Budge v JMK Building Pty Ltd [2018] QCAT 174
CITATION: Budge v JMK Building Pty Ltd [2018] QCAT
174
PARTIES: David Budge and Christine Budge
(Applicants)
v
JMK Building Pty Ltd
(Respondent)
APPLICATION NUMBER: BDL201-16
MATTER TYPE: Building matters
HEARING DATE: 19 and 20 September 2017
HEARD AT: Cairns
DECISION OF: Member Howe
DELIVERED ON: 26 February 2018
DELIVERED AT: Brisbane
ORDERS MADE: 1. The respondent pay to the applicants the
sum of $7,900.00 within 7 days of the date
hereof.
2. The parties file and serve submissions as
to costs within 14 days of the date of this
order and each file and serve any
submissions in reply within 14 days
thereafter.
CATCHWORDS: CONTRACTS – BUILDING ENGINEERING
AND RELATED CONTRACTS –
PERFORMANCE OF WORK – where owners
alleged defective building work – where
cladding sheets not joined as required by
architectural plans – where alternate method of
fixing confirmed by manufacturer – where
alternate method proved inadequate – where
further method of fixing recommended by
manufacturer – where owners refused to permit
– where owners required fixing in accordance
with contract plans – whether costs of fixing by
replacing all sheets and refixing in accordance
with original plans unreasonable in the
circumstance
-- 1 of 21 --
2
CONTRACTS – BUILDING ENGINEERING
AND RELATED CONTRACTS –
PERFORMANCE OF WORK – where
floorboards showing cupping effect – where
moisture content apparently not an issue –
whether secret nailing contributed to cupping –
where secret nailing probable cause
CONTRACTS – BUILDING ENGINEERING
AND RELATED CONTRACTS –
PERFORMANCE OF WORK – REMEDIES
FOR BREACH OF CONTRACT – DAMAGES –
solatium – where cladding primarily to achieve
trouble free maintenance – where aesthetic
considerations secondary – where significantly
cheaper method of fixing reasonable – where
replacement of cladding and re-fixing pursuant
to strict terms of contract unreasonable remedy
in the circumstances –where an estimate of
costs of rectification necessary in absence of
evidence
Domestic Building Contracts Act 2000 (Qld),
s 45(2)
Archibald v Powlett [2017] VSCA 259
Baltic Shipping Company v Dillon [1993] HCA
4
Bellgrove v Eldridge (1954) 90 CLR 613
Bitannia Pty Ltd v Parkline Constructions Pty
Ltd [2009] NSWSC 1302
Codelfa Construction Pty Ltd v State Rail
Authority of New South Wales (1982)149 CLR
337
Coshott and Anor v Fewings Joinery Pty Ltd
[1996] NSWCA 122
Radford v De Froberville [1978] 1 All ER 33
Ruxledge Electronics and Construction Ltd v
Forsyth [1995] 3 All ER 268
Silastone Trading Pty Ltd v Body Corporate for
Q1 [2017] QCAT 349
Tabcorp Holdings Ltd v Bowen Investments
Pty Ltd (2009) 236 CLR 272
Tamawood Ltd v Paans & Anor [2004] QDC
427
Tamburini v SFN Constructions Pty Ltd [2011]
NSWCTTT 26
Turner Corporation Pty Ltd v Austotel Pty Ltd
(1994) 13 BCL 378
-- 2 of 21 --
3
APPEARANCES:
APPLICANT: Mr and Mrs Budge represented themselves
RESPONDENT: Mr D McKinstry, Solicitor of Williams, Graham
Carman, represented the respondent
REASONS FOR DECISION
[1] Mr and Mrs Budge contracted with the respondent builder to build them a
home at Oak Beach near Port Douglas in North Queensland. The price
was $376,869 and work started immediately the contract was signed on
13 January 2015.
[2] The work finished on or about 19 August 2015. The owners had concerns
about the work. The significant issues were the timber floor and cracking
of the silicone used at some of the joins of the exterior cladding sheets.
[3] Some work to fix these problems was agreed and some carried out but the
owners were not satisfied. They complained to the Queensland Building
and Construction Commission (QBCC) and they finally brought the subject
proceedings in the tribunal.
The Terms of the Contract
[4] The contract was a Master Builders contract. A copy of the schedule and
appendices to the contract, architectural style drawings, the builder’s quote
and some extracted pages of the general conditions of the Master Builder’s
contract were tendered in evidence of the terms of the contract.
Unfortunately, neither party supplied a full copy of the general conditions of
contract. This was so despite an obvious issue prior to hearing about the
owners’ alleged refusal to allow the builder entry to rectify defects. The
general conditions of contract would usually be relevant in determining any
such issue.
[5] In the schedule to the contract at item 3, the description of works is “New
residential dwelling with 3 bedrooms and 2 bathrooms as per plans supplied
by owner dated 14.10.14.”
[6] Those plans carry a notation at various places1 concerning the cladding to
be used in fairly clear terms as follows: “Weathertex Weathergroove
Smooth Cladding joined on stud CW proprietary Trimtec aluminium
flashings and corner stops to framed exterior walls ….” The plans also state
that under no circumstances were there to be any substitutions of specified
items without the consent and approval of Vandyke Designs.2
1 Ex 1, Appendix 1, Drawings 4, 7, 8 and 12.
2 Ibid, Drawing 2.
-- 3 of 21 --
4
[7] In so far as the flooring is concerned however the plans lack specificity. All
that is said is “T & G internal floors generally”.3
[8] Both parties referred to the builder’s quotation as part of the terms of the
contract.4 Neither party took issue that the quotation is not specifically
referred to in the contract.
