Cheshire Contractors Pty Lt v Everett [2018] QSC 228 [2018] 42 QLR
SUPREME COURT OF QUEENSLAND
CITATION: Cheshire Contractors Pty Ltd v Everett [2018] QSC 228
PARTIES: CHESHIRE CONTRACTORS PTY LTD
(ACN 124 700 385)
(Plaintiff)
v
MARK LANSDOWNE EVERETT
(Defendant)
FILE NO/S: 154 of 2016
DIVISION: Trial
PROCEEDING: Claim
ORIGINATING
COURT:
Supreme Court at Cairns
DELIVERED ON: 8 October 2018
DELIVERED AT: Cairns
HEARING
DATES:
2, 3, 10, 11 August 2017; 8, 9 November 2017;
15, 16, 17 January 2018; 10, 11 April 2018.
JUDGE: Henry J
ORDERS: 1. Judgment for the plaintiff in the amount of
$450,493.59.
2. I will hear the parties as to costs if not agreed in the
meantime at 9.15 a.m. on 24 October 2018.
CATCHWORDS: CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – DISCHARGE, BREACH AND DEFENCES
TO ACTION FOR BREACH – REPUDIATION AND NON-
PERFORMANCE – where there was an oral contract for
works – where full payment for works was not made – where
there were complaints of non-compliance of works performed
– where there were complaints of other breaches of implied
terms – whether the works were compliant – whether there
were remedial works required – whether there was loss or
damage occasioned.
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION – where
there was an oral contract for the commencement of works –
where there were two phases to the works involved – where
phase one was a work for pay engagement – where phase two
had no substantive pay arrangement – where payment was to
be by reference to hourly rates for phase two – where there
existed a promise to delay the seeking of payment – whether
that promise amounted to a promissory estoppel.
-- 1 of 68 --
2
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
CONSTRUCTION OF PARTICULAR CONTRACTS –
where there were two phases to the works involved – where
there existed an oral contract for phase one works – whether a
further oral contract, joint venture or new contract existed for
further works – where there were works completed after
payment in full was not received for phase one and other works
completed– whether there existed any agreement for payment
for the further works.
Amos v Citibank Ltd [1996] QCA 129, cited.
Bellgrove v Eldridge (1954) 90 CLR 613, cited.
Combe v Combe (1951) 2 KB 215, 219, followed.
Foakes v Beer, (1884) 9 AC 605, followed.
Giumelli v Giumelli (1999) 196 CLR 101, cited.
Hughes v Metropolitan Railway Co (1877) 2 AC 439, cited.
John Alexander’s Clubs v White City, (2010) 241 CLR 1,
followed.
Legione v Hateley (1983) 152 CLR 406, followed.
Masters v Cameron (1954) 91 CLR 353, cited.
Riches v Hogben [1985] 2 Qd R 292, cited.
COUNSEL: WGC Lawyers for the plaintiff
Ascione & Associates for the defendant
SOLICITORS: C E Taylor for the plaintiff
C J Ryall for the defendant
Introduction
[1] The plaintiff, a civil contractor, performed development work on a proposed rural
subdivision of the defendant’s property west of Ingham. It claims $966,890.74 as
damages for breach of contract or as a debt pursuant to a contract.
[2] The work was performed in two phases, the first in 2011 (“phase one”), the second in
2014 (“phase two”). There was no apparent dispute by the end of phase one that the
defendant, Mr Everett, was obliged to pay the plaintiff, Cheshire Contractors Pty Ltd
(“Cheshire Contractors”) for the work it had performed. The problem at that stage
was that Mr Everett could not afford to pay. To cope with this dilemma, he
successfully prevailed upon Cheshire Contractors to confirm in an email of 20
December 2011 that it would not seek payment for work performed until there were
sufficient sales or presales to allow Mr Everett to make payment. Mr Everett is hiding
behind this email and recently conceived technical complaints as an unrealistic basis
to avoid his obligation to pay for the phase one works.
[3] He is not the only party who will not concede the obvious. After two further years
went by without payment to it, Cheshire Contractors took the fateful decision to
become proactively involved in assisting Mr Everett to advance the project. Amidst
-- 2 of 68 --
3
talk of a joint venture Cheshire Contractors rolled the dice and ploughed on into the
phase two works, without agreement about payment for the works having been
reached. Cheshire Contractors eventually ceased its phase two works, optimistically
asserting that it ought be paid for its speculative folly.
[4] So it is, with each party bogged in unrealistic positions, it is necessary to wade the
evidentiary mire of several years of ill-fated property development to expose the
reality of their commercial obligations to each other.
Determining the case
[5] Cheshire Contractors says its case is straightforward – its invoiced work should be
paid. What began as a listed hearing of four days but became an eleven day trial,
involving broken sets of hearing days spanning many months, as well as the
determination of a separate question,1 was far from straightforward.
[6] Cheshire Contractors asserts in respect of both phases of work it had an agreement
with Mr Everett to perform the works for payment at agreed rates, that it performed
the works and that it is entitled to be paid what it invoiced at the agreed rates for the
performance of the works. The consequent loss and damage is claimed as damages
for the breach of contract inherent in Mr Everett’s non-payment or alternatively as
money due and payable as a debt payable under each contract. The quantum of its
claim is founded upon the invoiced sums.
[7] No reliance was placed at trial on a quantum meruit or unjust enrichment claim.2
There was at one point a mid-trial application to amend the pleadings in a way which
may have varied that position but following a ruling on a separate question,3 that
application was dismissed.4 As a result of the ruling the parties agreed the plaintiff’s
claim would be reduced by $96,000.5
[8] Cheshire Contractors’ relatively simple pleading of its case attracted a lengthy
defence, the content of which raised a plethora of issues of varying significance. A
lengthy reply followed.
[9] In respect of phase one, Mr Everett does not deny there was an agreement. Rather he
alleges that, in breach of the implied terms of the agreement, the works were not
performed consistently with the project’s progressive compliance testing and
inspection requirements, the amounts charged for the phase one works were not
invoiced for several years and exceeded the agreed amounts and some of the invoiced
work was not required by the agreement or any variation thereto (“performance
compliance complaints”). He sets off the damages allegedly arising therefrom.6
1 [2017] QSC 287.
2 See, eg, T2-88-89, T2-95-96.
3 [2017] QSC 287.
4 T6-5 L41.
5 T6-5 L9.
6 The determination of the separate question dispensed with a counterclaim.
-- 3 of 68 --
4
[10] Quite apart from the performance compliance complaints, Mr Everett raises an over-
arching complaint of significance. He asserts Cheshire Contractors is precluded from
claiming for the phase one works by reason of its allegedly binding promise, contained
in its email of 20 December 2011, that it would not seek payment for work performed
until there were sufficient sales or presales to allow Mr Everett to make payment.
[11] In respect of phase two, Mr Everett denies there was any agreement akin to that for
phase one. Instead he asserts phase two proceeded pursuant to a joint venture
agreement, consistently with the promise not to seek payment presales. He contends
by that agreement sales profits were to be shared, any outstanding amount owing to
Cheshire Contractors became a liability of the joint venture and the works performed
by Cheshire Contractors were part of its contribution to the joint venture. He
complains Cheshire Contractors breached the joint venture agreement in declining to
continue work in late 2014.
[12] Alternatively, Mr Everett asserts that if there was an agreement pursuant to which
Cheshire Contractors was to be paid for works performed in phase two, those
payments were to be confined to a budgeted total exceeded by the claim. Mr Everett
also alleges if there was such an agreement it was breached in ways similar to those
alleged in respect of the performance compliance complaints regarding phase one. An
additional breach is said to arise by reason of Cheshire Contractors allegedly agreeing
but failing to affect the subdivision of lot 77 of Mr Everett’s land, thus preventing its
sale and consequent satisfaction of Mr Everett’s debt to the bank with consequent loss
to Mr Everett and deprivation of his capacity to advance the development or sell it.
He claims a set off of his losses caused by Cheshire Contractors’ alleged breaches.
[13] The task of ascertaining what are alleged to have been essentially oral agreements is
plagued by a lack of evidentiary precision about them. Neither of the main
protagonists, Mr Everett and Mr Barry Cheshire, the managing director of Cheshire
Contractors, impressed as having a reliable recollection of matters of detail. Mr
Everett was unwilling to make reasonable concessions and appeared too ready to shift
responsibility rather than concede his own involvement in and knowledge of relevant
events. His answers implausibly cast him as a powerless, ignorant bystander in his
own property development. Mr Cheshire tended to testify in broad and sometimes
unresponsive terms and was at his vaguest about the supposed agreement under which
he performed the phase two works. If there exists a sensible explanation for why
Cheshire Contractors embarked upon the phase two works in 2014, other than that it
gambled on the parties reaching an agreement and the project succeeding, the Court
did not hear it from Mr Cheshire.
[14] Determination of the performance compliance complaints may be assisted by the
content of the admittedly limited documentary communication and the industry and
project document requirements for work of the kind undertaken. This may include
documents like plans and approvals dealing with development compliance
requirements, such as progressive inspections of works at so-called hold points, some
of which the defendant complains were not complied with. That said, the significance
of such compliance documents or industry requirements is dependent upon whether
such agreement as was reached expressly or implicitly required Cheshire Contractors
to perform a role in respect of compliance requirements.
-- 4 of 68 --
5
[15] The case requires the analysis of relevant events during and between each of the two
phases of works, with a view to identifying any agreements and the extent to which
they were complied with. The analysis ought also deal with events between the
phases, particularly in connection with the 20 December 2011 email. The length of
the pleadings in this case makes it unhelpful to structure these reasons around them.
It is simpler to integrate the resolution of the issues to which the pleadings give rise
within the above analysis.
[16] These reasons will therefore progress in four parts:
Part A - General factual background
Part B - Phase one analysis
Part C- The December 2011 promise
Part D - Phase two analysis
Part E - Determination of award and or set off.
PART A - GENERAL FACTUAL BACKGROUND
Ph 1 works
[17] The phase one works focussed upon the western end of Mr Everett’s property, which
was owned by him in his representative capacity as trustee of the Everett Family
Trust.7
[18] The residential development planned for the property was then known as
Hinchinbrook Habitats. The development was planned to extend over a number of
areas on the property, not just the area the subject of the phase one works.8 Various
areas of the property were excluded from the development as sensitive environmental
habitats, pursuant to a development approval for material change of use of 14 May
2010.9
[19] The works consisted principally of the installation of a road along an existing road
easement through the property.10 The primary purpose of the phase one works was to
provide better access to the property and the lots for potential purchase, so as to excite
expressions of interest by prospective purchasers. In addition, as Barry Cheshire
conceded, the works “were also part of the proposed completed development”.
[20] The road was built to subgrade level. This, Barry Cheshire explained, is the layer
directly beneath the pavement layer. The latter layer typically involves a further two
or three layers of gravel followed by bitumen or asphalt.11
[21] Barry Cheshire testified that other work performed at Mark Everett’s request during
phase one included the clearing of mangroves,12 the removal of an old bridge which
7 SOC [1], Def [1].
8 See, eg, Ex 45.
9 Ex 47.
10 T2-92 L15.
11 T2-50 L33.
12 T2-56 L14, T3-14 L41.
-- 5 of 68 --
6
was part of a causeway,13 putting a drain along some lots on the high side of the road,14
building a boat ramp,15 applying extra fill so the batters were less steep and could be
mowed,16 the clearing of 15 lots,17 rock work near the dam,18 excavation up the hill,19
the installation of ag pipe to drain some blocks20 and putting some gravel running
surface on the road for use during construction when the surface was slippery.21
[22] Some excavation material, which was excess to the needs of a project being conducted
on the Mt Cudmore Road near the Cardwell Range, was supplied by an entity known
as Abigroup for Cheshire Contractors’ use on embankments and bridging out an area
of mangrove in the phase one works.22 Barry Cheshire testified the work involved in
respect of the material brought on site from Abigroup was “considerable”.23 Mr
Cheshire explained a large compactor was used to break down the fill material, which
was quite coarse, for use in lessening the batter slopes. This involved stripping back
topsoil, placing and compacting the material, levelling it out and then putting the
topsoil back over the top again.24
[23] The nature of the works additional to building the road to subgrade was canvassed
more extensively in exhibit material such as timesheets. It was work for which
Cheshire Contractors invoiced Mr Everett. There was a belatedly conceived and
faintly argued debate, with which I now dispense, about some work not being
performed or required. I accept the work which was invoiced for was in fact
performed and required.25 Mr Everett was unconvincing in his denials of the
occurrence of some work, which of its nature he would be unlikely to realise had
happened unless witnessing it directly.26 I accept the performance of works additional
to those initially agreed to was requested by Mr Everett. I reject as implausible the
notion inherent in Mr Everett’s unconvincing testimony about this debate27 that
additional works were performed without request by Mr Everett.
Ph 2 works
[24] The phase two works focussed upon the eastern end of Mr Everett’s property. By this
time the planned residential development was known as Riverviews Estate. Once
again, the works did not constitute the whole of the project and were targeted upon
getting the first 31 lots in an adequate state to go to market with disclosure notices to
13 T2-59 L8, T3-15 L33.
14 T3-15 L44.
15 T2-54 L25 – T2-55 L1.
16 T2-55 L23.
17 T2-55 L42.
18 T2-56 L28.
19 T2-58 L16.
20 T2-58 L33.
21 T2-59 L29, T4-8 L28.
22 T1-75 LL15-47.
23 T3-14 L38.
24 T4-6 LL35-45.
25 Subject to the invoicing errors discussed below.
26 Eg T8-46 L46, T8-47 L25.
27 Eg T7-18 L27, 7-20 L1
-- 6 of 68 --
7
attempt to secure presale contracts.28 The 31 lots included the original 15 lots
reconfigured into 10 lots.29
[25] Barry Cheshire described the phase two works as including building a road to
subgrade level, which included creating a road away from the existing track into
alignment with Mt Separation Road. Barry Cheshire explained the works also
involved levelling and draining lots and removing and restoring topsoil so that the lots
were at what he described as the disclosure stage, meaning they were ready for sale
without much further work.30 Barry Cheshire testified the works also involved
application of hydro mulch, the provision of environmental controls, the creation of
rock check dams and the installation of culverts.31
[26] The phase two works performed by Cheshire Contractors extended beyond mere
construction work. Cheshire Contractors was involved in managing and marketing
the project – a marked difference from its “construction only” role in phase one.
Roles
[27] Barry Cheshire only attended construction “possibly weekly”.32 He explained he
discussed matters daily with Mr Everett and visited him weekly.33 Mr Everett testified
that while the phase one work was being performed he was on site for a “little bit of
time most days”34 and he worked on site “every day” during the phase two works.35
[28] The foreman throughout the entirety of the phase one and phase two works was Barry
Cheshire’s son Shannon Cheshire.36 Another of his sons, Clinton Cheshire, worked
in office administration dealing with wages, age receivables, age payables and the
bookwork in general.37 Cheshire Contractors’ administrator was Daniel Spencer38
and its safety officer was Nicki Spencer.39
[29] Shannon Cheshire’s recollection was that Mark Everett assisted during the works by
driving a dump truck, driving his own excavator (Shannon Cheshire recalled Mr
Everett acquired a new excavator for the phase two works), putting in drains, moving
logs, digging holes to let spring water out and laying stormwater pipe.40 Shannon
Cheshire testified Mark Everett was not charged for performing such works by
Cheshire Contractors.41
28 T8-75 L15.
29 T8-78 L37.
30 T2-78 L33 – T2-79 L22.
31 T2-81 L40.
32 T2-38 L35.
33 T4-14 L43.
34 T5-5 L41.
35 T7-44 L22.
36 T1-45 LL5-10.
37 T1-77 L2.
38 T2-38 L16.
39 T2-38 L17.
40 T1-74 L43 – T1-75 L12.
41 T1-68 L11.
-- 7 of 68 --
8
[30] Mr Everett testified he did perform some work in phase one with an excavator, albeit
one owned by Cheshire Contractors.42 Mr Everett testified that during phase two he
worked on site every day doing the works, with an excavator he had bought by then,
and also watered the roads on the weekend.43
[31] David Johnstone of LCJ engineers, the project designers, testified LCJ’s main
dealings with the clients for phase one were with Mark Everett and his nephew Glen
Everett. Indeed, LCJ’s drawings name Glen Everett as the client.44 Mr Johnstone
testified that Glen Everett appeared to be more involved in phase one and Mark more
involved in phase two.45 Glen Everett was not called as a witness.
[32] Of the work performed by LCJ in phase one, Mr Johnstone’s recollection was that
LCJ designed documentation such that plans were produced to construct works and
that LCJ’s Owen Carter did work to obtain approvals from Government agencies.46
Mr Johnstone, the only witness from LCJ, could give little direct evidence relevant to
LCJ’s role in phase one.
Timesheets
[33] Shannon Cheshire testified timesheets were filled out daily by all staff working on the
project and verified and signed off by him as foreman the following morning.47 Every
employee had a triplicate copy timesheet book.48 It recorded name, date, hours,
work/machine type description and work’s description.49
[34] The exhibited timesheets for phase one50 recorded work occurring from 7 July 2011
to and including 7 December 2011.
[35] The exhibited time sheets for the phase two works recorded work occurring from 16
July 2014, with physical work on site from early August, to and including 17
November 2014.51
[36] Shannon Cheshire explained the accuracy of the timesheets he checked was important
to not charging the client for more work than was performed and also to the efficacy
of Cheshire Contractors.52 On his account, copies of them were posted back to
Cheshire Contractors’ office weekly.53
42 T7-17 L47.
43 T7-44 L23.
44 Ex 1 Vol 1 Tab 10.
45 T2-6 LL9-15.
46 T2-6 L33 – T2-7 L1.
47 T1-55 LL37-43.
48 T1-55 L30.
49 T1-55 L33.
50 Ex 1 Vol 3.
51 Ex 1 Vol 4.
52 T1-56 L16.
53 T1-55 L46.
-- 8 of 68 --
9
[37] Shannon Cheshire testified that client copies of the timesheets were not collected by
the client during the project nor did the client sign the timesheets.54 Barry Cheshire
explained in evidence that he had told Mark Everett the timesheets were available all
the time on site, but Mr Everett said he did not want them.55 Mr Everett claimed to
the contrary in his testimony,56 but I accept Mr Cheshire’s evidence.
Invoices
The issuing of the invoices
[38] Clinton Cheshire generated invoices to the client from the timesheets, creditors’
invoices, dockets and purchase orders.57
[39] Clinton Cheshire testified he would forward the client the invoice, the job sheet listing
the various work charged by reference to numbered timesheets and the timesheets
with the relevant entries highlighted.58 He testified that during phase one he was
emailing each invoice and its associated documents to Mr Everett about a fortnight
after the work dates referred to in the invoice. Evidence given by Clinton Cheshire in
re-examination seemed to implicitly accept the invoices were sent via the post in
contrast to via email.59 Despite this variation in testimony and despite the absence of
exhibited copies of any covering letters or email communications annexing the
invoices, Clinton Cheshire’s assertion that the invoices were sent was credible.
[40] Clinton Cheshire explained he sent invoices to Mr Everett less regularly in phase two,
doing so only when Barry Cheshire told him to.60 That is unsurprising and fits the
different character of the commercial arrangement in play. As will be seen, phase one
was a conventional, work for pay engagement. Phase two was more speculative as to
payment.
