Augustine v S J Builders Pty Ltd [2018] QCAT 248
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Augustine & Anor v S J Builders Pty Ltd & Anor [2018]
QCAT 248
PARTIES: EBY AUGUSTINE
IRIN SUSAN AUGUSTINE
(applicants)
v
S J BUILDERS PTY LTD
SANTI PHILIP
(respondents)
APPLICATION NO/S: BDL232-16
MATTER TYPE: Building matters
DELIVERED ON: 1 August 2018
HEARING DATE: 30 May 2018
HEARD AT: Brisbane
DECISION OF: Member Gardiner
ORDERS: 1. S J Builders Pty Ltd and Santi Philip pay Eby
Augustine and Irin Susan Augustine the sum of
$57,913.57 in full and final satisfaction of this
matter by 9 August 2018.
2. Eby Augustine and Irin Susan Augustine file in the
Tribunal two copies and give S J Builders Pty Ltd
and Santi Philip one copy of any writte n
submissions and supporting documentation in
relation to costs by 31 August 2018.
3. S J Builders Pty Ltd and Santi Philip file in the
Tribunal two copies and give one copy to Eby
Augustine and Irin Susan Augustine of any
submissions and supporting documentation in
response to the application for costs by 21
September 2018.
4. Eby Augustine and Irin Susan Augustine file in the
Tribunal two copies and give to S J Builders Pty
Ltd and Santi Philip one copy of any submissions
in reply by 5 October 2018.
5. The application for costs be determined by the
Tribunal on the papers without an oral hearing not
before 5 October 2018.
-- 1 of 22 --
2
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – OTHER MATTERS – where
claim made by homeowners on statutory insurance scheme
– where further dispute about matters outside statutory
scheme – where defects and incomplete work – where
claims for liquidated damages and consequential loss of
rent
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
CONSTRUCTION OF PARTICULAR CONTRACTS
AND IMPLIED CONDITIONS – VARIATIONS – where
quantum of various variations in dispute
Queensland Building and Construction Commission Act
1991 (Qld) s 77
Ascot v Nursing & Midwifery Board of Australia [2010]
QCAT 364
Baltic Shipping Company v Dillon (1993) 176 CLR 344
Environmental Systems Pty Ltd v Peerless Holdings
(2008) 19 VR 358
GEC Alsthom Australia Ltd v City of Sunshine
Unreported, FCA, 20 February 1996
Hadley v Baxendale [1854] EWHC J70
Harrison and Anor v Meehan [2016] QCATA 197
Lyons v Dreamstarter Pty Ltd [2011] QCATA 142
APPEARANCES &
REPRESENTATION:
Applicant: Self-represented
Respondent: Self-represented
REASONS FOR DECISION
[1] This matter came before the tribunal for hearing on 30 May 2018. At the hearing only
the applicants appeared. The tribunal made a number of attempts to contact Mr Philip
by telephone but he could not be contacted and at that point in the hearing, the tribuna l
was not aware of any application made by Mr Philip to attend by phone or any
application for an adjournment.
[2] At that time, the tribunal was satisfied that proper notice of the hearing date had been
given to Mr Philip in the order sent to him dated 4 April 2018 and the hearing
proceeded and concluded on 30 May 2018.
[3] Although Mr Philip did not appear at the hearing, substantial material had been filed
by him in response to the application and evidence of Mr and Mrs Augustine and to
the building expert report. The building expert appeared at the hearing to assist the
tribunal in its deliberations.
-- 2 of 22 --
3
[4] The tribunal was satisfied that adequate evidence was before the tribunal to be
informed of the view of Mr Philip on the items claimed by Mr and Mrs Augustine and
that this evidence could be taken into account despite Mr Philip not being present.
[5] At the conclusion of the hearing the decision was reserved.
[6] On 6 June 2018, the tribunal was informed of an application received from Mr Philip
in the mail on 30 May 2018 for an adjournment of the hearing on medical grounds.
This was the day of the hearing. The mail is not completely processed in the registry
of the tribunal on any day until at least 10.30am. Receipt of this application by the
tribunal would therefore have been after the commencement of the hearing at 9.30am.
The tribunal was unaware of Mr Philip’s application at any time during the hearing
day and the application was not before the tribunal on the day of the hearing for
consideration.
[7] Mr Philip did not inform the tribunal using any other communication method that he
had posted an application.
[8] At the directions hearing of this matter on 2 May 2018, an examination of the record
shows that Mr Philip informed the Senior Member that he would be overseas for the
period leading up to the hearing. An oral application for an adjournment was made
but dismissed by the member at that time.
[9] Eby and Irin Augustine entered into a contract with S J Builders Pty Ltd to build a
new home for them in July 2014. After hand-over, Mr and Mrs Augustine identified
numerous defects with the build and a complaint was made to the Queensland
Building and Construction Commission (QBCC).
[10] Many defective works are being attended to through the QBCC process, but a number
of other defects alleged by Mr and Mrs Augustine are considered contractual matters
between the parties and stand outside the QBCC process.
[11] On 12 September 2016, Mr and Mrs Augustine filed an application for a domestic
building dispute in this tribunal to have a determination made about these contractua l
matters.
[12] All parties have provided detailed responses and statements of evidence supporting
their positions.
[13] In addition, Mr and Mrs Augustine have filed statements from an independent
building expert and from a rental property manager. Mr Philip filed his own statement
in response to the building expert. An order of this tribunal dated 2 May 2018 allowed
Mr Philip to rely on this statement as his own evidence – not that of an independent
expert.
