Brookside Estate Pty Ltd v Brisbane City Council & Anor [2019] QPEC 33 [2019] QPELR 989
PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND
CITATION: Brookside Estate Pty Ltd v Brisbane City Council & Anor
[2019] QPEC 33
PARTIES: BROOKSIDE ESTATE PTY LTD (ACN 601 061 821) AS
TRUSTEE FOR BROOKSIDE ESTATE TRUST
(appellant)
v
BRISBANE CITY COUNCIL
(respondent)
and
TPG DEVELOPMENT 5 PTY LTD (ACN 159 649 420)
(co-respondent)
FILE NO/S: 2023/2018
DIVISION: Planning and Environment Court
PROCEEDING: Hearing of an appeal
ORIGINATING
COURT: Planning and Environment Court of Queensland, Brisbane
DELIVERED ON: 25 July 2019
DELIVERED AT: Brisbane
HEARING
DATES:
27, 28, 29, 30 May and 21 June 2019
JUDGE: R S Jones DCJ
ORDERS: 1. I will publish my reasons but will refrain from
making final orders until I hear further from the
parties
CATCHWORDS: PLANNING AND ENVIRONMENT – APPEAL – where the
respondent approved a subdivision intended to be developed
by the co-respondent – where appellant has appealed against
that decision – where the notice of appeal raised a number of
issues – stormwater – bushfire hazard – traffic – conflict with
the Planning Scheme – where central issue was whether
proposed development provided sufficient connectivity and
integration with surrounding land uses and infrastructure
Legislation
Sustainable Planning Act 2009 (Qld)
Planning and Environment Court Act 2016 (Qld)
Planning Act 2016 (Qld)
-- 1 of 27 --
2
Cases
Ashvan Investments Unit Trust v Brisbane City Council &
Ors [2019] QPEC 16
Bell v Brisbane City Council [2018] QCA 84
Dillon v Council of the City of Townsville (1981) 2 APA 134
Gold Coast City Council v K & K (GC) Pty Ltd [2019] QCA
132
Degee & Anor v Brisbane City Council & Anor (1998)
QPELR 287
COUNSEL: Mr A Skoien for the appellant
Mr J Ware for the respondent
Mr J Houston for the co-respondent
SOLICITORS: Keypoint Law for the appellant
City Legal for the respondent
Anderssen Lawyers for the co-respondent
[1] This proceeding is concerned with an appeal against the decision of the respondent to
approve a small lot subdivision. As a consequence of my findings set out below, I
will publish my reasons but will refrain from making final orders until I hear further
from the parties.
Introduction and background
[2] The subject land is described as Lot 2 on Survey Plan 114142 and Lot 21 on Survey
Plan 125114 and has, in total, an area of 1.423 ha. The street address of the land is
1022 and 1022A Blunder Road, Doolandella, an outer south-western Brisbane
suburb. The land fronts Blunder Road to the west, is largely cleared and is improved
by an existing dwelling house and small-out buildings. Directly to the west and north-
west is an expansive area of residential subdivision. To the east of Blunder Road and
to the north of the land is residential subdivision, however, in this instance, the
residential development is effectively divided into a number of pockets separated by
fingers of natural vegetation. To the further west is a large area of vegetated land.
To the immediate south are two separate parcels of land referred to during the
proceeding as Lots 3 and 4.
[3] To the further south, at the intersection of Blunder Road, Crossacres Street and
Brookside Street, are a number of existing and planned commercial developments.
On the north-eastern corner is a service station and a number of shops including a 7-
Eleven convenience shop that is associated with the service station. A McDonalds
-- 2 of 27 --
3
drive-through restaurant is also under construction on this site. On the north-western
corner is an existing childcare and education centre. During the course of the
evidence, reference was made to a potential Woolworths supermarket on the south-
western corner of the intersection.1 However, the likelihood of that development
proceeding and, if so, when it might occur, is uncertain. The approval dates back to
2012 and, despite being extended on 12 November 2015, lapsed on 3 February 2018.2
Despite this, Mr Perkins, the town planner relied on by the co-respondent (TPG), gave
evidence that was not challenged to the effect that Woolworths still had an interest in
developing this site.3 A substantial townhouse development exists on the south-
eastern corner of the intersection.
[4] To the east is land either developed, in the process of development or planned for
future development by the appellant (Brookside). Immediately adjoining the eastern
boundary of the land is a site owned by Brookside designated and approved for low
density residential use separated by a landscaped buffer area.4
The intended development
[5] On or about 25 August 2016, TPG lodged a Development Application with the
respondent (the Council) under the provisions of the Sustainable Planning Act 2009
(SPA). In summary, the Development Application proposed the reconfiguration of
the land into 18 residential lots to be, at least temporarily, serviced by an internal road
running along its northern boundary in an east-westerly direction from Blunder
Road.5 More will be said about the access situation below.
[6] A number of submissions were made opposing the proposed development including
a submission made by Brookside. Notwithstanding those submissions, on or about
27 March 2018, the Council approved the proposed development limited to 19 lots
ranging in area from 301m2 to 466m2.6 The larger and lower lot (Lot 19) at the eastern
end of the land was intended to include a building pad. That part of the original
proposal (Stage 2) was not a part of the development as approved. The consequence
of this is that Lot 19 is now described as a “Balance Lot”.
1 See generally Exhibit 7 at pp 5 and 17; Transcript (T) 3-10 ll 20-45.
2 Exhibit 16.
3 Transcript (T) 3-10 ll 28-45.
4 Exhibit 7, pp 15 and 20.
5 Ibid, p 4.
6 Exhibit 1, volume 2, pp 521 – 526.
-- 3 of 27 --
4
[7] At the time of the development application, the land was the subject of City Plan 2014
(CP 2014). Under that planning scheme the land was:
(a) Partly within the Emerging Community Zone;
(b) Partly within the Rural Zone;
(c) Within the Doolandella Neighbourhood Plan Area;
(d) Partly subject to the Medium and High Hazard Area Bushfire Overlay
map;
(e) Partly subject to the High Hazard Buffer Area Bushfire Overlay; and
(f) Partly subject to the Medium Hazard Buffer Area Bushfire Overlay.
[8] That part of the land where lots 1-18 would be located fell within the Emerging
Community Zone. That part of the land generally coinciding with the area of the
proposed Lot 19 fell partly within the Rural Zone.7
[9] The land was also subject to a number of other overlays, maps and constraints8 which
do not require any detailed consideration to dispose of this appeal.
The grounds of appeal and the real issues in dispute
[10] On 30 May 2018 Brookside filed its notice of appeal. After setting out a number of
factual matters, it is asserted against the proposed development that:9
“It has not been demonstrated that the Proposed Development
(a) would not result in adverse stormwater impacts;
(b) would not result in adverse bushfire impacts;
(c) would not result in adverse traffic safety and efficiency impacts; and
(d) would not result in adverse impacts upon the planning for trunk
infrastructure (park).