[41] A suggestion put to Mr Cheshire, that all Cheshire Contractors had done was to bundle
timesheets and hand them over to Mr Everett, was rejected as untrue.61 Mr Everett
testified he did not receive any claim for payment from Cheshire Contractors during
phase one.62 It is not entirely clear whether this was meant to amount to testimony
that no invoices were received. Assuming it was, I in any event accept Clinton
Cheshire’s evidence that the invoices were sent to Mr Everett regularly during phase
one and infer they were in turn received by Mr Everett.
[42] Over two years subsequent to the conclusion of phase one, on 16 May 2013, Barry
Cheshire emailed Mark Everett setting out the costs of completing further works. His
email noted the “costs of work to date” was $643,870.50.63 Counsel for Mr Everett
54 T1-56 L30.
55 T2-53 L6.
56 T8-46 L11.
57 T1-77 L42.
58 T1-79 LL10-38.
59 T1-82 L20.
60 T1-80 LL1-13.
61 T3-19 L26.
62 T7-23 L37.
63 Ex 27 (also Ex 62).
-- 9 of 68 --
10
at one point seized upon this email in support of the notion that Cheshire Contractors
had not delivered any invoices to Mr Everett for phase one, a suggestion rejected by
Barry Cheshire.64 While Mr Cheshire could not recall why he had sent the email of
16 May 2013,65 Mr Everett’s memory was that the email was sent in response to a
request from him to know how much it would cost to complete the development.66
The content of the email, which is quite detailed about the future costs, is entirely
consistent with such a request. The email provides no implicit support for what turned
out to be an unconvincing attempt to contend invoices were not sent during phase one.
[43] The coup de gras to Mr Everett’s claims about not having received invoices were his
own words in correspondence by him with a solicitor acting in the settlement for sale
of a lot from Mr Everett’s property – lot one – to Mr Cheshire and others in 2014. In
that email of 22 July 2014 Mr Everett wrote:
“[J]ust a quick note to let you know that the balance of settlement will
be made up by work completed by Cheshire Contractors to the value
of $200,000 plus GST. I have been invoiced for this work and I am
happy for this to happen.”67 (emphasis added)
The above emphasised words were a reference to the phase one invoices. Mr Everett’s
remarkable explanation for those words was to maintain that in fact he had not
received invoices by that time and had merely written what Barry Cheshire had told
him to write.68 I reject that evidence.
Phase One Invoices
[44] The main particulars of the 12 invoices tendered in evidence in respect of phase one69
are as follows:
Date Invoice No Description Amount
30/07/2011 00300021 Multiple quantities of concrete
(listed).
$96,865.8870
31/07/2011 00300035 Machine & labour hire, as per attached
worksheets which list various work
performed by named personnel by
reference to numbered timesheets
from 04/07/2011 through to &
including 28/07/2011.
$ 19,219.75
15/08/2011 00300034 Pegs for & rolls of silt fence and dust. $ 1,345.97
64 T3-19 L22.
65 T4-7 L47.
66 T7-63 L4.
67 Ex 103.
68 T9-33 L14.
69 Ex 1 Vol 2 pp 236-312.
70 This is the total of the invoice’s nominated total sales amount of $88,059.89 plus its nominated GST
amount of $8,805.99, which should more accurately have been $8,805.99. The correct total is
therefore $96,865.88. The invoice’s “balance due” is “$0.00” – an unexplained anomaly.
-- 10 of 68 --
11
15/08/2011 00300039 Machine & labour hire, as per attached
worksheets which list various work
performed by named personnel by
reference to numbered timesheets
from 02/08/2011 through to &
including 31/08/2011.
$ 28,804.88
15/09/2011 00300697 Work performed at Hinchinbrook
Habitat listed in attached spreadsheet,
which lists various work performed by
named personnel by reference to
numbered timesheets from 01/09/2011
through to & including 15/09/2011.
$103,626.88
01/10/2014 00300688 Work performed at Riverviews Estate $110,500.50
30/09/2011 00300698 Work performed at Hinchinbrook
Habitat listed in attached spreadsheet,
which lists various work performed by
named personnel by reference to
numbered timesheets from 24/09/2011
through to & including 30/09/2011.
$106,647.75
30/09/2011 00300699 Work performed at Hinchinbrook
Habitat listed in attached spreadsheet,
which lists various work performed by
named personnel by reference to
numbered timesheets from 01/10/2011
through to & including 31/10/2011.
$100,502.88
30/09/2011 00300700 Work performed at Hinchinbrook
Habitat listed in attached spreadsheet,
which lists various work performed by
named personnel by reference to
numbered timesheets from 01/11/2011
through to & including 07/12/2011.
$ 20,900.00
01/10/2011 00300045 Various quantities of substances like
crusher dust, mortar & concrete listed
along with water truck hire &
transportation costs, charges for
multiple field density determinations
(5, 6 and 68 determinations), moisture
density relationship tests (5, 6 and 67
tests), soil tests (7 tests) as well as soil
testers.
$ 64,680.15
31/10/2011 00300083 Charges for construction equipment
such as excavator hire.
$ 10,511.53
01/01/2012 00300130 Guide posts, concrete pipes, headwalls
& soil tests.
$ 3,364.42
Total charge: $666,970.59
[45] Curiously invoice 00300688 is typewritten dated 1/10/2014 but there is also a
handwritten date of 31.8.11 on it. The timesheets annexed to it span from 16/08/2011
to 31/08/2011. While not the particular focus of argument this date anomaly was
borne in mind by me in nonetheless accepting the evidence that the above invoices
were rendered in the era of the phase one works.
-- 11 of 68 --
12
[46] It is evident that the early and latter above invoices related to the costs of various
equipment and supplies. The invoices for the physical works performed on site range
from invoice 00300697 of 15 September 2011, with its attached spreadsheet listing
active site work from 1 September 2011, through to and including invoice 00300700
of 30 September 2011, which lists active work on site through to 7 November 2011.
By then clean-up tasks were being performed, although a number of other
miscellaneous aftermath tasks evidently continued through the balance of November
into early December.
Phase Two Invoices
[47] The main particulars of the seven invoices tendered in evidence in respect of phase
two71 are as follows:
Date Invoice No Description Amount
27/08/2014 00300644 Progress claim 1 – Riverviews Estate
subdivision
$139,596.75
11/11/2014 00300027 LCJ Engineers - for professional
services rendered on consultation,
detailed design & documentation &
submission to Council for operational
works approval for Riverviews Estate
– Stage 1.
$ 77,147.40
26/11/2014 00300701 Work performed at Riverviews
Estate, listed in attached spreadsheet.
$396,236.45
26/11/2014 00300702 Work performed at Riverviews
Estate, listed in attached spreadsheet.
$ 53,532.97
26/11/2014 00300703 Work performed at Riverviews
Estate, listed in attached spreadsheet.
$118,775.25
16/01/2015 00300028 Professional fees for survey services
Progress Claim 4.
$ 30,022.08
03/03/2015 00300740 Surveying fees from G Pozzi. $ 62,598.40
Total charge: $877,909.30
[48] Of the above invoices for phase two the first, a reference to progress claim 1, does not
of itself indicate what the work claimed for involved. Invoice 00300701 dated 26
November 2014, while referring to “work performed”, annexed a variety of
supporting documents relating to the physical cost for equipment and services paid by
Cheshire Contractors to others. Invoice 00300702 of 26 November 2014 similarly
involved a description of “work performed” which was supported by documents in
respect of various costs of goods and services paid by Cheshire Contractors.
[49] Invoice 00300703 of 26 November 2014, which again referred to “work performed at
Riverviews Estate” attached a schedule containing multiple entries for “project
managing, marketing/advertising and accounting” spanning from 3 March 2014
through to and including 26 November 2014. It is readily apparent from this annexure
that the majority of the charges do not merely relate to the administrative costs of
71 Ex 1 Vol 2 pp 318-408.
-- 12 of 68 --
13
Cheshire Contractors managing the physical works it performed on the project. As
much is also implicit in the descriptions, “project managing” and
“marketing/advertising”. However, any doubt on the point is removed by the fact that
such descriptions of work appear throughout March, April, May and June,
substantially before the commencement of any physical works on site in early August
2014.
Monies allegedly outstanding
Phase one
[50] The total of the above listed invoices for phase one is $666,970.59.
[51] It is common ground that if such a sum was owing it was reduced by a credit of
$220,000 on 7 August 2014, that amount being applied in part reduction of an amount
owed for purchase from Mr Everett of lot one of his property by Mr Cheshire and
others (discussed further below). On Cheshire Contractors’ case this gives an
amended balance claimed of $446,970.59.
[52] However, in the course of the trial, as a result of the aforementioned ruling on a
separate question, there was a further reduction of the amount allegedly owed by
$96,000. This gives rise to a further amended unpaid balance claimed for phase one
of $350,970.59.
Phase two
[53] The total of the above listed invoices for phase two is $877,909.30.
[54] Pozzi Surveying’s claim for $62,598.40 for their services, constituted by their
progress claims 1 to 4, was invoiced in invoice 300740. However, progress claims 1
and 3, totalling $26,570, were also claimed in invoice 300702 and progress claim 4,
totalling $30,022.08, was also claimed in invoice 300028. This erroneous double
invoicing of three of the Pozzi progress claims necessitates a reduction of the invoiced
total by $56,592.08 to an amended balance claimed of $821,317.22.
[55] It is common ground Mr Everett made two payments to Cheshire Contractors, namely,
$139,596.76 on 18 September 2014 and $62,598.40 on 4 March 2015. Those
payments so coincide with the amounts and general timing of invoices 300644 of 28
August 2014 and 300740 of 3 March 2015 as to compel the conclusion they were
made in payment of those invoices. Those payments, totalling $202,195.16 should
also be deducted from the above balance claimed. So too should an amount of
$3,201.81 incorrectly invoiced for design fees.
[56] Making those reductions gives a further amended unpaid balance claimed for phase
two of $615,920.25.
-- 13 of 68 --
14
PART B - PHASE ONE ANALYSIS
Ph 1: An agreement is reached
[57] Barry Cheshire’s involvement in phase one commenced via a mutual acquaintance,
resulting in Mr Everett asking him to attend a meeting at Mr Everett’s house, located
on a hill of the property. He attended the meeting. Mr Everett, his nephew Glen and
his son Stephen were present, along with Owen Carter of LCJ, perhaps another
representative of LCJ, a number of persons from the local Council and Mr Everett’s
then project manager Mr Roselle, from an entity known as Empero.
[58] Mr Cheshire testified the purpose in him attending was to give an opinion to Mr
Everett. The opinion given was that the costs to Mr Everett proposed by Empero were
too high.72 On Barry Cheshire’s account, Mr Roselle was speaking of the project
being a full-blown subdivision with reticulated power and sewage and $1 million
worth of landscaping.
[59] Barry Cheshire testified Mark Everett asked him to look at Mr Everett’s Bill of
Quantities. Mr Cheshire subsequently did so and on his account forwarded Mr Everett
Cheshire Contractors’ hourly rate price list.73 Mr Everett testified he did not receive
such a document.74 It is obvious that he did - a copy of an email dated 12 July 2010
to Mr Everett attaching Cheshire Contractors hourly hire rates was exhibited at trial.75
[60] Mr Cheshire testified that “they” – apparently a reference to LCJ – forwarded a Bill
of Quantities to Cheshire Contractors for pricing in August 2010.76
[61] On 16 August 2010 Daniel Spencer from Cheshire Contractors emailed Mark Everett
enclosing Cheshire Contractors’ priced submissions schedule for the project.77 The
covering email said:
“Please find attached our price to complete works for Mount Cudmore
Road access and stage 1 for the abovementioned project. Please note
this price includes project management and landscaping.”78
[62] Notwithstanding the covering email’s reference to the price including “project
management”, the attachment, styled “Submissions Schedule Hinchinbrook Habitats
Mt Cudmore Access and Stage 1”, listed a variety of physical works of the kind to be
expected for a construction contractor but listed no specific project management tasks.
Barry Cheshire accepted that the total price of $1,239,156.05 quoted in the attachment,
was the price he had priced for the project (as distinct from the smaller component of
it which would become phase one).79
72 T2-39 LL1-27, T7-8 L34.
73 T2-40 L8, Ex 2 Tab 12 p 1.
74 T7-16 L38.
75 Ex 78.
76 T2-40 LL25-38.
77 Ex 14.
78 Ex 14.
79 T2-57 L38.
-- 14 of 68 --
15
[63] Mark Everett testified he was “pretty keen” on Cheshire Contractors’ pricing
submission of 16 August and told Mr Cheshire, “looks like you’re doing it”.80
[64] Barry Cheshire testified that in early 2011 he attended a meeting at Mark Everett’s
house with Mark Everett and Tony Duggan of NAB. Mr Everett’s recollection was
that the meeting occurred earlier, in August 2010.81 Mr Everett also testified Mr
Duggan said the lending value ratio of the land looked good and the bank would fund
the cost of building the access road and stage 1 of the development.82 Mr Everett was
aware of a valuation dated 1 April 2011 which valued the “as is” land value of the
property at $4,500,000.83 On Barry Cheshire’s recollection, Mr Duggan said the
lending value ratio of the property looked good and both Mr Duggan and Mr Everett
told Barry Cheshire that funding would be available for the works.84
[65] On Mr Everett’s account, when Mr Duggan left the meeting, Mr Everett informed Mr
Cheshire he could not afford to pay for works without the NAB providing funding.85
He testified that when Mr Cheshire subsequently told him they would soon be
delivering machinery to the property to start the works Mr Everett said he could not
pay without the bank funding whatever was done, to which Mr Cheshire allegedly
responded, “That’s okay. I’ll get started, and we’ll sort it out later”.86 I reject the
notion Mr Everett told or implied to Mr Cheshire that there was doubt hanging over
his capacity to fund the phase one works. Such evidence may have been more credible
if it had been given regarding phase two, when there was a speculative commercial
quality about Cheshire Contractors’ involvement. I accept the true position, as
evidenced by Mr Cheshire, is that Mr Everett represented he would have funding
available for the works. Phase one was a conventional engagement and Mr Cheshire
had no reason to embark upon it had he known there was a material risk of non-
payment.
[66] On Barry Cheshire’s account, Mr Everett asked Mr Cheshire in early 2011 to perform
the works on an “hourly hire and cost plus basis”.87 Mr Cheshire testified he discussed
with Mark Everett doing the phase one works on, what Mr Cheshire described as, a
“contract basis”, namely a lump sum or fixed price project, or an hourly rates “plus”
basis.88 He testified it was agreed the works would be performed on an hourly rate
for Cheshire Contractors’ equipment and labour, and any materials or services which
Cheshire Contractors had to pay for would be “cost plus the margin”.89
[67] Mr Cheshire explained it was Mr Everett who made the decision that the roadworks
would only go to the top of subgrade because of the expense of going higher.90
80 T7-9 L12.
81 T7-10 L7.
82 T7-10 LL20-33.
83 Ex 48 p 33.
84 T2-43 LL15-33.
85 T7-16 L15.
86 T7-17 L4, T8-40 L45.
87 T2-42 L18.
88 T2-40 L43.
89 T2-53 L30.
90 T2-51 L10.
-- 15 of 68 --
16
[68] On Mr Everett’s account there was no discussion at the meeting with Mr Duggan or,
implausibly, on any other occasion about what rates would be charged by Cheshire
Contractors.91 He later seemed to retreat from that position, conceding that Mr
Cheshire told him it would be cheaper to work on an hourly rate and cost plus.92
[69] Mr Cheshire testified he agreed with Mr Everett to build the road in to get access, up
to subgrade, according to LCJ’s plans, at an hourly rate and cost plus (terms explained
above), and any other work that was requested by Mr Everett.93 I accept that evidence
accurately states the oral agreement reached between the parties.
[70] The evidence was muddy as to the point at which the agreement was reached – there
were evidently multiple conversations. However, I infer it was by about 1 July 2011.94
On that date Owen Carter of LCJ emailed Barry Cheshire and Daniel Spencer
requesting insertions for a Bill of Quantities with blank rates,95 enclosing various
approvals for “implementation during construction” and inviting the arranging of a
prestart meeting.96 While the content of that email did not of itself dictate the terms
of any agreement as between Cheshire Contractors and Mr Everett, it is obvious Mr
Everett had given his agents, LCJ, authority to initiate activity calculated at getting
the phase one works underway. It is inevitable, for Mr Everett to have taken that
logistical step, that he must by then have reached agreement with Cheshire
Contracting.
[71] It is convenient to now deal with a number of additional terms and complaints raised
by Mr Everett in respect of phase one.
Ph 1 implied term: Works to be charged on a “cost plus” basis not exceeding the
Bill of Quantities?
[72] Mr Everett pleads:
“That the cost of the works were to be completed on a “Cost Plus”
basis that would not exceed the amounts specified in the Bill of
Quantities produced by LCJ Engineers …”.97 (emphasis added)
[73] I have already found the works were to be performed at an hourly rate and cost plus
basis.
[74] As to the works not exceeding the Bill of Quantities it is not entirely clear what
document the pleading means. Mr Everett testified the Bill of Quantities was a
document “that had to go to Council”.98 He went on to testify a Bill of Quantities,
dated 17 October 2011,99 “was submitted to Council as part of our operational works
91 T7-15 L40 – T7-16 L1.
92 T8-43 LL29-34.
93 T2-48 L40 – T2-49 L5.
94 The parties admit agreement was reached on or about that date.
95 Ex 4.
96 T2-45 L27.
97 Def [3c].
98 T7-9 L16.
99 Ex 1 Vol 1 Tab 8 p 11.
-- 16 of 68 --
17
application”.100 However Council’s operational works permit had been granted back
on 1 April 2011.101 Mr Everett retreated from his assertion when the anomaly was
pointed out to him.102 The evidence did not explain how a Bill of Quantities which
did not yet exist featured in some binding way in the agreement reached by 1 July
2011.
[75] True it is Mr Cheshire conceded he may have stated the works would not cost more
than the amount quoted in the Bill of Quantities, but he qualified this by explaining if
the volume of work contemplated by the Bill of Quantities was exceeded, then it
would cost more.103 He also explained they were not “working on a Bill of
Quantities”.104 I accept that testimony. Indeed, as much is inherent in the fact, already
found, that they were working at an hourly rate and cost plus. Further to those
considerations, it is in any event determinative of this point that Mr Everett requested
additional works, inevitably taking the potential cost beyond the province of the works
eventually alluded to in the Bill of Quantities. The evidence does not support the
inference it was agreed the cost of works would not exceed the amount calculated by
LCJ in a Bill of Quantities.
Ph 1 implied term: Exercise of reasonable skill?
[76] Mr Everett pleads it was an implied term of the contract for phase one that Cheshire
Contractors would, in the performance of services, “exercise the degree of skill,
expertise, diligence and foresight which would from time to time be expected of
reasonably skilled and competent contractors or suppliers engaged in similar civil
works and construction projects”.105
[77] Mr Everett pleads such a term was necessary to give business efficacy to the contract
and was so obvious as to go without saying. I agree it is an obvious implied term of
the agreement. An expectation of professional competence in performing the
contracted service is unremarkable. However, that expectation is necessarily confined
to the performance of the contracted service. That service was the performance of
civil construction works, not the overall management of the development project. I
do not accept the implied exercise of professional competence here extended to some
form of prescience in anticipating, or obligation to make up for, shortcomings in the
principal’s management or delegation of management of the development project.
Ph 1 implied term: Fitness for purpose?
