Bell v Brisbane City Council [2018] QCA 84 (2018) 230 LGERA 374; [2022] QPELR 289
SUPREME COURT OF QUEENSLAND
CITATION: Bell v Brisbane City Council & Ors [2018] QCA 84
PARTIES: KATE PETA BELL
(applicant)
v
BRISBANE CITY COUNCIL
(first respondent)
SUNLAND DEVELOPMENTS NO 8 PTY LTD
ACN 128 607 714
(second respondent)
CHIEF EXECUTIVE ADMINISTERING THE
SUSTAINABLE PLANNING ACT 2009
(third respondent)
FILE NO/S: Appeal No 6214 of 2017
P & E Appeal No 2868 of 2015
DIVISION: Court of Appeal
PROCEEDING: Application for Leave Planning and Environment Court Act
ORIGINATING
COURT:
Planning and Environment Court at Brisbane – [2017] QPEC 26
(Rackemann DCJ)
DELIVERED ON: 4 May 2018
DELIVERED AT: Brisbane
HEARING DATE: 30 November 2017
JUDGES: Sofronoff P and Philippides and McMurdo JJA
ORDERS: 1. Leave to appeal is granted.
2. The appeal is allowed.
3. Remit the matter to the Planning and Environment
Court, to be further considered according to law.
4. The first and second respondents are to pay the
applicant’s costs of and incidental to the application
for leave to appeal and the appeal in this court.
CATCHWORDS: ENVIRONMENT AND PLANNING – ENVIRONMENTAL
PLANNING – DEVELOPMENT CONTROL – MATTERS
FOR CONSIDERATION OF CONSENT AUTHORITY –
CONSIDERATION OF PARTICULAR MATTERS –
AMENITY AND COMPATIBILITY – PARTICULAR CASES
– where the second respondent sought and obtained approval
from the first respondent for a material change of use to
develop the former Australian Broadcasting Commission site
at Toowong for residential use – where the proposed development
is three towers that each significantly exceed the relevant
-- 1 of 19 --
2
height restrictions in the applicable planning scheme – where
the applicant lives on adjoining land and made a submission
about the development application to the first respondent –
where the applicant’s case is that the proposed development
does not comply with the planning scheme – where the
Planning and Environment Court concluded that there were
sufficient grounds, in the public interest, to justify the decision
to approve the proposed development despite the conflict with
the planning scheme – whether the Planning and Environment
Court’s conclusion resulted from errors of law by the judge
Integrated Planning Act 1997 (Qld), s 3.5.14
Local Government (Planning and Environment) Act 1990
(Qld), s 4.4(5A)
Planning Act 2016 (Qld), s 311
Planning and Environment Court Act 2016 (Qld), s 63, s 65, s 76
Sustainable Planning Act 2009 (Qld), s 313, s 326, s 498
Bruce v Caloundra City Council [2007] QPELR 571; [2007]
QPEC 46, cited
Clark v Cook Shire Council [2008] 1 Qd R 327; [2007]
QCA 139, cited
Elan Capital Corporation Pty Ltd v Brisbane City Council
[1990] QPLR 209, considered
Grosser v City of Gold Coast (2001) 117 LGERA 153;
[2001] QCA 423, cited
Lockyer Valley Regional Council v Westlink Pty Ltd [2013]
2 Qd R 302; [2012] QCA 370, cited
Nevtan Investments Pty Ltd v Belyando Shire Council [2008]
QPELR 326, cited
Palyaris v Gold Coast City Council [2004] QPELR 162;
[2003] QPEC 56, cited
Prettlejohn v Cairns Regional Council [2012] QPELR 485;
[2012] QPEC 23, cited
Titanium Enterprises Pty Ltd v Caloundra City Council
[2007] QPELR 154; [2006] QPEC 106, cited
Warringah Shire Council v Sedevcic (1987) 10 NSWLR 335,
cited
Weightman v Gold Coast City Council [2003] 2 Qd R 441;
[2002] QCA 234, cited
Woolworths Ltd v Caboolture Shire Council [2004] QPELR 550;
[2004] QPEC 15, cited
Woolworths Ltd v Warehouse Group (Aust) Pty Ltd (2003)
123 LGERA 341; [2003] NSWLEC 31, cited
Zappala Family Co Pty Ltd v Brisbane City Council (2014)
201 LGERA 82; [2014] QCA 147, cited
COUNSEL: D R Gore QC, with M Batty, for the applicant
G J Gibson QC, with N Loos, for the first respondent
C L Hughes QC, with M Williamson and J Lyons, for the
second respondent
J Brien for the third respondent
-- 2 of 19 --
3
SOLICITORS: Connor O’Meara Solicitors for the applicant
Brisbane City Legal Practice for the first respondent
McCullough Robertson for the second respondent
Norton Rose Fullbright for the third respondent
[1] SOFRONOFF P: I agree with the reasons of McMurdo JA and with the orders that
he proposes.
[2] PHILIPPIDES JA: I agree with the orders proposed by McMurdo JA for the reasons
stated by his Honour.
[3] McMURDO JA: This is an application for leave to appeal against the decision of
the Planning and Environment Court,1 in which the applicant unsuccessfully
challenged the approval of a proposed development on the former Australian
Broadcasting Commission site, on the riverside at Toowong. The second respondent
sought and obtained approval from the Council for a material change of use, under
which it would develop the land, mainly for residential use, by the construction of
three towers, two of 24 storeys and one of 27 storeys containing a total of 555 units.
[4] The applicant lives on adjoining land. She made a submission about the application
to the Council and was thereby entitled to appeal against its decision. On her case,
the development proposal, in many respects, did not comply with the Council’s
planning scheme. The Planning and Environment Court concluded that although the
non-compliance was not as extensive as the applicant had alleged, there was a “level
of conflict with a number of provisions, or parts of provisions of relevance to the
assessment of the subject application” and that the level of conflict was “significant.”2
[5] The assessment of the development application, both by the Council and by the Court,
was made under the now repealed Sustainable Planning Act 2009 (Qld) (“the SPA”).