The Proposed Development involves the creation of standard residential
allotments without any proposed mix of allotment sizes or potential housing
types.” (Footnotes deleted)
[11] As a consequence it is then alleged that “in the circumstances” the proposed
development was in conflict with a number of provisions of the planning scheme.10
[12] During the openings of counsel, it was identified that bushfire impacts were no longer
in issue and stormwater impacts, insofar as they existed, could be dealt with by way
of appropriate conditions of approval and were not of themselves grounds for refusing
the application. However, access and road design, planning for trunk infrastructure
7 Exhibit 4, p 9; Exhibit 7, p 22.
8 Exhibit 7.
9 Grounds of appeal, paras 12 and 13.
10 Ibid, para 14.
-- 4 of 27 --
5
(park) and the proposed lot layout and lot sizes remained in dispute.11 At the heart of
Brookside’s case was that the proposed development constitutes an out of sequence
development and, as a consequence, involves an inefficient use of existing
infrastructure and results in an overall unacceptable interference with what would be
reasonably expected had the land been developed in conjunction with surrounding
land in a logical and sequential manner. Mr Skoien, counsel for the appellant,
relevantly said in this context:12
“The case that is made by the appellant finds its genesis in the fact that, quite
self-evidently, the proposed development of the subject land is out-of-
sequence development. It is not something that is readily able to make use
of the infrastructure, the particular road and the like infrastructure, to
facilitate its own development. But, again, there’s not necessarily anything
fundamentally wrong with out-of-sequence development, the appellant says,
but what’s important is that the development of the subject land out of
sequence is then (not) then able to be appropriately tied into development
and facilitate integrated and ordered development in due course. That’s
effectively the proposition that sits at the base of the appellant’s case. In
that regard, your Honour, very much (sic) there are four issues that are
raised, and it’s accepted by the appellant that they overlap.” (Emphasis
added)
[13] Those four categories or subcategories could be described as follows:13
(i) The proposed development fails to appropriately reflect any
appropriate infrastructure planning;
(ii) In reality the proposed temporary access to and from Blunder
Road is “either permanent access or permanent access by
another name or temporary access for a period of time that is
far longer than it ought to be…”;
(iii) Does not provide for a park which was clearly intended under
the planning instruments for this locality; and
(iv) The proposed development for “very small lot housing” fails
to take into account appropriate planning for the locality.
[14] Pursuant to s 45(2) of the Planning and Environment Court Act 2016 (PECA), it is
for TPG to satisfy me that Brookside’s appeal should be dismissed.
Recent statutory developments
[15] Notwithstanding that the subject Development Application was lodged under the then
SPA, it was not in contest that the appeal was one pursuant to s 229 of the Planning
11 Exhibit 2, paras 2-4.
12 T1-35 ll 33-43.
13 T1-35 ll 45-47; T1-36 ll 1-9.
-- 5 of 27 --
6
Act 2016 and was to be dealt with in accordance with the legislative scheme provided
under that Act. It was unsurprising then that the parties referred me to the recent
decision of Williamson QC DCJ in Ashvan Investments Unit Trust v Brisbane City
Council & Ors.14 In Ashvan, His Honour made a number of observations concerning
differences between the Planning Act and the SPA. Pursuant to s 326(1) of the SPA,
“the assessment manager’s decision must not conflict with a relevant instrument
unless… (b) there are sufficient grounds to justify the decision, despite the conflict”.
The term “grounds” is defined to mean “matters of public interest”.15
[16] Pursuant to s 45(5) of the Planning Act, when concerned with a development
requiring impact assessment, as is the case here:
“An impact assessment is an assessment that –
(a) Must be carried out –
(i) Against the assessment benchmarks in a categorising
instrument for the development; and
(ii) Having regard to any matters prescribed by regulation for this
subparagraphs; and
(b) May be carried out against, or having regard to, any other relevant
matter, other than a person’s personal circumstances, financial
or otherwise….” (Emphasis added)
[17] Pursuant to s 60 of that Act it is provided that:
“Deciding development applications
(1) This section applies to a properly made development application,
other than a part of a development application that is a variation
request.
(2) To the extent the application involves development that requires code
assessment, and subject to s 62, the assessment manager, after
carrying out the assessment –
(a) Must decide to approve the application to the extent the
development complies with all of the assessment benchmarks
for the development; and
(b) May decide to approve the application even if the
development does not comply with some of the assessment
benchmarks; and …
(c) May impose development conditions on an approval; and
(d) May, to the extent the development does not comply with
some or all of the assessment benchmarks, decide to refuse
the application only if compliance cannot be achieved by
imposing development conditions…” (Emphasis added)
14 [2019] QPEC 16.
15 Sustainable Planning Act 2009 (Qld) Schedule 3.
-- 6 of 27 --
7
[18] In Ashvan, after noting that the powers conferred pursuant to s 47 of the PECA gave
broad discretionary powers to the court, His Honour went on to say that that discretion
“does not require the Court to refuse a development application in circumstances
where ‘conflict’ is established with an adopted planning control and there is an
absence of ‘sufficient grounds’”.16
[19] The Overall Outcomes and Performance Outcomes identified by the traffic engineers
are of course relevant “assessment benchmarks”.17 As Williamson QC DCJ also
observed, the new statutory regime provides for more flexibility in the decision
making process in removing as the starting point the obligation to refuse an
application in the event of there being conflict with the planning scheme. As his
Honour said:18
“Dispensing with the so-called two part test means that non-compliance with
assessment benchmarks, which include planning schemes, no longer has
assumed primacy in the exercise of the planning discretion… in this way, the
discretion conferred by s.60(3) of the PA admits of more flexibility for an
assessment manager (or this Court on appeal) to approve an application in
the face of non-compliance with a planning document in contrast to its
statutory predecessor. This, the Explanatory Notes state, is to allow a
‘balanced decision in the public interest’ to be reached, based on an
assessment of the merits of an application having regard to established policy
and other relevant considerations.”