[9] The parties seem to be in consensus that the quotation correctly sets out
the agreed schedule of finishes as at date of contract. The contract was
signed on the same day the quotation was given. The contract price is as
per the quoted cost. The quotation does not conflict with the terms of the
contract given it appears there is no actual independent schedule of finishes
or specifications howsoever called. I conclude the quotation is admissible
to assist in the interpretation of the contract between the parties in respect
of agreed products and finishes to be utilised in the construction.5
[10] The builder quoted for supply of “Internal: 80 x 19 tongue and groove
standard grade spotted gum.”
[11] I might note the quotation also states the quotation is “…in accordance with
the stamped engineered plans and schedule of finishes supplied to me by
from designed by (sic) Chris Vandyke.”6 There was no such schedule of
finishes tendered at hearing nor any reference made throughout the hearing
to any specific schedule of finishes supplied to the builder.
The Cladding
[12] The external cladding was a Weathertex product. The product installation
guide provides for joining between sheets (1200mm wide) by means of a
proprietary “Weathergroove Joiner”.7
[13] As stated by the architectural plans the cladding was to be “Weathertex
Weathergroove smooth cladding joined on stud C/W proprietary Trimtek
aluminium flashings and corner stops to framed external walls.” I take C/W
to mean “connect with”.
[14] The builder did not use any proprietary joiners. Instead the join between
sheets was filled with a paintable silicone. That was not an approved
3 Ibid, Drawings 4, 5, 6 and 7.
4 The builder’s statement of evidence Ex 4 at [43] referred to “The building quote/contract
was for the supply and lay of standard grade flooring (Appendix 16).” Appendix 16 to
that statement of evidence is an extract from the builder’s quotation referring to
“Internal: 80 x 19 tongue and groove standard grade spotted gum”. The owners;
statement of evidence Ex 1 at [6] relies on the terms of the quotation in respect of the
builder’s obligations in respect of installation of the cladding.
5 Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (1982) 149
CLR 337.
6 Ex 1, Appendix 20.
7 Ex 1, Appendix 4, 4.
-- 4 of 21 --
5
method of joining sheets by the manufacturer nor the method specified in
the architectural plans.
[15] By July 2016, it became clear that the silicone joins were not working
properly and splitting and had to be remedied. The house had been built
on class P soil type meaning a problem site, though that is not necessarily
an unusual classification. The builder submitted structural movement had
probably contributed to separation of the cladding at some joins but I
conclude if the proprietary joiners had been used there would probably not
have been any discernible problem.
[16] According to the owners, some of the cracks between sheets were large
and the blue material underneath (sarking) could be seen. According to the
owners, the significant problem was not aesthetics but seeing the blue
waterproofing material under the joins showing through.8
[17] It is not clear on the evidence how many joins failed in this way. Mr Sargent,
a QBCC building inspector, investigated a complaint about the cladding by
the owners. He attended on 12 January 2016, which he said was within the
6-month defects liability period under the contract.
[18] He said he found no structural problem of water entry at that time so no
notice to remedy defective building work could be given. There was
obvious cracking to the silicone seals between sheets however, which he
described as settlement cracking, so he advised the builder to seek advice
from the manufacturer.
[19] The builder did that and the manufacturer, Weathertex, recommended
retrospective fitting of 10mm aluminium cover strips to the preformed
vertical grooved rebate where sheets met using a high quality flexible
paintable polyurethane sealant.
[20] The parties agreed to do that and documented that course of action by
writing dated 29 July 2016 signed by both parties. This was nearly one year
after practical completion on 19 August 2015. Documenting the agreed
course of rectification was suggested by the building inspector to ensure
the parties were “on the same page”9 which was an entirely sensible
suggestion on his part.
[21] In the 29 July document, the issue being resolved was described as an
aesthetic one. I note in that document the parties also agreed that the
builder would add timber beading to the window surrounds and the door
frames of the dwelling.
[22] The builder started to retrofit the aluminium cover strips but this almost
immediately proved less than satisfactory. According to the building
inspector, Mr Sargent, who came out again for another inspection following
the fitting of the aluminium strips, some were satisfactory but perhaps a
8 Transcript (T)1-23 Line (L)28.
9 T1-106 L1.
-- 5 of 21 --
6
quarter were not.10 He told the builder to fix those that were not. Mr Sargent
said the issue for him at the time was twofold, damage to the sheets being
caused in retrofitting the aluminium strips and the unacceptable finish.
[23] Again at Mr Sargent’s suggestion the builder went back to the manufacturer
for another solution and Weathertex suggested using 42mm x 12mm
vertical timber beading over the edges. The manufacturer approved that
as an acceptable solution on 10 August 2016.11 The builder in turn
proposed that solution to the owners. The owners rejected that proposal
however apparently by email dated 15 August 2016 to the building inspector
Mr Sargent.12 No copy of that email was tendered in evidence.
[24] Mr Sargent in turn wrote to the owners confirming the owners’ email
rejecting the timber beading solution and also advising the builder that the
owners refused him further access to the site “to rectify outstanding
defective items.” Mr Sargent then advised both owners and builder that the
QBCC would no longer be involved in the matter because the builder had
been denied reasonable access to undertake necessary rectification work.
The Timber Beading Solution
[25] The owners’ original brief to the building designers was “… to produce a
building that would be easy to maintain while being of a high quality.”13
[26] Mr Reason the building designer for the project said at hearing that he
thought the owners rejected the timber beading solution because it was
different to the original cladding specification. He said introduction of the
timber beading would add a third dimension to the cladding and he thought
perhaps that was why the owners rejected the proposal.14 But he also said
the aesthetics in using timber beading was entirely subjective.15 He said
he was involved at that time with another project at Port Douglas where
Weathertex cladding using timber beading cover strips were being used by
choice rather than proprietary joiners.16 Indeed they were being added at
300mm spaces, not only each 1200mm where sheets joined.
