Brooks Earthmoving & Quarries Pty Ltd v The Lockyer Valley Regional Council [2018] QPEC 51 [2019] QPELR 202
PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND
CITATION: Brooks Earthmoving & Quarries P/L v The Lockyer Valley
Regional Council [2018] QPEC 51
PARTIES: BROOKS EARTHMOVING & QUARRIES PTY LTD
(ACN 095 413 255)
(applicant)
v
THE LOCKYER VALLEY REGIONAL COUNCIL
(respondent)
FILE NO/S: D 49/2018
DIVISION: Planning
PROCEEDING: Application
ORIGINATING
COURT: Planning and Environment Court at Maroochydore
DELIVERED ON: 30 October 2018
DELIVERED AT: Maroochydore
HEARING DATE: 10 August 2018, 14 September 2018
JUDGE: Long SC DCJ
ORDER: IT IS DECLARED, pursuant to s 11(1) of the Planning
and Environment Court Act 2016, that:
1. The subject development permit has lapsed.
2. There has been non-compliance with the
requirements of s 369 of the Sustainable Planning
Act 2009 in that the applicant failed to apply for a
permissible change to condition 4 of the
development prior to it lapsing.
IT IS ORDERED, pursuant to s 11(4) and 76(6) of the
Planning and Environment Court Act 2016 and s 440 of
the Sustainable Planning Act 2009, that:
1. The non-compliance is excused.
2. The development permit be revived and amended
in accordance with the conditions attached hereto
and marked “A”, contained at pages 1–41.
-- 1 of 25 --
2
CATCHWORDS: ENVIRONMENT AND PLANNING – ENVIRONMENTAL
PLANNING – DEVELOPMENT CONTROL – CONSENTS,
APPROVALS, PERMITS AND AGREEMENTS – GENERAL
POWERS – where the applicant applies for revival and change
to a expired development approval – where the approval expired
on 31 December 2015 due to the operation of clause 4 of the
approval – where the application was filed on 3 May 2018,
being a date after the expiration of the approval – where,
consequently, there is non-compliance with the Sustainable
Planning Act 2009, the applicable Act at the time – where that
legislation is now repealed – where the application is to be
brought under the current legislation, by statutory effect –
whether the court has power to grant the relief sought – whether
the court should exercise its discretion to do so
LEGISLATION: Acts Interpretation Act 1954 ss 14A, 14B
Integrated Planning Act 1997 ss 4.1.5A
Planning Act 2016 ss 78–82, 85, 286, 311–312, 325
Planning and Environment Court Act 2016 ss 11, 37, 76
Planning and Environment Court Rules 2018 s 13
Sustainable Planning Act 2009 ss 341, 440
CASES: Agnes Bridge Pty Ltd v Central Highland Regional Council
[2015] QPEC 61
Beerwah Land Pty Ltd v Sunshine Coast Regional Council;
Woodlands Enterprise Pty Ltd v Beerwah Land Pty Ltd &
Anor and; Sunshine Coast Regional Council v Beerwah Land
Pty Ltd [2016] QPEC 055
Bielby v Moreton Bay Regional Council [2018] QPEC 50
Coominya Sand & Gravel P/L v The Council of The Shire of
Esk [2006] QCA 208
Devy & Anor v Logan City Council [2010] QPEC 96.