[78] The defendant pleads it was an implied term of the contract for phase one that
Cheshire Contractors would provide services and materials that were reasonably fit
for the purpose for which they were supplied.106 The purpose pleaded was:
“…to supply an access road suitable for the promotion of presales of
lots 1-31 on the proposed subdivision and to serve as part of the works
100 T7-9 L34.
101 Vol 1 Tab 4 p 15.
102 T8-38 L40.
103 T2-53 L39 – T2-54 L16.
104 T3-14 L46.
105 Def [3h].
106 Def [3g].
-- 17 of 68 --
18
necessary to complete the proposed subdivision works in accordance
with the original decision.” (emphasis added)
[79] Mr Everett pleads the implication of the fitness for purpose term was necessary to
give business efficacy to the contract and so obvious as to go without saying. Cheshire
Contractors denies there was such an implied term.107
[80] Barry Cheshire testified, in respect of the need for the works to be “fit for purpose”,
the purpose that he undertook the works for was:
“To allow vehicle traffic, buyers to view the lots”.
[81] Mr Everett acknowledged in cross-examination that the road constructed by Cheshire
Contractors had been in place for in excess of five years and in use during that time,
including being used by Mr Everett to go to and from his house. He acknowledged
the road remains usable and that there had been no failure in it causing him to be
unable to use the road.108
[82] The difficulty with the fitness for purpose term contended for by Mr Everett is that it
goes beyond the readily inferred purpose of allowing vehicular access to view lots. It
enlarges the purpose as being to serve as part of the works necessary to complete the
proposed subdivision works “in accordance with the original decision”. Such a broad
term does not arise by implication. Whether the works, which were but part of the
proposed subdivision, were fit for such an enlarged purpose was not inevitably a
matter within the control of Cheshire Contractors. Cheshire Contractors was to
perform civil construction works, not manage the overall development. Whether the
works they were asked to perform met the purpose of the intended overall
development was the responsibility of the person or persons in control of the overall
development. If, as now discussed, Cheshire Contractors did not have that control,
then whether there was an implied agreement that its works were to in some specific
way accord with “the original decision” would depend on whether it agreed to meet
some specific requirement.
[83] To put the point another way, it is self-evident that the phase one works were intended
to be part of a broader project, but it was for the project’s principal to ensure those
works fitted the purposes of the broader project. If there was anything the principal
specifically wanted Cheshire Contractors to do to meet those purposes it was
necessary for there to be agreement on such specifics. To talk generally of the works
needing to be fit for purpose, without identifying the specifics now complained about
takes the matter nowhere.
Ph 1: Who was to be in control of the overall development?
[84] As Shannon Cheshire testified, it is usually a so-called “superintendent” who directs
works in a project of this kind.109 The defendant’s expert witness, construction
engineer Patrick Brady, of UDP Consulting Engineers, a firm involved in land
subdivisions in the Townsville region, explained in a project of the present kind the
107 Further amended reply to defence (“Reply”) [12].
108 T9-40 LL29-45.
109 T1-57 L10.
-- 18 of 68 --
19
contractor ought not also be the superintendent. He said that is because the
superintendent’s role is to oversee the performance of the work, ensuring its adequacy
of completeness and compliance which may require issuing directions from time to
time to the contractor.110
[85] Shannon Cheshire explained he regarded Mark Everett as superintendent because the
superintendent is the agent of the customer and the customer had not appointed an
agent111 and because Mr Everett was “on the job” almost daily and would go through
different tasks he wanted done with Shannon Cheshire.112
[86] Barry Cheshire agreed in cross-examination that the purpose of a superintendent is to
act as the principal’s agent in the administration of the contract.113 Later, in re-
examination, Mr Cheshire explained that in his experience the superintendent would
deal with Council and other authorities in relation to:
“Anything to do with the subdivision, as in test inspections,
environmental, anything that’s involved in that type of thing is dealt
with by the superintendent.”114
[87] As to who the superintendent was, Barry Cheshire claimed that person would usually
be the design engineer on subdivisions. He testified the superintendent’s role was
fulfilled by LCJ in both phases one and two.115
[88] Under cross-examination Barry Cheshire seemed evasive when asked whether there
were any conversations between him and Mark Everett in which Mark Everett said he
was going to appoint LCJ as the superintendent of the project. He eventually asserted
Mark Everett said LCJ was to be appointed as superintendent at the first meeting
which Barry Cheshire had with Mr Everett in mid-2010.116 It is unlikely there was
any such conversation at this first meeting, given it was a meeting where Mr Everett’s
then project manager Mr Roselle, from Empero, was present. It was not the sort of
meeting at which specifics as to who would be superintendent were likely to be
discussed and, on Barry Cheshire’s own account, it was only after that meeting that
he made the suggestion to Mr Everett that he could do the works less expensively.117
[89] In cross-examination it was put to Barry Cheshire that during the phase one works he
told Mark Everett he would supervise the works for Mr Everett and manage the works
for him, in response to which Mr Cheshire answered: “I said I’d help him.”118 It was
also put that it would have been up to Barry Cheshire to liaise with anyone in relation
to inspections and tests, to which Mr Cheshire responded, in apparent rejection of the
propositions, “Construction only”.119 He elaborated upon this response in re-
110 T4-40 L30, T4-41 L4.
111 T1-67 L37.
112 T1-57 L35 – T1-58 L8.
113 T3-3 L12.
114 T4-3 L40.
115 T2-92 LL38-46.
116 T3-3 L25 – T3-4 L13.
117 T3-4 LL14-30.
118 T3-4 L42.
119 T3-4 L45.
-- 19 of 68 --
20
examination, explaining there was liaison by Cheshire Contractors in the context of
their construction in as much as they contacted Council in relation to inspections.120
[90] It is noteworthy that in HSC’s operational works permit dated 1 April 2011 clause
8(a) of its conditions of approval provided, “Civil works must be constructed as per
the submitted drawings” and thereafter listed the specifications of various submitted
drawings by LCJ. This included LCJ’s drawing EVEA001 C01. As Cheshire
Contractors’ expert witness engineer, Darren Weir, highlighted,121 that drawing
includes the following:
“ROADWORKS AND EARTHWORKS NOTES
1. EARTHWORKS ARE TO BE CARRIED OUT IN
ACCORDANCE WITH “AS3798, GUIDELINES ON
EARTHWORKS FOR COMMERCIAL AND RESIDENTIAL
DEVELOPMENTS”, EXCEPT WHERE VARIED BY THESE
NOTES. CERTIFICATES OF ALL DENSITY TESTS TO THE
ENGINEER.” (emphasis added)
[91] As Mr Weir demonstrated, AS3798 contains a designation of personnel. Its s 1.3(d)
defines “superintendent”, for the purposes of the standard, as being “The principal’s
authorised person, sometimes referred to as the engineer or the architect.”122 The
same section refers to the “constructor” as “sometimes referred to as the contractor or
the builder”. This supports the conclusion Cheshire Contractors was not the
superintendent.
[92] It is also relevant to note that the defendant’s own expert engineer, Mr Brady,
acknowledged in cross-examination that it is for a principal to appoint a
superintendent.123 He said he would have expected such an appointment for a project
of this size.124 He testified that often the design engineer takes the role of
superintendent in a development contract.125
[93] Cheshire Contractors’ Project Management Plan may be of some relevance to this
issue. Mr Cheshire testified that prior to the prestart meeting Cheshire Contractors’
Project Management Plan was emailed to Council.126 That plan refers to the project
name as “Hinchinbrook Habitats Stages 1A”. Issue one of the plan was exhibited.127
Its title page is dated 26 July 2011, the day before the prestart meeting (the date at the
foot of the ensuing pages of the exhibit, prior to its attachments, is 16 August 2011,
but no point was taken about that anomaly).
[94] The Cheshire Contractors’ Project Management Plan was produced in-house by Nikki
Spencer of Cheshire Contractors.128 Barry Cheshire testified by way of explanation:
120 T4-3 L8.
121 Ex 39 p 22.
122 Ex 39 p 26.
123 T4-33 L26.
124 T4-33 L30.
125 T4-33 L35.
126 T2-46 L31.
127 Ex 1 Vol 2 Tab 13.
128 Ex 1 Vol 2 Tab 13 p 8 et seq.
-- 20 of 68 --
21
“The only way you can start the job is that you’ve got to have a Project
Management Plan to give to Council. And Mr Everett, obviously,
didn’t have a Project Management Plan.”129
[95] Cheshire Contractors’ Project Management Plan did not define many of the terms it
used, save for its annexed “Organisational Chart”, which named various of its own
staff as holders of various positions internal to its performance of its role in the project.
This included naming Mr Steve Camp, of Cheshire Contractors, as “Project
Manager/Engineer”.130 Contextually it is clear that designation of project manager
and engineer was internal to Cheshire Contractors, referring to Mr Camp managing
or engineering Cheshire Contractors’ works project, not managing or engineering the
broader development project in which the works were being performed. The chart
contains no reference to a superintendent. The Project Management Plan’s various
earlier references to position titles that are listed in the Organisational Chart, are
obviously to the holders of the positions which appear in the Organisational Chart, not
to persons external to Cheshire Contractors. On the other hand, it is equally obvious
the performance management plan’s references to the “principal” and the
“superintendent” are to persons external to Cheshire Contractors.131
[96] At a later stage of the Project Management Plan there appears an induction booklet
which begins:
“Job Number: MEV10710
Job Name: Hinchinbrook Habitats
Stage 1A
Project Address: Mt Cudmore Rd
Bermerside, Qld
Client: Mark Everett
Superintendent:
Superintendent
Representative:
PRINCIPLE
CONTRACTOR:
Cheshire Contractors
Pty Ltd
ENGINEER: LCJ Engineers”132
The plan’s induction booklet’s absence of any notation as to who the superintendent
or the superintendent’s representative was, begs the question who the reference is to
the superintendent in the earlier more substantive part of the plan?
[97] Barry Cheshire testified the references in the Project Management Plan to the
superintendent were, he believed, to the engineer.133 Mr Cheshire maintained he
believed LCJ acted as the superintendent in both phase one and two.134 He explained:
“[T]hey did the design. I believe they were working with Mr
Everett.”135
129 T2-46 L25.
130 Ex 1 Vol 2 Tab 13 p 26.
131 See, eg, [9.4] and [13.2].
132 Ex 1 Vol 2 Tab 13 p 31.
133 T2-47 L39, Eg Ex 1 Vol 2 p 180.
134 T3-2 L43.
135 T2-47 L25.
-- 21 of 68 --
22
[98] Barry Cheshire claimed the Project Management Plan’s reference to “the project
manager”136 was to Mark Everett, explaining:
“Well it’s his project. We work on an hourly hire…plus costs basis…I
don’t remember any of our invoices or anything that charged for a
project manager; if it wasn’t charged for, it wasn’t supplied.”137
[99] That was an obviously erroneous interpretation – as already explained, Cheshire’s
Steve Camp was listed in the plan’s organisational chart as Cheshire’s project
manager. Much of Barry Cheshire’s evidence of his opinion of the meaning of his
company’s Project Management Plan was of dubious admissibility. His opinions
were in any event valueless because they seemed to overlook the distinction between
Cheshire Contractors’ internal roles and the broader respective roles in the project of
Mark Everett, LCJ and Cheshire Contractors. For instance, while Cheshire
Contractors may have had its own project manager – that is to say an internal manager
of Cheshire Contractors’ performance of the works project it had been engaged to
perform – it does not follow that person was managing the overall property
development project for the principal, Mr Everett.
[100] In any event Cheshire’s Project Management Plan does not credibly support the notion
that Cheshire Contractors was to superintend or manage the development project. Nor
does any other aspect of the evidence.
[101] To the extent any appointment of a superintendent could arguably be said to be
supported by implication from the evidence it would support LCJ. On the known
evidence however, it seems clear there was no express appointment of a
superintendent. Control of the overall development remained in the hands of the
principal, Mr Everett. He evidently delegated a degree of that control to LCJ, but he
did not delegate that control, or the role of superintendent, to Cheshire Contractors.
Ph 1 implied term: Compliance with specific requirements?
[102] It is pleaded by Mr Everett to be a material term of the agreement that:
“The works were to be completed in accordance with the design
completed by LCJ Engineers Pty Ltd and the specifications endorsed
on the drawings recording the design (“the original design”).”138
[103] Cheshire Contractors’ reply admits that term “to the extent that such design is as
shown on the LCJ Engineers’ drawings referred to in condition 8(a) of the
Development Approval”.139 However it denies the need to comply with the
specifications in the drawings. That is on the basis that the specification for the works
and the scope of works to be completed relevant to LCJ’s drawings was limited to:
- construction of the road to subgrade level to the extent necessary to enable access
for potential buyers to present an expression of interest in purchase,
136 Eg Ex 1 Vol 2 p 19.
137 T2-47 LL7-13.
138 Def [3b].
139 Reply [7].
-- 22 of 68 --
23
- the stormwater and drainage works necessary to facilitate such construction of the
road, and
- the earthmoving and site clearing required to facilitate construction of the access
road and the stormwater and drainage works pending final construction. 140
[104] It is not suggested Cheshire Contractors were given any plans other than those in
LCJ’s drawings in entering into the agreement to perform the works. LCJ’s drawings
contained plans describing what the works Cheshire Contractors was engaged to
perform were supposed to achieve, save that the plans were for a broader
development, not merely the phase one works. It is reasonable to infer it was an
implied term of the agreement that the phase one works to be performed by Cheshire
constructions would be in accordance with the design described in the plans of those
works in LCJ’s drawings, insofar as the plans related to the phase one works.
However, the drawings were not an agreement. The extent to which specifications in
those drawings were for Cheshire Contractors to perform obviously depends upon
what was agreed. This is discussed further below.
[105] Mr Everett also pleads it was an express or implied term of the first contract that:
“I. the plaintiff was to undertake all liaison with local, state and
statutory authorities in respect of the completion of the work;
and/or
II. comply with the requirements of local, state and statutory
authorities in the completion of the work.”141
[106] Cheshire Contractors’ reply denies that such a term was an express or implied term of
the agreement.142
[107] Mr Everett pleads the term was necessary to give business efficacy to the contract and
so obvious as to go without saying. On the face of it, such an assertion is
unsustainable. It would obviously be necessary for Mr Everett to point to some more
specific aspect of what was agreed in support of such a term. It was not suggested
such a term was specifically discussed and agreed between the parties.
[108] Mr Everett’s particulars of this aspect of the pleading are:
“A. The defendant supplied drawings of the works to be
completed prepared by LCJ Engineers EVEA001-C01 to C36
in a way that in the circumstances communicated to the
plaintiff that the works were to be done in accordance with
the drawings and specifications contained in them. LCJ
drawing EVEEA001-C01 states in the general notes as note 4
“All liaison with local, state and statutory authority is the
contractor’s responsibility”.
B. The plaintiff prior to commencement of works produced a
Project Management Plan that included in it provision that
“works shall not proceed past a “hold point” until the
140 Reply [7] read with [6(c)].
141 Def [3i].
142 Reply [14].
-- 23 of 68 --
24
principal has released that hold point. Written evidence of
the release of the hold point will be kept by Cheshire
Contractors Pty Ltd”
C. In the premises, it must be inferred that the plaintiff and
defendant intended the plaintiff was to liaise with the
authorities in respect of inspections and the like necessary to
produce compliant works. …”143
[109] Again, such assertions are best considered in an issue specific way. That can be done
by recourse to the content of LCJ’s drawings and the Project Management Plan
alluded to in particulars A and B, as well as HSC’s operational works permit for the
project.
LCJ’s Drawings
[110] Barry Cheshire agreed that, for the phase one works, the LCJ drawings and the HSC
approvals set out the technical requirements for the work he had to do.144 Of the LCJ
construction drawings he agreed that Cheshire Contractors had regard to the drawing
notes, but not that part of the general notes which said:
“4. All liaison with local, state and statutory authorities is the
contractor’s responsibility.”145
[111] On the face of it, Cheshire Contractors was the contractor referred to in the above
quoted note. But care is required in drawing inferences as to contractual terms from
such notes given the obvious prospect of a disconnect between what the drafter
contemplates and what is agreed between contractor and principal. For instance, the
drawings’ roadworks and earthworks note 2 refers to “the superintendent”. This
reveals the drafter contemplated a superintendent would be appointed but says nothing
of what the principal actually did in that regard either.
[112] There was no express agreement between Cheshire Contractors and Mark Everett that
Cheshire Contractors would have a role in dealing with government authorities.146
Nor could such a role be inferred from the general nature of the engagement – as
already discussed Cheshire Contractors was not the superintendent or manager of the
development project. It does not follow as a matter of inference from general note 4
that Cheshire Contractors agreed to perform the role of “all liaison with local, state
and statutory authorities”. The words “all liaison” are so broad as to render such an
inference unrealistic and their meaning is not confined by any accompanying
definition. Moreover, such an implication is inconsistent with some content of HSC’s
operational works permit and Cheshire Contractors’ Project Management Plan, which
contemplate others being involved in such liaison. I reject the implication that the
general role imputed by general note 4 to the contractor was a role on which the parties
agreed. That is not to say that agreement to perform some specific tasks involving
some liaison does not arise by implication from Cheshire Contractors’ Project
Management Plan discussed below.
143 Def [3i].
144 T3-5 L33.
145 Ex 1 Vol 1 construction drawing sheet CO1.
146 T2-52 L36.
-- 24 of 68 --
25
Operational works permit
[113] HSC’s operational works permit, which identified the “applicant” as the Everett
Family Trust Pty Ltd, contained conditions at paragraph 8.147 These included at 8(a)
that, “Civil works must be constructed as per the submitted drawings”, which
drawings were listed as including LCJ’s drawings. Further, paragraph 8(g) required,
“A Certificate of Completion is to be supplied by the Superintendent as works are
finalised”.
[114] Paragraph 8(f) of the conditions of approval provided:
“The applicant is required to submit a “Test and Inspection Plan”
which includes “Hold Points” requiring Council’s approval prior to
progressing works beyond the nominated points for the following
stages of work:-
(i) At the completion of subgrade works prior to commencing
the placement of base layers;
(ii) At the completion of pavement prior to priming;
(iii) Prior to the installation of stormwater pipes, kerb and channel
and inverts;
(iv) Prior to backfilling sewerage mains and structures including
inspection openings and manholes;
(v) Prior to the backfilling of water mains, valves and hydrants;
(vi) Prior to backfilling all stormwater pipes and culverts;
(vii) At practical completion to allow for the preparation of a
defects list prior to the commencement of the main list
liability period…”
[115] The reference to the “applicant” therein was to the Everett Family Trust Pty Ltd. Mr
Everett was the trustee148 and his case was conducted in implicit acceptance that he
was the representative of the applicant. The permit’s requirement that the applicant
submit a test and inspection plan to Council was effectively a requirement for Mr
Everett to fulfil.
[116] On 1 July 2011 Owen Carter of LCJ emailed Barry Cheshire and Daniel Spencer inter
alia attaching “Council, DERM and EPBC approvals…for your implementation
during construction” and noting, “Council has addressed the hold point on the jobs on
which they wish to inspect as well as ourselves”.149 Barry Cheshire confirmed in his
testimony that the email did annex the relevant approvals. He confirmed the prestart
meeting, to which the email of 1 July 2011 referred, did occur although Mr Cheshire
did not go himself.150
[117] On 15 August 2011 Hinchinbrook Shire Council wrote a letter to Owen Carter of LCJ
in terms commencing:
“Thank you for recently meeting onsite with Council’s Manager
Engineering Services, Bruce Leach, and Infrastructure Engineer,
147 Ex 1 Vol 1 Tab 4 p 16.
148 T4-56 L8.
149 Ex 4.
150 T2-45 L27.
-- 25 of 68 --
26
Jenna Devietti, at the abovementioned location on Wednesday, 27th
July 2011, to discuss operational works for the Hinchinbrook Habitats
development.”151
[118] The letter acknowledged receipt of the “Hinchinbrook Habitat stage 1A Project
Management Plan and revision E construction plans, which were delivered onsite”. It
went on to ask, “Please ensure you allow adequate time when requesting Council
undertake an inspection of the hold points” and again set out paragraph 8(f) of the
conditions of approval of operational works. 152
Project Management Plan
[119] As earlier mentioned, Cheshire Contractors’ Project Management Plan,153 was
provided to HSC. Cheshire Contractors well knew it was a document others would
act upon as representing how Cheshire Contractors would perform the works. To the
extent that plan represented what Cheshire Contractors would do in carrying out the
works it is reasonable to infer it was an implied term of its agreement with Mr Everett
that it would do those things.
