Body Corporate for Holland Park View Apartments v Queensland Building and Construction Commission [2019] QCAT 334
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Body Corporate for Holland Park View Apartments v
Queensland Building and Construction Commission
[2019] QCAT 334
PARTIES: BODY CORPORATE FOR HOLLAND PARK VIEW
APARTMENTS (CTS 50032)
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
APPLICATION NO/S: GAR200-18
MATTER TYPE: General administrative review matters
DELIVERED ON: 4 November 2019
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Howe
ORDERS: The decision of the Commission given on 24 May 2018
is confirmed
CATCHWORDS: ADMINISTRATIVE LAW – ADMINISTRATIVE
TRIBUNALS – QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL – general
administrative review – direction to rectify – where a body
corporate complained about defective work – where the
Commission found building work was not defective and
refused to direct rectification – where the work complied
with statutory requirements – where the body corporate
maintained the work did not comply with the contract –
whether failure to comply with the contract amounted to
defective building work
Queensland Building and Construction Commission Act
1991 (Qld), s 11, s 72, Schedule 2
Statutory Instruments Act 1992 (Qld), s 7(3)
R v Miller; ex parte Graham Evans and Co (Qld) Pty Ltd
[1987] 2 Qd R 446
QBSA v O’Brien & Ors [2002] QDC 329
REPRESENTATION:
Applicant: Self-represented by K Hua
-- 1 of 7 --
2
Respondent: Self-represented by S Tabaiwalu
APPEARANCES: This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld)
REASONS FOR DECISION
[1] On 6 December 2017 the applicant body corporate made a complaint to the
Queensland Building and Construction Commission (‘the Commission’) against the
builder of its apartment complex in relation to water ingress in the block walls of the
basement car park of the complex.
[2] After investigation on 9 March 2018 the Commission determined not to issue a
direction to rectify defective building work to the builder.
[3] The body corporate sought internal review of that decision but the decision was
confirmed on 24 May 2018 following internal review.
[4] The body corporate filed an application in the tribunal to review the decision on 19
June 2018.
[5] In the course of proceedings in the tribunal an expert conclave was held. The experts
agreed that none of the issues (some issues discussed at conclave went beyond the
single relevant complaint by the body corporate to the Commission concerning water
penetration of the block walls of the basement car park) affected the structural
performance of the building.1
[6] The experts agreed that the performance requirements regarding water penetration
were provided for in the Building Code of Australia at FP1.4 which states a roof and
external wall (including openings around windows and doors) must prevent the
penetration of water that could cause unhealthy or dangerous conditions, or loss of
amenity for occupants, and undue dampness or deterioration of building elements. By
FP1.4(a), FP1.4 does not apply to a class 7 or 8 building where the particular case
there is no necessity for compliance.
[7] By A1.7 of the code a class 7 building includes a car park. The experts agreed that the
car park in question fell within that umbrella exemption.
[8] The experts agreed that the design documentation from both the architect and engineer
specified that all external walls, with the exception of a piled wall on the Harold Street
boundary of the complex, were to be fully waterproofed on the exterior face.
[9] The experts concur that water penetration is occurring through the walls in the car
park which indicates that no waterproofing membrane has been applied to the block
work retaining walls (excluding Harold Street) or if applied it has failed to waterproof
the walls.
[10] Mr Aldrich the expert for the body corporate believes this amounts to defective
building work because the waterproofing membrane shown in the design drawings are
either failing or missing. Mr Van de Hoef for the Commission is of the opinion that
1 Experts’ joint report 18 April 2019 [5.1].
-- 2 of 7 --
3
there is no defective building work because the construction is in accordance with the
Building Code.
The legislation
The Queensland Building and Construction Commission Act 1991 (Qld) (‘QBCC
Act’) provides:
72 Power to require rectification of building work and remediation of
consequential damage
(1) This section applies if the Commission is of the opinion that—
(a) building work is defective or incomplete; or
(b) consequential damage has been caused by, or as a consequence of,
carrying out building work.
(2) The Commission may direct the person who carried out the building work
to do the following within the period stated in the direction—
(a) for building work that is defective or incomplete— rectify the
building work;
(b) for consequential damage—remedy the damage.
(3) In deciding whether to give the direction, the Commission may take into
consideration all the circumstances it considers are reasonably relevant
and, in particular, is not limited to a consideration of the terms of the
contract for carrying out the building work (including the terms of any
warranties included in the contract).
…
(5) The Commission is not required to give the direction if the commission
is satisfied that, in the circumstances, it would be unfair to the person to
give the direction.
[12] The body corporate submits that the design documentation clearly show that the
basement walls (with the exception of one single wall) were required to be
waterproofed. Given the water leaking through the walls either the waterproofing was
carried out and it was defective or it was not carried out at all. In either case the body
corporate says the walls are defective building work.
