Cherwell Creek Coal Pty Ltd v BHP Queensland Coal Investments Pty Ltd & Ors (No 19) [2019] QLC 13
LAND COURT OF QUEENSLAND
CITATION: Cherwell Creek Coal Pty Ltd v BHP Queensland Coal
Investments Pty Ltd & Ors (No 19) [2019] QLC 13
PARTIES: Cherwell Creek Coal Pty Ltd
(ACN 063 763 002)
(applicant)
v
BHP Queensland Coal Investments Pty Ltd
(ACN 063 763 002)
QCT Resources Pty Ltd
(ACN 010 808 705)
BHP Coal Pty Ltd
(ACN 010 595 721)
Mitsubishi Development Pty Ltd
(ACN 009 779 873)
QCT Investments Pty Ltd
(ACN 010 487 831)
Umal Consolidated Pty Ltd
(ACN 000 767 386)
QCT Mining Pty Ltd
(ACN 010 487 840)
(respondents)
FILE NO: MRA1332-08
DIVISION: General division
PROCEEDING: Requests from experts for further information in Court
Managed Expert Evidence (CMEE) process
DELIVERED ON: 7 March 2019
DELIVERED AT: Brisbane
HEARD ON: Submissions closed 1 February 2019
HEARD AT: Heard on the papers
PRESIDENT: FY Kingham
ORDER: The requests for information are declined.
CATCHWORDS: CIVIL PROCEEDINGS IN STATE AND TERRITORY
COURTS – PROCEDURE – whether to require the parties
-- 1 of 6 --
2
to respond to requests for information made by expert
witnesses during a meeting of experts in a Court Managed
Expert Evidence (CMEE) process – where two distinct
requests were made and the experts did not agree – where the
Court declined the requests
EVIDENCE – EXPERT EVIDENCE – where the experts
engaged by the parties made requests for further information
during a meeting of experts – where the information did not
relate to key facts relevant to issues in dispute – where the
Court considered it was not necessary or desirable for the
information to be provided to the experts – where the Court
declined the requests
Cherwell Creek Coal Pty Ltd v BHP Queensland Coal
Investments Pty Ltd & Ors (No 17) [2018] QLC 45,
considered
APPEARANCES: Holding Redlich Lawyers for the applicant
Allens for the respondents
[1] One of many issues that arises in this claim for compensation by Cherwell Creek Coal
Pty Ltd, for the loss of opportunity to develop its proposed mine, is the probable
conditions for and costs of road access for transporting coal from the proposed mine.
[2] Three expert witnesses1 are preparing a joint report to the Court about that. They have
made two requests for further information through Member Stilgoe, in her capacity
as the Convenor of the Court Managed Expert Evidence process in this case.
[3] In a recent decision in this case, I canvassed the relevant features of the Court’s rules
and procedures in relation to expert evidence.2 I will not repeat those passages here.
However, I have taken into account the features I identified in my earlier decision in
deciding these requests.
[4] The expert witnesses do not agree the information is necessary to prepare their joint
expert report and different experts have joined in or not opposed each request. The
Court may direct the parties to respond to a request, even if it is not unanimous, if
providing the information is necessary or desirable in preparing expert evidence for
the hearing.
1 Mr Thatcher and Mr Trevilyan (engaged by Cherwell Creek) and Mr Runge (engaged by BMA).
2 Cherwell Creek Coal Pty Ltd v BHP Queensland Coal Investments Pty Ltd & Ors (No 17) [2018]
QLC 45, [7]–[12].
-- 2 of 6 --
3
[5] Cherwell Creek supports a positive response to one of the information requests, and
takes no position on the other. The respondents (BMA) oppose the Court directing
the parties to provide the information requested, regardless of who made it.
[6] The first of the two requests relates to Cherwell Creek’s proposition that it would
have been able to “toll wash” coal from its mine at the Carborough Downs’ mine Coal
Handling Preparation Plant. The second request is for details of any road conditions
or agreements that applied to the Caval Ridge mine. It is not necessary for me to
descend to the detail of the requests or the experts’ reasoning in making the requests.
The Convenor has recorded that fully in her filed report.
Carborough Downs’ intersection
[7] It is standard industry practice to use a CHPP to wash, prepare and sort coal by grades
for transport to market. Many mines have an onsite CHPP. Cherwell Creek says it
would have used the CHPP on the nearby Carborough Downs mine for that purpose.
[8] Mr Runge has asked for information about the state of the intersection of the
Carborough Downs mine with the Peak Downs Highway as at April 2009, when
Cherwell Creek alleges it would have commenced bulk sampling of coal. Neither Mr
Thatcher nor Mr Trevilyan think the information is necessary to complete the joint
expert report, although Mr Trevilyan does not oppose the request.
