… a person who claims through or under a party may be either a person
seeking to enforce or a person seeking to resist the enforcement of an
alleged contractual right. The subject of the claim may be either a cause of
action or a ground of defence. Next, the prepositions ‘through’ and ‘under’
convey the notion of a derivative cause of action or ground of defence derived
from the party. In other words, an essential element of the cause of action or
defence must be or must have been vested in or exercisable by the party before
the person claiming through or under the party can rely on the cause of action
or ground of defence.”13
[27] As the plurality in Rinehart v Hancock Prospecting summarised, at [67]:
“To similar effect, but more explicitly, Deane and Gaudron JJ reasoned that
whether a party to proceedings is advancing a defence through or under a
party to an arbitration agreement is necessarily to be answered by reference
to the subject matter in controversy rather than the formal nature of the
proceedings or the precise legal character of the person initiating or defending
the proceedings.”14
11 See Flint Ink NZ Ltd v Huhtamaki Australia Pty Ltd (2014) 44 VR 64; (2014) 289 FLR 30 at [11] and [36] per
Warren CJ.
12 Rinehart v Hancock Prospecting at [61].
13 Emphasis added. See also Rinehart v Hancock Prospecting at [66].
14 Referring to Tanning Research at 353. Emphasis added.
-- 9 of 12 --
10
[28] And, further, at [68]:
“… as Deane and Gaudron JJ went on to explain, it is unnecessary that the
issues that the defence puts in controversy in the proceedings be limited to
the matter capable of settlement by arbitration. The two need not be
coextensive. It is sufficient that the defence puts in issue, among other things,
some right or liability which is susceptible of settlement under the arbitration
agreement as a discrete controversy.”15
[29] Appreciating that no defences have been filed yet (given the timing requirement of s 8),
it was nevertheless common ground that the plaintiff’s claims against the first defendant,
and the second and third defendants, are closely related, and depend upon findings about
the same factual matters. It was common ground that unless the plaintiff succeeds in
establishing its claim for payment against the first defendant, it cannot succeed against
the second and third defendants. It is essentially the same case against all parties. As the
plaintiff says in its written submissions:
“23. The respective claims will involve the Court determining a number of
similar factual matters, including, inter alia:
(a) whether certain building works were defective or properly carried
out;
(b) whether proper waterproofing was installed;
(c) whether certain works were within the contracted scope of works;
(d) whether certain variations were authorised, or validly rejected.
24. It is necessary for those factual matters to be determined in both claims,
because they go to:
(a) the amount the plaintiff is to be paid for building work under the
Contract; and
(b) whether the second and third defendants ought to have certified
those works, entitling the plaintiff to payment.”
[30] It follows from the overlap16 between the plaintiff’s claims as against the first defendant,
and the second and third defendants, that it is likely an essential element of the defence
by the second and third defendants will rely upon the rights vested in the first defendant
under the contract, and in that sense the second and third defendants can be said to claim
(or defend) “through or under” the first defendant. On this analysis, the second and third
defendants are a “party”, and the referral under s 8 applies to them also.
15 Referring to Tanning Research at 351-352.
16 Counsel for the plaintiff at T 1-38.4.
-- 10 of 12 --
11
[31] Even if the second and third respondents are not within the meaning of “party”, such that
the mandatory referral under s 8 applies to them also, it is within the discretionary power
of this Court to stay the proceedings against the second and third defendants in any
event.17 As it is common ground between the parties that the plaintiff must make out its
claim against the first defendant, in order to succeed in its claim against the second and
third defendants, it can be said that the claims against the second and third defendants
are ancillary to the matters the subject of the claim against the first defendant; and that
the decision of an arbitrator in relation to the latter will be determinative of the former.
It therefore makes sense, as a matter of discretion, to stay the plaintiff’s claim against the
second and third defendants, pending completion of the arbitration.18
[32] As indicated at the hearing, however, I will give the parties the opportunity to be heard
further in relation to this, should they wish to, before making orders.
Directions
[33] At the hearing, I raised with the parties whether the court has power to make directions,
at the same time as a referral under s 8.
[34] Section 8 of the Commercial Arbitration Act 2013 does not expressly provide for the
court to do more than refer the parties to arbitration (cf s 53 of the repealed Act, which
expressly provided for the court to “give such directions with respect to the future
conduct of the arbitration as [it] thinks fit”).
[35] In addition, s 5 of the Commercial Arbitration Act 2013 provides that “[i]n matters
governed by this Act, no court must intervene except where so provided by this Act”.
Section 6 confers particular functions on the Supreme Court,19 but not a general power
to make directions following a referral to arbitration. The conduct of arbitral proceedings
is dealt with in part 5 of the Act. Those provisions make it plain that it is the arbitral
tribunal which is to determine the rules of procedure. There is a general obligation
imposed on the parties by s 24B(1) to “do all things necessary for the proper and
expeditious conduct of the arbitral proceedings”, which includes taking without undue
delay any necessary steps to obtain a decision (if required) of the court in relation to a
function conferred on the court under s 6 (s 24B(2)(b)).
17 See r 16(g) of the Uniform Civil Procedure Rules 1999 (Qld).
18 See Tanning Research at 345 and 351; see also Recyclers of Australia Pty Ltd v Hettinga Equipment Inc (2000)
100 FCR 420; (2000) 175 ALR 725 at [65]-[66] per Merkel J; Casaceli v Natuzzi SpA (2012) 292 ALR 143 at
[48]-[49] per Jagot J; and CPB Contractors Pty Ltd v Celsus Pty Ltd [2017] FCA 1620; (2017) 353 ALR 84
at [54]-[56] and [122] per Lee J.
19 For example, in relation to disputes about the appointment of an arbitrator (ss 11, 13 and 14), or the jurisdiction
of the arbitral tribunal (s 16), recognition and enforcement of an interim measure (ss 17H to 17J), enforcement
of an order made or direction given by the arbitral tribunal in the course of the arbitral proceeding (s 19(6)),
assistance in taking evidence (ss 27 to 27B), orders prohibiting disclosure of confidential information (ss 27H
to 27J), orders as to costs of a failed arbitration (s 33D) and applications to set aside an arbitral award (s 34)
or an appeal on a question of law (s 34A).
-- 11 of 12 --
12
[36] From a consideration of the provisions of the Commercial Arbitration Act 2013, it does
not seem to me this Court has power to make any directions, further to the referral to
arbitration. However, I will give the parties an opportunity to be heard further in relation
to this also, at the time of delivering my reasons.
Orders
[37] There will be an order that the proceeding against the first defendant is stayed, and the
matter is referred to arbitration pursuant to s 8 of the Commercial Arbitration Act 2013.
[38] I will give the parties the opportunity to consider these reasons, and make further
submissions if they wish to, in relation to the second and third defendants’ stay
application and the court’s power to make directions. I will also hear the parties in
relation to costs.
-- 12 of 12 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2019/173