Cragcorp Pty Ltd v Qld Civil Engineering Pty Ltd & Ors [2018] QSC 203
SUPREME COURT OF QUEENSLAND
CITATION: Cragcorp Pty Ltd v Qld Civil Engineering Pty Ltd & Ors
[2018] QSC 203
PARTIES: CRAGCORP PTY LTD ACN 077 429 960 t/a
QUEENSLAND BRIDGE AND CIVIL
(Applicant)
v
QLD CIVIL ENGINEERING PTY LTD ACN 145 104
605
(First Respondent)
AND
BRYDGET BARKER-HUDSON ADJUDICATOR No.
J1087549
(Second Respondent)
AND
CHERIDEN FARTHING AS THE ADJUDICATION
REGISTRAR AND THE ADJUDICATION REGISTRY:
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(Third Respondent)
FILE NO/S: BS No 1854 of 2018
DIVISION: Trial
PROCEEDING: Application
ORIGINATING
COURT:
Supreme Court at Brisbane
DELIVERED ON: 12 October 2018
DELIVERED AT: Brisbane
HEARING DATE: 13 June 2018
JUDGE: Lyons SJA
ORDER: 1. I will hear from the parties as to the form of the
orders and as to costs.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – OTHER MATTERS – where the
applicant seeks a declaration that the adjudication application
of the first respondent to the third respondent is void, either in
whole or in part - where the applicant seeks a declaration that
the adjudication decision of the second respondent pursuant to
-- 1 of 23 --
2
the Building and Construction Industry Payments Act 2004
(Qld) is void, either in whole or in part – where the applicant
seeks a declaration that the payment claim made by the first
respondent to the applicant is void or is of no effect for the
operation of the Building and Construction Industry Payments
Act 2004 (Qld) – where the second respondent was engaged by
the applicant as a subcontractor for a construction project –
where the second respondent lodged a payment claim that was
subsequently disputed by the applicant – where the applicant
argues that the Adjudication Decision is affected by
jurisdictional error – whether the decision was affected by
jurisdictional error – whether the adjudicator failed to perform
the statutory task of valuation – whether the adjudicator denied
the applicant natural justice and failed to give proper written
reasons
Building and Construction Industry Payments Act 2004 (Qld)
Civil Proceedings Act 2011 (Qld)
Judicial Review Act 1991 (Qld)
Annie Street JV Pty Ltd v MCC Pty Ltd & Ors [2016] QSC
268
Ball Construction Pty Ltd v Conart Pty Ltd [2014] QSC 124
BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty
Ltd & Ors [2012] QSC 346
BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty
Ltd & Ors [2013] QCA 394
City of Ryde v AMFM Constructions Pty Ltd & Anor [2011]
NSWSC 1469
G W Enterprises Pty Ltd v Xentex Industries Pty Ltd & Ors
[2006] QSC 399
John Holland Pty Ltd v TAC Pacific Pty Ltd & Ors [2010] 1
Qd R 302
Northbuild Construction Pty Ltd v Central Interior Linings
Pty Ltd [2012] 1 Qd R 525
Ostwald Bros Pty Ltd v Jaylon Pacific Pty Ltd & Ors [2016]
QSC 240
Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty
Ltd [2018] HCA 4
South East Civil & Drainage Contractors P/L v AMGW P/L
& Ors [2013] QSC 45
-- 2 of 23 --
3
Southern Han Breakfast Point Pty Ltd (In liq) v Lewence
Construction Pty Ltd (2016) 91 ALJR 233
Thiess Pty Ltd and John Holland Pty Ltd v Civil Works
Australia Pty Ltd & Ors [2011] 2 Qd R 276
Wiggins Island Coal Export Terminal Pty Ltd v
Monadelphous Engineering Pty Ltd & Ors [2015] QSC 307
COUNSEL: B E Codd for the Applicant
M H Hindman QC with H Clift for the First Respondent
SOLICITORS: Batch Mewing Lawyers for the Applicant
HWL Ebsworth for the First Respondent
The dispute
[1] The Brisbane City Council engaged the applicant (Cragcorp) as the head contractor of a
construction project. Cragcorp engaged the first respondent, Qld Civil Engineering Pty
Ltd (QCE), as a subcontractor in relation to those works. This application relates to a
dispute about an Adjudication Decision under the Building and Construction Industry
Payments Act 2004 (Qld) (BCIP Act) which required Cragcorp to pay $205,218.53 to
QCE. Cragcorp argues that the Adjudication Decision should be declared void or
quashed.
This application
[2] By application filed on 20 February 2018, Cragcorp seeks the following declarations:
(a) The adjudication application of the first respondent made to the third
respondent (number QBCC 334008) on or about 19 December 2017 (the
Adjudication Application) is void, in whole or in part;
(b) The Adjudication Decision of the second respondent purportedly
pursuant to the BCIP Act given in respect to the Adjudication Application
on 6 February 2018 (the Adjudication Decision) is void, in whole or in
part;
(c) The payment claim made by the first respondent to the applicant on or
about 30 November 2017 is void (the Payment Claim) or of no effect for
the operation of the BCIP Act.1
[3] The application for the declaration in (c) is no longer maintained by the applicant and
should be dismissed. In relation to the relief claimed in (a), I do not consider that there is
any basis for a declaration that the adjudication application itself, as opposed to the
Decision, should be declared void. That aspect of the application should therefore also be
dismissed.
[4] Accordingly, the only aspect of the application to be considered is whether the
Adjudication Decision is void in whole or in part. The applicant relies on section 10 of
the Civil Proceedings Act 2011 (Qld) as the basis for their application. In the alternative,
1 Court File Document 1.
-- 3 of 23 --
4
Cragcorp seeks an order pursuant to s 41 of the Judicial Review Act 1991 (Qld) quashing
the Adjudication Decision.2
[5] The second and third respondents were not actively involved in the proceedings and in
accordance with the usual practice, will abide the order of the Court.
[6] The real dispute between the parties relates to whether the Adjudication Decision should
be declared void for jurisdictional error.
Background
[7] Cragcorp was engaged to replace the bridge over Wolston Creek and it engaged QCE as
a subcontractor to construct a sewer main and make modifications to a water main across
the creek.3 QCE signed a subcontract with Cragcorp on 5 July 2017 and Cragcorp signed
on 13 July 2017. The subcontract provided that that it was a combination Lump
sum/Schedule of Rates contract with a subcontract price of $729,080.25 (plus GST).4
[8] A letter of commencement was issued by Cragcorp on 17 July 2017 and works
commenced two weeks later on 31 July 2017.5
[9] The current issues arose when QCE lodged a payment claim of $250,649.69 (including
GST) dated and served on 30 November 2017 under the BCIP Act.
[10] On 5 December 2017, Cragcorp served QCE with a payment schedule that indicated the
scheduled amount was $49,016.01 (including GST).6 Cragcorp disputed amounts claimed
in respect of some variations and had set off liquidated damages of $36,454.01 and
deducted retentions of $36,454.01.
[11] QCE lodged an application for adjudication on 19 December 2017.7 This was then
referred by the third respondent to the second respondent for determination under the
BCIP Act.8
[12] On 19 December 2017, QCE provided its Adjudication Application which contained a
calculation that deducted the retention amount of $36,454.01 and indicated that the
amount in issue was $212,297.85.