[14] Mr and Mrs Augustine claim damages for breach of the contract by S J Builder s,
identifying what they say are defective or incomplete work arising under the contract.
They also seek damages for delays in completion of the build, rent lost and their costs
of this application.
[15] S J Builders through Mr Philip, deny liability for any defective or incomplete work,
rent lost and delays other than acknowledged in the final invoice to Mr and Mrs
Augustine. Mr Philip says that many of the allegations are outside the agreed contract
-- 3 of 22 --
4
or that he was denied access for maintenance or for restitution. He also alleges the
company is owed money for variations.
[16] Mr and Mrs Augustine intended to rent out the property although they did live there
for a short period once they took possession on 22 October 2015.
[17] There were building covenants attached to the land. Final approval in line with those
covenants was received from the developer on 25 September 2014.
[18] Mr and Mrs Augustine say this final approval was delayed because the first plans
drawn by S J Builders did not conform to the covenants and were rejected by the
developer.
[19] After some required amendments to the council plans, the building permit was finally
granted by the relevant Council in October 2014. There is a discrepancy between the
parties as to the exact date of approval although both parties agree it was in October
2014. Construction started on 3 November 2014.
[20] At the hearing Mr and Mrs Augustine identified their outstanding claims by way of a
schedule.1 The matters initially claimed at the beginning of the matter had been
reduced as S J Builders had attended to some rectification works, these items had since
been removed by Mr and Mrs Augustine from the final claim. Mr and Mrs Augustine
relied on the report of the expert to identify any items they say are defective or
constitute incomplete work and the responsibility of S J Builders.
[21] The further outstanding claims were for liquidated damages; variations from the
contract amount; cleaning costs; rental loss; costs including the application fee, legal
and expert expenses and witness fees.
[22] Each of these will now be addressed.
Defects and Incomplete work
[23] Mr Philip provided no independent expert opinion of the defects or otherwise of the
work and no costings of any potential remediation. Where I find remedial work must
be undertaken, the only evidence I have before me is that of the building expert and I
will accept that evidence.
[24] Where evidence is provided by Mr Philip on individual items this evidence is taken
from Mr Philip’s statement undated2 but provided in response to the report of the
building expert.
Driveway
[25] The building expert gave evidence that the driveway had been cut to remediate an
electrical issue. He said the homeowners initially disagreed with the cut of the
driveway and the builder offered to widen the driveway for compensation which was
agree to. The remediated section is now not bonded or fixed to the older pour and the
colour match is wrong. There has been settlement in the new work creating a trip
hazard.
1 Exhibit 10.
2 Exhibit 11.
-- 4 of 22 --
5
[26] If the driveway was to be removed and repoured, the homeowners would have to pay
for the widened section if they wanted to replace the existing structure.
[27] Mr Philip submitted S J Builders is not responsible for the widened section. This
accords with the building expert’s view and I accept these submissions.
[28] I accept there is a defect and accept the costing of remediation set by the build ing
expert at $3,244.06.
Front Facade Design
[29] The building expert gave evidence that the opening to the top of the wall on the left
hand side of the entry porch was not created as shown in the drawings. No variatio n
have been agreed this.
[30] Mr Philip says the opening in the front facade wall of the entry porch could not be
done as it would require cutting the structural load bearing frame of the house. It was
discussed and agreed with the client during construction and prior to completion. He
says the building certifier approved the frame stage inspection with this amendment
and issued a form 21 upon completion. Mr Philip believes there is also no change in
the energy rating as it was approved by a building certifier and that this was
communicated to the client during that stage.
[31] Mr and Mrs Augustine deny approving any change. The building expert denies any
load bearing effect.
[32] In the absence of a written variation, I accept there is a defect and accept the costing
of remediation set by the building expert at $2,296.20.
Kitchen splashback
[33] The building expert gave evidence that the circumstances of the colour choice for the
splash back is a matter for this tribunal.
[34] Mr Philip gave written evidence that the splash back glass was ordered on 18 August
2015 with the selected colour "Bright delight". Mr and Mrs Augustine were asked to
advise of any colour change immediately. Mr Philip says despite various reminders,
the request to change the colour was received on 8 September 2016. He says the
supplier had already completed the application of the colour. The site manager echoes
this evidence.3
[35] Mr and Mrs Augustine say they selected “whisper white with sparkles” during the
construction process and that the site manager was informed in August 2015 in a
conversation. They say the site manager then went on holidays. Mr and Mrs
Augustine did not recall a conversation on 8 September 2016.
[36] In the absence of any clear evidence, I accept that there is a clear communicatio n
breakdown between the parties and I will apportion the change of the glass between
the parties on a 50-50 basis. Using the costings of the building expert, half is set at
$264.05.
3 Exhibit 9.
-- 5 of 22 --
6
Three step cornices on garage, laundry and pantry
[37] The building expert gave evidence that three step cornices are generally only used in
the habitable parts of that building and that in other areas such as the garage, laundry
and pantry the less expensive cove cornices are used.
[38] The building expert said the builder appears to have intended to only use the three
step cornices as described above but this is not made clear in the contract.
[39] Mr and Mrs Augustine say they expected three step cornices throughout the home.
[40] Mr Philip says the inclusion states three step cornice/coved cornices. He says it was
meant and agreed to install three step cornices in the common living and habitable
area and coved cornice in the non-habitable rooms.
