DMS Maritime Pty Limited v Royal and Sun Alliance Insurance Plc [2018] QSC 303 [2019] 1 QLR
SUPREME COURT OF QUEENSLAND
CITATION: DMS Maritime Pty Limited v Royal and Sun Alliance Insurance
Plc [2018] QSC 303
PARTIES: DMS MARITIME PTY LIMITED
ACN 078 359 065
(plaintiff)
v
ROYAL AND SUN ALLIANCE INSURANCE PLC
ARBN 153 863 006
(defendant)
FILE NO/S: SC No 6807 of 2016
DIVISION: Trial Division
PROCEEDING: Trial
DELIVERED ON: 14 December 2018
DELIVERED AT: Brisbane
HEARING DATE: 19 – 21 March 2018
JUDGE: Bond J
ORDER: The orders of the Court are:
1. It is declared that the defendant is obliged to indemnify
the plaintiff for the amount of the settlement sum which
the plaintiff became liable to pay the Commonwealth of
Australia under the Commonwealth Settlement Deed,
pursuant to the terms of the Insurance Policies and the
Indemnity Settlement Deed.
2. The defendant must pay the plaintiff the sum of
$15,852,453.75 as the amount of its liability to
indemnify the plaintiff pursuant to the terms of the
Insurance Policies and the Indemnity Settlement Deed,
as declared in order 1.
3. Pursuant to s 57 of the Insurance Contracts Act 1984
(Cth), the defendant must pay the plaintiff interest on
the amount the subject of order 2, in the sum of
$2,027,669.99 calculated to the date of judgment, and
thereafter at the rate of $2,280.15 per day until the day
on which payment is made.
4. The parties will be heard on the question of costs.
CATCHWORDS: CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS –
-- 1 of 36 --
2
INTERPRETATION OF MISCELLANEOUS
CONTRACTS AND OTHER MATTERS – where the
plaintiff and the Commonwealth entered into a contract
pursuant to which the plaintiff supplied and provided in-
service support for a patrol boat called the HMAS Bundaberg
– where, whilst the HMAS Bundaberg was in the plaintiff’s
possession for the purpose of being worked on under the
contract, the HMAS Bundaberg was destroyed by fire – where
the plaintiff was liable to indemnify the Commonwealth against
“any loss or damage” to the HMAS Bundaberg – where the
plaintiff became liable to “promptly replace or otherwise make
good any loss of” the HMAS Bundaberg – where the plaintiff
and the Commonwealth settled the plaintiff’s liability as to
those obligations by way of settlement deed for $31.5 million –
where the defendant insured the plaintiff for the plaintiff’s
contractual liability to the Commonwealth under the contract
– whether the plaintiff’s settlement with the Commonwealth
fell within the proper construction of the plaintiff’s obligation
to indemnify the Commonwealth
INSURANCE – GENERALLY – CLAIMS GENERALLY –
OTHER MATTERS – where the plaintiff and the defendant
had a contract pursuant to which the defendant indemnified
the plaintiff for its liability to a third party – where the plaintiff
became liable to indemnify the third party for losses under the
contract – where the plaintiff and the third party settled the
plaintiff’s liability by way of settlement deed for $31.5 million
– where the plaintiff and the defendant entered into an
indemnity settlement deed whereby the defendant accepted
the obligation to indemnify the plaintiff for its liability to the
third party but insisted on the plaintiff proving the quantum of
that indemnity in accordance with the terms of the insuring
clause – whether the plaintiff is entitled to establish the
quantum of the defendant’s liability to indemnify the plaintiff
by reference to the settlement between the plaintiff and the
third party – whether the plaintiff’s settlement with the third
party was reasonable in all the circumstances
Insurance Contracts Act 1984 (Cth) s 57
Clark v Macourt (2013) 253 CLR 1, cited
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015)
256 CLR 104, applied
Onley v Catlin Syndicate Ltd as the Underwriting Member of
Lloyd’s Syndicate 2003 [2018] FCAFC 119, applied
Ruckman v Nominal Defendant [2013] QCA 56, applied
The Gazelle (1844) 2 W Rob (Adm) 279, 166 ER 759, cited
-- 2 of 36 --
3
Victoria v Tatts Group Limited (2016) 328 ALR 564, cited
White Industries Qld Pty Ltd v Hennessey Glass & Aluminium
Systems Pty Ltd [1999] 1 Qd R 210, applied
COUNSEL: R Douglas QC, with S McNeil, for the plaintiff
S Couper QC, with G Coveney, for the defendant
SOLICITORS: Herbert Smith Freehills for the plaintiff
Norton Rose Fulbright for the defendant
Introduction
[1] In 2003 the plaintiff and the Commonwealth of Australia entered into a contract (the
Contract) pursuant to which the plaintiff agreed to design, manufacture and supply
Armidale Class Patrol Boats and to provide them with in-service support for a 15 year service
period after commissioning.
[2] The HMAS Bundaberg was one of a fleet of 14 such boats built pursuant to the Contract. It
was commissioned into service with the Royal Australian Navy in March 2007.
Unfortunately, on 11 August 2014, whilst it was in the plaintiff’s possession for the purpose
of being worked on under the Contract, the Bundaberg was destroyed by fire.
[3] Pursuant to the Contract, the plaintiff became liable to indemnify the Commonwealth against
“… any loss or damage to the [Bundaberg]” and also to “promptly replace or otherwise
make good any loss of … the [Bundaberg]”.
[4] For a period there was a dispute between the plaintiff and the Commonwealth as to what the
plaintiff was required to do in order to discharge those obligations. That dispute was settled
on 10 June 2016 when the parties entered into a settlement deed (the Commonwealth
Settlement Deed) pursuant to which the plaintiff became liable to pay the Commonwealth
a settlement sum of $31.5 million.
[5] The defendant (and other insurers) had insured the plaintiff for the plaintiff’s contractual
liability to the Commonwealth under the Contract. There was no dispute as to the various
documents (the Insurance Policies) of which was comprised the insurance contract to
which the defendant (and other insurers) were parties. By the relevant insuring clause in the
Insurance Policies, the defendant (and the other insurers) had agreed:
to indemnify [the plaintiff] for all sums which [the plaintiff] shall become liable to pay by reason of the legal
liability of [the plaintiff] as shiprepairers for … (i) Loss of or damage to any vessel or craft which is in the care,
custody or control of [the plaintiff] for the purpose of being worked upon ...
[6] By this proceeding, the plaintiff sought a declaration that the defendant is and was obliged to
indemnify the plaintiff with respect to the $31.5 million settlement sum. It sought orders
resolving the amount that the defendant should now pay to discharge its liability, together
with interest thereon pursuant to s 57 of the Insurance Contracts Act 1984 (Cth).
[7] For the reasons which follow, in my view the plaintiff’s liability to pay the $31.5 million
settlement sum is and was to be regarded as falling within the insuring clause to which the
defendant (and other insurers) had subscribed. The defendant is obliged to indemnify the
plaintiff in respect of its liability to pay that sum and it should be so declared.
[8] It was common ground that if I formed that view, then, having regard to the defendant’s
share of the liability under the Insurance Policies and to a subsequent partial settlement
-- 3 of 36 --
4
between the plaintiff and the defendant, the plaintiff would be entitled to a judgment against
the defendant in the amount of $15,852,453.75. Having regard to the findings which I will
make as to the date as from which it was unreasonable for the defendant to have withheld
payment of the amount which it owned under the Insurance Policies, the defendant is also
obliged to pay the plaintiff interest calculated to the date of judgment in the amount of
$2,027,669.99 calculated to the date of judgment, and thereafter at the rate of $2,280.15 per
day until the day on which payment is made.
Factual background
The Contract
[9] The Contract was a written contract made on 17 December 2003. It was comprised of a
number of parts, only four of which are presently relevant, namely (1) the conditions of
contract; (2) Attachment A “Statement of Work” (or “SOW”); (3) Annexure A to the
SOW “Ship Specification”; and (4) Attachment M “Glossary”.
[10] By cl 1.6.1 of the conditions of contract, the plaintiff contracted to design, manufacture,
produce and deliver the Patrol Boats. “Patrol Boats” was defined to mean the patrol boats
described in the Ship Specification. Clause 3.2 of the conditions of contract set out the
plaintiff’s obligations in relation to design, development and production of the Patrol Boats,
including that they be produced in accordance with the Ship Specification. Amongst other
things, the Ship Specification required that the Patrol Boat would be capable of performing
all of the specified functional and operational requirements “for an average life in excess of
20 years”.1
[11] The Contract differentiated between a “Production Phase” and a “Support Phase”. The
Production Phase was defined as the period commencing on the “Effective Date” (namely
the date the Contract was signed – 17 December 2003) and (unless the Contract was earlier
terminated) ending on the date the last Patrol Boat was commissioned under the Contract.
The Support Phase was defined as the period commencing on the date the first Patrol Boat
was commissioned and ending (unless the Contract was earlier terminated) on the last day
of the “Service Period” for the last Patrol Boat commissioned under the Contract. The
Service Period for each Patrol Boat was defined as the period commencing on the date it was
commissioned and ending 15 years after that date. As will appear, the Contract provided for
the possible extension of that 15 year period by 5 years, which is consistent with the
specification requirement for an average life in excess of 20 years. Also consistent with this
was the contractual reference to the planned service life of the fleet being 20 years following
acceptance of the last Patrol Boat.2
[12] During the Support Phase, the plaintiff was obliged to provide the “Integrated Support
System” and to perform the “Integrated Support Activities” in such a way that the
Commonwealth, in operating the Patrol Boats, could achieve the “Required Availability”.3
The “Integrated Support System” was defined as the planned system by which the fleet
would be enabled to achieve the operational and performance outcomes provided for in the
Contract as further described in annexure B to the SOW. “Integrated Support Activities”
were any things or tasks which the plaintiff was, or may be, required to do to provide the
Integrated Support System in accordance with the Contract. The “Required Availability”
1 See cl 5.8.0-1 of the Ship Specification.
2 See cl 5.3.6 of the conditions of contract and the definitions of “Life-of-Type”; “Mission System” and “Patrol Boat
Force” in the Glossary.
3 See cl 1.6.1 of the conditions of contract, read with applicable definitions in the Glossary.
-- 4 of 36 --
5
was defined by reference to the provisions in the SOW which specified certain operational
availability outcomes.
[13] By the Glossary, the Contract defined “Supplies” as “the Patrol Boats, the Integrated
Support System and any other goods and services including Intellectual Property and
Technical Data required to be supplied under the Contract and included items acquired in
order to be incorporated in the Supplies.” The term was sufficiently widely drawn to
incorporate the Integrated Support Activities. The conditions of contract also imposed the
following obligations on the plaintiff:
(a) to ensure and warrant that any Supplies would be fit for purpose: cl 9.1.1; and
(b) a warranty that the design, materials and workmanship in the Supplies conform with,
and the Supplies meet the requirements of the Contract: cl 9.2.1.
[14] The Contract also addressed who bore the risk of damage occurring to a Patrol Boat or
anything else which fell within the definition of “Supplies” during either the Production
Phase or the Support Phase. As to this:
(a) By cl 6.8.1.1 the Contract provided (emphasis added):
…, [the plaintiff] bears the risk of and shall indemnify the Commonwealth against:
a. any loss or damage to a Patrol Boat or any other Supplies until delivery in accordance with
the Contract; and
b. after delivery of a Patrol Boat or any other Supplies, any loss or damage to the Patrol
Boat or other Supplies:
i. which occurs while [the plaintiff] or any Subcontractor is in possession of the
Patrol Boat or other Supplies for the purpose of carrying out its Integrated
Support Activities;
ii. to the extent it occurs as a result of [the plaintiff] or any Subcontractor carrying
out its Integrated Support Activities to the Patrol Boat or other Supplies; or
iii. which is caused by any act or omission of [the plaintiff] or any Subcontractor
during the Production Phase, or by any damage to the Supplies which occurred
prior to the delivery of the Patrol Boat or other Supplies.
(b) by cl 8.3.1, the Contract provided (emphasis added):
During the period in which [the plaintiff] bears the risk of loss or damage of anything under
clause 6.8, [the plaintiff] shall promptly replace or otherwise make good any loss of, or repair
the damage to, the thing at its cost unless [there followed exceptions from that promise which are
not presently relevant].
[15] By cl 1.7 of the conditions of contract, and subject to cl 1.8, the Contract commenced on the
Effective Date, and would end on the 15 th anniversary of the date the last Patrol Boat was
commissioned under the Contract. Clause 1.8 provided for an optional 5 year extension of
the Service Period for each Patrol Boat, and a concomitant extension of the term of the
Contract. The option had to be exercised by the Commonwealth not less than 2 years prior
to the end of the Service Period for the first Patrol Boat. The Contract also permitted the
Commonwealth to terminate by notice in writing in the event of certain events happening or
defaults by the plaintiff occurring, and also to terminate for convenience.4
[16] Thus, putting to one side the possibilities of extension of the contract period or early
termination, the date on which the Contract would end was the end of the Service Period for
the last Patrol Boat commissioned under its terms. At the time the Contract was entered
4 See cll 12.2 and 12.3 of the conditions of contract.
-- 5 of 36 --
6
into it would have been obvious that unless it was terminated early, it was likely to operate at
least for the period of the Production Phase plus 15, and possibly 20, years.
[17] By the time that the Bundaberg was destroyed by fire, the following aspects of timing would
have been apparent:
(a) The first Patrol Boat commissioned was the HMAS Armidale on 24 June 2005.