[13] On 22 January 2018 Cragcorp provided its adjudication response and argued for the first
time that QCE was not entitled to the progress payment claimed despite the fact that the
Payment Schedule detailed the scheduled amount as $49,016.01.
[14] On 6 February 2018, the second respondent made an Adjudication Decision under the
BCIP Act which required that Cragcorp pay QCE the amount of $205,218.53 (including
GST).9
2 Court File Document 1.
3 Court File Document 18 at [12] and [13]; Court File Document 13 at [5] – [6].
4 Court File Document 13 at [7]; Court File Document 18 at [13]; Court File Document 3, Exhibit DL-3 at 65.
5 Court File Document 3, Exhibit DL-2 at 25.
6 Court File Document 13 at [10].
7 Court File Document 13 at [8] – [11]; Court File Document 18 at [29].
8 Court File Document 13 at [11].
9 Court File Document 18 at [1] and [31].
-- 4 of 23 --
5
[15] Cragcorp seeks to have that Decision declared void, of no effect or quashed, and argues
that three aspects of the Adjudication Decision are affected by jurisdictional error;
namely, the decisions made with respect to Variation 1, Variation 2 and the decision in
relation to liquidated damages.
The BCIP Act regime
[16] The BCIP Act provides a legislative scheme for the resolution of payment claims for
construction work, pursuant to a construction contract.10 The scheme has been variously
described as “pay now, argue later” and as a “simple expeditious and robust mechanism
for ensuring the payment of progress claims.”11 The process is triggered by the claimant
serving a ‘payment claim’ upon the respondent. The respondent can resist this claim by
serving on the claimant a ‘payment schedule’ which must contain: identification of the
relevant payment claim; the amount the respondent proposes to pay, if any, and the
reasons for refusing to pay the remaining amount.12
[17] If the respondent fails to pay the amount in the claim, the claimant can make an
‘adjudication application’ under the BCIP Act to the registrar who can then appoint an
adjudicator to make a determination on the application.13
[18] It is then the adjudicator’s task to value the payment claim, in accordance with the
relevant legislative provisions of the BCIP Act.14 There is no appeal from an adjudicator’s
decision however a decision can be declared void for jurisdictional error.15
[19] As the High Court made clear in Southern Han Breakfast Point Pty Ltd (In liq) v Lewence
Construction Pty Ltd,16 there is a significant limitation in the scheme created by the
various BCIP Act regimes. That is, that the schemes provide a statutory mechanism for
securing payment for an amount claimed to be payable pursuant to an obligation to pay
for work under a construction contract. The High Court made clear that the scheme is not
a scheme which provides security for payment of an amount claimed for damages for
breach of a construction contract nor is it concerned to provide security for payment of
an amount which might be claimed as an alternative to damages by way of restitution.17
[20] Cragcorp argues that this is, in reality, an impermissible claim for restitution and seeks
orders for costs as well as orders:
(i) that the amount paid in to Court of $169,875.71 be released; and
(ii) the amount of $49,580.03 paid to QCE be repaid.
The factual issues giving rise to the dispute
10 Court File Document 13 at [13]; BCIP Act ss 5 and 10.
11 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd & Ors [2015] 1 Qd R 228 at [67] and [68].
12 Court File Document 13 at [14]; BCIP Act s 18.
13 Court File Document 13 at [15]; BCIP Act ss 21, 12 – 14, 25 and 26.
14 BCIP Act ss 12, 13, 14, 25, 26 and 27.
15 Chase Oyster Bay Pty Ltd v Hamo Industries Pty Ltd (2010) 272 ALR 750 at 752 – 755; Northbuild
Construction Pty Ltd v Central Interior Linings Pty Ltd [2012] 1 Qd R 525.
16 (2016) 91 ALJR 233.
17 Ibid at [66].
-- 5 of 23 --
6
[21] QCE commenced work on 31 July 2017. Rock was encountered shortly thereafter at about
4 metres from the surface. The geotechnical information provided by Cragcorp indicated
that rock was at a depth of 10 metres. The documents provided to the adjudicator in
support of the application indicated that on 3 August 2017 QCE submitted 2 requests to
Cragcorp. They were referred to as variation requests in relation to latent conditions in
the accompanying email as follows “VO 001-Latent Condition, Northern Bore pit-
Identified 1/8/2017” and “VO 002 Latent Condition, Additional bore length-Identified
1/8/2017.”18
[22] Each request stated that it was made “In accordance with Part B- Clause 30 (C) of the
A017 Subcontract agreement” and was a “variation request for the additional time and
cost expected to be incurred.”19 Each request gave an estimated value of additional works,
which in relation to VO-001 was $37,373 ex GST with an extension of time request of 4
days and $19,478.60 ex GST with no request for an extension of time in relation to VO-
002.20
[23] Clause 30 in Part B of the Subcontract provided:
“Clause 30 – Notices:
Any notice to be given under or in connection to this Subcontract
Agreement shall be in writing and shall be delivered by hand, post or
facsimile or email at the address for the contact person nominated in Part
A – Item 1 and for payment claims, in accordance with Clause 11.
The subcontractor shall, within three (3) business days after the first day
upon which the Subcontractor could reasonably been aware, provide
written notification to the Contractor of:
a. a breach of Contract;
b. an act, omission, direction or approval by the Contractor;
c. an event or circumstance that has occurred
where it may give rise to a claim in respect of or arising from any or all of
the above.
This notice shall provide sufficient details to identify it as a notification
of claim and particulars of the following:
a. the breach, act, omission, direction, approval, event or
circumstance in which the notice relates;
b. the contractual reference and basis for the claim; and
c. the likely quantum of the claim.
18 Court File Document 17, Exhibit DL-1 at 4-5.
19 Court File Document 17, Exhibit DL-1 at 4-5.
20 Court File Document 17, Exhibit DL-1 at 2 – 5.
-- 6 of 23 --
7
The Contractor shall not be liable upon any claim by the Subcontractor in
respect to any of the above items unless the provisions of this Clause are
met.”21
[24] The contract did not contain a provision in relation to latent conditions. Both requests
mistakenly referred to “AS4000-1997, Clause 25 Latent Condition” which was not in fact
part of the subcontract.
[25] Clause 7 stated that the subcontractor was deemed to have inspected the site including
“physical indications of above and below surface conditions prior to commencing work.”
Part C of the Subcontract also contained Special Conditions and clause 3.2 provided:
“The Subcontractor is deemed to have inspected the site and all relevant
contract documents and has made due allowances in its rates/price for all
reasonable site conditions, site obstacles, accesses and obstructions which
may affect any aspect of the Works.”
[26] Clause 13 related to Variations and was in the following terms:
“The Contractor may, at any time prior to completion of the Works, vary
the scope or the extent of the Subcontract Works by written direction to
the Subcontractor. The Subcontractor shall be bound to execute such
variation where it is within the general scope of the Works.
If the Subcontractor believes that they are entitled to a variation, they shall
notify the Contractor pursuant to Part B – Clause 30 of this agreement. To
remove any doubt, the Subcontractor shall not vary the Works unless it is
approved in writing by the Contractor.
The price for the variation must be agreed wherever possible prior to the
execution of the variation. In the absence of agreement, the price for a
variation must be a reasonable price determined by the Contractor. The
price for any variation shall be added to or deducted from the Subcontract
Sum.”