[9] Mr Runge’s evident concern is that the operations on Carborough Downs might affect
its capacity to receive coal from Cherwell Creek, resulting in additional cost to
Cherwell Creek. He informed the CMEE Convenor that the internal operations of
Carborough Downs would determine whether a left or right hand turn off the highway
was required. Both now exist. However, if there was no left hand turn in 2009, he
estimates it would have costed in the order of $1m to construct.
[10] Whether Cherwell Creek would be required to provide (and pay for) a left hand turn
depends on (at least) the following:
that there would have been operational constraints for Carborough Downs in
receiving coal from Cherwell Creek’s mine (including as a result of restricted
haulage hours taking into account school opening and closing times);
that there was no left hand turn in existence in 2009;
-- 3 of 6 --
4
that the Department of Transport and Main Roads would have required a left-
hand turn off the highway to the Carborough Downs CHPP; and
that Cherwell Creek would be required to pay the cost of providing that
facility.
[11] It is understandable that Mr Runge would prefer to eliminate uncertainty about
matters that might affect his opinion. Necessarily, there will be a great deal of
uncertainty in assessing Cherwell Creek’s hypothetical proposition in retrospect. The
information requested by Mr Runge will not resolve all uncertainty. For example, it
will not resolve whether the department would have required an upgrade and, if so,
who would bear the cost of the upgrade.
[12] I am also conscious that the parties would have to obtain the information from
witnesses who are not their employees or contractors, but third parties with no interest
in the proceedings. I would not require the parties to trouble such witnesses for further
information unless persuaded there was some real utility in doing so.
[13] Further, unlike my previous decision, this matter is not central to the case and it is not
clear whether any of the factors that I have identified are now or will be in issue at
the hearing. If there are relevant disputes, the Court will decide them, not the experts.3
[14] Whether in their own report or in a joint expert report, the Court expects expert
witnesses to identify any matters that might affect their opinion and the consequence
of those matters for their opinion. In a joint expert report, where the experts differ
about that, they must make that clear for the Court.
[15] That is consistent with the requirement for experts to identify the factual basis for
their opinion and the reasoning process that leads to their opinions.4
[16] Mr Runge accepts he is in a position to address different scenarios in a joint expert
report. I consider the information is not necessary or desirable for the expert witnesses
to prepare their joint expert report.
3 Makita (Australia) Pty Ltd v Sprowles (2001) 52 NSWLR 705, [77], [87].
4 Ibid [85].
-- 4 of 6 --
5
Caval Ridge information
[17] Mr Trevilyan and Mr Thatcher have made the second request. They would like to
have the conditions of approval and related documentation about road access and road
works for the Caval Ridge mine, constructed between 2012 and 2014. They identified
the following parallels between the Caval Ridge mine and the proposed Cherwell
Creek mine:
both sought to use AB-triples; and
the tonnages transported for the construction phase of the Caval Ridge mine
are comparable to the initial sample pit tonnages asserted for the proposed
Cherwell Creek mine.
[18] There is some inconsistency in the reasoning of Mr Trevilyan and Mr Thatcher in
support of the request. Mr Trevilyan said that it might help decide whether Cherwell
Creek would be required to upgrade site access from the Dysart turnoff to the
proposed Cherwell Creek mine. Mr Thatcher said the experts agree an upgrade would
have been required and only the standard of upgrade is in dispute.
[19] BMA is not confident it could retrieve the requested information. Even if it could do
so, I have reservations about the relevance of the Caval Ridge conditions and
infrastructure to Cherwell Creek’s proposed mine.
[20] The question is what upgrade, if any, Cherwell Creek would have been required to
undertake had its mine proceeded as it said it had planned. Mr Trevilyan and Mr
Runge have already provided reports on the conditions and cost of road access and it
is not clear how information about Caval Ridge could resolve any differences between
them.
[21] There is a real prospect the experts and the Court might be distracted by the dispute
between the expert witnesses about whether the Caval Ridge mine is a relevant
comparator and, if so, how it might be adjusted to accommodate any points of
distinction.
[22] It is not clear whether the parties are in dispute about those matters. BMA says Caval
Ridge is not a relevant comparator. Cherwell Creek has taken no position on the
request.
-- 5 of 6 --
6
[23] In those circumstances, I am not satisfied that providing the information is possible
or that it is necessary or desirable for the expert witnesses to prepare their joint expert
report.
[24] I will not direct any party to respond to either information request.
FY KINGHAM
PRESIDENT OF THE LAND COURT
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QLC/2019/013