(b) The Service Period for the Armidale would, in the normal course, have ended in 2020.
(c) Accordingly, the deadline for contract extension would have occurred in 2018, so
exercise of the option was still a possibility.
(d) The last Patrol Boat was commissioned in November 2007, therefore under clause 1.7
and other things being equal, the Contract would end in in 2022.
(e) If the option to extend was exercised that would have had the effect of extending the
service life of the fleet to 2027.
[18] The only other matter to be noted is that by cl 12.1 the Contract contained a dispute
resolution clause. It contemplated that in the event of any dispute arising from the Contract,
the parties would, first, seek to negotiate a resolution; second, seek to agree on an alternative
dispute resolution process; and, third, failing agreement about use of alternative dispute
resolution process, the parties would be free to commence court proceedings.
The Armidale Class Patrol Boats required remediation
[19] As a result of the Commonwealth’s border protection policies, between 2010 and 2013 the
Armidale Class Patrol Boat fleet had been increasingly used in operational areas such as
Christmas Island to intercept and turn back boats off the coast of Western and Northern
Australia. These waters were characterised by high seas.
[20] Performance issues had been experienced in the Armidale Class Patrol Boat fleet, including
corrosion to the internal and external areas of the boats; stern tube failures; structural
cracking in certain parts of the hull; and propulsion system reliability issues.
[21] The cause, solution and responsibility for those performance issues had been the subject of
ongoing discussion between the plaintiff and the Commonwealth from late 2012. The
Commonwealth blamed the plaintiff for the problems. The plaintiff denied fault, contending
that the Armidale Class Patrol Boat fleet had been subjected to operational requirements
outside the contracted design parameters.
[22] Whoever was at fault, the result was an increased maintenance burden, which restricted
availability and system reliability of the Armidale Class Patrol Boats. A remediation strategy
was necessary.
[23] By early 2014, discussions between the plaintiff and the Commonwealth had turned to the
possibility of their entering into a remediation deed with a view to adjusting the contractual
relationship between them having regard to some form of agreed resolution of the
remediation issues. There were communications between the two sides in late October 2014
and meetings thereafter with a view to reaching such an agreement by way of remediation
deed, but ultimately those negotiations failed to achieve a result. By a letter dated 23
February 2015, the plaintiff terminated negotiations for a remediation deed.
[24] Negotiations for a settlement concerning remediation started up again between about August
2015 and November 2015, this time focusing on a “Contract Change Proposal”. These
-- 6 of 36 --
7
negotiations were successful. By a deed dated 9 November 2015 (the remediation deed),
the Contract was varied such that –
(a) the expiry date of the Contract was brought forward to 30 June 2017;
(b) the Commonwealth agreed to give the plaintiff a “not to exceed” budget for the
carrying out of planned and corrective maintenance on the fleet until 30 June 2017; and
(c) the Commonwealth agreed to pay for the cost of remediating the fleet as an Ad Hoc
Service in accordance with cl 7.9 of the conditions of contract5 so long as the plaintiff
managed the remediation process on its behalf at cost (i.e. no profit margin) until 30
June 2017,
and otherwise, with one exception, the parties gave each other mutual releases from their
obligations under the Contract.
[25] The exception to the remediation deed concerned “any obligation, Claim or liability arising
out of, relating to or in any way in connection with the loss of HMAS Bundaberg on 11 August
2014.” The parties had treated the resolution of that claim separately to the resolution of
the remediation issues.
[26] As it transpired, during the period November 2015 to February 2017 the plaintiff by its
subcontractors carried out and was paid for (1) the contemplated remediation work (at cost
as provided for in the remediation deed); and (2) certain other additional work which was
treated as not covered by that obligation. Some of the work was done by the plaintiff’s
subcontractor in Singapore and some was done by another subcontractor in Australia. The
plaintiff’s Mr Miller (of whom more later) deposed to an analysis of which part of the costs
should be regarded as part of the contemplated remediation and which part should not. I
accept his evidence.
The loss of the Bundaberg
[27] On 11 August 2014, the Bundaberg was in dry-dock in the possession of the plaintiff for the
performance of routine scheduled repairs and maintenance pursuant to the provisions of the
Contract.
[28] An employee of the plaintiff’s subcontractor was welding on a vertical bulkhead in such a
way as to cause a “blow through” which resulted in red hot metal slag falling onto
combustible material behind the bulkhead, and out of sight of the welder. That caused a fire
which quickly spread throughout the vessel, resulting in its destruction. The subcontractor
had not taken reasonable precautions in the welding work, including by not having a fire
sentry posted on the other side of the bulkhead in order to detect and extinguish fires caused
in this manner.
[29] It was common ground before me that the circumstances in which the loss of the Bundaberg
occurred meant that –
(a) by cl 6.8.1.1 of the Contract, the plaintiff became liable to indemnify the
Commonwealth against “any loss or damage to the Patrol Boat”; and
(b) by cl 8.3.1 of the Contract, the plaintiff became liable to the Commonwealth to
“promptly replace or otherwise make good any loss of … the [HMAS Bundaberg]”.
5 Clause 7.9 was the equivalent of a directed variation clause in a construction contract.
-- 7 of 36 --
8
[30] As at the time that the plaintiff became subject to those obligations to the Commonwealth
under the Contract:
(a) There was no secondary market for Armidale Class Patrol Boats. Only 14 had ever
been constructed and the other 13 were all in service with the Royal Australian Navy.
In order to replace the Bundaberg with another Armidale Class Patrol Boat, the
plaintiff would have had to build a new one. As Armidale Class Patrol Boats had been
out of production for almost 7 years, the one-off construction of a replacement
Armidale Class Patrol Boat would have been a very expensive proposition.
(b) The Bundaberg had been in service for about 7½ years. It would not have reached the
end of the contractually-contemplated minimum 20 year service life until 2027. If the
Contract was not terminated or extended, the Bundaberg would have been expected to
be in service under the Contract for another 7½ years, until about March 2022. The
deadline for extension of the Contract had not yet been reached, so the possibility of
extension of the Service Period for 5 years beyond that still existed.
(c) It was known by both the plaintiff and the Commonwealth that, like the other Patrol
Boats in the fleet, the Bundaberg required remediation for the problems which I have
described under the previous heading.
[31] Further, although the remediation deed had not yet been made, there is no reason to think
its terms would have been materially different if the Bundaberg had not been lost. Mr Miller
suggested (and I would accept) that if the Bundaberg had not been destroyed, it is likely that
the plaintiff would have scheduled its remediation under the remediation deed via the
plaintiff’s Australian subcontractor in the January-February 2017 timeframe. On the basis
of the costs which were in fact incurred for remediation for each vessel Mr Miller opined
(and I would accept) that it is fair to say that the Bundaberg’s remediation would probably
have cost $2.64 million.
The dispute with the Commonwealth as to the quantum of the plaintiff’s liability
[32] The plaintiff’s Mr Miller was an engineer with over 30 years’ experience in senior
management, engineering and consulting roles, primarily focused on the maritime defence
industry. He was the plaintiff’s Head of Operations between May 2014 and December 2015,
with executive responsibility for the overall administration of the Contract. He was the
plaintiff’s officer in charge of examining the options by which the plaintiff could discharge
its obligations to the Commonwealth consequent upon the destruction of the Bundaberg.
[33] I received evidence from Mr Miller in affidavit and testimonial form. His evidence was both
credible and measured. I have no hesitation in accepting it. He knew that the plaintiff was
insured, but had at an early stage been copied in on material which revealed that the insurer
had not accepted liability. In my view his behavior and the judgments he formed during the
course of negotiations with the Commonwealth were at all times consistent with how a
prudent uninsured person in the position of the plaintiff would behave.
[34] In relation to the administration and management of the Contract, lines of communication
had long been established between Mr Miller and the Commonwealth’s Mr Evans, the
Director General Specialist Ships for the Defence Materiel Organisation (a division of the
Commonwealth’s Department of Defence). Those lines of communication continued in
relation to the resolution of the issues concerning the Bundaberg. Mr Evans was based in
Canberra and Mr Miller in Melbourne. Mr Miller had regular ongoing contact with Mr
Evans by way of emails and telephone calls approximately 2 or 3 times each week. He had
known Mr Evans professionally since about 2006 when they each had roles in other
-- 8 of 36 --
9
companies which were in competition with each other. Mr Miller trusted what Mr Evans
told him. There is no reason to think that was not a reasonable course of action.
[35] The plaintiff had, by its relevant officers, explored multiple options by which it could satisfy
its contractual obligation to “promptly replace or otherwise make good” the loss of the
Bundaberg. Mr Miller deposed to the analyses which were done and I accept his evidence.
[36] Mr Evans had from an early stage and on a number of occasions emphasized to Mr Miller
the Commonwealth’s preparedness to accept in principle that the plaintiff could meet its
obligation to “promptly replace or otherwise make good” the loss of the Bundaberg by
meeting the cost of the provision of an alternative vessel with acceptable functionality.
[37] Mr Miller took the view (and there is no reason to think that this was not a reasonable view)
that the functionality provided by the Armidale Class Patrol Boats included at least the
following requirements:
(a) To operate on continuous patrol, around the clock, for up to 42 days, in certain oceanic
regions of interest to Australia, noting that some of these regions are characterized by
heavy weather and high sea states, all of which impose design requirements for range,
endurance and “ride control” to ensure stability and seaworthiness in rough seas.
(b) To accommodate a Navy crew of a specified size plus a specified number of non-
military passengers, such as asylum seekers or rescue survivors.
(c) To conduct secure, encrypted electronic communications regarding classified military
matters using equipment that met demanding military specifications.
(d) To conduct gunnery operations at night or in low visibility, fire-control for which
required a complex system of hardware and software including an electro-optical
acquisition and control sensor.
[38] By September 2014, Mr Miller had considered and rejected the possibility of building a new
Armidale Class Patrol Boat. The production line which had been used by the plaintiff’s
Australian subcontractor during the course of original construction had been closed for years,
and equipment and other items essential for the vessels were no longer available. Mr Miller
considered that a one-off new build was not a viable option. It might have been technically
feasible, but would likely be cost-prohibitive. That view was later confirmed by expert
reports dated 6 and 10 November 2014, which valued at $40,527,932 the cost to build a vessel
with functionally identical to the Bundaberg in an Australian Shipyard using 2014 rates for
labour and materials. Mr Miller did not see those figures until later, but when he did, thought
that they were likely to be an under-estimate of what a rebuild would actually cost. As will
appear, his view about likely cost was supported by the quantum of the claim eventually
advanced by the Commonwealth on the basis of replacement.
[39] One possible option was a vessel referred to as an Inshore Patrol Vessel, which was in service
with the Royal New Zealand Navy. That vessel was steel-hulled rather than aluminium-
hulled but was dimensionally and operationally similar to the Armidale Class. The
Commonwealth looked at this possibility but was unable to progress a long-term deal with
New Zealand. Accordingly, this turned out not to be a feasible solution.
[40] Between September and November 2014, the plaintiff explored the possibility of procuring
a commercial vessel with similar physical dimensions as an Armidale Class Patrol Boat and
then modifying the vessel with a view to providing equivalent functionality. An approach
was made to Clarksons Shipbrokers, but to no avail. The possibility of pursuing either of two
vessel configurations offered by Damen Shipbuilders was explored. Initial cost estimates
-- 9 of 36 --
10
were $35.6 million for the first configuration and $48.9 million for the second. The problem
with these options were, as the plaintiff later advised its insurers (and there was no challenge
to the advice so given), (1) the cost was very high, and costs might increase when conversion
started; and (2) the capability achieved would still be less than provided by an Armidale Class
Patrol Boat.
[41] By letter dated 17 April 2015, the Commonwealth advanced a formal claim against the
plaintiff on the hypothesis that the plaintiff was obliged to replace the Bundaberg with
another Armidale Class Patrol Boat. It quantified the claim at $51,047,000, calculated by
reference to the original build cost of the Bundaberg, indexed for inflation, together with a
further $306,764.21 for other losses.
[42] On 20 April 2015, just after the Commonwealth had advanced its $51 million claim based on
replacing the Bundaberg with another Armidale Class Patrol Boat, the Commonwealth (by
Mr Evans) expressed to the plaintiff (by Mr Miller) its desire that the plaintiff indemnify it
for the cost of a Cape Class Patrol Boat as a replacement for the Bundaberg rather than a
modified Damen vessel. The Cape Class was a type of Patrol Boat then in production via a
contractor named Austal. With some systems upgrades, a Cape Class Patrol Boat could be
made functionally equivalent to an Armidale Class Patrol Boat. Amongst other things, Mr
Evans told Mr Miller that the Navy had formed a strong preference for the Cape Class vessels
and proposed to acquire two such vessels, by a 3 year lease arrangement. It was not clear to
Mr Miller why such a short term proposal was being advanced when the Bundaberg would
have been in service for much more than 3 years, and he asked that question of Mr Evans by
email the next day.
[43] Mr Evans’ response made it clear that the Commonwealth had not finalized its plans as to
how it would replace the functionality lost when the Bundaberg was destroyed. By email on
21 April 2015, he conveyed to Mr Miller that the 3 year lease proposal in respect of Cape
Class vessels was only part of those plans. There would likely be a need to lease a further set
of vessels for about the 7 year period from 2017 to 2024, where a new class of vessel (Offshore
Patrol Vessels, or OPVs) would start to come in. Mr Evans referred to a need for a “White
Paper” before plans could be finalized.