[27] The submissions of Counsel for QCE sets out the relevant background correspondence in
relation to the additional works. I shall adopt this as a convenient summary of the facts in
relation to the request for and notice of those additional works. On 28 August 2017, in
response to QCE’s letter of 3 August 2017 requesting the variations, Cragcorp sent an
email in the following terms:
“Just checking how you are progressing with finalising the latent
condition relating to the rock excavation for the north pit and switching
of pits from jacking to receiving and vice versa for your VO#001. Would
you be able to supply this in the next day or so?”22
[28] The following day another email was sent to QCE as follows:
21 Court File Document 3, Exhibit DL-3 at Clause 30 of the Subcontract Agreement.
22 Court File Document 17, Exhibit DL-1 at 20.
-- 7 of 23 --
8
“You mentioned yesterday that you have not received any confirmation
from QBC for the rock excavation and the switching of the jacking and
receiving pits as of yet. Please refer the below email from Brett
confirming the direction to proceed with these works”.23
[29] The email referred to was an email to QCE dated 8 August 201724 which directed QCE
to proceed with the variations sought. That email gave a direction to proceed with (1) the
“Change to Locations of Entry and Receiving Pits” and (2) “Effects to Excavation of
Northern Side Entry Pit Due to Underlying Rock Layer” and concluded:
“The above is deemed to be the Contractor’s Direction for the
Subcontractor to proceed with contract works on site. Once Equipment
and Labour hours have been receive (sic) I will organise a meeting with
Dave Bloomfield to finalise the quantum. This will then formulate the
Contractors assessment for Item 2-Additional Works to Stabilise the
Excavation of the submitted VO-001. In regards Item 1 of VO-001 I will
provide my formal response by COB Wednesday.”25
[30] On 29 August 2017, David Bloomfield (QCE) emailed Reece Doyle (Cragcorp) with
documentation regarding variation 1.
[31] On 29 September 2017, Darren Hausknecht (QCE) emailed Doyle (Cragcorp) enquiring
as to what was happening with variation 1.
[32] On 31 October 2017, Hausknecht (QCE) wrote to Brett Lukritz (Cragcorp) to provide
documentation, including a variation and documentation to support the valuation
regarding variation 2. He wrote: “In accordance with Part B- Clause 30 (C) of the A017
Subcontract agreement, and following our original notice issued 3 August 2017 and
QBC’s acceptance of the latent condition on 29 August 2017, QCE submit to QBC the
variation for the additional time and cost incurred to overcome the latent condition.”26
(my emphasis). The letter then provided details of the claim, which were that:
(a) Rock was encountered at approximately 4 metres from surface
level at the northern bore pit. Geotechnical information had
identified that the rock layer was about 10 metres from surface
level;
(b) Direction was provided to relocate the pit to minimise excavation
and expedite works. Relocation and stabilisation were claimed
under variation 1; and
(c) The construction process was materially different from what was
planned prior to commencement.
[33] On 6 November 2017, Doyle (Cragcorp) wrote to Hausknecht (QCE) in relation to
variation 1 as follows:
23 Court File Document 17, Exhibit DL-1 at 22.
24 Court File Document 17, Exhibit DL-1 at 24.
25 Court File Document 17, Exhibit DL-1 at 24.
26 Court File Document 17, Exhibit DL-1 at 130.
-- 8 of 23 --
9
“In accordance with Part B Clause 13 of the Standard Subcontract of the
Subcontract Agreement, the Contractor has assessed Variation 001
(VOR001 – Latent Condition – North Bore Pits) and herewith approves
the value of $14,616.00… Please find attached the valuation breakdown
for the above mentioned Latent Condition Variation.”27
The cost of the variation was based on the value under the contract of an Enveloper bore.
[34] On 14 November 2017, Lukritz (Cragcorp) wrote to Hausknecht (QCE) regarding
extension of time (EOT) requests. In a letter regarding EOT#01 he wrote, “Pursuant to
clause 14 of Subcontract Agreement 195-005, the Contractor herewith provides an
extension of time due to the advised latent condition for rock encountered in the northern
bore pit.”28 In another letter, he wrote that EOT#03 was provided “as a consequence of
the delay to works due to rock encountered in the SRM Enveloper bore.”29
[35] The parties exchanged further correspondence which resulted, on 12 December 2017, in
two letters from Cragcorp to QCE. The first regarding a revision to the valuation of
variation 1 ($15,789.15 excluding GST); the second regarding a valuation of variation 2
($38,198.21 excluding GST).30
Adjudication Application Submissions
[36] In its Adjudication Application, QCE contended they had demonstrated that they had
performed the variation work and was entitled to be paid for that work under the
subcontract. It summarised the matters in dispute in relation to the variations required and
set out the terms of the contract relied upon, particularly clause 13. Reliance was placed
on the emails and letters referred to above. QCE then argued that Cragcorp had approved
the variations and paid amounts in relation to Variation 1 and 2 ‘on account’ but that the
amount payable was in issue.
[37] At 2.1 of the Adjudication Application Submissions, QCE summarised the matters in
dispute, indicating that the total progress payment payable was $250,646.69. However,
they also indicated that the amount claimed by the Adjudication Application was $212,
297.85. The submissions noted that Cragcorp had delivered a revised assessment of
$15,789.15 (ex GST) in relation to Variation 1 and $38,198.21 in relation to Variation 2
in correspondence, which was 7 days after the Payment Schedule was lodged.
[38] It was also submitted that, pursuant to s 24(4) of the Act, the Adjudication Response could
not include any reasons for withholding payment unless they had been included in the
Payment Schedule when served on QCE. It was argued therefore that the new reasons set
out in the letter delivered to QCE on 12 December 2017 could not be considered by the
Adjudicator. The various terms of the Contract relied upon were outlined in the
Adjudication Application.
[39] In respect to the position on liquidated damages, QCE asserted that it was entitled to
extensions of time and that the provision for liquidated damages was a penalty.
27 Court File Document 17, Exhibit DL-1 at 62.
28 Court File Document 17, Exhibit DL-1 at 73.
29 Court File Document 17, Exhibit DL-2 at 256.
30 Court File Document 18 at [25]; Court File Document 17, Exhibit DL-2 at 103 and 263.
-- 9 of 23 --
10
[40] QCE also argued that the operation of cl.14 of the Contract is conditioned by cl.31 and
that the unadjusted date for completion under the Contract was 4 September 2017 but that
completion was not achieved as at 30 November 2017 and the adjusted date for
completion was 18 December 2017.31
Adjudication Response
[41] Cragcorp’s adjudication response contended that the entitlement to claim under the BCIP
Act was limited to entitlements arising under the Contract and it was exclusive of any
other legal entitlement. Cragcorp argued the Contract did not include an entitlement to be
paid for additional work arising from latent conditions. It was therefore argued that as
QCE had no entitlement to be paid for latent condition then the adjudicator had no
jurisdiction to award payments in relation to the contentious variations.
[42] It was also argued that the scheduling of an amount “on account” without an admission
of liability by the applicant did not relieve the first respondent from the obligation to make
a determination as to the entitlement under the Contract. Furthermore, the date for
completion under the Contract as adjusted was 26 September 2017 and the date of
completion was 10 October 2017.
[43] Cragcorp also argued that it was entitled to liquidated damages as a setoff to the amount
claimed. 32
[44] It was further argued that if there was an entitlement to a payment claim established under
the contract, the amount payable was the scheduled amount and not the amount claimed
in the Payment Claim.
