Craig MacGregor Davies (t/a Trojan Tilers) v Austruct Pty Ltd [2019] QCAT 266
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Craig MacGregor Davies (t/a Trojan Tilers) v Austruct
Pty Ltd [2019] QCAT 266
PARTIES: CRAIG MACGREGOR DAVIES (T/A TROJAN
TILERS
(applicant)
v
AUSRUCT PTY LTD
(respondent)
APPLICATION NO BDL047-18
MATTER TYPE: Building Dispute
DELIVERED ON: 6 September 2019
HEARING DATE: 22 August 2019
HEARD AT: Brisbane
DECISION OF: Dr J R Forbes, Member
ORDER: The Respondent Austruct Pty Ltd must pay to the
Applicant Trojan Tilers the sum of $17,388.25 within
21 days.
CATCHWORDS: CONTRACT – BUILDING AND CONSTRUCTION
CONTRACT – MINOR CIVIL DISPUTE – minor
commercial building dispute – subcontract – where
subcontractor suing for moneys due – where opponent
counterclaiming for defective work – where opponent
seeks to tender evidence of more than one expert – whether
one expert rule applies – whether defects major or minor –
preferred expert advises minor – where offer of
subcontractor to remedy defects gratis not accepted –
whether compensation recoverable for defects
Queensland Building and Construction Act 1991 (Qld) s
77
Queensland Civil and Administrative Tribunal Act 2009
(Qld) Schedule 3
QCAT Practice Direction No 9 of 2009
Uniform Civil Practice Rules 1999 (Qld) rules 367(3)(e),
423, 429H
Ardlethan Options Ltd v Easdown (1915) 20 CLR 285
-- 1 of 7 --
2
CH2M Hill Australia Pty Ltd v New South Wales [2012]
NSWSC 808
D v S [2009] QSC 446
Iezzi Constructions Pty Ltd (in liq) v C & E Pty Ltd [2005]
QSC 158
Jamif Pty Ltd v Grant Torrens International Marine Pty
Ltd [2006] QSC 229
Simpson v Brett and Suncorp General Insurance Ltd
(unreported, Qld SC Rockhampton, McMeekin J, 8
December 2008
Stolfa v Owners of Strata Plan 4366 (No 2) [2008]
NSWSC 531
APPEARANCES: Ms J MacGregor-Davis for the Applicant
Mr A Ward for the Respondent
REASONS FOR DECISION
[1] In 2016-2017 a commercial-residential complex was being built beside the Story
Bridge at Kangaroo Point Brisbane. On 21 December 2016 the Respondent Austruct
Pty Ltd (`Austruct’) engaged the Applicant Trojan Tilers (`Trojan’) to install
waterproofing and to lay tiles on its behalf.
[2] Trojan now claims that it is still owed almost half its contract price1, while Austruct
alleges that Trojan’s work is so seriously defective that it owes Austruct $25,000.
[3] On 13 June 2017, having fulfilled a precondition,2 Trojan commenced these
proceedings, claiming $17,734.55 for the balance of its agreed price. The calculation
of that amount is not in dispute.
[4] Two months later Austruct responded with a counterclaim for $25,0003, alleging
defective work, and claiming cleaning costs, payment for goods supplied and
variations allegedly not approved. If upheld, Austruct’s action would, of course,
conveniently extinguish its obligation to pay Trojan about 45% of the contract price
and leave Austruct $7,000-odd in credit. Accordingly, relying upon a set-off, Austruct
contends that it is entitled to reject Trojan’s claim.
Trojan’s quest for payment
[5] The contract provided for periodic invoices and payments as sections of Trojan’s job
were completed. But Mrs MacGregor-Davis says that even before the `balconies
dispute’ existed, Trojan had considerable difficulty in obtaining regular and timely
payment from Austruct. She particularises this grievance as follows4 in a list not
disputed:
1 $32,734.55/
2 Queensland Building and Construction Act 1991 (Qld) s 77(2).
3 $25,000 is the monetary limit of the Tribunal’s jurisdiction: QCAT Act Schedule 3: `prescribed
amount’defined.
4 Operations and Compliance Manager of Trojan, affidavit sworn on 24 April 2019, paragraphs 13 to
46.
-- 2 of 7 --
3
(a) A deposit of $5000 was never paid. (Austruct says that it was not a term of
the agreement.)
(b) However, when Trojan, on 24 and 30 December 2016 sought payment of the
deposit, Austruct replied that it would be lodged `overnight’. It was not.