[20] His Honour then went on to say, among other things, that:
It should not be assumed that non-compliance with an assessment benchmark
automatically warrants refusal. This must be established, just as the non-
compliance must itself be established.19
The manner in which the balance between rigidity and flexibility is struck in any
given case does not lend itself to a general statement of principle, or precise
formulation. The planning discretion, and the inherent balancing exercise, is
invariably complicated, and multi-faceted. It is a discretion that is to be exercised
based on the assessment carried out under s.45 of the PA. It will turn on the facts
and circumstances of each case, including the nature and extent of the non-
compliances….20
16 Ashvan Investments Unit Trust v Brisbane City Council & Ors [2019] QPEC 16 at [41].
17 Planning Act 2016 (Qld) s 43.
18 Ashvan Investments Unit Trust v Brisbane City Council & Ors [2019] QPEC 16 at [51].
19 Ibid, [53].
20 Ashvan Investments Unit Trust v Brisbane City Council & Ors [2019] QPEC 16 at [60].
-- 7 of 27 --
8
The balance between a rigid and flexible approach may more easily be struck
where development complies with adopted statutory planning controls. As this
Court has recognised, ordinarily, one would need strong reasons for refusing an
application, which on its face, was consistent with the adopted planning controls.21
[21] I respectfully agree with his Honour’s observations. However, they have to be
considered having regard to the reasoning of the Court of Appeal in the Gold Coast
City Council v K & K (GC) Pty Ltd.22 In that case Sofronoff P (with Fraser JA and
Flanagan J agreeing) relevantly said:23
“At the heart of decisions like these is the acknowledgement that
conformity with the Planning Scheme is, prima facie, in the public
interest. That approach is consistent with decisions of this Court from the
time of the earliest planning legislation. For example, in Dillon v Council of
the City of Townsville24 Carter DCJ said that the very raison d’être of a
Planning Scheme is to best serve the needs of a community in a particular
area. Most recently, McMurdo JA emphatically restated the principle in Bell
v Brisbane City Council.25
…
There has been a failure by the parties in this case to apprehend and apply
the applicable statutory requirements. It has been established beyond
argument that a decision maker must take a Planning Scheme to be an
expression of the public interest in terms of land use. The proposition
can be put the other way around. It is, in general, against the public
interest to approve a development that conflicts with the Planning
Scheme. To justify such a development it must be demonstrated that
the desired deviation from the Planning Scheme serves the public
interest to an extent greater than the maintenance of the status quo. The
public interest that is to be satisfied by the proposed development must be
greater than the public interest in certainty that the terms of a Planning
Scheme will be faithfully applied. Some such examples appear in the
Ministerial Guidelines to which I have referred.” (Emphasis added)
[22] In K &K it was also said:26
“…The process under s 326(1)(b) does not involve a consideration of the
‘competing merit and weight of the grounds relied upon to justify approval’.
That was the process required by former legislation, namely the Local
Government Act 1936 (Qld). Section 17 of the Local Government
Amendment Act 1975 (Qld) established criteria (for the first time) for a
decision to allow a rezoning application. In William McEwans Pty Ltd v
Brisbane City Council, Carter DCJ said that the decision making process
under the Local Government Act 1936 (Qld) was a flexible one and that
21 Ibid, [61].
22 [2019] QCA 132.
23 Ibid, [47] and [67].
24 (1981) 2 APA 134.
25 [2018] QCA 84 at [70].
26 Ibid, [60].
-- 8 of 27 --
9
applicable statutory criteria would vary from case to case. That is not what
s 326 of the SPA requires.”(Emphasis added) (Footnotes deleted)
[23] As I appreciate the reasoning of the Court of Appeal, once the intent and desired
outcomes of the planning scheme are sufficiently identified, the starting point is that
they represent what is in the best public interest. And, accordingly, any material
departure from those desired outcomes or objectives is, prima facie, contrary to the
public interest. These principles are not concerned with the construction of legislation
such as the SPA or the Planning Act but with the construction of the relevant planning
scheme itself. The fact that the starting point under the SPA, in the case of conflict,
was refusal of the development application is no longer the case since the introduction
of the Planning Act does not, in my view, derogate in any meaningful way from the
observations made by the Court of Appeal emphasised above. What has changed, to
use the terminology adopted by Williamson QC DCJ in Ashvan, is that non-
compliance with the planning scheme does not have the assumed primacy it once had
under the SPA.27
[24] It is tolerably clear that the outcome of the appeal in K & K largely turned on the
operation and effect of s 326 of SPA and how that differentiated the approach that
was legitimate under previous legislation such as the Local Government (Planning
and Environment) Act (1990) (LGPEA). Under the LGPEA it was uncontroversial
that it permitted a more flexible approach that was not permissible under the SPA
because of the operation of s 326.28
[25] Since the Planning Act came into effect, which no longer has as its starting point that
a development that was in conflict with the planning scheme ought be refused, as
Judge Williamson QC DCJ observed in Ashvan, it permits of a more flexible approach
in construing a planning scheme to achieve a “balanced decision in the public
interest”. Or, to adopt the words used by the Court of Appeal when referring to the
case DeGee & Anor v BCC & Anor,29 the Planning Act permits the balancing of the
relevant facts, circumstances and competing interests in order to decide whether a
particular proposal should be approved or rejected.
27 Ashvan Investments Unit Trust v Brisbane City Council & Ors [2019] QPEC 16 at [51].
28 See at paras [56]-[60].
29 (1998) QPLER 287: referred to in K & K at para [58].
-- 9 of 27 --
10
Access and traffic issues
[26] After a more detailed analysis of what the traffic engineers considered relevant, each
of them in their joint expert report provided a summary of their conclusions.30
Mr Williams, the traffic engineer relied on by the Council and TPG, summarised his
conclusion in the following way:
“Mr Williams believes that the development of the Subject Land in the
manner as proposed and as had been approved by the Council is acceptable
and would not unnecessarily prejudice the future development of Lot 3
and Lot 4. He does not believe that any of the issues raised by Mr Douglas
are of such a significant nature that the development should be rejected on
traffic engineering and transport planning grounds.” (Emphasis added)
[27] Following a query from me, Mr Williams expressed the view that the reference to
unnecessary prejudice was probably better understood as meaning that the access
proposed for the intended development would not unreasonably prejudice the
development of lot 3 and/or 4.31
[28] Mr Douglas, the traffic engineer relied on by Brookside, summarised his conclusions
in the following terms:32
“Mr Douglas considers the proposed development represents an
unnecessarily poor traffic engineering and transport planning outcome.
It fails to meet a number of Council’s Performance Outcomes and it
specifically runs against the orderly, safe and efficient development of the
precinct from a vehicular, pedestrian and cyclist standpoint.
In Mr Douglas’ opinion the development as proposed should be rejected on
traffic engineering and transport planning grounds.” (Emphasis added).
[29] For the reasons that follow, I agree that as is currently designed, the proposed
development ought not be permitted to proceed. However, subject to an appropriate
condition concerning access being imposed, an acceptable town planning outcome
could be achieved.
[30] It is common ground of the traffic engineers that access to and from Blunder Road, it
being a four lane busy arterial road, should be temporary. That intention is made
abundantly clear in conditions 37 and 37(a) of the development conditions imposed
by Council. Condition 37(a) relevantly provides:33
30 Exhibit 5, p 9.
31 T1-66 ll 30 – 45.
32 Exhibit 5, p 9, paras 5.1 – 5.3.
33 Exhibit 3, volume 2, p 547.
-- 10 of 27 --
11
“Close the temporary vehicular access on the Blunder Road frontage of the
site when the permanent access is available to provide access to the
development via Brookside Street and Sallyanne Street. The closure of
the temporary access is to be undertaken in accordance with the
following requirements…” (Emphasis added)
[31] Those requirements include the installation of bollards at the Blunder Road frontage
to prevent direct vehicular access to and from that road and, associated with that, the
removal of the crossover on the Blunder Road frontage of the site and the
reinstatement of the concrete verge.