[120] The performance management plan deals with “Quality” in part 9. Part 9 provides,
inter alia:
“9.2 Inspection and Test Plans
Providing high quality work that satisfies or exceeds our clients’
expectations is our main goal. Inspection and test plans (ITP’s)
generally include observations, measurements and/or tests at Cheshire
Contractors Pty Ltd’s facilities. The project manager will be
responsible for arranging all tests and inspections on the project.
Frequencies for inspection and testing will be outlined in the
inspection and test plans (ITP’s) in appendix M. …
9.4 Hold Points
Work shall not proceed past a “Hold Point” until the Principal has
released that Hold Point. The Project Manager is responsible for
ensuring that the Principal is given sufficient advance notice of Hold
Points.
Written evidence of the release of a Hold Point will be kept by
Cheshire Contractors Pty Ltd.
9.5 Contract Requirements
A list of contract specifications, legislation, approvals, licences and
permits relevant to this contract have been provided in appendix N.
Any obtained licences and permits will also be filed in appendix N,
once obtained. …” (emphasis added)
The appendices to the Project Management Plan appear to be included with the
exhibit, albeit not marked with an appendix number.
151 Ex 5 (also part of Ex 64).
152 Ex 5.
153 Ex 2.
-- 26 of 68 --
27
[121] It is not in dispute that Cheshire Contractors’ project manager did not gather written
evidence of the release of hold points by the principal. 154 The principal was Mr
Everett. It will be recalled he was on the job daily. He was in a position to witness
the progression of the works. There is no suggestion he intervened or did not approve
of the progression of the works.155 Whether there were hold points reached to require
his release is returned to hereunder.
[122] The inspection and test plan, inferentially appendix M, contains a table itemising
various elements of work against which appear entries regarding witness and hold
points under the heading “Engineer’s responsibilities” and the heading “Council’s
responsibility”.156 The entries in the Project Management Plan’s inspection and test
plan identify the following potentially relevant elements of work and responsibilities:
“Elements
of work
Engineer’s
responsibility
Council’s
responsibility
Subgrade
Compaction
CBR tests (if
ordered)
Horizontal
and vertical
alignments
Profile
Routinely visit
site. HOLD
POINT. Attend
during proof
rolling.
Examine and
assess all test
results and cross
section
geometry.
Forward to
Council for
approval.
Visit site for
random audit
inspections.
HOLD
POINT Joint
inspection
during proof
rolling.
…
Stormwater
drainage
Location of
structures
SL & IL of
structures
Material
quality
Manholes
Drain lines
Backfilling
HOLD POINT.
Visits to assess
compliance and
to view progress
and works.
WITNESS
POINT.
Visit site for
inspection
prior to
backfilling,
laying of pipe
and
bedding.”
[123] It follows that Cheshire Contractors’ project manager was responsible for arranging
the inspections contemplated by that table. Whether that occurred is in issue.
[124] After the inspection table, the appendix contains a table of “test requirements”, therein
detailing the relevant “construction activity”, “verification requirement – test
description”, “test method”, “test frequency”, “specification” and “minimum no. of
154 T1-69 L10, T3-5 L28.
155 T8-45 L38.
156 Ex 1 Vol 2 Tab 13 pp 180-182.
-- 27 of 68 --
28
test number”.157 These are the requirements to be met by the testing which was to be
carried out by Cheshire Contractors’ project manager. For present purposes it is
sufficient to describe the relevant testing as compaction testing. Whether compaction
testing occurred as contemplated by the table is also in issue.
No loss occasioned
[125] Issues about compliance breaches in phase one are a relatively recent development in
this case. It is noteworthy that even as recently as an emailed statement by Mark
Everett directed to his son Stephen to help in the settling of the initial defence of this
case,158 Mr Everett expressed no concerns that there had been a failure to comply with
specifications during phase one. He wrote:
“It should be noted that the first access road was built to Council’s
specs after we had operational works approval. The second stage has
not been checked by Council nor has any testing been carried out. The
work was all but complete before we had operational works approval
and all of the pipes and driveways have to be pulled up and redone as
they are only temporary to try and get presales as per Cheshire’s
instructions.” (emphasis added)
[126] Mr Everett conceded he did not have any discussions with Mr Cheshire in the early
days of the project about testing and inspections159 or about liaising with local
authorities.160
[127] The debate about inspection and testing of works in respect of phase one had a surreal
character. The fact is that the development stalled and even by the time of trial, years
after the completion of subgrade, there is no evidence of the development being
sufficiently completed for it to meet the requirement of the development approval. As
Mr Weir observed, the lapse of time is such that some further trimming and testing of
the works would now be required to meet the requirements of the development
approval.161 I accept that evidence.
[128] It is convenient here to consider the attempt via Mr Brady to undermine the evidence
of compliance with testing and inspection and its consequences. The evidentiary
foundation for many of Mr Brady’s opinions was not identified. Mr Brady’s expert
report162 outlined various opinions premised upon some assumptions about
contractual terms. The value of his opinion is necessarily influenced by whether there
were in fact contractual terms of the kind upon which his opinions are premised.
Notably his opinion imports the AS4000 general conditions of contract. It was no part
of the expressed or implied terms of any agreement between Mr Everett and Cheshire
Contractors that it included the general conditions of contract contained in AS4000.
157 Ex 1 Vol 2 Tab 13 pp 183-187.
158 Ex 67, T8-4 LL25-35.
159 T8-44 L2.
160 T8-44 L10.
161 Ex 39 p 2 [10],
162 Ex 42.
-- 28 of 68 --
29
[129] A significant aspect of Mr Brady’s opinion is that, because of the absence of
documentation of the inspection process, the works are unlikely to be accepted by
HSC as complying with its approvals. Mr Brady does not purport to express any
opinion as to whether any of the material supplied by Cheshire Contractors was fit for
purpose. He accepted that the phase one works were fit for purpose, if their purpose
had been to allow potential purchasers access to the site.163 To the extent he expresses
an opinion that the works are not fit for purpose, it is by reason of his view that the
absence of documentation of the inspection process or of a statement of compliance
makes it unlikely HSC will accept the works are compliant.164
[130] That opinion’s reference to the absence of a statement of compliance is a distraction
– such a statement was the responsibility of a superintendent, not Cheshire
Contractors, per paragraph 8(g) of the operational works permit. The foundation for
the opinion arising from the absence of documentation of the inspection process is
lacking in a number of ways.
[131] Firstly, there is no evidence that the Council regards the works as uncompliant.
Indeed, the phase one works did not advance the development to the point where
Council has had to form a final view of the matter. Evidence from James Stewart, an
executive manager from Hinchinbrook Shire Council, called as a witness by Mr
Everett, fell well short of demonstrating Council regards the works as non-compliant.
In an email to Mr Everett of 9 March 2016 Mr Stewart alluded to having driven on
the road at the development and having concerns about its condition and compliance
with construction drawings. The truth of this aspect of the email was not sought to be
proved by evidence-in-chief but in any event it was neutralised in cross-examination
when Mr Stewart conceded the road’s condition was of an acceptable standard given
how long ago it was built and allowing for wear and tear in the meantime.165
[132] Secondly, Mr Brady’s view as to the likelihood of what Council may or may not do
is premised, by reason of what he understands to be the advice of James Stewart, on
Council taking the view that no compliance inspections were requested or undertaken.
As is soon explained, that is not supported by Mr Stewart’s evidence. Thirdly, there
appears to be no evidence of an absence of Council’s records of it conducting
inspections during the phase one works.
[133] In Mr Stewart’s email to Mr Everett of 9 March 2016166 he indicated he could not
locate evidence that conditions (c), (e), (f) or (g) of the operational works permit
issued on 18 October 2014 had been addressed and complied with and could find no
record of inspections requested or carried out in accordance with condition (g) of that
permit. Mr Stewart confirmed the truth of those propositions in his testimony,
although he acknowledged having found some further documents relevant to the
project since his email.167 None of this however related to any search for records of
inspections requested or carried out in accordance with the conditions of the
operational works permit issued in 2011. In short it was evidence relevant to the phase
two works.
163 T4-31 L20.
164 T4-30 L43 – T4-31 L7.
165 T4-22 L46 – T4-23 L13.
166 Ex 41.
167 T4-20 L35.
-- 29 of 68 --
30
[134] Its relevance even to phase two was neutralised when it emerged in cross-examination
that Mr Stewart’s inability to find records of inspections having occurred did not mean
the inspections had not occurred. He confirmed the accuracy of what he had
previously said in an affidavit on the topic to the following effect:
“The results of that review have failed to locate records of inspections
having been performed. That is not to say that they were not
performed. The relevant staff members whom should have been
tasked for that function are no longer employed by Council, and it is
thus not possible to confirm with certainty the status of the record of
inspections. … I am thus unable to state with certainty that inspections
were done or not done. All I can say that on my review, I have not
been able to locate records of such inspections.”168
It is unknown whether, like Mr Stewart’s email, that affidavit related to an attempt to
locate records relevant to compliance with the conditions of the 2014 operational
works permit.
[135] Further to all of this, Mr Brady accepted in cross-examination that normally when a
Council inspector attends an inspection of works of the kind with which this case is
concerned, the inspector does not leave the contractor with documentary evidence of
that inspection.169 He also acknowledged in cross-examination that, whilst rare, it
does happen that Council inspectors contacted by a contractor with a request to attend
site for an inspection may indicate they cannot soon attend but that the works can keep
going rather than being held up waiting for the inspector.170
[136] My very strong impression of the evidence overall is that the quality of the product
provided by Cheshire Contractors was good, that is, I am satisfied Mr Everett received
the product he bargained for. If any shortcomings regarding testing and inspection
were to be causative of loss it would be that because of them Council would not
approve the development or further development without requiring remedial action.
There is no evidence from Council to indicate their actual position. Mr Brady’s
opinion that Council lacks documentation of the process is without evidentiary
foundation. Thus, the premise for his opinion that Council would likely require
substantial repetition of the works because of no documentation, is missing. Further,
his prediction of what Council would do is itself bereft of an identified foundation,
that is, the basis for him being able to forecast what Council will require is not
explained.
[137] The apparently satisfactory quality of the works makes it inherently unlikely that
remedial action required by Council would in all seriousness be the removal of the
works so that they may be started again from scratch. The much more probable
scenario, consistent with Mr Weir’s evidence, is that regardless of how satisfactory
Council understands the old testing and inspection process was or was not, Council
would in any event, because of the lapse of time, request the tidying up and testing of
the works as they now present.
168 T4-22 LL11-24.
169 T4-31 L30.
170 T4-31 L45 – T4-32 L2.
-- 30 of 68 --
31
[138] It is fatal to Mr Everett’s recently conceived complaints that even if the alleged
compliance breaches are proven they have occasioned no loss and are not of such
magnitude as to avoid the contract. While this is sufficient to dispense with Mr
Everett’s complaints I will nonetheless deal with their substance.
Ph 1: Did Cheshire Contractors comply with inspection notification and hold
point requirements?
Inspections
[139] Shannon Cheshire testified he would give LCJ and Council notice when Cheshire
Contractors was going to dig or lay stormwater piping.171 On his account, he would
phone Council and LCJ and sometimes Council would opt not to come with its
representative saying that they were too busy, however LCJ would come every
time.172
[140] On Shannon Cheshire’s account, Council and or LCJ would, when inspecting, just say
the work was fine and to continue.173 He testified he received no documents from
Council or LCJ when they conducted their hold point inspections.174 Mr Johnstone of
LCJ testified LCJ “completed inspections” during construction in phase one.175 He
explained he had seen records of such inspections held by LCJ.176
[141] As simple as the evidence of compliance with inspection notification requirements
was, it was credible. It was not contradicted, for instance by evidence from any
employees or former employees of LCJ or Council.177 It will be recalled Mr Johnstone
from LCJ gave evidence but he had no active involvement in phase one.
[142] I accept Cheshire Contractors did comply with its obligation to arrange inspections by
LCJ and Council during the phase one works.
Hold points
[143] There are two relevant hold points in issue – subgrade compaction and stormwater
drainage. It will be recalled it was for Cheshire Contractors to ensure work did not
proceed past a hold point until it was released by the principal, and to keep a written
record of the release. The engineer and Council were to inspect proof rolling of the
subgrade and inspect/witness stormwater drainage prior to backfilling.
171 T1-59 L40 – T1-60 L5.
172 T1-65 LL15-45.
173 T1-66 L4.
174 T1-66 LL15-20.
175 T2-7 L5.
176 T2-7 L29.
177 Evidence adduced from HSC’s James Stewart related to the 2014 operational works permit though in
any event it was of neutral consequence on this issue.
-- 31 of 68 --
32
[144] Firstly, as to stormwater drainage,178 it is apparent that work did progress past the
relevant hold points. There appears to be no specific evidence of the principal
releasing hold points or records of the release but I accept the above-mentioned
evidence that LCJ and Council were notified when Cheshire Contractors was going
to dig or lay stormwater piping. If the failure to seek and document the principal’s
release of hold points be a breach the measure of damage would be the amount
required to remedy any defect arising.179 There is no evidence to suggest the works
are per se defective so that the only potential damage arising would be the cost of
rectifying the works in the event Council required them to be re-done in whole or in
part because of a lack of documented release of hold points by the principal. I am
unpersuaded that is likely.
[145] Secondly, as to subgrade, Barry Cheshire explained of the inspection and test plan
within Cheshire Contractors’ Project Management Plan180 that the hold point relevant
to subgrade is the point when subgrade is reached. He explained it is after that and
before the next layer is going down, usually the day before, that proof rolling
occurs.181 His point was that Cheshire Contractors had not proceeded past the relevant
hold point in respect of subgrade. Shannon Cheshire testified to similar effect. 182
[146] Mr Brady agreed that the carrying out of inspection and testing required to release a
hold point is part of the next phase of work in the sense that the works should not
progress further until the hold point has been released.183
[147] Mr Brady’s supplementary report, responding to Mr Weir’s opinions, inferred that
completion of the works to subgrade level would include the compulsory inspection
of those works by Council but provided no real foundation for that inference. Indeed,
he conceded that ordinarily inspection of subgrade would occur before the
commencement of the next phase, namely the laying of the base layers.184 He
acknowledged that for the testing and approval of the subgrade to be required at the
completion of subgrade as distinct from prior to progression beyond subgrade, there
would need to be a contract specific term providing for it.185 There was no such
contract specific term here. Mr Brady accepted that proof rolling, which is part of the
inspection of subgrade process, is done just prior to the commencement of pavement
work so that if there were to be a gap in time between completion of subgrade and
commencement of pavement, it would be appropriate to defer the hold point
inspection until the proof rolling occurs immediately before the commencement of the
paving layer.186
[148] On the face of it, the hold point inspection of subgrade was unnecessary because the
works did not progress beyond subgrade. However, Mr Cheshire testified that the
transportation of the Abigroup fill onto site caused difficulties including with dust
178 Some, not all, of the stormwater drainage work is amongst works excluded from consideration in the
answer to the separate question determined during the trial.
179 Bellgrove v Eldridge (1954) 90 CLR 613.
180 Ex 1 Vol 2 p 180.
181 T2-84 LL15-40.
182 T1-71 L7.
183 T4-42 L40.
184 T4-43 L33.
185 T4-43 L39.
186 T4-44 L20.
-- 32 of 68 --
33
control as a result of which Cheshire Contractors applied a 70 mil minus gravel
running surface to the road.187 Mr Brady expressed the opinion that putting a gravel
running surface on top of the subgrade would constitute work proceeding beyond the
subgrade hold point.188 I reject this. There is no evidence to suggest the gravel applied
for dust control involved the actual commencement of the paving layers above
subgrade or that it would prevent the ability to conduct proof rolling (whether over it
or after sweeping it off).
[149] For completeness I note there are references in LCJ’s Bill of Quantities of 17 October
2011 referring at [2.5.2] and [5.8.2] to the application of subbase having occurred.189
The tendering of documents by consent, as occurred with this document, does not
overcome the need for such documents to be explained. If Mr Everett was serious
about this issue he hardly needed to rely on some unexplained documentary anomaly.
There still exists the road in question. Mr Everett could easily have gathered direct
evidence about the surface of his road. That did not occur. Even assuming these
references to “subbase”, now emphasised by Mr Everett’s counsel, are to some layer
above subgrade, they are at odds with and do not cause me to doubt the weight of
testimony that subgrade was not passed in any material sense.
Ph 1: Did Cheshire Contractors comply with test requirements?
[150] Compaction testing in phase one was conducted by Soil Engineering Services
(“SES”). Shannon Cheshire testified during the works at certain stages of layer
depths he would call in SES to conduct tests.190 He explained the need for testing was
indicated by the testing plan which was part of Cheshire Contractors’ Project
Management Plan.191
[151] Mr Brady and Mr Weir have reviewed the supplied testing results.192 Mr Weir opined
all but one of the tests met the minimum compaction requirements outlined in the
Inspection and Test Plan. I infer from his evidence that Cheshire Contractors likely
did meet their testing obligations under their Project Management Plan.
[152] Mr Brady noted the test results do not include ground surface compaction (pre-road
fill) results. He opined there should have been a minimum of 63 tests, though
acknowledges 70 were provided. He noted 10 compaction tests were undertaken for
allotments 1 to 5 and no results were provided for 6 to 10. He opined seven of the
allotment tests were unsatisfactory because they did not adequately identify the test
location or level. As to the 60 road compaction tests he opined one failed to achieve
the minimum compaction standard of 97 per cent, one was taken at a chainage outside
the supposed contract area and 12 are unsatisfactory because they did not adequately
identify the test location or level.
187 T4-8 L25.
188 T4-55 L4.
189 Vol 1 Tab 8 pp 3, 6.
190 T1-58 LL16-25.
191 T1-58 L41 – T1-59 L3.
192 Ex 42 pp 15, 16; Ex 39 p 31.
-- 33 of 68 --
34
[153] In short, the bulk of the reports attracting Mr Brady’s criticism result from his opinion
they do not adequately identify the test location or level. No attempt was made to
explain the foundation for this opinion, for instance by reference to the exhibited
results (which appear detailed), and I accord no weight to it. I found Mr Weir’s
opinion to be a more reliable assessment.
[154] Mr Brady’s response to Mr Weir’s opinion was to generally assert in disagreement,
again without foundational explanation of the deficiency, that the testing was not
sufficient in accordance with the Development Approval and LCJ Engineers design.
He went on to say:
“[T]he testing appears to have not been supervised or directed in
accordance with the requirements of AS3798 and there is no as
constructed information provided to show the works have been
constructed to the correct levels and alignment as per the LCJ
Engineers design.”
[155] It is not apparent how the provision or non-provision of as constructed survey
information bears upon adequacy of testing. That may have been a comment directed
at another issue. As to the requirements of AS3798, they are relevant to the present
issue but not in a way which helps Mr Everett.