[44] The plaintiff’s formal response to the Commonwealth’s $51,047,000 claim was a letter of 15
May 2015. The plaintiff accepted liability to replace the Bundaberg. However, it contended
the claim was excessive; it would be to “unjustly enrich” the Commonwealth if it were to be
provided with the value of a new Patrol Boat in the place of a Patrol Boat which had been in
heavy use for some 8 years; and that the realistic value of the Commonwealth’s loss was the
“pre-fire value” of the boat, namely between $16.245 million and $17.55 million. The
quantum of the contention there advanced was based on an expert valuation opinion dated 6
November 2014, which valued the Bundaberg based on original cost of construction less an
allowance for depreciation.
[45] In the meantime, by mid-late 2015, Mr Evans moved away from the position expressed in
April 2015 and informed Mr Miller that the Commonwealth had settled on an arrangement
whereby two Cape Class Patrol Boats were to be loaned to the Navy by the Australian Border
Force for a period of two years until 2017, during which period the Commonwealth would
then contract with Austal (a boat builder), via an arrangement whereby the National
Australia Bank would own the vessels, to build two new Cape Class Patrol Boat expressly for
the Commonwealth’s use. The two Cape Class Patrol Boats on loan from the Australian
Border Force would be returned to the Australian Border Force. The loan of vessels during
the construction period came at a cost to the Navy.
-- 10 of 36 --
11
[46] So far as the dispute between the Commonwealth and the plaintiff as to the quantum of the
plaintiff’s liability was concerned, the positions crystallized by the formal claim dated 17
April 2015 and the formal response dated 15 May 2015 were maintained when the
Commonwealth delivered a formal position paper dated 31 July 2015 and the plaintiff
responded on 3 August 2015. By that time the plaintiff had received advice from its solicitors
that:
There is a not insignificant risk that a Court could accept the Commonwealth argument that the obligation to
‘make good’ the loss requires [the plaintiff] to pay the full cost of the Commonwealth reinstating whatever
equivalent Patrol Boat capacity it is able to find. If the only available replacement vessel is a new [Armidale
Class Patrol Boat], the Commonwealth may be reasonable in contending that the present day value of
reinstating the vessel is the minimum that will be sufficient to ‘make good’ the loss (although even if that be
the appropriate measure of damages, we would query whether the original build cost indexed for inflation
bears any relevance to the current cost of building another [Armidale Class Patrol Boat]).
The dispute as between the plaintiff and its insurers
[47] The plaintiff was insured against its contractual liability to the Commonwealth under the
contract for the loss of the Bundaberg. The defendant was one of its insurers. Under the
Insurance Policies the defendant agreed to indemnify as to 100% of a primary layer of $10
million and as to 50% of a first excess layer of $40 million in excess of the $10 million first
layer.
[48] It is common ground that the clause of the Insurance Policies which operated as the insuring
clause was in these terms:
Underwriters hereby agree, subject to the limitations, terms and conditions hereinafter mentioned to
indemnify the Assured for all sums which the Assured shall become liable to pay by reason of the legal
liability of the Assured as shiprepairers for:-
(i) Loss of or damage to any vessel or craft which is in the care, custody or control of the Assured
for the purpose of being worked upon including shifting and moving within the limits of the port
at which the work is being carried out and including trial trips but not exceeding 100 miles from such
port;
…
(vi) Loss of or damage to third party property occurring in the course of or arising from the ship repairing
operations of the Assured,
where such liability results from negligence of the Assured, his servants, agents or sub-contractors
occurring during the period of this insurance.
[49] An initial dispute between the plaintiff and the defendant as to whether the defendant should
indemnify was settled on terms recorded in a deed dated 25 November 2015 (the Indemnity
Settlement Deed). Relevantly, the Indemnity Settlement Deed provided:
Recitals
1 On 17 December 2003, DMS entered into the APCB Contract with the Commonwealth of Australia
(Commonwealth) for the supply and support of Armidale Class Patrol Boats (ACPB Contract).
2 On or about 20 February 2014 RSA agreed on certain terms set out in the Insurance Policies to
indemnify DMS (among other things) in respect of any liability which DMS may incur to the
Commonwealth under the ACPB Contract.
3 One of the vessels for which DMS was responsible under the APCB Contract, the HMAS
Bundaberg, was destroyed by fire on 11 August 2014 whilst in the possession of a DMS
subcontractor.
4 A claim has been made against DMS under the ACPB Contract in respect of the fire and discussions
with the Commonwealth are ongoing, although the quantum of liability has yet to be determined
(Commonwealth Claim).
-- 11 of 36 --
12
5 DMS has made a claim under the Insurance Policies seeking indemnity in respect of its liability to
the Commonwealth for the damage to the HMAS Bundaberg (HMAS Bundaberg Fire Claim).
6 A dispute has arisen between RSA and DMS in relation to whether RSA is obligated to indemnify
DMS under the Insurance Policies (Dispute).
7 On a without admissions basis, the parties have settled the Dispute on the terms set out below in full
and final settlement of RSA’s liability for the HMAS Bundaberg Fire Claim.
8 The parties wish to enter this deed to record the terms of settlement and have effect in a manner
that most effectively resolves any Claims of the parties against each other in relation to the HMAS
Bundaberg Fire Claim.
9 RSA’s obligations under this settlement and deed relate to its own liabilities under the Insurance
Policies for its share or proportion of liability only. RSA has not acted for and does not act for and
on behalf of any other insurer and nothing in this Deed shall constitute or be construed as
constituting an attempt by RSA to bind any other insurer for its part.
1 Confirmation of coverage
(a) Subject to paragraph (b) and (c) below, RSA for its part and proportion alone confirms coverage for
DMS of the HMAS Bundaberg Fire Claim under the insurance policies and specifically confirms
that RSA:
(1) will indemnify DMS in accordance with the terms of the Insurance Policies for the HMAS
Bundaberg Fire Claim; and
(2) save for amounts/categories of claim that are not covered by the terms of the Insurance
Policies (see clause 1(c) below), waives any right RSA may have had to decline or reduce
payment of the HMAS Bundaberg Fire Claim, including as a result of any acts or omissions
of DMS prior or subsequent to inception of the Insurance Policies.
(b) In consideration of the confirmation of coverage set out in paragraph (a) above, DMS has agreed to
accept 80% of the quantum to which it would otherwise have been entitled to be paid by RSA under
the terms of the Insurance Policies in full and final settlement of RSA’s liability under the Insurance
Policies.
(c) The parties agree that settlement of the Commonwealth Claim shall not be determinative of the
amount to which DMS is entitled to be indemnified for the HMAS Bundaberg Fire Claim under the
insurance policies. Such amount to be indemnified shall be determined in accordance with the terms
of the Insurance Policies alone.
…
2 Mutual Releases
Subject to clause 1 above being abided:
(a) each party releases and discharges the other party from any Claim that either party has or may have
against the other in respect of the HMAS Bundaberg Fire Claim (the Released Matters).
(b) in support of the releases in (a) above each party covenants with the other party not to claim, sue or
take any action against the other party in respect of the Released Matters. Each party acknowledges
that the other party is entitled to enforce this deed directly and may plead this deed in bar to any
Claim by the other party in respect of the Released Matters.
(c) the parties acknowledge that except as expressly dealt with by this deed, the terms of the Insurance
Policies otherwise remain in full force and effect.
…6
4 Defence of Commonwealth Claim
The parties agree that:
(a) DMS will keep RSA fully advised of significant developments in the Commonwealth Claim. In
particular, DMS will advise RSA without delay of any offers or proposals made in the
6 Clause 3 expressed a confidentiality clause, the terms of which are unnecessary to record.
-- 12 of 36 --
13
Commonwealth Claim and shall without delay be offered the opportunity to participate in any
meetings or conferences (in person, by videocon, or by telephone as appropriate).
(b) Stephenson Harwood, for and on behalf of RSA, will be copied in to all advices from Herbert Smith
Freehills relating to the dispute. All relevant advices already sent to DMS will be provided to
Stephenson Harwood within 14 days of the execution of this deed.
(c) No agreement on settlement of the dispute, or compromises shall be concluded by DMS without
RSA having been given reasonable opportunity to comment. For the avoidance of doubt, RSA
acknowledges that it does not have the right to veto or (subject to clause 1(c) above) object to any
settlement or compromise which DMS wishes to offer or accept based on legal advice.
Events leading up to the plaintiff’s settlement with the Commonwealth
[50] At [41] to [46] above, I identified the way in which the respective positions of the plaintiff
and the Commonwealth were crystallized and then formalized between April and August
2015.
[51] The next significant step was that a meeting occurred on 18 December 2015 between the
plaintiff and the Commonwealth. Mr Evans represented the Commonwealth (although a
Commonwealth lawyer was present by telephone). The plaintiff was represented by Mr
Lantz, Mr Miller and Mr Makotsvana. Mr Lantz was general counsel of the plaintiff’s parent
company. He had first become involved after the receipt of the Commonwealth claim of 17
April 2015 and had been involved in drafting the response dated 15 May 2015. He was
familiar with the competing positions there expressed and also as maintained in the
Commonwealth’s position paper dated 31 July 2015 and the plaintiff’s response of 3 August
2015. Mr Makotsvana was a Financial Officer within the plaintiff’s parent company.
[52] Essentially three matters of note occurred, the last being the only matter of present
significance. First, Mr Lantz conveyed that any settlement would require consultation with
the plaintiff’s insurers and sign off at parent company board level. Second, each party
reiterated the positions which they had already conveyed during previous negotiations. In
particular Mr Evans kept reiterating the proposition that the plaintiff had to replace or make
good the loss of the Bundaberg by either replacing it with another Armidale Class vessel or
with a vessel with equivalent operational capabilities, and the plaintiff’s liability was not
based on the depreciated value of the Bundaberg. Third, Mr Evans expressed what he
described as the Commonwealth’s best and final offer, namely that it would accept $31.5
million in full and final settlement of its claim.
[53] Mr Evans advanced the following explanation for the quantum of that offer:
(a) The Commonwealth had been in negotiations with Austal to build two Cape Class
vessels, which would cost a base price of $31.5 million per vessel.
(b) The price of $31.5 million was a result of hard fought negotiations by the
Commonwealth, was part of a 2 vessel build price, and did not take into account the
costs of upgrading a Cape Class vessel with the necessary equipment to make it an
equivalent in functionality and capability to the Bundaberg.
(c) Those costs would bring the base cost to over $40 million, but the Commonwealth was
willing to absorb those additional costs if they could reach a settlement with plaintiff to
pay the $31.5 million base build cost.
[54] Each of Mr Lantz, Mr Miller and Mr Makotsvana formed the view – based on the statements
made by Mr Evans – that the $31.5 million offer was the lowest the Commonwealth was
prepared to go in terms of compensation for the loss of the Bundaberg. They discussed it
amongst themselves in another room. Mr Miller had the view that the Commonwealth offer
-- 13 of 36 --
14
of $31.5 million “was the lowest number of any feasible option that [the plaintiff] had
considered”. He saw no merit in trying to advance a contention that the figure should be
further reduced by reference to the notion that the Commonwealth would not have to
undergo the costs of remediation of the Bundaberg that they would otherwise have had to
undergo, because he felt that such a course would simply cause the Commonwealth to return
to the starting point of $40 million. The outcome of the internal discussion was that the
plaintiff’s representatives agreed that the position taken by the Commonwealth seemed to
be a reasonable one.
[55] Following the private discussion, Mr Lantz conveyed to Mr Evans that the plaintiff
understood the Commonwealth’s position and the logic behind it and that it appeared
reasonable. Mr Lantz explained that they would recommend acceptance of the offer but that
it would be a matter for approval by the parent company board in consultation with their
insurers. The meeting then ended with Mr Evans saying that he hoped to hear from them as
soon as possible.
[56] Subsequent to the meeting, on 3 February 2016, Mr Evans followed up Mr Miller, reiterating
the key points which he had made at the 18 December 2015 meeting, in these terms:
Dave - I have not heard from you on the matter of the Bundaberg loss indemnification since our meeting on
the 18th December last year with Robert Lantz. We have now spent a great deal of money setting up
arrangements with Austal, Border Force, the Defence Minister’s Office, not to mention Navy, to cover that
loss, and we are going to need the recompense for that loss very shortly. To re-cap on only a couple of the
major threads in those talks in your office prior to Christmas, I advised that -
• The $31.5 Million figure provided is a floor level below which we will not go, and has had 8 months
of hard fought negotiations with Austal to arrive at that replacement cost for the new-build boats
which must replace Bundaberg, and the availability shortfalls arising from the hull Remediation
which could now cost $50 - $60 Mill, which the company should have covered and did not. We have
not claimed that in our settlement discussions.
• As an indicator of how tough I’ve been on Austal in driving that cost down, you will find in the
Australian National Audit Office report on the “Management of the Cape Class Patrol Boat
Program” (in Customs & Border Protection), - ANAO Report No13 2014-15, that Customs paid
$277.7 Million for 8 of the exact same Capes in August 2011. That cost does not include anything
other than cash advances on the build, and equates to a vessel cost equivalent of $34.71 Million
dollars each - over 4 years ago!! - the $31.5 Mill figure represents a cut of nearly 10% on significantly
fewer boats to manufacture, and against an externally contested competitive tender process.