Section 326(1) of the SPA provided that a decision to approve the development was
not to conflict with a “relevant instrument”, which was defined to include a planning
scheme,3 unless there were “sufficient grounds to justify the decision, despite the conflict”.
The term “grounds” was defined to mean “matters of public interest”.4
[6] The Court concluded that there were sufficient grounds, in the public interest, to
approve the proposed development notwithstanding its conflicts with the planning
scheme.5 By her proposed appeal, the applicant would challenge that conclusion,
arguing that upon a number of bases, it resulted from errors of law by the judge.6 One
of those errors is said to be that the judge was mistaken about the extent of the non-
compliance, because he erred in interpreting provisions of the planning scheme which
limited the height for any building on this site.
The planning scheme
[7] The application for approval required an “impact assessment” under the SPA,7 so that
it had to be assessed against the planning scheme.8 The relevant scheme is the Brisbane
1 Bell v Brisbane City Council & Ors [2017] QPEC 26 (“Judgment”).
2 Judgment at [381].
3 SPA, s 313(2)(e)(iii), s 326(2).
4 SPA, Schedule 3.
5 Judgment at [393].
6 Despite its repeal, the SPA continues to apply in this case: Planning Act 2016 (Qld), s 311.
7 Judgment at [8].
8 SPA, s 314(2)(g).
-- 3 of 19 --
4
City Plan 2014 (“the Scheme”), under which the site is within the Major Centre zone
and in the locality which is subject to that part of the Scheme, which is called the
Towong-Auchenflower Neighbourhood Plan (“TANP”).
[8] The Scheme contains many such neighbourhood plans. They contain a hierarchy of
provisions which are categorised as overall outcomes, performance outcomes and
acceptable outcomes. The categorisation is explained in Part 7, s 7.1(6) of the Scheme as
follows:
“(6) Each neighbourhood plan code identifies the following:
(a) the application of the neighbourhood plan code;
(b) the purpose of the neighbourhood plan code;
(c) the overall outcomes that achieve the purpose of the
neighbourhood plan code;
(d) the purpose and overall outcomes for each precinct;
(e) the performance outcomes that achieve the overall
outcomes of the neighbourhood plan code;
(f) the acceptable outcomes that achieve the performance
outcomes of the neighbourhood plan code;
(g) the performance and acceptable outcomes of a precinct
that achieve the overall outcomes of the precinct.”
[9] The purpose of the TANP is expressed in s 7.2.20.3.2 of the Scheme as follows:
“(1) The purpose of the Toowong-Auchenflower neighbourhood
plan code is to provide finer grained planning at a local level
for the Toowong-Auchenflower neighbourhood plan area.
(2) The purpose of the Toowong-Auchenflower neighbourhood
plan code will be achieved through overall outcomes including
overall outcomes for each precinct of the neighbourhood
plan area.”
[10] The overall outcomes for the TANP are prescribed by s 7.2.20.3.2, to include the
following:
“(3)…
(h) Development is of a height, scale and form which is
consistent with the amenity and character, community
expectations and infrastructure assumptions intended for
the relevant precinct, sub-precinct or site and is only
developed at a greater height, scale and form where there
is both a community need and an economic need for the
development.”
I will refer to this as overall outcome (3)(h).
[11] The overall outcomes for the sub-precincts including that within which this site is
found, are prescribed by s 7.2.20.3.2 to include the following:
-- 4 of 19 --
5
“(4) …
(h) Development on sites adjoining the Brisbane River
ensures the public access to the river, and buildings
adjoining riverfront public spaces include a lively blend
of retail, commercial, residential and community uses.”
I will refer to this as overall outcome (4)(h).
[12] Overall outcome (3)(h) is central to the applicant’s case. The judge found that the
height of the proposed buildings was not consistent with community expectations.
The corresponding performance outcome is expressed within s 7.2.20.3.3.A as follows:
“Development is of a height, scale and form that achieves the intended
outcome for the precinct, improves the amenity of the neighbourhood
plan area, contributes to a cohesive streetscape and built form
character and:
(a) …
(b) is aligned to community expectations about the number of
storeys to be built[.]”
I will refer to this as PO1(b).
In turn, the corresponding acceptable outcome is expressed within the same provision
as follows:
“Development complies with the number of storeys, building height
and the minimum site frontage in Table 7.2.20.3.3.B”,
with the notation that:
“Neighbourhood plans will mostly specify maximum number of
storeys where zone outcomes have been varied in relation to building
height. Some neighbourhood plans may also specify height in metres.
Development must comply with both parameters where maximum
number of storeys and height in metres are specified.”
I will refer to this as AO1.1.
[13] As the judge found, Table 7.2.20.3.3.B does not specify a maximum height, but it
does specify a maximum number of storeys, namely in this case, being one for the
development of a site of 1500 square metres or more with a frontage of at least
36 metres in this sub-precinct, a limit of 15 storeys.9
[14] The Scheme10 provides that the purpose of the Major Centre zone is to provide “a mix
of uses and activities” including “concentrations of higher order retail, commercial
offices, residential, administrative and health services, community, cultural and
entertainment facilities and other uses capable of servicing a subregion in the planning
scheme area.” As already noted, the TANP, by overall outcome (4)(h), requires a diversity
of uses for development on sites adjoining the Brisbane River. The judge found that
the development did not comply with those provisions.11
9 Judgment at [64].
10 s 6.2.2.2.
11 Judgment at [382].
-- 5 of 19 --
6
[15] Another relevant performance outcome is that designated as PO2,12 which provides
that a development site should, amongst other things, provide “a highly active [street]
frontage”. The judge rejected an argument by the present second respondent that PO2
was relevant only where what was proposed were buildings on the street front, rather
than set back as with the three towers under this proposal. The judge found that this
proposal involved “some level of conflict with PO2”, although he said it exhibited
“significant merit in the way that it addresses the streetscape.”13
[16] There were further provisions of the Scheme with which, on the judge’s findings, the
proposed development was inconsistent, but they need not be discussed.