[156] It will be recalled LCJ’s drawings contain a note requiring earthworks to be carried
out in accordance with AS3798 guidelines. When cross-examined about those
guidelines193 Mr Brady acknowledged the standard at page 29 contemplates two
different levels of potential testing by its clause 8.2, “8.2 level 1 inspection and
testing”, and 8.3, “8.3 Level 2 sampling and testing”. He agreed the LCJ drawings
did not specify which was the applicable level194 but accepted, by reference to LCJ’s
Bill of Quantities, that it was clause 8.3, not clause 8.2, of the Standard which was
relevant here.195 Clause 8.3 provides:
“8.3 Level 2 sampling and testing
A geotechnical testing authority (GTA) will be appointed to carry out
sampling and testing as required or specified. The GTA is responsible
for selecting the location of sampling and testing operations within
each visit made to the site. The superintendent is responsible for
advice as to when such visits are required and is responsible for
ensuring that sufficient samples and tests are taken over the project.
On completion of the earthworks, the GTA may be required to provide
a report, setting out the sampling and testing it has carried out, and the
locations and results thereof. The GTA will not be in a position to
express any opinion beyond this as to the compliance of the works
with the specification or their suitability for any particular purpose.”196
[157] Mr Brady’s report asserted that compaction testing of the subgrade by a registered
geotechnical testing authority is required to be submitted by the contractor and
193 Ex 44.
194 T4-35 L45.
195 T4-36 LL8-21.
196 Ex 44 p 29.
-- 34 of 68 --
35
verified by the superintendent as compliant with the design and specification.197
However it is clear that clause 8.3 of the earthworks Standard does not require the
superintendent to verify the testing. Rather it is for the superintendent to co-ordinate
and ensure the occurrence of sufficient testing.
[158] Mr Brady acknowledged that, pursuant to clause 8.3, if the Standard was followed
correctly, it is the superintendent who would advise when the visits are required and
who was responsible for ensuring sufficient sampling and testing occurs.198 He
acknowledged in the absence of some contract specific requirement the task of
ensuring compliance with AS3798 fell to the superintendent.199 Clause 8.6 provides,
“In cases where a GTA is employed for level 2 supervision only, the statement of
compliance is the responsibility of the superintendent.” While Mr Brady noted the
GTA, which in this case was SES, could provide a statement of compliance,
responsibility for the provision of a statement of compliance fell to the
superintendent.200 Mr Weir reiterated in cross-examination that a statement of
compliance is provided on completion of works.201
[159] Mr Brady also accepted that the test reports from SES were, of their general nature,
sufficient to satisfy the requirements for reporting in clause 8.3 of the earthworks
Standard.202 The earthworks Standard also makes provision for the frequency of field
density tests in respect of type 1 earthworks which these earthworks were.203 Mr
Brady agreed that the testing and inspection plan in Cheshire Contractors’ Project
Management Plan for phase one satisfied the Standard’s relevant requirement for
frequency of field density tests.204
[160] The failure to have a superintendent to have ensured compliance with AS3798’s was
no fault of Cheshire Contractors. It might be thought that omission would be more
likely to trouble an official considering testing compliance requirements than the one
unsatisfactory test of the many arranged by Cheshire Contractors consistently with
their testing plan in their Project Management Plan.
[161] Further to all of this Mr Weir opined that satisfaction the work is complete and meets
the requirements in AS3798 can be achieved through visual assessment, test rolling
surveillance and the relative compaction testing.205 He emphasised it remains the case
that the subgrade, which is the material being tested, is still available, albeit after
exposure to weather for some years. So, the testing for compaction can still occur,
along with visual assessment and test rolling, so that the opportunity to test and prove
and gain satisfaction has not passed.206
197 Ex 42 p 7.
198 T4-38 L2.
199 T4-38 L11.
200 T4-38 LL25-40.
201 T3-76 L8.
202 T4-39 L20.
203 Ex 44 p 31, T4-36 L35.
204 T4-36 L45.
205 T3-77 L13.
206 T3-77 LL12-33.
-- 35 of 68 --
36
[162] None of this aids Mr Everett’s arguments. In any event I am satisfied that Cheshire
Contractors did not breach the testing obligations assumed by them in their Project
Management Plan.
Ph 1: Other complaints
[163] Other remaining complaints can be dispensed with briefly.
[164] Mr Everett pleads that in breach of the implied terms207 as to the quality of the services
to be provided, Cheshire Contractors failed to obtain and supply “as constructed”
survey information.208
[165] The particulars of this breach plead that without an as constructed survey it would not
be possible for persons to know whether the works had been completed in accordance
with the original design and thus know that they were fit for the purpose of serving as
part of the works necessary to complete the proposed development. The alternative
particular pleaded is that a contractor exercising reasonable skill would have ensured
as constructed surveys were completed and provided to Mr Everett.
[166] I am unpersuaded of the existence of the implied term. Mr Everett conceded he had
no discussions with Cheshire contracting about the provision of as-constructed survey
information during construction.209 Barry Cheshire testified:
“There was no reason to have an as constructed survey at that stage
of the job.”210
He explained the obligation to provide “as built data” or “as constructed information”
had not arisen because the need for “as constructed” plans is when the sealing and
approval of plans by Council is to occur. He explained they had such data stored
electronically so that it would be available when the relevant need arose in the
future.211
[167] Mr Brady agreed that in the course of a normal construction contract, the as-
constructed survey information is usually compiled towards the end of the job so it
can be reviewed by the superintendent and ultimately supplied to Council.212 As to
whether a provision of such information ought have occurred earlier in this particular
project, Mr Brady acknowledged that would depend upon the scope of work or the
reduced scope of work.213
[168] In Mr Brady’s supplementary report he asserted that the testing and as-constructed
information is required to be supplied by the contractor at the time of submitting a
payment claim for the works and not at the end of the project.214 However, Mr Brady
207 The implied terms are nominated as those pleaded in [3f and g] but the reference to “quality of the
services” suggest they were probably meant to be those in [3g and h].
208 Def [4A].
209 T8-44 L39.
210 T2-93 L13.
211 T2-85 LL4-36.
212 T4-44 L35.
213 T4-44 L40.
214 Ex 43 p 3.
-- 36 of 68 --
37
conceded he was there talking about payment claims made progressively by
contractors on projects where the payment claims claimed a percentage of completed
project works.215 He conceded the position was less clear where a contract involved
payment by reference to hourly rates where there is no inherent requirement for the
progressive supply of as-constructed information, explaining it would depend upon
the terms of the contract.216 There were no terms of the contract here requiring such
progressive supplies of as-constructed information.
[169] Mr Weir disagreed with Mr Brady’s implication that the absence of an as-constructed
survey was problematic because the development works were incomplete.217 He
rejected the proposition that the absence of an as-constructed survey ought result in
the view that the works cannot be valued and are thus valueless. He went on to say:
“I’d say there’s clearly value in the works. There’s been a large
amount of work completed based on the records that I’ve seen and
they’re – up until the recent footage that I’ve seen, at least, they’re –
they’re serving a purpose as – albeit uncomplete, as a road.”218
[170] Even Mr Brady acknowledged the road built by Cheshire Contractors had been in
place and in use over a number of years and that there must be some value to it.219
[171] Mr Weir emphasised that both of Council’s operational works permits required a
superintendent to supply a certificate of completion prior to release of the survey
plan.220 As to the need for a superintendent to be satisfied the progressive compliant
steps required had been taken, Mr Weir noted the Council did not describe what the
certificate of completion was to include but suggested it would require an indication
the works had been completed in accordance with technical drawings and
specifications.221
[172] Finally, there was in summary an allegation of overcharging premised upon Mr
Brady’s evidence. Mr Brady acknowledged, while he was briefed to provide an
opinion on the estimate of costs of Cheshire Contractors doing the work and supplying
any materials, he did not provide such an opinion.222 Rather, the assessment contained
in his opinion is based entirely upon the Bill of Quantities.223
[173] The Bill of Quantities does not provide a record of the work performed and charged
for, nor, for reasons already explained, were the works confined to those contemplated
by the Bill of Quantities.
[174] Mr Brady acknowledged that while he had been briefed to provide an opinion
assuming additional works were done beyond the scope of the LCJ plans, he did not
215 T4-45 L8.
216 T4-45 L12.
217 T3-72 L22.
218 T3-72 LL20-36.
219 T4-52 L22.
220 T3-69 L20.
221 T3-70 L10.
222 T4-47 L4.
223 T4-47 L9.
-- 37 of 68 --
38
take any additional works into account in respect of either phase.224 He conceded, in
forming his opinion as to the value of work performed, he had no regard to the number
of hours of labour and equipment use.225
[175] The exercise carried out by Mr Brady does not support a complaint of overcharging.
I am satisfied Cheshire Contractors charged for phase one works in accordance with
the agreed rates.
Everett liable to pay for phase one works
[176] The upshot then is that Mr Everett’s attempts to avoid liability in respect of payment
for the phase one works have failed. His obligation under his agreement with Cheshire
Contractors was to pay for the invoiced works. His failure to do so was in breach of
contract. Subject to the consequences of the below discussed December 2011
promise, I accept he is liable for the unpaid amount both as damages for that breach
and as a debt under the contract.
PART C – THE DECEMBER 2011 PROMISE
The December 2011 promise
[177] Mr Everett testified that by the time the phase one works were “all but finished or had
finished”,226 his loan application to the NAB, made subsequent to the meeting earlier
in the year with Mr Duggan, was declined.227 The trust’s debt to the bank was then
about $1,000,000 according to Mr Everett,228 who testified that while the bank
declined the loan application to pay for the civil works it approved lending to fund the
holding costs and maintenance of the property.229
[178] Barry Cheshire testified that at the end of 2011 Cheshire Contractors demobilised
offsite. Around this time he heard that Mark Everett’s application for finance had
been unsuccessful (though not from Mr Everett’s bank manager Mr Duggan230 as Mr
Everett’s testimony claimed231). Mark Everett assured him Mr Everett would have
sales and Cheshire Contractors would be paid. The development did not advance and
there were no sales. The situation drifted on without payment being made to Cheshire
Contractors to about late 2013.232
[179] That Cheshire Contractors took no action to compel payment in the interim may be
explained by an alleged promise it made not to do so during December 2011.
224 T4-51 LL30-43.
225 T4-46 L45.
226 T2-21 L25.
227 T2-13 L6.
228 T7-21 L36.
229 T7-22 L28.
230 T3-16 L25.
231 T7-22 L45.
232 T2-62 LL1-10.
-- 38 of 68 --
39
[180] On Barry Cheshire’s account, in December 2011, when the phase one works were
completed,233 Mark Everett told him the NAB would provide further funding just for
maintenance, to give Mark Everett more time to market the property, on the condition
that Barry Cheshire did not make a claim for the phase one works.234 The bank was
concerned at the prospect of Mr Everett having an aggrieved creditor.235 This was
evidently around 16 December 2011, because on that date Tony Duggan of the NAB
sent an email to Mark Everett, stating:
“Agreement between the client and road contractor is to be sighted by
the Banker to ensure that no funds are required to be paid prior (sic)
to the road contractor prior to presales occurring and development
funding being provided.”236
[181] Barry Cheshire testified Mark Everett sent him Mr Duggan’s email of 16 December
2011 and told him, “If we don’t get any funding, well, you’re not going to get paid”.237
As a result, Barry Cheshire forwarded Mark Everett an email on 20 December 2011
stating:
“Cheshire Contractors Pty Ltd will not seek payment for work
performed on the Hinchinbrook Habitat subdivision until there
sufficient sales or presales that allow you to make payment.”238
[182] Mark Everett responded by email to Barry Cheshire the following day on 21
December 2011 writing:
“thanks you. hopefully thats enough to satisfy them”239
[183] I will for convenience refer to Mr Cheshire’s email of 20 December 2011 as “the
December 2011 promise”. What is its significance?
Discussion
[184] Mr Cheshire obviously intended the December 2011 promise to be shown by Mr
Everett to Mr Everett’s bank, as an accurate statement of Cheshire Contractors’
intention. Mr Cheshire did not testify that it was a false representation of his
company’s position. The position Cheshire Contractors took, of not taking action to
recover payment, is also consistent with the truth of the representation. The December
2011 promise was a “promise” in the lay sense of the word but even in the lay sense
its parameters are informed by more than its literal content. Taken literally the
promise could mean Cheshire Contractors would never press for payment because if
Mr Everett chose to never advance the project or did so unsuccessfully, then there
would never be any sales or presales. That is obviously not what was contemplated
by the promise. It was a promise to delay, not deny, the exercise of the right to
payment. Mr Everett could not have thought otherwise.
233 T2-61 L26.
234 T3-16 LL28-35.
235 Ex 79.
236 Ex 16.1.
237 T2-61 L2.
238 Ex 16.2.
239 Ex 16.2.
-- 39 of 68 --
40
[185] It was a promise made on request for the purpose of assisting Mr Everett in his
dealings with the bank. Implicit in Mr Everett’s act of seeking it was the implication
that he would continue to advance the project to the point where there would be
sufficient sales or presales to fund payment to Cheshire Contractors of what they were
owed. Putting it another way, this was not a promise to delay seeking payment
indefinitely. Rather, it was a promise to postpone seeking payment until Mr Everett
had had sufficient time within which to advance the project to the point of being able
to raise money to pay from funds from presales or sales.
[186] That finding of fact is very significant. Even if it were the case, as Mr Everett argues,
that he acted to his detriment on the strength of the December 2011 promise, so that
the December 2011 promise ought be legally binding, his problem remains that it was
never more than a promise to delay seeking payment. Anything he did to his detriment
by acting on the promise could only have been in the understanding that Cheshire
Contractors would delay seeking payment. That delay was only as long as the passage
of a sufficient period of time within which to advance the project to the point of being
able to raise money to pay for the phase one works from funds from presales or sales.
[187] Mr Everett had more than sufficient time after the December 2011 promise to advance
his project to that point. Another year to a year and a half would have been amply
sufficient time for Mr Everett to advance the project to that point if he could.
However, making some further generous allowance for the variables inherent in
development work, I find two years was sufficient time. I find the postponement
period contemplated by the promise was over by 1 January 2014.
[188] Remarkably, all these years later, Mr Everett still relies on the December 2011
promise as a means to try and avoid liability to pay for the phase one works. Even if
the December 2011 promise was legally binding the time long ago passed for its
continued operation as a basis to avoid liability for paying the monies outstanding on
the phase one works. Subject to Mr Everett’s claim of set off, Cheshire Contractors
should at the least have judgement for the total outstanding of those monies. As earlier
explained that total is $350,970.59.
[189] This does not render the debate as to whether the December 2011 promise was legally
binding irrelevant, because it bears upon the point in time from which the calculation
of interest on the outstanding amount ought be calculated. The events of phase two
may bear upon that. It is a therefore a topic to which I will return after dispensing
with phase two.
PART D – PHASE TWO ANALYSIS
Ph 2: An elusive agreement to plead
Oral agreement?
[190] Cheshire Contractors plead that on or about 12 August 2014 it entered into a further
oral contract with Mr Everett, by which Cheshire Contractors agreed to supply
services at Mr Everett’s request including civil services, consultation, obtaining
operational work permits, surveying, supervision and site management and
-- 40 of 68 --
41
development management.240 By the agreement Cheshire contractors was allegedly
to invoice for services as and when performed at the same rates as phase one for civil
services, at a commercial rate for development management services and at cost plus
15 per cent for other services. It was allegedly agreed Mr Everett would pay the
invoices within 30 days of issue.
Joint venture?
[191] Mark Everett denies there was ever any agreement between him and Cheshire
Contractors of the kind alleged by Cheshire Contractors in respect of phase two.241
Rather Mr Everett pleads the parties reached an oral joint venture agreement on or
about late January 2014 by which Cheshire Contractors were to provide an array of
additional services beyond construction of roads, drainage and lots and including an
array of other tasks including the employing of appropriate soil testers, design
engineers, surveyors and real estate agents, and sourcing financial funding for the
project.242
[192] One of those tasks related to part of the land on the hill where Mr Everett’s house was
located and which was to be surveyed as a separate lot, to be called lot 77. That task
was pleaded as:
“Arrange for all works to be done and steps to be taken to create the
proposed Lot 77 so it may be sold to assist in facilitating funding of
the development.”243
[193] Mr Everett’s pleading of the terms of the joint venture included that any sums
outstanding under the terms of the first contract would be carried forward to and
become the liability of the joint venture and that Mr Everett’s contribution would
include the $440,000 derived from net proceeds of sale of lot one.244
Alternatively a Riverviews Estate contract?
[194] In the alternative to the joint venture Mr Everett pleads that in or about May 2014 the
parties entered into a contract (“the Riverviews Estate contract”) whereby it was
agreed the sale of lot one would occur with Mr Everett accepting $220,000 of the
purchase price as a credit against monies to fall due in the future under the first
contract and to apply the balance in accordance with the project budget. Other terms
alleged were that Cheshire Contractors would ensure the subdivision of lot 77 could
proceed so as to facilitate further financing and Cheshire Contractors would complete
all the works contemplated by the budget and would be paid for the works in
accordance with the budget.245
[195] Mr Everett pleads the implied terms of the Riverviews Estate contract were that
Cheshire Contractors would provide services and materials reasonably fit for purpose,
240 SOC [10].
241 Def [10aa].
242 Def [10b].
243 Def [10b i N].
244 Def [10b iv vi].
245 Def [11E].
-- 41 of 68 --
42
would perform services with reasonable skill and would undertake all liaison with
local, State and statutory authorities in respect of the completion of the work and
comply with the requirements of local, State and statutory authorities. The budget
referred to was said to be the budget prepared by Cheshire Contractors to be submitted
by Mr Everett in his name to his bank, prepared in draft form dated 8 May 2014 and
in final form dated 28 May 2014.246
[196] Cheshire Contractors denies the Riverview Estate contract pleaded by Mr Everett on
the basis the oral contract was as pleaded by Cheshire Contractors.247
An agreement from the pleadings?
[197] The fact that each side in different ways pleaded the existence of an agreement does
not mean there was an agreement. The pleadings implicitly accept that Mr Everett
and Mr Cheshire were in some way agreed that Cheshire Contractors would perform
further works. As much is obvious from the fact that Mr Everett permitted, and
Cheshire contractors performed, further works. But there is no common ground on
the pleadings as to any agreement about the essential contractual element of
consideration for those works.248 If there was any agreement it could at best arise
from the evidence, not the pleadings.
Ph 2: Any agreement to be extracted from the evidence?
Cheshire Contractors ventures actively into the project
[198] After the December 2011 promise Mr Everett evidently did not secure any pre-sales.
On his account he did advertise,249 without success, and made an unsuccessful attempt
to sell the property.250 This was not the decisive conduct of a developer able to
advance his development in a timely way.
[199] On Barry Cheshire’s account, in late 2013 or early 2014, by which time he was
doubtless rightly concerned by the lack of progress, he told Mark Everett he was
interested in working with Mr Everett to continue the development in order that he
could get paid. Barry Cheshire testified he came up with the idea of doing the project
as a rural subdivision to eliminate a lot of infrastructure and cost.251 He testified of
his motivation at this point, “I thought it was probably the only way out”,252 an
obvious reference to his desire to be paid for phase one.