[27] Whilst the agreement of 29 July 2016 refers to an aesthetic issue, the timber
beading solution had not been raised at that stage and that agreement was
only concerned with cracks in the original silicone caulking.
[28] Mrs Budge also said the owners wanted the original contract adhered to “if
the external cladding is to perform as originally specified and not incur
significant costs to the plaintiffs in the future.”17 It is not clear what
10 T1-99 L25.
11 Ex 4, Appendix 11.
12 Ex 1, Appendix 10.
13 Ex 1, [3].
14 T1-127 L34.
15 T1-128 L1.
16 T1-124 L32-37.
17 Ibid, [10].
-- 6 of 21 --
7
significant costs are referred to but I conclude she was saying the owners
did not want a problem arising some time in the future with maintaining the
cladding:
It is apparent that any remedial repair will not work and that the
external cladding needs to be installed as per JMK’s quotation, Master
Builders contract, manufacturers and architect installation instructions
if it is to perform as is reasonably expected.
This would require removal of the cladding and the installation of new
cladding on stud as per architectural drawings and manufacturer’s
instructions with the required pvc joiners, and finished with the
required paint to complete the cladding to a satisfactory standard.18
[29] In cross-examination, Mrs Budge seemed to identify water ingress as her
major issue.19 She subsequently added the owners wanted the Weathertex
smooth look rather than timber beading at every join, but that appeared to
be only a secondary complaint to that of water entry.20 In the owners’ initial
application, the owners stated the reasons for seeking replacement of the
cladding was “the issue of integrity in a high cyclone area and validity of
manufacturers warranty.” There is no mention of the timber beading
solution being unacceptable because of appearance in any of the many
statements of evidence filed by the owners. Further, I note in the agreement
of 29 July 2016 that the owners agreed to have timber trim (beading) added
to the windows and the door frames, and the builder’s proposal about
adding timber beading to cover the joins of the cladding would have
matched that.21
[30] Nowhere in their material nor at the hearing have the owners challenged
the timber beading solution as proposed by the builder and approved by the
manufacturer as being unworkable. Rather they simply “declined” that
proposed solution.22
[31] Mr Wakefield said in his evidence he had spoken to the Weathertex
representative who told him Weathertex could provide a solution to make
the cladding “compliant”, following which the cladding would stay under
warranty.23
[32] But despite that, the owners say that the only realistic solution to the
external cladding is its removal and replacement with new cladding
18 Ex 1, [19]-[20].
19 T1-29 L34.
20 T1-30 L6.
21 Ex 4, Appendix 11.
22 Ex 3.
23 T1-118 L36. See also Ex 2 Appendix 6 at [6] where the warranty conditions refer to
modifications requested and carried out as instructed by Weathertex.
-- 7 of 21 --
8
“installed as per original contract, architectural drawings and manufacturers
installation guide”.24 The evidence does not support that proposition.
[33] Mr Reason the building designer considered the timber beading solution
would remedy the problem he saw there.25
[34] Mr Sargent thought there was no water penetration problem even without
the beading because the sarking or sisalation or whatever waterproofing
had been used under the cladding would prevent water penetration. Mr
Sargent said the manufacturer accepted the timber bead solution and
therefore so did he.
[35] The owners’ expert, Mr Wonnacott, was principally concerned with potential
water entry at the sheet joins in using the 10mm aluminium strips. He did
not deal with the timber beading solution at all.
[36] Mr McIntosh, another builder who gave evidence for the owners, conceded
that if the manufacturer proposed a method of rectification of the cladding
joins that method would be an appropriate remedy.26 He said he had not
been aware of the proposal to retrofit the 42mm timber beading as a
solution to the cladding joins.
[37] The owners also called a joint sealer, Mr Iverson, to give evidence. Mr
Iverson made it clear he was a joint sealer, not a builder. In his statement
of evidence27 he said he had inspected the cladding, evidently a few months
before hearing, and he saw water penetration behind cracked silicone
seals. He said there was water damage occurring. Strangely enough, he
made no mention of the fitted 10mm aluminium strips between sheets. He
recommended removing the cladding and re-sheeting the entire external
area “using the correct method.”28 He does not make clear what the correct
method is.
[38] He had not been aware of the proposal to fit timber beading over the joins
either. When the beading proposal was put to him at hearing, he did not
agree that a timber bead “to make it look pretty”29 would remedy the
problem. The proposal to fit the timber beading is for more than aesthetic
purposes however. Mr Iverson’s focus was on achieving a waterproof join
by using silicone and his worry was moisture behind the sheets preventing
a silicone seal. It was not put to him that Mr Middleton proposed to fix the
beading by nailing it between sheets directly onto studs.30
[39] Mr McIntosh also based his view about replacement of all sheets being
necessary on his observation that some sheets moved at joins and
24 Ex 2, [12].
25 T1-125 L39.
26 T1-64 L2.
27 Ex 3.
28 Ibid.
29 T1-69 L40.
30 T1-87 L24.
-- 8 of 21 --
9
therefore he suspected some sheets were not joined on stud. Mr Middleton
said all the sheets were joined on stud. He was very clear about that31 and
that was also Mr Sargent’s view.32 I prefer Mr Sargent’s evidence on this
point and where his evidence conflicts with others. I found him to be clear
and impartial in his evidence, well aware of all the cladding issues and
proposals about fixing them and generally seemed to me to be
knowledgeable in building matters. I conclude the sheets are joined on stud
and therefore there is no cause on that basis to require all the sheets to be
removed and replaced.