• The ANAO report is a matter of public record, and you will find the references at Pages 16 and 26
of that report. The Acquisition cost with spares ran to $316.5 Mill or just under $40 Million for each
boat - to reiterate - in 2011 (see page 26). If you have trouble finding the ANAO report, give me a
call and I will copy it for you. Note that on my initial approaches to then Austal Marketing Director
- Dave Shiner, I was quoted $42 Million per boat as a “special favour” to Defence.
• Chief of Navy personally made the choice of replacement on the closet possible exemplar to the
Armidales in selecting that replacement boat, despite other more readily available options being
provided to him. The Cape Class boat is an Armidale family vessel.
We have covered a lot of ground in our discussions on this matter, and I won’t repeat it all here, but there is
no case for a market price on a specialised military asset like this, and the arguments over depreciated value
have been had between the lawyers, and don’t stack up. The $31.5 Million figure is the bottom figure, and it
should be settled without delay, or I fear this set of discussions will be taken out of my hands, and head in a
decidely [sic] different and sub-optimal direction.
Your attention to this matter will be most appreciated. - We have demonstrated our patience on a fire and
catastrophic loss that occurred in August 2014, in quite unsatisfactory and frankly avoidable circumstances,
and it is time to settle. Please bring this to a speedy conclusion for all our benefits.
-- 14 of 36 --
15
[57] The offer, of course, was a lump sum offer, explained by reference to the costs of acquisition
of Cape Class vessels. Yet, as I have already recorded, the plaintiff had been told that the
Commonwealth intended to embark upon a lease rather than purchase arrangement. Mr
Makotsvana asked Mr Miller to obtain details about the lease costs. On 12 February 2016,
Mr Evans responded to the enquiry which Mr Miller had made of him in these terms
(emphasis added):
Dave - Cape Class costs as follows -
• Leasing for 3 years - $29.529 Mill for 2 boats - Required out to 2025 minimum!
• ISS Costs for 2 Loan boats from Customs till early 2017 - $13.53 Mill for 2 years
• ISS Costs & Comms for Lease boats - ie, 2017 to 2020 - $27.21 Mill (detail list available)
• Crew Training - has been $640.8k - will repeat every 2 years.
• 2 x Ship managers funded at Customs (ACT) permanently, and 3 Project Staff at Henderson WA
for the duration of CCPB Build and bring into Service & Close out (End of 2017) - $2.44 Mill
annually
• Warehourse Spares & OAL - $1.2 Mill (per 12 mths)
• ICT Installation & Training - $417k for 2 years
• Extra Comms costs - FB500 data costs - $2.4 Mill (2 years) - List available
• 3G data costs - $480k (2 years)
• AMOS Licences, ECDIS Licences, MES & Liferaft, Change Certificate - ie, AMSA to Naval Flag -
$200k+ at start
etc. These don’t include all the bring into Navy service processes, re-run of SATs etc, nor the replacement
of the Seaboat which can’t handle 8 + 2 crew ($1 Mill per boat), etc
There is a variety of start-up, and then run costs which you’ll be able to re-cipher from the list. The costs
need to be extrapolated out to 2025 which I have not had time to do (but can if you specifically need it),
and we were not able to lease boats for a longer period by Minister Andrews - Had to be a ‘stop gap’
measure before replacement by OPVs from 2020.
Hope it helps - We are seriously out of pocket at a $31.5 Mill claim.
[58] Mr Miller reported on that information to Mr Lantz and Mr Makotsvana. Initially Mr Miller
told them that he thought the Commonwealth was going to buy the two Cape Class vessels
when the two boats on loan from the Border Force were returned. However he realized that
was an error and he emailed them that:
Current boats are loaners. The new boats being built now will be leased through NAB for 2-3 years and after
that it gets very fuzzy due to uncertainty re the OPV program.
[59] Mr Miller was cross-examined on his understanding of the lease arrangements mentioned in
various conversations with Mr Evans. He was also cross-examined on whether there was
some inconsistency between the notion of costs being required out to 2025 minimum and the
recognition that after the expiry of the NAB lease, it “gets very fuzzy due to uncertainty re
the OPV program”. His understanding was as follows:
(a) Of the two vessels the subject of the lease arrangements, one was intended by the
Commonwealth as the replacement for the Bundaberg and the other was intended to
replace the availability lost over the whole fleet because of remediation issues.
(b) He thought that Mr Evans’ reference to “required out to 2025 minimum” was a
reminder that the Commonwealth was entitled to expect that the Bundaberg would
have been in service through to 2025.
-- 15 of 36 --
16
(c) It was his understanding that the Commonwealth had not made any specific decision
as to precisely how it would replace the loss of the capability of the Bundaberg after the
leases expired.
(d) His reference to it getting “very fuzzy” after the expiry of the initial lease term was
intended to convey that it was unclear to him whether the Commonwealth would
extend the lease or pursue some other option for the replacement of the Bundaberg.
(e) He thought that none of this affected the extent of the plaintiff’s obligation to replace
or otherwise make good the loss of the Bundaberg.
[60] By letter dated 7 April 2016, Mr Evans confirmed the Commonwealth’s position that it
would not go below the $31.5 million offer in these terms:
1. It is now some months from our meeting on the 18th December 2015, where discussion and agreement
was reached on the recompense of the Indemnity for the loss of HMAS BUNDABERG in a fire in
Brisbane at August 2014.
2. We spent some hours in those talks where I covered the basis of the cost below which we cannot go,
based on the capital costs of two new Cape Class Patrol Boats being built by Austal in Henderson, W.A.
That capital cost of $31.5 Million was negotiated intensely over 8 months, and is substantially below the
cost paid by Customs & Border Protection for their 8 Capes as contracted three years earlier in a
competitive tender. Further, the Capes are the exemplar as judged by Chief of Navy, to be the boat
most closely approximating the Armidale Class Patrol Boats.
3. It is now 20 months since the loss of BUNDABERG whilst under the control of [the plaintiff] at the
ABA yard in Brisbane, and you advised that your insurer wanted the Revised In-Service-Support-
Contract negotiations completed, before the Insurance claim on BUNDABERG would be considered.
That time is now also well passed, and there will be no further negotiations on this matter.
4. We expect your payment of the settlement amount to us, by no later than the 31st May 2016. I would
appreciate your confirmation that earlier verbal assurances on this matter will see the Indemnity cleared
well inside the end of the current financial year.
[61] In further correspondence dated 28 April 2016, Mr Evans again put the Commonwealth
position and requested payment by 31 May 2016. He was evidently frustrated at the lack of
progress in resolving the matter, especially given what he thought had been a resolution
reached at the December meeting. Referring to that meeting he wrote (bold emphasis
added):
…
6. During those talks, I discussed the three main methodologies of valuation of the loss, and believed
that we achieved consensus by the end of the meeting that a “Market Value” methodology could
not be validly applied to a bespoke design military asset, and I did relate to the gents that there
were some 500 patrol boats on the world market at the time (I had personally checked!), and none
would have made a satisfactory replacement, due to either being short, too long, too old,
insufficient range, etc.
7. I demonstrated that the “Depreciated Value” methodology also had major shortcomings, and
noted that on Monday of the week of our December talks, Austal had advised the winning of the $63
Million dollar contract with Defence to build two Cape Class Patrol Boats. Chief of Navy, VADM Tim
Barrett had personally selected these boats as the closest possible exemplar vessel to replace
BUNDABERG. I advised the SERCO gents that the $31.5 million dollar unit price of those boats was
significantly below the price that Customs had paid for their eight boat fleet two years prior. The Austal
negotiations had taken eight months of my personal involvement, and one of those boats was the direct
replacement of BUNDABERG. As a consequence, I expressed the view that the “Replacement
Cost” methodology of valuation most closely reflected our actual loss, and I specifically noted that
the $31.5 Million dollar cost had no allowance for Spares & Consumables, etc, which would add
millions of dollars.
-- 16 of 36 --
17
[62] Following receipt of the 7 April 2016 letter from the Commonwealth seeking demand of
payment of $31.5 million by 31 May 2016, Mr Lantz decided to seek independent advice on
the reasonableness of the Commonwealth’s offer. Mr Lantz instructed a separate firm of
solicitors who recommended that Mr Jackman SC be briefed to provide an opinion on the
reasonableness of the offer. Mr Jackman SC and Ms Taylor of junior counsel were briefed
on 3 May 2016 and their opinion was received on 10 May 2016.
[63] Counsel’s opinion was that it would be reasonable for the plaintiff to accept an offer of $31.5
million in full and final settlement of the Commonwealth’s claim.
[64] Counsel identified that there were, by the time of the Commonwealth’s $31.5 million offer,
at least four methods of valuing the loss of the Bundaberg, namely:
(a) the Commonwealth’s initial claim of $51,047,000 based on cost of replacement with
an another Armidale Class vessel;
(b) a Commonwealth claim based on the cost of making a Cape Class vessel functionally
equivalent to an Armidale Class, which the Commonwealth had suggested was
$40,500,000;
(c) replacement value on the same basis, but as valued by the plaintiff’s own valuers in the
sum of $40,527,932; and
(d) asset value of the Bundaberg as valued by the plaintiff’s own valuers in the range of
$16,245,000 to $17,550,000.
[65] Counsel considered that an analysis of the case law concerning the measure of damages when
a vessel is lost due to actionable wrong was an appropriate means by which to assess the
measure of the plaintiff’s liability to indemnify the Commonwealth against the loss of its
vessel.
[66] After an analysis of those authorities, Counsel expressed the following conclusions:
52. The Asset Value originally propounded by DMS in its negotiations with the Commonwealth (in the
range of $16,245,000 to $17,550,000) is an inappropriate measure of damages, for at least the
following reasons:
a. The Asset Value range proceeds on the basis of an assumed market value, which (as the
cases above establish) is not ordinarily the correct measure of damages for a destroyed
vessel in respect of which there is no second-hand market;
b. The assumed market value on which the Asset Value range is based (ie. before the
depreciation is applied) is unlikely to be made good on the evidence. There is no market
for the vessels. Further, it is based on the cost of a new vessel when built with an economy
of scale which is no longer available;
c. The Asset Value is likely to under-compensate the Commonwealth, as it cannot obtain the
replacement vessel that it needs to carry out the functions of the HMAS Bundaberg for a
price within that range. Where the vessel is a one-off (or, at least, was custom built as one
of 14 vessels for particular navy purposes), the cost of reinstatement is a more reasonable
measure of damages, as it was in Randell, and
d. …
53. On the other hand, the Replacement Value calculated by DMS’ valuers significantly exceeds the
Commonwealth’s offer of settlement and is based on the cost of a newly built vessel (in the amount
of $40,527,932). The cases referred to above are inconsistent as to whether the Commonwealth
would be entitled to the cost of a newly built vessel without accounting for the benefit it receives by
obtaining new for old. However, there are several cases which suggest that the concept of
betterment would not apply in light of the fact that the Commonwealth arguably has no real choice
in that there is no cheaper equivalent vessel available on the second-hand market. In any event, the
-- 17 of 36 --
18
Replacement Value is substantially higher than the Commonwealth’s offer of $31,500,000, and on
the basis of the limited information available we therefore consider that this figure provides adequate
allowance for any hypothetical benefit to the Commonwealth as well as the uncertainty which arises
in the case law on this issue.
54. Further, we consider that the Cape Class Alternative Replacement Cost put forward by the
Commonwealth to justify its offer is calculated on a basis which is consistent with many of the above
cases. We note our instructions that the Chief of Navy considered the Cape Class vessels to be the
closest type to the HMAS Bundaberg. We have no reason to doubt the Chief of Navy’s opinion on
this issue, and in addition we consider it unlikely that DMS would be in a position to lead convincing
evidence to dispute this claim. Nor have we, at this stage, any reason to doubt the Commonwealth’s
estimate for upgrading the Cape Class vessel to meet the requirements of the Armidale Class. If
those assumptions are correct, the Commonwealth’s claim to be entitled to a sum in the order of
$40,500,000 is convincing. In forming this conclusion, we have had regard to the following:
a. The Cape Class Alternative Replacement Cost seems to us to be a reasonable calculation
which would take account of the applicable principles such as those stated in Randell v
Atlantica Insurance Company Ltd at 287 and Port Kembla v Braverus at [486]-[488], to the
effect that the cost of reinstatement is appropriate where there is a vessel designed for the
plaintiff’s own use, and a plaintiff is not ordinarily obliged to account for any advantage or
betterment which has been obtained by acquiring a new article for old in the case of a
replacement after total loss; and
b. Further, and in any event, the offer of $31,500,000 makes a considerable allowance for any
such benefit or advantage which might be obtained by the Commonwealth as a result of the
reinstatement of a newly built vessel.
55. Each of the above bases for calculating damages does not make any allowance for the
Commonwealth’s other potential claims such as procurement, training, costs of maintaining a
replacement vessel, and legal costs. As at 17 April 2015 the Commonwealth estimated these other
potential claims at over $300,000. In addition, no allowance has been made for interest.
56. We are conscious of the fact that DMS might have arguments available to it to reduce the damages
available from the Cape Class Alternative Value or the Replacement Value. For example, if further
facts were available, in theory it might be possible to claim that the Commonwealth’s claim to
require a newly built upgraded Cape Class Patrol Boat is not reasonable in the circumstances (see,
eg, The “Maersk Colombo” [2001] 2 Lloyd’s Rep 275 and Voaden v Champion at [88], quoted above).