[200] An email from Mr Cheshire to Mr Everett of 28 October 2013 enclosed some draft
plans for the varied project by Mark Valmadre.253 Mr Everett testified he and Mr
246 Def [11D].
247 Reply [42].
248 Compare for instance the highly qualified admissions in the Reply [42,43] to Def [11D, 11E].
249 T7-23 L44.
250 Ex 49.
251 T3-22 LL14-20.
252 T3-22 L25.
253 Ex 50.
-- 42 of 68 --
43
Valmadre spoke with HSC about the potential change and Council was receptive.254
Mr Everett testified Mr Cheshire visited him, explaining his idea of changing the
development to acreage blocks and pursuing it “fifty-fifty” as a joint venture.255
[201] On 6 December 2013 they met without success with some potential private funders of
the project.256 On 20 December 2013 Mr Everett consulted with Nathan Fien, a
financier of Corporate Finance Group, in respect of development funding for Mr
Everett’s project. On the same date Mr Fien forwarded Mr Everett an email
summarising the effect of their discussion, which email Mr Everett forwarded to Mr
Cheshire.257
[202] It was put to Barry Cheshire in cross-examination that in January 2014 he started
paying for work which needed to be done in connection with the project, to which Mr
Cheshire responded, “Only because he couldn’t pay”.258 That response, implicitly
accepting the proposition put, confirms Mr Cheshire was moving to advance Mr
Everett’s project, presumably perceiving it had positive commercial prospects.
[203] By 9 February 2014 Mr Everett was seeking advice from his accountant Mr Carey on
a proposal of Mr Cheshire which he described in the email as follows:
“…Barry’s proposal to shift the larger blocks, not having the sewerage
treatment plant, underground power and water treatment plant, all of
these things are not required with the larger blocks reducing initial
capital cost dramatically.
The blocks would end up bigger but able to be sold for less money.
NAB has given me an extension until June but with some covenants
that may prove difficult to meet. As time is short should I go ahead
with the changes or try to sell the whole place as is with the current
approvals?
Barry has agreed to project manage the development for a percentage
of the profit on each block so a potential JV partner can have comfort
in the management.
As you would be aware pressure is a nasty thing and I need to make a
decision and run with it before I run out of money again.”259
The email went on to mention that Mr Everett’s former wife Gail was “off the bank
loans now and off the title”.
[204] On 10 March 2014 Daniel Spencer of Cheshire Contractors wrote to a town planning
firm known as RPS, identifying various changes, including a change in the
development’s name to Riverviews Estate.260 Mr Everett testified that by this stage
Mr Cheshire had made himself project manager. When asked to explain what he
meant by that testimony he responded:
254 T7-26 L47.
255 T7-27 L11.
256 T7-27 L25, Ex 51.
257 Ex 68, T8-6 L20.
258 T3-22 L41.
259 Ex 69.
260 Ex 53.
-- 43 of 68 --
44
“That was one of the preconditions of him doing a joint venture. … I
admitted that I made a few mistakes in the past, and he appointed
himself project manager. That was one of the conditions of him
getting involved.”261
[205] On 21 March 2014 Mr Yelavich of town planning firm RPS emailed Daniel Spencer,
explaining his firm’s dealings to date regarding conditions of the Federal Department
of Environment, nominating RPS’s fee for proceeding further and requesting
confirmation whether it was “OK to proceed”262 to which, on 26 March 2014, Daniel
Spencer authorised RPS to proceed.263
[206] On 26 March 2014 Mr Cheshire emailed Mr Everett writing:
“As per our discussions recently regarding the possibility of JV or a
partnership between Cheshire Contractors and Mark Everett to
progress the development of your Mt Cudmore property I suggest a
meeting with Robert Carey to obtain advice on the best possible way
of proceeding.
One thought is for Cheshire Contractors and Mark Everett to purchase
Racehub Pty as a vehicle to purchase the property from the Everett
Family Trust with enough excess funding to enable the construction
and sales of 24 lots in the initial stage.
Initial sale prices are attached and would realise about $4.5 mil not
including sale on Mt Separation.
The changes to design have enabled much lower costs for construction
and also allowing lesser sales prices.
Estimates to complete works to Mark’s house intersection on Mt
Separation Road is $1,300,000 and estimates to complete the
remaining is $1,500,000.
We believe total sales would realise $18 mil.
Cheshire Contractors are keen to progress this partnership and help
make this a viable project.”264
[207] Mr Everett forwarded that email to his accountant Mr Carey and to Mr Duggan,
writing, “This is what Barry is suggesting”.265 The email’s reference to Racehub Pty
was a reference to a company owned by Mr Everett and his former wife.266
[208] On 7 April 2014 Mark Everett emailed Barry Cheshire a list of Mr Everett’s
apparently monthly expenses for payments towards plant, equipment, insurance, rates
and power.267 Mr Cheshire rejected the suggestion this email was sent because Barry
Cheshire needed to know information for a potential financing arrangement.268 On
261 T7-30 L10.
262 Ex 54.
263 Ex 54.
264 Ex 52.
265 Ex 52, T7-28 L38.
266 T7-28 L42.
267 Ex 30.
268 T3-24 L37.
-- 44 of 68 --
45
Mr Everett’s account he sent the email in response to a request from Clinton Cheshire
so Cheshire Contractors would know what payments would need to be made when Mr
Everett ran out of money.269 Further enmeshing itself in the affairs of the project,
Cheshire Contractors made an application in around April 2014 to Telstra, to have
headworks performed through the subdivision.270
Joint venture and the hunt for funding
[209] Discussion of Cheshire Contractors becoming a joint venturer in Mr Everett’s project
must have been well underway by April 2014. At that stage Mark Everett was trying
to secure project refinancing through Mr Fien. Barry Cheshire testified there was
interest in Cheshire Contractors because they had income. On 15 April 2014 he
emailed Mr Fien about Cheshire Contractors and Mark Everett being involved in a
joint venture.271 That email commenced:
“Mark Everett from Ingham has given me your details. He has
contacted you in regards to financing a development at Cardwell
Range near Ingham in North Queensland.”272
[210] The email went on to explain the background of Mr Cheshire and his company. It
then continued:
“I have known Mark for several years and he has approached us to
help develop his land at Ingham. His development has been going for
some time but with little direction and with a development type which
would be better suited to city outskirt boutique type subdivision with
smaller lots. I have engaged town planners RPS from Cairns and
redesigned the development to acreage lots in a rural zoning which has
reduced the construction costs, lifted the yields so as to make it a very
viable proposition. I believe the development will be self-funding
after the first stage and have attached some forecasts for you to have a
look at. The three scenarios provided and the cash flows are for the
first stage only with the third as a reference to “if sales were
catastrophic” with the first scenario being very probable and possibly
exceeded with the advertising budget available.”273
[211] The letter went on to describe the virtues of the property’s location and then continued:
“The NAB has a first mortgage over the property securing a loan of
$2.4 mil. We are seeking a lender to take over the NAB debt and fund
the construction cost as shown in the cash flows. The loan would be
secured by the land and subsequent developed lots and the proposal
would be as a joint venture between Mark Everett and Cheshire
Contractors.
This is a brief overview of the project looking to gain the interest of a
prospective lender.
269 T7-33 L33.
270 T2-64 L45.
271 Ex 17.
272 Ex 17.
273 Ex 17.
-- 45 of 68 --
46
If you’re interested in the above project you can contact me…”274
(emphasis added)
[212] Mr Cheshire asserted in re-examination that he was not involved in any approaches to
financiers other than Mr Fien.275
[213] Barry Cheshire agreed that in about April 2014 he had created a document styled
“River views lifestyle acreage estate”,276 based on information from Mr Everett. The
document, which Barry Cheshire testified he had drafted at Mark Everett’s request,
provided a short overview about the proposed development and set out a variety of lot
prices and construction costs through various stages of development, along with a
number of cash flow projections based on different scenarios.277 Mr Everett testified
he was unaware of the document being produced and on his account was given it by
Mr Cheshire who requested he give it to Mr Duggan of the NAB.278 Mr Everett gave
it to Mr Duggan.279
Sale of lot one to help funding
[214] By May 2014 it had been agreed between Mark Everett and Barry Cheshire that lot
one on Mr Everett’s property ought be sold to Barry Cheshire and his wife, and
another couple associated with Cheshire Contractors. Lot one had been valued at
about $600,000.280 It was separated from the rest of Mr Everett’s property by a
railway line and had been used by Cheshire Contractors as their work depot during
phase one.
[215] The arrangement struck, evidently allowing for GST, was that the property would be
purchased for $660,000 – a fair commercial price - with the amount of a deposit of
$220,000 being credited by Cheshire Contractors against the amount of money Mark
Everett owed to Cheshire Contractors, thus reducing that debt. The $440,000 balance
of the purchase price (the balance was said to be $462,000 elsewhere in the evidence
but nothing turns on the point) was to be paid to Mark Everett, hopefully to be used
by him to advance the project to a stage where it could be offered for presales.281
The hunt for further funding continues
[216] Apparently on the strength of the arrangement for the sale of lot one, Barry Cheshire
emailed Mr Tony Duggan of NAB on 8 May 2014 saying:
“Here is the 1st draft of land sale deal from Everett Family to Cheshire
Contractors as previously discussed. Let me know your thoughts and
suggest any amendments.”282
274 Ex 17.
275 T4-10 L2.
276 Ex 18, T3-25 LL22-35.
277 Ex 18.
278 T7-32 L 7, T7-33 L3.
279 T7-33 L5.
280 Ex 19 p 82.
281 T2-63 LL1-10.
282 Ex 32.
-- 46 of 68 --
47
[217] Attached to the email was an unsigned letter by Mark Everett of the same date marked
for the attention of Mr Duggan, saying:
“I refer to the sale of Lot 1 CWL 2514 and advise as to the expenditure
of the proceeds of the sale which will be used for further development
and associated costs.
The following budget has been produced for this purpose.”283
[218] There followed an itemised budget allocating expenditure to items of construction, lot
preparation, Council and MRD contributions, engineering and survey design, town
planning, estate management and maintenance, advertising and marketing, living
costs and bank fees and charges and “payment of 30% deposit for part payment of the
construction of the access road by Cheshire Contractors”. This gave rise to a total
budgeted figure of $900,000. The letter continued:
“I propose to have Mount Separation Road and Everett Road
completed with earthworks, stormwater & a running surface to service
all 31 lots in stage 1. These blocks will be able to be sold using
disclosure plans and disclosure statements.
Town planners RPS have been engaged to redesign the development
to acreage lots which will reduce construction costs & increase profit.
A contract has been extended with LCJ Engineers for engineering
design to include the extra lots.
An advertising program is being set up with a marketing company in
Townsville and a sales person will be engaged to follow through with
sales leads. The lots will also be available for sale through the buyers
preferred real estate agent.
Estate management and maintenance includes estate presentation with
costs to mow the lots & keep the estate tidy to attract potential
investors.
I have included a summary of overall budget cost to complete stage 1
and a projected sales program. Stage 1 will be fully completed on the
back of sufficient sales in stage 1.”284
[219] On 28 May 2014 Tony Duggan responded to Barry Cheshire by email, saying:
“Have had a look at this and with Val now coming in at $660K this
will have to be revised.
Can you please liaise/discuss with Mark how this can be done with
reduced amount.”285
Mr Cheshire did then discuss this issue with Mr Everett and Mr Everett testified he
said he was still prepared to proceed with the sale of lot one “to get the JV going”.286
[220] Two hours later on the same date, 28 May 2014, Barry Cheshire emailed Mark Everett
saying:
283 Ex 32.
284 Ex 32.
285 Ex 33.
286 T7-40 L15.
-- 47 of 68 --
48
“This is the land expenditure proposal for NAB. If you like it sign it
and send to Tony.”287
[221] Attached thereto was again an unsigned letter by Mark Everett for the attention of
Tony Duggan, this time dated 28 May 2014. The letter was identical to the content of
a letter which had been annexed in Mr Cheshire’s email to Tony Duggan on 8 May
2014 except that the costings for the various budgeted items were all reduced so as to
give rise to a total of $660,000 as distinct from the earlier total of $900,000.288 Mr
Everett signed the letter of 28 May 2014 and sent it to Mr Duggan.289
[222] In this era Mr Everett also had dealings with David Manchee of Belvedere Share
Managers who, on 11 June 2014, emailed Mr Everett with the details of two
companies who had shown some interest in joint venture financing.290 Mr Everett
forwarded this email to Mr Cheshire on the same date.
NAB variations
[223] On 10 July 2014 the NAB offered variations to Mr Everett’s existing loan facility,
which were accepted by Mr Everett on 16 July 2014. The variations were to extend
the existing loan facility limit of $1,750,000 to 31 December 2014 and remove lot one
from the security supporting the facility. The variation also imposed additional
lending covenants as follows:
“Additional lending covenants
Marketing plan to be provided to the bank by 30/09/2014.
Boundary realignment to be completed and separate title issued for
proposed Lot 77, also known as “house block” by 30/9/2014.
In the event that equity partner or presales cannot be achieved, a
marketing program for the sale of the proposed Lot 77, also known as
“house block” is to be provided by 31/12/14.”291
[224] An explanatory note by the NAB, also signed by Mr Everett on 16 July 2014,
explained the security provided by lot one was being released in order to allow its
sale. The note recorded, inter alia:
“The property being sold is being released without associated
reduction. The funds will be used to allow the customer to further
improvements to develop the block with the main expense being an
access road. The NAB has not assessed the revised development and
previously has indicated the need for presales as part of any proposal.
The customers need to have the access road to allow presales to be a
more realistic option.
At this stage the customer needs to clearly understand that the NAB
has not made any commitment to funding the development and the
allowing of some funds for this purpose does not constitute a future
approval of support. …
287 Ex 34.
288 Ex 34.
289 Ex 65, T7-78 L13.
290 Ex 70.
291 Ex 56.
-- 48 of 68 --
49
I note the customers have outlined three options prior to DEC 2014 to
allow the additional $1.0M to be sourced to complete the project.
1. the presales to allow the NAB or other financier to consider the
development funding.
2. equity partner.
3. sale of house block, this option would again require the NAB to
allow some funds from existing security being sold. This decision
would be made on the information held at the time and the
proposal put.
2 or 3 options require the NAB to agree to something which simply at
this point in time we are not in a position to decision (sic). The
customers need to clearly understand that the NAB is not making any
commitment past 31/12/2014 to renew facilities or any funding of the
development.
I would suggest the ABM clearly details the customers’ understanding
of this.”292
[225] The circumstance under which the bank came to release lot one from the lending
facility’s security, namely the arrangement to sell lot one to raise some funds to
advance the project, is clear from the facts discussed above. Much less clear is the
genesis of the additional lending covenant requiring the boundary realignment of lot
77 by 30 September 2014 and the provision of a marketing program for the sale of
that lot by 31 December 2014 in the event that an equity partner or presales could not
be achieved. Mr Everett unconvincingly claimed to have had no communication with
the bank regarding the options of presales, the finding of an equity partner or the sale
of lot 77.293 However, he later acknowledged in evidence-in-chief the possibility of
separating title on the hill where the house block was located had been discussed with
him by the bank 12 months earlier.294
[226] Mr Cheshire accepted in cross-examination that he knew Mr Everett would only have
about $400,000 available to him from the sale of lot one and allowing for third party
payments would only have enough available from that amount to pay Cheshire
Constructions for the first two budgeted road construction items, priced at $115,000
and $62,000 respectively.295 Mr Cheshire conceded he knew there would not be
enough from the lot one sale proceeds to pay his company in full for its work.296
[227] When asked in re-examination why he was prepared to commit to doing further work
with such knowledge, Mr Cheshire responded:
“Because there was always the chance at the end that the lots would
be sold and we’d be paid out of the lots.”297
292 Ex 57.
293 T7-41 L38.
294 T7-42 L47 – T7-43 L2.
295 T3-34 L38 – T3-35 L2.
296 T3-35 L22.
297 T4-11 L28.
-- 49 of 68 --
50
Such evidence makes a mockery of Cheshire Contractors’ attempt to allege that the
phase two works involved an agreement like the phase one works, under which
invoices were to be paid soon after they were issued.
What agreement?
[228] Barry Cheshire testified that within four to six weeks of his 15 April 2014 proposal
being put to Mr Fien of Capital finance it was “knocked back”.298 In the meantime,
on 16 May 2014 Mr Cheshire and Mr Everett each executed an agreement forwarded
by Mr Cheshire to Mr Fien for the engaging of a finance broker.299 Cheshire
Contractors paid the requisite brokerage fee of $1650.300 It is noteworthy that in
executing the document they each described themselves as a “JV partner”, though at
that stage had only discussed a joint venture and not reached an agreement.301
[229] Allowing for the passage of four to six weeks from 15 April would suggest Mr Fien’s
“knock back” occurred about mid to late May though Mr Cheshire testified it was
probably June.302 Mr Cheshire’s recollection is consistent with an email of 19 June
2014 from Mr Fien to Mr Everett advising the preferred course was for Mr Everett to
work with his existing lender.303 The email identified a number of issues detracting
from the development’s appeal to financiers.
[230] Barry Cheshire explained it was after Mr Fien rejected their proposal that Mr Cheshire
had discussions with Mark Everett about performing the phase two works charged at
the same rates as phase one.304 As to what was said, this vague exchange occurred in
evidence-in-chief:
“And do you recall – can you cast your mind back to recall the actual
discussion with Mr Everett and what might’ve been said by Mr Everett
and what might’ve been said by you? Are you able to recall that?---I
think it was a situation we said we’ll carry on from what we did in the
first stage, we’ll do in the second stage. And it would be under the
same arrangement.
But did Mr Everett ask you to do that or did you - - -?---Yeah.
- - - propose to do that or - - -?---No, Mr Everett asked me to do
that..”305
[231] This was unconvincing evidence that there was any agreement on similar terms to
phase one. As to terms of payment this similarly unhelpful exchange occurred in
evidence in chief:
“Now, Mr Cheshire, you were saying just before the break that you’d
had some discussions with Mr Everett about getting the work done and
you were explaining the work that was to be done. What, if anything,
298 T2-77 L42 – T2-78 LL5-12.
299 Ex 55.
300 Ex 55 p 28.
301 T8-12 LL25-35.
302 T2-78 L9.
303 Ex 71.
304 T2-77 L15.
305 T2-78 LL22-30.
-- 50 of 68 --
51
was discussed with Mr Everett about the process for and the timing of
claiming for payment of the work to be done, in respect of phase
two?--- Our terms of payment have always been the same: 30 days
after the end of the month.
Okay. So just – we won’t repeat all that we did a little bit on about
phase 1, but just in terms of any discussions with Mr Everett about
that, did you have any discussions with Mr Everett specifically about
the terms of payment for phase 2 works?--- No. Only apart from the
fact that he was going to pass us of the sale.”
[232] The first above quoted answer was unresponsive. The second answer seemed to
acknowledge an absence of discussion of payment terms other than that payment was
going to be made from “the sale”. Presumably that was a reference to funds from the
sale of lot one, which were never going to be enough to cover the cost of the phase
two works.
[233] It will be recalled that by the time of this vague and unconvincing alleged exchange,
inferentially in around the second half of June of 2014, Cheshire Contractors had
already been performing “project managing” and “market/advertising” for three
months. Barry Cheshire explained that Cheshire Contractors charged Mark Everett for
sales and marketing expenses because Mark Everett could not get credit for television
and other media, and because “Mr Everett asked us to”.306
[234] Mr Everett rejected the suggestion that agreement was reached with Mr Cheshire that
Cheshire Contractors would be paid for carrying out the phase two works on the same
hourly rate basis or the same cost plus basis that had applied for phase one.307 To the
extent any common ground was conceded in this context by Mr Everett, he conceded
that the amended decision notice of HSC of 22 July and the settlement of 7 August
2014 were events which enabled “the project to get going”.308 But Mr Everett rejected
the suggestion there had been an agreement reached with Mr Cheshire as to the basis
upon which the work being performed would be charged for.309
[235] It is improbable in light of Mr Everett’s financial difficulties and Cheshire
Contractors’ already active role in advancing the project, that there occurred an oral
agreement for Cheshire Contractors to proceed with the phase two works on the basis
it would be paid forthwith for work performed.
