Cousins v Barber [2018] QCAT 34
CITATION: Cousins & Anor v Barber [2018] QCAT 34
PARTIES: Darren Cousins
Nicole Cousins
(Applicants)
v
Daniel Barber t/as Impact Asphalt
(Respondent)
APPLICATION NUMBER: BDL025-16
MATTER TYPE: Building matters
HEARING DATE: 13 April 2017
HEARD AT: Maroochydore
DECISION OF: Member McLean Williams
DELIVERED ON: 16 February 2018
DELIVERED AT: Brisbane
ORDERS MADE: 1. The Respondent is required to pay to
the Applicants the sum of $23,593.10
within 28 days of the date of these
orders.
CATCHWORDS: Construction of an asphalt driveway –
questions regarding adequacy of workmanship
APPEARANCES:
APPLICANT: Mr Darren Cousins, in person for both
Applicants
RESPONDENT: Respondent, in person
REASONS FOR DECISION
[1] On 24 June 2014 the Applicants Mr Darren Cousins and Mrs Nicole
Cousins retained Mr Daniel Barber (who trades as ‘Impact Asphalt’) to
construct an asphalt driveway with brick edging at their home at Doonan,
on the Sunshine Coast. The driveway is a relatively large one,
approximately 90 metres in length, with a total area of approximately 462
square metres. Impact Asphalt laid about 45 tonnes of asphalt (to a depth
of 40 millimetres) during construction. The cost for same, including all
-- 1 of 7 --
2
necessary site works, the brick edging, and drainage works was quoted by
Impact Asphalt at $32,780. Ultimately, Impact Asphalt was paid $32,160 by
Mr and Mr Cousins.
[2] One week after the driveway was finished a very heavy rainfall washed
away approximately 3-4 metres of the road base, out from under the lower
right side of the driveway. Mr Barber came back at that time and effectuated
some repairs. Mr Barber took the view that these problems were not
attributable to any of the works that he had performed, as he had departed
from the site instructing Mr and Mrs Cousins that a depression adjacent to
the driveway at that location needed filling. This was to be done as part of
on-going landscaping works that were being performed next to the
driveway, by a landscape contractor.
[3] Within a few further weeks the Applicants noticed other problems with the
driveway, this time referable to subsidence and cracking. Mr Barber again
returned, yet expressed the view that the cracking and subsidence was
nothing to worry about. The Applicants did not agree with that assessment.
[4] Much of the mortar between the brick edging on the sides of the driveway
also started to degrade and fall apart, also within only a few weeks of initial
installation. Although Mr Barber again returned to site to inspect the mortar
joints, Mr and Mrs Cousins say that he insisted to them that these looked
completely normal. Mr Barber, on the other hand, says that he agreed to
fix at least a portion of the brick edging, yet says that Mr and Mrs Cousins
refused to let him do this work.
[5] Investigations by engineers and other tradesmen commissioned by Mr and
Mrs Cousins now lead them to contend that the works undertaken by Impact
Asphalt was so defective that the driveway needs to be completely redone,
primarily by reason that the road base beneath the asphalt was not
adequately compacted, before the final asphalt surface was laid upon it.
The Applicant’s say that further significant damage has been caused to the
driveway by the inadequate drainage installed by Mr Barber, and that the
brick edging failed because the mortar mix used to bed the bricks was much
too sandy.
[6] On 19 February 2016 Mr and Mrs Cousins commenced these proceedings
by way of an Application for domestic building disputes seeking an award
of damages in the amount of $25,000 from Daniel Barber. In Part C of that
Application, Mr and Mrs Cousins indicate that they are actually seeking
$27,816 by way of refund from Daniel Barber, comprising:
$2,440: for the cost of having all the mortar between the bricks on
the edges of the driveway removed, the pavers cleaned, and then re-laid
correctly;
$20,526: for the cost of removing the existing asphalt, properly
compacting the road base beneath it, and then laying new asphalt.
-- 2 of 7 --
3
$4,850: as the cost for installing proper drainage, to replace the
allegedly inadequate and defective drainage installed by Impact Asphalt.
[7] By the time this matter was heard before me at Maroochydore, the
Applicants had refined their claim, and were now seeking $32,304,
comprised by:
$2,440: repairs to brick edging
$20,526: quoted costs to repair the driveway
$4,850 Quoted costs to repair the drainage;
$599.60: QCAT filing fee
$643.50 Compaction testing
$1,045: cost of Cardno Engineering Report
$2,200.00 Engineer’s fees for the QCAT Expert’s conclave (only an
estimate).
Respondent’s Case
[8] Mr Barber does acknowledge that one section of the brick edging required
some remedial work (which he had agreed to undertake at no cost to the
Applicants) yet that they refused to let him come back and do this work. Mr
Barber otherwise denies that the driveway was improperly constructed,
although he does indicate that he did offer to repair two further sections of
it (despite those defects not being attributable to any of his work), but that
Mr and Mrs Cousins again refused his offer.
