Cotter v Youngberry & Anor [2019] QCATA 104
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Cotter v Youngberry & Anor [2019] QCATA 104
PARTIES: COLIN COTTER
(applicant/appellant)
v
KEVIN YOUNGBERRY
HYACINTH YOUNGBERRY
(respondents)
APPLICATION NO/S: APL237-18
ORIGINATING
APPLICATION NO/S:
MCDO 40/18
MATTER TYPE: Appeals
DELIVERED ON: 11 July 2019
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Justice Carmody
ORDERS: The application is dismissed.
CATCHWORDS: APPEAL – MINOR CIVIL DISPUTE – CONSUMER
DISPUTE – where consumer paid respondents’ company
to replace structural elements of fibreglass boat – where
work done allegedly defective – where quoted cost of
rectification exceeds amount paid – where consumer claim
dismissed – whether grounds for leave to appeal.
Queensland Civil and Administrative Tribunal Act 2009
(Qld) s 32
REPRESENTATION:
Applicant: Self-represented
Respondent: Self-represented
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld).
-- 1 of 8 --
2
REASONS FOR DECISION
[1] The application is for leave to appeal a dismissal order in a consumer dispute.
The context
[2] The applicant is renovating a 1980’s Swift Craft fibreglass boat.
[3] On 30 June 2016 the respondents’ company, Gale Force Boats, agreed to “to replace
floors, stringer, transom, enclosed transom, bait tanks, under floor fuel tank, to replace
pirspex (sic) windscreen. Flowcoat all boat” for a lump sum of $10,000 cash.1
[4] The respondents have since sold the business and were substituted as parties on
30 January 2019.
[5] Typically, in fibreglass boats stringers (or tabs) are long thin parallel battens or lengths
of bonded solid core (in this case wooden) load bearing structural supports for the hull
and deck running longways from transom to bulkhead overlaid with a protective
fibreglass coating. The repair order does not mention how many stringers were to be
replaced and uses the word “stringer” which normally denotes the singular but the
image on page 3 of the applicant’s survey report shows a series of three (3) stringers
in black.
[6] Depending on the extent of decay the process of repairing damage involves removing
the rot in the underfloor beams and then either replacing it with matching material or
plywood and refitting. Smaller sections can be dried, cleaned and injected with resin
in situ. It is not clear whether the parties intended the entire stringer system to be
replaced, regardless of the degree of deterioration, or repaired where possible.
Bulkheads are partitions inside the hull between the stringers used to stiffen the vessel.
[7] The deck is structural planking or multiple layers of plywood coated over with layers
of fibreglass soaked in a plastic resin covering the hull for rigidity. Wood rots and the
fibreglass delaminates over time due to water saturation and penetration. Voids
between the layers of plywood trap water and accelerate rotting if not waterproofed
with resin and painted. This naturally weakens the structure and seaworthiness of the
boat.
[8] The transom is the square end at the stern (or back) that reinforces the hull where the
sides of the boat meet.
[9] Gale Force started the job in mid-July 2016 and finished in November 2016.
According to the applicant “the boat was an empty shell so the work to be done was
easily foreseeable”. He inspected and photographed the work in progress three or four
times a month before going on an overseas holiday between 10 September–8 October
2016.
[10] The evidence of the order in which each item of work was done up to his departure,
and the stage reached prior to him leave the country, is disjointed but the applicant
asserts the photographs he took before leaving reveal “little to nothing was done
internally”.
1 Acknowledgement of satisfactory repair/supply document dated 30 June 2016.
-- 2 of 8 --
3
[11] By the time he got back less than a month later the fuel tank “…was already installed
and the deck was … back on” so that the timber work below was not visible.
[12] Extras were later added including installation of a pod, drum winch compartment,
gunnel, pumps and hoses to the bait tanks, grab rails and supports for the marlin chair.
A different contractor installed the outboard motor, but Gail Force connected “… the
wiring on the sender from the fuel tank to make it easier for the motor installer to
access the wiring loom for completing the motor installation”.
[13] The applicant says there were ongoing problems after the boat was delivered in late
2016 with the bait tanks pump (replaced in May 2017 for $115) and fumes from the
new fuel tank.
[14] Just before Christmas 2017 Hervey Bay Fibreglass cut into the deck to access the
petrol tank and found fuel leaks a crimp in the breather hose fixed and damage to the
sender wire and fuel line. The hull had to be flushed out costing the applicant $825.