[13] The body corporate says regardless of whether strict compliance with the building
code has been achieved, the real question is whether the walls have been constructed
to the waterproofing standard required by the approved design documents, that is, the
contractual documents. On the evidence the body corporate says the answer is no.
[14] The Commission does not challenge the claim that there is water penetration through
the car park walls. The Commission says however that the water penetration in the
circumstances does not amount to defective building work. The basement is a car park
and therefore compliance with the building code section FP1.4 is not required. The
water penetration does not affect the structural performance of the building. It doesn’t
affect the functional use of the car park. It does not cause unhealthy or dangerous
conditions or loss of amenity to occupants given it is a non-habitable area.
-- 3 of 7 --
4
Discussion
[15] Insofar as relevant, s 72(1) provides that if the Commission is of the opinion that
building work is defective or incomplete, s 72 applies.
[16] Defective in relation to building work is defined in schedule 2 to the QBCC Act as
including work that is faulty or unsatisfactory. In the current circumstances that broad
definition is of little assistance.
[17] By s 11 of the QBCC Act one of the functions of the Queensland Building and
Construction Board is to decide amongst other things operational policies to be
followed by the Commission. One of those policies that has been devised is the
Rectification of Building Work Policy of 10 October 2014. The policy is a statutory
instrument because it is a guideline of a public nature.2 The policy attempts to provide
some guidance as to the ambit of defective building work means by giving examples
of faulty or unsatisfactory building work. The examples are that the work does not
comply with the Building Act 1975 (Qld), Building Code of Australia or an applicable
Australian standard or involves the use of a manufactured product, and that product
has been used, constructed or installed in a way that does not comply with the product
manufacturer’s instructions.
[18] The policy goes on to provide meanings for non-structural defective building work
and structural defective building work, neither of which assists in the present
circumstances.
[19] Surprisingly there is little authority on the issue whether breaches by a builder of the
contractual terms amounts to defective building work in circumstances where the
construction otherwise complies with statutory and standard requirements.
[20] It has been said in a number of cases that whether or not work is defective is to be
ascertained objectively. The authority for that statement is R v Miller; ex parte
Graham Evans and Co (Qld) Pty Ltd.3 There, the Builders Registration Board of
Queensland (the predecessor to the Commission) directed a builder to rectify defective
building work. There were two aspects to the direction to rectify, one concerning the
failure to use material fit for the purpose of waterproofing and the other resulting from
faulty design. Neither item was a responsibility of the builder. Derrington J (as he then
was) said:
It is therefore in conformity with the plain and ordinary meaning of the terms
in subs.(3)(b) to find that they apply to the objective state of the finished work
itself, but that if that position derives from the builder’s adherence to the
contract then it is in the discretion of the Board, depending upon the
circumstances, whether he should be ordered to remedy the work.4
[21] Immediately before that his Honour had said:
That a builder’s work comes within the definition of building work that is faulty
or unsatisfactory within the meaning of subs.(3) does not of itself impose any
liability upon him but merely enlivens the discretion of the Board to order him
2 Statutory Instruments Act 1992 (Qld), s 7(3).
3 [1987] 2 Qd R 446.
4 Ibid 458.
-- 4 of 7 --
5
to remedy the work, for the use of the permissive “may” in the investment of
the Board’s powers also vests such a discretion in the Board.
…
In some circumstances, there is obvious need for protection of the owner even
though the builder may be able to point to a term of the contract justifying the
defective result, while in others the builder may be perfectly justified in
conforming with the specifications and should not be required to remedy the
defect.5
[22] In QBSA v O’Brien & Ors,6 McGill DCJ commented on Miller as the lead authority
in this area as follows:
I was also referred to the decision in Wilson v Queensland Building Services
Authority [2000] QBT 53, where reference was made to a series of decisions
where it had been concluded that it was not appropriate to give a direction to a
builder where the builder had neither contractual nor tortious liability to the
owners in respect of the defective work in question. That approach was followed
in that case also. Although it would be inappropriate to fetter the discretion by
any such rule, it is clear from the decision in Miller that the fault of the builder
is a relevant consideration, and I think it follows logically that whether the
defective work amounts to a breach of any contractual obligation of the builder
to the owner, or involves breach of a duty to take care owed to the owner, would
be aspects of whether the builder was at fault. Nevertheless, it is not a matter
which ought to be regarded as necessarily determinative of the discretionary
decision to issue a notice.7
[23] The reference to consideration of the builder’s potential contractual or tortious
liability as an aspect of fault must be understood in context however. In the decisions
concerning the exercise of discretion to direct or not to direct rectification of defective
building work the common scenario has uniformly been one where defective work is
apparent or at least not disputed but the fairness in holding the builder responsible for
rectification challenged.