Flamingo Enterprises Pty Ltd v Sunshine Coast Regional
Council [2009] QPEC 101
Grassby v R (1989) 168 CLR 1
Jakel Pty Ltd & Ors v Brisbane City Council & Anor [2018]
QPEC 21
Knight v SP Special Assets Ltd (1992) 174 CLR 178 at 205
Maryborough Investments Pty Ltd v Fraser Coast Regional
Council [2010] QPEC 113
Oshlack v Richmond River Council (1998) 193 CLR 72
R v Forbes; Ex parte Bevan (1972) 127 CLR 1
Tremellen & Tremellen v Southern Downs Regional Council
& Ors [2010] QPEC 94
COUNSEL: A Williams (sol.) for the applicant
R Duhig (sol.) for the respondent
SOLICITORS: p&e law for the applicant
Thomson Geer for the respondent
-- 2 of 25 --
3
Introduction
[1] By originating application filed on 3 May 2018 the applicant sought the following
declarations and orders in respect of a development permit for a Material Change of
Use (Impact Assessment) and Environmentally Relevant Activity no. 20B and 22B
for extractive industries, at 362 Seventeen Mile Road, Helidon and described as lot 2
on RP189455:
“1. Declarations pursuant to s 11(1) of the Planning and
Environment Court Act 2016 (Qld) (PEC Act), as varied by
s 76(1)(b) and (4)(a) of that Act, that:
a. The development permit being a material change of
use and environmentally relevant activity no. 20B and
22B for extractive industries (the Development
Approval), has lapsed pursuant to condition 4 of that
approval;
b. There has been non-compliance with the requirements
of s 369 of SPA in that the applicant failed to apply
for a permissible change to delete condition 4 prior to
its lapsing; and
c. The proposed change to delete condition 4 is a ‘minor
change’ pursuant to the Planning Act 2016, and
2. Orders pursuant to s 11(4) of the PEC Act that:
a. The failure to apply for a permissible change to the
Development Approval under SPA prior to its
lapsing, is excused; and
b. the development approval be revived; and
c. the development approval be amended by deleting
condition 4 and deleting references to mining leases
50094 and 50110.
3. Any such further or other orders as this Honourable Court
considers appropriate.”1
[2] The uncontentious contextual circumstances to this application are that:
(a) In 1995 and 1996, Helidon Sandstone (Australia) Pty Ltd, the previous
owner of the subject land, was granted mining leases (ML) 500942 and
501103 to mine building stone (sandstone) on the land.
(b) Around 12 January 2005 Helidon Sandstone (Australia) Pty Ltd made
a development application, to the Gatton Shire Council under the
repealed Integrated Planning Act 1997 (“the IPA”), for the extraction
1 Originating Application pp 1-2.
2 Exhibit MH–2 at p 76.
3 Exhibit MH–2 at p 73.
-- 3 of 25 --
4
of sandstone boulders, gravel and base.4 And that was given the
reference no. DA3314. After appropriate referrals the application was
impact assessed against the planning scheme of the Shire of Gatton
1995 and ultimately approved, subject to conditions.5 It may be noted
that:
(i) The approval described the use as “‘mining lease plus
extractive industry”6 but the mining lease regulated the mining
activities, pursuant to the Mineral Resources Act 1989, and the
extractive industries use was regulated by the IPA approval.
(ii) Whilst the extraction and screening of gravel and base was
associated with the mining activities, it did not form part of
those activities authorised under the mining leases and
therefore required a separate development approval under
IPA.7
(iii) Condition 4 of the Development Approval was as follows:8
‘The life of this development permit is limited to
31 December 2015 to coincide with the expiry of ML
50094 and 50110. After such time the landowner may
lodge a new application to undertake further
extractive industries on the subject land’; and
(c) Around 6 December 2011, Trevor Brooks Earthmoving Pty Ltd
purchased the land with the benefit of the mining leases, development
approval and extractive industries local law permit issued under the
now repealed local law no. 34.9 Subsequently, the applicant
commenced extraction and screening on the land and has only
operated the extractive industries and does not carry out mining
activities.10
[3] As is common ground, the development approval has expired or lapsed, in the
following circumstances:
4 Exhibit MH–2 at p 2.
5 Exhibit MH–2 at pp 2, 16–24.
6 Exhibit MH–2 at p 16.
7 See applicant’s written submissions filed on 10 August 2018 at [6(c)(iv)]
8 Exhibit MH–2 at p 17.
9 Exhibit TMC–2 at [9].
10 Affidavit of Therese Marie Cottone at [8]–[9] and [23].
-- 4 of 25 --
5
(a) On 3 December 2014 the applicant was advised by its town planning
consultant that the approval would expire on 31 December 2015, to
coincide with the expiry of the mining leases.11
(b) The applicant chose not to renew the mining leases. However on 13
February 2015, the site senior executive for the applicant attended
upon the respondent to enquire as to what steps needed to be taken to
prevent the approval from lapsing. She was advised that local law no.