[17] Maps within the TANP designated the site as a “catalyst site” and a “landmark site”.
As the judge said,14 the term “catalyst site” is explained in s 7.2.20.3.2(3)(s), where
one of the overall outcomes is expressed to be that “[s]tructure planning of catalyst
sites … addresses the unique characteristics of these sites ensuring that development
integrates with surrounding land, creates an attractive public realm and urban environment,
provides public space and retains and re-uses on-site heritage structures.” The term
“landmark site” is defined in the Scheme15 as a site:
“identified in the neighbourhood plan to accommodate buildings or
developments that attain citywide prominence through a combination
of notable architectural excellence, siting and location.”
[18] The site is the subject of its own performance outcome in the TANP. PO11 provides
the development on this site should be such that it:
“(a) enhances the pedestrian experience with high-quality building
design, streetscape and waterfront amenities providing a direct
and tangible linkage between Toowong and the river;
(b) provides a new public space with supportive uses to encourage
activity on and occupation of the river’s edge;
(c) maintains the natural quality of the waterfront experience for
access by the general public;
(d) reflects the local culture and heritage of Middenbury House;
(e) provides an arcade between Coronation Drive and Archer Street.”
It also is the subject of specific acceptable outcomes, described in the TANP as AO11.
The judge found no inconsistency between the development and PO11 or AO11.
The Reasons for Judgment
[19] There were many issues which were the subject of evidence and argument in the
Planning and Environment Court, during a hearing occupying 13 days in June, July
and August 2016. From his Honour’s extensive Reasons for Judgment, it is necessary
to consider only the findings which were made about the provisions of the TANP
which I have identified and the reasons for his Honour’s conclusion that there were
sufficient grounds to justify an approval of the project, notwithstanding its conflict
12 s 7.2.20.3.3.
13 Judgment at [348] – [350].
14 Ibid at [45].
15 SC1.2.3.B.
-- 6 of 19 --
7
with the Scheme. For the most part, the applicant’s arguments focus upon the
development’s inconsistency with the TANP’s provisions about the appropriate
height of buildings by limiting the number of storeys.
[20] The starting point is that according to the TANP, a maximum number of storeys was
prescribed as 15, whereas two of the proposed towers would be 24 storeys and the
third would be 27 storeys. Consequently, the judge found, the proposal departed from
the relevant acceptable outcome, AO1.1.16 However, the judge said it did not follow
that the proposal was inconsistent with the TANP, “because acceptable outcomes are
not mandatory”.17 The basis for that observation, in the case of AO1.1, is open to
question. As I have set it out above, it contains the statement that a development must
comply with a limit which is expressed as a maximum number of storeys.
[21] By s 7.1(6)(f) of the Scheme,18 the performance outcomes of a neighbourhood plan
code are achieved by the acceptable outcomes. Only one of the acceptable outcomes
is relevant to the height and number of storeys of a structure, and it is AO1.1. It
quantifies what would meet “community expectations about the number of storeys to
be built.” Although the judge accepted that community expectations would be at least
in part informed by that prescribed maximum of 15 storeys, he said that the community
might expect a development could exceed that maximum.19 Again, that is open to question.
[22] Nevertheless, the judge found that:20
“Even if reasonable expectations are not limited to 15 storeys … the
height of this particular proposal [was not] aligned to community
expectations about the number of storeys to be built [and] therefore
does not meet PO1 in relation to height.”
[23] His Honour then said that the non-compliance with PO1 was not the end of the matter
because the development might still comply with the relevant overall outcome (3)(h).
It is convenient to again set out that provision:
“Development is of a height, scale and form which is consistent with
the amenity and character, community expectations and infrastructure
assumptions intended for the relevant precinct, sub-precinct or site and
is only developed at a greater height, scale and form where there is
both a community need and an economic need for the development.”
That provision raised two questions in the present case. The first was whether the
heights of the proposed towers exceeded “community expectations”. The judge found that
they did. At one point he found that the proposed towers were of a height which
exceeded “reasonable expectations”,21 but at another point in the judgment, he found
that the height did not accord with community expectations.22
[24] The second question, under overall outcome 3(h), was whether there was both a
community need and an economic need for the development. His Honour found that
there was a need of each kind. That finding is strongly challenged by an argument
that it involved a legal error in the interpretation of the provision.
16 Judgment at [66].
17 Ibid at [64].
18 Set out above at [8].
19 Judgment at [70].
20 Ibid at [76].
21 Ibid at [382].
22 Ibid at [76].
-- 7 of 19 --
8
[25] In describing the question of community and economic need as follows, the judge
said that:23
“(b) the community need and economic need do not have to be
specifically demonstrated for the amount which is not “consistent”
with the amenity and character, community expectations and
infrastructure assumptions for the relevant precinct, sub-precinct or
site;
(c) nor does the community need and economic need have to be
specifically demonstrated for the amount which, for example in
the case of building height, the proposed development exceeds
the building height specified in an acceptable outcome;
(d) community need and economic need must be for “the development”
– meaning the totality of what is proposed[.]”
[26] The judge discussed the evidence from three economists, Mr Brown (who was
engaged by the applicant), Ms Shimmin (who was engaged by the Council) and Mr Dimasi
(who was engaged by the second respondent). The judge began by accepting Mr Dimasi’s
evidence that:24
“… there is a considerable economic and community need for the
subject site to be developed and a significant economic and community
disbenefit from the past, and any significant future, delay in realising
the site’s development potential [which is] an opportunity cost.”
(Emphasis added.)
[27] The judge noted that the site had been vacant for a decade and that it had “stayed
effectively derelict”, notwithstanding that it had become designated as a landmark
site and a catalyst site under the Scheme. He said that there was “a substantial
economic and community disbenefit in the site remaining in its current state,”25 and
continued:
“[273] Further, I accept Mr Dimasi’s point that it would be economically
inefficient and would impose an economic and community
disbenefit if efficient development were to be refused with the
consequence of the site remaining vacant until what some might
regard as a “perfect” development can be achieved, whatever
that might be. That, however, cannot be taken too far. It would
be the antithesis of proper planning to allow the “opportunity
cost” argument to justify permitting any form of development
whatsoever, no matter how unacceptable otherwise, simply in
order to get something developed promptly on the site. In this
case however, the proposal would not only facilitate the meaningful
development of the site, but would do so in a way which
addresses economic and community need.” (Emphasis added.)