[41] I accept that the use of both three step and coved cornices in different parts of the
build are a normal building practice and there is no requirement under the contract for
three step cornices in every room.
[42] I dismiss this item claim.
No linen chute
[43] Mr Philip says during the design stage and at the approval of the working drawings,
it was discussed and approved that a laundry chute was not possible as the media room
is above the laundry. A laundry chute was also not shown in working drawing. He
further says Mr and Mrs Augustine requested many changes after signing the contract
and during the working drawing stage, including changes in the master bedroom
ensuite, the powder room, walk in robe, kitchen and bed room 4 ensuite and bed room
4 walk in robe. The linen chute was cancelled at that time. Mr Philip says all these
changes were done at the request of Mr and Mrs Augustine without any changes to
the contract amount.
[44] Mr and Mrs Augustine say S J Builders did not advise a laundry chute could not be
constructed and no credit has ever been given for it not being installed.
[45] The building expert gave evidence that he was not provided with a written variatio n
for the removal of a chute.
[46] I accept there is no written variation for the removal of a chute from the contact and I
therefore accept an allowance must be made for its inclusion in accordance with the
contract. The cost is set by the building expert at $266.63.
No wash basin in upstairs WC
[47] Mr Philip says the wash basin is shown only in powder room on the ground floor, not
in first floor WC. He says it was a writing error in the inclusion list mentioning wash
basin in all WCs. The vanity is not shown in the contract design and working drawing
and it was mutually agreed that the vanity would only be installed in ground floor
powder room. The installation was as per drawing approved by Mr and Mrs
Augustine.
-- 6 of 22 --
7
[48] The building expert gave evidence that based on industry practice, he is of the opinion
that a virtuous china wall basin, with matching tapware, plumbing and drainage
should be installed in the upstairs WC.
[49] I accept the evidence of the building expert and will allow this item set at a cost of
$1,206.52.
Cabinets not as per design
[50] The issue identified by the building expert is that the drawings show the vanity
extending wall to wall. The wall that separates the WC from the vanity has been
removed and substituted with a glass panel so that the wall becomes a glass panel.
The builder provided a sketch showing the vanity unit design.
[51] The design shows a separation between the vanity unit and the glass panel. What has
been constructed is the vanity unit butting against the glass panel. To seal the vanity
unit against the glass a silicone sealant has been applied. This is clearly visible from
the toilet side of the glass.
[52] Mr and Mrs Augustine say the vanity should have been constructed as shown in the
sketch4 and not manufactured two metres wide.
[53] The building expert gave evidence of an unsightly finish and that what would be usual
building practice was leave a gap there for the purpose of cleaning.
[54] I accept the evidence of the building expert and will allow this item set at a cost of
$4,930.63.
Poor paint finish in garage
[55] Mr Philip says he has no objection to this claim if the matter is not attended to under
the QBCC insurance claim.5
[56] The claim was refused by the QBCC.6
[57] The building expert gave evidence that rectification involved stripping and re-
applying an epoxy finish. I accept the evidence of the building expert and will allow
this item set at a cost of $2,291.83.
Wrong size door in garage
[58] Mr Philip says all the internal doors installed are 2340 mm. Only the external door at
this location was 2040 mm high. Normally, an external garage door is 2040 mm high.
Mr Philip says it was an error of the draft person and that this was discussed with Mr
Augustine and he agreed to the change.
[59] Mr Augustine denied these discussions took place.
4 Expert Building Report attached to Exhibit 4, pg 28.
5 Exhibit 11, page 3, item 15.
6 Exhibit 7 Annexure 12 Item 22.
-- 7 of 22 --
8
[60] There is no variation for the wrong sized garage door. The building expert gave
evidence that the door should be replaced to reflect the one specified in the drawings
and the inclusions list.
[61] I accept the evidence of the building expert and will allow this item set at a cost of
$604.25. This item has been declined by the QBCC under the insurance policy.7
Poor paint and plaster finish
[62] The building expert gave evidence that only a sealing and undercoat had been applied
to the relevant walls. No top coat was evident on his inspection. I accept the evidence
of the building expert and will allow this item set at a cost of $13,050.38.
Tiles not laid to design
[63] Mr and Mrs Augustine say the wall tiles in the ensuite were to be laid floor to ceiling
and were to be a brown metallic tile.
[64] The building expert gave evidence that the updated tiling plan is inconclusive. The
marked up floor plan seems to indicate the wall in question is shaded separately to the
rest of the room. In the building expert’s professional opinion it would be very rare
to see a single wall not tiled to the same height as the rest of the room, particularly in
a home with ‘high end’ finishes. It would be expected that a prudent builder would
tile to match the existing height of the other walls.
[65] Mr Philip says tiles were laid in accordance with the selection by the owner and was
a variation. This is denied by Mr and Mrs Augustine.
[66] I am satisfied on the balance of probabilities the height of the tiles should have
matched the rest of the room. I am not satisfied there is sufficient evidence before the
tribunal to conclude there was agreement on the colour of the tiles. I accept the
evidence of the building expert I will allow the cost of the extra tiling at $302.54.
Window locks are rusty
[67] The building expert gave evidence that the home is located within one kilometre of
the coast. The external door hinges, window and door furniture are manufactur ed
with metal surfaces not suited to the salt air environment to which the property will
be exposed.
[68] The building expert says Mr and Mrs Augustine advised Mr Philip of the corrosion as
part of the defect list issued in October 2015, prior to occupation.