[32] In reality, before the subject land could have access via Brookside Street and
Sallyanne Street, road works would have to be carried out on Lot 4 which is
immediately to the south of the eastern section of the subject land. As Mr Williams
accepted, the development of Lot 4 controls the timing of the closure of the temporary
access and that accordingly, “the timing is completely at the hands of somebody
else”.34 Not surprisingly, this was also a matter of concern to Mr Douglas.35
[33] Another issue having negative traffic ramifications identified by both the traffic
engineers was that in the event that Lot 3 were developed before Lot 4, the traffic
generated from that development would have to utilise the temporary access through
the subject land.36 At the time of the hearing of this proceeding, no application was
before the Council for the development of either Lot 3 or Lot 4.
[34] It is convenient at this stage to note two further matters arising from the evidence of
the traffic engineers. The first is that Mr Williams accepted that the temporary access
solution was not an optimal outcome and is indeed one that will prejudice the efficient
development of Lot 4.37
[35] The second matter is that while Mr Douglas’ opinion was that the proposed access
arrangements were sufficient to warrant “refusal”, it was not that temporary access to
Blunder Road of itself was fatal to the proposal.38 His evidence made it clear that
there were three potential alternate internal street layouts which, if provided for,
would not then warrant refusal on traffic grounds.
34 T1-53 ll 25-29.
35 Exhibit 5, pp 3-4, items E and F; Exhibit 12, p 9, para 38(a).
36 Exhibit 12, p 9, para 38(a); Mr Williams evidence at T1-51 ll 1-7.
37 Exhibit 5, p 9, para 5.4; T1-66 ll 30-45.
38 T2-21 ll 40-46.
-- 11 of 27 --
12
[36] One solution would be for the road identified in the current proposal be relocated to
run along the southern boundary of the land. That would provide extensive potential
access to both Lots 3 and 4. Mr Douglas described that option as his “utopian”
outcome.39
[37] Other options identified by Mr Douglas, which while not the most desirable, would
be to provide for access to Lot 4 through that part of Lot 19 immediately adjacent to
Lot 18.40 Alternatively, and potentially a better outcome, would be to provide for
future road access to Lot 4 by re-aligning the proposed road in a north-south direction
opposite the existing pedestrian link to the north.41 This option would of course
require some additional reconfiguring (and possibly loss) of lots and additional
roadworks. Neither of those consequences are likely to be desirable insofar as TPG
is concerned.
[38] While the imposition of a condition providing for a road connection to Lot 4 will not
provide a determinative solution for the timing of the closure of the temporary access,
it would go a long way to resolving the “connectivity” concerns raised by Mr Douglas.
In this context, the three town planners who gave evidence, all agreed that the
provision for future road access to Lot 4 was a better town planning outcome than
that resulting from the existing proposal.42
[39] In the joint expert report of the traffic engineers,43 Mr Douglas expressed the opinion
that, in respect of traffic/road design, the proposal conflicted with various provisions
of the planning scheme. He then sets out the fundamental bases for those conclusions
in subparagraphs (a) to (h) inclusive of that report.44
[40] In respect of those matters, subparagraphs (a), (b), (c) and (g) are concerned with the
issue of road connectivity and integration to the south via Lot 4. Subparagraphs (d),
(e), (f) and (h) are, while clearly involving the issue of road connectivity to the south,
primarily directed to concerns about the timing of the closure of the temporary access
to and from Blunder Road. Subparagraph (g) is primarily concerned with pedestrian
39 T2-34 ll 1-10.
40 Exhibit 12, p 9, paras 43-45.
41 Opposite proposed Lots 16 and 17; See generally T3-21 ll 30-46 and T3-22 ll 1-25.
42 Mr Perkins evidence at T4-19 ll 31-45; Mr Holt evidence at T4-49 ll 28-31; Mr Brown evidence at
T4-78 ll 35-47 and T4-79 ll 1-20.
43 Exhibit 5.
44 Ibid, pp 3-4, para 4.1.
-- 12 of 27 --
13
and cyclist access to park areas. It is not necessary to go into the evidence of
Mr Williams in detail insofar as the issues raised in subparagraphs (d), (e), (f) and (h)
inclusive are concerned. That is so because, as already identified, the temporary
access issue is not of itself a reason for refusal. In his individual report, Mr Douglas,
under the heading “conclusion” stated:45
“The proposed subdivision results in unnecessary staging issues that are
likely to:
(a) Significantly extend the period over which the temporary left-
in, left-out driveway to Blunder Road will be required to service
residents on the Subject Land, noting that future residents of
any subdivision of Lot 3 will also have to rely on the temporary
left-in, left-out driveway to Blunder Road, at least until Lot 4 is
developed.
(b) Require Lot 4 to be developed to provide the proposed local
park that was previously indicated on the Subject Land;
(c) Be quite circuitous and less safe for pedestrians (including
children) to access the park, particularly if Lot 4 develops prior
to Lot 3; and
(d) Increase the likelihood that such pedestrians will have to walk
along the Blunder Road verge which currently does not have a
formed footpath and would also require pedestrians to cross the
driveways to the commercial centre currently under
construction.
In my opinion, the proposed subdivision therefore does not provide for
development to be carried out in an orderly sequence nor is it well
integrated with surrounding land uses and infrastructure.
The proposed subdivision does not contribute towards a connected and
permeable network of roads and walking and cycling routes and it does
not provide a high level of internal accessibility nor good connections for
local vehicles, pedestrian and bicycle networks.” (Emphasis added)
[41] As already identified, according to Mr Douglas, absent a condition being imposed to
provide for future access to the northern boundary of Lot 4, the proposed development
ought be refused. In this context, Mr Douglas in particular opines that the existing
proposal is in material “conflict” with the Overall Outcomes (OO) 3(a), 3(o) and 3(h)
of the Emerging Community Zone Code46 and Performance Outcomes (PO) 10 and
11 of the Subdivision Code of the planning scheme.47
45 Exhibit 12, paras 38 – 40.
46 Exhibit 9, volume 2, pp 254 – 255.
47 Ibid, pp 314 – 316.
-- 13 of 27 --
14
[42] The Overall Outcomes are concerned with well planned, orderly, integrated and
connected development having regard to existing land uses and infrastructure (such
as roads and existing road networks). PO10 and PO11 relevantly provide:
“PO10
Development ensures that the transport network and all its elements is
designed to:
(a) have a clear hierarchal structure using the existing network
classification;
(b) provide a high level of internal accessibility and good external
connections for local vehicle, pedestrian and bicycle networks;
(c) include a minor road network that creates convenient and safe
movement between uses and to higher order roads;
(d) contribute to the bicycle network….