[28] His Honour noted that the development would result in more than a thousand
residents on the site, with flow-on benefits for the locality by increasing its “activity
23 Ibid at [79].
24 Ibid at [271].
25 Ibid at [272].
-- 8 of 19 --
9
and vibrancy”.26 The development would also provide a significant area of public
open space and public access to the river bank, through land between the towers. The
judge said that the development proposed “a high quality public realm, bike paths and
walkways, the retained, rejuvenated and repurposed Middenbury [a heritage building
on the site], a café/restaurant associated with that and a café nearer the riverfront.”27
The judge endorsed a statement in the joint report of Mr Shimmin and Mr Dimasi that:28
“…a need exists if the wellbeing of the community is enhanced,
including subsectors of the community at large.”
[29] His Honour found that the development would achieve a “city-wide prominence”
(a reference to its status as a landmark site), that it would act as a “catalyst” and that
it would meet community expectations “that a high-quality development with a high
level of amenity, particularly public realm, would be established on the site”, as well
as being a “development [which] should achieve architectural excellence”.29
[30] The judge accepted evidence from Mr Shimmin that the development would
“represent modern, new and regenerative [development]” and would “lift the bar” by
“creating a new development benchmark in the Towong major centre, and indeed in
inner Brisbane as well[.]”30
[31] His Honour was unpersuaded by Mr Brown’s concern that there was no demonstrated
need for the extent of residential development which was proposed. The judge said
that Mr Brown’s analysis had overlooked “the relative scarcity of truly comparable
residential developments to the subject”.31 The judge concluded that the apartments
to be offered under this development would have “very wide appeal to many segments
and will draw from a broad spectrum, including all parts of the Brisbane metropolitan area
generally as well as from interstate.”32 He found that the development had a “combination
of attributes” which would offer “something which is not truly comparable”.33
[32] Still on the subject of community and economic needs, the judge discussed a further
question, for which there had been evidence from Mr Brown, of whether the approval
of this development would “prejudice the need for the subject site to be used for retail
and commercial office space purposes.”34 He found that the “level of need for the
subject site to be given over to significant commercial office space development is
relatively weak”.35 Similarly, he found that there was “a relatively modest demand
for additional retail floor space within the Toowong major centre.”36 He accepted
that there will be a need for further retail development in the Toowong centre and
“that the subject site would be suitable for some retail uses”. But he found that it was
“unlikely that a large retail focused catalyst/landmark development would be
achieved on the subject site, at least in the short to medium term.” Therefore, he
concluded, “[t]here would be public disbenefit in quarantining the subject site in the
26 Ibid at [275].
27 Ibid at [276].
28 Ibid.
29 Ibid at [278].
30 Ibid at [279] – [280].
31 Ibid at [288].
32 Ibid at [290].
33 Ibid at [291].
34 Ibid at [294].
35 Ibid at [295].
36 Ibid at [303].
-- 9 of 19 --
10
meantime in the hope that there might be a build-up of demand, over the longer term,
to excite such a proposal.”37
[33] In concluding that there was both an economic and a community need for the
development as a whole, the judge said:38
“I am satisfied that refusing the subject development in the hope that
a different proposal, with a much more substantial retail and/or
commercial focus being put forward, is likely to be to the community
disbenefit.”
[34] At the end of the judgment, his Honour considered whether there were sufficient
grounds under s 326(1)(b) of the SPA, and the summary which follows refers to his
reasons on that question. He there observed that there had been many suggested
inconsistencies with the Scheme, which he had not accepted, and that there were
“many provisions of [the Scheme] with which the proposal is either consistent or
positively supports or achieves.”39 The judge said that there were inconsistencies,
“although the conflict is not as great as was alleged by the appellant”. He said that
“there is a level of conflict with a number of provisions, or parts of provisions of
relevance” and that the level of conflict was “significant”.40 In particular he identified
these matters:
“[382] I have found that the proposed towers are of a height which
exceeds reasonable expectations, that the built form does not
have an active built form edge to the streetscape or at ground
level (in the case of the towers) and the development does not
contain a balanced mix of uses or include a significant
component of non-residential centre activities. It has insufficient
non-residential uses in order to avoid a finding of some conflict
on that account.” (Footnotes omitted.)
[35] The judge then observed that some of those inconsistencies had resulted from the
adoption of a tower-in-plaza design, rather than a tower-over-podium design and that
he had found that the development would serve “useful purposes, in the public
interest”,41 and that the use of higher towers would result in “much greater space at
ground level than would otherwise be expected.”42 He found that the development
proposal “achieved a highly open site at ground level”, with much of that space being
“to the public benefit, by designating it as public open space”.43 He said there was
a larger area than could be expected, according to the TANP, for public open space.
[36] His Honour referred to the site’s status as a landmark site, saying that “[t]he adoption
of a more vertical built form, in conjunction with the site location, building siting and
adoption of a bold, interesting, architectural design of the highest quality by a world
renowned architect also capitalises on the potential to achieve city-wide prominence
as a visual reference.”44 He said that on the other hand, it was “difficult to see how
37 Ibid at [310].
38 Ibid at [311].
39 Ibid at [380].
40 Ibid at [381].
41 Ibid at [383].
42 Ibid at [384].
43 Ibid at [385].
44 Ibid at [387].
-- 10 of 19 --
11
the community would be substantially advantaged by the provision of substantially
more non-residential uses”.45
[37] The judge concluded as follows:
“[389] The respects in which the proposal is otherwise in conflict with
the planning scheme have been discussed. Any conflict is not
accompanied by an undue effect. The amenity impacts of the
co-respondent’s proposal have been assessed and found to be
acceptable.