However, any such argument would involve extensive factual inquiry, including the preparation of
expert evidence, and would be the subject of contest in any final hearing. The reality is that a judge
with no particular expertise in naval vessels and naval requirements would require compelling
evidence before departing from what is ex hypothesi the view of the navy itself as to the suitability of
the various vessels available and the operational requirements of the Navy. In the circumstances,
we think that the figure of $31,500,000 provides ample allowance for the potential for the
Commonwealth’s best claim to be reduced on any such factual grounds which might be available.
57. We further note that litigation will be a lengthy, costly, and uncertain process. On balance, it is likely
that the Commonwealth could be awarded damages greater than $31,500,000, together with interest
on any award of damages. There is therefore a real benefit to DMS in obtaining a full and final
settlement at this early time.
58. For all of these reasons, we consider that a settlement of $31,500,000 in final settlement of the
Commonwealth’s claim is reasonable.
[67] Obviously enough, Counsel’s opinion supported the view which had been reached internally
within the plaintiff and for which the plaintiff had expressed in-principle support at the
December 2015 meeting with the Commonwealth.
[68] The plaintiff provided the opinion to the defendant and sought its support for a settlement
in the terms proposed by the Commonwealth. That support was not forthcoming. There
followed further correspondence between the plaintiff and the defendant culminating in an
exchange of letters dated 27 May 2016. As to this:
-- 18 of 36 --
19
(a) The defendant’s letter of 27 May 2016 from the defendant included criticism that the
plaintiff had not conducted adequate factual analysis of the differences between the
Cape Class vessel and the Bundaberg, and because of this, “any settlement reached
without a full factual enquiry as to the differences between the two types of vessels is
not reasonable under Australian law.” Further the defendant asserted that had this
factual analysis been undertaken, it would have advanced a significantly lower
settlement figure than $31,500,000.
(b) The plaintiff’s letter dated 27 May 2016 rejected the defendant’s approach; contended
that any such “full factual enquiry” would be a waste of time and resources; pointed
out various other alleged defects in the defendant’s position (including that the
defendant’s conduct had been inconsistent with its obligations of good faith); and
concluded with an advice that the plaintiff intended to accept the offer to settle the
Commonwealth claim for $31,500,000.
[69] The Commonwealth Settlement Deed providing for the plaintiff to pay to the
Commonwealth the sum of $31.5 million in 2 equal instalments was signed on 10 June 2016.
The instalments were paid by the plaintiff on 23 June 2016 and 25 July 2016.
The list of agreed issues
[70] The plaintiff and the defendant agreed on a list of issues requiring determination by the
Court. Subject to some re-wording for sense, I reproduce the list below.
1. In considering the quantum of the contractual liability of the plaintiff to the
Commonwealth under the Contract, what is the proper construction and effect of cl
8.3.1?
2. In considering the quantum of the defendant’s liability to the plaintiff under the
Insurance Policies, as amended by the Indemnity Settlement Deed, what is the proper
construction and effect of cl 1(c) of the Indemnity Settlement Deed?
3. Is the plaintiff entitled to establish the quantum of the defendant’s liability to the
plaintiff under the Insurance Policies, as amended by the Indemnity Settlement Deed,
by reference to a settlement of the contractual liability of the plaintiff to the
Commonwealth under the Contract provided that the plaintiff proves such settlement
is reasonable in all the circumstances?
4. Was the Commonwealth Settlement Deed a reasonable settlement of the contractual
liability of the plaintiff to the Commonwealth under the Contract in all the
circumstances?
5. In assessing the reasonableness of the Commonwealth Settlement Deed, in respect of
the contractual liability of the plaintiff to the Commonwealth under the Contract:
(a) was the measure of the liability the cost to the Commonwealth to purchase a
Cape Class Patrol Boat as at 11 August 2014?
(b) if “yes” to (a), should that cost be reduced by reference to betterment, and if so,
to what extent?
(c) in the alternative to (a), was the measure of the liability the market value of
HMAS Bundaberg as at 11 August 2014?
(d) in the alternative to (a), was the measure of the liability the depreciated value of
HMAS Bundaberg as at 11 August 2014?
-- 19 of 36 --
20
(e) in the alternative to (a), was the measure of the liability that pleaded in paragraph
28(d)(iv)(C) of the defence?
(f) with respect to each of the above alternatives, was the measure of the liability to
be determined by taking into account any costs savings to the Commonwealth of
the kind pleaded in paragraph 22U to 22W of the defence?
6. If “no” to 3, is the defendant’s liability to the plaintiff under the Insurance Policies, as
amended by the Indemnity Settlement Deed, to be calculated based on the defendant’s
share of the likely final judgment had the contractual liability of the plaintiff to the
Commonwealth under the Contract been determined at trial based on replacement of
HMAS Bundaberg as pleaded in paragraph 48 of the statement of claim (capped at the
defendant’s share of the $31.5 million settlement sum)?
7. If yes to 3 and 4, or alternatively if yes to 6, what sum is payable by the defendant to
the plaintiff in respect of the defendant’s liability to the plaintiff under the Insurance
Policies, as amended by the Indemnity Settlement Deed?
8. What sum, if any, is payable by the defendant to the plaintiff by way of interest on
account of the defendant paying the $31.5 million settlement sum to the
Commonwealth?
[71] I will address these issues under separate headings below.
Issue 1: In considering the quantum of the contractual liability of the plaintiff to the
Commonwealth under the Contract, what is the proper construction and effect of cl 8.3.1?
[72] Relevantly the clause provided:
[the plaintiff] shall promptly replace or otherwise make good any loss of, or repair the damage to, [the
Bundaberg] at its cost …
[73] In Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104, French CJ
and Nettle and Gordon JJ at [46]-[51] made the following statement of principle in terms
which were subsequently approved by the High Court in Victoria v Tatts Group Limited
(2016) 328 ALR 564 per French CJ and Kiefel, Bell, Keane and Gordon JJ at [51]:
[46] The rights and liabilities of parties under a provision of a contract are determined objectively, by
reference to its text, context (the entire text of the contract as well as any contract, document or
statutory provision referred to in the text of the contract) and purpose.
[47] In determining the meaning of the terms of a commercial contract, it is necessary to ask what a
reasonable businessperson would have understood those terms to mean. That inquiry will require
consideration of the language used by the parties in the contract, the circumstances addressed by the
contract and the commercial purpose or objects to be secured by the contract.
…7
[51] Other principles are relevant in the construction of commercial contracts. Unless a contrary intention
is indicated in the contract, a court is entitled to approach the task of giving a commercial contract an
interpretation on the assumption “that the parties ... intended to produce a commercial result”. Put
another way, a commercial contract should be construed so as to avoid it “making commercial
nonsense or working commercial inconvenience”.
[74] The following observations may be made about the context within which cl 8.3.1 appeared
and the likely purpose of the clause:
7 It is not necessary to quote the paragraphs which deal with the sometimes vexed issue of the use which may be made
of extrinsic material, because that question does not presently arise.
-- 20 of 36 --
21
(a) The Contract was a contract to design, manufacture, produce and deliver Patrol Boats
to be owned by the Commonwealth and to provide Integrated Support Activities over
a contractual service life of at least 15 years.
(b) The Patrol Boats had to be capable of performing specified functional and operational
requirements for an average service life in excess of 20 years, from the date they were
commissioned. The relevant functionality and operational requirements are
summarized sufficiently at [37] above.
(c) At the end of the contractual service life, although the plaintiff would no longer owe
any contractual obligations to the Commonwealth under the Contract, the contractual
contemplation was that the Commonwealth would still own the Patrol Boats.
(d) The cl 8.3.1 promise would apply for the whole of the contemplated life of the Contract.
That means it would have applied during the Production Phase, but would also apply
long after the Production Phase was completed.
(e) The promise would apply to cases in which there was fault by the plaintiff or its
subcontractor (which might also give rise to a contractual remedy for damages)8 and
to cases in which there was not. In either case the promise to replace or otherwise
make good applied.
(f) The promise to “replace or otherwise make good any loss of the thing at its cost” was
a promise which, relevantly, applied to any “thing” falling within the conception of
“Patrol Boat or other Supplies” after it had been delivered, where the damage to the
thing occurred whilst the plaintiff or its subcontractor was in possession of the thing
for the purpose of carrying out Integrated Support Activities.
(g) The thing which was lost could be as big a thing as the entire Patrol Boat, or as small a
thing as a discrete item of equipment used by the Patrol Boat. Whatever it was, the
evident object of the promise was that the Commonwealth would be promptly restored
to the position of having the thing which had been lost.
[75] Against that background, relevant dictionary definitions of the text which the parties chose
may be examined. They are as follows (emphasis added):
(a) The Macquarie Dictionary relevantly defines “replace” as follows:
2. to provide a substitute or equivalent in the place of: to replace a broken vase.
3. to restore; return; make good: to replace a sum of money borrowed.
(b) The Oxford English Dictionary relevantly defines “replace” as follows:
To provide a substitute for; to put an equivalent in place of (something lost, broken, etc.).
(c) The Macquarie Dictionary relevantly defines “otherwise” as follows:
2. in another manner; differently
(d) The Oxford English Dictionary relevantly defines “otherwise” as follows:
a. In another way or ways; in a different manner; by other means; in other words; differently.
….
(e) The Macquarie Dictionary relevantly defines the phrase “make good” as follows:
to make recompense for; pay for
8 See the warranties referred to at [13] above in relation to the performance of Integrated Support Activities.
-- 21 of 36 --
22
(f) The Oxford English Dictionary relevantly defines the phrase “to make good” as
follows:
a. To put right a deficiency.
(a) …
(b) To repay (something that is owed); to pay for; (more generally) to compensate
or atone for.
(c) transitive. To replace, repair, or restore to good condition (something
damaged, faulty, or worn); to repair (damage). Also intransitive: to restore or
repair something, esp. a surface; to fill or raise something up to a specified level.
Frequently in Building.
[76] By adding “otherwise” to “make good”, the text of cl 8.3.1 suggest a link between the
conceptions of “replace” and “make good”. It suggests that the making good must amount
to an equivalent to replacement, a concept which itself required the provision of a substitute
or equivalent thing to the thing lost.
[77] Accordingly, having regard to the plain English meaning of the text used and the context in
which it appeared, the proper construction of the obligation is that if a thing is lost in a way
which engages the promise, the plaintiff must, promptly and at its own cost, either provide a
substitute thing in the place of the lost thing (the provision of an equivalent thing rather than
an identical thing being permissible); or in some other equivalent way make recompense to
the Commonwealth for the loss of the thing. Essentially the cl 8.3.1 promise is properly to
be construed as a promise promptly to restore the Commonwealth to the position of having
the thing lost, or its equivalent. The obligation could be discharged by the plaintiff either by
itself promptly obtaining a replacement thing and providing it to the Commonwealth, or by
paying the Commonwealth sufficient money to enable the Commonwealth to obtain the
replacement thing itself and to make recompense for the fact of it having been lost.
[78] That articulation of the construction of cl 8.3.1 allows me to dispose of one argument
advanced by the defendant.
[79] At the time the parties entered into the Contract, it would have been apparent that the only
Armidale Class Patrol Boats in existence would be those which were going to be made under
the Contract. In the event that one of them was lost during the period of the Contract in
circumstances which engaged the cl 8.3.1 promise, there would never have been a way to
provide an Armidale Class Patrol Boat equivalent in age and usage to the one which was lost,
even if the loss occurred during the Production Phase of the Contract, and building a new
one was a more feasible option. Replacing a lost Armidale Class Patrol Boat with another one
(or even an equivalent), was always likely to carry with it an element of conferring some
degree of benefit on the Commonwealth, in the form of betterment. What was the
contractual contemplation in the event such betterment issues arose?
[80] Similar problems are well known in cases involving the assessment of damages where a
commercial vessel has been lost due to a defendant’s fault. Even though the present issue of
construction cannot proceed on an assumption that the plaintiff was at fault, in light of the
fact that I have construed the promise as being intended to provide for a prompt restitutio, I
think the observations made by Dr Lushington in The Gazelle (1844) 2 W Rob (Adm) 279,
166 ER 759 are apposite:
The right against the wrongdoer is for restitutio in integrum, and this restitution he is bound to make without
calling upon the party injured to assist him in any way whatsoever. If the settlement of the indemnification
be attended with any difficulty (and in those cases difficulties must and will frequently occur), the party in
fault must bear the inconvenience. He has no right to fix this inconvenience upon the injured party; and if
-- 22 of 36 --
23
that party derives incidentally a greater benefit than mere indemnification, it arises only from the impossibility
of otherwise effecting such indemnification without exposing him to some loss or burden, which the law will
not place upon him.
[81] The observations which Dr Lushington made about the right of the injured party against the
wrongdoer are entirely consistent with what the reasonable business person standing in the
shoes of the present contracting parties at the time of contract would have thought about the
intended content of the right of the Commonwealth against the plaintiff as obligor under cl
8.3.1, in the event that the lost thing was one of the Patrol Boats. If the only way of putting
the Commonwealth in the position of having the lost boat, or its equivalent, was a course of
action might have the effect of conferring a greater benefit on the Commonwealth than if the
boat had not been lost in the first place (because a newer and less costly to maintain boat was
provided), then the Contract contemplated that the plaintiff would nevertheless have to take
that course of action.
[82] Another argument advanced by the defendant was that if one of the Patrol Boats was lost, at
least in theory it would have sufficed, in effect, to lease an equivalent boat for the duration of
the remaining service life of the Patrol Boat (or to pay the Commonwealth the monetary
equivalent of the cost of such a lease). I reject that argument. Replacing ownership of a boat
with a lease of a boat could not be that which the promise contemplated, because it would
not give the Commonwealth something which it continued to own at the end of the Contract.