[69] The building expert gave evidence that the hinges and door furniture are not ‘fit for
purpose’ and should be replaced with stainless steel items.
[70] Mr Philip says the window locks were not rusty at the time of hand over and they
became rusty after the maintenance period. He says this is the responsibility of the
owners.
7 Exhibit 7 Annexure 12 Item 24.
-- 8 of 22 --
9
[71] As the rusting was first identified in the defects period, I do not accept Mr Philip’ s
evidence.
[72] I accept the evidence of the building expert I will allow the cost of replacing hinges,
window and door furniture at $1,781.16.
Intercom fitted in wrong position
[73] Mr Philip says the position of the intercom was fixed after discussion and verbal
consent from the owner. This is denied by Mr and Mrs Augustine.
[74] The building expert gave evidence that there is no written variation that he has seen
and the intercom should be re-located to the position shown on the contract drawings.
[75] I accept the evidence of the building expert I will allow the cost of the extra tiling at
a cost of $688.64.
Towel rail in upstairs ensuite
[76] Mr Philip says the towel rail was installed as per industry standard and not reported at
the time of handover or during the 3 month maintenance period. He says he is not
sure how the rail is not level. He believes S J Builders is not responsible.
[77] The building expert gave evidence that the towel rail is not level and as an installatio n
defect, this should be rectified. I accept the evidence of the building expert I will
allow the cost of the extra tiling at $33.78.
Hot and cold kitchen tap back the front
[78] This is clearly an installation defect and I accept must be corrected in the interests of
safety.
[79] I accept the evidence of the building expert and I will allow the cost of the rectificatio n
of the taps at $36.20.
Gap in bench top in kitchen
[80] This item has been declined by the QBCC under the insurance policy as a matter of
measurement, not building work.8
[81] The building expert gave evidence that the upright gas appliance is not flush and
protrudes beyond the stone bench top. The gas fitting should be located to align with
the open space for this fitting at the rear of the appliance so the appliance can sit back
hard against the wall. The builder has attempted to force it back to fit the rear space
and has bent the back panel. The appliance needs to be pulled the out and repositioned.
[82] Mr Philip says the owner selected a free standing cooking appliance and the usual gap
from the wall to give a clear space was allowed for gas fitting elbow which allow
removal and maintenance of the cooking appliance in the future. If the appliance is
moved further back, the elbow may get damaged. Hence, Mr Philip believes the
8 Exhibit 7, Annexure 12 Item 8.
-- 9 of 22 --
10
current installation is correct and that the Commission’s inspection report dated 23
May 2016, confirms item number 18 is not defective work.
[83] I accept the evidence of the building expert I will allow the repositioning cost at
$45.00.
Unsafe power points in bathroom
[84] The building expert gave evidence that he believed there was a mistake in the upstairs
bathroom where the electrician placed a blank plate over what was a power point. The
power point has now been relocated but the blank plate behind the sink should be
removed and replaced by a tile.
[85] Mr Philip says a compliance certificate has been issued by the electrician and the
building inspector. He states this item was not reported at handover or during the
maintenance period.
[86] I accept that this is a minor matter but agree with the building expert that the matter
should be rectified. I accept the evidence of the building expert I will allow the cost
of rectification at $302.54.
External doors
[87] This item was withdrawn by Mr and Mrs Augustine at the hearing.
Front deck
[88] The building expert gave evidence that no gap exists where the deck abuts the exterior
of the building. No termite barrier is visible between the deck and the exterior wall –
unlike the rear deck where a Kordon physical barrier was sighted.
[89] Mr Philip says installed a Kordon physical barrier was installed and provided enough
gap between deck and building. A compliance certificate has been issued for termite
treatment and relevant building certifier inspected and approved the work and issued
Form 21.
[90] In the absence of strong evidence from the building expert and based on the evidence
of Mr Philip I am not satisfied on the balance of probabilities the barrier is not in place
and I will disallow this claim.
Window sills
[91] The building expert gave evidence that reconstructed window sills on two windows
in the kitchen and the media room still don’t have the right slope away from windows.
Remedial work has been undertaken once, but the contractor builder has introduced a
slope of six degrees. A fifteen degree slope is what is typically required. Since then,
the Commission has not re-inspected to the knowledge of the building expert.
[92] In the opinion of the expert building inspector, this is a category one defect and should
be reported to the Commission as water egress is possible, although this does not
appear to have occurred so far.
[93] Mr Philip says this item has been fixed by the sub-contractor when completing
external cladding work and has been approved by the Commission.
-- 10 of 22 --
11
[94] I am satisfied on the balance of probabilities that this item should be referred back the
Commission and I will disallow this claim.
Staircase
[95] Mr Philip says the staircase was supplied and installed by the sub-contractor during
construction and all the works were done as per manufacturer's specification.
[96] The building expert gave evidence that on inspection the stairs were found to squeak.
He says the wedges to the treads and rises are on one side only. In his view, the stairs
were made too wide and cut down on one side on site to fit.
[97] It will be necessary to put wedges in the treads and rises on the missing side of each
stair to enable adjustment of the stairs to stop the squeaking.
[98] The photographs provided in the building report show a lack of treads and rises on
one side of each stair.
[99] I accept the evidence of the building expert I will allow the cost of remediation at
$151.10.
Rear balcony
[100] The building expert gave evidence that the outer edge of the balcony has been installed
flush. This is not in accordance with the Building Code and the Australian standards
which require a 20 mm edge.
[101] Mr Philip does not object to this item.