[40] I conclude the proposal to fit timber beading over the joins by nailing to the
studs and adding a flexible sealant to the timber beading would resolve any
issue about water penetration at the sheet joins into the future. That
solution would not result in the owners incurring any notable maintenance
or other costs with respect to the cladding in the future. I accept Mr
Wakefield’s evidence that the cladding would enjoy any Weathertex
warranty otherwise accorded appropriately fixed cladding.
Costs of Rectification of the Cladding
[41] The contractor failed to adhere to the building designer’s direction to use
proprietary Weathertex joiners with the cladding. In doing so he breached
the warranty imposed by s 45(2) of the Domestic Building Contracts Act
2000 (Qld) (which applied to this contract entered into on 13 January 2013)
to carry out the work in accordance with the plans.
[42] What remedy do the owners have in consequence of that breach of
warranty? The accepted statement of general principle in building cases
about rectification work is that made by the High Court in Bellgrove v
Eldridge:33
The measure of the damages recoverable by the building owner for
the breach of a building contract is, it is submitted, the difference
between the contract price of the work or building contracted for and
the cost of making the work or building conform to the contract, with
the addition, in most cases, of the amount of profits or earnings lost
by the breach.
[43] The High Court also said however that that statement of principle was
qualified by the requirement that not only must the work to be undertaken
be necessary to produce conformity to the contract but also it must be a
reasonable course to adopt.34 The example given in Bellgrove about that
was a building contract calling for erection of a house with cement rendered
walls of second-hand bricks and the builder uses new bricks instead. In
31 T87 L27, L35.
32 T104 L36.
33 (1954) 90 CLR 613, the High Court adopting the statement of principle about damages
in building cases as stated in Hudson on Building Contracts.
34 Ibid, 618.
-- 9 of 21 --
10
that situation, the owner would not be entitled to the cost of demolishing the
walls and re-erecting them using second-hand bricks.
[44] The High Court went on to say in Tabcorp Holdings Ltd v Bowen
Investments Pty Ltd35 that the example of unreasonableness given in
Bellgrove indicated that the test of “unreasonableness” is only to be
satisfied by fairly exceptional circumstances. The Court also said there may
be other factors besides financial considerations to be considered in
determining what is reasonable rectification work. Factors such as
aesthetic expectations may also be an important feature of the
transaction.36 In that regard the High Court adopted with approval the
words of Oliver J in Radford v De Froberville:37
If he contracts for the supply of that which he thinks serves his
interests – be they commercial, aesthetic or merely eccentric – then if
that which is contracted for is not supplied by the other contracting
party I do not see why, in principle, he should not be compensated by
being provided with the cost of supplying it through someone else or
in a different way, subject to the proviso, of course, that he is seeking
compensation for a genuine loss and not merely using a technical
breach to secure an uncovenanted profit.38
[45] How do these principles and matters for consideration apply to the matter
at hand?
[46] I have concluded the fixing of timber beads would rectify any issues about
water entry at the edges of the sheets. The owners reject that proposed
method of rectification but not any reasonable basis that this method would
not work. The cost of replacement and resheeting using proprietary joiners
is $42,810.86 based on Mr McIntosh’s quotation.
[47] According to Mr Middleton, the cost of the timber beading material will be
around $300 but there is no estimate about cost of labour. It is clear
however that Mr Middleton submits the all up costs of the timber beading
fix will be very modest in comparison to Mr McIntosh’s proposed costs.
[48] As stated, I am unable to attribute any significant aesthetic concerns to the
owners’ rejection of the timber beading solution.
[49] I conclude it is unreasonable to make the builder pay for the removal and
replacement of all the cladding using proprietary Weathertex joiners at a
cost of $42,810.86 in such circumstances. The use of timber beading as
suggested by the builder and approved by the manufacturer39 is a
reasonable course of rectification in the circumstances and the costs sought
35 (2009) 236 CLR 272; [2009] HCA 8.
36 Ibid, [16].
37 [1977] 1 WLR 1262, 1270; [1978] 1 All ER 33, 42.
38 Op.cit 618.
39 Ex 4, Appendix 11.
-- 10 of 21 --
11
by the owners is unreasonable in the circumstances. The builder should
be responsible for the cost of the timber beading solution.
Cost of Timber Beading Remedy
[50] The builder suggests a cost of $300 to add the timber trim. That is only the
cost of the material however.40 He gives no estimate of cost of labour or
contractor’s margin. Neither do the owners. I must do the best I can
however to assess such cost. The costs must be the estimated cost of the
exercise to the owners engaging an independent contractor to perform the
work.
[51] The work must entail the labour involved in fixing and sealing the timber
beading around the entire perimeter. There will be some painting required
to match the cladding. I estimate that $1,500 for labour and $300 for
materials would be a reasonable sum in the circumstances. That totals
$1,800.
Solatium
[52] The builder’s solicitor suggested the owners would be entitled to an award
for solatium rather than damages for breach of contract, that is an award of
money to assuage disappointment. In Tamburini v SFN Constructions Pty
Ltd,41 this type of award was described as possibly available where the
owner’s “loss cannot be fully or adequately compensated by an order for
damages under the usual heads.”
[53] I addressed the issue of solatium in the not dissimilar matter to the matter
at hand of Silastone Trading Pty Ltd v Body Corporate for Q1.42
[54] Awards of solatium rely for their authority on the House of Lords decision
of Ruxledge Electronics and Construction Ltd v Forsyth.43 There an award
was made for an owner who had contracted with a builder for a pool of a
particular depth but when built proved to be 9 inches less than designed.
The owner was awarded general damages of £2,500 for loss of amenity.
There was no diminution in the value of the property due to the breach of
contract. The cost of demolishing and rebuilding the pool was £21,569.
The only defect with the pool was the depth.
[55] The award was confirmed by the House of Lords but on a number of bases.
