Cameron v Guise [2019] QCAT 220
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Cameron v Guise [2019] QCAT 220
PARTIES: CRAIG CAMERON
(applicant)
V
REECE BRIAN GUISE
(respondent)
APPLICATION NO/S: BDL321-18
MATTER TYPE: Building matters
DELIVERED ON: 12 August 2019
HEARD AT: Brisbane
DECISION OF: Senior Member Brown
ORDERS: Reece Brian Guise must pay Craig Cameron
SEVEN THOUSAND, FOUR HUNDRED AND
SEVENTY-FIVE DOLLARS ($7,475.00) by
4:00pm on 9 September 2019.
Reece Brian Guise must pay Craig Cameron’s costs
fixed in the amount of THREE HUNDRED AND
THIRTY-EIGHT DOLLARS AND TWENTY
CENTS ($338.20) by 4:00pm on 9 September 2019.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
LEGALITY - where domestic building contract does not
comply with Schedule 1B of the Queensland Building and
Construction Commission Act 1991 (Qld) – whether a
breach of contract can be established
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – DAMAGES – MEASURES
OF – where contract entered into for the performance of
building work – where builder is unlicensed - where
builder performs unlicensed building work – where builder
not entitled to consideration for performing building work
– assessment of damages
Queensland Building and Construction Commission Act
1991 (Qld) s 77, sch 1B s 13(2), s 13(5), sch 2
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 48
-- 1 of 7 --
2
Bellgrove v Eldridge (1954) 90 CLR 613
Cook's Construction P/L v SFS 007.298.633 P/L (formerly
trading as Stork Food Systems Australasia P/L) [2009]
QCA 75
Corporation of the City of Adelaide v Jennings Industries
Ltd (1985) 156 CLR 274
Robinson v Harman (1848) 1 Ex 850; 154 ER 363
Ventura v Svirac (1961) WAR 63
REPRESENTATION:
Applicant: Self-represented
Respondent: No appearance
APPEARANCES: This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld)
REASONS FOR DECISION
Mr Guise contracted with Mr Cameron to complete an office fitout and a workshop
fitout at Mr Cameron’s home. Mr Cameron paid the contract amount in full prior to
the work commencing. Mr Guise failed to complete all of the work under the contract.
Mr Cameron filed in the tribunal an application for a domestic building dispute. Mr
Guise has not complied with any tribunal directions including failing to file a response
to the application.
Background to the dispute
The parties entered into an agreement for the performance of building work on or
about 27 July 2017. Mr Cameron says that the agreement was a verbal one. Mr
Cameron says that the details of the building work Mr Guise agreed to undertake were
contained in an invoice provided by Mr Guise to Mr Cameron on 27 June 2017. The
invoice was not signed by either party.
The invoice refers to “Office fitout” and “Workshop fitout”. In respect of each of the
fitouts, the invoice contains particulars of the building works to be carried out. The
total amount payable by Mr Cameron to Mr Guise for the building work was
$7,475.00 inclusive of GST.
Mr Cameron paid the invoice amount in two instalments. The first payment in an
amount of $5,000.00, was made on 28 July 2017. The second payment in an amount
of $2,475.00, was made on 29 July 2017.
Mr Cameron says that Mr Guise did not complete the building work. Over a period
of approximately one year, Mr Cameron made numerous attempts to have Mr Guise
complete the work. When these attempts failed, Mr Cameron sent Mr Guise a letter
of demand for $3,000 which was Mr Cameron’s estimate of the cost of completing
the building work.
-- 2 of 7 --
3
Mr Cameron subsequently discovered that Mr Guise’s builder licence had been
cancelled on 13 January 2017.1
Statutory framework – building disputes
The relevant enabling Act in respect of the present dispute is the Queensland Building
and Construction Commission Act 1991 (Qld) (‘QBCC Act’).