(c) Messages sent by Trojan to Austruct on 27 and 28 December 2016 were not
answered.
(d) Austruct secured a pause by asking for copies of invoices and bank account
details, which Trojan supplied.
(e) On 27 and 30 January, and 2, 3 and 6 February 2017 Trojan sent messages
to Austruct requesting payment of outstanding invoices. Austruct did not
respond.
(f) On 6 February 2017 Mr Ward of Austruct denied that he was `hanging up’
on Mrs MacGregor-Davis’ phone calls and sent her a text message stating that
he was `trying to call [her] back’. He did not do so.
(g) On 8 February 2017 Mr Ward emailed Trojan to say that `he [would] have
more funds soon as he [was] trying hard to chase up a payment claim’ made
upon an unnamed third party.
(h) On 9 February 2017 Trojan enquired `what was going on as no money had
been received’.
(i) On 10 February 2017 Trojan informed Austruct that Trojan would `escalate’
its complaints by reporting them to the Queensland Building and Construction
Commission (QBCC). Austruct replied that it expecting payments from its
debtors and would soon be transferring money to Trojan.
(j) On 11 February 2017 Austruct ordered Trojan to fit wall skirting and to
complete waterproofing and tiling. Trojan declined to perform any further work
until it received a `significant amount of remittance’
(k) On 14 February 2017 Trojan informed Austruct that it had received `nothing
but broken payment arrangements’ and once again sought a meaningful
discussion. Austruct’s Mr Ward replied that he was in a meeting but would call
back when it concluded. He did not do so.
(l) On the next day Trojan asked why the promised return call did not occur.
Mr Ward replied that he `was having some phone issues’.5 However, on 17
February 2017, when he and Trojan had several discussions about a replacement
subcontractor, `Mr Ward appeared to have no phone issues on this day.’
(m) By 17 February 2017 Trojan was in serious financial difficulties. Ward
stated that `he would authorise a payment of $2,500 ... into our personal
account’. One week later Ward promised that `money would be forthcoming
next Wednesday the 1st of March’.
5 Presumably this was a claim that Austruct’s phones were out of order. `Issue’ is currently a vague and
much abused term, not restricted to points of disagreement, but variously used to indicate illness,
mechanical faults, and all manner of difficulties.
-- 3 of 7 --
4
(n) Messages from Trojan to Austruct on 20 and 21 March and 10 May 2017
received no response.
Tiling work – repairs or total demolition and replacement?
[6] By far the largest item in Austruct’s list of claims is an amount of $26,391, allegedly
required to re-do, totally, Trojan’s tiling on two balconies. It is common ground that,
in some places, the tiles, as laid by Trojan, do not allow a complete runoff of water,
so that `pooling’ occurs from time to time.
[7] Trojan’s case is that this problem can be satisfactorily and less expensively resolved
by lifting tiles where `dips’ occur, augmenting the bedding and relaying the tiles
involved. But Austruct, for its part, insists that complete retiling of the affected areas
is necessary.
[8] Expert evidence in support of Trojan’s view is given by Mark Peter Kennedy, a
registered builder and a member of the Queensland Building and Construction
Commission for some 25 years. According to Mr Kennedy `total removal of the tiled
area is not called for’, and he describes a procedure for eliminating `pooling.’6 He
favours a modest, relatively inexpensive and non-destructive solution to what is
scarcely a major building problem.
[9] However, Austruct insists that occasional puddles on the outdoor patios can only be
avoided by complete demolition and replacement, at an estimated cost in excess of
$25,000. For that proposition Austruct relies on no fewer than three experts, namely
Garry Carpenter (Datum Building Consultancy)7, Robin Spencer Architects Pty Ltd8,
and Christopher Felix Boyle.9 Mr Boyle’s report appears almost as an afterthought,
fourteen months after that of Datum, nearly one year after Robin Spencer’s, and about
four weeks before the hearing.
The One expert rule
[10] At the hearing, Mr Ward stated that, at an interlocutory stage, the Tribunal had told
him that the Boyle report might (or would) not be admitted in evidence. The reasons
for that warning appear below. However, I received that report provisionally, so as to
have an opportunity to consider whether to allow it as a matter of discretion.