34 had been repealed and that there was no need to renew the local law
permit and that the quarry would need to continue to operate in
compliance with the conditions of approval. It is noted that such
advice was effectively confirmed by way of an email dated
20 February 2015.12
(c) The uncontested evidence before the court is that the senior executive
for the applicant failed to understand the difference between the local
law permit and the material change of use permit and the need to renew
the material change of use permit.13
(d) However, in November 2017, the applicant was made aware that the
approval had in fact lapsed. And on further enquiry made for the
applicant, an officer of the respondent advised that at the time of the
enquiries in February 2015, the applicant should have been clearly
advised to apply to have the condition deleted and that if this did not
occur, a new development application would need to be made at the
applicant’s expense. It was then in late November 2017 that the
applicant was advised by a town planner that an alternative option was
to seek relief from the court.14
[4] It may be noted that Trevor Brooks Earthmoving Pty Ltd, as owner of the subject
land, has given consent for this application.15 And further, that when the application
came before the court on 10 August 2018, the position of the respondent was to
support the making of the orders sought by the applicant, as follows:16
11 Affidavit of Therese Marie Cottone at [12].
12 Affidavit of Therese Marie Cottone at [13]–[17].
13 Affidavit of Therese Marie Cottone at [18].
14 Affidavit of Therese Marie Cottone at [20], [24]–[25].
15 Exhibit HCS–2.
16 T1–9.15–23.
-- 5 of 25 --
6
“IT IS DECLARED, pursuant to ss11(1) of the Planning and
Environment Court Act 2016, that:
1. The subject development permit has lapsed.
2. There has been non-compliance with the requirements
of s369 of the Sustainable Planning Act 2009 in that
the Applicant failed to apply for a permissible change
to condition 4 of the development permit prior to it
lapsing.
3. The proposed changes to the development permit are
minor changes.
IT IS ORDERED, pursuant to ss11(4) of the Planning and
Environment Court Act 2016, that:
1. The noncompliance is excused.
2. The development permit be revived and amended is
accordance with the conditions attached hereto and
marked “A”, contained at pages 1–41.”
[5] That position was presented as an agreed position between the parties and so that the
operation of the otherwise lapsed approval was extended from 31 December 2015 to
a new expiry date on 31 December 2030 and to incorporate other changes as required
by the respondent, so as to bring the approval within contemporary compliance
requirements for such an approved use. Such additional changes were identified to be
of a kind that might be allowed pursuant to s 81(4)(a) of the PA.
[6] However the nature of the relief being sought is not of a kind which may be granted
by the court on a consent basis. As was accepted by each party, there remains the
question of the exercise of the court’s discretion and moreover, and as the applicant
initially sought to identify, the basis upon which the court might grant that relief,
particularly having regard to the consideration of the legislative changes, whereby the
Sustainable Planning Act 2009 has now been repealed by the enactment of the
Planning Act 2016, with the concomitant enactment of the Planning and Environment
Court Act 2016, with effect from 3 July 2017.
[7] Such orders were not made when they were first sought on 17 August 2018. That
was largely due to issues raised by the court in respect of the identification of the
basis upon which the court was invited to act pursuant to the PECA and the PA.
Subsequently leave has been granted for the making of further written submissions
and the taking of further submissions and which have served to crystallize some
significant issues as to whether or not the Court has power to grant the relief that is
sought and particularly upon the applicant’s purported reliance solely upon s 11(4) of
the PECA, in that respect.
-- 6 of 25 --
7
Discussion
[8] Ultimately, both parties sought to maintain the position that s 11(4) provided the
power for granting the relief sought consequently to the declarations sought pursuant
to s 11(1) of the PECA. However the respondent also embraced an alternative
contention that the appropriate interpretation of s 76(6) of the PECA was that the
operation of s 440 of SPA was preserved, in these circumstances, and available as that
source of power. As it will be necessary to return to these contentions in more detail,
below, it suffices, at this point, to note that although the applicant did raise this
alternative prospect, the contention was neither entirely embraced nor entirely
abandoned.17
[9] As is exemplified by the decision in Coominya Sand & Gravel P/L v The Council of
The Shire of Esk [2006] QCA 208, prior to the operation of the Sustainable Planning
Act 2009 (“SPA”) the power of this court to excuse the type of non-compliance with
legislative requirements, as is sought here and to make remedial orders, was quite
limited. In that case the Court of Appeal upheld the decision of the primary judge to
dismiss an application made pursuant to the IPA to amend a condition in a permit
permitting the use of land for sand mining. In that case the condition in issue
provided:
“This approval will be valid for a period of ten (10) years from the
date of issue of a Town Planning Consent Permit [issued on 8 May
1995] in accordance with condition two (2) of this Order.”18
That may be compared with the condition in issue on the application made here,
which is in the following terms:
“4. The life of this development permit is limited to 31December
2015 to coincide with the expiry of ML50094 and 50110. After
such time the land owner may lodge a new application to
undertake further extract of industries on the subject land.”