[390] Senior counsel for the appellant accepted that the quality of the
architecture is relevant, although he submitted that it should not
carry the day.
[391] Economic and community need have been discussed earlier. For
the reasons given, there is a need for the development potential
of the site to be realised and a need for the development
proposed. The development would also be the instigator of
further activity within the centre.
[392] The merits of the proposal generally have been discussed earlier
and are substantial.
[393] On balance, I am satisfied that there are sufficient grounds, in
the public interest, to approve the proposed development
notwithstanding conflict with the planning scheme.” (Footnotes
omitted.)
The application for leave to appeal
[38] The judgment was delivered on 10 May 2017. The application for leave to appeal
was filed on 21 June 2017. According to the applicant’s submissions, leave to appeal
is sought pursuant to s 63 of the Planning and Environment Court Act 2016 (Qld).
Section 76(2) of that Act provides that it applies to any appeal in relation to a proceeding
mentioned in s 76(1)(a), which is a proceeding which had started under the SPA, but
had not ended before the commencement of the 2016 Act on 3 July 2017. Final orders
have not been made in this proceeding, so that it is s 63 of the Planning and Environment
Court Act 2016 (Qld) which governs this application for leave to appeal. In any case,
if the present application is governed by s 498 of the SPA, again the appeal to this
Court may be made only by leave and is limited to an error of law or an error as to
the jurisdiction of the Planning and Environment Court.46
[39] In the usual way, this Court has heard full argument on the merits of the proposed
appeal. The third respondent to this application is the Chief Executive administering
the SPA, who was not an active participant in this Court.
Grounds of the proposed appeal
Community and economic needs
[40] I have referred to the two questions under overall outcome (3)(a). The applicant’s
argument is that notwithstanding the judge’s extensive discussion of the evidence of
45 Ibid at [388].
46 SPA, s 498(1).
-- 11 of 19 --
12
the three economists, his Honour did not consider the second of these questions,
which is whether there was a community need and an economic need for the
development. In essence, the argument is that it was necessary to consider whether
there was a need, of each kind, for this development, rather than a need which could
be satisfied by a development of the same kind, but of a height and scale which was
consistent with community expectations and, in particular, which complied with the
prescribed maximum of 15 storeys.
[41] The same argument was advanced in the Planning and Environment Court and was
rejected by the judge in the passage which I have set out above at [25].47 The submissions
in this Court for the respondents, in substance, adopt the judge’s reasoning. For the
following reasons, the applicant’s argument should be accepted.
[42] The question here was whether there was both a community need and an economic
need “for the development”, an expression which unambiguously refers to the
particular development which is being assessed. The question arises in the context of
the height of the development being inconsistent with community expectations for
the relevant precinct, sub-precinct or site. Consequently, the question must be
answered by reference to a development of this height.
[43] For the purposes of discussion, let it be assumed that there is a community need, and
an economic need, for a high quality residential development which provides public
spaces of the kind and to the extent which the judge described; but let it also be
assumed that these needs could be satisfied by the provision of, say, 300 units within
three towers, none of which would exceed 15 storeys. In that case, the second respondent’s
proposed development might be described as satisfying a need. But this development
would more than do so. The question is not whether the development would satisfy
community and economic needs; it is whether there is a need for this development, or
put another way, whether it is necessary to develop their site by buildings of this height.
[44] To vary the facts of that example, take a case where there are community and
economic needs for, say, 300 units and for the other benefits as I have described, but
where for reasons of commercial practicality, no development providing only that
number of units within 15 storeys or fewer, would be undertaken. In that case, it
would be necessary to construct buildings which were inconsistent with community
expectations, because a smaller and compliant development, being commercially
impracticable, would not be built and therefore could not satisfy the need.
[45] The judge observed that this site had been unused for a decade. He referred to the
“disbenefit” to the community in that respect. Perhaps he had the impression, given
the length of that period, that this could be a case of a kind which I have described in
the preceding paragraph. But if so, there was nothing said of it in the judgment. His
Honour did not consider whether a development had to be of this height to satisfy
community and economic needs.
[46] His Honour said that there would be “an economic and community disbenefit if
efficient development were to be refused with the consequence of the site remaining
vacant until what might be regarded as a “perfect” development can be achieved,
whatever that might be.”48 But the question was not whether there was a need for
some development of the site. Nor was the question whether, as the judge put it, the
47 Judgment at [79].
48 Ibid at [273].
-- 12 of 19 --
13
proposal “addresses” economic and community need. It was whether this development
was necessary, which did not require a consideration of whether there was a “perfect”
development which could be achieved.
[47] By endorsing the proposition that “a need exists if the well-being of the community
is enhanced [by the development]”,49 again his Honour addressed the wrong question.
The well-being of the community could be enhanced by something which provided
more than the community needed.
[48] In his reasoning on this question, the judge also referred to the status of the site as a
landmark site and as a catalyst site. He found that there was “an expectation that
development should achieve architectural excellence and obtain citywide prominence.”
He was satisfied that the development would achieve those things.50 Accepting that
to be so, those attributes could be relevant to this question under overall outcome (3)(h),
only if there was a community need and an economic need for a development with
those attributes. But the judge did not find that there was both a community and an
economic need for those attributes. And nor did he find that only this development
could provide them.
[49] Accepting, as this Court must, the judge’s analysis of the evidence in his discussion
of this question, his findings provided no basis for a conclusion that upon the proper
interpretation of this provision, there was a demonstrated community need and
economic need for this development. In the absence of a demonstrated need of each
kind, the development was inconsistent with overall outcome (3)(h). The extent of
that inconsistency was considerable: two of the towers exceeded the maximum
number of storeys by more than 50 per cent and the third tower was even higher.
Section 5.3.3 of the Scheme
[50] Something should be said of another submission for the applicant, which is that there
was an error in the assessment of whether the proposal complied with the Scheme,
under s 5.3.3 which prescribes rules for the assessment of different types of development.