The Adjudication Decision
[45] On 6 February 2018, the Adjudicator made the Adjudication Decision which provided for
an amount of $205,218.53. The contentious aspects of the Adjudication Decision and the
reasons of the adjudicator related to the determination that the absence of a latent
condition provision in the contract was irrelevant and the conclusion that it was a valid
payment claim for variations under the Contract, albeit for a latent condition. The
adjudicator noted that Cragcorp used the terms “latent condition” when referring to some
of the variations but paid a scheduled amount where a variation had been accepted and in
some instances had granted extensions of time. The contractual requirement that the
parties treat each other in good faith was also considered. The adjudicator also held that
the liquidated damages claim is equal to and negated the Retention held by Cragcorp.33
[46] I shall deal with the contentious aspects of the Adjudication Decision in more detail as
set out below.
Essential Issues
[47] Under the Act, there is no appeal from an adjudicator’s decision and there is no general
jurisdiction to set aside the decision for error. There is a line of authority, however, which
establishes that an adjudication decision under the BCIP Act may be set aside for
31 Applicant’s Amended Outline at [43] – [45]; Court File Document 3, Exhibit DL-2 at 56.
32 Applicant’s Amended Outline at [46].
33 Court File Document 17, Exhibit DL-7 at [155].
-- 10 of 23 --
11
jurisdictional error in the performance of that function. This principle was most recently
discussed by the High Court in Probuild Constructions (Aust) Pty Ltd v Shade Systems
Pty Ltd34 where the majority held that the principal basis for making an order to set aside
a decision or have it declared void is jurisdictional error, which enforces the limits of a
decision-makers functions and powers. The majority declared that: “The jurisdiction of a
State Supreme Court to review an exercise or purported exercise of power for
jurisdictional error, and to grant relief in the nature of certiorari (and prohibition and
mandamus) where jurisdictional error is found, serves to enforce the limits of State
executive and judicial power.”35
[48] Once established, jurisdictional error vitiates the whole of a decision and there is no
discretion as to the nature of the remedy and a declaration that the decision is void or an
order quashing the decision must follow except to the extent that severance is permitted
pursuant to the amendments to the Act. The applicant argues that the Decision of the
adjudicator in this case was not a valid exercise of jurisdiction because she failed to
identify and apply the terms of the contract, failed to make a decision within the scope of
ss 25 and 26 of the Act and denied the applicant natural justice.
[49] The specific grounds upon which the applicant relies in this application are:
(a) Ground 1 – The Adjudication Decision determined amounts as payment
beyond the jurisdiction of the second respondent.
(b) Ground 2 – The second respondent failed to perform the statutory task
by applying the terms of the Contract and by failing to have regard to
properly made submissions of the applicant.
(c) Ground 3 – The second respondent denied the applicant natural justice.
(d) Ground 4 – The second respondent failed to give proper written reasons
in non-compliance with s 26(3) of the BCIP ACT.
(e) Ground 5 – The Adjudication Application is an impermissible claim for
restitution in the face of no contractual entitlement.36
[50] The applicant essentially submits that this Decision can be declared void or set aside due
to jurisdictional error or the Decision can be quashed.37 If there has been such an error,
the next consideration is whether, pursuant to s 100(4) of the BCIP Act, that part of the
Decision can be severed.
The entitlement to variations under the contract
[51] Whilst five grounds are listed, many of those grounds are interrelated and overlap, as
counsel for QCE argues. The major complaint by Cragcorp seems to be with the way in
which the adjudicator dealt with the liquidated damages aspect of the claim and what
QCE referred to as VO-001 and VO-002 and Cragcorp’s argument that those claims did
34 [2018] HCA 4.
35 Ibid at [29].
36 Court File Document 13 at [3].
37 Court File Document 13 at [18] – [19]; Civil Proceedings Act 2011 (Qld) s 10; Judicial Review Act 1991 (Qld)
ss 41, 43 and 47.
-- 11 of 23 --
12
not properly arise under the contract. This was because they were latent conditions and
as the subcontract provided no entitlement to payment for latent conditions, QCE had no
contractual basis for the payment claim.
[52] Cragcorp argues that the reasons do not disclose the contractual or factual basis on which
the second respondent determined the adjudication, arguing that they are no more than
statements of conclusion which are unsupported by an analysis of the facts or submissions
that were before the adjudicator. In particular, in relation to VO002, the applicant argues
that the adjudicator did not have regard to the submissions of the applicant.
[53] It is also argued that the Adjudicator failed to base her reasons on an analysis of the
contractual terms or an identification of the manner in which they are said to operate. The
applicant also argues that the Adjudicator wilfully departed from the evidence and
submissions made by the parties without putting any of the matters before the parties for
submissions and that the reasons involved a rewriting of the contract.
Grounds 1 and 2: failure by the adjudicator to perform the statutory task of
valuation
[54] It is uncontentious that in the context of the BCIP Act, the essential question in
determining whether there is jurisdictional error is whether the adjudicator has actually
performed the function required on the adjudicator under the Act. The relevant principles
were outlined by White JA in Northbuild Construction Pty Ltd v Central Interior Linings
Pty Ltd:38
“The discussion in Minister for Immigration and Citizenship v SZMDS concerning
the relationship between jurisdictional error in respect of reasoning which is
“clearly unjust”, “arbitrary”, “capricious” and “Wednesbury unreasonable”
demonstrates that attaching these descriptors to the good faith debate possibly
adds little more than did the original understanding of good faith in the review of
statutory decision making that the power must be exercised honestly for the
purpose for which it was given. As the New South Wales Court of Appeal did in
Holmwood, the enquiry should focus more on whether the adjudicator has
performed the function demanded by the Payments Act and less on pursuing
elusive synonyms, keeping always in mind that the legislative intent dictates a
person with recognised expertise in the area be selected for the task by an
informed body and this, necessarily, facilitates the rapid decision making
required.”39 (my emphasis)
[55] Cragcorp argues that the adjudicator failed to have regard to and apply the contract in
assessing the Payment Claim and that such failures were material jurisdictional errors.
Cragcorp argues that Items 1 and 2 of the alleged Variations were articulated to them in
the administration of the Contract, the Payment Claim and in the Adjudication
Application as latent conditions which were said to arise pursuant to Clause 25 of
AS4000. In this regard there can be no doubt that the contract does not in fact import and
is not otherwise informed by AS4000. I also accept that the contract makes no provision
for entitlement for a payment for a latent condition. Cragcorp argues that a submission
in these terms was squarely made but ignored by the Adjudicator without any explanation.
38 [2012] 1 Qd R 525.
39 Ibid at [96].
-- 12 of 23 --
13
[56] Cragcorp also submits that at common law there is no right to payment for an unforeseen
condition encountered in a building project unless the contract expressly provides for
payment for such an unforeseen condition. Furthermore, it is argued that the mere fact
that the contract was more difficult to perform as a result of unforeseen circumstances
does not relieve QCE from the obligation to perform the contract. It also is argued that
such an unforeseen circumstance did not engage an entitlement to an implied term for
payment.
[57] Whilst the Adjudicator summarised the position put by the applicant at paragraph 71 and
72 of the Decision, Cragcorp maintains that the adjudicator then determined that she could
treat VO001 and VO002 as variations but without any analysis as to whether or not the
direction relied upon in terms of Clause 13 of the Contract involved a variation of scope
or extent of the subcontract works.