[10] However, in the Coominya case, the problem was that the application had been made
before the permit expired, on 12 May 2005, but it did not come before the Court, for
determination, until after that date and therefore after the expiry of the permit. The
effect of the decision was that after finding the absence of any provision in the IPA
to save the permit from lapsing or expiring in accordance with the abovementioned
17 See applicant’s written submissions filed on 17 August 2018 at [14] and the applicant’s third
supplementary written submissions filed 14 September 2018.
18 Coominya Sand & Gravel P/L v The Council of the Shire of Esk [2006] QCA 208 at [11].
-- 7 of 25 --
8
condition, there was, by the time the matter came before this court, “no longer any
permit with conditions to amend.”19 And as Muir J found, there was no basis for
finding error in the conclusion of the primary judge that the approval to which the
condition had attached had expired through effluxion of time after the filing of the
application and before the determination of it, with the consequence that the Court
“had no power to order that the condition be changed.”20 His Honour further
observed:
“[34] It has long been established that, in the absence of some
enabling provision, the making of an application for renewal
during the term of a lease or licence granted under statute does
not preserve the power to renew the lease or licence after its
term has expired. The fact that the Planning and Environment
Court or other determining authority may be unable to extend
the term of a permit once it has expired does not appear to me
to be a matter of concern. A permittee may make a timely
application. It would also be within power to extend the term
of a permit for a period sufficient to enable an application to
be heard and determined before the permit expires.
[35] In the course of argument, the view was expressed from the
bench that it would have been open to the applicant to include
in its application an application for an order extending the
term of the Permit for a period sufficient to enable the
principal application to be heard and determined prior to the
expiration of the Permit. Counsel for the applicant accepted
that such a course would have been open to the applicant.”
[11] However and as may be noted from the applicant’s reliance upon the decision in
Agnes Bridge Pty Ltd v Central Highland Regional Council,21 this court has since
accepted and acted upon the basis that such power was provided by the enactment of
s 440 of SPA, which provides:
“440 How court may deal with matters involving noncompliance
(1) Subsection (2) applies if the court finds a provision of this
Act, or another Act in its application to this Act, has not been
complied with, or has not been fully complied with.
(2) The court may deal with the matter in the way the court
considers appropriate.
(3) To remove any doubt, it is declared that this section applies in
relation to a development application that has lapsed or is not
a properly made application.”
19 Ibid at [7].
20 Ibid at [13] and [37].
21 [2015] QPEC 61.
-- 8 of 25 --
9
[12] As discussed in Tremellen & Tremellen v Southern Downs Regional Council & Ors,22
in reference to the equivalent transitional provisions, in s 820 of SPA and in respect
of matters that arose under the repealed IPA, that position is to be contrasted with the
restrictions of the nearest prior analogue in the IPA, s 4.1.5A, and as those restrictions
were particularly noted in Flamingo Enterprises Pty Ltd v Sunshine Coast Regional
Council23 and in Devy & Anor v Logan City Council.24 In the latter case, it was
observed:
“The situation has been recognised and remedied by the legislature in
the SPA which provides an untrammelled discretion where a,
‘provision has not been complied with – or fully complied with.’
What is evident, in any event, from the different language used in the
statute is reaffirmed by the Explanatory Notes, including the
Explanatory Note to section 440 which, in part, provides, ‘The term,
“provision” is intended to be interpreted broadly and it's not limited to
circumstances where there is a positive obligation to take a particular
action.’"25
[13] In the Agnes Bridge decision,26 there is reference to these earlier decisions of the
Court recognising this broad effect of s 440 and the identical provision in s 820, and
the applicability of such provisions to lapsed approvals. A reason for the reference to
the Agnes Bridge decision is that it also involved a lapsed or expired approval because
of the following condition of the approval:
“The use permitted as part of this approval is retail/commercial
complex. This approval has a currency period of four years and will
remain in force until 16 June 2014. Should the development not be
completed within this timeframe, this approval will lapse. A new
application will need to be made to council unless an approval has
been obtained for an extension of this period.”27
This decision is also an example of the granting of the entire form of relief that is
sought by this applicant and which was there described as “an application which
essentially seeks to revive, change and extend a lapsed development permit.”28
However and in that regard, it is necessary to note that in that case, the application
for permissible change to the development approval and so as to allow the extension
22 [2010] QPEC 94.