[11] After such consideration I have decided that the Boyle report should not be admitted,
and I rule accordingly. This decision rests upon a relatively recent and important
reform of civil procedure, commonly referred to as the `one expert rule’. The Uniform
Civil Procedure Rules 1999 (Qld) (`the UCPR’) provide:
The main purposes of this part10 are to ... ensure that, if practicable, and without
compromising the interests of justice, expert evidence is given on an issue by a
single expert agreed by the parties or appointed by the court; and ... to avoid
unnecessary costs associated with the parties retaining different experts... 11
6 Affidavit and Report of M P Kennedy for Brisbane Pre-Purchase Inspections, filed herein on 29 July
2018 page 10 recommendation number 1.
7 Report of Garry Carpenter (Datum) dated 14 May 2018.
8 `Defects List’ prepared by Robin Spencer Architects Pty Ltd 30 August 2018.
9 The Boyle report was filed herein on 12 July 2019. 6
10 Part 5 - Expert evidence.
11 UCPR rule 423. See also rule 429H.
-- 4 of 7 --
5
[12] Elsewhere the UCPR state:
The court may make an order or direction about the conduct of a proceeding it
considers appropriate, even though the order or direction may be inconsistent with
another provision of these rules ... [T]he court may at any time ... limit the number
of witnesses (including expert witnesses) a party may call on a particular issue ...12
[13] The UCPR apply in this Tribunal.13
[14] The `one expert’ rule serves several worthy purposes: (a) it avoids the delay, expense,
complexity and possible oppression of an opponent by a party calling a multiplicity
of experts; (b) it disposes of the popular misconception that the party with the most
experts will prevail; and (c) it discourages `expert shopping’, whereby a party
dissatisfied with an initial opinion, looks about for someone else who, it may even be
hinted, will better support his case
[15] The rule is no longer a novelty; `timely’ reminders of it, and strict applications were
issued by the Supreme Court over ten years ago,14 and the file in this case shows that
Austruct has had the benefit of professional advice. The rule may be relaxed in
`exceptional’ circumstances, but it should not be thought that the mantra `the interests
of justice’ is a ready escape from the rule itself. In CH2M Hill Australia Pty Ltd v New
South Wales15 McDougall J observed:
The purpose of [the one expert rule] would be subverted if the court were simply to
regard, as exceptional circumstances, the fact that a party did not appreciate that
particular evidence was expert evidence. That would mean that parties who were
ignorant or inattentive would gain a procedural advantage, possibly of a very
significant nature, denied to parties who were careful ... I do not think that anything
in the Rules, or for that matter in the `just, quick and cheap’ objective ... requires
such a conclusion.
[16] I see no sufficiently `exceptional’ or compelling circumstances in this case. When the
Boyle report was filed, Austruct had already filed (already contrary to the rule) two
expert opinions on the `repair or replace’ issue. The Boyle report is not admitted in
evidence.
Rival reports compared.
[17] For Austruct, the Datum report deals with several matters which could not
conceivably be seen as Trojan’s responsibility. For example, there is extensive
criticism of the roof construction, unfavourable comment on fire protection
installation, and disapproval of `PVC pipework to the roof water plumbing on the
existing Night Owl building’.
[18] However, Datum’s `Balcony Repair Costs’ are predicated on `removal of all tiles and
bedding’16 without any justification of that radical conclusion, or discussion or
12 UCPR rule 367(3)(e).
13 QCAT Practice Direction No 4 of 2009. Paragraph 2: `A party ... may call only one expert for each
area of expertise.
14 Jamif Pty Ltd v Grant Torrens International Marine Pty Ltd [2006] QSC 229 at [21]; Iezzi
Constructions Pty Ltd (in liq) v C & E Pty Ltd [2005] QSC 158 at [12]; D v S [2009] QSC 446. The
rule was strictly applied in Stolfa v Owners of Strata Plan 4366 (No 2) [2008] NSWSC 531 and
Simpson v Brett and Suncorp General Insurance Ltd (unreported, Qld SC Rockhampton, McMeekin
J, 8 December 2008.
15 [2012] NSWSC 808 at [16].
16 Annexure `K’ to Datum Report.
-- 5 of 7 --
6
criticism of the more conservative view of Mr Kennedy. The repairs, as Datum
suggests with surprising precision, would cost $26,391. That is an estimate only; the
balconies remain as Trojan left them.17
[19] Also for Austruct, there remains the brief Robin Spencer report. It was originally
obtained by the head contractor, but in effect Austruct adopted it as its own. It may
remain upon the record, as one not averse to the interests of Trojan. It contains two
relevant comments: (a) `builder to take up tiles re level and relay to correct faults”;
and (b) `replace tiles holding water’. Each comment is reconcilable with the Kennedy
view. Spencer’s comment `(b)’ specifies the `tiles holding water’, not the tiles in
general.