[58] In this regard I note that work is defined in Clause 1 as:
“Works means the work to be executed by the Subcontractor for the
Contractor, as evidenced by the documents set out within the Subcontract
Agreement.”
[59] Variation is defined in Clause 1 as:
“Variation means a direction by the Contractor to the Subcontractor prior
to completion to vary part or all of the works. The direction is to be made
pursuant to Part B – Clause 13 and shall be within the general scope of
the work.”
[60] In relation to VO002, Cragcorp argues that by proceeding to value the drilling work as a
variation, the Adjudicator engaged in jurisdictional error by wrongly assuming
jurisdiction to determine an amount which did not give rise to an entitlement to payment
under the Contract.
[61] Cragcorp argues that the Adjudicator purported to value Variations 1 and 2 as variations,
whereas an entitlement to a claim for a variation under the contract was regulated by
Clause 13, with the definitions which were to be considered for variation works in Clause
1. Clause 30 was also relevant in relation to the provision in relation to notices. Cragcorp
argues, therefore, that on a proper construction of the contract, taking into account those
clauses, it was necessary for there to be:
(a) a direction in writing from the Contractor;
(b) which was a direction which “varies part or all of the works”; and
(c) the direction must either state that it is to “vary the scope or extent of the
Subcontract Works”; or
(d) the Subcontractor must have given notice within three business days of
the relevant direction that it was claiming a variation.
[62] In order to ascertain whether there has been jurisdictional error, it is necessary to refer to
the way in which the Adjudicator approached her task and the key findings that were
made with respect to the issues which are in dispute in this proceeding. The question is
-- 13 of 23 --
14
not whether the Court would have come to the same conclusion as the Adjudicator but
whether the Adjudicator performed the functions required by the Act.
[63] A consideration of the Adjudicator’s Decision indicates that, as required by the Act, the
Adjudication Decision outlined the objects of the Act and then referred to s 26 and the
matters an Adjudicator is to decide; namely, the valuation of the payment claimed. The
Decision noted that the only matters the Adjudicator was able to consider were the Act,
the contract, the Payment Claim and Payment Schedule, as well as properly made
submissions in support of the Claim and the Schedule. A perusal of the Decision indicates
that the Adjudicator approached her task in the proper way, conscious of the relevant
legislation as well as relevant documents, particularly the subcontract. She then noted the
key dates and the essential matters in dispute and then turned to a consideration of matters
that an adjudicator may consider and is to decide.
[64] The Adjudicator was satisfied that the Payment Claim was valid and dealt, as a
preliminary matter, with the issue of whether there was a contractual right to variations.
In particular, at paragraph 22, she referred to the contract provisions and later in the
Decision she specifically referred to QCE’s Adjudication Application Submissions and
Cragcorp’s Adjudication Response.40 She was therefore acting within jurisdiction when
she concluded after an examination of the contract, that the absence of a latent condition
clause in the subcontract was irrelevant to a consideration as to whether they in fact
constituted variations under the subcontract, albeit for a latent condition.
[65] In relation to the ability to claim variations, an analysis of the Decision, particularly the
initial determination in relation to jurisdiction, indicates that the adjudicator specifically
considered the subcontract. Particular reference was made to QCE’s claim that the
amounts claimed were variations pursuant to the subcontract and Cragcorp’s response
that the payment claim was made without jurisdiction on the basis that QCE had no
contractual right to the variations claimed as they were latent conditions and QCE had
not demonstrated how the work claimed was in fact a variation work within the meaning
of clause 13 of the Subcontract and was not subject to the express risk allocation
expressed in clause 7.
[66] In my view, a fair reading of the Decision indicates that the Adjudicator did address the
issue as to whether there was an ability to claim variations under the subcontract and
correctly noted that the term ‘latent conditions’ appeared not to have been used in the
contract but that it provided for variations and there was a requirement that the parties
were to deal with each other in ‘good faith’. The Adjudicator in particular accepted that
“The email of 8 August 2017 from the [Cragcorp] Project Manager, directed Qld Civil to
proceed to swap the pits and sought details of any costs incurred to be submitted and once
agreed, to be paid as an ‘over activity’.”41
[67] The Decision referred to the subcontract not only providing for variations but how they
were to be claimed and answered by adjustment of the contract price and EOTs. Reference
was then made to Cragcorp’s Adjudication Response which referred to the fact that it
scheduled amounts for VO1, VO2 (and VO4) in the payment schedule and that the
amounts were scheduled ‘on account’ and ‘in good faith’. In this regard the adjudicator
noted that Cragcorp referred to them as “Variations being in respect of ‘latent conditions’”
40 Court File Document 3, Exhibit DL-7 at [63] – [91].
41 Court File Document 3, Exhibit DL-7 at [83].
-- 14 of 23 --
15
and gave a scheduled amount where a variation had been accepted and in some case had
granted extensions of time in respect of them.42
[68] The Adjudicator had before her all of the all of the supporting documentation in relation
to QCE’s claims for variations as outlined above, which included evidence of ‘directions’
to QCE in accordance with the contractual requirements. The Adjudicator’s Decision was
clearly based on a consideration of the documentary material which indicates that whilst
QCE used the term latent condition in some of their correspondence, it was always in
relation to a variation. That documentation revealed that QCE had made it very clear that
they were seeking variations and that they were giving notice pursuant to Clause 30(c) of
the contract. The emails of 3 August 2017 specifically referred to Clause 30(c) of the
Subcontract and stated “QCE submit to the Contractor (QBC) a variation request.”43
Those requests for variations could not have been more explicit.
[69] Furthermore, the correspondence from Cragcorp also adopted that terminology. Indeed,
the letters from Cragcorp of 8 and 28 August 2017 made it clear that Cragcorp was giving
a direction to QCE to proceed with the work as a variation. As Counsel for QCE submits,
the letter from Cragcorp of 8 August 2017 specifically indicated that any costs incurred
for “rectification of the unstable ground needs to be submitted for approval.”44
Accordingly, it was not just a direction to do the work, which would of course be
unnecessary given the terms of the contract. Rather, as Counsel for QCE put, it was in
clearly relation to a variation: “Here’s a direction. I’m directing you. If you’ve got claims
for costs get them to us.”45 The entitlement to a variation was contingent on a direction.
The adjudicator considered not only the terms of the contract, but the factual
circumstances surrounding the performance of the work and was clearly satisfied on the
material that a direction was given and it was a variation in terms of the subcintract.
[70] All of the supporting documentation was provided to the Adjudicator and clearly was
considered by her in coming to her Decision. Cragcorp indeed accepts that it directed
QCE in writing to swap the locations of the entry and receiving pits the subject of VO001
and that the excavation of the pits involved excavation in rock but argues it was simply a
direction to proceed with the works and not a direction in relation to a variation. There
can be no substance to the argument that the adjudicator failed to have regard to and apply
the contract in assessing the Payment Claim and that she ignored Cragcorp’s submissions.
[71] I note that Counsel for Cragcorp sought to rely on a series of decisions including BM
Alliance Coal Operations Pty Ltd v BGC Contracting46 (where the contracts contained
specific clauses in relation to latent conditions), to argue that the work done here was in
fact work done because of a latent condition. Counsel argued that the works done when
rock was encountered have “All the hallmarks of a latent condition as described by Justice
Muir in BM Alliance Contracting.”47 As there was no specific clause in relation to latent
conditions in this case, those decisions need to be read in that context and were therefore
of limited assistance in the circumstances of this case.