PO11
Development provides a transport network which has permeability,
connectivity and safety for vehicles, pedestrians and cyclists.”
[43] Having regard to the evidence of both traffic engineers I am left with little doubt that
the development as presently proposed would result in material non-compliance with
OO3(h) and PO’s 10 and 11 for the reasons identified by Mr Douglas.
[44] In addition to the connectivity and integration problems resulting from the failure to
provide a road connection point at the northern boundary of Lot 4, the failure to do
so is also likely to delay the closure of the temporary access to Blunder Road.
Additionally, the notional relocation of the proposed park to the northern side of
Brookside Street tends to emphasise the need for a safer and more convenient internal
route to that park for pedestrians and cyclists. Until access through Lots 3 and/or 4
is available to the park, pedestrians and cyclists would be required to travel along the
verge of Blunder Road and then Brookside Street.
[45] As already identified, the level of non-compliance with relevant traffic assessment
benchmarks would warrant refusal of the current proposal. However, a relevant
matter for the purposes of the Planning Act would clearly involve the consideration
of whether an appropriate condition might not satisfactorily address those areas of
non-compliance.48 On balance, I have reached the conclusion that the imposition of a
condition securing access to the northern boundary of Lot 4 would adequately address
the area of non-compliance identified.
48 Planning Act 2016 (Qld) s 60(2)(d).
-- 14 of 27 --
15
[46] First, such a condition would be more likely to increase the likelihood of bringing
forward the closure of the temporary access arrangements. As Mr Williams stated,
“Lot 4, controls that timing”.49 Associated with that is that, in the event that Lot 3
were developed before Lot 4, the potential for increased traffic volumes utilising the
temporary access could be, if not entirely avoided, then at least likely be more short
lived. Another associated likely consequence is that internal access for pedestrians
and cyclists to the commercial development to the south and any future park would
occur sooner than if no such condition was imposed. That is, the use of Blunder Road
for access to those facilities would be shortened. A result also considered by Mr
Williams to be desirable.50
[47] There can be little room for doubt that an access point to Lot 4 is much more likely
to provide for orderly development of the remaining undeveloped land.51 Finally, no
traffic matters or reasons exist that would prevent the imposition of such a condition.
A matter also accepted by Mr Williams.52
[48] Turning to the evidence of the town planners. In respect of OO3(h), Mr Perkins was
of the opinion that the proposed development was consistent with that outcome.53 Mr
Holt was of a similar view.54 However, both Mr Perkins and Mr Holt expressly stated
that in respect of the issues raised under those performance outcomes concerning the
transport network, they would defer to the traffic engineers.55 Insofar as there may
be tension between the evidence of Mr Douglas and the town planners regarding
integration and connectivity of motor vehicle, pedestrian and cycling traffic, I prefer
the evidence of Mr Douglas.
[49] To conclude the discussion on this topic I would make three final observations. First,
to secure access to the east of the subject land through to Bi Em Street would be
entirely consistent with TPG’s own Master Plan.56 Second, it is accepted by
Brookside that, with appropriate conditions in place, the temporary access
arrangements proposed might not warrant refusal.57 Lastly, during final submissions,
49 T1-53 ll 20-24.
50 T1-56 ll 38-47.
51 Exhibit 12, p 9 per Mr Douglas; Mr Williams’ evidence at T1-57 l 40-46 and T1-58 ll 1-9.
52 T1-51 ll 1-22.
53 Exhibit 4, para 91.
54 Ibid, para 92.
55 Ibid, paras 109(c) and 110(c).
56 Exhibit 7, p 15.
57 Appellant’s written submissions, paras 3.52-3.54.
-- 15 of 27 --
16
Mr Houston, counsel for TPG, stated that if I were to determine that road connection
to Lot 4 was “appropriate”, that he had instructions that his client would have no
objection to the imposition of an appropriate condition to accommodate that
outcome.58 For the reasons given, I have reached the conclusion that a condition
formulated to ensure road connectivity from the subject land to Bi Em Street in the
manner contemplated in the TPG Master Plan ought be imposed.
The remaining planning issues
[50] Disagreement existed between Mr Perkins and Mr Holt on the one hand and
Mr Brown on the other in respect of a number of the elements of the planning scheme.
It is no longer necessary to resolve any dispute between the town planners insofar as
stormwater and/or bushfire risk is concerned, as it is accepted that neither individually
nor together would those matters necessitate refusal of the proposed development.
The remaining issues would then appear to be:
1. The pattern and type of the development proposed including lot sizes;
2. Whether, leaving aside the traffic issues already dealt with, the proposed
development constitutes an orderly and sequential pattern of development;
3. Whether, leaving aside road/traffic matters the proposed development
provides an appropriate response to other urban utilities including water,
sewerage, electricity and telecommunications; and
4. The location of any future parkland.
[51] Insofar as all but the last matter identified above are concerned, having determined
the traffic issue in the manner that I have, I do not consider it necessary to deal with
the evidence of the planners other than to state that I agree with the evidence of Messrs
Perkins and Holt that those objectives of the planning scheme concerning the other
remaining matters would be adequately met by the proposal. To the extent that there
may be concerns about lot size/density, Mr Brown conceded that these were lower
order matters that would not warrant refusal.59 As Mr Skoien, counsel for Brookside,
accepted in closing submissions, the two key issues were “traffic and park”.60
58 T5-4 ll 27-37.
59 T4-95 ll 29-40. See also, appellant’s written submissions, para 3.43 (re housing mix and lot sizes)
and T5-11 ll 6-23.
60 T5-11 ll 1-5.
-- 16 of 27 --
17
[52] As to the location of a park, the public’s expectations would have been informed by
the Neighbourhood Plan, the Local Government Infrastructure Plan (LGIP) and the
Priority Infrastructure Plan (PIP). Notwithstanding that the structure plan received
by the Council on 31 January 2013 which was lodged by Brookside is not a plan that
has any statutory force, it would not be unreasonable to expect that that plan might
not have also had an effect on the public’s expectations. Both the Doolandella
Neighbourhood Plan (North and South) identify a future park on the subject land.61 I
would also observe here that notwithstanding the fact that, in the most recent iteration
of the Doolandella Neighbourhood Plan, the proposed district park identified on the
south-western corner of Crossacre Street and Blunder Road has been deleted, and the
location of a future park broadly located on the subject land was retained.62 In the
Infrastructure Plan, an indicative location for a park acquisition is located south of
the subject land, broadly speaking, at the intersection of Lots 3, 4 and 9.63
[53] Broadly consistent with the park location identified in the neighbourhood plans, the
structure plan lodged by Brookside in the furtherance of its proposed development,
placed the park at the intersections of lots 2, 3 and 4, but primarily on the subject
land.64
[54] Of course, the public would recognise that the location of any future park as identified
in any of the above mentioned documents was meant to be indicative only. Public
expectations would also, in my view, be influenced by adherence to, or departure
from those planning documents. As was identified by the Council, there have been a
number of material departures from the neighbourhood plans. These include the
development of the Doolandella Childcare Centre, the development of the service
station and convenience centre on the north-eastern corner of Blunder Road and
Brookside Street and the approval for multiple dwellings to the east of the subject
land in land previously zoned as rural.
