Colagrande & Anor v D A Radic Pty Ltd trading as David Radic Prestige Homes [2019] QCATA 176
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Colagrande & Anor v D A Radic Pty Ltd trading as David
Radic Prestige Homes [2019] QCATA 176
PARTIES: CES COLAGRANDE AND REBECCA
COLAGRANDE
(applicant\appellant)
v
D A RADIC PTY LTD TRADING AS DAVID RADIC
PRESTIGE HOMES
(respondent)
APPLICATION NO/S: APL081-18
ORIGINATING
APPLICATION NO/S:
BDL118-16
MATTER TYPE: Appeals
DELIVERED ON: 11 December 2019
HEARING DATE: 16 November 2018
HEARD AT: Brisbane
DECISION OF: Senior Member Brown
Member Olding
ORDERS: 1. The appeal is allowed.
2. The decision of the Tribunal made 12 March
2018 is set aside.
3. Ces Colagrande and Rebecca Colagrande must
pay D A Radic Pty Ltd trading as David Radic
Prestige Homes SEVEN THOUSAND, TWO
HUNDRED AND FIFTY DOLLARS ($7,250)
within fourteen (14) days of the date of this
decision.
4. The parties must file and exchange written
submissions in respect of the question of costs of
the appeal within twenty-eight (28) days of the
date of this decision.
CATCHWORDS: APPEALS AND NEW TRIAL – APPEAL – GENERAL
PRINCIPLES – WHEN APPEAL LIES – ERROR OF
LAW – WHAT IS – GENERALLY – whether material
before tribunal admitted of the conclusion that respondent
-- 1 of 36 --
2
had established ‘exceptional circumstances’ and
‘unreasonable hardship’
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
RECOVERY – where the parties entered into a building
contract for construction of a luxury home – where disputes
arose as to variations and as to the amount payable for the
works – where builder non-compliant with requirements
for contractual variations under the Domestic Building
Contracts Act 2000 (Qld) – whether builder should be
permitted to recover amounts for non-compliant variations
– whether exceptional circumstances– whether
unreasonable hardship
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
CONSTRUCTION OF PARTICULAR CONTRACTS
AND IMPLIED CONDITIONS – VARIATIONS – where
builder non-compliant with requirements for contractual
variations under the Domestic Building Contracts Act 2000
(Qld) – whether liquidated damages payable for delays in
practical completion – whether builder made an application
to adjust completion date under s 18(6) of the Domestic
Building Contracts Act 2000 (Qld)
Domestic Building Contracts Act 1995 (Vic), s 38
Domestic Building Contracts Act 2000 (Qld) s 3, s 7, s 16,
s 18, s 79, s 80, s 81, s 82, s 83, s 84, s 92, s 93, sch 2
Queensland Civil and Administrative Tribunal Act 2009
(Qld) s 142, s 147
Allaro Homes Cairns Pty Ltd v O’Reilly & Anor [2012]
QCA 286
Australian Broadcasting Tribunal v Bond (1990) 170 CLR
321
Better Homes Queensland Pty Ltd v O’Reilly [2012]
QCATA 37
Cachia v Grech [2009] NSWCA 232
Collector of Customs v Agfa-Gevaert Ltd (1996) 186 CLR
389
Collector of Customs v Pressure Tankers Pty Ltd and
Pozzolanic Enterprises Pty Ltd [1993] FCA 322
D A Radic Pty Ltd t/as David Radic Prestige Homes v
Colagrande & Ors [2018] QCAT 112
Ericson v Queensland Building Services Authority [2013]
QCA 391
Glenwood Properties Pty Ltd v Delmoss Pty Ltd [1986] 2
Qd R 388
Hayler v Hart [2013] QCAT 252
Hayes v Federal Commissioner of Taxation (1956) 96 CLR
47
Hope v Bathurst City Council (1980) 144 CLR 1
-- 2 of 36 --
3
Lida Build Pty Ltd v Miller (No 2) [2010] QCAT 431
Mahmudov v Goncalves [2012] QCAT 629
Mann v Paterson Constructions Pty Ltd (2019) 93 ALJR
1164
McIver Bulk Liquid Haulage Pty Ltd v Fruehauf Australia
Pty Ltd [1989] 2 Qd R 577
Piper v Hookham Constructions Pty Ltd [2015] QCATA
77
Poiner v Quirk [2007] QDC 299
QUYD Pty Ltd v Marvass Pty Ltd [2009] 1 Qd R 41
Ross v Rangel [2004] QCCTB 98
Vetter v Lake Macquarie City Council (2001) 202 CLR 439
Applicant: Mr J Faulkner instructed by Barron & Allen Lawyers
Respondent: Mr Hitchcock, solicitor, AJ & Co Lawyers
REASONS FOR DECISION
[1] D A Radic Pty Ltd trading as David Radic Prestige Homes (‘Radic’) built a home for
the applicants. The parties fell into dispute. Radic commenced proceedings in the
Tribunal to recover from the applicants monies it said were due and owing in respect
of the building works. The applicants counter claimed for, among other things,
liquidated damages and negative contractual variations.
[2] The Tribunal ordered the applicants to pay Radic $59,477.83 (the decision).1 The
applicants appeal the decision.
The background to the dispute
[3] The applicants and Radic entered into a contract to construct a new home on the Gold
Coast. The contract price was $2,291,136.00. During the building works it was
decided that the scope of works would be varied by constructing a roof deck structure.
The applicants paid an additional cash amount to Radic in respect of the works. There
was a dispute about the amount of the payment and the amount payable in respect of
the variation works.
[4] The building work commenced on 28 May 2014 and was completed by 18 December
2015 when the building was handed over.
[5] Radic sought payment of a final amount of $191,482.73 at the time of handover. The
amount comprised $114,556.80 being the practical completion stage payment and
$76,925.93 being a combined variation claim and contract adjustment.
1 D A Radic Pty Ltd t/as David Radic Prestige Homes v Colagrande & Ors [2018] QCAT 112.
-- 3 of 36 --
4
[6] The applicants paid the final payment after deducting an amount of $53,047.30 said
to comprise $27,177.63 for a number of variations and $25,250.00 for liquidated
damages.
The statutory framework – appeals to the Appeal Tribunal
[7] An appeal to the Appeal Tribunal on a question of law is as of right.2 An appeal on a
question of fact or mixed law and fact may only be made with the leave of the Appeal
Tribunal.3
[8] If an appeal is one against a decision on a question of fact only or a question of mixed
law and fact, and leave to appeal is granted, the appeal must be decided by way of
rehearing with or without the hearing of additional evidence as decided by the appeal
tribunal.4 In deciding the appeal, the appeal tribunal may confirm or amend the
decision or set aside the decision and substitute its own decision.5
[9] The relevant principles to be applied in determining whether to grant leave to appeal
are: is there a reasonably arguable case of error in the primary decision?;6 is there a
reasonable prospect that the applicant will obtain substantive relief?;7 is leave
necessary to correct a substantial injustice to the applicant caused by some error?;8 is
there a question of general importance upon which further argument, and a decision
of the appellate court or tribunal, would be to the public advantage?9
[10] If an appeal involves a question of law, unless the determination of the error of law
decides the matter in its entirety in the appellant’s favour, the proceeding must be
returned to the tribunal for reconsideration.10
Building disputes – the statutory framework
[11] This appeal involves a consideration of the (repealed) Domestic Building Contracts
Act 2000 (Qld) (‘DBC Act’).11
[12] The stated purpose of the DBC Act is found at s 3:
The purpose of this Act, in regulating domestic building contracts, is –
(a) to achieve a reasonable balance between the interests of building
contractors and building owners; and
(b) to maintain appropriate standards of conduct in the building industry.
2 Queensland Civil and Administrative Tribunal Act 2009 (Qld) (‘QCAT Act’), s 142(1).
3 Ibid, s 142(3)(b).
4 Ibid, ss 147(1), (2).
5 Ibid, s 147(3).
6 QUYD Pty Ltd v Marvass Pty Ltd [2009] 1 Qd R 41.
7 Cachia v Grech [2009] NSWCA 232, [13].
8 Ibid.
9 Glenwood Properties Pty Ltd v Delmoss Pty Ltd [1986] 2 Qd R 388, 389; McIver Bulk Liquid Haulage
Pty Ltd v Fruehauf Australia Pty Ltd [1989] 2 Qd R 577, 578, 580.
10 Ericson v Queensland Building Services Authority [2013] QCA 391.
11 The DBC Act was repealed on 1 July 2015 however the Act continues to apply to domestic building
contracts entered into before the repeal. Accordingly, the provisions of the DBC Act apply to the
dispute the subject of this appeal.
-- 4 of 36 --
5
[13] By s 7(1) of the DBC Act ‘domestic building contract’ includes a contract to carry out
domestic building work. By s 6(2), the ‘contract price’ for a domestic building
contract is the total amount payable under the contract for the contracted services. By
s 6(5), if a contract is varied the reference in s 6(2) to the total amount payable under
the contract is a reference to the total amount payable under the contract, as varied.
[14] The meaning of ‘variation’ is found at s 16 of the DBC Act:
16 Meaning of variation
(1) A variation, of a domestic building contract, is –
(a) an addition of domestic building work to the subject work; or
(b) an omission from the subject work.
(2) However, for a cost plus contract, an addition or omission is a variation
only if the addition or omission is not reasonably contemplated by the
contract.
[15] ‘Subject work’ as referred to in s 16(1) is defined as:12
(a) the domestic building work carried out, being carried out or to be carried
out under the contract; or
(b) the domestic building work the carrying out of which has been, is being or
is to be managed under the contract.
