Allen v Queensland Building and Construction Commission [2019] QCAT 20
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Allen & Anor v Queensland Building and Construction
Commission [2019] QCAT 20
PARTIES: REECE JUSTIN ALLEN
(first applicant)
CHANTELL RENEE MARIA TAYLOR
(second applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(respondent)
APPLICATION NO/S: GAR136-18
MATTER TYPE: General administrative review matters
DELIVERED ON: 17 January 2019
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Cranwell
ORDERS: The application for miscellaneous matters filed on 29
November 2018 is dismissed.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE
AND TERRITORY COURTS – JOINDER OF CAUSES
OF ACTION AND OF PARTIES – PARTIES –
GENERALLY – where excessive delay in seeking joinder
Queensland Building and Construction Commission Act
1991 (Qld), s 71
Queensland Civil and Administrative Tribunal Act 2009
(Qld), s 21, s 42
REPRESENTATION:
Applicant: Project Legal
Respondent: Self-represented
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld).
-- 1 of 2 --
2
REASONS FOR DECISION
[1] On 19 March 2018, the Queensland Building and Construction Commission (QBCC)
decided to decline a claim by Mr Allen and Ms Taylor under the statutory insurance
scheme.
[2] On 11 April 2018, Mr Allen and Ms Taylor filed an application to review that decision
in the Tribunal.
[3] Directions were subsequently made in relation to the conduct of the proceedings. The
QBCC filed documents pursuant to s 21(2) of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld) (QCAT Act) on 5 July 2018. Mr Allen and
Ms Taylor filed voluminous statements on 4 September 2018 and 19 October 2018.
A compulsory conference was held on 20 September 2018. The QBCC had been
directed to file any further statements of evidence in reply by 16 November 2018, but
none had been filed. The matter was listed for a directions hearing before me on 29
November 2018. The matter appeared for all intents and purposes ready to be listed
for hearing.
[4] On 29 November 2018, the QBCC lodged an application to join Contrast
Constructions Pty Ltd (Contrast Constructions) as a respondent to the proceedings.
The joinder application was made on the basis that the interests of Contrast
Constructions may be affected by the proceeding pursuant to s 42(1)(b) of the QCAT
Act. This is undoubtedly the case because if Mr Allen and Ms Taylor are successful,
the QBCC may recover any payment under the statutory insurance scheme from
Contrast Constructions pursuant to s 71(1) of the Queensland Building and
Construction Act 1991 (Qld).
[5] However, the joinder of parties is a discretionary matter. The fact that the interests of
Contrast Constructions may be affected by the proceedings should have been apparent
from 11 April 2018, when the proceeding was first commenced. The very nature of
the decision under review should have alerted the QBCC to that possibility from the
outset. Rather than make an application for joinder in a timely fashion, the QBCC
decided to wait until the proceedings were apparently ready to be listed for hearing
before making the application. No explanation was provided for this delay.
[6] Mr Allen and Ms Taylor have expended considerable effort and no doubt cost in
preparing their material. They should not be forced to incur additional costs and
delays as a result of the excessive and unexplained delay by the QBCC relating to the
joinder application.
[7] I dismiss the joinder application.
-- 2 of 2 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2019/020