[55] That such flexibility existed was recognised by Mr Skoien in final submissions, where
he said in respect of the park:65
61 Exhibit 7, pp 23 and 24.
62 Exhibit 10, p 125.
63 Exhibit 7, p 25; See also Exhibit 10, p 69.
64 Exhibit 7, p 16.
65 T5-18 ll 24-37.
-- 17 of 27 --
18
“Here, for instance, as the appellant suggest (sic), it might be a very sensible
outcome for it all to be moved to the eastern end of lot 2, and that might be
something that, for instance, a determination of this court could stand in the
shoes of the assessment (manager) could (sic) determine as being a location
for the park. And that may be able to be used in substitution for what’s
identified in the planning authority in the neighbourhood planning process.
…
In or around Lot 19. What, in my submission, it doesn’t amount to is a
developer coming along and saying ‘here’s a structure plan where we suggest
that somebody else should put the park on their land and that’s the way we
should approach it’. That is not a determination of a location in accordance
with development assessment process, in my submission….”
[56] The reference to Brookside’s “suggestion” is a reference to what was referred to as a
“potential solution” in Brookside’s written submissions when, insofar as the park was
concerned, it was submitted:66
“There is, of course, a sensible and rational solution to the issues raised by
the Appellant in this appeal, ….
Second, proposed Lot 17, proposed Lot 18 and proposed Lot 19 can be
dedicated as local park, being trunk infrastructure, totalling some 5,000m2.
That local park would be immediately connected to the pedestrian and
bicycle access to the boarder locality, via the path to Hanley Place, would
have a road frontage for its full width, and would ultimately be connected
directly to the surround road network via Bi Em Street upon the development
of Lot 4.
That dedication would allow Council to make a decision (as planning
authority) about whether it wishes to expand the local park (perhaps doubling
it in size) when Lot 4 is developed. That dedication would enable the co-
respondent to receive credits for the provision of trunk infrastructure in
accordance with the Council’s long-term planning for that infrastructure.
Whether the co-respondent would make such amendments to the plan of
development, or agree to the imposition of conditions to require such
amendment, is a matter that only the co-respondent can answer.” (Footnotes
deleted)
[57] Each of the town planners were in agreement that a local park east of Blunder Road
and north of Brookside Street was a desirable planning outcome. The dispute centred
around where that park should be located. That question was, to a material extent, to
be answered by reference to, in particular, accessibility, area and public expectations.
By reference to the neighbourhood plan in particular, Mr Brown was of the opinion
that the failure to provide for a park area incorporating at least part of the subject land,
constituted a material non-compliance with the Neighbourhood Plan Code.67 Mr Holt
and Mr Perkins disagreed.
66 Appellant’s written submissions, paras 3.52, 3.55, 3.56 and 3.57.
67 For example see Exhibit 4, p 54, paras 126-128.
-- 18 of 27 --
19
[58] In their joint expert report the town planners identified a number of “Key Issues”.
Insofar as the park was concerned, they reported:68
“Provision of Park – Notice of Appeal Paragraph 12(d) and Paragraph 14(c)
- Specific Outcomes SO1 and SO3 of Element 2.4 of section 3.4.5 – Strategic
Framework; Notice of Appeal 14(c); (d); (e); (f); (g); Notice of Appeal
Paragraph 14(j) – Doolandella Neighbourhood Plan 7.2.4.2.2 Overall
Outcomes (3)(a) and (3)(c) – Notice of Appeal.
Paragraph 14(I); Subdivision Code – 9.4.10.2, Overall Outcome (2)(h);
9.4.10.3 Performance Outcomes PO10, PO21 and PO29.
Relevant Matters – grounds to justify approval despite any potential
conflicts with the planning scheme.”
[59] Specific Outcome 1 is designed to ensure that Brisbane has a range of accessible
multipurpose community facilities, including parks, which meet the physical, social
and cultural needs of the local and wider community. Land use strategies include that
developments accord with the social infrastructure identified in priority infrastructure
plans, appropriate facilities are located in or near centres and public transport stations
or, are encouraged to cluster around existing facilities and link with active travel and
public park networks.69 Specific Outcome 3 is concerned with the need for parks and
open space to provide for a diversity of experience. Land use strategies in respect of
this outcome include, but are not limited to, ensuring that parks are planned and
managed to provide for a diversity of experiences.70
[60] Turning then to the Doolandella Neighbourhood Plan, s 7.2.4.2.2 identifies the
purpose of the plan and relevantly provides:71
“(1) The purpose of the Doolandella Neighbourhood Plan Code is to
provide finer grained planning at a local level for the Doolandella
Neighbourhood Plan area;
(2) The purpose of the Doolandella Neighbourhood Plan Code will be
achieved through Overall Outcomes;
(3) The Overall Outcomes for the Neighbourhood Plan are:
(a) Development creates functional and integrated communities;
…
(c) Open space, parks and recreational facilities meet the needs
of the community and are located in accessible locations that
are well connected within the neighbourhood plan area. …”
(Emphasis added)
68 Exhibit 4, pp 31-32.
69 Exhibit 9, V1, p 54.
70 Ibid, p 55.
71 Exhibit 9, V2, p 281.
-- 19 of 27 --
20
[61] Performance Outcome 5 relevantly provides that:72
“Development ensures that:
(a) the centre and adjoining park form a local community focus;
(b) the centre and adjoining park remain as an attractive and safe
informal meeting place by promoting high levels of integration
between the centre and the park and facilitating pedestrian movement
between the two sites.”
[62] Acceptable Outcomes include that:73
“Development provides park in the locations identified in Council’s Priority
infrastructure Plan and
Development involving buildings, pathways, landscaping and car parking
areas integrates the centre and park and facilitates casual surveillance of the
park by:
(a) maximising buildings fronting the park and providing direct
pedestrian connections…”
[63] Turning then to the Subdivision Code, s 9.4.10.2 identifies its purpose will be
achieved through a number of overall outcomes including that subdivision
development be designed to effectively integrate with existing and planned
infrastructure and services.74 One of the elements of the intended development of a
highly connected and legible neighbourhood is that parks be centrally located.75
Performance Outcome 29 has a similar theme in that it is expected that:76
“Development provides land for park purposes which is well distributed and
located and is consistent with:
(a) the nature of surrounding parks;
(b) the needs of occupants and visitors;
(c) the safety and connection to the transport network.”