[16] Section 79 deals with the requirement for contractual variations to be in writing:
79 Variations must be in writing
(1) The building contractor under a regulated contract must ensure any
variation of the contract agreed to between the building contractor and
building owner is put into written form –
(a) within the shortest practicable time; and
(b) for a variation consisting of an addition to the subject work—before
any domestic building work the subject of the variation is carried out.
Maximum penalty—20 penalty units.
(2) Subsection (1) does not apply to a building contractor for a variation of a
contract if –
(a) the variation is for domestic building work that is required to be
carried out urgently; and
(b) it is not reasonably practicable, in the particular circumstances, to
produce a variation document before carrying out the work.
(3) Subsection (4) applies if –
12 DBC Act, sch 2 (definition of ‘subject work’).
-- 5 of 36 --
6
(a) a proposed variation of a regulated contract has not yet been agreed to
between the building contractor under the contract and the building
owner, but is proposed to come into existence on the signing of a
variation document by the owner and the contractor; and
(b) the variation document is to be the first and only agreement between
the building contractor and the building owner for the particular
variation.
(4) If the proposed variation consists of an addition to the subject work, the
building contractor must ensure that no domestic building work the subject
of the proposed variation is carried out until the variation document has
been signed.
Maximum penalty—20 penalty units.
(5) When the variation document is signed, the following provisions do not
apply for the variation –
(a) subsections (1) and (2);
(b) section 82;
(c) section 83(1)(b);
(d) section 84(2)(a) and (3)(a)(i), to the extent the provisions concern
sections 82 and 83(1)(b).
[17] Sections 80 and 81 deal with the contents of a variation document. Section 80
provides:
80 General contents of variation document
(1) The building contractor under a regulated contract must ensure a variation
document for the contract complies with the formal requirements for a
variation document. Maximum penalty—20 penalty units.
(2) A variation document complies with the formal requirements for a
variation document if the document –
(a) is in English and is readily legible; and
(b) describes the variation; and
(c) if the variation was sought by the building contractor—states the
reason for the variation; and
(d) if the variation will result in a delay affecting the subject work—states
the building contractor’s reasonable estimate for the period of delay;
and
(e) for a fixed price contract—states the change of the contract price
because of the variation, or how the change of the contract price is to
be worked out; and
(f) for a cost plus contract—states a fair and reasonable estimate of the
costs associated with the addition or omission the subject of the
variation; and
-- 6 of 36 --
7
(g) if the contract provides for progress payments—makes appropriate
provision for payments under the contract to reflect any change of the
contract price caused by the variation.
[18] Sections 82 and 83 deal with the requirements for a variation document to be signed
and a copy given to the building owner:
82 Variation document must be signed
As soon as practicable after an appropriate variation document is made, the
building contractor must—
(a) sign the document; and
(b) take all reasonable steps to try to ensure the document is signed by the
building owner.
83 Copy of variation document for building owner
(1) As soon as practicable (but within 5 business days) after a variation of a
regulated contract is agreed to between the building contractor and building
owner, the building contractor must give the building owner—
(a) a readily legible signed copy of an appropriate variation document for
the variation; or
(b) if acceptable circumstances apply to the building contractor—a readily
legible copy of an appropriate variation document for the variation, signed
by the building contractor.
(2) For subsection (1)(b), acceptable circumstances apply to the building
contractor if the building contractor has taken all reasonable steps to try to
ensure an appropriate variation document for the variation is signed by the
building owner, but the building owner has not signed the document.
[19] Section 84 deals with the recovery by a building contractor of an amount for a
variation and provides:
84 Right of building contractor to recover amount for variation
(1) This section applies if –
(a) the building contractor under a regulated contract gives effect to a
variation of the contract; and
(b) the variation consists of –
(i) an addition to the subject work; or
(ii) an omission from the subject work that results in the building
contractor incurring additional costs.
(2) If the variation was originally sought by the building owner, the building
contractor may recover an amount for the variation –
(a) only if the building contractor has complied with sections 79, 80, 82
and 83; or
-- 7 of 36 --
8
(b) only with the tribunal’s approval given on an application made, as
provided under the QCAT Act, to the tribunal by the building
contractor.
(3) If the variation is not a variation that was originally sought by the building
owner, the building contractor may recover an amount for the variation –
(a) only if –
(i) the building contractor has complied with sections 79, 80, 82 and
83; and
(ii) the ground of unforeseen circumstances applies; or
(b) only with the tribunal’s approval given on an application made, as
provided under the QCAT Act, to the tribunal by the building
contractor.
(4) The tribunal may approve the recovery of an amount by a building
contractor for a variation only if the tribunal is satisfied that –
(a) either of the following applies –
(i) there are exceptional circumstances to warrant the conferring of
an entitlement on the building contractor for recovery of an
amount for the variation;
(ii) the building contractor would suffer unreasonable hardship by
the operation of subsection (2)(a) or (3)(a); and
(b) it would not be unfair to the building owner for the building contractor
to recover an amount.
(5) For subsection (3)(a)(ii), the ground of unforeseen circumstances applies
if the variation became necessary because of circumstances that could not
have been reasonably foreseen by the building contractor when the contract
was entered into.
(6) If the building contractor is entitled to recover an amount for the variation
of a fixed price contract, the amount is –
(a) the increase in the contract price stated, or worked out in the way
stated, in the appropriate variation document for the variation; or
(b) if paragraph (a) does not apply—the cost of carrying out the variation
plus a reasonable profit.
(7) If the building contractor is entitled to recover an amount for the variation
of a cost plus contract, the amount is the amount worked out in the way
stated in the contract.
[20] Part 9 of the DBC Act deals with other matters relating to contracts. Relevant to this
appeal is s 92 which provides:
92 Effect of failure by building contractor to comply with requirement
-- 8 of 36 --
9
Unless the contrary intention appears in this Act, a failure by a building
contractor to comply with a requirement under this Act in relation to a domestic
building contract does not make the contract illegal, void or unenforceable.
[21] Section 18 deals with the completion date under the contract and adjustments to the
completion date where there is variation work that does not comply with a variation
provision.13 Specifically, s 18(6) provides:
If the contract is varied but the building contractor has not complied with a
variation provision for the variation, the stated completion date or period—
(a) must be adjusted to take account of any reduction in the number of days
required to carry out the subject work; and
(b) may, with the tribunal’s approval given on an application made, as
provided under the QCAT Act, to the tribunal by the building contractor, be
adjusted to take account of any additional days required to carry out the subject
work. (emphasis added)
[22] Section 18(10) deals with the approval by the tribunal of an application by a building
contractor to adjust the completion date where there is non-compliant variation work:
The tribunal may give an approval for subsection (6)(b) only if it is satisfied
that—
(a) either of the following applies—
(i) there are exceptional circumstances to warrant an allowance being made
for the additional days;
(ii) the building contractor would suffer unreasonable hardship if an
allowance for the additional days were not made; and
(b) it would not be unfair to the building owner to make an allowance for the
additional days.
[23] Section 93 relevantly provides:
(1) A domestic building contract is void to the extent to which it—
(a) is contrary to this Act; or
(b) purports to annul, exclude or change a provision of this Act.
13 A ‘variation provision’ means ss 79,80, 82 or 83 of the DBC Act.
-- 9 of 36 --
10
The decision at first instance
[24] Relevant to the present appeal the learned member found:
(i) There were nine (9) variations in dispute, each variation having been
requested by the applicants and each variation being a necessary part of
the works;14
(ii) The circumstances of the subject build were relevant when considering
the variations claimed;15
(iii) The applicants and Radic were sophisticated persons with experience in
business at a high level;16
(iv) Radic would suffer hardship by not being paid the amount of $58,927.63,
of which the amount for variations of $40,144.83 was the most significant
part;17
(v) To be not paid for the variations would cause unreasonable hardship to
Radic;18
(vi) The applicants were not arguing that all of the variations which did not
comply with the DBC Act should be disallowed and were seeking to avail
themselves of the provisions of the DBC Act where it suited them and
where they sought to challenge the quantum of the charge for the item and
not the making of the charge for the item in itself;19
(vii) There would be no unfairness to the applicants in having to pay a proper
amount for variations that they requested, had the benefit of, and which
had been properly completed;20
(viii) There were exceptional circumstances to warrant Radic recovering an
amount for variations;21
14 D A Radic Pty Ltd t/as David Radic Prestige Homes v Colagrande & Ors [2018] QCAT 112, [54].
15 Ibid, [60].
16 Ibid.
17 Ibid, [62].
18 Ibid.
19 Ibid, [66].
20 Ibid, [67].
21 Ibid, [68].
-- 10 of 36 --
11
(ix) It would not be unfair to the applicants for Radic to recover for the
variations.22
(x) The contract provided for a completion period of 420 days for the original
contract works;23
(xi) The period of 55 days allowed for in the contract for ‘calculable delays’
did not include delays as a result of variation works;24
(xii) An additional period of 55 days should be allowed for variation works;25
(xiii) The adjusted completion date, allowing for delays, was 21 December
2015;26
(xiv) The applicants had no entitlement to claim liquidated damages.27
The grounds of appeal
[25] The applicants rely upon a number of grounds of appeal.28 Essentially however the
appeal requires the determination of two principal issues:
(i) Whether the learned member correctly applied s 84 of the DBC Act;
(ii) Whether the learned member erred in refusing to allow the applicants’
claim for liquidated damages.
[26] The applicants say that the learned member erred in finding that Radic had established
exceptional circumstances and unreasonable hardship entitling Radic to recover an
amount for variations not complying with s 84 of the DBC Act.
[27] In determining the first issue it is necessary to consider a number of discrete issues
which we will address separately.
Did the learned member correctly apply s 84 of the DBC Act?