[236] By the time settlement of the lot one sale occurred on 7 August 2014310 the phase two
works were underway.311 Shannon Cheshire, the foreman for Cheshire Contractors,
did not know who gave the go-ahead for work on the second phase to commence,
although he recalls there were meetings onsite with Barry Cheshire and
representatives of LCJ.312
306 T2-83 L27.
307 T8-75 L25.
308 T8-76 L40.
309 T8-77 L3.
310 Amended Statement of Claim (“SOC”) [6(b)], Further Amended Defence (“Def”) [7].
311 T2-75 L46.
312 T1-74 L13.
-- 51 of 68 --
52
[237] Mr Everett acknowledged in cross-examination that at the time of lot one’s settlement
he had had to arrange for NAB’s release of the mortgage to allow the settlement to
take place “for the funds to flow through to get the work going”.313 But, considered
in context, this was not a concession of an agreement having been reached with Mr
Cheshire.314 The timesheets show that there was some work performed in July with
the substantive construction work commencing from 31 July 2014.
[238] Barry Cheshire testified Mark Everett asked for work to be performed, “as the works
went on”.315 Even if that is correct it says nothing of the commercial basis, if any,
upon which the works underway were being performed.
[239] In weighing up whether an agreement can be inferred it is of course relevant to bear
in mind that on 18 September 2014 Mr Everett paid Cheshire Contractors’ first invoice
for the phase one works, dated 27 August 2014, in the amount of $139,596.76. It will
be recalled settlement of lot one had occurred in August with the consequence Mr
Everett had some liquidity. In the mix of what was then occurring the payment at
least carries the hallmark of a show of good faith support for the unfolding enterprise.
It will be borne in mind no other invoices for phase two, other than the invoices
covering the costs of Pozzi Surveyors, were paid. In the absence of any other credible
evidence in support of the inference of agreement having been reached regarding
consideration, this evidence of a one off payment in September, soon after the lot one
settlement, does little to help sustain such an inference.
Attempt to document joint venture
[240] According to Barry Cheshire, the work in both phases one and two was “completely
finished” before there was discussion of a joint venture.316 That is plainly wrong. Mr
Cheshire was referring to a prospective joint venture as long ago as his email to Mr
Fien of 15 April 2014 and he signed the finance broker letter of engagement of 16
May 2014 as a “joint venture partner”.
[241] Moreover, the phase two works had not long been underway when, on 12 August
2014, Barry Cheshire forwarded to Mark Everett’s solicitor, Peter Elliott, a document
headed “Basis of agreement for joint venture”, which document incorporated a dot
point proposal as well as reference to the sale of lot one.317 It appears Mr Everett had
first consulted Mr Elliott back on 22 July 2014 at which time there had been a
discussion by them with Barry Cheshire by telephone in respect of a proposed joint
venture agreement.318 Mr Everett conferred again with Mr Elliott on 5 August 2014,
giving instructions for the contacting of Mr Cheshire regarding setting up a draft joint
venture agreement.319
313 T8-75 L3.
314 T8-75 L3.
315 T2-83 L12.
316 T3-30 L35.
317 T2-68 L22, Ex 19.
318 Ex 72, T8-18 L46.
319 Ex 72.
-- 52 of 68 --
53
[242] This likely prompted Mr Cheshire’s letter of 12 August, in which he contemplated the
balance of the purchase price for the lot one sale, of $462,000 would be applied to
cover development costs until the presales stage. It explained:
“Mark Everett will reinvest this $462,000 … into the development to
facilitate holding costs, town planning costs, engineering costs,
surveying costs, construction costs, advertising and marketing and
maintenance costs. These funds will allow construction to proceed to
a stage where presales will be able to be put to contract.
It is anticipated that there will be sufficient presales to gain finance to
complete the necessary works to grant title and receive settlements
from the existing presales.
As proceeds from the sales exceed the required amount for day-to-day
costs funds will be used to pay debts belonging to Mark Everett for the
amount of $2,800,000 … and pay Cheshire Contractors for works
completed.
After construction costs and Mark Everett’s debts have been settled
the remaining funds excess to that previously mentioned and required
to maintain and keep the land will be split on a 50/50 basis between
Cheshire Contractors and Mark Everett except for the initial
$2,000,000 excess which will be paid to Mark Everett being payment
for 50% of the land valuation by Taylor Byrne of $4,000,000.”320
[243] On 11 September 2014 Mr Everett’s solicitors forwarded him a copy of a draft joint
venture agreement. The letter also recorded a variety of information which may
reasonably be inferred to have come from the solicitors’ client, Mr Everett,321 despite
Mr Everett’s reluctance to admit as much in the witness box.322
Cheshire Contractors continued active role in the project
[244] Cheshire Contractors had used its finance and credit to engage GT Pozzi consulting
surveyors to perform work during phase two.323 The role of Mr Pozzi’s firm included
surveying and sub-dividing lot 77 from Mr Everett’s house, with a view to creating a
registered title to lot 77 to sell. Mr Cheshire conceded in cross-examination he was
aware the registration of lot 77’s title, with a view to its sale, was required of Mr
Everett by his bank to raise money.324 He conceded in cross-examination that he
became aware of this when Mr Everett’s approval from the bank to sell lot one had
occurred, there had been an accompanying strict time limit imposed for the
subdivision of lot 77.325 It will be recalled that the NAB’s variation of 10 July 2014
required the creation of the separate title by 30 September 2014. Mr Cheshire’s
awareness of the need to advance the title creation was implicit in an email to him of
21 September 2014 in which Mr Everett wrote:
320 Ex 19.
321 Ex 73.
322 T8-20-21.
323 T3-41 L27.
324 T3-39 L35, T3-41 LL14-22.
325 T3-39 L26.
-- 53 of 68 --
54
“Do you need me to do anything to get this going to meet the bank’s
requirements?”326
Mr Cheshire responded to that email the following day, writing, “All done”.327
[245] Mr Cheshire explained in re-examination that the surveying off of lot 77 had not been
“part of the original plan”.328 He testified:
“Well, I knew nothing about it until I received a email from Mr
Everett, saying, “What do we do about this?” And I found out that the
– from that that a part of his funding from the bank was to have that
lot cut off. … I don’t believe it was anything to do with the
subdivisional side of it until such a time as the titles were to be,
basically, in the Council and the job was finished.”329
The reference to an email in that testimony was not specific but was likely intended
to be a reference to the email of 21 September 2014. This fits a chronology outlined
in a memorandum dated 17 August 2015 by Mr Hopkins of Pozzi Surveyors, setting
out the chronology of their role. That memorandum describes how in August 2014
Mr Cheshire had approached Pozzi Surveyors to carry out the boundary survey for
Riverviews Estate and soon afterwards had advised that the excision of lot 77 would
be the priority.330
[246] Mr Everett agreed in cross-examination that the first occasion he raised the topic of
lot 77 was around the same time as the settlement of lot one in August 2014.331
Curiously, he rejected the suggestion he had requested Mr Cheshire to organise a
surveyor for that purpose332 although he acknowledged he subsequently paid via his
accountant for the cost of the surveying work performed.333
[247] On 26 September 2014 Barry Cheshire emailed Mark Everett a number of emails.
According to Mr Everett’s testimony this occurred after he complained to Mr Cheshire
about not being kept informed of what was going on with the development and Mr
Cheshire said he would send everything through.334 One of the emails sent on 26
September was a copy of an email to Cheshire Contractors from Evan Yelavich of
RPS. 335 Mr Cheshire had used RPS in relation to some of the town planning aspects
of phase two,336 apparently including securing HSC’s amended decision notice of 22
July 2014 approving development permits for reconfiguring a lot and material change
of use.337 The email of 26 September 2014 related to RPS’s proposals on how to
persuade Council to approve an amended development proposal.338 Barry Cheshire
agreed Cheshire Contractors paid RPS to be doing this “under instruction from Mr
326 Ex 35.
327 Ex 35.
328 T4-10 L23.
329 T4-10 LL11-16.
330 Ex 11.
331 T8-83 L46.
332 T8-84 L12.
333 T8-84 L15.
334 T7-45 L17.
335 Ex 28.
336 T3-54 L36; see also, eg, Ex 59.
337 Ex 1 Tab 6 p 35.
338 Ex 28.
-- 54 of 68 --
55
Everett” who could not pay for it.339 This is further powerful evidence that Cheshire
Contractors was, by this stage, an active player in advancing the development, not just
a firm contracted to perform works for money.
[248] Also on 26 September 2014, at the same time as the above email was sent, Barry
Cheshire emailed to Mark Everett an email internal to Cheshire Contractors of 30
January 2014, in which Daniel Spencer wrote:
“Jobs set up as follows:
RVE10114 – River Views Estate subdivision – construction
of the development
RVE20114 – River Views Estate project management –
project management, marketing, town planning,
engineering, etc anything not associated with construction of
the project”.340
[249] According to Barry Cheshire, this was a “normal costing program we use for every
job we do”.341 Clinton Cheshire testified he was told to split the job administration
like that.342 Such a split suggests Cheshire Contractors had not been approaching
phase two in the capacity of a mere contractor engaged to construct works.
[250] In cross-examination, Barry Cheshire agreed that for phase two Cheshire Contractors
took on the role of project manager but said that was only for construction.343 He
conceded that he had asked LCJ to organise the various consultants so that Cheshire
Contractors could obtain an operational works permit.344 He also explained Cheshire
Contractors had engaged LCJ Engineers on the basis they would be the quickest and
because Mr Everett had not paid them for their earlier work.345 An undated Bill of
Quantities, apparently relating to phase two by LCJ, was entitled:
“Riverviews Estate
For Cheshire Contractors Pty Ltd
Bill of Quantities”346 (emphasis added)
This is further evidence of the extent to which, in contrast to the phase one works,
Cheshire Contractors was actively involved in advancing the property development
project during the time of the phase two works.
[251] On 7 October 2014 Peter Ellis of LCJ Engineers emailed Barry Cheshire about
planning site inspections and seeking a “construction program” so LCJ could arrange
inspections at “hold/witness points”, listing those points as including “pipes prior to
backfill” and “proof roll of sub base”.347
[252] In cross-examination, Barry Cheshire was obviously reluctant to concede that since
Cheshire Contractors was both directing and conducting the works, there was no room
339 T3-23 LL7-13.
340 Ex 29.
341 T3-24 L3, T4-9 L30.
342 T1-83 L5.
343 T3-7 L5.
344 T3-7 L17.
345 T2-80 L27 – T2-81 L3.
346 Ex 1 Vol 1 Tab 9 p 12.
347 Ex 26.1.
-- 55 of 68 --
56
for a superintendent. He claimed they still needed a superintendent to deal with the
principal and the Council, and that Cheshire Contractors was not qualified to be and
did not have the necessary insurance to be a superintendent.348 It is noteworthy that
LCJ apparently continued to have a role as the engineers in phase two. For example,
in the operational works permit issued by HSC on 18 October 2014 the applicant for
the permit was described as LCJ Engineers.349
[253] On 13 October 2014 Barry Cheshire emailed Mark Everett offering his thoughts on
potential sale prices for lot 77.350 Mr Cheshire explained of this email, “It was a
suggestion of mine…so I could get paid”.351 Mr Everett’s recollection was that the
email followed him seeking Mr Cheshire’s advice on how to price lot 77.352 In any
event, that email, like so much of what occurred in 2014, is inconsistent with Cheshire
Contractors merely performing work for payment.
An operational works permit issues in the midst of works
[254] HSC, by correspondence dated 18 October 2014 addressed to Peter Ellis of LCJ
Engineers, granted an operational works permit.353 By this time works were already
underway on site, and had been since early August.
[255] It remains a mystery why Cheshire Contractors took the risk of lurching so
prematurely into works, not only without waiting to reach an agreement with Mr
Everett but also without waiting for the operational works permit to issue.
The joint venture documents are not finalised
[256] There had still been no completion of any joint venture negotiations by the time of
issue of the operational works permit, notwithstanding that the phase two works on
site were well advanced.
[257] On 16 October 2014 Mark Everett emailed Barry Cheshire seeking a copy of the dot
points he had provided in his email to Mark Everett’s solicitor Peter Elliott of 12
August 2014.354 Mr Everett acknowledged in that email that he probably should have
asked for the dot points “way before now”, consistent with the reality, which Mr
Everett was curiously reluctant to concede in cross-examination, that no joint venture
agreement had been finalised.355 Mr Everett received a response and, on his account,
became concerned that the proposed joint venture was weighted heavily towards
Cheshire Contractors.356 Mr Everett enlisted the assistance of his accountant in
relation to the proposed joint venture.357
348 T3-7 LL20-42.
349 Ex 1 Vol 1 Tab 7 p 49.
350 Ex 31 (also Ex 63).
351 T3-28 L17.
352 T7-63 L31.
353 Ex 1 Vol 1 Tab 7 p 49.
354 Ex 20.
355 Eg T8-23 L14.
356 T7-47 L9, T7-47 L17, T7-48 L44, T7-49 L4.
357 Ex 74.
-- 56 of 68 --
57
[258] On 11 November Mr Everett emailed Mr Cheshire a copy of the most recent draft
joint venture agreement.358 On 12 November 2014 Robert Carey, Mark Everett’s
accountant, emailed Mr Cheshire, saying, inter alia:
“I had a meeting with Mark yesterday to discuss the Riverviews Estate
joint venture arrangement. I have also had an opportunity to review
the Joint Venture Deed prepared by Peter Elliott (lawyer).
There are a number of matters in the Deed that require some
adjustments or amendments and Peter Elliott has forward to me a copy
of the draft agreement in Word format so that I can provide my input
in a “marked up” version. The following information is also required
for the JV Deed: …
6. Under the heading “Development costs”, there is an item
called “Interest”!! Can you please advise specifically what interest
that this refers to (JV borrowings, existing borrowings of the owner,
new JV borrowings!!)
7. Would you kindly forward the most recent development cost,
advertising and marketing estimates schedule for the initial stage 1 of
31 lots.
8. Please forward a copy of the Developer’s Public Risk
insurance policy as outlined on the proposed agreement at clause
5(ii)(b).
9. Both the Developer and owner have independently paid costs
towards the JV which will need to be reconciled. …”359
[259] Mr Cheshire emailed a response, at a time when he evidently did not realise a copy of
the draft had been emailed to him the day before. He wrote, inter alia:
“Thanks for your email.
I find it all very interesting but I have never received a copy of the
draft JV so really have no idea of what we are talking about.
Peter Elliott asked for some dot points to prepare the JV which I
supplied about 3 months ago on the 12/08/14.
Mark did not want to be involved at that stage so I sent what I thought
was relevant.
I did read the draft at Mark’s house some time back but don’t recall all
of the details. …
I realise this JV should have been in place before any work started on
the development, but due to time and financial restraint issues by the
NAB it was necessary for Cheshire to expend considerable money and
work to get to a position to enable land sales before certain time lines
were reached. …”360 (emphasis added)
[260] The following exchange occurred in cross-examination, after it was highlighted Mr
Cheshire had said in the above email that he realised the joint venture should have
been in place before any work started:
358 Ex 21.
359 Ex 40.
360 Ex 22.1.
-- 57 of 68 --
58
“What you’re referring to there is you were saying that you should
have had a written joint venture agreement in place before the work
started?--- Should have had an agreement in place.
Well, just to make it clear, I’m suggesting to you that you’re not
suggesting there wasn’t an agreement. There was an agreement, but
what you should have had was a written agreement?--- Sorry, there
was no agreement, but we should have had a written agreement.”361
[261] Mr Cheshire’s final answer in the above exchange was a concession of the obvious -
Cheshire Contractors’ work on phase two had been undertaken without any agreement
being in place.
[262] Mr Cheshire rejected the suggestion there had been a joint venture in contemplation
before he started work because Mr Everett did not otherwise have the money or
financial resources to pay for the works.362 This prompted the following exchange in
cross-examination of Mr Cheshire:
“Where was he going to get the money from?--- If we got the
subdivision to a stage where he could get people on blocks and get
sales of the blocks he would pay us out of the sales of the blocks, and
up until a week before this I think he was – still had potential buyers
visiting the site for him to sell the site for them, and he also had a JV
deal he was looking at with some – Devine and someone else, I think,
just a – I don’t know. Might have been a month before this.”363 (The
reference in that answer to “this” was to his email of 12 November
2014, Ex 22.1.)
[263] Once again, such evidence affirms Cheshire Contractors’ involvement in phase two
was speculatively premised on the development succeeding and sales paying for the
work performed.
[264] Later on 12 November there were email exchanges between Robert Carey and Barry
Cheshire by which a draft Joint Venture agreement was forwarded by Mr Carey and
it was agreed there was a need, as Mr Cheshire put it, to meet “to quantify and
document contributions and future commitments to the JV”.364
[265] On 17 November 2014, the last day of work recorded in the timesheets, Barry
Cheshire emailed Robert Carey and Mark Everett a number of tracked changes to the
draft joint venture agreement.365
Cheshire walks out
[266] Later, on Monday 17 November 2014, after the above email, there was a meeting
between Barry Cheshire and Mark Everett, and perhaps Mr Carey. On Barry
Cheshire’s account, after the meeting started Mark Everett said, “You realise this joint
361 T3-37 LL1-8.
362 T3-37 L21.
363 T3-37 LL23-28.
364 Ex 40 (also Ex 75), Ex 76.
365 Ex 22.2.
-- 58 of 68 --
59
venture’s only for 31 lots, not for the entire subdivision” to which Barry Cheshire
responded, “If that’s the case, well, I’m no longer interested” and he walked out of
the meeting. He testified his reaction was because a venture involving only 31 lots
would only cover costs, giving no margin and meaning there was “no point in being
there”.366
[267] On Mark Everett’s account of what occurred on the 17th, he was not satisfied with the
changes Mr Cheshire had suggested to the draft joint venture agreement including, on
his recollection, a replacement of a reference to mortgage with a reference to a lien.367
Mr Everett testified:
“I was getting crooker I suppose and I said to him, “Look, this is not
fair what is written here and we’ve got to try and sort something out”.
And as far as the mortgage or lien is concerned I can’t do that because
it’s not what is done in these sorts of arrangement where someone half
finishes a road. … I was really no better off than what I was before,
especially after Mr Cheshire said the work he done was only
temporary. And I said, “Look, let’s just – I can’t do it. Why don’t you
just buy the place?” and Mr Cheshire said, “We don’t want it”, and I
said, “Well, just do stage 1 and, you know, do what you want to do”,
and he says not enough money in it and I said, well, tell me what I
have to reduce the price of the land stage 1 to to make it viable for you,
but before you do that I’m going to ask you to redo your prices on the
roadworks and the civil works. At that stage there was four prices
floating around. And he said, “I’m not going to redo my prices so you
can show them to everyone else and get it done cheaper”. And Mr
Cheshire got pretty cranky and then I shut down.”368
[268] Mr Everett acknowledged in his evidence he had at this meeting proposed that the
joint venture only apply to the first stage rather than to the other stages.369
[269] On Wednesday, 19 November 2014 Mr Cheshire emailed Mr Carey saying, inter alia:
“Following our meeting on Monday, Mark requested another meeting
with me at his house on Tuesday. This was to discuss costs involved
in stage 1.
You may have gathered at our Monday meeting that I was a little
surprised when told the JV was applicable to the 31 lots on stage 1
only.