42 Court File Document 3, Exhibit DL-7 at 135.
43 Court File Document 17, Exhibit DL-1 at 4.
44 T 1-44: 1 – 6.
45 T 1-44: 9 – 10.
46 [2013] QCA 394.
47 T 1-18: 44- 45.
-- 15 of 23 --
16
[72] Cragcorp argued in the Adjudication Response for the first time that QCE had no claim
for a latent condition and could only make claims for payment under the contract
provision. The adjudicator noted that the issue of latent conditions was not raised in the
Payment Schedule and she determined that under s 24 of the Act she could only refer to
issues raised in the Schedule and not those raised for the first time in the Response.
Significantly, in the Payment Schedule, Cragcorp had not disputed the existence of the
variation claims. I note that Cragcorp’s Payment Schedule contained a heading
“Approved Variations” and records at VAR001 that $14,616 had been previously
approved and therefore, of the total of $29,025.25 claimed by QCE, the amount of
$15,263.40 was in dispute with a notation under the heading “Justification/Reason for
Difference” that it was ‘paid on account’.48
[73] Similarly, VAR002 shows that the total claimed was $143,911.66 and $28,782.33 had
been previously claimed and therefore the amount claimed was $115,129.33. It was
accepted that $14,391.17 was to be paid and therefore $100,738.16 was in dispute with a
similar notation that it was ‘paid on account’. Variations 5, 6, 7 and 8 referred to in the
Schedule are not in dispute. Cragcorp argues now that whilst the term “on account” was
used that was “without any admission of liability.”49 There is a line of authority including
G W Enterprises Pty Ltd v Xentex Industries Pty Ltd & Ors,50 Wiggins Island Coal Export
Terminal Pty Ltd v Monadelphous Engineering Pty Ltd & Ors51 and Thiess Pty Ltd and
John Holland Pty Ltd v Civil Works Australia Pty Ltd & Ors52 supporting the principle
that an adjudicator should not take into account reasons for withholding payments that
were not raised in the Payments Schedule. It is clear, however, that an adjudicator is still
required to perform an adjudication in accordance with the Act and the contract under
consideration irrespective of whether the parties had made submissions about the
particular issue. In South East Civil & Drainage Contractors P/L v AMGW P/L & Ors53
Jackson J held that s 17(4) of the Act had not been complied with and the mere fact that
the submissions of the respondent did not take the point did not excuse compliance with
the requirements of the Act.54
[74] The adjudicator clearly considered the terms of the contract and the requirements of the
legislation as she was required to do but was entitled to disregard any new reasons
submitted for the first time in the Payment Schedule in that context. There can be no doubt
that the Payment Schedule did not dispute entitlement to either variation but rather
accepted the entitlement. Whilst the Adjudicator stated that she was barred from “taking
account of the material in the Adjudication Response”55 in relation to this issue, she
clearly considered whether there was indeed an entitlement under the contract as she was
required to do and she had all the relevant primary documentation before her. The
documents speak for themselves.
[75] In my view, the use of the words ‘on account’ would support an inference that a variation
had been approved at the time and that only quantum is in dispute. Whilst paragraphs 107
and 108 of the Decision indicate that the Adjudicator considered Cragcorp’s reasons in
48 Court File Document 3, Exhibit DL- 5 at 104.
49 Court File Document 13 at [46].
50 [2006] QSC 399 at [36].
51 [2015] QSC 307 at [51].
52 [2011] 2 Qd R 276.
53 [2013] QSC 45.
54 [2013] QSC 45 at [45].
55 Court File Document 3, Exhibit DL-7 at [110].
-- 16 of 23 --
17
the Payment Schedule were sparse and the submissions in the Adjudication Response
would not be taken into account pursuant to s 24(4) of the Act, the issue was clearly
considered. The submissions in the response effectively tried to assert a different factual
basis for the use of the term “on account” and the Adjudicator was entitled to disregard
those submissions. As the Adjudicator noted, even a quick assessment by Cragcorp in the
Payment Schedule would have indicated the main areas of disagreement as the Act
requires.
[76] I consider therefore that the adjudicator performed the task required of her under the Act.
She made a decision that QCE’s payment claim was a claim for a variation under the
contract after considering the contract, the Act and all supporting documentation. Counsel
for Cragcorp sought to rely on the decision of Douglas J in Ball Construction Pty Ltd v
Conart Pty Ltd56 to argue that the adjudicator engaged in jurisdictional error by failing to
apply the terms of the contract. In my view, consistent with the statements of principle by
Applegarth J in BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd &
Ors,57 the adjudicator has found a legal source for the entitlement to a variation in the
construction contract, albeit for a latent condition which was not otherwise specifically
dealt with in the subcontract. I also consider that the Adjudicator provided sufficient
reasons in relation to this aspect of her Decision.
[77] I do not consider that the adjudicator has fallen into jurisdictional error in this regard. The
adjudicator was entitled to reach that conclusion based on a consideration of the material
before her.
Grounds 3 and 4: the adjudicator denied Cragcorp natural justice and failed to give
proper written reasons in non-compliance with s 26(3) of the BCIP ACT.
[78] Cragcorp argues that the Adjudicator denied Cragcorp natural justice because in
interpreting the contract in a manner not contended for by either party, she has failed to
provide Cragcorp with the opportunity to make an argument which might have persuaded
the Adjudicator to reach a different decision. It is contended that this occurred particularly
in relation to the claim for liquidated damages where it is alleged that the Adjudicator
made a decision in the absence of submissions from the parties.
[79] The Adjudicator’s Decision sets out the history of this aspect the dispute. Cragcorp had
argued in the Adjudication Response that they were entitled to deduct liquidated damages
because QCE failed to reach completion of the works by the Adjusted Date for
Completion of 26 September 2017. The amount of $36,454.01 was therefore calculated
from 26 September to 10 October 2017. Cragcorp argued that pursuant to Clauses 11.6
(Set-off) and 15 (Liquidated damages), it was entitled to elect to withhold payments.
[80] In the Adjudication Application Submissions, QCE had made it clear that there was no
mention of Liquidated Damages in the Payment Claim but that the Payment Schedule
sought to impose a set-off for liquidated damages of $36,454.01. QCE accepted that the
subcontract allows for liquidated damages which was capped under the contract at no
more than 5% of the contract price which was $36,454.01. QCE submitted, however, that
the attempt to impose liquidated damages was misconceived and ignored the terms of the
contract in circumstances where the adjusted date for completion was no earlier than 18
56 [2014] QSC 124.
57 [2012] QSC 346 at [56].
-- 17 of 23 --
18
December 2017. A date which was expressly directed by Cragcorp. The submission then
contained 4 pages of references to emails and other factual material outlining the history
and duration of the delays in relation to the claimed variations which they argued
substantiated the date of 18 December 2017. QCE argued that 10 October 2017 was an
arbitrary date.
[81] QCE also argued that the liquidated damages regime was a penalty in circumstances
where Cragcorp’s liability to Brisbane City Council relates to practical completion and it
therefore had the ability to penalise QCE for minor non–conformance. They concluded
at paragraph 20.33 in the following terms:
“Reading clause 15 and the rate for liquidated damages together with
fairness, reasonableness and good faith principles at clause 31, the
liquidated damages regime ought to be found to be unenforceable by
virtue of it being a penalty.”
