ChongHerr Investments Ltd v Ardent Group Pty Ltd [2019] QCATA 41
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: ChongHerr Investments Ltd v Ardent Group Pty Ltd
[2019] QCATA 41
PARTIES: CHONGHERR INVESTMENTS LTD
(appellant)
v
ARDENT GROUP PTY LTD
(respondent)
APPLICATION NO/S: APL274-18
ORIGINATING
APPLICATION NO/S:
MCDO60047-17 (Brisbane)
MATTER TYPE: Appeals
DELIVERED ON: 03 April 2019
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Howe
ORDERS: Application for leave to appeal refused.
CATCHWORDS: APPEAL AND NEW TRIAL – APPEAL – GENERAL
PRINCIPLES – RIGHT OF APPEAL – WHEN APPEAL
LIES – ERROR OF LAW – where parties agreed upon a
costs of preparation of environmental reports – where
invoices rendered – where the appellant refused payment
on an invoice on the grounds the respondent had not
completed the scope of work agreed – whether the
respondent had performed all work able to be performed
without additional information from the appellant – where
part of scope of work performed by the respondent on a
complimentary basis without charge
Pickering v McArthur [2005] QCA 294
REPRESENTATION:
Applicant: Self-represented
Respondent: Self-represented
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld).
-- 1 of 7 --
2
REASONS FOR DECISION
[1] The respondent (‘ChongHerr’) is the holder of a sandstone mining lease at Helidon.
They engaged the applicant company (‘Ardent’) to prepare a stormwater management
plan for both existing and future activities on the lease and to update a Plan of
Operations due to expire.
[2] Ardent quoted $6,000 plus GST to prepare the stormwater management plan. The
scope of work included a site visit. That quote was given on 14 October 2016.
[3] The Plan of Operations was a summary of planned disturbances and the rehabilitation
techniques to be employed rehabilitating the disturbances. A ‘financial assurance’
covering the cost of rehabilitation was also required. There were two options for this.
Either use the Department of Environment and Heritage Protection (‘DEHP’) standard
contractor rates or source independent third-party contractor rates.
[4] On 2 December 2016 Ardent quoted $7,600 for the Plan of Operations and confirmed
its quote of $6,000 for the stormwater management plan. Ardent noted ‘[w]e have
assumed that ChongHerr will use this [DEHP rates] rather than individual contractor
rates’ in quoting on the Plan of Operations.
[5] ChongHerr wanted to pay less. ChongHerr asked if Ardent would be prepared to map
the stages of rehabilitation for the next 5 years and prepare a stormwater management
plan for $10,000 all up.
[6] On 8 December 2016 Ardent prepared an updated proposal in which they said,
assuming ChongHerr used the DEHP new financial calculator to determine
rehabilitation liability, they would prepare rehabilitation costings based on the
calculator and complete the financial assurance lodgement form, together with an
‘initial stormwater management plan’ for $10,000.
[7] ChongHerr queried what ‘initial stormwater management plan’ was and asked if it
would satisfy DEHP requirements raised during an earlier compliance inspection and
Ardent said it would and described it as ‘a stormwater plan for the current layout of
the quarry, but not for future stages.’1
[8] On 12 December 2016 ChongHerr asked Ardent to proceed with the Plan of
Operations together with a stormwater management plan for $10,000. However, they
asked Ardent to make the quote ‘reflect’ that the entire cost was for the scope of work
of the stormwater management plan, and complimentary with respect to the Plan of
Operations.
[9] Ardent sent through a new quotation on 12 December 2016, which described the
charge was $10,000 to prepare ‘a stormwater management plan that meets the
requirements of the Environmental Authority’ and now noting the update of the Plan
of Operations would be complimentary at no cost.
[10] On 9 January 2017 Ardent wrote to ChongHerr and said work was being done on the
stormwater plan and because now there was no site visit as part of that work it would
be helpful to be provided with various documents which were then listed. No issue
1 Email, 9 December 2016.
-- 2 of 7 --
3
was taken by ChongHerr about there being no site visit associated with preparation of
what had become described as an initial stormwater management plan.