The tribunal has jurisdiction to hear and decide building disputes.2 A building dispute
can be a domestic building dispute or a minor commercial building dispute or a major
commercial building dispute.3 A domestic building dispute includes a dispute between
a building owner and building contractor relating to the performance of reviewable
domestic work or a contract for the performance of reviewable domestic work.4
‘Building contractor’ and ‘building owner’ are defined in the QBCC Act.5
‘Reviewable domestic work’ means domestic building work under s 4 of Schedule 1B
of the QBCC Act. The renovation, alteration, extension, improvement or repair of a
home is domestic building work.6 A home is a building or portion of a building that
is designed, constructed or adapted for use as a residence.7
In deciding a building dispute the tribunal may order the payment of an amount found
to be owing by one party to another.8
Statutory framework - bringing proceedings in the Tribunal to an early end
Proceedings in the Tribunal may be brought to an early end in circumstances where
the tribunal considers a respondent in a proceeding is acting in a way that
unnecessarily disadvantages an applicant by not complying with a tribunal order or
direction without reasonable excuse. In such circumstances, the tribunal may make its
final decision in the proceeding in the applicant’s favour.9
Consideration
I make the following findings:
1 QBCC licence search 11 May 2019,
2 QBCC Act, s 77.
3 Ibid, sch 2 (definition of ‘building dispute’).
4 Ibid, (definition of ‘domestic building dispute’).
5 Ibid, (definition of ‘building contractor; definition of ‘building owner’)
6 Ibid, sch 1B, s 4(1)(b).
7 Ibid, sch 1B, s 9(1).
8 Ibid, s 77(3).
9 Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 48.
-- 3 of 7 --
4
(a) Mr Guise agreed with Mr Cameron to undertake, and subsequently undertook,
domestic building work;
(b) Mr Cameron was a building owner and Mr Guise was a building contractor;
(c) the dispute between the parties is a domestic building dispute;
(d) the Tribunal has jurisdiction to hear and decide the dispute;
(e) service of the application for domestic building dispute has been properly
effected upon Mr Guise;10
(f) Mr Guise has failed to comply with any directions made by the Tribunal
including failing to file a response to Mr Cameron’s application;
(g) in failing to comply with Tribunal directions Mr Guise has unnecessarily
disadvantaged, and continues to unnecessarily disadvantage, Mr Cameron. The
disadvantage to Mr Cameron is that he is unable to progress his claim to final
resolution.
I have considered the matters at s 48(3) of the QCAT Act. Whether and to what extent
Mr Guise is familiar with the tribunal’s practices and procedures and Mr Guise’s
capacity to comply with tribunal directions are matters in relation to which I am unable
to form a view given Mr Guise’s lack of engagement in the proceedings. Mr Guise’s
failure to comply with directions would appear, in the absence of an explanation to
the contrary, to be a deliberate act. I am satisfied that it is appropriate to exercise my
discretion and make a final decision in the proceeding in favour of Mr Cameron.
Breach of Contract
Mr Cameron says that Mr Guise partially completed the work associated with the
“Office fitout” and failed to complete any of the work associated with the “Workshop
fitout”. Mr Cameron’s claim for $3,000 is based upon his assessment of the value of
the work yet to be completed by Mr Guise less an allowance for some additional work
that Mr Guise completed.
Ordinarily the failure by a building contractor to complete works without reasonable
excuse is a substantial breach of contract, constituting repudiatory conduct, and giving
rise to an entitlement to terminate the contract by the building owner. In such event,
the building owner is entitled to claim damages for the builder’s breach. Where a
building owner sustains a loss by reason of a breach of contract by a builder, the
10 Affidavit of Service of the applicant filed 7 December 2018.
-- 4 of 7 --
5
building owner is, so far as money can do it, entitled to be placed in the same situation,
with respect to damages, as if the contract had been performed.11 The measure of
damages recoverable by a building owner for breach of a building contract is the
difference between the contract price for the work and the cost of making the work
conform to the contract, subject to undertaking the work necessary to achieve
conformity being a reasonable course to adopt.12 In assessing the building owner’s
damages, the builder must be given credit for any unpaid part of the contract sum.13
The QBCC Act provides that a domestic building contract for an amount more than
$3,300 and less than $20,000 is a level 1 regulated contract.14 By s 13(2) of Schedule
1B of the QBCC Act, a level 1 regulated contract, inter alia, must be in writing and
signed by the parties in order to have effect. Indeed, by s 13(5) of Schedule 1B, a level
1 regulated contract only has effect if it complies with s 13(2).
Mr Guise provided to Mr Cameron a quote dated 27 June 2017. It is not signed by
either of the parties. The quote does not comply with the requirements of the QBCC
Act in relation to level 1 regulated contracts. As I have observed, unless a level 1
regulated contract is in writing, dated and signed by the parties it is of no effect. The
failure by a building contractor to comply with a requirement under the QBCC Act in
relation to a domestic building contract does not make the contract illegal, void or
unenforceable unless the contrary intention appears in the Act.15 Section 13(5) is
expressed in clear and unequivocal words. A contract that is not in writing, signed by
the parties and dated is of no effect. A contract that has no effect is void and cannot
be enforced. Mr Cameron cannot rely upon the agreement to make a claim against Mr
Guise.