That hypothesis would involve attributing to the parties an assumption that at the end of the
20 year contractual service life, the Patrol Boats would have no possible value or utility to
the Commonwealth. There is no evidence which supports that hypothesis and I reject it.
The hypothesis is not supported by expert opinion evidence as to the absence of a market
value of the Patrol Boats.
[83] In summary, on the proper construction of cl 8.3.1, in the event that one of the Armidale
Class Patrol Boats was lost in circumstances which engaged the indemnity promise, the
plaintiff became obliged, promptly and at its own cost, to restore the Commonwealth to the
position of having the lost boat, or its equivalent. The plaintiff could fulfil its obligation by –
(a) promptly providing the Commonwealth with ownership of a substitute Armidale Class
Patrol Boat in the place of the one which was lost; or
(b) promptly providing the Commonwealth with ownership of some other vessel with
functionality and characteristics which were the equivalent of the lost Armidale Class
Patrol Boat; or
(c) in some other equivalent way promptly making recompense to the Commonwealth for
the loss of the boat (including by paying sufficient money to enable the Commonwealth
to obtain the replacement thing itself and to make recompense for the fact of it having
been lost).
Issue 2: In considering the quantum of the defendant’s liability to the plaintiff under the
Insurance Policies, as amended by the Indemnity Settlement Deed, what is the proper
construction and effect of cl 1(c) of the Indemnity Settlement Deed?
[84] The Indemnity Settlement Deed is a commercial compromise agreement between an insured
and an insurer. The relevant clauses are recorded at [49] above. The deed does, ultimately,
re-express an indemnity obligation in an insurance context. But the construction of
insurance policies does not call for any different approach to the approach identified in Mount
Bruce Mining Pty Ltd. Thus, in Onley v Catlin Syndicate Ltd as the Underwriting Member of
Lloyd’s Syndicate 2003 [2018] FCAFC 119 at [33], Allsop CJ, Lee and Derrington JJ referred
-- 23 of 36 --
24
to the “well-established principles concerning the construction of policies of insurance as
commercial contracts” in these terms (emphasis added):
…. Necessarily, a policy of insurance is assumed to be an agreement which the parties intend to
produce a commercial result: Electricity Generation Corporation t/as Verve Energy v Woodside Energy Ltd
(2014) 251 CLR 640 at [35]: as such, it ought to be given a businesslike interpretation being the
construction which a reasonable business person would give to it: Ecosse Property Holdings Pty Ltd v Gee
Dee Nominees Pty Ltd (2017) 343 ALR 58 at [17]; Simic v New South Wales Land and Housing Corp (2016) 260
CLR 85 at [78]; Todd v Alterra at Lloyd’s Ltd (2016) 239 FCR 12 at 22–23 [42]; Weir Services Australia Pty Ltd
v AXA Corporate Solutions Assurance [2018] NSWCA 100, [52]. The contract is naturally enough
interpreted, in a temporal sense, as at the date on which it was entered into: Ecosse Property Holdings at
[16] per Kiefel, Bell and Gordon JJ; Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR
104 at 116 [47]; Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165 at [40]. The Courts
frequently have regard to the contextual framework in which a contract is formed, to the extent to
which it is known by both parties, to assist in identifying its purpose and commercial objective: McCann
v Switzerland Insurance Australia Ltd (2000) 203 CLR 579 per Gleeson CJ at 589 [22]; Mount Bruce Mining at
117; Franklins Pty Ltd v Metcash Ltd [2009] 76 NSWLR 603 per Allsop P at 618 [19]. It goes without saying
that a construction that avoids capricious, unreasonable, inconvenient or unjust consequences, is to be
preferred where the words of the agreement permit.
[85] In my view a reasonable business person standing in the shoes of the plaintiff and the
defendant just prior to entering into the Indemnity Settlement Deed would have been aware
of at least this context:
(a) The respective parties had entered into the Contract and the Insurance Policies, and
those documents contained the terms to which I have referred.
(b) Events had occurred on 11 August 2014 such that pursuant to cll 6.8.1.1 and 8.3.1 of
the Contract the plaintiff had become the subject of the onerous contractual liabilities
to the Commonwealth to which it had not previously been subject, namely:
(i) the obligation to indemnify the Commonwealth against the loss of the
Bundaberg; and
(ii) the obligation to promptly replace or otherwise make good the loss of the
Bundaberg at its own cost.
(c) The only open question as between the plaintiff and the Commonwealth was the
quantum of that liability. As to that, negotiations had occurred and would occur in the
future, but unless they were successful, the quantum of the liability would have to be
resolved by an agreed alternative dispute resolution process, or in Court, in which the
Commonwealth asserted a claim for damages for breach of the promise to indemnify.
(d) The plaintiff had made a claim on the insurers under the insuring clause seeking
indemnity in respect of its liability to the Commonwealth, but the plaintiff and the
defendant were in dispute as to whether the defendant was obliged to indemnify. Until
the deed was entered into, as between the plaintiff and the defendant both liability and,
necessarily, quantum were still live issues.
[86] Such a person would have reached the view that the purpose of the Indemnity Settlement
Deed was to make it clear that the defendant accepted the obligation to indemnify, but
intended to insist on the plaintiff proving the quantum of that indemnity in accordance with
the terms of the existing insuring clause. That agreement and the extent of the compromise
which was made are recorded in cll 1(a) and (b) of the Indemnity Settlement Deed.
[87] If the defendant had authorized the plaintiff to settle with the Commonwealth on a particular
amount or within any particular range, then the settlement in that amount or within that
-- 24 of 36 --
25
range would have been determinative of the quantum to which the plaintiff was entitled to
be indemnified. The possibility of such authority being given at some future time existed,
because cl 4 of the Indemnity Settlement Deed obliged the plaintiff to keep the defendant
informed and to give it an opportunity to comment before striking any settlement. To my
mind, the evident purpose of cl 1(c) was to make it clear that there was no such authority at
the time of entering into the Indemnity Settlement Deed and that, absent such authority
being given, the plaintiff would have to prove the amount it was entitled to be indemnified in
accordance with the insuring clause and it could not prove that amount simply by proving
the fact of settlement of the Commonwealth claim at a particular amount. I think that is its
proper construction.
[88] The plaintiff does not suggest that proving the fact of settlement at a particular amount is
determinative of the amount of the indemnity to which it is entitled. It accepts that it must
prove more, and contends that it must prove the settlement was reasonable.
[89] The defendant attributes a much greater operative effect to cl 1(c). It contends that the
purpose of the clause was to exclude the possibility that proof of a reasonable settlement by
the plaintiff might be determinative of the quantum of the amount for which the plaintiff was
entitled to be indemnified, so as to put the plaintiff in the position of having to prove what
was the actual amount it was in fact legally liable to the Commonwealth. As to this:
(a) The usual meaning of a contract of insurance providing indemnity against sums which
the insured becomes legally liable to pay to a third party is that the obligation to
indemnify will arise when liability to pay the third party is established by judgment,
arbitral award or reasonable compromise, and not before.9
(b) These principles are and were well-known. Both parties to the Indemnity Settlement
Deed were legally advised. If they had intended to exclude the operation of the
“reasonable compromise” possibility of crystallizing indemnity, it would have been
easy to add the adjective “reasonable” in front of “settlement” in cl 1(c). However
they did not.
(c) In my view there is nothing in the text which the parties chose to express their intention
which supports the defendant’s construction. Indeed, on the defendant’s
construction, the plaintiff would have made it harder for itself to obtain indemnity than
was the position before entering into the deed. The defendant’s construction runs
contrary to what seems to me to be the purpose of the deed. The reasonable business
person standing in the shoes of the plaintiff and the defendant at the time of entering
into the Indemnity Settlement Deed would not have thought the clause had the
meaning which the defendant now attributes to it. Such a person would not have
thought that the Indemnity Settlement Deed was intended to alter the means by which
the quantum of the defendant’s liability could otherwise be proved.
(d) I reject the defendant’s construction of the clause.
Issue 3: Is the plaintiff entitled to establish the quantum of the defendant’s liability to the
plaintiff under the Insurance Policies, as amended by the Indemnity Settlement Deed, by
reference to a settlement of the contractual liability of the plaintiff to the Commonwealth
9 See Post Office v Norwich Union Fire Insurance Society Ltd [1967] 2 QB 363 at 373-374 per Lord Denning MR, at 378
per Lord Salmon LJ; Bradley v Eagle Star Insurance Co Ltd [1989] 1 AC 957 at 966 per Lord Brandon of Oakbrook (with
whom Lord Keith of Kinkel, Lord Oliver of Aylmerton and Lord Jauncey of Tullichettle agreed); Distillers (Bio-
Chemicals) (Aust) Pty Ltd v Ajax Insurance Co Ltd (1974) 130 CLR 1 at 26 per Stephen J; Unity Insurance Brokers Pty Ltd
v Rocco Pezzano Pty Ltd (1998) 192 CLR 603 at [64], 626 per Gummow J.
-- 25 of 36 --
26
under the contract provided that the plaintiff proves such settlement is reasonable in all the
circumstances?
[90] In my view the answer to this question requires a close focus on the terms of the insuring
clause, quoted at [48] above.
[91] The elements of the insuring clause (eliminating words which are irrelevant for present
purposes) are:
(a) Underwriters agree to indemnify the Assured;
(b) for all sums which the Assured shall become liable to pay;
(c) by reason of the legal liability of the Assured as ship-repairers for loss of any vessel
which is in the care, custody or control of the Assured for the purpose of being worked
upon;
(d) where such liability results from negligence of the Assured, his servants, agents or sub-
contractors.
[92] Under the insuring clause the insured’s right to an indemnity from the insurers will accrue
on the happening of the insured event. In this case the insured event is the insured becoming
subject to a liability of a particular character. It must (1) be a liability to pay a sum; and (2)
the liability to pay the sum must have arisen in a particular way, namely “by reason of” a
legal liability of a particular character, where that legal liability was caused in a particular way.
[93] The insured can establish the happening of the insured event by whatever evidence will prove
on the balance of probabilities that the insured event has occurred. That there is a liability
to pay a sum will usually be easily established, and in this case there was no dispute that the
plaintiff had reached a deed of compromise with the Commonwealth which imposed a
liability on it to pay a sum of $31.5 million to the Commonwealth.
[94] More difficult is the means by which the insured establishes that the liability to pay arose in
the requisite manner. Under the insuring clause, what would be needed from the insured’s
point of view was evidence which explained how the liability to pay the sum arose, that
evidence being such as would establish on the balance of probabilities that the liability to pay
the sum met the description required by the insuring clause, in this case as set out in [91](c)
and [91](d) above.
[95] I make the following observations:
(a) There was no dispute between the plaintiff and the defendant as to the terms of the
Contract between the plaintiff and the Commonwealth, or that the Bundaberg was
being worked on under the terms of that Contract.
(b) There was no dispute between the plaintiff and the defendant that the Bundaberg was
in the plaintiff’s care for the purpose of being worked upon by the plaintiff’s
subcontractor in discharge of the plaintiff’s in-service support obligations under the
Contract.
(c) There was no dispute between the plaintiff and the defendant that on 11 August 2014
a fire occurred in that context, destroying the Bundaberg.
(d) Nor was there any dispute between the plaintiff and the defendant that consequent
upon those events, cll 6.8.1.1 and 8.3.1 of the Contract were engaged and the plaintiff
became the subject of the onerous contractual liabilities to the Commonwealth to
which it had not previously been subject, namely:
-- 26 of 36 --
27
(i) the obligation to indemnify the Commonwealth against the loss of the
Bundaberg; and
(ii) the obligation to promptly replace or otherwise make good the loss of the
Bundaberg at its own cost.
(e) Further, the recitals to the Indemnity Settlement Deed note the Commonwealth had
advanced a claim and that only quantum was disputed and the operative terms record
that the defendant insurer agreed to indemnify the plaintiff.
(f) The foregoing were sufficient to establish that the plaintiff had a legal liability to the
Commonwealth, and that the legal liability met the description of “a legal liability as
shiprepairers for loss of any vessel which is in the care, custody or control of the
Assured for the purpose of being worked upon”.
(g) Further the terms of the Indemnity Settlement Deed (by accepting liability under the
insurance claim and disputing only quantum) rendered it unnecessary to prove that the
legal liability to the Commonwealth had resulted from “negligence of the Assured, his
servants, agents or sub-contractors” (although the evidence before me established that
fact anyway).
[96] If the plaintiff’s case had stopped there, the plaintiff would have proved that it had become
liable to pay a $31.5 million sum, but it would not have put the Court in the position to form
the view that the liability to pay the $31.5 million sum arose “by reason of” the legal liability,
the other requisite characteristics of which it had established.
[97] Of course the plaintiff’s case did not stop there. It sought to prove the course of events which
led up to the striking of the compromise, including the investigations which it made, the legal
advice which it obtained, the decision-making process which it took, and the risks to which
it was subject, to justify the proposition that the settlement was reasonable in all the
circumstances.
[98] Whether the settlement was to be so regarded is the subject matter of issue 4, to which I will
next turn, but the present question is whether the plaintiff was entitled to establish its claim
under the insuring clause, having regard to the Indemnity Settlement Deed, by proving that
the settlement was reasonable in all the circumstances.