Lord Jauncey and Lord Mustill confirmed the award because it had not been
challenged by the appellant builder. Lord Lloyd said swimming pools were
not necessities but for fun. They were a pleasurable amenity. He found
the loss of that amenity may sound in damages. Both the judge at first
instance and Lord Lloyd based the award on English holiday cases, where
the object of the contract was to afford pleasure. In those cases where a
40 T2-13 L12.
41 [2011] NSWCTTT 26.
42 [2017] QCAT 349
43 [1995] 3 All ER 268.
-- 11 of 21 --
12
tour operator failed to provide what the contract called for the plaintiff could
recover damages for disappointment. Similarly, it was reasoned the
contract for the pool was for the provision of a pleasurable amenity and the
owner’s pleasure was not as great as it would have been if the swimming
pool had been 9 inches deeper.44
[56] Ruxledge was relied on by the New South Wales Court of Appeal in Coshott
and Anor v Fewings Joinery Pty Ltd45 where the owner engaged a builder
to build a home and stipulated that the construction be to a very high
standard. A number of joinery items were found to be defective including
defective window sills. The owner wanted all window structures replaced,
not just the sills, at a cost of $25,687.99. The judge at first instance allowed
$3,205 for replacement of sills and also awarded “solatium” of $5,000 as
compensation for the inconvenience the plaintiffs would suffer from the
rectification work and for their disappointment in not getting the exact high
quality result for which they had bargained. The builder said there was no
basis for making such an award. The Court of Appeal upheld the judge’s
decision to give such award relying on Ruxley.
[57] In Tamawood Ltd v Paans & Anor,46 McGill DCJ said (citing Coshott):
If there has been no loss of value, then damages for loss of amenity can be
awarded on the basis of the decision in Ruxley Electronics and Construction
Pty Ltd … a decision which has been followed in Australia.47
[58] However, in Archibald v Powlett,48 the Victorian Court of Appeal in
discussing damages for distress and disappointment in breach of contract
cases reminded us that:
The general rule is that damages for anxiety, disappointment and distress
are not recoverable in an action for breach of contract. The principal
exceptions to that rule are where the contract is one whose object is to
provide enjoyment, relaxation or freedom from molestation, and where the
damages proceed from physical inconvenience caused by the breach. It is
the latter exception upon which the respondent relied.
The respondent pointed to several cases in which damages for anxiety,
distress and disappointment have been awarded following breach of a
building contract giving rise to physical discomfort or inconvenience.
However, all of these cases involved physical imposition upon the plaintiff,
whether by virtue of having to live with offensive odours or a leaking roof, or
in unsanitary or dirty conditions, or being obliged to vacate the defective
premises.49
44 At 289.
45 [1996] NSWCA 122.
46 [2004] QDC 427.
47 Ibid, [60].
48 [2017] VSCA 259.
49 Ibid, [62]-[63].
-- 12 of 21 --
13
[59] The Victorian Court of Appeal cited Baltic Shipping Company v Dillon50
where Mason CJ said:51
On the other hand, as a matter of ordinary experience, it is evident that, while
the innocent party to a contract will generally be disappointed if the
defendant does not perform the contract, the innocent party's
disappointment and distress are seldom so significant as to attract an award
of damages on that score. For that reason, if for no other, it is preferable to
adopt the rule that damages for disappointment and distress are not
recoverable unless they proceed from physical inconvenience caused by the
breach or unless the contract is one the object of which is to provide
enjoyment, relaxation or freedom from molestation. In cases falling within
the last-mentioned category, the damages flow directly from the breach of
contract, the promise being to provide enjoyment, relaxation or freedom from
molestation.
[60] Ruxley, where the pool was for pleasure and the loss of pleasure swimming
in a shallower pool was recognised as a loss of amenity, is within the
exceptions to the rule against damages for disappointment or distress
stated in Baltic Shipping. But similarly the limitations on such awards as
stated in Baltic Shipping should not be overlooked.
[61] In the matter at hand, I have determined that the principal issue about the
cladding for the owners was utility of purpose. I conclude the rectification
of the cladding by fixing and sealing timber beads to sheet joins and
requiring the builder to pay for that exercise will adequately compensate the
owners for the builder’s breach of contract. I cannot find any loss of amenity
to the owners in respect of aesthetics that should sound in an additional
award for solatium.
The Floor
[62] The owners also complain about the timber floor. They complain that the
floorboards show cupping.
[63] Mr Wonnacott, the owners’ builder, inspected the house on 21 August 2015
and gave a report of even date. He did not say much about the floor other
than there were gaps in the floor in many locations, which was
unacceptable. There was no mention of cupping problems at that stage.
[64] The owners complained about the floor to the builder and the parties agreed
that the floor should be allowed to settle for 12 months and then the builder
would arrange at the builder’s cost for the floor to be sanded again and
given a re-coat. The owners agreed. The builder confirmed that proposal
in a letter to the owners dated 6 September 2015.52
50 (1993) 176 CLR 344; [1994] HCA 4.
51 Ibid, [44].
52 Ex 2, Appendix 2.
-- 13 of 21 --
14
[65] The floor was not noted as a defective item of work in the owners’ statement
of defects completed on 7 September 2015 but that was because the matter
had been addressed in the agreement of the day before.53
[66] That remedial work was never done however because in November 2015,
the owners complained to the QBCC about defects, in particular the
cladding. The floor was not an item of complaint to the QBCC.
[67] Because of the complaint to the QBCC, the builder withdrew its offer to pay
for sanding and re-coating after 12 months.