[15] Mr Sayer a marine surveyor with over 21 years’ experience examined under the deck
of the boat out of the water on 18 January 2018. He reported finding: half the
fibreglass/plywood deck had previously been removed by Hervey Bay Fibreglass, the
hull in average condition, an “indescribable” mess of dry fibre glass with no structural
strength or purpose, areas of fibreglass missing.
[16] More relevantly, the port stringer was not one continuous length to the bow and butts
into a rotten bulkhead (photo 4 on page 5), another was laid over a piece of rotten
decking and painted over (photo 3 of page 4) and construction pine instead of marine
ply was used on the deck the new deck allegedly installed to hide the poor repair
(photo 1 on page 3) and fastened down with sub-standard furniture grade screws
(photo 2 page 4). The applicant says this was when he first became aware that “rotten
timber was left in my boat … and painted or fibre glassed over instead of removing
it”.
[17] No specific criticism was made of the refitted deck floors, transom, windscreen,
flowcoat or extras.
[18] Nor are there any comments or photos of the condition of stringers, flooring or
bulkheads not adversely mentioned in the report.
[19] On 29 January 2018 Hervey Bay Fibreglass quoted $3,800 for removing the rot in the
V berth, $1,200 for supply and fitting a new fuel tank, $800 for flowcoat and fleck,
$3,200 for replacing the deck and $3,800 for new stringers aft of the main bulkhead
plus $2,200 for materials.
[20] The applicant claimed compensation of $15,000 plus $3,519.80 in out of pockets or
$10,000 plus all necessary materials to repair the boat or alternatively approximately
$52,000 for the respondents to purchase the board from him to cover his costs to date.
[21] The respondents denied any defective work and liability for asserted losses.
[22] The tribunal accepted their evidence “about what work was done and how” and
dismissed the claim because the applicant had failed to prove that poor workmanship
had caused his loss.
-- 3 of 8 --
4
[23] At T1-4: L34 the tribunal notes “…that the applicant …suggests that the work that
was done while he was away overseas was shoddily performed because he was not
able to inspect it. I do not accept this. I also note that it was approximately one year
for the complaint to be made.”
The filed grounds
[24] The applicant’s major complaint is that the respondents either intentionally or
negligently painted or fibre glassed over rotten internal structural timbers in the deck,
stringers and bulkhead instead of replacing them with new materials as agreed.
[25] In legal terms the applicant’s case is that Gale Force did not earn the price of the
contract because of substantial non-performance of its conditions and the respondents
should have been ordered to refund the $10,000 already paid plus pay 50% more so
the applicant can get the job redone now by a reputable local repairer.
[26] Put another way, Gale Force repudiated or seriously breached its contract obligations
and would be unjustly enriched if it kept the payment.
[27] This is a difficult proposition to sustain in a hearing conducted wholly on the papers
without any cross-examination where there is an obvious risk of information gaps and
the tribunal is deprived of standard forensic aids such as demeanour in credit and
opinion-based cases. Efficiency is good but a decision on the merits with the benefit
of all relevant facts is better.
[28] The written submissions dated 27 November 2018 identify “…the main concern (as)
the rotten timber … transom and stringers …” in structural parts “… meaning the boat
was not seaworthy.”
[29] Specific grievances are that the tribunal:
a) was side-tracked by other issues and missed the main point of the claim (the
failure to perform the contract by not removing and properly replacing rotten
timber in the internal structures – floors, transom and stringers – to make his
boat safe and seaworthy);
b) failed to see why Mr Sayers’ occupation (marine surveyor not “an experienced
boat builder” as he was referred to) is significant;
c) did not to give any weight to the independent expert findings and corroborative
photographs of an independent expert about the structural integrity of the boat
and instead giving too much weight to the biased contrary evidence of a party
to the more experienced and independent expert;
d) wrongly blaming the repairs and inspections of other parties including himself
for some undoing of the respondent’s work including breaking down of the
fibreglass;
e) unfairly criticising him for not making a complaint for more than 12 months
where the defects were not reasonably discoverable any earlier.
-- 4 of 8 --
5
[30] The applicant does not contend that there was no evidence to support the tribunal’s
critical findings, inferences or conclusion but that they were unreasonable or against
the overall weight of the evidence. This raises a question of fact not law.