As I stated at the meeting on Monday there is very little profit in stage
1 as was planned at the outset of the project design and certainly not
enough to entertain a JV with the current exposure Cheshire
Contractors have with this venture. …
I have attached the rough outline of points to be included in the JV
which I sent to Peter Elliott that clearly shows the 81 lots being
included in the JV and as I have mentioned before Mark did not want
366 T2-74 LL1-13.
367 T7-49 L25.
368 T7-49 LL29-45.
369 T7-50 L2.
-- 59 of 68 --
60
any input at this stage although we had discussed the high upfront
costs of this project.
If the following stages, 2, 3 and 4 were not included:
- How would Cheshire Contractors be compensated for the
complete design and approval of the remaining 50 lots?
- What would prevent Everett from developing stages 2, 3 and 4
before stage 1 was sold and being in direct competition?
- Why would the JV on stage 1 pay for the upgraded road
requirements to service future stages?
- Why would the JV on stage 1 pay for the upgraded Ergon
requirements to service future stages?
- Who would pay for the highway upgrade?
The Joint Venture draft points were emailed to Peter Elliott on the
12/8/14 which is one week after we started work on the construction
work on the 5/8/14. The works were commenced before the revised
operational works permit was issued [in] an effort to obtain presales
within the timeframe as allocated by the NAB.
I therefore find it unacceptable that Mark has held back the JV
agreement until the 12/11/14 and that on Monday 17/11/14 informed
me that he now considers the JV is only applicable to stage 1.
I am willing to consider proposals that you may have with the JV
attached to stage 1 only but this would only be considered if it included
a guaranteed return appropriate to the costs and exposure including
interest for the unsecured debts currently owed by Everett to Cheshire
Contractors in 2011.
Failing an agreement we would have no option apart from taking the
necessary steps to receive immediate payment for the current debt.”370
[270] As with Mr Cheshire’s email of 12 November 2014 this email also alluded to the
phase two works having commenced in response to some financial pressure from the
NAB. Whereas the email of 12 November 2014 noted the works had commenced
before a JV was in place, the email of 19 November 2014 noted the works had
commenced before the revised operational works permit had been issued. These
hindsight acknowledgments are consistent with Cheshire Contractors having
embarked upon the phase two works prematurely.
[271] The content of an email by Barry Cheshire to Robert Carey of 24 November 2014 was
emblematic of the reality there had actually been no agreement. It noted the absence
of response since 19 November 2014 regarding the proposed joint venture agreement
and then said:
“As you are aware the Cheshire Group have a considerable investment
in the Riverviews Estate project and because of this investment we are
anxious to enter a suitable agreement between the parties involved.
370 Ex 40 p 99.
-- 60 of 68 --
61
As it is over 3 months since the draft points were forwarded to
Everett’s lawyer, I believe there has been ample time to produce a joint
Venture Agreement that suits all parties.
If I have not received a suitable proposal regarding these issues by
COB at the end of this week … we shall issue all appropriate invoices
and pursue payment by whatever means necessary. …”371 (emphasis
added)
[272] On 1 December 2014 Barry Cheshire emailed Mark Everett and Robert Carey,
referring to there having been “no attempt to sort out the JVA since I sent a draft dot
point proposal to Mark’s solicitor, Peter Elliott in August”.372 The email advised:
“As a result I hereby withdraw our offer of a joint venture agreement
and enclose our accounts for works performed less credits due. …
Please find attached invoices.”373
[273] The email attached copies of all of the phase one invoices and four of the phase two
invoices, namely invoices #688 of 1 October 2014, #701 of 26 November 2014, #702
of 26 November 2014 and #703 of 26 November 2014, all of which were for work
performed by Cheshire Contractors at Riverviews Estate.374
[274] On 3 December 2014 email exchanges between Mr Everett and his accountant’s
bookkeeper, Ms Brown, show they were already embarking upon scrutinising
information in support of the invoices. One such email by Mr Everett noted:
“[W]e have only seen construction invoices, I am predicting
management ones to follow…….just thinking.”375
Payments contemplated but not made
[275] On 6 January 2015 Mr Cheshire emailed Mr Carey advising, inter alia:
“I have accounts from the surveyor in relation to subdividing Mark’s
house on Lot 77 into a separate title.
I have paid $38,000 and expect a further $26,500 in accounts to
complete this exercise. Some of this survey overlaps onto the
subdivision.
Upon payment of the amount of $64,500 incl GST I will release all
documents etc related to the work performed by G Pozzi
Surveyors.”376
It was suggested to Mr Cheshire in cross-examination that his expectation of a further
$26,500 in accounts to complete the exercise was because it had not been completed
and the surveyor was still working, to which Mr Cheshire responded, “It was
completed, but they hadn’t sent the final account in.”377
371 Ex 41 p 101.
372 Ex 23.
373 Ex 23.
374 Ex 23.
375 Ex 104.
376 Ex 36.
377 T3-43 L9.
-- 61 of 68 --
62
[276] On 23 January 2015 Mark Everett emailed Barry Cheshire, referring to Barry Cheshire
having terminated the “proposed joint venture” on 1 December 2014 and notifying
expenditure beyond the date of termination “will be at your cost”. The email also
stated Mark Everett would be paying “costs incurred with the subdivision to 1
December 2014”, once verified by an accountant and bookkeeper.378
[277] By the time of the above email exchanges in December and January, the phase two
works had ceased.379 As mentioned above, the timesheets show the last work was on
17 November 2014.
[278] On 24 January 2015 Robert Carey emailed Barry Cheshire seeking access to
information to allow verification of costs through to 1 December 2014.380
[279] On 4 March 2015 $62,588 was paid to Cheshire Contractors to pay for surveyors fees
on Mr Everett’s behalf by his accountant Mr Carey.
[280] On 10 March 2015 Ms Brown, bookkeeper to Mr Everett’s accountant Mr Carey,
emailed Mr Carey and Mr Everett, writing:
“The current “official” outstanding amount to Cheshire is $815K,
however that includes “project management” fees of $118K, which are
yet to be confirmed as legitimate. It has also included the $62K
surveyor invoice, which you have now settled. The other invoices
charged, appear to be accurate, based on the timesheets that Cheshire’s
have provided. I’m waiting on Clinton to revise the accounts and send
an adjusted final total, however based on above, the amount
outstanding is $635K.”381 (emphasis added)
[281] Mr Everett accepted Ms Brown’s role had included checking through the invoices and
timesheets to verify what was outstanding.382
[282] On 26 March 2015 Barry Cheshire emailed Robert Carey requesting immediate
payment of $1,181,236.17, being the amount owing (seemingly calculated at
$919,389.50 as at that time plus interest).383
[283] On 30 March 2015 Robert Carey emailed Barry Cheshire, referring to an attempt
underway to have the project refinanced so as to include the outstanding development
costs to date.384
[284] On 1 April 2015 Robert Carey emailed Barry Cheshire, explaining a refinance
application had been lodged and that, once approved, Cheshire Contractors’ accounts
378 Ex 24.
379 T2-75 L35.
380 Ex 25.
381 Ex 105.
382 T9-39 L19, T9-40 LL1-7.
383 Ex 25.
384 Ex 25.
-- 62 of 68 --
63
would be settled. Barry Cheshire responded giving them two weeks’ grace, but no
payments were made.385
Everett not liable for phase two
[285] In light of the evidence reviewed above I find there was no agreement reached,
whether expressly or impliedly, regarding the essential contractual element of
consideration in respect of Cheshire Contractors’ performance of the phase two works
or work related thereto. With the acquiescent approval of Mr Everett, Cheshire
Contractors appear to have embarked entirely speculatively upon performing such
work in the hope that agreement regarding consideration for the work would
eventuate. It never did. The fact that works were embarked upon does not mean
agreement had been reached. In some cases, such a fact might support that inference,
but not in this case, not where there is such an abundance of evidence to the contrary.
[286] Further the fact that some payment was actually made by Mr Everett to Cheshire
Contractors in respect of the phase two works does not alter my view there was no
contract. Mr Everett would not be the first person to pay money out of a sense of
moral obligation, for instance a sense of otherwise being unjustly enriched. His
property did after all benefit from the works performed.
[287] To remove doubt, I also reject the notion that there was a joint venture agreement or
alternatively the agreement pleaded by Mr Everett as the “Riverviews Estate Contract.
The latter pleading built upon what I find was a stand-alone agreement regarding the
sale of lot one, to link it in as part of an agreement that Cheshire Contractors would
perform the phase two works for payment in accordance with the budget. In fact there
was no agreement reached regarding payment for performance of the works. The so-
called Riverviews Estate Contract did not occur.
[288] As to the alleged joint venture agreement, the term “joint venture” in this context is
nothing more than a badge to describe an agreement by which, if the agreement was
reached, the parties would each contribute to the progression of the property
development and would share in the profits of the development after deduction of
funds to recompense them for their contributions. The fact that the badge name was
bandied about between the parties does not mean there was an agreement reached. As
was confirmed by the High Court in John Alexander’s Clubs v White City,386 the name
“joint venture” ascribes no legal consequence and what must be considered is the
detail of what the parties have agreed and done.
[289] It is unnecessary to consider the categories of potential agreement discussed in
Masters v Cameron,387 for this is was not a case in which the parties agreed upon
contractual terms not yet dealt with by a formal contract. It is clear they were unable
to reach agreement on terms in the first place (Even if that conclusion is incorrect and
it can be said they reached an agreement of sorts to be formalised, such agreement
would in any event be in the unbinding third category discussed in Masters v
385 Ex 25.
386 (2010) 241 CLR 1, 21.
387 (1954) 91 CLR 353, 360.
-- 63 of 68 --
64
Cameron, namely one where no bargain is to be concluded without formalising a
formal contract).
[290] The conclusion there was no agreement is fatal to Cheshire Contractors’ claim in
respect of the outstanding payments invoiced in phase two. That is because the claim
is premised on proof of a further oral contract which it failed to prove. None of this
means works of some value were not provided during phase two but I am not here
concerned with a quantum meruit or unjust enrichment claim.
[291] Because of the failure of this aspect of Cheshire Contractors’ claim it is unnecessary
to consider Mr Everett’s allegations of Cheshire Contractors’ compliance breaches
and breach of contract for this aspect of the claim.
PART E – DETERMINATION OF AWARD AND OR SET OFF.
Everett’s offsetting claim
[292] The pleaded offsets in respect of phase one, premised on compliance breaches, have
failed in light of my findings regarding those alleged breaches.
[293] Mr Everett’s offsetting claim is otherwise made on the basis there was a breach of the
joint venture agreement.388 There was no joint venture agreement. The foundation
for the offsetting claim fails at the threshold.
December 2011 promise legal binding?
[294] It will be recalled that even if the December 2011 promise was legal binding it was
not of indefinite duration and is no longer a basis for Mr Everett to avoid liability for
paying for phase one. Nonetheless it remains necessary to determine whether it was
legal binding at all, for that likely impacts upon when interest ought be calculated
from.
[295] A number of arguments were advanced by Mr Everett. One was that the promise was
made when the contract was still in the executory phase because Cheshire Contractors
had agreed to undertake additional works requested by Mr Everett. I reject that. The
agreement to perform additional works requested by Mr Everett was not like an
ongoing retainer. It only related to the performance of works during the phase one
works. The phase one works had been completed by the time of the December 2011
promise.
[296] Another argument advanced was premised upon the invoices not having been
rendered by the time of the December 2011 promise but I have accepted Cheshire
Contractors’ position on that topic. It is true that the last of the phase one invoices
remained to be issued at that time but that has no material bearing on the argument
advanced.
388 Defendant’s amended written submissions [175].
-- 64 of 68 --
65
[297] Another argument advanced was that the December 2011 promise was binding as a
contract. How could that be? The rule in Foakes v Beer,389 that the consideration for
discharging an indebtedness cannot consist of a promise to pay later, remains good
law in Queensland.390 What consideration could there have been? Two fanciful
purported forms of consideration were contended for.391 One was supposedly
avoiding the “disbenefit” of forcing a failure of Mr Everett’s liquidity and consequent
incapacity to pay all creditors including Cheshire Contractors by Mr Everett being
given time to continue the development and raise enough money to pay. This falsely
frames what is no more than a promise to pay later as a benefit because it is better
than the option of not now being paid much of an existing debt. It is not consideration.
The other argument is that, if payment were not pressed for, Mr Everett could further
pursue the development, thus giving Cheshire Contractors “the opportunity to engage
in further potentially profitable work”. It is sufficient to dispense with this argument
by observing that it lacks evidentiary foundation – there was no holding out of an
opportunity for further work at the time the promise was solicited and made.
[298] Having dispensed with these drossy distractions I finally come to a more substantive
argument – that the promise and events which followed it gave rise to a promissory
estoppel in equity. The equitable doctrine of promissory estoppel was articulated in
Hughes v Metropolitan Railway Co392 by Lord Cairns LC thus:
“… if parties who have entered into definite and distinct terms
involving certain legal results - certain penalties or legal forfeiture -
afterwards by their own act or with their own consent enter upon a
course of negotiation which has the effect of leading one of the parties
to suppose that the strict rights arising under the contract will not be
enforced, or will be kept in suspense, or held in abeyance, the person
who otherwise might have enforced those rights will not be allowed to
enforce them where it would be inequitable having regard to the
dealings which have thus taken place between the parties.”
[299] The doctrine, which has been accepted in Australia,393 is a safeguard against a party
insisting on the party’s strict legal rights when it would be unjust for them to be
enforced in light of what has taken place in reliance upon the promise.394 In
observations approved by the High Court,395 McPherson J in Riches v Hogben396
explained the crux of the doctrine:
“It is not the existence of an unperformed promise that invites the
intervention of equity but the conduct of the plaintiff in acting upon
the expectation to which it gives rise.”
[300] Setting to one side the events of 2014, then long in the future, the change in Mr
Everett’s position, said to have occurred in reliance upon the December 2011 promise,
389 (1884) 9 AC 605
390 Amos v Citibank Ltd [1996] QCA 129.
391 Defendant’s amended written submissions [30].
392 (1877) 2 AC 439, 448.
393 Legione v Hateley (1983) 152 CLR 406
394 Combe v Combe (1951) 2 KB 215, 219.
395 Giumelli v Giumelli (1999) 196 CLR 101, 121.
396 [1985] 2 Qd R 292, 300-301.
-- 65 of 68 --
66
is his “entry into further obligations to the NAB”, allegedly making it impossible for
him “to return to the position anterior to the promise of time to pay”.397
[301] Consideration of what followed has a hypothetical flavour in that it is not suggested
Cheshire Contractors pressed for payment during the period of the promise’s
currency, that is, prior to 1 January 2014, although by late 2013 it was certainly
pressing in an active way for the project to be advanced. The hypothetical enquiry is
whether equity would have prevented them from doing so. If it would have then the
award of interest on the amount owing probably ought not claw back to that period
and ought only commence form 1 January 2014, a topic to which I will return.
[302] It is uncontroversial that what followed the making of the promise urged by the NAB
was the NAB continued Mr Everett’s existing loan facility. Mr Everett testified the
bank also approved the advancing of “a few hundred thousand dollars” to help with
holding costs and maintenance.
[303] In effect, the December 2011 promise helped Mr Everett to “keep the dream alive” of
holding onto his property and developing it. The following exchange in cross-
examination about the email of 20 December 2011 illustrates the point:
“Once you’ve received that email from Mr Cheshire and you
forwarded it onto the bank, your evidence yesterday was that you then
got going to go to the market to try to get some sales?--- That’s correct.
But the – what I’m putting to you – the proposition that I’m asking
you to consider is that you didn’t do anything different after getting
that email than you would have done in any event. You did the same
thing as you were always going to do anyway, isn’t – that’s true, isn’t
it?--- I suppose you’re right, yeah.”398 (emphasis added)
[304] That the December 2011 promise assisted Mr Everett does not however mean he did
not change his position on the strength of the promise. The evidence is not entirely
clear on the “but for” scenario, but it appears likely, absent the promise, that the bank
would not have continued its loan facility or at least would have confined it. At one
level that would have been to Mr Everett’s disadvantage but at another it would have
meant he did not extend his level of indebtedness to the bank. While acting on the
promise was helpful to him to keep his dream alive, it also meant he incurred a greater
level of debt to the bank than he otherwise likely would have, had the promise not
been made.
[305] In weighing these considerations, it is important to bear in mind the promise had a
direct causal connection with Mr Everett’s financial position vis a vis his bank. Not
without some hesitation, I conclude against the above background it would have been
inequitable to permit Cheshire Contractors to exercise its legal right to payment until
the elapsing of a sufficient period of time within which to advance the project to the
point of being able to raise money to pay for the phase one works from funds from
presales or sales. I have found as a matter of fact that period had passed by 1 January
2014. Coalescing with that finding I conclude by reason of the protection equity
would have given Mr Everett on account of him acting upon the December 2011
397 Defendant’s amended written submission [44].
398 T9-2 LL34-43.
-- 66 of 68 --
67
promise that Cheshire Contractors would have been estopped from seeking payment
for the phase one works prior to, and only prior to, 1 January 2014.
[306] A final argument advanced by Mr Everett is that a form of estoppel by conduct or
convention arose from the combination of the December 2011 promise and the 2014
sale of lot one. The argument as elaborated upon was that the promise became
irrevocable with the arrangement by which there was a credit of $220,000 given as
part of the sale of lot one. There is no doubt that Mr Everett changed his position in
entering into the 2014 sale and allowing the crediting of the deposit against his debt
to Cheshire Contractors. But that has nothing to do with the 2011 promise. That
promise, as Mr Everett would well have appreciated, was only a promise to postpone
pressing for payment for a sufficient period, which period I have found had ended by
1 January 2014. I additionally note the fact that Mr Everett entered an arrangement
later in 2014 by which he sold property at a fair market price and a payment would be
credited to reduce his indebtedness to Cheshire Contractors is entirely consistent with
him no longer acting on the strength of the December 2011 promise.
[307] There is no evidence supporting the implication of some new or varied promise that
by the arrangements for the sale of lot one and the crediting of the deposit against the
existing debt, Cheshire Contractors would not pursue payment of the balance of the
phase one debt. Perhaps that might have been a clause to which Mr Everett could
have aspired for a joint venture agreement but, as I have already found, no such
agreement was reached.
[308] The final matter to consider is the significance of the finding that the December 2011
promise was only good as a protection against demand for payment before 1 January
2014. Does it mean that Cheshire Contractors’ entitlement to interest on its award for
the outstanding phase one amount dates from the initial time of non-payment of
invoices when due or does it date from 1 January 2014?
[309] The evidence and submissions were largely silent on this issue. One can conceive of
cogent arguments either way but they are not well informed by evidence. The onus
in this context was on the plaintiff to have satisfied me both that interest was payable
upon unpaid invoices once past their due date and that the December 2011 promise
did not relieve Mr Everett of the burden of interest accruing upon the debt during the
currency of the promise not to seek payment of the debt. Given the dearth of relevant
evidence I am not so satisfied, with the consequence the outcome should favour the
party who does not carry the onus.
[310] The award in respect of the amount outstanding on the phase one works, of
$350,970.59 should therefore attract interest from 1 January 2014 to today, an amount
of $99,523. This gives rise to a judgment sum for that component of the claim – the
only component to have succeeded – of $450,493.59.
Orders
[311] It will be necessary to hear the parties as to costs unless they are agreed.
[312] My orders are:
-- 67 of 68 --
68
1. Judgment for the plaintiff in the amount of $450,493.59.
2. I will hear the parties as to costs if not agreed in the meantime at 9.15 a.m. on 24
October 2018.
-- 68 of 68 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2018/228