[68] Mr Wonnacott returned for another inspection on 29 July 2016 and reported
cupping in the floor giving a ripple effect in sunlight. He suggested the ripple
effect was exacerbated because the boards were laid perpendicular to the
external source of light. He also commented that the boards had been
installed on top of particle board which was not unusual but not appropriate,
in his opinion, in the damp far North Queensland environment. This was
because particle board absorbed moisture readily. Further, the air
conditioner drained moisture from inside the house to under the raised floor
which was not ideal.
[69] He admitted however that he also found gapping occurring between some
boards which would indicate drying and shrinking of floorboards. He could
not explain the dichotomy.
[70] Mr Wonnacott further reported about the problem on 3 May 2017. He
commented there that the floor had been fixed using secret nailing rather
than face nailing through the top of the boards. He said it was not
recommended to use secret nailing of boards greater than 86mm in width.
[71] At hearing, Mr Wonnacott agreed particle board was used fairly commonly
in floors but he suggested it is not common in low set house(s) “which has
the elements going underneath it. The reason that it was stipulated as
hardwood flooring only in the drawings was for that reason.”54
[72] He also admitted he did not know the cause of the cupping given the
statement from the timber merchant supplying the boards that the boards
supplied had an acceptable moisture content. The boards were supplied
by Rankine Timber and Truss and Mr Wakefield, a salesman from that
company who gave evidence, said the timber was tested for appropriate
moisture content before leaving the timber yard.
[73] Mr Wonnacott thought the cause of the cupping could be lack of care storing
the timber on site and causing moisture absorption or the use of inadequate
expansion joints. He said if the timber was supplied at an acceptable
moisture level and it is now cupped then between delivery and installation
something has happened.
53 Ex 1, Appendix 6.
54 T1-57 L15.
-- 14 of 21 --
15
[74] Mr Wakefield also said however that the boards were again checked for
moisture content immediately before they were laid by specific request.
They were within the required moisture content range at that time as well.55
There does not appear to have been any lack of care on the part of the
builder between supply and fixing.
[75] Mr Wonnacott agreed that whether it was appropriate for particle board to
be used as an underlay was up to the certifier for the project. Mr Reason,
who was not the certifier but was the building designer, saw no problem
using the particle board as an underlay for the spotted gum floorboards.56
[76] Mr Wakefield’s evidence was also that he was asked to attend the site on
1 September 2015 to discuss a cupping issue and he thought the problem
was because of the sun shining through large doors and windows. He
advised Mrs Budge to hang curtains to minimise the sunlight effect.
[77] Mr Wakefield said he attended the house sometime before June 2017 and
tested the moisture content of the particle board laid as a subfloor under
the spotted gum flooring. The particle board moisture content was only 6%
to 7% which was a low moisture reading, and according to him as was
expected of the product.
[78] He said he last saw inside the house in about September 2016 which was
about a year after the floor had been laid. He saw some cupping in sections
close to the glass windows but the floor was fine further away from the
windows where there was no direct sunlight.57
[79] Mr Wonnacott’s evidence however was that the cupping was extensive and
was throughout the house.58 He did not agree that the sun might be an
issue. It had been involved in many other builds and the windows letting
sun in had not caused cupping.
[80] Mr Wakefield said timber floors reach an equilibrium after a time, after some
years, and in his opinion all that would be needed here would be a light
sand and recoat and the floor would be in very good condition. He did not
believe the floor needed removal and replacement. Additionally he did not
think there was a problem using 130mm spotted gum floorboards. He
himself had such in his own home. Nor did he see any issue about using
secret nailing with wide boards. Secret nailing was the preferred method
today he said. He had sold a lot of floors and he had not heard of problems.
[81] Mr Wonnacott suggested most builders in Cairns would not use 90mm
boards, they would use something smaller to reduce the cupping effect. So
too did Mr McIntosh. Mr McIntosh said he had visited the house on 5 April
2017 and he observed significant cupping of the flooring. He also states in
his report of 7 July 2017 that secret nailing is not recommended for boards
55 Ex 4, Appendix 25.
56 T1-126 L9, L20.
57 T1-114 L1.
58 T1-55 L10.
-- 15 of 21 --
16
wider than 86mm in the tropical north. He recommended face nailing the
existing flooring and sealing the underside of the chipboard to “help prevent
further movement”.59 His estimate of the cost of that exercise was
$18,603.56.
[82] In cross-examination, Mr McIntosh agreed that if the floor had been lightly
sanded to remove imperfections and a single coat of product applied to the
floor would present “much better” than when he had inspected it.
[83] Mr Middleton does not concede that the floor is defective. He said at
hearing that he inspected the floor after the “second last mediation” and it
had settled to the point of being satisfactory. I am not sure what or when
the second last mediation referred to occurred, but according to Mr
Middleton, what he saw on that inspection, together with the advice from Mr
Sargent that he would not be allowed back on site to remedy defects,
prompted him to cancel the arrangement with the owners to have the floor
lightly sanded and recoated as agreed. However, Mr Middleton gave a
different reason for cancelling it in his statement of evidence of 7 August
2017.60 There he said it was because of the ongoing unrealistic
expectations of the owners as well as the costs that he had already
incurred.61
[84] He also referred to a statement in a letter from Mr Sargent to the effect that
the floor was performing satisfactorily in support of his contention. Mr
Sargent however said at hearing that he was referring to complaints by the
owners about screws protruding under the floor. He did not go into the
house. He thought the matter of the floor finish had been resolved between
the parties with the agreement of 6 September 2015.
[85] I conclude the floor is defective because it shows cupping of boards. The
cupping is visible in the photograph in Mr Wonnacott’s report of 29 July
2016, though as Mr Wonnacott suggested the visual ripple effect of the
cupping is exacerbated by the direction of the boards laid perpendicular to
the primary light source. According to Mr Wonnacott and Mr McIntosh, the
cupping is now significant.