[99] In my view the question posed by issue 3 must be answered in the following manner:
(a) The plaintiff is entitled to establish the obligation to indemnify in respect of the $31.5
million settlement sum, by whatever manner of evidence establishes that the
relationship between –
(i) the legal liability of the plaintiff to the Commonwealth for the loss of the
Bundaberg; and
(ii) the liability to pay the $31.5 million settlement sum to the Commonwealth,
was one of cause and effect so that the latter could be said to arise “by reason of” the
former.
(b) In the circumstances of this case, proof of the reasonableness of the settlement in the
sense contended for by the plaintiff would establish that the relationship between the
legal liability and the settlement sum was such that the latter arose “by reason of” the
former. It would negate possible factors that would interfere with that conclusion.
(c) Accordingly, the question should be answered in the affirmative.
-- 27 of 36 --
28
[100] I reach the foregoing conclusion by reference to what seems to me to be the proper
construction of the particular insuring clause in this case, bearing in mind the issues about
which there was no dispute. The conclusion also finds support in the case law which has
considered equivalent questions under different forms of liability insurance policies: see
[89](a) above.
Issue 4: Was the Commonwealth Settlement Deed a reasonable settlement of the contractual
liability of the plaintiff to the Commonwealth under the contract in all the circumstances,
having regard to the matters pleaded in paragraphs 18 to 37 of the Statement of Claim,
paragraphs 18 to 37 of the Defence and paragraphs 4 to 18 of the Reply?
[101] Broadly speaking, the referenced paragraphs in the statement of claim pleaded the course of
events which led up to the striking of the compromise, including the investigations which the
plaintiff made, the legal advice which it obtained, the decision-making process which it took,
and the risks to which it was subject, to justify the proposition that the settlement was
reasonable in all the circumstances.
[102] The following observations may be made concerning the matters pleaded in the referenced
paragraphs in the defence and the reply:
(a) The defendant contested the reasonableness of the settlement.
(b) The defendant pleaded that the Bundaberg had a number of defects that would have
required ongoing maintenance and extensive remediation work. The plaintiff accepted
the existence of the defects which would require remediation.
(c) The defendant contended that at the date of its destruction the market value of the
Bundaberg was nil and it would have remained so, had it not been destroyed by fire.
The plaintiff rejected that argument, contending that the fact that there was no second-
hand market did not mean the Bundaberg had no value, and that its value to the
Commonwealth could be measured by the amount which it would cost the
Commonwealth to replace it.
(d) The defendant contended (and the plaintiff agreed) that –
(i) the Commonwealth had in fact covered the gap in availability caused by the loss
of the Bundaberg by borrowing a Cape Class Patrol Boat from the Australian
Border Force between 2015-17 while a new vessel was being constructed and
then leasing a Cape Class Patrol Boat from the National Australia Bank between
2017 to 2020;
(ii) by in or about February 2016, the Commonwealth had decided that it would
replace the Armidale Class Patrol Boat fleet with a new class of Offshore Patrol
Vessels (OPVs) commencing in 2020.
(e) The defendant contended and the plaintiff did not admit that the three year term of
the lease would not or was unlikely to be extended by the Commonwealth. The
plaintiff rejected the relevance of the proposition in any event.
(f) The defendant contended and the plaintiff disputed that the borrowing of the Cape
Class Patrol Boat from the Australian Border Force was at nil cost to the
Commonwealth, despite the fact that the Navy incurred a cost to the Border Force,
because both the Navy and the Border Force were instruments of the Commonwealth.
(g) The defendant contended and the plaintiff disputed that in those premises the
maximum amount of the Commonwealth’s loss was the net present value of the actual
-- 28 of 36 --
29
costs incurred by the Commonwealth to lease a Cape Class Patrol Boat from the
National Australia Bank from 2017 to 2020 to replace the operational capability lost by
the destruction of the Bundaberg at a cost of around $14.9 million.
[103] It is appropriate first to identify the approach which should be taken in assessing whether the
settlement was reasonable.
[104] In Ruckman v Nominal Defendant [2013] QCA 56 at [16], White JA (with whom Fraser JA
and Applegarth J agreed) applied the following summary of the leading High Court authority
which had been made by the judge below (Martin J):
The primary judge considered Unity Insurance Brokers Pty Ltd v Rocco Pezzano Pty Ltd (1998) 192 CLR
603. The issues in that case were different from the present, however, an aspect of the litigation between that
insured and the broker was whether the settlement reached between the insurer and the insured was a
reasonable one. The primary judge summarised the following propositions:
(a) The test of reasonableness is an objective one. (Brennan CJ at [6] and Hayne J at [29])
(b) Evidence of the advice which the insured received to induce it to enter into the settlement is not
proof in itself of the reasonableness of the settlement advised. (Brennan CJ at [6])
(c) Evidence of the receipt of advice is relevant but what will usually be much more important is the
reasoning that supported that advice because that will usually disclose why it was thought reasonable
to compromise the claim. (Hayne J at [129])
(d) The reasonableness of a settlement depends on the circumstances existing at the time, provided the
plaintiff has acted reasonably in discovering the circumstances material to the settlement at that
time. (Brennan CJ at [7])
(e) Reasonableness is not to be judged according to whether material which was obtained later shows
that a different result might have been obtained. (Hayne J at [130])
(f) Consideration will often be required of whether the party maintaining that the settlement was
reasonable had made sufficient inquiries and had sufficient information available to it to warrant
reaching the compromise. (Hayne J at [131])
(g) In making that inquiry attention may need to be given to whether the cost of seeking further
information would outweigh the benefit that it was reasonable to expect may be obtained from doing
so. (Hayne J at [131])
(h) What is a reasonable compromise of the claim will almost always require consideration of the
chances of the parties succeeding in their respective claims or defences and that prediction of likely
outcomes must always be imperfect and imprecise. (Hayne J at [132])
[105] The point made at (e) is also the subject of direct authority in the Court of Appeal. In White
Industries Qld Pty Ltd v Hennessey Glass & Aluminium Systems Pty Ltd [1999] 1 Qd R 210,
Pincus JA observed at 218:
A settlement which is reasonable, in the sense of being entered into in good faith after careful consideration
and on proper advice, may later be proved to have been quite unnecessary, for example because some
evidence comes to light which shows that the claim settled was in truth unsustainable. But such evidence
would not displace the presumption that the settlement was reasonable, which was held to apply in Wong v.
Hutchison (1950) 68 W.N. (N.S.W.) 55 at 58, nor show that the party agreeing to pay under the settlement
acted unreasonably in doing so.10
[106] Against that background of the law, what assessment should be made as to the objective
reasonableness of the settlement?
10 Derrington J also expressed the view at 227 that “Even if it be shown that the loss was actually less in certain respects
than the amounts allowed in the compromise of the claim, that will not necessarily mean that the settlement was not
reasonable.”
-- 29 of 36 --
30
[107] In my view an assessment of the evidence leads plainly to the conclusion that the settlement
was a reasonable one. And my view of the reasonableness of the settlement is such that I find
that the liability to pay the $31.5 million settlement sum to the Commonwealth arose by
reason of the legal liability of the plaintiff to the Commonwealth for the loss of the
Bundaberg.
[108] First, the process by which the options were examined, advice taken, and the settlement
reached was carried out by the plaintiff in good faith. It is common ground that the
Commonwealth Settlement Deed was the culmination of a lengthy process of
communications, negotiations and settlement discussions over a period of approximately 12
months, including the exchange of legal submissions in respect of the parties’ respective
settlement positions. Mr Miller’s evidence was perfectly clear: he regarded the plaintiff’s
role in the negotiations to try to get the best deal (in the form of the lowest overall cost) which
it could and still stay within the bounds of its contractual obligation.
[109] Second, the research which was done under the supervision of Mr Miller into potential
options was considerable. The conclusion that Mr Miller reached that the quantum of the
Commonwealth’s offer was “was the lowest number of any feasible option that [the plaintiff]
had considered” was reasonable and rational, and well supported by evidence which the
plaintiff then had. The plaintiff had made sufficient inquiries and had sufficient information
available to it to warrant forming that view. Indeed it was common ground that the plaintiff
had made reasonable sufficient inquiries and had sufficient information available to it to
determine an appropriate compromise.
[110] Third, it was reasonable for the plaintiff to act on Counsel’s opinion. Although Counsel’s
analysis of the content of the indemnity obligation did not replicate my own, in that Counsel
considered that an analysis of the case law concerning the measure of damages when a vessel
is lost due to actionable wrong was an appropriate means by which to assess the measure of
the plaintiff’s liability to replace or otherwise make good the loss of the Bundaberg, I think
that was a reasonable approach to take. The fact that I have interpreted the promise to
“replace or otherwise make good any loss of the thing at its cost” as a promise promptly to
restore the Commonwealth to the position of having the thing lost, or its equivalent, means
that there is and was a real corollary between the approach which should be taken to the
assessment of the content of the promise to restore and the approach which is to be taken to
the assessment of compensatory damages for actionable wrong. Both my analysis and that
of Counsel reject the conclusion that there should be any adjustment for betterment.
[111] Fourth, the analysis contained in Counsel’s opinion recorded at [66] above was objectively a
reasonable approach to take and it was reasonable for the plaintiff to act on it. In my view,
by the time of settlement, there was not a significant risk that the Commonwealth would
obtain a judgment based on the cost of replacement with a new Armidale Class Patrol Boat,
if it was forced to litigate its claim for indemnity. On the other hand, the asset value measures
for which the plaintiff had contended were flawed, for the reasons which the Commonwealth
argued and as Counsel concluded. There was a strong likelihood that any judgment would
be based on the cost of replacement with a Cape Class Patrol Boat, modified so as to become
functionally equivalent to the Armidale Class Patrol Boat. At the time of settlement, all the
evidence pointed to a liability well above $31.5 million – because that figure was only the bare
cost of the replacement vessel – suggesting a lack of merit in further and more detailed
examination of the precise amount of the judgment which the Commonwealth would obtain
at a trial.
-- 30 of 36 --
31
[112] Fifth, it was common ground in the expert opinion evidence adduced by both the plaintiff
and the defendant at the trial before me, that the cost of replacement with a Cape Class Patrol
Boat, when evaluated with an assessment of the cost of modification so as to become
functionally equivalent to the Armidale Class Patrol Boat, would have been a figure well
above $31.5 million. When one factors in the fact that any judgment obtained by the
Commonwealth for such an amount would be inclusive of interests and costs, that conclusion
alone provides further objective support for the reasonableness of the settlement at the bare
cost of the replacement vessel without the requisite upgrades. It is not necessary further to
delve into the differences between the expert opinions.
[113] Sixth, I reject the defendant’s argument concerning the impact of the fact that the Bundaberg
had a number of defects that would have required ongoing maintenance and extensive
remediation work. First, the evidence at the time of settlement suggested that the difference
between a reasonable assessment of the cost of a Cape Class Patrol Boat, modified so as to
become functionally equivalent to the Armidale Class Patrol Boat, was so far above the $31.5
million settlement sum as to make it reasonable to ignore the issue. In this regard, I have
already indicated that I accept Mr Miller’s assessment that the likely amount which would
have been spent on the Bundaberg for the remediation program was $2.64 million. Second,
the plaintiff’s own thinking about not raising that issue was reasonable, namely that raising
it might have caused the opportunity to settle at the base cost to be lost. Third, my
assessment of the law (and that of Counsel in the opinion which the plaintiff obtained) is that
the argument that an allowance for betterment (or costs savings consequent upon notionally
receiving a newer non-defective boat) should be deducted was flawed.
[114] Seventh, I reject the defendant’s argument against the inclusion in any assessment of
notional liability to the Commonwealth of the cost to the Commonwealth of securing
replacement vessels during the period of construction of the replacement vessels. The
defendant’s argument was that monies which the Royal Australian Navy paid to the
Australian Border Force could not be regarded as part of the cost of replacement, because
they were entirely internal to the Commonwealth. But the Commonwealth would
undoubtedly be entitled to assert that the loss of its patrol boat for the period of construction
of a replacement was a real loss to it for which it was entitled to be compensated: McGregor
on Damages (19th ed., 2014) at 35-042 to 35-059. Had there been no settlement, and the
Commonwealth had been forced to sue for damages for breach of the obligation promptly to
replace or otherwise make good the loss of the Bundaberg, the Commonwealth would have
been entitled to a substantial component of damages reflecting the loss of use. Using the hire
charges which the Border Force charged the Navy may have been a sufficient basis for
measuring that loss, giving a claim for of the order of $3 million over 2 years. Alternatively,
the assessment may have been performed by reference to an interest on the capital value of
the replacement vessel at the time of loss. It is unnecessary to be precise in working out how
much that would have been: this factor is another reason why the settlement at $31.5 million
(which was a bare cost figure and paid no regard to loss of use damages) was a reasonable
settlement.
[115] Eighth, I also reject the defendant’s argument that the evidence concerning the leasing
transaction and the commencement of the replacement of the Armidale Class Patrol Boat
fleet with a new class of vessels commencing in 2020, meant that any liability which the
plaintiff had to the Commonwealth was capped at the net present value to the
Commonwealth of the lease costs for the 3 year period of the lease. I make the following
observations:
-- 31 of 36 --
32
(a) The evidence before me suggested the details of the lease arrangements and the
proposed replacements for the Armidale Class Patrol Boats were as follows:
(i) The Commonwealth financed the acquisition of the two Cape Class Patrol Boats
by way of a Bareboat Charter Agreement through the National Australia Bank,
which it entered into on 1 December 2015.