[11] Ardent sent an invoice on 22 December 2016 for $3,300 charging for consulting from
16 December to 22 December 2016 ‘preparing Plan of Operations and stormwater
plan’. That was paid by ChongHerr without demur on 7 March 2017.
[12] The Plan of Operations was finished and forwarded to ChongHerr on 11 January 2017.
It was lodged with DEHP and accepted by the department but the department had
questions about the financial assurance calculations. Ardent said they could assist with
that but that was outside the agreed scope of work.
[13] Ardent then invoiced ChongHerr on 25 January 2017 the further amount of $6,325.
The invoice said it was for consulting from 22 December 2016 to 11 January 2017
‘preparing the Plan of Operations and stormwater plan’.
[14] ChongHerr ultimately refused to pay. Ardent commenced proceedings in the Tribunal
to recover on the unpaid invoice and the matter was heard on 24 January 2018 and
then on 29 May 2018. The learned Adjudicator who heard the matter ordered
ChongHerr pay Ardent the sum of $6,437.50 representing its full claim plus filing fee.
[15] ChongHerr now seeks leave to appeal that decision.
[16] Given this is an appeal from a decision made in the Tribunal’s Minor Civil Dispute
jurisdiction, leave to appeal must first be obtained before any appeal proceeds.2
[17] Leave to appeal will usually only be granted where an appeal is necessary to correct
a substantial injustice to the appellant and where there is a reasonable argument that
there is an error to be corrected.3 There may be other relevant considerations, but these
are primary.
[18] ChongHerr raises a number of issues in its application for leave to appeal:
The Adjudicator was wrong allowing Ardent to recover for its work on the
stormwater management plan because no plan was ever provided to ChongHerr.
DEHP required further information about rehabilitation cost and Ardent failed
to supply it though that was within the scope of work of the Plan of Operations.
The sum of $3,300 paid Ardent was reasonable value for the work done by
Ardent which was less than the agreed scope of work.
Stormwater management plan
[19] ChongHerr submits that the learned Adjudicator made a mistake when he found that
Ardent had provided a stormwater management plan. No such stormwater
management plan had ever been provided. Therefore Ardent was not entitled to be
paid.
[20] The learned Adjudicator in fact found that a draft initial stormwater management plan
had been prepared and that Ardent claimed a reduced amount reflecting that the claim
2 QCAT Act, s 142(3)(a)(i).
3 Pickering v McArthur [2005] QCA 294, [3].
-- 3 of 7 --
4
was only for preparing a draft. The full amount owing was $11,000. $3,300 had been
paid which left a balance of $7,700 due under the contract. The amount claimed for
the draft initial stormwater management plan was $6,325. The full claim had therefore
been reduced by $1,375.
[21] The learned Adjudicator said Ardent couldn’t complete the initial stormwater
management plan because it needed information from ChongHerr and that
information was not forthcoming.4
[22] A perusal of the documents available at hearing shows the disputed invoice for $6,325
was sent undercover of an email dated 25 January 2017 and the email referred to it as
a ‘progress invoice for the Plan of Operations/Stormwater Management Plan’.
[23] In the proposal of 12 December 2016 Ardent had said their estimate of fees assumed
they would be provided with relevant site information regarding the existing layout of
the site and existing stormwater infrastructure and management. They said they
further assumed that ChongHerr would provide maps indicating the stages of mining
over the next Plan of Operations area and the staged rehabilitation proposed.
ChongHerr did not challenge that.
[24] On 9 January 2017 Ardent emailed ChongHerr to say Ardent was working on the
stormwater plan and because there would be no site visit as part of the work it would
be helpful if ChongHerr could provide additional information and then went on to
detail various maps that were required and other information about the lowest point
of each pit and where water typically pooled after rain.
[25] There was no response to that email and Ardent wrote again on 10 February 2017
asking for the same information. Significantly, in the email of 10 February 2017
Ardent said ‘if you can provide some of the information above, then I can complete
this plan for you’.