[28] Where the DBC Act applies, a building contractor who gives effect to a variation of a
building contract may only recover an amount for the variation if the builder brings
themselves within s 84 of the Act.
[29] A builder may bring themselves within s 84 in two ways.
[30] Firstly a builder may comply with sections 79, 80, 82 and 83 of the Act. These
provisions detail the requirements for compliant contractual variations.
22 Ibid.
23 Ibid, [13], [216].
24 Ibid, [217].
25 Ibid, [220].
26 Ibid.
27 Ibid, [222] - [223].
28 Application for leave to appeal or appeal, filed 9 April 2018.
-- 11 of 36 --
12
[31] Where a builder is non-compliant with those sections, the builder must apply to the
tribunal to recover an amount for the variation. The builder must satisfy the tribunal
that:
(i) There are exceptional circumstances to warrant conferring upon the
builder an entitlement to recover an amount for the variation; or
(ii) The builder would suffer unreasonable hardship if recovery of the amount
was not permitted; and
(iii) It would not be unfair to the building owner for the building contractor to
recover an amount.29
[32] The meaning of ‘exceptional circumstances’ was considered by the Court of Appeal
in Allaro Homes Cairns Pty Ltd v O’Reilly & Anor (‘Allaro’)30 where it was held:
The phrase “exceptional circumstances” is not defined. It is found in an act
whose purpose or object is to achieve a reasonable balance between the interests
of building contractors and building owners and to maintain appropriate
standards of conduct in the industry. It may be vague but the matters that might
be considered relevant to such an inquiry will be indicated by the particular way
in which the Act was not complied with and the circumstances particular to the
dispute. In this Act, it directs attention to those circumstances which are
exceptional and warrant conferring upon the building contractor an entitlement
to recovery for the variation which its conduct, by failing to meet the obligations
imposed by the statute, deprived it. It would therefore suggest, in the context of
this dispute, attention might be directed to the circumstances that applied that
prevented compliance or explained non-compliance with s 80(2)(e), which
required the building contractor to state the change of the contract price because
of the variation or how the change in price might be worked out. Circumstances
such as an unanticipated event requiring work to be done urgently might, for
example, afford an explanation and constitute an “exceptional circumstance”.
But this comment should not be regarded as exhaustive, the term is broad and it
is not desirable to attempt an exhaustive statement of what might be in any given
dispute an exceptional circumstance.31
[33] In Poiner v Quirk McGill DCJ considered the entitlement of a builder to recover for
non-compliant variations which had been requested by the owner:
The Tribunal found that there were no exceptional circumstances surrounding
the claim, and it does not appear from the written submissions on behalf of the
appellant that any exceptional circumstances were even alleged: p 13. Indeed
those submissions do not address the requirements of s 84 at all; they proceed
on the basis that it is sufficient that the work was carried out on instructions
from and with the knowledge of the respondents, which is not enough to satisfy
s 84.32
[34] In Ross v Rangel the meaning of s 84 was considered:
In the use of this terminology the DBC Act must envisage circumstances
somewhat above the normal, that is something out of the ordinary: Fay v Fay
29 DBC Act, s 84(4)
30 [2012] QCA 286.
31 Ibid, [15] (citations omitted).
32 [2007] QDC 299, [73].
-- 12 of 36 --
13
[1982] All ER 922 at 926 per Lord Scarman; Re: Washington [1967] QWN 10
per Hart J.
It is not exceptional (nor can it be in terms of Part 7 and section 84 of the DBC
Act) for a homeowner or, indeed, a builder to raise a variation to the works. It
is a common occurrence. Given that, the legislature sets down a scheme which
is expected/demanded of a builder, if the builder is to be compensated.33
[35] Ross v Rangel has been cited with approval in a number of decisions.34
[36] In Hayler v Hart35 the Tribunal held that the raising of variations was a common
occurrence and not, in itself, exceptional.
[37] In Allaro the Court of Appeal also considered the meaning of ‘unreasonable hardship’:
Turning to the question of “unreasonable hardship”. The evidence before the
Appeal Tribunal was scant but included the contract price, the cost of and
findings with respect to the cost of the variation and the circumstance that the
work had been performed but not paid for. In addition, there was evidence from
the director of the applicant of the turnover of the applicant’s business. Plainly,
it was a substantial building company with a turnover varying over three years
between $11,000,000 and $17,000,000. There was no evidence going to the
consequences for the applicant of non-payment.
The circumstance that a builder might be unpaid for work done does not
necessarily lead to an inference that hardship is suffered. Something more than
non-payment should be demonstrated to establish “unreasonable hardship”
suffered from the operation of the Act. Both the Tribunal and the Appeal
Tribunal concluded that the applicant had demonstrated neither hardship nor
that it was unreasonable. That conclusion is dictated by the evidence in this case
and I can see no error of fact or law in that conclusion.36
[38] In Poiner v Quirk37 McGill DCJ was also required to consider the meaning of
‘unreasonable hardship’:
On the face of it, if this work was required by the respondents, the appellant
simply did not comply with the requirements of the statute. He ought to have
required them to sign a variation before he did the work. There cannot be said
to be unreasonable hardship just because he incurred some additional cost which
33 [2004] QCCTB 98, [64] – [65].
34 See for example, Lida Build Pty Ltd v Miller (No 2) [2010] QCAT 431; Mahmudov v Goncalves [2012]
QCAT 629.
35 [2013] QCAT 252.
36 [2012] QCA 286, [20] – [21].
37 [2007] QDC 299, [74].
-- 13 of 36 --
14
he cannot recover, one would expect that this is precisely what the legislature
intended in such circumstances. There was nothing to indicate that he would
have suffered unreasonable hardship from enforcing the requirement that he
comply with ss 79, 80, 82, and 83. In my opinion, there was no proper basis on
which the Tribunal could have held in the circumstances of this matter that the
appellant had satisfied the requirements of s 84 to recover payment for this
amount, even assuming that the work was carried out on instructions from and
with the full knowledge of the respondents. If the tribunal had found that the
respondents had not requested that this work be done, it seems to me that this
would simply be a further impediment to satisfaction of the requirements of s
84, since I cannot see how in those circumstances the Tribunal could have
concluded that it would not be unfair to the respondents for the appellant to
recover an amount for this work.
[39] In Better Homes Queensland Pty Ltd v O’Reilly38 the QCAT Appeal Tribunal
considered what was required to satisfy ‘unreasonable hardship’:
The test of unreasonable hardship requires an assessment of the impact of that
sanction on the builder in the circumstances in which the noncompliance
occurred. That is both a subjective and an objective enquiry: subjective, in that
evidence must be led to demonstrate hardship to the builder; and objective, in
that the nature and extent of the hardship must be unreasonable in the
circumstances in which it occurs.
The magnitude of the sum that cannot be recovered is a relevant consideration
in both respects. Subjectively, the inability to recover an amount may or may
not cause hardship to the builder, depending on its financial circumstances. A
small sum for a sole operator whose margins are slim might have a greater
financial impact on that builder than a much larger sum would have on an
enterprise with a large turnover and good profit margin.
Objectively, the amount the builder is out of pocket will be one of many possible
factors to consider in determining whether the hardship would be unreasonable.
Other factors include the conduct of each of the builder and the owner in
explaining why the variation was not documented and any discussions they had
about the matter.
[40] In Mann v Paterson Constructions Pty Ltd39 the High Court had this to say regarding
provisions in the Domestic Building Contracts Act 1995 (Vic) analogous to s 84:
The apparent purpose and legislative effect of these provisions is that a builder
shall not be permitted to recover any money in respect of owner-initiated
variations (other than for prime cost items and by way of provisional sums)
except in accordance with these provisions. As such, they function as protective
provisions, designed to prevent the kinds of problems likely to arise where
domestic building contract variations are dealt with informally, as by oral
request by an owner for a variation and compliance by the builder without first
agreeing with the owner on the price and other consequences of giving effect to
the variation; in particular, to avoid the surprises and consequent disputation
likely to arise where plans and specifications under a major domestic building
contract are varied without the degree of formality mandated by s 38(1) and (2)
or (3). Hence, subject to only one exception, they prohibit a builder recovering
any money in respect of owner-initiated variations unless the required degree
38 [2012] QCATA 37, [29] – [31].
39 (2019) 93 ALJR 1164.
-- 14 of 36 --
15
of formality has been observed. The one exception reflects a legislative
recognition that there can sometimes be instances of non-compliance which are
in themselves exceptional or would result in the builder suffering exceptional
hardship and in which it is not unfair to require the owner to pay a reasonable
recompense for the variation, namely, the cost of the variation and a reasonable
profit margin in accordance with s 38(7).40
[41] In the proceedings below, Radic relied upon both limbs of s 84(4)(a) of the DBC Act.
In its amended Application for domestic building disputes Radic said:
12. At all material times the Respondents gave all instructions and
communications for contract work to be performed through the
Male Respondent, who requested the work of the variations,
instructed the work to be performed, but as a practising cosmetic
surgeon asserted that he did not have the time for the administration
and execution of variation documents, and/or failed or refused to
respond to the Applicants documents concerning those variations,
and threatened damages claims for late completion.
13. The conduct of the Respondent leading to completion represented
exceptional circumstances to warrant the conferring of an
entitlement on the building contractor for the recovery of the amount
being that (sic) the reasonable value of the work performed.
14. The Applicant would suffer unreasonable hardship by the operation
of the act (sic), and it is not unfair to the building owner for the
Applicant to recover the amount being the reasonable value of the
work performed on the instruction of the Respondents pursuant to s
84(4) of the Domestic Building Contracts Act 2000, or alternatively
by way of Quantum Meruit.