[64] An acceptable outcome is that “development provides land for park purposes which
is in compliance with the Park Planning and design code and the Priority
Infrastructure Plan”.77
72 Exhibit 9, V2, p 284.
73 Ibid, p 284.
74 Ibid, p 309.
75 Ibid, p 319, PO21(e).
76 Ibid, p 323.
77 Ibid, p 323.
-- 20 of 27 --
21
[65] It was Mr Perkins’ opinion that the location of the park as proposed by TPG created
no meaningful conflict with the relevant planning documents. His basis for that
conclusion could be summarised by reference to the following matters:78
“The proposal does not provide land for park purposes but the covering letter
to the decision notice…identified that ‘Brisbane City Council has levied
infrastructure charges for the transport, community purposes and
stormwater trunk infrastructure network. The provision charges notice has
been attached to the decision notice’ (Subdivision Code PO29).
While the Doolandella Neighbourhood Plan Code indicates a ‘Future Park’
on the centre of the site, the more detailed, recent and relevant priority
infrastructure plan map (and more recently the Local Government
Infrastructure Plan map) indicate that the site for Park Acquisition –
Indicative Location is not located on the site but is instead on land further to
the south where it also corresponds to a higher concentration of land mapped
as containing regulated vegetation.
The indicative location of a future park to the south of the site as indicated
by the Priority Infrastructure Plan and the Local Government Plan and the
Draft Structure Plan is more desirable and logical for the following reasons:
(a) The LGIP location to the south of the subject land is closer to a higher
order road and can be designed to provide an appropriate level of road
frontage consistent with appropriate principles and would comply
with overall outcome (3)(c) of the Doolandella Neighbourhood Plan
Code;
(b) The LGIP location could also accommodate the retention of
Regulated Vegetation;
(c) The LGIP location would have the potential to comply with the
Desired Standard of Service for Recreation (Urban) whereas the
subject site is not big enough with an area of approximately 1.423
hectares and a width of approximately 60 metres.
(d) The Neighbourhood Plan Code identifies that development is to
provide park in locations identified in Council’s Priority
Infrastructure Plan. This outcome acknowledged the potential that
more detailed infrastructure planning would supersede park locations
shown in the Neighbourhood Plan Code as is the case here.”
(Emphasis added)
[66] Mr Holt did not express a final view about whether the location for the park proposed
by Brookside is in conflict with the planning scheme but nonetheless agrees with the
opinions of Mr Perkins. He reports:79
“Mr Holt is of the opinion the development meets the needs of the
community expectations of facilitating development within an area that has
access to existing or planned open space, parks or recreation facilities. Mr
Holt notes the significant growth within the area has increased the amount
of people living within the area and highlights the planned park…Mr Holt is
also of the opinion each dwelling lot will provide private outdoor open space
78 Exhibit 4, pp 50-51.
79 Ibid, pp 53-54, paras 124-125.
-- 21 of 27 --
22
which will provide individual open space opportunities for the future
residence.
Mr Holt agrees with Mr Perkins that while the Doolandella Neighbourhood
Plan Code…indicates a ‘future park’ on the centre of the site, however the
LGIP has progressed to a greater detail to identify and investigate the most
practical accessible and functional location for a park within the area on land
further to the south where incorporating a higher concentration of existing
and map regulated vegetation, provides greater opportunities for
connectivity within a central pocket of land either approved for development
or planned for development and will provide a greater level of compliance
with the Desired Standards of Service for Recreation (Urban) for size and
locational requirements for park areas.”
[67] Mr Brown disagrees with the opinions of Messrs Perkins and Holt. In his court report,
after considering a number of parks in the district he concluded:80
“City Plan 2014 informs community expectations as to the pattern of future
development that can be reasonably anticipated. I cannot agree with Mr
Perkins… or for that matter the opinions of Mr Holt…that in effect, the
provisions of the Local Government Infrastructure Plan in relation to the
suitable location for a local recreation park (which is an indicative location
only), are to be preferred over the planning for park location within the
Doolandella Neighbourhood Plan… I consider that the planning for the
locality and the community expectations would be derived from the more
detailed provisions of City Plan 2014 – in this case the Doolandella
Neighbourhood Plan Code.”
[68] While not necessarily agreeing with Mr Brown’s opinion that community
expectations would be set by the Doolandella Neighbourhood Plan Code location for
the park, I am nonetheless able to accept that either by reference to the
Neighbourhood Plan or the relevant infrastructure plans, that community expectations
would be for a more centrally located park. The infrastructure plans referred to by
both Mr Perkins and Mr Holt, while having an indicative location south of that
identified in the Neighbourhood Plan, nonetheless identifies a location more central
than that proposed.
[69] Adopting the language used in s 45(5) of the Planning Act, under the heading
“relevant matters” the town planners set out their opinions. Insofar as they are
concerned with the park, they are:81
“Mr Perkins opinion
If there are any conflicts with the planning scheme (noting that Mr Perkins
does not consider that there are), he considers that the following represent
relevant matters that may justify the approval despite any conflicts:
80 Exhibit 11, p 4, para 13.
81 Exhibit 4, p 55, paras 129-131.
-- 22 of 27 --
23
(a) The approved development represents a logical and appropriate
extension to the existing pattern of development and uses in the
surrounding area;
(b) The proposed residential subdivision is consistent with community
expectations for the site and is consistent with the lot sizes and layouts
present in the surrounding area;
(c) The Neighbourhood Plan envisaged that it would be the Priority
Infrastructure Plan (now Local Government Infrastructure Plan) that
would determine final park locations;
(d) It is apparent that a flexible approach has been adopted in the
implementation of the Neighbourhood Plan’s figures (a) and (b) as
evidenced by a comparison between the outcomes mapped on those
figures and those evident on the ground and in current approvals…
Mr Holt’s opinion
Mr Holt is of the opinion if the court considers there is a conflict with the
applicable Planning Scheme provisions, Mr Holt considered there are
sufficient grounds to justify the approval despite any conflicts as follows:
(a) The proposed development integrates with the immediate and
surrounding areas and forms a logical use of the land…
(b) ….
(c) The proposed development aligns with community expectations and
development outcome that is reasonably expected within an Emerging
Community Zone and potential development area in accordance with
the Doolandella Neighbourhood Plan;
(d) The Local Government Infrastructure Plan has provided a desired
location for a future park and the proposed development will be located
within walking distance to that future park.
Mr Brown’s opinion
Mr Brown is of the opinion that in a number of respects as outlined within
(the) report the proposed development is non-compliant with the applicable
Planning Scheme provisions and does not consider that there are relevant
matters sufficient to overcome the non-compliance in relation to matters
including the lack of provision of park…”
[70] It is tolerably clear that both Mr Holt and Mr Brown addressed the issue of “relevant
matters” for the purposes of s 45(5) of the Planning Act as if they were carrying out
a “sufficient grounds” exercise for the purposes of the SPA.