[9] Mr Barber now claims $2,281 that he says is outstanding from Mr and Mrs
Cousins, referable to (a) $1,661 for repair works performed by him after part
of the driveway was washed away in the heavy rain event, and (b) the GST
component ($620) on the bricks used in the brick edging which he says Mr
and Mrs Cousins never paid.
[10] Mr Barber says that a vibrating roller was used in an appropriate manner
during construction to compact the road base, and that adequate drainage
for the driveway was installed. Mr Barber agrees that repair works had to
be undertaken by him after torrential rain damaged part of the driveway, yet
says that this damage arose only because Mr and Mrs Cousins failed to
back-fill an area adjacent to the driveway after it had been completed, in
the manner that he had advised them, and they had agreed that they would
do.
[11] Mr Barber says that the workmanship guarantee given by Impact Asphalt is
limited by specified terms and does not include damage to the driveway that
is caused by:
…
-- 3 of 7 --
4
(4) Any act or omission by the owners, or any employee, servant guest and
or agent of the owners; or
(5) Cracking or shrinkage due to the existence of tree roots and/or sub-
surface earth movement due to changing weather conditions including
earthquakes, flood, burst pipes easements; or
(6) Damage caused by the use of heavy earthmoving machinery and/or
heavy vehicles prior to obtaining advice or consent from Impact Asphalt.
You must inform Impact Asphalt at the time of your initial measure and
quote if you require the use of heavy earthmoving machinery or heavy
vehicles in the future and/or after completion of Impact Asphalts work to
avoid unnecessary damage. We use a standard depth of 150mm crush
rock with our driveways although this may increase to 150mm to 300 mm
if the area is to have the use of heavy machinery and/or vehicles in the
prevention of any damage.
[12] Mr Barber contends that the problems seen with the driveway have arisen
as the result of the failure by Mr and Mrs Cousins to back-fill an area
adjacent to the driveway in the manner that he had advised them, as well
as being due to “changing weather conditions” and either (a) earthmoving
machinery (as used by landscape contractors retained by Mr and Mrs
Cousins around the time of the construction of the driveway) or (b),
subsequently, by grocery delivery trucks driving on the driveway, which are
all events that Mr Barber contends are excluded from his warranty by
clauses 4, 5 and 6, as excerpted, by me in paragraph [11], above.
Applicant’s evidence
[13] The Applicants commissioned an engineering investigation by Cardno
Construction Sciences (‘Cardno’). This investigation included invasive
testing of the compacted road base beneath the asphalt by means of a
dynamic cone penetrometer (‘DCP’). The DCP testing undertaken by
Cardno reveals that the degree of compaction of the road base at the three
selected test sites, as measured by DCP varied between 90.5% and 94%.
These results were considered by Cardno to be too low. The Cardno report
says that the Brisbane City Council requires 95% compaction, and the
Sunshine Coast City Council requires 97% compaction. Road base
thickness at the three selected DCP test sites was found by Cardno to be
135mm, 215mm, and 300mm. Asphalt thickness at the test sites was
between 40 and 45mm, yet the overall thickness of the driveway was (at
least in the opinion of Cardno), insufficient in some places for a lightly
trafficked granular pavement.
[14] Mr and Mrs Cousins also obtained evidence from Mr Glenn Palk, who is a
bricklayer. Mr Palk says that the mortar used in the brick edging on the
driveway had not been mixed correctly and was much too sandy. Mr Palk
also says that no mortar haunch had been applied to the side of the bricks,
so as to prevent them from moving laterally. Mr Palk says that on 22 and
23 October 2014 he and his workers lifted all the bricks, and then re-laid
these, correctly. Mr and Mrs Cousins were charged for that work.
-- 4 of 7 --
5
[15] Finally, Mr and Mrs Cousins rely on evidence from Mr Peter Smith from
Dynamic Turf Management. Mr Smith says that he was on site laying turf
in July 2014, when Impact Asphalt was constructing the driveway. Mr Smith
says that he did not see Impact Asphalt using a vibrating roller to compact
the road base. Mr Smith says that he observed the road base being spread
by means of a skid steer loader, and that the only compaction undertaken
of the road base - at least as was observed by Mr Smith - was by means of
the skid steer loader. Mr Smith does however say that Impact Asphalt used
a vibrating roller once the hot mix asphalt was laid, subsequently. Mr Smith
further says that the drainage installed by Impact Asphalt was, in his view
at least, wholly inadequate, and could not cope with rainwater runoff, and
that this resulted in a portion of the driveway becoming undermined during
a heavy downpour. Mr Smith was then retained by Mr and Mrs Cousins to
redo the drains.
[16] By way of reply to that evidence Mr Barber says that, although one section
of the brick edging did require some remedial work the primary difficulty with
the brick edging has been caused by landscape machinery, used by other
contractors (presumably Mr Smith), having driven over it. Mr Barber also
says that Mr Palk’s evidence about haunching should be ignored by me, as
laying each paver in a 90mm bed of concrete (as he says that he did in this
instance) is, in his view at least, far superior to haunching.