[42] In their amended response, the applicants neither admitted nor denied that they had
requested the variation works. In his statement of evidence however Dr Colagrande
said that some of the variation works were not instructed by him to be performed.41
[43] Despite the evidence not being entirely clear on the point, it appears from the parties’
written submissions below that it was not disputed that the variation works had been
requested by the applicants.42 The learned member made this finding.43 The finding
is not appealed.
Exceptional circumstances
[44] In their grounds of appeal the applicants say that the learned member erred in finding
that there were exceptional circumstances entitling Radic to recover for the non-
compliant variations. The particulars of this ground, relied upon by the applicants, are:
there was no evidence of exceptional circumstances; no pleading by Radic of
exceptional circumstances; no submissions by Radic as to what constituted the
exceptional circumstances; and no analysis by the learned member of what constituted
exceptional circumstances in the context of the decision.
40 Ibid, 1197 [157] (citations omitted).
41 Exhibit 9, 46(a)
42 Applicants’ submissions at [15] - [35]
43 D A Radic Pty Ltd t/as David Radic Prestige Homes v Colagrande & Ors [2018] QCAT 112, [54].
-- 15 of 36 --
16
[45] The applicants say that as a result of the asserted errors by the learned member, they
were denied procedural fairness.
[46] The applicants say that the learned member failed to properly analyse what constituted
‘exceptional circumstances’. Failing to give adequate reasons is an error of law.
However at the hearing of the appeal, Counsel for the applicants declined to seek an
amendment to the grounds of appeal to include a failure by the learned member to
give adequate reasons.
[47] At the hearing of the appeal, Counsel for the applicants submitted that there was no
evidence, or no probative evidence, upon which the learned member could have been
satisfied that Radic had established exceptional circumstances.
[48] Whether facts fully found fall within the provision of a statutory enactment properly
construed is generally a question of law.44 Where a statute uses words according to
their ordinary meaning and the question is whether the facts as found fall within those
words, where it is reasonably open to hold that they do, then the question whether they
do or not is one of fact.45 If facts fully found are within the spectrum of
reasonableness, the question is a mixed question of fact and law.46 Whether there is
evidence of a particular fact is a question of law. A finding of fact in the absence of
evidence to support the finding is an error of law.47
[49] In Vetter v Lake Macquarie City Council the High Court held:48
Whether facts as found answer a statutory description or satisfy statutory criteria
will very frequently be exclusively a question of law. To put the matter another
way, indeed, as it was put by Priestley JA in his judgment, whether the facts
found by the trial court can support the legal description given to them by the
trial court is a question of law. However, not all questions involving mixed
questions of law and fact are, or need to be susceptible of one correct answer
only. Not infrequently, informed and experienced lawyers will apply different
descriptions to a factual situation. That is why the test whether legal criteria
have been met has been expressed in language of the kind used by Jordan CJ in
The Australian Gas Light Co v Valuer-General:
"[I]f the facts inferred ... from the evidence ... are necessarily within the
description of a word or phrase in a statute or necessarily outside that
description, a contrary decision is wrong in law".
[50] In Hope v Bathurst City Council Mason J held:49
Many authorities can be found to sustain the proposition that the question
whether facts fully found fall within the provisions of a statutory enactment
properly construed is a question of law. One example is the judgment of
Fullagar J in Hayes v Federal Commissioner of Taxation, where his Honour
quoted the comment of Lord Parker of Waddington in Farmer v Cotton's
44 Vetter v Lake Macquarie City Council (2001) 202 CLR 439; Hayes v Federal Commissioner of
Taxation (1956) 96 CLR 47, 51; Collector of Customs v Agfa-Gevaert Ltd (1996) 186 CLR 389, 394
– 395;
45 Collector of Customs v Pressure Tankers Pty Ltd and Pozzolanic Enterprises Pty Ltd [1993] FCA 322.
46 Ibid.
47 Australian Broadcasting Tribunal v Bond (1990) 170 CLR 321.
48 202 CLR 439, 450 [24] (citations omitted).
49 (1980) 144 CLR 1, 7 – 8.
-- 16 of 36 --
17
Trustees, which was adopted by Latham CJ in Commissioner of Taxation v
Miller, that where all the material facts are fully found, and the only question is
whether the facts are such as to bring the case within the provisions properly
construed of some statutory enactment, the question is one of law only. Fullagar
J then said:
'... this seems to me to be the only reasonable view. The distinction between the
two classes of question is, I think, greatly simplified, if we bear in mind the
distinction, so clearly drawn by Wigmore, between the factum probandum (the
ultimate fact in issue) and facta probantia (the facts adduced to prove or
disprove that ultimate fact). The "facts" referred to by Lord Parker ... are the
facta probantia. Where the factum probandum involves a term used in a statute,
the question whether the accepted facta probantia establish that factum
probandum will generally - so far as I can see, always - be a question of law.'
However, special considerations apply when we are confronted with a statute
which on examination is found to use words according to their common
understanding and the question is whether the facts as found fall within these
words. Brutus v. Cozens (1973) AC 854 was just such a case. The only question
raised was whether the appellant's behaviour was "insulting". As it was not
unreasonable to hold that his behaviour was insulting, the question was one of
fact.
The judgment of Kitto J. in N.S.W. Associated Blue-Metal Quarries Ltd. v.
Federal Commissioner of Taxation (1956) 94 CLR 309 is illuminating. Kitto J.
observed that the question whether certain operations answered the description
"mining operations upon a mining property" within the meaning of s. 122 of the
Income Tax Assessment Act 1936, as amended, was a mixed question of law
and fact (1956) 94 CLR, at pp 511-512 . He went on to explain why this was
so: "First it is necessary to decide as a matter of law whether the Act uses the
expressions 'mining operations' and 'mining property' in any other sense than
that which they have in ordinary speech." Having answered this question in the
negative, he noted that the "common understanding of the words has . . . to be
determined" as "a question of fact". He continued (1956) 94 CLR, at p 512 :
"The next question must be whether the material before the Court reasonably
admits of different conclusions as to whether the appellant's operations fall
within the ordinary meaning of the words as so determined; and that is a
question of law (1941) 65 CLR, at p 155 : see also per Isaacs and Rich JJ. in
Australian Slate Quarries Ltd. v. Federal Commissioner of Taxation (1923) 33
CLR 416, at p 419. If different conclusions are reasonably possible, it is
necessary to decide which is the correct conclusion; and that is a question of
fact: see per Williams J. in the Broken Hill South Case (1941) 65 CLR 150, at
p 160 ."
[51] In Vetter v Lake Macquarie City Council the majority held:50
In Hope v Bathurst City Council, Mason J pointed out that when it is necessary
to engage in a process of construction of the meaning of a word (or phrase) in a
statute a question of law will be involved, but that the question may be a mixed
one of fact and law. His Honour's reasons make it clear that a question
exclusively of law arises, as the respondent sought to argue was the position in
this case, if, on the facts found only one conclusion is open.
50 (2001) 202 CLR 439, 451 [27].
-- 17 of 36 --
18
[52] For the reasons that follow we conclude that the learned member erred in law in
finding that, on the facts found, Radic had established exceptional circumstances for
the purposes of s 84(4)(a)(i) of the DBC Act.
[53] The learned member found that the variations had not been signed by the applicants
prior to the work being carried out. He found that the variation documents had been
prepared by Radic on about 7 December 2015 and forwarded to the applicants on 15
December 2015.51
[54] The learned member referred to the relevant provisions of the DBC Act dealing with
contractual variations.52 The learned member found that the applicants had requested
the variation works and that the variations were ‘a necessary part of the requested
works’.53 The latter finding is somewhat opaque however we understand the finding
to mean that the building works performed were necessary to give effect to the
variations. In any event these findings are not appealed.
[55] The learned member then went on to address the total cost of the variations,54 Radic’s
financial circumstances55 and the evidence about the impact upon Radic of the unpaid
variations.56 The learned member referred specifically to Mr Radic’s evidence about
the ‘huge financial burden’ on the builder.
[56] The learned member went on to consider the test for establishing unreasonable
hardship, referring to Better Homes Queensland Pty Limited v O’Reilly & Anor.57 The
learned member referred to the following circumstances of the construction as being
‘relevant’:
(a) The building works involved a very expensive architect designed luxury house;
(b) The house was built for a professional person by an experienced builder of
luxury homes on the Gold Coast;
(c) The parties were sophisticated persons having experience in business at a high
level.58
51 D A Radic Pty Ltd t/as David Radic Prestige Homes v Colagrande & Ors [2018] QCAT 112, [46].
52 Ibid, [51] – [53].
53 Ibid, [54].
54 Ibid, [55].
55 Ibid, [56].
56 Ibid, [57] – [58].
57 Ibid, [59].
58 Ibid, [60].
-- 18 of 36 --
19
[57] The learned member did not explicitly state whether the matters to which he referred
were relevant to exceptional circumstances, unreasonable hardship or both.
[58] The learned member observed that Radic’s apparently high annual profit based simply
on turnover and a supposed margin did not show that Radic would not suffer hardship
by not being paid the variations. The learned member then speculated about various
matters that might impact Radic’s financial position.59
[59] The learned member went on to find that Radic would suffer unreasonable hardship
if it was not paid for the variations.60
[60] The learned member considered whether it would be unfair to the applicants for Radic
to be paid for the variations, concluding that it would not be.61 This finding is not
appealed.