[71] On balance, when all relevant matters are taken into account, I am sufficiently
satisfied that the location of a park in the area indicted in the TPG Master Plan is an
acceptable outcome82 and would not warrant refusal.
[72] The reasons for reaching this conclusion are as follows. First, the future park is
identified in the Neighbourhood Plan as a district park. Under the planning scheme,
82 Exhibit 7, p 15.
-- 23 of 27 --
24
an area of 0.8ha for parks is identified within table 5.4.6.1.1 concerned with the “land
provision standard for the public parks network.”83 Under the schedule of works for
future trunk infrastructure adopted by the Council on 13 May 2016, an area of 1ha for
park purposes is identified for acquisition at a cost of $1,576,592.84 As Mr Brown
appeared to accept, the 0.5ha park area originally contemplated in the Neighbourhood
Plan had been overtaken by more contemporary planning objectives.85
[73] The location identified in the infrastructure plan is no longer available given the
commercial development to the south. The nearest alternate option would therefore
be to locate the park either wholly within Lot 3 or wholly within Lot 4 or partly within
both. Of itself, the whole of Lot 3 would only be capable of accommodating 0.872ha.
In all probability then, it would be more likely than not that any future park close to
that identified in the infrastructure plan would be spread over both Lots 3 and 4 or,
located wholly within Lot 4.
[74] An equal sharing of the park area over both lots would leave only approximately
4000m2 of Lot 3 available for its intended land use being for low density residential
multiple dwellings.86 That would not be a desirable planning outcome in my view.
[75] The second matter, which is directly associated with that discussed above, is that if
the whole or a major part of the future park was located within Lot 4, that would have
a similar impact on the planned use for that lot. Of course the location identified in
the proposed development would have the same consequences, however, as both Mr
Perkins and Mr Holt recognised, the proposed location would, consistent with what
occurred in the Redhead Street residential development, facilitate the integration and
retention of the category B regulated vegetation located at the south-eastern portion
of Lot 4.87 This is again a more desirable planning outcome.
[76] Of course, if the park was to be only 0.8ha instead of 1ha the consequences referred
to above would be lessened but would not, in my view, have any material impact on
the potential negative outcomes to which I have referred. Further, the more
83 Exhibit 9, V1, p 125.
84 Exhibit 22, p 9.
85 T4-87 ll 27-40.
86 Exhibit 7, p 23.
87 Ibid, p 26.
-- 24 of 27 --
25
persuasive evidence on this matter is that contained in the infrastructure plan. As Mr
Brown recognised, the 0.8ha area is the minimal requirement.88
[77] Consistent with one of the objects of the Neighbourhood Plan concerned with parks,
the proposed location would have good access via Brookside Street and Bi Em Street
and, in due course, via the extension of Sallyanne Street.89Another planning benefit
associated with the proposed location of the park is, as Mr Brown accepted,90 that it
would be adjacent to the commercial development on the corner of Blunder Road and
Brookside Street. That said, I do not consider that this would result in any benefits
concerning surveillance and security.
[78] While not of great weight, as Mr Brown put it, “a miniscule benefit”,91 is that locating
the park wholly in Lot 4 would require the acquiring authority to only have to deal
with one property owner.
[79] It is true, as Mr Skoien pointed out, that the proposed development would place the
park even further towards the southern extremity of the likely catchment area.92 That
however has to be seen in context. The proposed location of the park would be only
in the order of between 150m and 200m further from the indicative location shown
on the infrastructure plans, the Neighbourhood Plan and that part of the subject land
to the east identified by Mr Skoien in both his oral and written submissions. That
additional distance would have little if any significance for those intending to use the
park and arrive by motor vehicle or bicycle. It might be a deterrent to those intending
to walk to the park but that also has to be seen in the context of the existing and
proposed development in the near locality, including that on the subject land and to
the south of Brookside street.
[80] Before concluding my consideration of the location of the park, there are three further
matters that I should address. First, at no time did I understand Mr Brown to be
critical of the proposed location for the park on the basis of it being in a poor location,
or otherwise incapable of meeting the needs of the community. His criticism seemed
to be focussed on it not being in line with public expectations.93 Indeed, during cross-
88 T4-88 ll 8-17.
89 See Exhibit 7, p 15.
90 T4-93 ll 33-45.
91 T4-89 ll 36-47.
92 See for example Exhibit 7, p 15.
93 See Exhibit 11, p 4, para 13.
-- 25 of 27 --
26
examination he agreed that, insofar as the park was concerned, that was his major
concern as a town planner.94 Given that the location of the park in the relevant
planning document is indicative only, I do not find this to be a particularly persuasive
consideration for two reasons. First, the relatively small shift in the geographical
location of the park. Second, and somewhat associated with the first point, given the
other developments to which I have referred95 which are at odds with those plans, I
do not consider that the public expectations would be greatly offended by the change
in location contemplated.
[81] The second matter is that Mr Brown asserted that there was non-compliance with, in
particular, OO3(c) of the Neighbourhood Code.96 Leaving aside the issue of public
expectations, Mr Brown did not say that the proposed park could not meet the needs
of the community. Also, for the reasons given, the proposed location would be an
acceptable one with connectivity within the plan area. I am not persuaded by Mr
Brown’s evidence on this topic.
[82] The final matter is that raised by Mr Skoien in final submissions concerning the
location of the park on the eastern portion of the subject land. Leaving aside any
stormwater damage issues that might arise, there is, as far as I am aware, no evidence
in support of that location, save perhaps for the indicative locations in the
infrastructure and neighbourhood plans. By that I mean it was not a location
advocated for by Mr Brown and nor was it one taken up with Mr Holt. And, when
this option was put to Mr Perkins, he clearly had concerns, legitimate ones in my
view, about it being a workable solution.97 On the evidence before me, I do not
consider setting aside the proposed Lot 19, even incorporating proposed Lots 15 to
18, would be likely to result in a planning outcome any better than that proposed.
[83] Insofar as there might be a departure from public expectations created by the
infrastructure and/or Neighbourhood Plans, I do not consider it to be unacceptably so.
That is because, to the extent that there may be any tension in that regard, the more
desirable planning outcomes to which I have referred more than offset those
expectations.
94 T4-16 ll 10-47; Exhibit 4, p 40, para 77(b).
95 At para [54].
96 Exhibit 4, paras 126-128.
97 T3-68 ll 1-39.
-- 26 of 27 --
27
Conclusion
[84] For the reasons given, subject to an appropriate condition or conditions concerning
access to Bi Em Street via Lot 4 being imposed, I do not consider that there are any
grounds that would warrant refusing the application. Also, having regard to the
reasons given, I do not consider it necessary to deal with the matters discussed by the
town planners under the heading “relevant matters” in their joint expert report.
[85] Accordingly, I will publish my reasons but will refrain from making final orders until
hearing further from the parties.
-- 27 of 27 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2019/033