[102] I accept the evidence of the building expert I will allow the cost of the remediation at
$2,130.81.
Downstairs powder room
[103] The tiles in this area do not match the adjoining living room tiles. The updated tiling
plan shows these tiles to be the same as the hallway tiles.
[104] Further, the downstairs powder room requires a metal angle water stop to be installed
in this designated ‘wet area’ as required by the Building Code and the Australia n
standards AS3740-2010.
[105] Mr Philip says these tiles were installed as per the owner’s selection but provides no
evidence of this choice.
[106] I accept the evidence of the building expert form the tiling plan and will allow the cost
of the remediation at $770.94.
Final amount
[107] The total amount to remediate the above items is $34,397.26
[108] These costs, as supplied by the building expert, are exclusive of an allowance for the
builder’s margin and GST. The evidence of the building expert was that both of these
percentages should be added as a normal cost incurred as part of the remediatio n
-- 11 of 22 --
12
process. I accept this evidence and will allow additional to the remediation amount,
a builder’s margin of 15% and GST at 10%, totalling 25%.
[109] The final amount for this category is $42,996.57.
Lost rent - A consequential loss?
[110] Mr and Mrs Augustine claim loss of rent under the contract. It was their evidence that
this home was always intended to be an investment property. They took possession
of the property on 22 October 2015 and rented the property from 4 January 2016.
[111] Evidence of the rental return from this date was given by the rental manager for the
agency managing the property. The property manager said:
(a) The weekly rental for the first tenancy agreement was $800 per week;
(b) The first tenants were under a lease from 4 January2016 to 16 January 2017;
(c) There was a rental reduction from 28 January 2016 to 3 March 2016 of $50 per
week due to ongoing issues including water entering the property and build ing
repairs;
(d) The tenants broke the lease on 15 August 2016 but rent was paid up until 4
September 2016;
(e) The second and current tenants pay $750 per week;
(f) Due to ongoing building works, this rent has at times been reduced depending
on the severity of the building issues as follows:
(i) In December 2016, a once off reduction of $1,000;
(ii) From 5 September 2016 to 12 March 2017, a weekly reduction of $50;
(iii) From 13 March 2017 to 12 November 2017, a weekly reduction of $375;
(iv) From 18 December 2017 and continuing, a weekly reduction of $50.
[112] The property manager opined that if there were no leaks or other defective build ing
work issues with the property, the weekly rent in the current market should be $750.
[113] It is reasonable, in her view, to reduce the rent paid by tenants in properties where
there is a loss of amenity, building defects and issues with quiet enjoyment of the
property. The property was subject to ongoing rectification works and as such tenants
were entitled to a reduction in rent.
[114] The total rent lost up until the date of the hearing was $6,425.00.
Discussion
[115] Mr and Mrs Augustine are claiming this loss of rent as a consequential loss from the
building contract.
-- 12 of 22 --
13
[116] The Appeal Tribunal9 has previously provided guidance concerning ‘consequentia l
loss’ explaining this category of claim as first subject to the rules in Hadley v
Baxendale:
… prescribe the measure of damages in respect of breach of contract to include
not only damage naturally resulting from the breach ("i.e. according to the usual
course of things") but also damage which might "reasonably be supposed to
have been in the contemplation of both parties, at the time they made the
contract, as the probable result of the breach of it". Additional or special
knowledge known to both parties may widen or contract the scope of liability
for breach. These rules have been merged in a single principle.10
[117] The Appeal Tribunal also point to a distinction between normal loss and consequentia l
loss. Normal loss is loss that every plaintiff in a like situation will suffer.
Consequential losses are anything beyond the normal measure, such as profits lost or
expenses incurred through breach.11
[118] The learned Appeal Tribunal members further refer to Environmental Systems Pty Ltd
v Peerless Holdings,12 where the Victorian Court of Appeal held:
In my view, ordinary reasonable business persons would naturally conceive of
“consequential loss” in contract as everything beyond the normal measure of
damages, such as profits lost or expenses incurred through breach. Despite the
construction which has been put on “consequential losses” by cases such as
Millar and Croudace, it would be unrealistic to suppose that the appellant and
the respondent employed the expression “consequential loss” in cl 8.9 of the
agreement advisedly in that sense. It is more likely in this context that they
intended the expression to have its ordinary and natural meaning. Accordingly,
I would construe the expression “consequential loss” in cl 8.9 as intended to
have that meaning. Read in the light of the contract as a whole, and giving due
weight to the context in which the clause appears, including the nature and
object of the contract, I see no ambiguity which as a matter of principle would
warrant a departure from that view. It follows as I see it that, although the
judge’s approach in this case was in accordance with the English cases, it was
not correct to construe “consequential loss” as limited to the second rule in
Hadley v Baxendale.
[119] The learned Appeal Tribunal members point to GEC Alsthom Australia Ltd v City of
Sunshine which held that:13
…the term consequential loss connotes a loss at a step removed from the
transaction and its immediate effects.
[120] I am satisfied that this claim is more than a normal loss arising from a domestic
building contract and is characterised more properly as a consequential loss.
9 Harrison and Anor v Meehan [2016] QCATA 197 starting at [95].
10 Baltic Shipping Company v Dillon (1993) 176 CLR 344.
11 Harrison and Anor v Meehan [2016] QCATA 197 starting at [96].
12 (2008) 19 VR 358.