[17] In regards to the engineering evidence from Cardno, Mr Barber says that
his own inquiries with Austroads (an Industry Advisory Body for road
construction) reveal that there is no industry design standard for driveways
and that the closest design standard is the Pavement Design Standards for
Light Traffic: which suggests that a minimum base thickness of 125mm is
acceptable for ‘light traffic’ contexts. The Cardno investigations reveal that
the minimum road base depth installed on the Cousin’s driveway by Impact
Asphalt is 135mm, thus exceeding that standard (although I do here note
that this is less than the 150mm minimum thickness promised in the Impact
Asphalt warranty, as excerpted by me in paragraph [11], above).
[18] Mr Barber also submitted a statement from a Barry Schulz, dated 10 April
2017. Mr Schulz says that he operates a water truck, and that he applied
water to the road base on the Cousin’s driveway at Doonan in July 2014,
whilst Mr Barber compacted the newly wetted road base, by means of a
vibrating roller.
Conclusions and the evidence
[19] I accept the evidence of Mr Palk the bricklayer. I conclude that the mortar
mix used in the brick edging along the entire length of the driveway was
much too sandy, and that the brick edging should have been installed with
a proper mortar shoulder haunch. I do not accept that Mr Barber’s claimed
90mm mortar bed is superior to haunching. Although Mr Barber is of the
opinion that much of the damage to the brick edging must have been
caused by the landscape contractors driving their machinery over the brick
edging, that is just supposition, by him. There is not sufficient independent
evidence of that before the Tribunal to allow me to be satisfied that I could
-- 5 of 7 --
6
comfortably reach that conclusion. I find that the brick edging was not
satisfactorily installed, and was already in a poor condition within only a few
weeks after installation.
[20] I accept that the thickness of the sub-bed road base and the asphalt
installed by Impact Asphalt on the Cousins driveway at Doonan were of an
acceptable industry standard. The road base was not less than 125mm in
thickness, and the asphalt was between 40mm and 45mm.
[21] Although I am prepared to accept that Mr Barber did use a vibrating roller
on the road base before the asphalt was subsequently laid over the top of
it, I conclude that the road base was not however sufficiently compacted by
Mr Barber before the asphalt top surface was then laid over it, and that the
lack of sufficient compaction is now confirmed by the Cardno invasive
testing, by means of DCP. I conclude that this has caused the early signs
of degradation now seen in the driveway. I do not accept that earthmoving
machinery and/or delivery trucks subsequently driving on the driveway have
caused this damage, because there is insufficient evidence to allow me to
draw that conclusion.
[22] Mr Barber’s own web site marketing material (as has been put into evidence
by the Applicants) says that driveways may fail, if road base is not
adequately compacted. The website also says that the rectification process
is costly, necessitating the removal of the new driveway in order to address
the problem.
[23] The area of most contention in the evidence relates to the adequacy of the
drainage works performed by Mr Barber. Mr Barber says that his drainage
work was entirely adequate, and that back filling over the drainage pipe
installed by him was to be completed by other contractors. There is no
dispute that a heavy rain event did wash away a sizeable portion of the
driveway, even before the Cousins had any reasonable opportunity to back
fill over the drain installed by Mr Barber. That was most unfortunate.
Ultimately, I do not think that responsibility for the timing of that rain event
should be a matter attributed to Mr Barber. Nor should Mr Barber be
required to meet the cost of it.
[24] The Cardno report commissioned by Mr and Mrs Cousins proffers no real
opinion in relation to the drainage issues. Although Mr Smith, the
landscaping contractor called on behalf Mr and Mrs Cousins, does say that
the drainage installed by Mr Barber was inadequate, Mr Smith does not go
on in his very short statement to elaborate and explain the nature of that
reputed inadequacy. Because of that, I do not regard Mr Smith’s opinion
as affording sufficient basis for a finding in relation to the drainage issue.
Ultimately, I conclude that the Applicants have not adduced sufficient
evidence in relation to the drainage issue to make out that specific
component of their claim against Mr Barber.
[25] In the end, I am of the view that the Applicant’s should have judgement
against the Respondent for the following amounts:
-- 6 of 7 --
7
a) $2,440: repairs to brick edging;
b) $20,526: quoted costs to repair the driveway;
c) $599.60: QCAT filing fee;
d) $643.50 Compaction testing;
e) $1,045: cost of the Cardno Engineering Report.
[26] I make no provision in the judgement sum for the Applicant’s to have the
costs of Cardno Engineering attend the compulsory conference. Equally,
the Respondent Mr Barber should be entitled to the $1,661 that he says
was invoiced to the Cousins (yet never paid) in order to effectuate further
repairs after the rain event that caused damage to the driveway
approximately 1 week after it was completed. That sum should now be
deducted from the award to Mr and Mrs Cousins.
[27] I order that the Respondent pay to the Applicant’s the sum of $23,593.10
within 28 days.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2018/034