23 [2009] QPEC 101.
24 [2010] QPEC 96.
25 Ibid at p 3.
26 [2015] QPEC 61 at [12]–[15].
27 Ibid at [3]. Similar reference may also be made to Beerwah Land Pty Ltd v Sunshine Coast Regional
Council; Woodlands Enterprise Pty Ltd v Beerwah Land Pty Ltd & Anor and; Sunshine Coast
Regional Council v Beerwah Land Pty Ltd [2016] QPEC 055 at [38] and Maryborough Investments
Pty Ltd v Fraser Coast Regional Council [2010] QPEC 113 at [30].
28 Ibid at [1].
-- 9 of 25 --
10
of the operation of the approval, had been made to the Court (because the approval
had been by prior order of the Court) five days prior to the expiry date, as set out in
the condition.
[14] For the applicant, it is correctly pointed out that an effect of s 76(6) & (7) of the PA
is to recognise and clarify such breadth of operation of s 440 of the repealed SPA and
to that such clarification is also expressed in s 37(3) of the PECA. It is desirable to
note the full terms of each section:
“37 Discretion to deal with noncompliance
(1) If the P&E Court finds there has been noncompliance with a
provision of this Act or an enabling Act, the court may deal
with the matter in the way it considers appropriate.
(2) Without limiting subsection (1) and to remove any doubt, it
is declared that subsection (1)—
(a) applies for a development approval that has lapsed, or
a development application that has lapsed or has not
been properly made under the Planning Act; and
(b) is not limited to—
(i) circumstances in relation to a current P&E
Court proceeding; or
(ii) provisions under which there is a positive
obligation to take particular action.
(3) In this section—
noncompliance, with a provision, includes—
(a) non-fulfilment of part or all of the terms of the
provision; and
(b) a partial noncompliance with the provision.
provision includes a definition.
…
76 Proceedings
(1) This section applies to a matter under repealed SPA or an
enabling Act if a person—
(a) had started proceedings under repealed SPA before
the commencement but the proceedings had not ended
before the commencement; or
(b) had, immediately before the commencement, a right
to start proceedings under repealed SPA; or
(c) has a right to start proceedings that arises after the
commencement in relation to—
(i) a statutory instrument mentioned in the
Planning Act, section 287; or
-- 10 of 25 --
11
(ii) an application mentioned in the Planning Act,
section 288; or
(iii) any provision of an enabling Act that provides
for the continuation of the matter after the
commencement.
(2) This Act applies to any appeal in relation to proceedings
mentioned in subsection (1)(a).
Example—
Proceedings are continued under the Planning Act,
section 311(2)(a). This Act will apply to an appeal in
relation to the proceedings.
(3) This Act applies to the proceedings mentioned in subsection
(1)(b) or (c) subject to subsections (4) and (5).
Example—
A person starts proceedings under the Planning Act,
section 311(4). This Act will also apply to the
proceedings.
(4) For proceedings brought under section 11—
(a) a reference in that section to the Planning Act is taken
to include a reference to repealed SPA; and
(b) a reference in that section to the Planning Act, chapter
3, part 6, division 2 is taken to include a reference to
repealed SPA, chapter 6, part 11, division 1; and
(c) a reference in that section to the Planning Act, chapter
3, part 6, division 3 is taken to include a reference to
a call in of an application under repealed SPA, chapter
6, part 11, division 2.
(5) For proceedings brought under section 12—
(a) a reference in that section to the application the
subject of a call in under the Planning Act is taken to
include a reference to an application under repealed
SPA, chapter 6, part 11, division 2; and
(b) a reference in that section to the assessment manager
is taken to include a reference to an assessment
manager under repealed SPA.