The rules are expressed differently for code assessable development than for impact
assessable development, the latter being relevant in this case. It is said that at times,
the judge applied criteria that applied to code assessable development rather than
impact assessable development. It is said that the judge was thereby diverted from
the requirement in s 5.3.3 for impact assessable development that the ”development … be
assessed against the planning scheme, to the extent relevant”. I am unpersuaded that
the criticism is justified. In any case, it is not shown to have been material to the outcome.
Section 326 of the SPA
[51] The remaining arguments for the applicant are relevant to the question of whether
there were sufficient grounds to justify the decision, according to s 326 of the SPA
which is as follows:
“326 Other decision rules
(1) The assessment manager’s decision must not conflict with a
relevant instrument unless—
(a) the conflict is necessary to ensure the decision complies
with a State planning regulatory provision; or
49 Ibid at [276].
50 Ibid at [278].
-- 13 of 19 --
14
(b) there are sufficient grounds to justify the decision, despite
the conflict; or
(c) the conflict arises because of a conflict between—
(i) 2 or more relevant instruments of the same type,
and the decision best achieves the purposes of the
instruments; or
Example of a conflict between relevant instruments—
a conflict between 2 State planning policies
(ii) 2 or more aspects of any 1 relevant instrument, and
the decision best achieves the purposes of the
instrument.
Example of a conflict between aspects of a relevant
instrument—
a conflict between 2 codes in a planning scheme
(2) In this section—
relevant instrument means a matter or thing mentioned in
section 313(2) or 314(2), other than a State planning regulatory
provision, against which code assessment or impact assessment
is carried out.”
[52] Before going to those arguments, it is necessary to refer to the authorities in this Court
on the provision. Many of the cases which were cited in argument were decided under
the statutory predecessor of s 326 of the SPA, namely s 4.4(5A) of the Local Government
(Planning and Environment) Act 1990 (Qld) (“the 1990 Act”). It provided that a local
government must refuse to approve an application if it conflicted with any relevant
strategic plan or development control plan and there were not “sufficient planning
grounds to justify approving the application despite the conflict”. In Grosser v City
of Gold Coast,51 White J (with whom Thomas and Williams JJA agreed) said that
s 4.4(5A) provided “a simple two-stage process which first requires the identification
of conflict with the Strategic Plan, then, if conflict is present, the application must be
refused if there are not sufficient planning grounds to justify approving the
application despite the conflict.”52 In that case, the primary judge was found to have
erred, by reasoning that s 4.4(5A) was not engaged, because the inconsistencies with
the Strategic Plan were not “so fundamental” as to do so.53
[53] The same provision of the 1990 Act was considered in Weightman v Gold Coast City
Council,54 where the primary judge had found that a development would exceed
a prescribed maximum height under the planning scheme, but that there were
sufficient planning grounds to justify approving the application despite the conflict.
The principal judgment was given by Atkinson J, with whom McMurdo P agreed.
The Chief Justice dissented in the result, but stated his agreement with the principles
expressed by Atkinson J.55 Her Honour noted that under s 4.4(5A), it was a “mandatory
51 (2001) 117 LGERA 153; [2001] QCA 423.
52 Ibid at 166 [49].
53 Ibid.
54 [2003] 2 Qd R 441; [2002] QCA 234.
55 Ibid at 446 [8].
-- 14 of 19 --
15
requirement” that the approval be refused if there were not sufficient grounds to
justify it. Her Honour considered that the primary judge had wrongly held that the
provision was directory only.56 She said that the provision required the decision
maker to: (1) examine the nature and extent of the conflict with the planning scheme;
(2) determine whether there were any planning grounds which were relevant to the
part of the application which was in conflict with the planning scheme and if the
conflict could be justified on those planning grounds; and (3) determine whether the
planning grounds in favour of the application as a whole were, on balance, sufficient
to justify approving the application notwithstanding the conflict.57 In her concurring
judgment, the President said that only when the extent of the conflict with the planning
scheme was appreciated, could the discretion under s 4.4(5A) be properly exercised.58
[54] Section 4.4(5A) of the 1990 Act was re-enacted in s 3.5.14 of the Integrated Planning
Act 1997 (Qld), which was later amended (in 2006) in terms which were subsequently
replicated in s 326 of the SPA. The question became, as it is under s 326 for this case,
whether there were “sufficient grounds”, rather than “sufficient planning grounds”,
to justify the decision and the term “grounds” was defined to mean matters of public
interest, and not including the personal circumstances of an applicant, owner or
interested party. In Lockyer Valley Regional Council v Westlink Pty Ltd,59 Holmes JA (as
the Chief Justice then was) said that the expression “planning grounds” required
a narrower inquiry than that entailed in assessment of the unqualified and broadly
defined “grounds” which had become relevant under the amended s 3.5.14.
[55] Section 326 of the SPA was considered in Zappala Family Co Pty Ltd v Brisbane
City Council.60 Morrison JA there said that in applying s 326(1), the Court must
examine the nature and extent of the conflict with the planning scheme, for which he
cited Weightman v Gold Coast City Council and Lockyer Valley Regional Council v
Westlink Pty Ltd. He held that this had not occurred in that case because the judge
had wrongly considered that a certain provision of the planning scheme, dealing with
car parking, was inapplicable.61
The so-called “Elan Capital” error
[56] In Elan Capital Corporation Pty Ltd v Brisbane City Council,62 Quirk DCJ described
a proposed development, which was the subject of a re-zoning application, as
a “serious intrusion upon the integrity of [part of the planning instrument]”, such that
to permit the development would unacceptably “cut across” the Council’s “planning
strategy”. He said that it was not the court’s function to substitute planning strategies
(which on evidence given in a particular appeal might seem more appealing) for those
which a planning authority in a careful and proper manner had chosen to adopt.63
That judgment has been cited in many cases, including in this Court’s judgment in
Grosser v Gold Coast City Council.64
[57] It is argued that in the present case, the judge reasoned inconsistently with the
principle from Elan Capital, by effectively substituting his own planning opinions in
place of those which are expressed in the Scheme.