[86] However, I am unable to accept Mr Wonnacott’s suggestion that the particle
board underlay has contributed to cupping by constituting a moisture
absorbing layer. Mr Wonnacott identified the dichotomy of some boards
gapping and others cupping in one of his early reports. That, together with
Mr Wakefield’s evidence about the low moisture content of the particle
board at 6% to 7% shortly before June 2017, which he said was a low
moisture reading “as expected of the product”, leads me to conclude the
particle board underlay is not the cause of the cupping.
59 Ex 2, Appendix 17.
60 Ex 5.
61 Ibid, [5].
-- 16 of 21 --
17
[87] Mr McIntosh said he had visited the house on 5 April 2017 and observed
significant cupping but he also agreed when it was put to him that if the floor
was lightly sanded and recoated with product the floor would present “much
better” than when he had inspected it. I take that to mean that such
remedial work would leave the floor smooth, polished and no cupping.
[88] Mr Wakefield is not a builder. He has sold timber products for many years
however and I conclude in respect of the attributes of such organic product
he is well able to give credible evidence about it and problems associated
with its use in construction. He said that timber reaches an “equilibrium”. I
take that to mean in the context of timber flooring that the timber will reach
a point where it neither gains nor loses moisture and thereby achieves
stability. He said that may take years. He gave the example of his own
floor. That was also similarly 130mm spotted gum. He said there was a
place in his floor which expanded and rose a little and there was some
cupping but then it stopped and there was no issue there any more.
[89] Here the floor was laid some 2 ½ years ago. I conclude that the floor will
most probably have stabilised now given that passage of time.
[90] As to the use of secret nailing, both Mr Wonnacott and Mr McIntosh
suggested the problem with the floor might be attributable to the width of
the boards combined with fixing by secret nailing. Both said secret nailing
through the hidden edges of the boards was not recommended for boards
wider than 86mm in tropical North Queensland. Neither pointed to
authorities in support of that assertion.
[91] Mr Wakefield said he had not had complaints about secret nailing of wide
boards such as used here. He said secret nailing was currently the
preferred method of fixing but he did not distinguish between narrow and
wide boards.
[92] Mr Middleton attached a publication62 to his statement of evidence from an
organisation called Timber Queensland. The publication deals with
recommended practices in laying timber strip floors over timber joists and
structural subfloors such as particle board. The document is referred to as
a technical data sheet. It is very detailed but no formal basis is laid for
acceptance of the information contained within the document. Having said
that, s 28(3)(b) and 28(3)(c) of the QCAT Act provides the Tribunal is not
bound by the rules of evidence, or any practices or procedures applying to
courts of record, other than to the extent the tribunal adopts the rules,
practices or procedures; and may inform itself in any way it considers
appropriate. That is subject to the rider that the rules of natural justice are
applied.
[93] The Timber Queensland Publication was attached as an appendix to Mr
Middleton’s statement of evidence and had the owners disagreed with the
62 Ex 4, Appendix 28.
-- 17 of 21 --
18
observations made in it they have had ample opportunity to present their
own views and evidence.
[94] The Timber Queensland publication does not suggest secret nailing is
inappropriate in boards wider than 86mm. It does say top (face) nailing is
a more robust fixing method than secret nailing. It states that for boards up
to 135mm wide secret fixing of boards requires one staple or cleat at the
appropriate spacing and for top nailing two nails per board. In humid
localities (such as far North Queensland) it says consideration should be
given to board moisture contents, providing for expansion, board size, the
species and fixing method. It states:
In some locations top (face) nailing may be the preferred option or a
full bed of adhesive used. Overlay flooring can be more reactive to
changes in environmental conditions that may be induced not only by
conditions beneath the floor but also by sun exposure through large
windows above the floor. Some manufacturers do not recommend
that their 130 x 19mm or wider boards be secretly fixed and other
manufacturers have specific fixing recommendations providing for the
secret fixing of wider flooring that should be strictly adhered to.63
[95] It is unclear who the “manufacturer” is that is referred to but Mr Wakefield
from Rankine Timbers, timber merchants had no objection to using secret
nailing of the subject floor comprising 130mm boards. Given the boards
have been fixed by secret nailing it is impossible to say whether the
appropriate number and spacing of fixings have been employed and
whether adhesive to the underlay appropriately applied, if at all. What is
clear is that secret nailing is potentially problematic where wide floorboards
are laid and some care and thought is called for in its laying.
[96] I conclude the most likely cause of cupping of the floorboards in the matter
at hand was the inadequacy of the secret nailing of the wide floorboards or
the adhesive under or both. That inadequacy I conclude is most likely
attributable to the builder failing to use appropriate care and skil. Possibly
exposure of parts of the floor to direct sunlight, which was entirely beyond
the control of the builder, also played a factor, but I determine no significant
factor compared to the inadequacy of the secret nailing.
[97] There was a suggestion by Mr Wonnacott that the problem could be
attributed to lack of expansion joints, however their lack is fairly easily
identified by measurement and had there been an issue with inadequate
spacing of expansion joints one might have anticipated it would have been
identified with some precision by both Mr Wonnacott and Mr McIntosh,
which it was not.
[98] I accept Mr Middler’s evidence that he changed the flooring from 80mm
wide boards to 130mm at the request of the owners. The responsibility for
appropriate fixing of such wide boards however remained with the
63 Ibid, 5.
-- 18 of 21 --
19
contractor. There is no evidence the builder warned the owners of potential
problems with use of wide boards nor of issues about secret nailing as
opposed to face nailing. I conclude the builder did not know of the potential
difficulties with using secret nailing of wide floorboards.
[99] As stated, I do not find the problem has been contributed to by high moisture
levels in either the particle board substrate or the floorboards themselves.