Claim in negligence
A domestic building dispute may include a claim or dispute in negligence relating to
the performance of reviewable domestic work.16 A building owner, in order to
establish negligence by a builder, must prove that: the builder owed to the owner a
duty of care; the builder breached the duty; as a result of the breach of duty, the owner
has suffered loss.
11 Robinson v Harman (1848) 1 Ex 850; 154 ER 363.
12 Bellgrove v Eldridge (1954) 90 CLR 613.
13 Ventura v Svirac (1961) WAR 63 cited with approval in Corporation of the City of Adelaide v Jennings
Industries Ltd (1985) 156 CLR 274.
14 Queensland Building and Construction Commission Act 1991 (Qld), sch 1B, ss 1 (definition of
‘regulated amount’), 6(1)(a), 7(2); Queensland Building and Construction Commission Regulation
2018 (Qld) s 45.
15 Ibid, sch 1B, s 44.
16 Ibid, sch 2 (definition of ‘domestic building dispute’)
-- 5 of 7 --
6
Generally speaking, a builder owes to an owner a duty to perform building works in
an appropriate and skilful way and with reasonable care and skill. Mr Cameron has
not framed his claim in negligence. He does not assert that the building work
performed by Mr Guise was not carried out appropriately and skilfully. Rather, Mr
Cameron say that Mr Guise did not complete the agreed works. That is a contractual
issue and as I have found, Mr Cameron is not entitled to pursue any contractual
remedies against Mr Guise.
I am not satisfied that Mr Cameron has established a breach of duty by Mr Guise.
Unlicensed Building Work
By s 42(1) of the QBCC Act, a person must not carry out, or undertake to carry out,
building work unless the person holds a contractor’s licence of the appropriate class
under the Act. By s 42(3) of the QBCC Act, a person who performs unlicensed
building work is not entitled to any monetary or other consideration for doing so. Any
monetary or other consideration paid to an unlicensed builder must be repaid.17
It is clear from the provisions of the QBCC Act that the prohibition on unlicensed
building work is in respect of:
(a) An unlicensed contractor agreeing to perform building works;
(b) An unlicensed contractor performing building works;
(c) An unlicensed contractor receiving payment for performing building works;
(d) An unlicensed contractor retaining any payment received for performing
building works.
I find that at the time Mr Guise entered into the agreement with Mr Cameron, at the
time Mr Guise performed the building work, and at the time Mr Cameron paid Mr
Guise, that Mr Guise was not a licensed contractor.
I find that Mr Guise was in breach of s 42(1) of the QBCC Act when he undertook to
carry out the building work in September 2017 and when he subsequently performed
the building work. I find that Mr Guise was not permitted to carry out the building
work nor was he entitled to any monetary consideration for so doing. I find that,
pursuant to s 42(3) of the QBCC Act, Mr Guise was not entitled to the payment of
$5,000.00 that he received on 28 September 2017 and was not entitled to the payment
17 Cook's Construction P/L v SFS 007.298.633 P/L (formerly trading as Stork Food Systems Australasia
P/L) [2009] QCA 75..
-- 6 of 7 --
7
of $2,475 he received on 29 September 2017. Mr Guise has no entitlement to retain
the money he was paid by Mr Cameron.
There is no application before the Tribunal by Mr Guise pursuant to s 42(4) of the
QBCC Act. Mr Guise must therefore pay to Mr Cameron the amount of $7,475.00.
Costs
The tribunal may award costs in building disputes.18 The discretion to award costs is
a broad general one which must be exercised judicially, not upon irrelevant or
extraneous considerations but upon facts connected with or leading up to the litigation.
I find Mr Cameron is entitled to recover the filing fees on the application. This cost
was reasonable and necessary to enable Mr Cameron to pursue his legal entitlements.
I fix the total costs payable by Mr Guise in the amount of $338.20.
Orders
There will be a final decision for Mr Cameron as follows:
(a) Claim $7,475.00
(b) Costs $ 338.20
18 QBCC Act, s 77(3)(h).
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2019/220