13 GEC Alsthom Australia Ltd v City of Sunshine (Unreported, FCA, 20 February 1996, Ryan J).
-- 13 of 22 --
14
[121] Mr and Mrs Augustine gave oral evidence at the hearing that it was their intention to
rent the house. Yet for the first two months after taking possession of the property
they did reside in it.
[122] I do not accord a lot of weight to this fact. What is more important is whether renting
the home on completion was within the contemplation of both parties at the time they
made the contract (the company through Mr Philip and Mr and Mrs Augustine) and
that loss of rent would be a probable result of a breach of the contract (my emphasis
added).14
[123] Mr Philip’s only response to the claim for lost rent is that it does not form part of the
contract.15
[124] There is no evidence before me that the intention of Mr and Mrs Augustine to rent the
property was known to the builder at all. Likewise, there is no evidence to show it was
within the contemplation of both parties, (in particular the builder) at the time they
entered into the contract.
[125] On that basis this claim for rent lost must fail.
Liquidated damages
[126] Mr and Mrs Augustine claim for liquidated damages for 204 days under the contract
item 18 which allows $50 for each day of delay in achieving practical completion.16
[127] The clause requires the builder to pay these damages if the builder fails to bring the
works to the practical completion stage by the date set in the contract for that stage
and ends on the day practical completion is reached or the owner takes possession of
the works, whichever first occurs.
[128] The contract was signed on 31 July 2014. Item 8 of the contract allowed a
construction period of 241 days. Item 9 fixed the date of commencement as 1
September 2014 and practical completion as 31 March 2015 – 211 days after the
commencement of construction (item 10). The building permit period was set at 19
days which means construction should have commenced on 1 September 2014. In
reality, building approval was gained on 9 October 2014. The difference is 37 days
(excluding both days).
[129] Mr and Mrs Augustine say there was delay in getting approval to commence build ing
as the builder did not conform to the developer’s covenants when drawing the plans
and the developer would not consent to the plans on two occasions until they were
amended. The developer’s approval was gained on 25 September 2014. Mr and Mrs
Augustine say the covenants were supplied to the builder before the contract was
signed.
[130] Once the developer’s consent was given, the building permit was granted dated 9
October 2014.
[131] There were 2 steps to be able to commence the building works – first developer’s
approval and second council approval. There does not seem to be an unreasonable
14 See para 116 above
15 Exhibit 2, Annexure para 12.
16 Contract clause 18.
-- 14 of 22 --
15
delay on gaining council approval. On the dates provided by Mr and Mrs Augustine
this took about 2 weeks. The time allocated in the contract by the builder was 19 days.
Minus two weeks or 14 days, the builder seems to have allowed five days for the
developer’s approval.
[132] This seems to be a short period. If the equivalent time is reasonably allowed for the
developer as was taken by the council, the whole building permit period should have
objectively been about 4 weeks or 28 days. I will allow this 28 day period as a
reasonable period for this stage of the building process.
[133] I am satisfied therefore, on the balance of probabilities that that the extra delay of 9
days was due to the delay in the developer’s consent. In the absence of any comment
from the builder, I accept the evidence of Mr and Mrs Augustine that this was due to
the plans not being drawn in conformity the developer’s covenants and will allow a
period of nine days in the calculations of liquidated damages under the contract as
attributable to this delay.
[134] Work commenced on site on 3 November 2014. The clause 8 period of 241 days
minus the 19 days allowed for building approval leaves a construction period of 222
days or 31 weeks 5 days. Counting forward this ends (rounded up by one day) on 5
June 2015.
[135] I am satisfied that the intervening three weeks from council approval is not an
unreasonable period for construction preparations between approval and
commencement.
[136] The building was handed over on 22 October 2015. The difference between 5 June
and 22 October (excluding both days) is 19 weeks and 4 days or 137 days. Added to
this is the extra 9 days referred to above becoming a total of 146 days.17
[137] At $50 per day this is $7,300.00.
[138] I am satisfied this is an appropriate amount on balance between the parties to this
dispute and will allow this amount as the claim by Mr and Mrs Augustine for
liquidated damages set at $7,300.00.
Variations from the contract amount
[139] Mr and Mrs Augustine gave evidence that the total contract price was $370,000. This
amount has been paid to the builder.18
[140] At the conclusion of the build, the builder provided a final tax invoice.19 Mr Augustine
identifies a number of items on the final tax invoice of variations from the builder
dated 1 October 201520 that he disputes, in particular landscaping provisional suMrs
not used.
[141] The items on the tax invoice that are disputed or credited will now be addressed.
17 The builder allowed an amount of $4,600 for a delay of 92 days - see Annexure to Exhibit 2.
18 Exhibit 5 para 34.
19 Exhibit 13.
20 Exhibit 13.
-- 15 of 22 --
16
[142] Mr and Mrs Augustine say the contract was varied by requests from them for upgrades
of the following items:
(a) Wiring for OH projector $ 385.00
(b) Electrical switch upgrades $ 1,525.00
(c) Additional LED lights $ 1,500.00
(d) Additional lights rear side $ 200.00
(e) 2-way switches $ 200.00
Total owing to builder $3,810.00
[143] Mr and Mrs Augustine say the contract was also varied by credits to them for work
not carried out by the builder in the following items:
(a) Free standing bath tub $ 400.00
(b) Bath hardware $ 300.00
(c) Kitchen appliances $ 439.00
(d) Letterbox $ 51.00
(e) Fencing and retaining wall $ 5,500.00
(f) Additional light fittings $ 3,000.00
(g) Landscaping $ 3,500.00
Total owing to owners $13,190.00
[144] Mr and Mrs Augustine say the other variations in dispute are:
(a) Water filter dispenser
Mr and Mrs Augustine say there is one installed but not listed in the inclusio ns
list.21 They say they asked for a quote before deciding whether to install but did
not receive it. They say there were given an approximate cost verbally but it
was ordered and fitted by the builder without their permission.