[26] In a statement of evidence of William Haylock filed on behalf of Ardent Mr Haylock
said Ardent was unable to complete the stormwater plan because, despite multiple
requests, ChongHerr failed to provide the requested necessary information.5
According to Mr Haylock, if Ardent had received the information the initial
stormwater management plan could have been completed.
[27] Ardent said it invoiced ChongHerr monthly, although there was apparently only the
two invoices ever generated. Also according to Ardent, the disputed invoice sent on
25 January 2017 was never challenged until some 4 months after it was rendered.
[28] At the hearing of 29 May 2018 the learned Adjudicator invited the parties on two
occasions to make submissions or to clarify any matters that they would care to
highlight or to add to the written material submitted. The oral submissions made by
Ms Ting for ChongHerr in response to that invitation were somewhat lacking in clarity
or precision. This is well understandable because clearly English is not Ms Ting’s
primary language. The transcript reveals however the following statement by her
concerning Ardent’s failure to complete the work:
4 Transcript (‘T’) 1 – 4, Line (‘L’) 6.
5 [31].
-- 4 of 7 --
5
Ms TING: Yeah. I should think that we were still waiting for them to put the
work to us for assessment and the work didn’t come through. And their building,
actually, as I has touch on in the respond that they actually build earlier than the
– you know, the work that had completed so I don’t buy that.6
[29] I assume Ms Ting was saying ‘billing’ rather than ‘building’ as recorded in the
transcript. Further that the reference to ‘the respond’ is a reference to the Response
document filed by ChongHerr. At paragraph 7 of the Response the following
statement is to be found:
7. In the proposal of the stormwater management plan, the scope proposed by
Ardent includes site visit and prepare a storm management plan that meets the
requirement of DEHP, as detailed as per paragraph 3 of quote dated on
14/10/2016 in appendix 1. Ardent had requested for some information for the
plan from ChongHerr and Ardent was advised that the information that it holds
does not reflect the current status and is of little value for the proposed plan and
that Ardent needs to make site visit for the purpose. Ardent did not make any
site visit and until today ChongHerr have not received the proposed stormwater
management plan.
[30] ChongHerr’s position seems to have been that it considered the information requested
by Ardent of little value and instead Ardent should have made a site visit.
[31] Ardent didn’t consider the information requested irrelevant. Whilst a site visit was
included in the original quote of 14 October 2016, there is no reference to it in the
subsequent cheaper proposals of 8 and 12 December 2016.
[32] The learned Adjudicator found that there was no evidence to support ChongHerr’s
proposition that a site visit was within the final scope of work. He found it telling that
the later proposals of 8 and 12 December 2016 were all reasonably detailed yet made
no mention of a site visit.
[33] The learned Adjudicator found that a satisfactory Plan of Operations had been
prepared, submitted and approved by DEHP and that a draft initial stormwater
management plan had been prepared. The learned Adjudicator concluded the reduced
claim representing the work done preparing a draft initial stormwater management
plan on the information available at the time was appropriate in the circumstances.
[34] I conclude, given the material available to the learned Adjudicator at hearing, those
findings were reasonably open to him on the evidence.
[35] The complaint by ChongHerr is that the learned Adjudicator mistakenly concluded
that a stormwater management plan had been submitted to them by Ardent. The
learned adjudicator did not assume that, but rather he accepted that the stormwater
management plan could be done in-house, without a site visit being required, subject
to the paperwork needed being supplied by ChongHerr. ChongHerr however failed to
supply it.
[36] The learned Adjudicator said that the Plan of Operations could be prepared (and had
been approved) using existing data only and that supported the view that a site visit
was similarly unnecessary for the preparation of the initial stormwater management
6 Transcript of hearing dated 29 May 2018 T1, L5 - 8.
-- 5 of 7 --
6
plan.7 There was no evidence led by ChongHerr to counter that proposition, simply
an assertion that a site visit was necessary.