[61] The learned member found that both limbs of s 84(4)(a) had been made out by Radic.62
The relevant finding by the learned member in relation to exceptional circumstances
is found in the following passage:
I therefore consider that the requirements of section 84 of the DBC Act are made
out:- that there are exceptional circumstances to warrant the conferring of an
entitlement on the builder for recovery of an amount for variations; that the
builder would suffer unreasonable hardship if the variations were not paid for;
and that it would not be unfair to the owners for the builder to recover for the
variations.63
[62] The ‘exceptional circumstances’ relied upon by Radic in its amended application was
the following conduct of the Colagrandes:
(i) Requesting the work of the variations;
(ii) Instructing the work to be performed;
(iii) Failing and/or refusing to respond to the applicants’ ‘documents’
concerning the variations;
(iv) Threatening the applicants with a claim for damages for late completion.
59 Ibid, [61].
60 Ibid, [62].
61 Ibid, [63] – [67].
62 Ibid, [68].
63 Ibid.
-- 19 of 36 --
20
[63] In his statement of evidence filed in the proceedings below, Dr Colagrande said that
he did not instruct the performance of some of the works the subject of the
variations.64 In cross examination at the hearing, Dr Colagrande was asked a series of
questions about whether he had requested the performance of the variation works. Dr
Colagrande’s evidence in this regard was somewhat equivocal.
[64] The evidence of Mr Radic was that there were exceptional circumstances applying in
respect of the variation works. He stated that ‘a lot of the work’ happened ‘in the last
few weeks of the job’.65 Mr Radic’s evidence, when asked why the variations were
not documented, was that his wife ‘… does all that side of the work, to be honest.’66
Mr Radic said that he was ‘not 100 per cent sure’ whether a variation document was
required to be issued prior to the commencement of the variation works. Somewhat
tellingly, the evidence of Mr Radic was:
We’ve always had the understanding that if a client asks for something and it’s
– it’s on a text or some, you know, written – it’s somewhere, then it forms the
basis for you to do the work. If – and the majority of people we deal with or – I
could say pretty much all of them bar one have been happy to operate that way.67
[65] The evidence of Mr Radic was that the variation works were undertaken at the request
of Dr Colagrande.68 He stated that some of the variation works were ongoing at the
time the variations were submitted by Radic to the applicants.69 Mrs Radic’s evidence
was that the variation works were commenced prior to the variations being submitted
to the applicants ‘but a lot of them weren’t completed until close to the date of the
7 th .’70
[66] Mr Radic gave evidence regarding the circumstances relevant to the variations.71
There was no evidence by Radic’s witnesses that the variation works were required to
be carried out urgently thus rendering compliance with the requirements of the DBC
Act not possible, impractical or otherwise explicable.
[67] Circumstances involving a request by a building owner to have variation works
carried out and instructing the builder to carry out the works will not, generally
64 Statement of Ces Colagrande, dated 20 January 2017, [46].
65 Transcript of Proceedings, D A Radic Pty Ltd t/as David Radic Prestige Homes v Colagrande & Ors
(QCAT BDL118-16, Member Paratz, 29 March 2017) 59.
66 Ibid, 60.
67 Ibid, 61.
68 Ibid, 95.
69 Ibid, 111.
70 Ibid, 10.
71 Statement of David Radic, dated 29 June 2016, [112] – [154]; Supplementary statement of David
Radic, dated 14 February 2017, [12] - [30].
-- 20 of 36 --
21
speaking and without more, be exceptional where there is non-compliance with the
requirements of s 84 of the DBC Act. The evidence of Radic was that it only built
luxury homes of the type constructed for the applicants. Mr Radic’s evidence was that:
We solely build luxury homes of this type. Owners are spending a lot of money
on a dream home. We therefore work with the owners and accept them changing
their minds and last minute changes.72
[68] The evidence would certainly suggest that variations were not uncommon in the
context of the nature of the building work performed by Radic. It goes without saying
that Radic should have been aware of the requirements of the DBC Act regarding
variation works.
[69] The evidence about whether the applicants threatened Radic with a claim for damages
for late completion can be found in Mr Radic’s statement:
In a telephone call on the 17 (sic) December 2015 of December 2015 (sic) he73
threatened that if it was not handed over for Christmas he would sue me for
huge damages and we wouldn’t get a cent from him of our final payment.74
[70] It is difficult to apprehend how a conversation that took place after the variation
documents had been submitted could be relevant to a consideration of exceptional
circumstances.
[71] Radic asserted that the applicants had not responded to the ‘documents’ concerning
the variations. This appears to be a reference to the variation documents prepared by
Radic on or about 7 December 2015 and received by the applicants on or about 15
December 2015. Again, it is difficult to apprehend how the failure by the applicants
to provide written approval for the variations at such a late stage of the build could be
relevant to exceptional circumstances.
[72] As the Court of Appeal observed in Allaro one might expect the evidence regarding
‘exceptional circumstances’ to be directed to the circumstances preventing
compliance or explained non-compliance with s 80(2)(e), requiring the building
contractor to state the change of the contract price because of the variation or how the
change in price might be worked out. The relevant provisions of the DBC Act are
protective in nature and, as was observed by the High Court in Paterson, designed to
prevent the kinds of problems likely to arise where variations are dealt with
informally, and to avoid the disputes likely to arise where variations are undertaken
without the formality required by the Act.
[73] It is appropriate to briefly consider the variations and whether there was evidence to
support a finding that there were exceptional circumstances warranting conferral upon
Radic an entitlement to recovery. In particular it is appropriate to consider whether
there was evidence about particular circumstances preventing compliance or
explaining non-compliance with the Act including for example work required to be
undertaken urgently as a result of an unanticipated event.
[74] We confine our consideration to those variations allowed by the learned member.
72 Statement of David Radic, dated 14 February 2017, [41].
73 Dr Colagrande
74 Statement of David Radic, dated 29 September 2016, [36].
-- 21 of 36 --
22
Porcelain sheet
[75] The learned member’s findings in relation to this item are found at reasons [71] to
[89]. The applicants advised the builder in August 2015 that they wanted to use
porcelain sheets in the living room and main ensuite. The applicants ordered the sheets
on 29 October 2015 which were delivered to site on 12 November 2015. The laying
of the sheets was completed on 4 December 2015.75 There is no evidence by Mr Radic
about why the variation provisions of the DBC Act were not, and could not have been,
complied with by the builder. The learned member allowed the variation in the
amount of $17,616.50. There was no evidence of exceptional circumstances relating
to this variation.
Tap install
[76] The learned member’s findings in relation to this item are found at reasons [93] to
[94]. The builder installed 3 zip taps. Mr Radic’s evidence was that the applicants
supplied the taps. There is no evidence by Mr Radic about why the variation
provisions of the DBC Act were not, and could not have been, complied with by the
builder. The learned member allowed the variation in the amount of $330.00. There
was no evidence of exceptional circumstances relating to this variation.
Insinkerator install
[77] The learned member’s findings in relation to this item are found at reasons [95] to
[96]. Mr Radic’s evidence was that the applicants instructed the builder to supply and
install five insinkerators. The applicants provided these instructions in August 2015.
There is no evidence by Mr Radic about why the variation provisions of the DBC Act
were not, and could not have been, complied with by the builder. The learned member
allowed the variation in the amount of $475.00. There was no evidence of exceptional
circumstances relating to this variation.
Doors vestibule
[78] The learned member’s findings in relation to this item are found at reasons [97] to
[98]. Mr Radic’s evidence was that the applicants instructed him to install a wall and
door not included on the plans and to ‘charge [the applicants] at a later date’.76 The
learned member allowed the variation in the amount of $420.00. The obligations
contained in the DBC Act relating to variations are cast upon the builder. That a
homeowner may advise a builder to raise a charge for a variation at a later date does
not, without more, constitute exceptional circumstances. There was no evidence of
exceptional circumstances relating to this variation.
Plumbing labour
[79] The learned member’s findings in relation to this item are found at reasons [99] to
[100]. Mr Radic’s evidence was that the applicants decided in June 2015 to include
additional rooms in the basement of the building. Plans were drawn up and provided
to the builder in July 2015. Mr Radic’s evidence was that in July 2015 the applicants
agreed to the variation works being charged, essentially, on a cost plus basis.77 Mr
75 Statement of D Radic at 96 - 98
76 Statement of D Radic at 123 – 124.
77 Statement of D Radic at 125 – 126.
-- 22 of 36 --
23
Radic says that the applicants dispute only the plumbing labour cost. The learned
member allowed the variation in the amount of $5,880.33. For the reasons outlined
in relation to the ‘doors vestibule’ item, there was no evidence of exceptional
circumstances relating to this item.
Extra render
[80] The learned member’s findings in relation to this item are found at reasons [101] to
[102]. Mr Radic’s evidence was that during the construction of the concrete block
boundary fences the applicants instructed the builder to increase the overall height of
the fence by 200mm. The evidence of Mr Radic was that the applicants provided these
instructions while the trades were on site and that a variation could not be processed
before the work was done.78 The evidence of Dr Colagrande was that the builder was
not instructed to undertake the works.79 The learned member allowed the variation in
the amount of $2,134.00.
[81] Notwithstanding the instructions provided by the applicants it was open to the builder
to comply with the obligations imposed by the DBC Act. There is no evidence to
suggest, for example, that the work was required to be undertaken as a matter of
urgency. Rather it seems that the decision not to comply with the variation provisions
was born of expediency and convenience. There was no evidence of exceptional
circumstances relating to this item.
Stainless steel grate
[82] The learned member’s findings in relation to this item are found at reasons [103] to
[104]. Mr Radic’s evidence was that this variation, relating to changes to garden beds,
was necessitated following instructions provided by the applicants in August 2014.
Mr Radic’s evidence is that, following receipt of the applicants’ instructions, he
advised the applicants that additional drainage would be required. Mr Radic advised
the applicants that the cost of the variation would be on a cost plus basis. He says that
this was agreed to by the applicants.80 The learned member allowed the variation in
the amount of $4,290.00.