[31] However, the leave point is equally capable of being framed as one of pure law viz.,
whether the tribunal failed to decide the dispute according to the substantial merits.
[32] The distinction affects the appeal powers and procedures but for the moment the
pivotal question is whether the applicant has carried the burden of demonstrating that
the tribunal’s decision to dismiss his claim was contrary to the only conclusion the
evidence most favourable to the respondents reasonably permitted.
(a) The rotten timbers found in 2018
[33] The deck and stringers account for more than 50% of the total rectification quote.
[34] The applicant had the burden of proving that Gale Force was liable for compensation
to cover it because it breached the implied warranty of workmanship. This included
negativing any response. For this he relied on his own observations, photographs as
well as Mr Sayer’s affidavit and report.
[35] In further submissions on 31 January 2019 he claims at [6] that the rot in issue can
easily be seen in photographs of the stringers and the floor taken before 10 September
2016.
[36] The respondents claim that the rot the applicant observed and photographed before
going on holidays in 2016 is not the same as the decay Mr Sayers reported on in 2018
because any rotten structural timber, they came across within scope was removed.
They also maintain that on proper inspection none is evident in the photographs
including the one taken on the 15 July 2016 at 10:03am.
[37] Whether or not there is rot visible in the 2016 photographs is a question of fact which
the tribunal chose to resolve in favour of the respondents based on examination and
interpretation of the document. Unless that view is demonstrably mistaken it doesn’t
matter whether I agree with it or not. It is not enough for the applicant to show that
the tribunal’s opinion is doubtful or arguably wrong. My opinion about contestable
questions of fact does not prevail over the tribunals where there is more than one
possible answer.
[38] There was no discussion by Mr Sayer of the wood decaying process, or the likely age
of the rot found in the stringers, decking and bulkhead beams in 2018. Nor is there
any evidence of the use and care taken of the boat between November 2016 and
January 2018.
[39] Likewise, the inference that the rot Mr Sayer found in the stringer and bulkhead
timbers in 2018 was the same as the rot the applicant says existed in 2016 was
certainly open to the tribunal but it is not an irresistible one. It was up to the applicant
to address and refute reasonably credible alternative explanations and provide the
tribunal with the material it needed to resolve the issue in his favour. Otherwise, the
tribunal was perfectly entitled to accept and act on the contrary conclusion that Gale
Force removed all existing rot in the structural timber in 2016.
-- 5 of 8 --
6
[40] Even if the same rot in the stringers, decking and bulkhead found in 2018 did pre-date
the 2016 repairs Mr Sayers does not clearly explain why not removing it in 2016
makes the boat unseaworthy now or why the disputed work substantially non-
compliant and significantly sub-standard. Nor does the applicant’s material make it
clear why the boat needs a complete structural rebuild rather than repair.
[41] Experts give opinions. The tribunal finds the facts based on observations, inference
and any admissible opinions it accepts as trustworthy. The ultimate fact of whether
the boat was unseaworthy and in need of a structural rebuild in 2018 because of the
respondent’s breach of its duty of care in 2016 is a matter for the tribunal not Mr Sayer
to decide.
[42] Likewise, the tribunal was not compelled by the laws of logic to find that the rot Mr
Sayer discovered was “covered up” (deliberately or otherwise) when the applicant
was overseas and therefore were not discoverable (if they existed) before redelivery
in late November 2016 or until late 2017 at the earliest.
[43] While the stringer photographed by Mr Sayer was not continuous to the portside wall
its structural integrity is nonetheless ensured by the beams in the v-berth which the
respondents were not engaged to repair and it is the only area of rot Hervey Bay
Fibreglass quoted to remove.
(b) Use of construction instead of marine ply
[44] The applicant says in his last set of submissions –
“Construction ply?? Name alone says it shouldn’t be used in a salt water marine
environment. If epoxy doesn’t stick to marine ply, this would make marine ply
redundant and not be able to be used for its intended purpose. You use
construction ply because it is extremely cheap as opposed to marine ply. Plus
they say its fully encapsulated yet they drove plain furniture screws through it
creating a hole as the furniture screw will rust out quickly in a marine
environment leaving cheap and nasty construction ply to also rot thereafter.”
[45] All the respondents’ witnesses explained that construction ply was used for the deck
instead of marine ply marine ply is compatible with epoxy but not the polyester resin
used in this boat. 2 Mr Sayer commented on it but did not contradict this assertion.