[37] The Adjudicator made clear distinction between the preparation and submission of a
Plan of Operations and the preparation but no submission of a draft initial stormwater
management plan. He said:
What is clear, in the event, then, is that a satisfactory Plan of Operations has
been prepared, submitted and approved as envisaged, and that Ardent – sorry –
and that a draft initial stormwater management plan has been prepared. Part
payment in terms of the 8 December and 12 December quotes has been made.
A reasonable reduced sum only has been claimed: $6,325, inclusive of GST, in
lieu of what otherwise would have been contractually owing: $11,000 minus
$3,300 equals $7,700. That was to take account of preparation of the draft plan.
The reduction, GST inclusive, is $1375. The deduction is specific and
calculable in term of the quotes. That being the case, there is no basis for not
paying the invoice as claimed.8
[38] The agreement between the parties was without any great detail to it. There was no
mention of when accounts could be rendered. There was no prohibition on Ardent
rendering progressive accounts as the work was done.
[39] There is no suggestion that the intention was that the contract be entire, that is, that all
the work had to be completed before Ardent would be entitled to payment. But even
if it was entire, given the reasonable conclusion is that the initial stormwater
management plan could not be finalised because ChongHerr failed to provide the
required information as contemplated under the proposal of 12 December 2016,
ChongHerr is not entitled to benefit from its own wrong doing in making the contract
fail.
[40] On the information available to him the learned Adjudicator was entitled to conclude
the costs claimed by Ardent were reasonable for the work done, that no site visit was
necessary for the preparation of the initial stormwater management plan, that the
completion of the work required the provision of further information by ChongHerr
but that was not forthcoming despite repeated requests for it made by Ardent, and that
Ardent was entitled to recover its invoice amount from ChongHerr.
[41] There is no discernible error in the findings and reasoning of the learned Adjudicator.
ChongHerr has limited prospects of succeeding on this ground of appeal.
Further information about rehabilitation cost
[42] ChongHerr says DEHP required further information about rehabilitation costs after
the Plan of Operations was lodged, Ardent failed to supply it, and responding to that
request was within the agreed scope of work of the Plan of Operations.
[43] ChongHerr says it had to spend ‘resources’ to rework the calculations and therefore
Ardent shouldn’t be awarded the full costs claimed for this work.
[44] A major difficulty with this proposition is that Ardent didn’t claim any costs for this
work. It was done on a complimentary basis. That was at the request of ChongHerr.
7 T1 – 6, L 23.
8 T1 – 6, L 32 – 40.
-- 6 of 7 --
7
The charges, agreed at $10,000, were only for preparation of the initial stormwater
management plan.
[45] In an email of 12 December 2016 Ms Ting said:
On the other note, we are happy to get you to proceed with the plan of operation
together with stormwater management plan at $10,000. However we would like
you to represent the quote to reflect that the entire cost be the scope for
stormwater management plan with complimentary updating of plan of operation
for 2017 – 2022. Having doing so, the actual scope of works still remains the
same as what it was quoted/proposed.
[46] But in any case, Ardent maintained that there was no time to do more than rely on
general DEHP rates in calculating rehabilitation costs. ChongHerr left it very late to
engage them. On 6 December 2016 Ms Ting sent an email to Ardent advising that
DEHP required the revised Plan of Operations by 15 December 2016, that is, within
9 days. The Plan was lodged and accepted by DEHP. As stated in its proposal of 12
December 2016, the DEHP rates would be used. They were. Ardent completed the
agreed work. The matters raised by DEHP after that fell outside the agreed scope of
the contract.
[47] The learned Adjudicator concluded that Ardent had reasonably completed the agreed
scope of work for the Plan of Operations.9 He was entitled to make that finding on the
evidence before him.
[48] This ground of appeal also has limited prospects of success.
Reasonable value for work done
[49] The final ground of appeal relied on is that the monies paid, $3,300, represented
reasonable value for the work done by Ardent which was less than the scope of work
agreed. In light of the abovementioned findings on the previous grounds of appeal,
this ground of appeal similarly lacks reasonable prospects of success.
[50] In all the circumstances, leave to appeal is refused.
9 T1 – 5, L 44.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QCATA/2019/041