[83] There is no evidence by Mr Radic about why the variation provisions of the DBC Act
were not, and could not have been, complied with by the builder. It is, in our view, no
satisfactory answer for the builder to assert that the applicants accepted a credit
relating to the variation works but dispute the claim by the builder. As we have
78 Statement of D Radic at 130 – 131.
79 Statement of C Colagrande at 81
80 Statement of D Radic at 133 – 135.
-- 23 of 36 --
24
observed, the onus is upon the builder to comply with the variation provisions. There
was no evidence of exceptional circumstances relating to this item.
Blockwork raised
[84] The learned member’s findings in relation to this item are found at reasons [105] to
[106]. Mr Radic’s evidence was that, at the request of the applicants, additional block
work was added to raise a window. Mr Radic said that he advised the applicants that
the block layers would be required to return to the site to undertake the work and that
the applicants would be charged the cost in this regard. As with a number of the
disputed variations the builder says that the applicants agreed to this.81 The evidence
of Dr Colagrande was that the builder was not instructed to undertake this work.82 The
learned member allowed a variation of $252.00 for this item. Again, there is no
evidence by Mr Radic about why the variation provisions of the DBC Act were not,
and could not have been, complied with by the builder. There was no evidence of
exceptional circumstances relating to this item.
Aluminium louvre
[85] The learned member’s findings in relation to this item are found at reasons [107] to
[108]. The evidence of Mr Radic was that the applicants requested that the fence be
reconfigured and that an additional fence be added for privacy reasons. The request
by the applicants was made in August 2014. Mr Radic says that the applicants
provided the design for the screens ‘around 10 November 2015’. Attached to Mr
Radic’s statement is an invoice dated 27 November 2015 in respect of the manufacture
of the screens. The learned member allowed a variation of $1,753.00 for this item.
While this work may be have been undertaken relatively late in the build, there was
no evidence that the builder could not have obtained a quote for the cost of the
manufacture of the screens and submitted variation documents to the applicants. There
was no evidence of exceptional circumstances relating to this item.
Tiling play area
[86] The learned member’s findings in relation to this item are found at reasons [109] to
[110]. The learned member allowed an amount of $2,495.00 for this variation. There
was no evidence given by the builder about this variation. There was no evidence of
exceptional circumstances relating to this item.
Stone column
[87] The learned member’s findings in relation to this item are found at reasons [111] to
[112]. Mr Radic’s evidence was that in November 2015 the applicants requested the
installation of stone over two columns in the living room. Mr Radic’s evidence was
that this occurred ‘only a couple of weeks away from the handover’. Mr Radic says
that he told the applicants that the amount charged by the tiler for laying the stone
would be charged to the applicants and that the applicants agreed to this.83 The amount
allowed by the learned member for this variation was $924.00. As with the variation
relating to the aluminium louvre, while this variation work may be have been
undertaken relatively late in the build, there is no evidence that the builder could not
81 Statement of D Radic at 138 – 139.
82 Statement of C Colagrande at 81
83 Statement of D Radic at 146.
-- 24 of 36 --
25
have obtained a quote for the cost of laying the stone and submitted variation
documents to the applicants. There was no evidence of exceptional circumstances
relating to this item.
Plumbing, splashback
[88] The learned member’s findings in relation to this item are found at reasons [113] to
[116]. The learned member allowed a total of $2,621.00 for these variations. There
was no direct evidence given by Mr Radic in relation to these variations. There was
no evidence of exceptional circumstances relating to these items.
BBQ fabricated frame, benchtop frame, fabricated counter frame
[89] The learned member’s findings in relation to this item are at reasons [121] to [128].
The learned member did not allow the claimed variations for the benchtop frame and
fabricated counter frame. These findings are not disputed. In relation to the BBQ
fabricated frame the evidence of Mr Radic was that this variation was requested by
the applicants in various emails dated 2 November 2015, 3 November 2015 and 11
November 2015. The learned member allowed $2,805.00 for the variation. Again,
and as with the variation relating to the aluminium louvre and the stone column, the
variation work was undertaken late in the build, however there is no evidence that the
builder could not have obtained a quote for the cost of the work and provided variation
documents to the applicants. There was no evidence of exceptional circumstances
relating to this item.
Door handle
[90] The learned member’s findings are at reasons [129] to [130]. The evidence of Mr
Radic was that the request for this variation was not made by the applicants until 27
November 2015 and the manufacturer’s invoice was not provided until 8 December
2015.84 The learned member allowed $1,309.00 for the variation. The hand over was
arranged to take place on 18 December 2015. We accept that the request for the
variation work was made late in the build. However the response by the builder was
consistent with all of the variation works. That is, the builder did not attempt to
comply with the variation provisions notwithstanding that there was an opportunity,
albeit a limited one, to do so. There was no evidence by the builder regarding why the
variations provisions could not be complied with. There was no evidence of
exceptional circumstances relating to this item.
Robinhood iron
[91] The relevant findings are at reasons [131] and [132]. The evidence of Mr Radic was
that the applicants requested the installation of an ironing centre on 1 December 2015.
Mr Radic’s evidence was that he advised the applicants he would purchase the item
and add the cost to the final variations.85 The learned member allowed $360.00 for
this item. There was no evidence of exceptional circumstances in relation to this item.
Summary of the evidence in relation to exceptional circumstances
84 Statement of D Radic at 150
85 Statement of D Radic at 151
-- 25 of 36 --
26
[92] The evidence did not support the conclusion that there were exceptional circumstances
to warrant conferring upon Radic an entitlement to recover amounts for any of the
disputed variations. The builder made no attempt to comply with the variation
provisions of the DBC Act. In undertaking the variation works in the absence of
compliance with the Act, Radic proceeded at its peril.
[93] The evidence to which the learned member referred in the reasons went to the issue
of unreasonable hardship rather than exceptional circumstances. Indeed, the learned
member’s reasons are limited in their consideration of the relevant issues to
unreasonable hardship.86 There was no analysis by the learned member of the
principles relevant to the determination of whether there were exceptional
circumstances for the purposes of s 84(4)(a)(i) of the DBC Act nor do the reasons
reveal how the learned member came to conclude that there were exceptional
circumstances in relation to the variation works.
[94] The evidence before the learned member did not, in our view, reasonably admit of
different conclusions as to whether the circumstances relied upon by Radic were
exceptional circumstances. In our view only one conclusion was open on the facts.
That conclusion was Radic had failed to establish exceptional circumstances. A
question exclusively of law arises if, on the facts, only one conclusion is open. We
find that the learned member erred in law in finding that exceptional circumstances
applied for the purposes of s 84(4)(a)(i) of the DBC Act.
Unreasonable hardship
[95] The applicants say, in relation to the finding that Radic would suffer unreasonable
hardship if it was not permitted to recover for the variations: there was no evidence to
support the finding; the learned member failed to apply the correct legal test; the
learned member reversed the onus of proof.
[96] The relevant finding by the learned member regarding unreasonable hardship is found
in the following passage:
The mere fact that the builder appears to make a high annual profit based simply
on turnover and a supposed margin does not show that the builder would not
suffer hardship by not being paid for variations in the amount of $40,144.83.
The builder may have debt obligations, or there may be many other factors that
impact upon its overall financial position.
I accept the evidence of Mr and Ms Radic that the builder would suffer hardship
by not being paid the amount of deducted amount of the final claim for
86 D A Radic Pty Ltd t/as David Radic Prestige Homes v Colagrande & Ors [2018] QCAT 112, [54] –
[70].
-- 26 of 36 --
27
$58,927.63, of which the amount for variations of $40,144.83 is the most
significant part, and consider that to be not paid for the variations would cause
unreasonable hardship in the circumstances.87
[97] The evidence before the learned member about the financial hardship Radic would
suffer if not permitted to recover an amount for the non-compliant variations was
limited.
[98] In his statement of evidence Mr Radic said:
Because we are a small business and operate on small profit margins the $59k
that we have not been paid has been a huge financial blow to us and burden on
our family as we have 2 small children under the age of 7.88
[99] Perhaps unsurprisingly, in light of Radic’s evidence in chief and the paucity of
evidence about financial circumstances, Mr Radic was not cross-examined about the
financial hardship the company would suffer if recovery of the amounts for the
variations was not approved.
[100] In her statement of evidence Mrs Radic said:
We did not accept the payment of $138,435.43 on 18 December 2015 as full
and final payment. Mr Colagrande did not say that and the money was not given
to us on that basis. What he actually said was that he had been advised we could
not refuse hand over if he paid that amount. He proceeded to tell us if we have
an issue with the final payment he was making, then we would have to pursue
it through QCAT. We said to Mr Ces Colagrande that we would be pursuing the
balance owing, through QCAT. He said “we have lots of information about you,
my father was on site all the time, he saw what went on here, we have lots of
evidence, we will have a big counterclaim, my barristers will deal with you, and
you won’t get a cent.” It was a tense and heated meeting. Ces Colagrandes (sic)
father was also present at the time and said to us “You think you’re smarter than
us, but you aren’t and you will never beat us.” The last words said by us as we
left the meeting were, we will see you in the tribunal. We would never accept
this a (sic) final business as we are such a small business and cannot afford to
be out of pocket $59k. This has been a huge financial burden on us and caused
a lot of stress for me and my family. (emphasis added) 89
[101] Mr Radic gave evidence at the hearing about the respondent’s financial circumstances:
87 Ibid, [61] – [62].
88 Statement of David Radic, dated 29 September 2016, [30].
89 Statement of Natasha Radic, dated 29 September 2016, [9].
-- 27 of 36 --
28
Mr Ledger: So you’re doing pretty – you did pretty well 2014/15 year,
didn’t you? And you’re doing pretty well now?