(ii) The Bareboat Charter Agreement was for a 3 year period (2017-2020) following
delivery of each vessel, with a 2 year option (2021-2022). At the end of the
period, the Commonwealth will not own the vessels and does not have any right
to acquire the vessels under either the Master Bareboat Charter Agreement or
the Shipbuilding Contract.
(iii) The charter of the first vessel commenced on 27 April 2017 and the charter of
the second vessel commenced on 31 May 2017.
(iv) In 2017, the Naval Shipbuilding Plan, issued by the Department of Defence,
indicated that the Offshore Patrol Vessels will be constructed from 2018. They
will progressively replace the Armidale Class Patrol Boats. Known timelines
suggest the first of the vessels will likely enter service in the early 2020s, with the
last entering into service by 2030.
(b) Even if the plaintiff had known at the time of settlement that the Commonwealth had
finally decided that it would replace the Armidale Class Patrol Boat fleet with a new
class of vessels commencing in 2020 and that it definitely would not renew the lease of
the Cape Class vessels, that fact would have been legally irrelevant11 to the proper
measure of the plaintiff’s contractual obligation to the Commonwealth, or of the
plaintiff’s liability to the Commonwealth for damages for failure to perform its
obligation promptly to replace or otherwise make good the loss of the Bundaberg. The
obligation had to be performed promptly after 11 August 2014. The defendant argued
that the Commonwealth must be regarded as having mitigated the loss which it
suffered consequent upon the failure of the plaintiff promptly to replace or otherwise
make good the loss of the Bundaberg. I reject that analysis. The pecuniary value of
performance of that obligation had to be measured as at that the date it had to be
performed, if the Commonwealth was to get the benefit of its bargain. What the
Commonwealth did subsequent to receipt of the proper discharge of the obligation
would be a matter for the Commonwealth and could have no bearing on its entitlement
or the liability of the plaintiff under the Contract: cf Clark v Macourt (2013) 253 CLR 1
at [109] – [110] per Keane J.
(c) I also think that there are at least two other conceptual flaws in the defendant’s
argument. The logic seems to be this: (1) the contractual obligation was to replace the
Bundaberg’s functionality for the period in which it would have been available; (2) it
may be accepted that the contractual contemplation was that the Bundaberg’s
functionality would have been expected to be available until 2022, and, at the option of
the Commonwealth, until 2027; (3) however the Bundaberg’s functionality has in fact
been replaced by a combination of a vessel loaned from the Border Force and by a 3
11 This conclusion is not gainsaid by the fact that Mr Lantz, at least, would have regarded such a fact to be commercially
relevant. We are here concerned with measuring the value of legal rights, not with arguments which might have been
capable of being deployed in a commercial negotiation. That the point made no difference to the legal assessment is
consistent with the evidence before me which demonstrates that such information would not have altered Mr Jackman
SC’s opinion if he had known it at the time.
-- 32 of 36 --
33
year lease which is unlikely to be renewed; (4) therefore all that is required is to
measure the cost of the 3 year lease. In the first place, I have already explained that
one cannot ignore the fact that the replacement obligation required the replacement of
the lost Bundaberg with a replacement which would be owned by the Commonwealth:
see [82] above. But more importantly, the identification of the way the Commonwealth
has replaced the Bundaberg’s functionality over the contractually contemplated period
is too limited. If part of the Bundaberg’s functionality is being replaced over the period
contemplated by the Contract by the functionality made available by bringing forward
the construction of Offshore Patrol Vessels so that one or more of those vessels does
the job which would have been done by the Bundaberg during the period in which the
Bundaberg should have been available, then that must come at a cost to the
Commonwealth, yet the defendant’s theory pays no regard to that cost. If, contrary to
my view of the law, the defendant’s “mitigation” hypothesis should have been brought
into account, in my view the onus of demonstrating the validity of the hypothesis would
have been on the defendant, and because the hypothesis does not account for the
complete means by which the Bundaberg’s functionality will be replaced, the theory is
incomplete and I am not persuaded by it.
(d) And even if I am wrong about the points made in the previous two subparagraphs, the
reasonableness of the settlement is not to be judged according to material which was
obtained later which shows that a different result might have been obtained: see [104]
and [105] above. I observe:
(i) The evidence of the witnesses before me did not justify a finding that at the time
of the settlement the plaintiff knew that the lease would not or would probably
not be renewed, because the Commonwealth’s plans in relation to the Offshore
Patrol Vessels were not sufficiently clear to the plaintiff. Certainly that was Mr
Miller’s position, and he was the plaintiff’s officer who its decision makers relied
on for factual and costing detail. In any event, his evidence was the most
persuasive of the witnesses from whom I heard. He said he never had the
understanding that the Commonwealth would have a 3 year lease, and otherwise
not seek to replace the Bundaberg.
(ii) The defendant sought to rely on – as an admission justifying such a finding – the
statement made in the plaintiff’s solicitors instructions to Mr Jackman SC in
November 2017 (when seeking a follow up opinion). Their instructions were
that a summary which they recorded of the defendant’s allegations was “largely
accurate … and mostly known to [the plaintiff] (without the minute details) at
the time it accepted the settlement offer – However [the plaintiff] did not ever
consider this to be relevant (and still does not consider it to be relevant)”.
(iii) But I do not regard the fact and wording of those instructions to be a secure basis
to make such a finding: the summary of the defendant’s case was expressed in
the present tense and incapable of being known at the time of settlement; there
is too much imprecision in the alleged admitting words; and I do not know how
precise the solicitors were in formulating the instruction. I accept Mr Miller’s
position and regard it to be demonstrating the reasonable extent of the plaintiff’s
knowledge at the time of settlement.
(e) In any event, even now it is not clear that there definitely will not be a renewal of the
lease. The lease provides for one renewal and a further renewal could be negotiated.
Further, the replacement vessels will be commissioned over a period of years, so
-- 33 of 36 --
34
presumably there will continue to be a need for Armidale Class Patrol Boats (or their
replacements) for some time.
[116] For the foregoing reasons, I conclude that the settlement was a reasonable one and the
question posed by issue 4 should be answered in the affirmative. My finding as to the
reasonableness of the settlement also justifies my conclusion that the liability to pay the $31.5
million settlement sum to the Commonwealth arose by reason of the legal liability of the
plaintiff to the Commonwealth for the loss of the Bundaberg.
Issue 5: In assessing the reasonableness of the Commonwealth Settlement Deed, in respect
of the contractual liability of the plaintiff to the Commonwealth under the contract:
Issue 5(a): Was the measure of the liability the cost to the Commonwealth to purchase a Cape Class
Patrol Boat as at 11 August 2014?
[117] I have explained my conclusion that, on the proper construction of cl 8.3.1, on 11 August
2014 the plaintiff became obliged, promptly and at its own cost, to restore the
Commonwealth to the position of having the Bundaberg, or its equivalent. The plaintiff
could have fulfilled its obligation by –
(a) promptly providing the Commonwealth with ownership of a substitute Armidale Class
Patrol Boat in the place of the Bundaberg; or
(b) promptly providing the Commonwealth with ownership of some other vessel with
functionality and characteristics which were the equivalent of the Bundaberg; or
(c) in some other equivalent way promptly making recompense to the Commonwealth for
the loss of the Bundaberg.
[118] The prompt payment of money was an obvious way to make recompense to the
Commonwealth for the loss of the Bundaberg. In order for that way to be equivalent to
prompt restoration of the Bundaberg, the requisite amount of money would have to be at
least the same as the cost as at 11 August 2014 of acquisition of a Cape Class Patrol Boat and
of making such improvements to it as would make it equivalent in functionality to an
Armidale Class Patrol Boat. It would also have to include an amount representing general
damages for loss of the use of a Patrol Boat equivalent to the Bundaberg, for the period it
would take to have a replacement built.
Issue 5(b): If “yes” to 5(a), should that cost be reduced by reference to betterment, and if so, to
what extent?
[119] No, for the reasons discussed at [79] to [81], [110] and [115](b).
Issue 5(c): In the alternative to 5(a), was the measure of the liability the market value of HMAS
Bundaberg as at 11 August 2014?
[120] There was no secondary market for Armidale Class Patrol Boats. Any attempt to reach a
market value unless by reference to replacement cost of an equivalent vessel, would
inevitably under-compensate the Commonwealth. This question must be answered in the
negative.
Issue 5(d): In the alternative to 5(a), was the measure of the liability the depreciated value of
HMAS Bundaberg as at 11 August 2014?
[121] No, the provision of depreciated value would not have been sufficient to discharge the
obligation owed under the Contract. That measure would inevitably under-compensate the
Commonwealth.
-- 34 of 36 --
35
Issue 5(e): In the alternative to 5(a), was the measure of the liability that pleaded in paragraph
28(d)(iv)(C) of the defence?
[122] The measure pleaded in the referenced paragraph of the defence was “the net present value
of part of the actual costs incurred by the Commonwealth to charter a Cape Class vessel from
the National Australia Bank from 2017 to 2020, but only insofar as those costs were directly
attributable to replacing operational availability lost by the destruction of HMAS
Bundaberg”.
[123] The question should be answered in the negative for the reasons discussed at [115] above.
Issue 5(f): With respect to each of the above alternatives, was the measure of the liability to be
determined by taking into account any costs savings to the Commonwealth of the kind pleaded in
paragraph 22U to 22W of the defence?
[124] The referenced paragraphs of the defence provide as follows:
22U. By in or about November 2015, and before the entry into the Commonwealth Settlement Deed, the
Commonwealth had assumed the financial obligation for the costs of ongoing maintenance and
remediation works in respect of the remaining Armidale Class Patrol Boats.
22V. If HMAS Bundaberg had not been destroyed, the Commonwealth would have assumed the financial
obligation for the cost of the ongoing maintenance and remediation works for HMAS Bundaberg.
22W. The ongoing maintenance and remediation cost to the Commonwealth over the remaining service
life of HMAS Bundaberg if it had not been destroyed would have been $17.58 million, or
alternatively, a lesser sum of several million dollars. Particulars will be supplied after disclosure and
non-party disclosure.
[125] No, the incurrence of costs savings is to be treated in the same way as betterment issues and
for the same reasons.
Issue 6: If “no” to Issue 3, is the defendant’s liability to the plaintiff under the Insurance
Policies, as amended by the Indemnity Settlement Deed, to be calculated based on the
defendant’s share of the likely final judgment had the contractual liability of the plaintiff to
the Commonwealth under the contract been determined at trial based on replacement of
HMAS Bundaberg as pleaded in paragraph 48 of the statement of claim (capped at the
defendant’s share of the $31.5 million settlement sum)?
[126] This question is unnecessary to answer because Issue 3 was answered in the affirmative.
Issue 7: If yes to Issues 3 and 4, or alternatively if yes to Issue 6, what sum is payable by the
defendant to the plaintiff in respect of the defendant’s liability to the plaintiff under the
Insurance Policies, as amended by the Indemnity Settlement Deed?
[127] The sum to be paid to the plaintiff is $15,852,453.75 (being the agreed calculation of the
defendant’s adjusted share of a $31.5 million sum paid by the plaintiff to the
Commonwealth).
Issue 8: What sum, if any, is payable by the defendant to the plaintiff by way of interest on
account of the defendant paying the $31.5 million settlement sum to the Commonwealth?
[128] The plaintiff has claimed interest pursuant to s 57 of the Insurance Contracts Act 1984 (Cth)
in respect of its claim for $15,852,453.75. That section obliges an insurer in the position of
the defendant to pay interest on the amount of its liability under a contract of insurance at a
prescribed rate for the period commencing on the date from which it was unreasonable for
the defendant to have withheld payment of the amount.
-- 35 of 36 --
36
[129] The parties provided me with a spreadsheet which would give rise to an agreed calculation,
once I made a finding as to the date from which it was unreasonable for the defendant to
withhold payment.
[130] The plaintiff submits, and I agree, that the dates on which it was unreasonable for the
defendant to withhold payment were the dates on which the payments were made by the
plaintiff. Whilst an insurer is entitled to a reasonable time to conclude its examination of the
issues relating to the claim and of the amount which it should pay on the claim, such a time
had expired by the time that the plaintiff determined to enter into the Commonwealth
Settlement Deed. The defendant’s reasons for withholding payment at that time were
reasons the validity of which I have rejected. No submission that I should find some other
dates as the dates appropriate for the calculation was advanced by the defendant.
[131] Accordingly, the two payments being made on 23 June 2016 and 25 July 2016, the application
of the spreadsheet gives rise to the conclusions that the interest owed to the date of this
judgment is $2,027,669.99 and interest will continue to accrue at a daily rate of $2,280.15
until payment.
The orders which should be made
[132] I would make the following orders:
1. It is declared that the defendant is obliged to indemnify the plaintiff for the amount of
the settlement sum which the plaintiff became liable to pay the Commonwealth of
Australia under the Commonwealth Settlement Deed, pursuant to the terms of the
Insurance Policies and the Indemnity Settlement Deed.
2. The defendant must pay the plaintiff the sum of $15,852,453.75 as the amount of its
liability to indemnify the plaintiff pursuant to the terms of the Insurance Policies and
the Indemnity Settlement Deed, as declared in order 1.
3. Pursuant to s 57 of the Insurance Contracts Act 1984 (Cth), the defendant must pay the
plaintiff interest on the amount the subject of order 2, in the sum of $2,027,669.99
calculated to the date of judgment, and thereafter at the rate of $2,280.15 per day until
the day on which payment is made.
4. The parties will be heard on the question of costs.
-- 36 of 36 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2018/303