This item is not included in the inclusions list. Although there is a dispute
around the installation of this item, I am satisfied that Mr and Mrs Augustine
have the benefit of this item and the builder should be paid for it. I will allow
the item as an additional payment to the credit of the builder fixed at $450.00.
(b) Scratch coat rendering
21 Inclusions list annexed to contract dated 31 July 2014.
-- 16 of 22 --
17
Mr and Mrs Augustine say the builder applied scratch coat rendering but say the
rendering has to be re-applied and the scratch coat rendering could not be re-
applied so that now it is a normal smooth rendering only.
I am satisfied on the evidence before me that Mr and Mrs Augustine do not have
the benefit of this item and the builder should not be paid for it.
(c) Glass balustrades for stairs
The inclusions list shows “Hardwood timber stairs with polished finish from
builder’s range”. Mr and Mrs Augustine say the range shown to them included
glass balustrades – which they chose.
I am satisfied this glass was chosen as described by Mrs Augustine from the
builder’s range and is included under the contract as an inclusion. I will not
allow this item as an additional payment to the credit of the builder.
(d) Under counter mounted sinks for kitchen
Mr and Mrs Augustine say the kitchen sink is under mounted because the builder
allowed them to choose how the sink would be installed. They say they were
not told there was an extra charge to under mount the sink.
I am satisfied that Mr and Mrs Augustine have the benefit of this item and the
builder should be paid for it. However, as the cost was not discussed on the
evidence of Mr and Mrs Augustine, I will allow the item as an additiona l
payment to the credit of the builder fixed at half the cost claimed $150.00.
(e) Stone top an cabinets at WI Pantry
The inclusions list under “Kitchen” shows the inclusion of a 20 mm thick stone
bench top in the pantry. I am satisfied these are included under the contract as
an inclusion and will not allow this item as an additional payment to the credit
of the builder.
(f) Concealed flush tank WC for powder room
Mr and Mrs Augustine asked for a quote for this installation as the room is small.
The room size required this type of installation. I am satisfied that Mr and Mrs
Augustine have the benefit of this item and the builder should be paid for it. I
will allow the item as an additional payment to the credit of the builder fixed at
$95.00.
(g) Plain concrete at rear of house
Mr and Mrs Augustine say there is a slab of concrete outside the rear of the
house that is part of the landscaping. They say they were told it would cost
$800. No costing of the concrete laid was in evidence.
I am satisfied that Mr and Mrs Augustine have the benefit of this item and the
builder should be paid for it. I will allow the item as an additional payment to
the credit of the builder fixed at half the sum claimed at $1,000.00.
(h) Glass door LIN 1 for WIR
-- 17 of 22 --
18
Mr and Mrs Augustine say this was a particular door and not covered in the
inclusions list. Mr and Mrs Augustine say they were told in an email the extra
cost would be $68.00. I accept this evidence.
I am satisfied that as Mr and Mrs Augustine have the benefit of this item and
the builder should be paid for it. I will allow the item as an additional payment
to the credit of the builder fixed at $68.00.
(i) Speakers for the music system
The inclusions list shows “Hills music hub with cabling and sockets”. Mr and
Mrs Augustine say this included the speakers claimed here by the builder. I
accept this evidence.
I am satisfied this item is included under the contract as an inclusion and will
not allow this item as an additional payment to the credit of the builder.
(j) Vanity lights above mirror
Mr and Mrs Augustine say these were not installed at all. I accept this evidence
and will not allow this item as an additional payment to the credit of the builder.
(k) Skirtings from 67 to 92 mm
Mr and Mrs Augustine say they did not request this enlargement.
I accept this evidence and will not allow this item as an additional payment to
the credit of the builder.
(l) Splashback with sparkles
Mr and Mrs Augustine say the splashback was installed without sparkles. I
accept this evidence and will not allow this item as an additional payment to the
credit of the builder.
(m) Upgrade the entrance porch to timber decking
Mr and Mrs Augustine say they did not ask for a deck at the front of the house
but one was installed and that the builder said there was no difference between
tiling and timber for the surface. No variation has been signed for this porch –
in fact, no variations are in evidence at all.
I am satisfied that Mr and Mrs Augustine have the benefit of this item and the
builder should be paid for it. I will allow the item as an additional payment to
the credit of the builder fixed at $500.00.
(n) Upgrade to phase 3
I accept this is a mistake by the builder and not an additional item. I will
disallow this claim.
(o) Fix bath mix
-- 18 of 22 --
19
Mr and Mrs Augustine say in one ensuite there was a particular bath tap mixer
that was supplied by Mr and Mrs Augustine. The builder installed the hardware.
I am satisfied this is a responsibility of the builder under the contract as an
inclusion and will not allow this item as an additional payment to the credit of
the builder.
Cleaning Costs
[145] Mr Philip says he undertook both an internal and external clean prior to handing over
the property.22 Mr and Mrs Augustine claim $1,030.97 for further cleaning internally
($500) and externally ($530.97). Mr and Mrs Augustine produced an invoice for the
hire of a bobcat to support the cost of the external clean23 but no further evidence on
the cost of the internal clean.