[24] It is significant that in Miller the legislation before the Full Court was in different
terms to that of the current. In Miller the Builders’ Registration and Homeowners
Protection Act 1979 (BRHP) provided in so far as relevant:
59. Remedy for unsatisfactory work.
(1) Where the Board is of the opinion (after consideration of all the relevant
circumstances) that building work performed by a person who is …
(a) a registered builder; …is faulty or unsatisfactory the Board, in
writing served on that person –
(c) may order him to remedy the building work that is faulty or
unsatisfactory; … within a reasonable time specified by the Board
in its order.
5 ibid
6 [2002] QDC 329
7 [47]
-- 5 of 7 --
6
(3) For the purposes of this section, the expression “building work that is
faulty or unsatisfactory” includes building work that has not been
performed in accordance with all of the following provisions:
(a) in a proper and workmanlike manner;
(b) with materials of good quality that are fit for the purpose for which
they are used;
(c) in such a manner that the building concerned is fit for human
habitation;
(d) to the standard to be expected of a reasonably competent registered
builder;
(e) so as to comply with –
(i) every relevant Act, regulation or by-law; or
(ii) all relevant provisions of a contract entered into in relation
to the performance of the building work concerned.8
(emphasis added)
[25] Within the range of factors specified to be taken into account by the Board under
s 59(3) in determining whether the building work was faulty or unsatisfactory was
compliance with the terms of the contract. This provision is markedly different to the
current s 72 of the QBCC Act.
[26] Instead s 72 provides a staged progression in the decision making process whether or
not to issue a direction to rectify or complete.
[27] There is a threshold stage of the Commission forming an opinion as to whether or not
the work complained about is defective. If the opinion is formed that it is, then the
next stage, the second stage, is invoked, which is whether the direction should be
given, and in that second stage, s 72(3) provides that all the circumstances considered
relevant, which is not limited to but will include consideration of the terms of the
contract, as too warranties included in the contract, may be taken into account.
[28] Amongst the warranties will be those implied by Part 3 Division 2 and 3 of schedule
1B of the QBCC Act which includes s 23(2), that the building contractor will carry
out the work in accordance with the plans and specifications of the contract.
[29] In so far as the complaint to the Commission concerns defective building work, I
conclude giving effect to the legislation requires consideration of the builder’s
contractual compliance at the second rather than threshold stage of the process.
[30] Accordingly the builder’s contractual compliance is not a factor for consideration in
the Commission forming an opinion whether building work is defective. The
comments by Derrington J in Miller remain apposite that that opinion should be based
on the objective state of the finished work. That proposition has been cited with
8 [1987] 2 Qd R 446, 446.
-- 6 of 7 --
7
approval in many decisions in circumstances where the current form of legislation
applies.9
[31] If that opinion is formed, then by s 72(2) the Commission is then required to exercise
a discretion whether or not to direct the person who carried out the building work
found defective to rectify it. It is at the stage of deciding whether or not to give that
direction that the Commission may take into account such relevant circumstances as
the terms of the contract for the purpose of deciding whether to give the direction.
Conclusion
[32] In the matter at hand there is no contest that the car park construction complies with
the legislative requirements including the Building Code of Australia. Based on that,
the Commission formed the opinion that the work complained about was not defective
and therefore refused to issue a direction to rectify. The claim that the builder failed
to comply with the contract does not fall for consideration.
[33] A decision by the Commission not to give a direction to rectify is a reviewable
decision in the tribunal.10 In the circumstances set out above it is appropriate to
confirm the decision of the Commission. The building work complained about is not
defective building work for the purpose of s 72 QBCC Act.
[34] I should add, this matter only concerns a complaint about defective building work. It
does not involve a complaint about incomplete building work. In so far as a complaint
concerns incomplete work, the contract terms must obviously fall for consideration at
the threshold stage of the Commission forming an opinion whether the work is
incomplete. It is not necessary in resolving the application at hand to consider the
boundaries that might apply to that process.
[35] Finally I note the body corporate is not left without remedy. It is entitled to pursue the
matter of failure to comply with the contract as a building dispute before the tribunal
or subject to the monetary claim, before the appropriate court.
9 QBSA v O’Brien; Cantamessa v QBCC [2019] QCAT 268; CMG Homes Pty Ltd v QBCC [2019]
QCAT 191; Goldfield Projects Pty Ltd v QBCC [2016] QCAT 361; QBCC v JM Kelly (Project
Builders) Pty Ltd [2016] QCATA 10; Leo v QBSA [2012] QCAT 640.
10 QBCC Act, s 86(1)(e).
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2019/334