Mr Radic: Nothing’s really changed in my life. We just continue on.
We pay our bills and we keep working. Yep.90
[102] Mr Radic was asked a series of questions about the company’s turnover. The solicitor
for the applicant, addressing the Tribunal during cross examination, said:
And, as you know, part of the Act provides that, as a test, he needs to be
suffering financial hardship, and he’s clearly not. He’s clearly not suffering
financial hardship. It’s one of the requirements under section 84(4), I think it
is.91
[103] There can be no doubt that the parties were, in the proceedings below and at the
hearing, well and truly alive to the issues regarding whether Radic would suffer
unreasonable hardship as a result of the application of s 84(2)(b) of the DBC Act.
[104] Evidence was given at the hearing by both Mr and Mrs Radic about the financial
affairs of the company. Mr Radic gave evidence that in the 2014/15 financial year, ‘it
could be’ correct that the company had a turnover of $5,707,070.92 When asked
whether in the 2016/17 financial year the company turnover would be $12,851,618
Mr Radic’s evidence was that this figure was correct.93 Mr Radic’s evidence was that
‘turnover is not profit’94. Mr Radic gave evidence that the company’s margin averaged
15 per cent.
[105] Mrs Radic gave evidence that the company held a category 2 builder’s licence which
‘allowed’ the company to ‘perform’ a turnover of between ‘3 million and up to 12
million during the 2016 and 2017 year.’95 Mrs Radic gave evidence that the turnover
of the company was ‘in the millions’ but questioned the relevance of this fact stating
that ‘(t)urnover and profit…has no relevance to each other’.96 Regarding the
company’s profit margin, Mrs Radic’s evidence was that the amount varied, that it
‘can be less generally’ than 15 per cent97 and was ‘far less’ than 15 per cent on the
subject contract.98
[106] There is evidence about the contract price and the cost of the variations and the
circumstances in which the work had been performed but not paid for. The learned
member made findings about these matters.
[107] As in Allaro, there is some evidence from Mr and Mrs Radic of the turnover of the
business although this was evidence given under cross examination and Radic filed
no statements of evidence or supporting documentation addressing the issue. The only
evidence going to the consequences for Radic of non-payment for the variations is
90 Transcript of Proceedings, D A Radic Pty Ltd t/as David Radic Prestige Homes v Colagrande & Ors
(QCAT BDL118-16, Member Paratz, 29 March 2017) 65.
91 Ibid, 63.
92 Ibid, 63.
93 Ibid, 63.
94 Ibid, 63.
95 Transcript of Proceedings, D A Radic Pty Ltd t/as David Radic Prestige Homes v Colagrande & Ors
(QCAT BDL118-16, Member Paratz, 20 July 2017), 8.
96 Ibid, 8.
97 Ibid.
98 Ibid, 9.
-- 28 of 36 --
29
found in the statements by Mr and Mrs Radic to which we have referred which was
limited to the assertion that the consequences of the non-payment of the amount for
the variations was ‘a huge financial burden’ and ‘a huge financial blow’.
[108] Radic was required to satisfy the tribunal that, subjectively, it would suffer hardship
if recovery for the variations was not approved and that, objectively, the nature and
extent of the hardship was unreasonable in the circumstances.
[109] There was no evidence before the learned member about whether the inability to
recover the amount may or may not have caused hardship to Radic other than the very
brief statements by Mr and Mrs Radic. Radic led no other evidence about the impact
upon it of the non-payment of the variation amounts. In our view, the bare statement
by a builder that non-payment of an amount for a non-compliant variation will result
in a ‘huge’ financial burden or blow, without more, is not capable of satisfying the
requirements of s 84(4)(a)(ii) of the DBC Act.
[110] The learned member observed that the builder may have debt obligations, or there
may be many other factors that impacted upon its overall financial position. There
was, however, no evidence before the Tribunal about these matters.
[111] The learned member considered the circumstances of the construction to be relevant
including that the build involved a luxury house and the builder and applicants were
sophisticated persons with experience in business at a high level. It is not immediately
apparent from the reasons how these matters could be relevant to the consideration of
unreasonable hardship. The learned member, after citing a passage from the decision
of the QCAT Appeal Tribunal in Better Homes Queensland Pty Limited v O’Reilly &
Anor, held:99
Objectively, the amount the builder is out of pocket will be one of many possible
factors to consider in determining whether the hardship would be unreasonable.
Other factors include the conduct of each of the builder and the owner in
explaining why the variation was not documented and any discussions they had
about the matter.
[112] The Appeal Tribunal in Better Homes clarified what circumstances, objectively, may
be relevant in determining whether unreasonable hardship had been made out. These
circumstances included the amount the builder is out of pocket and the conduct of
each of the builder and the owner in explaining why the variation was not documented
and any discussions they had about the matter. These were not matters referred to by
the learned member.
[113] The relevant findings of fact by the learned member regarding unreasonable hardship
are limited to a finding that the builder would suffer unreasonable hardship if not
permitted to recover an amount in respect of the variations.100 The learned member
made no findings about how or why such hardship would be suffered. It is implicit in
the reasons that the learned member accepted the evidence of Mr and Mrs Radic about
the consequences of the non-payment of the amount for the variations. However, as
we have observed, the mere assertion by a builder that hardship will be suffered if
99 D A Radic Pty Ltd t/as David Radic Prestige Homes v Colagrande & Ors [2018] QCAT 112, [59]
(citations omitted).
100 Ibid, [61] – [62].
-- 29 of 36 --
30
recovery of an amount for non compliant variations is not permitted will be
insufficient to satisfy the requirements of s 84(4)(a)(ii) of the DBC Act.
[114] In our view, the material before the Tribunal below did not reasonably admit of
different conclusions as to whether Radic had established unreasonable hardship. The
only conclusion open on the facts was that Radic had failed to establish that it would
suffer unreasonable hardship if it was not permitted to recover an amount for the non-
compliant variations.
[115] The learned member erred in law in so finding.
Unfairness
[116] In light of our findings, it is not necessary for us to deal with whether the learned
member erred in finding that it would not be unfair to the applicants for Radic to
recover an amount for the non-compliant variations. However for the sake of
completeness we will address the ground of appeal.
[117] The learned member found:
64 The owners clearly have significant financial means and have increased the
cost of the home as the works progressed (for example, by adding an entire roof
deck that was not in the initial plans). There is no evidence that proper payment
by the owners, for the benefit they have received from the variation works being
completed at their request, would place them under financial stress, or be unfair
to them.
65 The owners agreed to pay, and did pay on handover, for some variations that
were not the subject of signed variations. They have selected some other
variations which they have chosen to dispute, not as to their being requested or
as to adequate performance, but only as to quantum. They have paid substantial
moneys (either $160,000.00 or $165,000.00) for the roof deck without any
written variations being signed.
66 The owners therefore are not arguing that all of the variations which were
not signed should be disallowed – rather they have paid, and do not question,
some items, but object to paying others. The owners are thereby seeking to avail
themselves of the provisions of the DBC Act where it suits them, but do not
seek to do so where it does not suit them, and where they in reality wish to
challenge the quantum of the charge for the item, not the making of the charge
for the item in itself.
67 I do not consider that there would be any unfairness to the building owners
in having to pay a proper amount for variations that they have requested, that
they have the benefit of, and which have been properly completed, in all the
circumstances.101
[118] The applicants say that the learned member erred in finding that it would not be unfair
to them to be required to pay for the non-compliant variations. Their principal
complaint is that, as the learned member erred in finding that Radic had established
exceptional circumstances and unreasonable hardship, he could not go on to find as
he did in relation to s 84(4)(b) of the DBC Act.
101 Ibid, [64] – [67].
-- 30 of 36 --
31
[119] The applicants say that the findings by the learned member at reasons 64 and 67 were
not relevant factors in considering whether unfairness was established and that the
learned member engaged in speculation as to the applicants’ financial circumstances.
[120] We accept that there was no direct evidence before the learned member as to the
financial circumstances of the applicants. It is relevant however that the building
project involved a luxury home of substantial proportions and particular
specifications. It is also relevant that the contract price was in excess of two million
dollars and that the contract was not subject to finance. The male applicant was a
cosmetic surgeon operating a medical clinic. The applicants made a significant cash
payment in the order of $160,000 to the builder for a non-compliant variation. These
matters all pointed to the applicants’ financial standing.
[121] There was no error by the learned member in taking into consideration that the
applicants had requested the variation works. Whether variation works have been
requested by a building owner is relevant in considering whether it would be unfair to
permit recovery of an amount for the variation. It was also relevant for the learned
member to take into consideration that the applicants had not disputed other non-
compliant variations particularly in circumstances where the learned member found
that the variations, the subject of the dispute, had been requested by the applicants. As
we have observed, this finding is not challenged on appeal.
[122] We find no error by the learned member.
The liquidated damages claim
[123] The learned member found:
(a) The contract provided for a completion period of 420 days for the original
contract works;102
(b) The period of 55 days allowed for in the contract for ‘calculable delays’ did not
include delays as a result of variation works;103
(c) An additional period of 55 days should be allowed for variation works;104
(d) The adjusted completion date, allowing for delays, was 21 December 2015;105
(e) The applicants had no entitlement to claim liquidated damages.106
[124] The applicants say that the learned member erred in not allowing the liquidated
damages claim and say that:
(a) Radic did not make an application pursuant to s 18(6) of the DBC Act;
(b) Radic did not satisfy the requirements of s 18(10) of the DBC Act.