[146] Mr and Mrs Augustine say the bobcat was necessary to level a pile of soil in the corner
of the back yard. The inclusions lists identifies ‘cleaning site on completion’ but does
not list a requirement to level the ground. I am not satisfied the builder is responsible
for this item.
[147] Mr and Mrs Augustine say the inspection report they returned to the builder identified
that the house required cleaning. There was a bill for the internal clean but that has
been lost in moving. They gave evidence that this cost them about $500.
[148] I accept this evidence and will allow this item set at an amount of $500.00.
Conclusion
[149] The final amounts are calculated as follows:
Owing to the homeowners:
Category Amount ($)
Defects and incomplete work 42,996.57
Lost rent nil
Liquidated damages 7,300.00
Variations from the contract
amount owing to the owners
13,190.00
Other variations in dispute to be
paid to the owners
nil
Cleaning costs 500.00
Total costs to owners 63,986.57
22 Exhibit 11 para 26 and para 27.
23 Exhibit 5 annexure ‘J’.
-- 19 of 22 --
20
Owing to the builder:
Category Amount ($)
Defects and incomplete work Nil
Lost rent nil
Liquidated damages Nil
Variations from the contract
Amount owing to builder
3,810.00
Other variations in dispute to be
paid to the builder
2,263.00
Total costs to builder 6,073.00
[150] The net amount therefore to be paid to Mr and Mrs Augustine is $ 57,913.57
Costs
[151] Mr and Mrs Augustine claim the following costs arising from this application:
(a) Fees of building expert for the report and giving evidence:
$ 7,660.00
(b) Fees of real estate manager for the report and giving evidence :
$ 400.00
(c) Legal fees for preparation of documents:
$ 5,987.95
[152] Mr and Mrs Augustine provided invoices for all of the above amounts except a verbal
amount indicated by the real estate manager for preparation and attendance at the
hearing.24
[153] Directions will be made for the filing of submissions in support of this application for
recovery of costs for the report and attendance of the real estate manager at the
hearing.
[154] As all parties to this application are self-represented, the Tribunal makes the following
comments concerning costs to assist the parties.
[155] The starting point for a decision on costs is s 77(3)(h) of the Queensland Building and
Construction Commission Act 1991 (Qld) (‘QBCC Act’).
24 Exhibits 14, 15 and 16.
-- 20 of 22 --
21
[156] The section modifies the general position under the QCAT Act to give the Tribunal a
broad general power to award costs in cases caught by these enabling provisions. 25
This enabling Act allows that while the power must be exercised judicially, it is ‘in
markedly different terms from s 100 of the QCAT Act’26 which starts with the parties
bearing their own costs.
[157] The Tribunal has discussed the principles applicable in a costs application in a
building dispute in these matters:27
(a) The Tribunal’s discretion to award costs in a building dispute is a broader and
more general discretion than the one conferred by the QCAT Act because there
is an express power to award costs conferred by the QBCC Act, the relevant
enabling Act. Unlike in the QCAT Act, there is no strong contra-indication in s
77 of the QBCC Act against a costs order.
(b) It remains necessary to consider whether an award of costs is justified in the
circumstances.
[158] As his Honour, the then President of QCAT determined in the appeal decision of
Lyons v Dreamstarter Pty Ltd28 about s 77 of the QBCC Act,
“The discretion to award costs starts with the proposition that it is just and
reasonable that a party who causes another to incur costs should reimburse the
other party for them. Otherwise the factors affecting the discretion will vary in
each case.”
[159] The Tribunal, in exercising its general discretion to award costs, may consider the
factors referred to in s 102(3) of the QCAT Act. The then Deputy President of QCAT,
Judge Kingham in Ascot v Nursing & Midwifery Board of Australia29 stated:
“The considerations identified in s 102(3) are not grounds for awarding costs.
They are factors that may be taken into account in determining whether, in a
particular case, the interests of justice require the tribunal to make a costs
order.”
[160] Section 102 of the QCAT Act provides that the Tribunal may make an order as to
costs in the interests of justice, having regard to certain factors. That section relevantly
provides:
(102) Costs against party in interests of justice
(1) The tribunal may make an order requiring a party to a
proceeding to pay all or a stated part of the costs of another
party to the proceeding if the tribunal considers the
interests of justice require it to make the order.
……
25 Lyons v Dreamstarter Pty Ltd [2011] QCATA 142 at para [33].
26 Ibid [10].
27 Ryan v Worthington Simmons Builders [2016] QCATA 116.
28 Ibid [11].
29 [2010] QCAT 364 at para [9]; see also Rintoul v State of Queensland & Ors [2018] QCA 20 at para
[38].
-- 21 of 22 --
22
(3) In deciding whether to award costs under subsection
(1) or (2) the tribunal may have regard to the following
relevant sections–
a. whether a party to a proceeding is acting in
a way that unnecessarily disadvantage s
another party to the proceeding, includ ing
as mentioned in section 48(1)(a) to (g):
b. the nature and complexity of the dispute
the subject of the proceeding
c. the relative strengths of the claims made
by each of the parties to the proceeding
d. ….
e. the financial circumstances of the parties
to the proceeding;
f. anything else the tribunal considers
relevant.
[161] These considerations can be characterised as either ‘entitling’ or ‘disentitling’ factors.
[162] It would be of assistance to the Tribunal if these listed sections could be addressed by
the parties in any further submissions.
-- 22 of 22 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2018/248