56 Ibid at 453 [35].
57 Ibid at 453 [36].
58 Ibid at 448 [15].
59 [2013] 2 Qd R 302 at 323 – 324 [25]; [2012] QCA 370.
60 (2014) 201 LGERA 82; [2014] QCA 147.
61 Ibid at 107 [118].
62 [1990] QPLR 209 (“Elan Capital”).
63 Ibid at 211.
64 (2001) 117 LGERA 153 at 155 [6] (Williams JA) and 163 [38] (White J).
-- 15 of 19 --
16
Irrelevant considerations
[58] It is submitted that in determining the question under s 326, the judge erroneously
took into account irrelevant considerations, of which two are identified.
[59] The first is the judge’s finding that although there were conflicts with the Scheme,
the development proposal was consistent with the Scheme in many other respects.65
The other is said to have been the judge’s incorrect interpretation of overall outcome (3)(h)
and s 5.3.3 of the Scheme.
[60] As to the former, the judge’s consideration of the s 326 question was affected by his
incorrect interpretation of that provision, as I will discuss. However, the characterisation
of that legal error as a consideration of an irrelevant matter, adds nothing to the
applicant’s case. And as to s 5.3.3, it is not demonstrated that if there was an error in
that respect, it mattered for the s 326 question or otherwise.
Failure to consider relevant matters
[61] It is submitted that the judge erred in failing to take into account necessary
considerations, two of which are said to be the correct interpretation of overall
outcome (3)(h) and the correct interpretation of s 5.3.3. What I have just said under
the last heading applies equally to this submission.
[62] It is submitted that the judge failed to consider whether another development, one
which did not conflict with relevant provisions of the Scheme, could achieve the same
(or similar) positive outcomes as the judge relied upon to find sufficient grounds
under s 326. Counsel for the applicant described this as the “alternative development
point”. The argument cites a number of judgments in the Planning and Environment
Court which are said to support the proposition, that to qualify as a sufficient ground
under s 326, the ground must be one “which would establish positive betterment in
terms of planning outcomes which would not otherwise be achievable through the
existing Planning Scheme.”66
The “public detriment” argument
[63] It is submitted that the judge overlooked a principle that there is a real public interest
in upholding obedience to the planning laws by all members of the community, and
by all local governments, even in circumstances where there is no associated harm.
But the cases which are cited for this submission were not concerned with s 326(1)(b)
or any analogous provision. They were cases where development had occurred, in
non-compliance with a development permit, and in that context, the court emphasised
the importance of obeying the law.67
Section 326 - consideration
[64] By s 314(2) of the SPA, an application must be assessed against each of the matters
or things there listed, to the extent that it is relevant. The list includes “a planning
65 Judgment at [380].
66 Palyaris v Gold Coast City Council [2004] QPELR 162, 169 [41]; [2003] QPEC 56; Titanium Enterprises Pty
Ltd v Caloundra City Council [2007] QPELR 154, 164 [59]; [2006] QPEC 106; Bruce v Caloundra
City Council [2007] QPELR 571, 575 - 576 [38]; [2007] QPEC 46; Nevtan Investments Pty Ltd v
Belyando Shire Council [2008] QPELR 326, 335 [52]; Prettlejohn v Cairns Regional Council [2012]
QPELR 485, 492 [53]; [2012] QPEC 23.
67 Warringah Shire Council v Sedevcic (1987) 10 NSWLR 335, 339 – 340; Woolworths Ltd v Warehouse
Group (Aust) Pty Ltd (2003) 123 LGERA 341, 348; [2003] NSWLEC 31; Woolworths Ltd v Caboolture Shire
Council [2004] QPELR 550, 560; [2004] QPEC 15.
-- 16 of 19 --
17
scheme”. By s 324(2), the decision on the application for approval must be based
upon such an assessment.
[65] Section 326(1) requires that the decision not be in conflict with a relevant instrument,
including a planning scheme, unless the circumstances engage one of the four
exceptions which are there stated. In the present case, only the exception within
s 326(1)(b) was thought to be relevant. The judge did not identify a conflict between
two or more relevant instruments of the same type, or between two or more aspects
of any one relevant instrument.68 In particular, his Honour did not identify a conflict
between the Scheme’s designation of the site as a catalyst site and a landmark site
and, on the other hand, the Scheme’s prescription of a maximum number of storeys.
[66] Section 326(1)(b) will be engaged only where there is a tension between the
application of the relevant instrument, here a planning scheme, and the public interest.
If that tension exists, it will be for the decision maker to consider whether there are
sufficient grounds, in the public interest, to depart from the instrument. Necessarily,
cases where that tension exists will be exceptional, because a planning scheme must
be accepted as a comprehensive expression of what will constitute, in the public
interest, the appropriate development of land. In Clark v Cook Shire Council,69 Keane JA,
with the agreement of the other members of this Court said:
“The terms of a planning scheme inevitably reflect the striking of an
overall balance, in the public interest, between the many interests
potentially affected by the planning scheme.” (Emphasis added.)
[67] It is not for the decision maker (including in this context a Court), to gainsay the
expression of what constitutes the public interest that is in a planning scheme.
A decision maker might think that a limit of 15 storeys is too restrictive, and the
public would be better served by a higher limit. But this decision maker must accept
that it is in the public interest that the limit be 15 storeys, because that is what the
planning scheme effectively provides.
[68] Cases could arise where relevant circumstances have changed since the planning
scheme was made, or where it can be seen that there is a factual error in the scheme
itself. Cases of that kind were identified in the explanatory notes for s 3.5.14 of the
Integrated Planning Act 1997 (Qld). There might also be cases where it is evident
that the planning scheme has not anticipated the existence of circumstances which
have created a need for a certain development in the public interest. In exceptional cases
of all of these kinds, the decision maker might be able to conclude that the planning
scheme is not, in the particular case, an embodiment of what is in the public interest.