[82] In the Decision, the Adjudicator considered that QCE’s position was that it was entitled
to extensions of time and that whilst the date for completion under the Contract was 4
September 2017, the operation of clause 14 in relation to extensions of time was
conditioned by clause 31 which contained the good faith clause. In this respect the
extensions were required as a result of events beyond their control. QCE had submitted
that Cragcorp had given an EOT until 18 December 2017 but had misidentified it as 10
October. QCE argued that completion was the completion of all work, with there being
no link between practical completion and liquidated damages. Alternatively, it was
argued that completion was achieved when the sewer became live which was not until
which was not achieved until 30 September 2017.
[83] It was noted that QCE argued that as the EOT’s were events beyond their control
Cragcorp was required to reasonably assess the validity of the EOT claim. It was also
argued that Cragcorp had not properly applied the subcontract and that determining the
date of completion as “Practical Completion” is not a term of the contract. Furthermore,
the date for completion was adjusted several times with the last adjustment on 20
November when Cragcorp directed QCE complete the works by 18 December 2017.
[84] The Adjudicator then set out the response by Cragcorp noting that it was argued by
Cragcorp that QCE was required by the contract to complete the work by the date set by
Cragcorp. This was defined as completion which was the point of time determined by
Cragcorp. The date of 18 December could not thereby be sustained.
[85] Cragcorp claimed that, rather than be a penalty, the liquidated damages were not out of
proportion with Cragcorp’s foreseeable loss but a genuine pre-estimate of loss. It was
noted that on 14 November 2017 Cragcorp had given QCE a Certificate of Completion
for 10 October at the same time it had provided an EOT in relation to the scour pit
variation VO005 of 18 December 2017. The EOT of 18 December was only relevant to
variation 5.
[86] The Adjudicator, in assessing that aspect of the adjudication, stated she had considered
clauses 14 and 15 of the Subcontract and noted that Practical Completion was not defined
in the Subcontract. She referred to Cragcorp’s argument that the giving of the Certificate
-- 18 of 23 --
19
“indicates completion”58 and the fact that the sewer became live on 30 September was
irrelevant. The Adjudicator noted the four dates which were proposed as the date of
Practical Completion namely 26 September 2017 (certified by Cragcorp as an EOT), 30
September (the date the sewer went live), 10 October 2017 (the date certified as practical
Completion by Cragcorp and QCE demobilised), 18 December 2017 (date for completion
of scour pit by EOT).
[87] The Adjudicator then stated that the terms of the contract included “good faith” provisions
but that liquidated damages were not generally seen as a penalty if applied within the
contract. Reference was made to the fact that unscheduled meetings must have been
occurring during a “contentious time when decisions were being made and rescinded”59
and that during this time liquidated damages of 14 days was raised by Cragcorp. It was
noted that work continued to 10 October when QCE demobilised with an agreement that
the scour pit would be treated as a defect with a formal EOT of 18 December. The
Decision continued:
“176. In a situation where the parties have agreed to deal with each other
in ‘good faith’ could the subcontractor have taken this acceptance as the
date after which the liquidated damages provisions became applicable? I
think they could.
…
178. In this situation, I consider that the parties came to a general
understanding under this ‘good faith”-based contract. The work was 'live’
seemingly within the requirements of the Brisbane City Council and I
have no information that [Cragcorp] suffered a penalty for the work being
delivered late.
….
180. In these circumstances, I determine that [Cragcorp] cannot
reasonably impose liquidated damages on [QCE].
181. Adjudicated amount- I reject the payment and do not deduct a sum
in this regard from the Collection”60
[88] In relation to Retention, the Adjudicator considered that QCE appeared to claim the
Retention from Cragcorp based on the assertion that the works were complete by the date
of the Payment Claim, which was 30 November 2017. She considered that was contrary
to the reality that the work in relation to VO005 was to be completed by 18 December
and was in fact completed by 5 December 2017. Accordingly, she considered that seeking
the Retention with the Payment Claim was premature and she rejected the claim to the
Retention.
[89] There can be no doubt, as Counsel for QCE contends, that for Cragcorp to establish a
denial of natural justice the denial must be substantial. Has there been such a material or
58 Court File Document 3, Exhibit DL-7 at [169].
59 Court File Document 3, Exhibit DL-7 at [173].
60 Court File Document 3, Exhibit DL-7 at [176], [178], [180] – [181].
-- 19 of 23 --
20
substantial denial? As Applegarth J put the question in John Holland Pty Limited v TAC
Pacific Pty Ltd & Ors61 whether “the matter about which the adjudicator did not provide
an opportunity to be heard was a point upon which the adjudicator based his or her
decision and was significant to the actual determination.”62 A perusal of the Decision
indicates that the basis of the Adjudicator’s Decision was the submission from QCE but
that a different conclusion was reached to the one contended for. As Counsel for QCE
argues, Cragcorp had the opportunity to respond to those submissions and had indeed
done so.
[90] Furthermore, there must be a consideration of the substantial effect of the denial of natural
justice and whether providing an opportunity to be heard would in fact have made a
difference to the outcome. There is no indication that this would in fact have been the
case here as whilst the affidavit material indicates that further submissions would have
been provided if called for, there is no evidentiary basis to conclude that the adjudicator
would have made a different decision. Whilst an Adjudicator may ask for further
submissions, there is no obligation to do so and this was not a case where the adjudicator
was minded to decide a significant issue of law on a basis for which neither party had
contended.
[91] There is no doubt that the reasons in relation to liquidated damages and the issue of
Retention are brief, however, in my view, the Adjudicator considered the terms of the
contract and the documentary material before her as required by the Act. No jurisdictional
error is shown in this regard.
[92] It is also argued that the Adjudicator relied on the good faith obligation under the contract
to allow QCE to claim a latent condition as a variation and that an opportunity for further
submissions would have meant that conclusion would not have been reached. An analysis
of the Decision, however, reveals that the conclusion in relation to whether there had been
a variation was based on a consideration of all of the contractual terms and there was no
particular reliance on this provision as contended.
[93] It is also argued that the Adjudicator’s reasons failed to provide sufficient reasons which
explained the basis of her Decision and that this was jurisdictional error. Reliance was
placed on the decision of Flanagan J in Annie Street JV Pty Ltd v MCC Pty Ltd & Ors63
where it was held that if the reasons do not reveal any foundation or logical basis for a
decision then there has been a failure to exercise jurisdiction.64
[94] Cragcorp argues that in relation to Variation VO001 the controversy relates to the
difference between the amount claimed in the Payment Claim of $29,979.40 and the
updated Scheduled amount of $15,789.15 but that the reasons “fail to have regard to, or
even mention, the $15,789.15 conceded.”65 In this regard I note that at paragraph 78 that
amount is in fact specifically referred to and it was noted that Cragcorp “had raised the
assessment to $15,789.15.”66 I accept, however, that whilst the Adjudicator discusses the
submissions in the Decision, at no point is there an identification of:
61 [2010] 1 Qd R 302.
62 Ibid at [40].
63 [2016] QSC 268.
64 Ibid at [30].
65 Court File Document 13 at [93].
66 Court File Document 3, Exhibit DL-7 at [78].
-- 20 of 23 --
21
(a) conclusions as to amounts for each element of work claimed;
(b) the basis of the total amount assessed from the elements of work she
concluded;
(c) from which parties’ evidence she deduced the elements of work said
to be part of the variation; and
(d) from which parties’ evidence she calculated the value as against the
contractual standard.