Given that I have also concluded that the flooring has most probably
stabilised and reached a point of “equilibrium” in the words of Mr Wakefield,
I determine if the boards were now sanded and product applied the cupping
will be removed and the floor will achieve an acceptable final finish. I might
comment that because the boards lie perpendicular to entry of direct
sunlight, slight imperfections with the floor may well continue to be
highlighted post rectification, but that will not be the fault of the builder.
Cost of Rectification of the Floor
[100] The builder agreed with the owners that the floor needed to be sanded and
recoated with product in the agreement of 6 September 2015. There is a
quotation for recoating the floor, which refers to an area of 140 sq m.64
[101] Mr McIntosh agreed that if the floor was lightly sanded and recoated with
product the floor would present “much better” despite his description of the
cupping as significant in his report and quote of 7 July 2017.
[102] I have concluded the subfloor particle board is not a source of moisture and
the floorboards have now, after 2 ½ years, most probably stabilised. Given
that, I am not convinced that face nailing is necessary in addition to sanding
and recoating the floor with appropriate product.
[103] The builder suggests the cost of sanding and recoating would be $1,200. I
feel that is very much on the low side.
[104] Mr McIntosh’s quote was much more extensive but it did cover sanding
and coating as a discrete item of charge. His quote for that was $7,650. I
note the builder’s original quote was for interior “woodwork” to have 3 coats,
a sealer coat and two top coats. I regard that as fairly standard treatment.
I conclude the reasonable cost of sanding the existing secret nailed floor
and applying 3 further coats would be somewhere in between the two
estimates given. I consider 3 coats will be necessary because the sanding
to remove the cupping will take the floor back to bare timber.
[105] Mr McIntosh’s quote was based on sanding and coating timber floorboards
after face nailing the boards. After that all nail holes would have to be filled.
Given face nailing is not required those costs would not be incurred. I do
not accept that there would be any need for touch up painting with the skills
of floor sanders and their modern equipment and certainly not $1,500 worth
64 Ex 2, Appendix 9.
-- 19 of 21 --
20
as suggested in his quote. I feel his quotation is on the generous side of
the equation.
[106] In the circumstances, I allow $4,500 for sanding and recoating the
floorboards throughout the house.
[107] The owners also claim for the costs of accommodation away from the home
whilst rectification work is carried out. The addition of timber beading to the
cladding will not require the owners to leave the home. The sanding and
recoating of the entire timber floor will. The owners claim 10 days at $500
per day at a nearby luxury resort saying it is close to their children’s bus
stop. I consider that unreasonable. The children attend school in Cairns.
There is no good reason the accommodation could not be in Cairns. I allow
6 days apartment accommodation at $200 per night, which totals $1,200.
Furniture must be removed before sanding and after the final coat drying
and hardening needs to occur before re-habitation. I allow $400 cost of
labour to remove furniture and return it after the work is done.
[108] There is a large covered verandah at the property. I am not convinced that
would not be adequate to store the furniture in the home during the floor
work. The cost for hire of a container is therefore unnecessary and is not
allowed.
Comment
[109] It is not to any point that the builder offered to pay for a sanding and
recoating 12 months after September 2015. Nor should the cost of the work
now be limited to the sum the builder maintains he would have paid then if
he had had it done. He did not do it. It is also not to any point that the
builder says he was refused access to rectify defective or incomplete work.
[110] I accept the evidence of the owners that they were referring to the cladding
rectification work only when they told Mr Sargent they would not let the
builder return. The sanding work was to be done by a third party and the
evidence was not that the builder was not able to perform the sanding work
because of denial of access but cancelled by the builder because the
owners had “unrealistic expectations” and also because of the costs that
the builder had already been put to.65
[111] The builder submits there is a general principle in Australian law that a
building owner is not entitled to recover the costs of rectification or
completion where it denies the building contractor an opportunity to rectify
or complete. I cannot accept that such a broad proposition is correct. It
has been held that the builder’s contractual rights to return to remedy
defects or complete work during any defect liability period is a right under
the contract. Where that contractual right to return to rectify is breached
65 Ex 5, [5].
-- 20 of 21 --
21
the owner will in turn be in breach of the contract and cannot claim general
damages for the builder’s original breach.66
[112] There are other cases where such breach of the right to rectify during the
defects liability period results in the builder being required to pay no more
than the cost of the rectification would have been to him (rather than the
costs of a third party contractor engaged by the owner) had he been
permitted to return.
[113] But the defect liability period, which I assume was 6 months (neither party
tendered a full copy of the general conditions of contract),67 was finished
before the builder was refused access. After expiry of the defects liability
period there was no right in the builder to return to complete or rectify
defects.
[114] There was no consideration for the owners’ agreements about cladding and
sanding of July 2016 and September 2016 respectively and no contractual
relations were created by those documents independently of the original
contract. In respect of both issues, these concerned defects arising out of
the builder’s performance of the building contract. The defects liability
period had ended by around February 2016. I conclude that was how the
builder saw the issues too, or he would not have agreed to perform the
additional work set out in the documents, rather than, as submitted, that it
was a concession of good will on his part.
Conclusion
[115] The builder is responsible for the costs of rectification of the cladding in the
sum of $1,800, floor sanding and coating with product in the amount of
$4,500, accommodation of $1,200 and labour costs of $400 with respect to
removal of furniture for the floor work.
[116] The parties should be given an opportunity to make submissions on costs.
66 Bitannia Pty Ltd v Parkline Constructions Pty Ltd [2009] NSWSC 1302, [73] following
Turner Corporation Pty Ltd v Austotel Pty Ltd (1994) 13 BCL 378.
67 Generally, Master Builder contracts allow 6 months for the defects liability period
commencing on the date of practical completion and finishing 6 months after that date
-- 21 of 21 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2018/174