[69] The submissions for the respondents emphasise that in Elan Capital, Quirk DCJ used
the expression “planning strategies”, which they distinguish from the relevant provisions
of the Scheme in this case. However, what must be applied here are the terms of
s 326(1)(b) of the SPA, for which there was no legislative equivalent when Elan
Capital was decided.70
68 SPA, s 326(1)(c).
69 [2008] 1 Qd R 327 at 338; [2007] QCA 139.
70 The case was apparently decided under the Local Government Act 1936 (Qld), s 33(6A). By s 33(6A)(e)(iii)
of that Act, the local authority was obliged to consider whether the proposed re-zoning accorded or
conflicted with any strategic plan or development control plan, but that was not a provision in the
mandatory terms of s 326(1)(b) of the SPA. Section 4.4(5A) of the 1990 Act was inserted in 1992.
-- 17 of 19 --
18
[70] Consequently, any consideration of the application of s 326(1)(b) of the SPA must
proceed upon the premise that it is in the public interest that the planning scheme, in
each relevant respect, be applied, unless the contrary is demonstrated. Thus in the
present case, it had to be assumed that the public interest would be served by
confining the development of this land to buildings of a height that accorded with
community expectations that buildings would not extend, or at least significantly
extend, beyond 15 storeys. That was not an arbitrary limit; it was an expression of
a means by which, in the public interest, the scale of any development would be kept
in alignment with community expectations. The Scheme was unambiguous in providing,
within AO1.1, that “[d]evelopment must comply with both parameters where
maximum number of storeys and height in metres are specified.”
[71] His Honour did not discern any ambiguity or error in the Scheme in this respect. Nor
did he find that the relevant provisions of the Scheme could not be assumed to
represent what was in the public interest, because the relevant circumstances had
changed since the Scheme came into force. Notably, the TANP made particular
provision for this site, but without qualifying overall outcome (3)(h) and AO1.1.
[72] The judge considered that there were certain benefits from the heights of these
proposed buildings. He concluded that the heights would enhance the enjoyment of
the site, by providing less of a building footprint and consequently more land which
could be used for public open space. He also concluded that the greater heights of the
buildings would give them a prominence, both in terms of visibility and architectural merit,
which would enhance the contribution of the development as a landmark site. They
were factual conclusions which had an evidentiary basis. But whether they provided
sufficient grounds to justify a conflict with the Scheme was another matter.
[73] After discussing the height of the proposed buildings, the judge set out and adopted a
number of submissions which had been made for the Council. Amongst them was
the proposition that if community need and economic need were established, that
would call for something of a “balancing exercise”, under which there would be
“a balancing consideration of all positive and negative attributes of the proposed
development (for example, particular community benefits might weigh in favour of
approval even where a proposal is not consistent with the community expectations).”71
[74] In that passage, the judge did not identify the legal source for that balancing exercise.
The judge did not proceed to a factual analysis of that kind, except in his consideration, at
the end of the judgment, of s 326.72 It would appear that the judge undertook that
broad balancing exercise in the belief that this was what s 326(1)(b) required. In my
respectful opinion, the judge misconstrued the provision. This would explain his Honour’s
observation, in considering s 326, that there were many provisions of the Scheme with
which the proposal was either consistent or which it “positively supports or achieves”.73
[75] His Honour repeated his finding that there was a community need and an economic
need under overall outcome (3)(h),74 in his conclusion about the operation of s 326.
With respect, that reasoning is difficult to accept. If, in truth, there was a community
need and an economic need for this development, it would follow that overall
outcome (3)(h) would be satisfied, the decision would not conflict with it and it would
71 Judgment at [79] (e), (f).
72 Ibid at [378] – [393].
73 Ibid at [380].
74 Ibid at [391].
-- 18 of 19 --
19
not matter for s 326. On the other hand, if there was no demonstrated community
need and economic need for this development, there would have been a conflict, in
which case there had to be some reason for concluding that the Scheme did not
accurately represent what was in the public interest.
[76] At an earlier point in the judgment, his Honour said that “[e]ven if there were a
conflict with OO(3)(h), this is, in my view, an exceptional case in which the proposal
warrants approval notwithstanding.”75 However the judge did not reveal why this
was an exceptional case, so as to satisfy s 326(1)(b), other than by the broader
balancing exercise to which I have referred.
[77] At no point did the judge refer to the Scheme as an embodiment of what represented
the public interest. The judge did not identify any way in which the Scheme’s
specification of an acceptable height was to be disregarded as the result of an error in
drafting, a change in relevant circumstances from those which existed when the
Scheme was prepared or a failure of the Scheme to anticipate a need, in the public
interest, for a development on this site with buildings of this height. In essence his
Honour formed his own judgment of what was in the public interest without
recognising the relevance of the Scheme to that question. The same may be said of
his conclusion that the public interest justified the conflict between the decision and
overall outcome (4)(h).
[78] Ultimately, by the judge substituting his own view of the public interest for that which
was expressed in the Scheme, there was a legal error which affected his conclusion
under s 326. Further, that was also affected by the legal error in the interpretation of
overall outcome (3)(h).
Conclusion and orders
[79] In my conclusion, the judgment was affected by errors of law, which warrant a grant
of leave to appeal and the appeal being allowed.
[80] It was submitted for the applicant that if she succeeded upon this basis, this Court
should consider whether the development should be approved. I would accept that
the respondents should not be able to adduce further evidence, having failed to establish,
upon a proper interpretation of overall outcome (3)(h) that there was a community
need and an economic need for this development. But I am not persuaded that this Court
would be well placed to consider what is ultimately a factual question, under s 326,
once that question is considered according to law. The case should be remitted to the
Planning and Environment Court, under s 65 of the Planning and Environment Court
Act 2016 (Qld). Counsel for the applicant disavowed a suggestion that the case should
be remitted to another judge. Clearly this judge should have a better understanding
of the evidence.
[81] I would order as follows:
1. grant leave to appeal.
2. allow the appeal.
3. remit the matter to the Planning and Environment Court, to be further
considered according to law.
4. the first and second respondents to pay the applicant’s costs of and incidental
to the application for leave to appeal and the appeal in this Court.
75 Ibid at [81].
-- 19 of 19 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2018/084