[46] This is a reasonably credible response that was challenged but not rebutted.
(c) Inadequate fastenings
[47] The applicant submits that “furniture screws through it creating a hole as the furniture
screw will rust out quickly in a marine environment leaving cheap and nasty
construction ply to also rot thereafter”.
[48] Mr Sayers report at page 4 says at recommendations “… furniture grade screw which
was used to fasten the new deck down with. These should be replaced with marine
grade fastenings”.
2 Respondents’ submissions 14 January 2019 at para 35(i).
-- 6 of 8 --
7
[49] According to the respondents the fasteners and screws had no structural role and
merely held things in place temporarily until the adhesive bog between the floor and
stringer system hardens prior to fibre glassing.3 This is a reasonably credible response
that was not negatived.
(d) The fuel tank damage
[50] The respondents says the fuel tank was sealed and not leaking when the boat left the
workshop in 2016.
[51] The fuel filler was installed in the top deck instead of to the floor at the applicant’s
request despite the risk of overfilling and spillage. The placement of fuel filler was
“insisted” upon by the applicant “against the respondents’ advices”.4
[52] Notably, the Aquaholics invoice for recalibrating the gauge and refilling the tank does
not suggest that it was leaking then and even the applicant conceded in his complaint
to the Office of Fair Trading that the tank was not leaking after Hervey Bay Fibreglass
fixed the crimp in the hose in 2017.
[53] Faulty work carried out over 12 months previously is not the only rational possible
explanation for it was up to the applicant to provide the tribunal with the material it
needed to resolve the issue.
[54] The tribunal was clearly unconvinced that the respondents were to blame for any
leakage problems.
[55] The proposed evidence about the genesis fuel tank does not necessarily contradict the
implied finding that the tank was not leaking when the boat left the workshop in 2016.
(e) The live bait pump
[56] The pump was replaced in May 2017 ostensibly because it was too noisy because it
was installed upside down but, on one interpretation, the manufacturer confirms by
email that it is not possible to fit it upside down and the respondent denies that the
mounting angle adversely affects operation (HY4).5
[57] The tribunal finding has not been shown to be contrary to compelling contrary
evidence or inferences.
(f) Untidy fibreglass finish
[58] This is not a major fault or breach justifying non-payment or substantial
compensation. The fibre glass near the rear bulkhead was damaged when the fuel tank
was removed.
(g) Flowcoat
[59] The respondents have already smoothed out free of charge.
3 Respondents’ submissions 14 January 2019 at para 35(o).
4 Respondents’ submissions 14 January 2019 at para 35(e); Hyacinth Youngberry affidavit of 24/07/18
at [27] and Kevin Youngberry affidavit of 24/07/18 at [22]-[23].
5 Email of 17 July 2018 from Johnson Pump National Sales Manager, attachment HY4 to Hyacinth
Youngberry affidavit of 24/07/18.
-- 7 of 8 --
8
Conclusion
[60] Preferring one party’s affidavits or submissions over the other when deciding a minor
civil dispute is not an appealable error unless the primary or inferential facts on which
the decision rests are not rationally and logically supported by credible evidence.
[61] Applications for leave to appeal are not judicial rehearings conducted for the benefit
of a disgruntled applicant hoping for a better result second time around.
[62] On the contrary, tribunal decisions are prima facie final not provisional pending
confirmation on appeal. The applicant’s apparently genuine belief that he had
presented an open and shut case that only an unreasonable or biased tribunal could
reject is not enough. Nor is a difference of opinion. Even if the appeal tribunal
disagrees with the tribunal’s reasoning or prefers the opposite conclusion decisions or
orders stand unless vitiating error and substantial injustice to the applicant is
demonstrated.
[63] Leave is not justified here because although contestable the disputed findings and
inferences were reasonably open to the tribunal and therefore unimpeachable on
appeal.
[64] There is no indication that the tribunal side-tracked itself and missed the point, ignored
the marine surveyor, did not see the significance of Mr Sayer’s occupation, irrationally
favoured the respondents or acted unfairly.
[65] The tribunal was entitled to reject the applicant’s case for want of proof because
though prima facie credible, if not compelling, it did not either grapple with or
persuasively rebut a plausible answer.
[66] The application is dismissed.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2019/104