102 Ibid, [13], [216].
103 Ibid, [217].
104 Ibid, [220]
105 Ibid.
106 Ibid, [222] – [223].
-- 31 of 36 --
32
[125] The applicants’ written submissions raise a further ground of appeal: the learned
member erred in failing to consider that an extension of time under the contract
required the builder to adopt the process set out under the contract.
[126] To the extent that it is necessary to do so, and in the absence of any objection by the
respondent, we give leave for the applicants to amend their grounds of appeal to
include the further ground.
[127] The learned member observed that the matter concerned disputes as to variations and
liquidated damages.107 He referred to the relevant contractual provision relating to
liquidated damages.108 The learned member referred to the claim by the applicants for
liquidated damages as articulated in their closing submissions.109
[128] It is apparent from the reasons that the learned member found 55 business days was
an appropriate assessment in respect of the time required for the builder to undertake
the variation works.110 That finding is not appealed.
[129] The contract provided that if the builder failed to achieve practical completion by the
date specified in the contract, the builder was required to pay the owners liquidated
damages at the rate of $250 per day.111 The contract stated the completion period for
calculating the date for practical completion.112 By clause 13 of the contract the
builder was required to achieve practical completion by the date for practical
completion or ‘any extended date under Condition 14 or under Condition 7.’113
[130] Condition 14 of the contract dealt with extensions of time of the date of practical
completion. The contract provided that if the builder wished to claim an extension of
time for practical completion, the builder was required to give to the owners a QBCC
Form 2 with the particulars completed ‘or other written notice’. The notice was
required to:
(a) be given within 10 business days of the occurrence of the relevant cause of
delay;
(b) identify the cause of the delay;
107 Ibid, [23].
108 Ibid, [15].
109 Ibid, [21].
110 Ibid, [219].
111 QBCC New Home Construction Contract, dated 21 May 2014, cl 19, sch, item 12.
112 Ibid, sch, item 6.
113 Ibid, cl 13.1.
-- 32 of 36 --
33
(c) state the period of the extension of time claimed;
(d) attach supporting documents.114
[131] The owners were required to respond to the claim within 10 business days of receipt
by giving a written notice either accepting the claim or rejecting the claim, with
reasons.115
[132] In their amended response the applicants said that Radic had failed to complete the
building work within the time stipulated in the contract116 thus entitling them to
recover liquidated damages.117 In its amended response and reply, Radic said that the
time for practical completion had been extended by express agreement ‘and/or’ the
(applicants) seeking additional work.118
[133] The learned member considered whether the unsigned variations, which he had
allowed, should be given a time allowance.119 The learned member referred to the
contract in determining that the contract provided for a period of 420 days for
construction of the work from the commencement on 28 May 2014 which ended on
22 July 2015.120 The learned member found that Radic was seeking ‘a further 55
business days allowance for the unsigned variations.’121 The learned member allowed
the additional 55 business days for the unsigned variations.
[134] The applicants say that the learned member erred in not considering the relevant
provisions of the contract and, if he had, the absence of compliance by Radic with the
terms of the contract relating to extensions of time meant that the date for practical
completion could not have been extended. In addition, the applicants rely upon s 18
of the DBC Act and say that Radic did not comply with the requirements of the Act.
[135] Radic says that it is clear the learned member extended time under the statutory power
conferred by the DBC Act and not under the contract.
[136] It is not clear from the reasons the precise basis upon which the learned member
undertook consideration of the applicant’s entitlement to liquidated damages. The
114 Ibid, cl 14.4.
115 Ibid, cl 14.5.
116 Amended response, dated 5 October 2016, [28].
117 Ibid, [31].
118 Amended response and reply, dated 17 October 2016, [1].
119 D A Radic Pty Ltd t/as David Radic Prestige Homes v Colagrande & Ors [2018] QCAT 112, [214].
120 Ibid, [215].
121 Ibid, [219].
-- 33 of 36 --
34
learned member does not refer in the reasons to the relevant contractual provisions or
to s 18 of the DBC Act.
[137] The evidence before the learned member was that the extension of time claim form
stipulated by the contract was not provided by Radic to the applicants until 15
December 2015122 and was rejected by the applicants.123 It seems readily apparent
that in failing to comply with the provisions of the contract relating to extending the
date of practical completion, Radic could not, and did not, bring itself within the terms
of the contract. Accordingly, insofar as the learned member relied upon the provisions
of the contract in finding that the time for completion had been varied, any such
finding was unsupported by the evidence and by a proper construction of the contract
and was an error of law.
[138] It is not contentious that the subject contract was varied and that Radic had not
complied with a variation provision for the variation. Accordingly, s 18(6) of the DBC
Act was enlivened.124
[139] Whether Radic had applied to the tribunal to adjust the completion date as required
by s 18(6)(b) of the DBC Act was the subject of submissions at the appeal hearing.
Mr Hitchcock for Radic submitted that the application was to be found in the amended
Application for domestic building dispute filed 16 May 2016. The following relief
was sought by the applicants in the amended Application:
A. a Declaration authorising payment of variations 9-14
B. a Declaration as to the Contract Term and Contract completion date
C. orders for payment of $58,927.63
D. interest
E. costs
[140] Mr Hitchcock submitted that the application to extend time pursuant to s 18 was the
‘request for the variation – for the declaration of the effective time of the contract’.125
Mr Hitchcock expanded upon this submission. Referring to paragraph 21 of the
schedule accompanying the Amended application, Mr Hitchcock relied upon the
Schedule to the amended Application and paragraph 21 thereof:
The Applicant seeks a declaration as to the proper calculation of time under the
contract.
[141] Mr Hitchcock submitted that the ‘function of that request a declaration of the time
period of the contract’126 was the application to extend time pursuant to s 18(6)(b) of
the Act.
[142] In our view, Radic’s submission cannot be accepted. This was a building dispute, of
some legal and factual complexity, in which both parties were legally represented.
122 Statement of David Radic, dated 29 September 2016, [21].
123 Ibid.
124 Piper v Hookham Constructions Pty Ltd [2015] QCATA 77.
125 Transcript of Proceedings, Colagrande & Ors v D A Radic Pty Ltd t/as David Radic Prestige Homes
(QCAT APL081-18, Senior Member Brown, Member Olding, 16 November 2018), 41, lines 8-9.
126 Ibid, 42, lines 15-16.
-- 34 of 36 --
35
The issues in relation to variations and the date of practical completion were
vigorously contested. Notwithstanding Radic’s submissions, the amended
Application makes no reference to s 18 of the DBC Act. On no reasonable view of the
Amended application is it apparent that there was an application by Radic pursuant to
s 18(6)(b) of the DBC Act. We are not satisfied that there was any such application.
[143] In the absence of an application by Radic pursuant to s 18(6)(b) of the Act, it was not
open to the learned member to adjust the completion date. To the extent that the
learned member relied upon s 18(6)(b) of the Act in finding that the date for practical
completion was extended, there was an error in law.
Conclusion
[144] We have found errors of law by the learned member.
[145] The orders sought by the applicants are to set aside the decision below and to
substitute a decision in the following terms:
(a) A declaration that the applicants are entitled to set off the amount of $13,000
against the final payment claimed by Radic being the liquidated damages
pursuant to clause 19 of the contract; and
(b) An order that the applicants pay to the respondents $12,250.
[146] At the hearing of the appeal, Counsel for the applicants submitted that the correct
figure in respect of the liquidated damages calculation was $18,000.00 and that the
final order sought was that Radic pay the applicants $7,250.00. The calculations were
not disputed by Radic’s solicitor.
[147] If the determination of the questions of law decides the appeal entirely in the
applicants’ favour, we may set aside the decision below and substitute our own
decision.
[148] There is no cross appeal by Radic.
[149] We have concluded that it was not open to the learned member to approve the non-
compliant variations. The learned member allowed $32,985.83 in respect of the non-
compliant variations.127
[150] We have found that in the absence of a contractual entitlement to do so or an
application by Radic in accordance with s 18(6)(b) of the DBC Act there was no basis
to adjust the completion date. The learned member found that the date for practical
completion pursuant to the contract was 22 July 2015.128 The learned member
adjusted the date to take into consideration the agreed variations. The additional time
allowed by the learned member for the agreed variations was from 22 July 2015 until
7 October 2015.
[151] The finding by the learned member, that 55 additional days be permitted in respect of
the agreed variations, and thus adjusting the date for practical completion to 7 October
2015 is not challenged.
127 D A Radic Pty Ltd t/as David Radic Prestige Homes v Colagrande & Ors [2018] QCAT 112, [145].
128 Ibid, [215].
-- 35 of 36 --
36
[152] It is uncontentious that, in the absence of a finding that the date for practical
completion was extended in respect of the non-compliant variations, the date for
practical completion was 7 October 2015. It is also uncontentious that practical
completion was achieved on 18 December 2015. The contract provided for the
payment of liquidated damages at the rate of $250.00 per calendar day in the event
the builder failed to achieve practical completion by the due date.
[153] The delay in achieving practical completion was 72 calendar days. Undertaking the
required arithmetical exercise the calculation of liquidated damages is $18,000.00.
The learned member calculated the relevant period from 7 October 2015 to 18
December 2015 as being 52 business days. However the contract provides for the
payment of liquidated damages calculated by reference to calendar days not business
days.
[154] The applicants are entitled to recover liquidated damages in the amount of $18,000.00.
It is uncontentious that the applicants withheld the amount of $25,250 from the final
progress payment.
[155] We have found errors of law by the tribunal below. The determination of the appeal
on the questions of law resolves the matter entirely in the applicants’ favour. The
appeal is allowed and the decision below set aside. The applicants must pay to the
respondent $7,250.00. We order accordingly.
[156] We will make directions for the parties to file submissions on costs.
-- 36 of 36 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2019/176