[20] The qualifications and experience of Trojan’s expert, Kennedy, are impressive, and
relying on his report, coupled with Robin Spencer’s brief but cautious comment, I find
it more probable than not that the tiling problem could be dealt with quite adequately
in the manner that Kennedy recommends. According to Kennedy most water on the
balconies drains satisfactorily, indicating that the `fall’ towards the outlets is generally
adequate.
[21] I note that on 6 June 2017 Ward told Trojan: `We suggest holding off on purchasing
[a] large qty of tiles at this stage until a suitable method is agreed upon to rectify these
works.’18 Evidently, at that stage, neither the Datum nor the Robin Spencer report was
interpreted by Ward as inevitably calling for wholesale revision of the work. The
Kennedy solution was still on the cards. It was only after Boyle report that the much
more expensive method was unequivocally adopted by Austruct.
Mitigation
[22] A party claiming redress is expected to take all reasonable steps to minimise loss or
damage, a duty to the opponent.19 It is simply a matter of fairness and reasonableness
towards the opponent. In late January 2017 Trojan corrected some silicone defects
without charge. 20 On 20 April 2017 Trojan made this open offer:
In the event that our independent building inspector finds defective workmanship
to be below Australian standards, we are more than happy to address ALL work of
scope that DOES NOT meet QBCC Standards at no additional cost to Austruct.21
[23] However, Austruct has not seen fit to allow Trojan back.22 The letter just quoted is
cordial, and there appears to be no such mutual animus that compromise and
reconciliation are impractical. It is Austruct’s choice to reject practical compensation
in kind and without charge, but in those circumstances it is not appropriate recover a
substantial sum that they may or may not ever spend on the balconies, or which simply
serves to absolve them from paying Trojan more than one half of the contract price.
There will be no award for demolition and wholesale replacement of the balcony tiles.
Resolution
17 Affidavit of Craig MacGregor-Davis sworn 24 April 2019 paragraphs 22(b), 43.
18 Email Ward to Jennifer MacGregor-Davis 6 June 2017.
19 Ardlethan Options Ltd v Easdown (1915) 20 CLR 285.
20 Affidavit of Craig MacGregor-Davis sworn 24 April 2019 paragraph 4(d).
21 Email Trojan to Austruct 20 April 2017 emphases in the original.
22 Affidavit of Craig MacGregor-Davis sworn 24 April 2019 paragraph 14(a).
-- 6 of 7 --
7
[24] Austruct claims $2,160 for employing third parties to apply silicone to skirting tiles
and splashbacks. This claim is not specifically contested by Trojan, and it is admitted
that Trojan ceased work for a period as a protest against delayed payments.23 This
claim is allowed.
[25] Further, Austruct claims $1,288.03 for materials supplied to Trojan. Trojan contends,
and I accept, that these goods were ordered before Trojan’s arrival by the
subcontractor who resigned.24 It is unclear whether they were invoiced to the latter,
or (as seems more likely) to Austruct. In any event, insofar as they were used by
Trojan, the benefit accrued to Austruct. This claim is disallowed.
[26] Austruct also claims $400 for part of the cost of cleaning cement splatters and
builder’s debris. This appears to be a reasonable charge, and it is allowed.
[27] For reasons set out above, Austruct’s claim of $26,391 for demolishing and replacing
balcony tiles is disallowed.
[28] It follows that Austruct is entitled to set off against the balance of Trojan’s
remuneration an amount of $2,560, leaving in Trojan’s favour a balance of
$15,174.55.
[29] Trojan has applied for interest and costs. Interest is allowed in accordance with the
relevant Practice Direction25 at $1,896 with costs of $315.70.
[30] In the overall result Austruct owes Trojan $17,388.25. There will be judgment for that
amount.
Order
[31] The Respondent Austruct Pty Ltd must pay to the Applicant Trojan Tilers the sum of
$17,388.25 within 21 days.
23 Affidavit of Jennifer MacGregor-Davis sworn 24 April 2019 paragraph 26.
24 Affidavit of Craig MacGregor-Davis sworn 24 April 2019 paragraph 34.
25 QCAT Practice Direction 9 of 2013.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2019/266