[95] However, as QCE argues, there is no contractual basis for Cragcorp’s submission that the
adjudicator was required to determine the extra work by the particular item and then value
the extra work on the basis of identifying a reasonable price. The requirement was to
identify a reasonable price. Whilst the adjudicator was required to consider and decide
between the parties the competing positions on each part of VAR001, she was entitled to
ignore their submissions that were made in support of the contention that the amounts
claimed were not variations. As previously noted, the submissions which must be
considered are submissions which are properly made. They submit that properly made
means “submissions that support what you have said in your payment schedule and if you
haven’t said in the payment schedule ‘This isn’t in fact a variation,’ then the submission
isn’t properly made and it’s not a matter that ought be considered.”67
[96] Furthermore, it not necessary that there be precision in relation to every factual matter
and in my view, the reasons provided in this regard indicate that the Adjudicator
considered all the material she was required to and she gave a clear conclusion. It must
be remembered that the Adjudicator is required to make a decision within exceedingly
tight timeframes in circumstances where a large volume of material is provided. The
Adjudicator makes a decision on the material provided in accordance with the Act and
whilst the reasons are scant, I do not consider there has been a denial of natural justice
because the reasons do not go into precise detail. It is clear enough from the reasons the
conclusions reached and why. The adjudicator allowed $20,724.75 in circumstances
where the scheduled amount was $15,789.15.
[97] In relation to VO002 there is no doubt that the Adjudicator dealt with that issue briefly
but as already noted the Payment Schedule did not disclose a reason for withholding
payment. Whilst reasons were later put forward by Cragcorp which endeavoured to argue
a different interpretation for the words “on account”, the Adjudicator considered the
submissions before her that had been properly made and concluded that it was a variation.
The Adjudicator was also satisfied that the value of that variation was properly supported
on the material and was $143,000 as claimed. No jurisdictional error has been revealed
in this regard as once again the Adjudicator performed the task she was required to
perform under the Act.
[98] Even in cases where it has been considered that the reasons were inconsistent and
illogical, that has not been sufficient to establish jurisdictional error if there was at least
some process of reasoning disclosed in the reasons. As Brereton J held in City of Ryde v
AMFM Constructions Pty Ltd & Anor:68
67 T 1-50: 22 – 24.
68 [2011] NSWSC 1469.
-- 21 of 23 --
22
“As to the first of these, the inadequacy, insufficiency, inconsistency or
illogicality of reasons for a decision, even when the governing statute
requires a decision-maker to give reasons in conjunction with and
contemporaneously with the decision, does not of itself amount to
jurisdictional error. The significance of the reasons, or their inadequacy,
is that in the context of the surrounding material they may reveal
jurisdictional error, or that the adjudicator has not performed the task of
determining an adjudicated amount by reference to the specified relevant
factors in accordance with s 22 of the Act.
….
The way in which inadequacy of reasons may be used to reveal or
illuminate jurisdictional error is apparent from the decisions of the Court
of Appeal in Halkat Electrical Contractors Pty Ltd v Holmwood Holdings
Pty Ltd [2007] NSWCA 32, and of McDougall J in Bauen Constructions
v Westwood Interiors [2010] NSWSC 1359. What is important to
appreciate is that it is not a question of a plaintiff in this Court pointing to
the reasons and saying “well, it is not apparent how the adjudicator
reached this particular decision”; rather the plaintiff must be able to show
that the reasons, in the context of the surrounding material, demonstrate
that there has been a failure on the part of the adjudicator to perform his
or her statutory function. That was, for example, apparent in Halkat v
Holmwood and in Bauen v Westwood, because the adjudication
determination proceeded not by reference to the matters referred to in s 22
at all, but by the adjudicator, with an acknowledged inadequacy of
evidence to determine the matter, proceeding to do so on an essentially
capricious basis.
In considering whether it can be shown from an adjudicator’s reasons that
he or she has not performed the statutory obligations required by s 22, it
is also important to bear in mind that adjudicators operate under confined
timeframes, and that their decisions are given not in a vacuum but in the
context of the payment claim, payment schedule, adjudication application
and adjudication response that have preceded them. It is worth observing
that in this case the adjudication response alone amounted to some 17
pages, accompanied by a statutory declaration which had annexed to it
approximately 220 pages. It is not realistic to expect an adjudicator
operating under the time constraints imposed by the legislation to produce
reasons that address, in a detailed way, every single point raised in that
bulky material.”69
[99] Section 26(1) of the Act sets out what an adjudicator is to decide; namely, the amount of
the progress payment, if any, to be paid as well as the date it is to be paid and the rate of
interest. Section 26(2) makes it clear what can be taken into account by the adjudicator
when making that determination, which is restricted to the Act, the contract, the payment
claim and payment schedule together with all submissions and relevant documentation
that has been properly made in support of the payment claim and the payment schedule.
69 Ibid at [9], [12] and [13].
-- 22 of 23 --
23
The decision must be in writing and include reasons as required by s 26(3). The task
required was summarised by Burns J in Ostwald Bros Pty Ltd v Jaylon Pacific Pty Ltd &
Ors70 in the following terms:
“The task of an adjudicator is to decide the adjudication application
having regard only to the matters specified in s 26(2) of the Act. That
involves a consideration of the provisions of the Act to the extent that they
are relevant, the provisions of the construction contract from which the
application arose, the payment claim (and all supporting submissions and
material) and the payment schedule (and all supporting submissions and
material). As McDougall J observed in David Hurst Constructions Pty Ltd
v Durham in connection with the New South Wales scheme of provisions:
‘[What] is called for is some process of balancing or evaluating the
competing materials supplied by the parties. It is not a matter of
calling evidence. Nor is it a matter of conducting some mini trial. But
at the same time, if the Adjudicator is to determine the amount of a
progress payment, it is implicit in the requirement to do so that he or
she be satisfied that the amount so determined is in fact fairly or
properly payable, having regard to the provisions of the Act and of the
relevant construction contract (and any other relevant material duly
put forward). Thus, one might think, it is incumbent on the claimant
to put before the adjudicator material that is rationally capable of
persuading the adjudicator that the amount claimed was in fact
payable.’”71 (citations omitted)
[100] In my view, that was in fact the process the Adjudicator engaged in. The Adjudicator
determined that in accordance with s 13 of the Act the amount of the Progress Claim was
$205,218.53 (GST inclusive).
[101] No jurisdictional error has been identified.
[102] I do not therefore consider there is any basis for the relief sought pursuant to s10 of the
Civil Proceedings Act 2011 (Qld) or the inherent jurisdiction of the Court. I also note that
in part 2 of Schedule 1 of the Judicial Review Act 1991 (Qld) there is a specific reference
to the BCIP Act legislation as an enactment to which the Act does not apply. I note the
arguments of Counsel for Cragcorp that as a result of obiter dicta in Northbuild, it could
be debated that the exclusion only operates in relation to cases which do not involve
jurisdictional error. I do not need to specifically consider that issue, however, given that
jurisdictional error has not been established in the circumstances of this case.
[103] I consider therefore that the originating application filed on 20 February 2018 should be
dismissed. I note that on 22 February 2018 Orders were made by Atkinson J in relation
to an amount to be paid into court. I will therefore hear from the parties as to the form of
order and as to costs.
70 [2016] QSC 240.
71 [2016] QSC 240 at [26].
-- 23 of 23 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2018/203