(6) Also, to remove any doubt, it is declared that repealed SPA,
section 440—
(a) applies also for a development approval that has
lapsed; and
(b) is not limited to—
(i) circumstances in relation to a court proceeding
under repealed SPA or a current P&E Court
proceeding; or
(ii) provisions under which there is a positive
obligation to take particular action; and
-- 11 of 25 --
12
(c) applies as if a reference to a provision not being
complied with, or not being fully complied with, is
taken to include—
(i) non-fulfilment of part or all of the provision;
and
(ii) a partial noncompliance with the provision.
(7) In this section—
provision includes a definition.”
[15] In order to confirm such an interpretation or the purpose of these provisions, reference
is made to the explanatory notes accompanying the bills which, respectively, became
the PECA and the PA:29
(a) In respect of s 37, as follows:
“Clause 37 provides the Planning and Environment Court with
broad discretionary powers to relieve against any non-
compliance, partial non-compliance or non-fulfilment of any
provision of the Bill or an enabling Act. The intent of this
clause is to ensure a person’s rights to a hearing are not
compromised on the basis of technicalities concerning
processes.
Recent case law has identified issues with the current
equivalent provision in SPA, section 440, and the transitional
provision in section 820. It was held by the Planning and
Environment Court that these provisions do not apply to
matters of non-fulfilment, and it was unclear whether the term
‘provision’ also includes a definition. This clause aims to
address these identified issues, to ensure the Planning and
Environment Court has appropriate excusatory powers.
The term “provision” is intended to be interpreted broadly,
includes a definition, and is not limited to circumstances where
there is a positive obligation to take a particular action.
The clause clarifies that it applies to a development approval
that has lapsed, or a development application that has lapsed
or has not been properly made under the Planning Act. The
intent is to include other matters that may not otherwise by
valid, for example, timeframes that have not been complied
with, fees that have not been paid, a change or mistake in
relation to: ownership details; boundaries of land; an entity
which should have issued a notice; provisions referred to in a
development application or development approval under the
Planning Bill 2015 or an approval or permit (howsoever called)
granted under an enabling Act.
This clause enables the court to give relief in response to
proceedings commenced for that purpose or in the context of
other proceedings; and to give that relief notwithstanding any
29 Planning and Environment Court Bill 2015 and Planning Bill 2015.
-- 12 of 25 --
13
other provision of the Bill or an enabling Act, including
provisions which would otherwise provide that an application
had lapsed.
The court’s power is not restricted to proceedings before it.
This allows access to the Planning and Environment Court for
declarations and orders about procedural disputes which do not
form part of wider proceedings.
The intent of the clause is that the Planning and Environment
Court may deal with the matter in the way it considers
appropriate. The inbuilt flexibility of this clause enables the
parties to achieve a range of outcomes, premised on the
position that legal technicality should not defeat appropriate
development, unless in the court’s discretion there are reasons
to do so.”
(b) And in respect of s 76, as follows:
“…
Also, the clause provides for how the Planning and
Environment Court is to deal with noncompliance under
repealed SPA section 440. This is intended to ensure the
Planning and Environment Court has as much flexibility as is
necessary to adequately dispense with matters.
….”
[16] However and as was recognised for the applicant, it was recently determined in Jakel
Pty Ltd & Ors v Brisbane City Council & Anor,30 that the SPA may not be regarded
as an “enabling Act” for the PECA.31 Accordingly, resort to section 37 of PECA is
not available for this application.
The power of the Court pursuant to s 11(4) of the PECA
[17] First, it is convenient to note the provisions of s 11 of the PECA:
“11 General declaratory jurisdiction
(1) Any person may start a P&E Court proceeding seeking a
declaration (a declaratory proceeding) about—
(a) a matter done, to be done or that should have been done
for this Act or the Planning Act; or
(b) the interpretation of this Act or the Planning Act; or
(c) the lawfulness of land use or development under the
Planning Act; or
(d) the construction of a land use plan under the Airport
Assets (Restructuring and Disposal) Act 2008 and the
interpretation of chapter 3, part 1 of that Act; or
30 [2018] QPEC 21 at [51].
31 See s 7 PECA.
-- 13 of 25 --
14
(e) the construction of the Brisbane port LUP under the
Transport Infrastructure Act 1994.
Note—
Under the Acts Interpretation Act 1954, section 7, a reference to an Act
in this list of subject matter about which a declaration may be sought
includes a reference to the statutory instruments made under the Act.
(2) However, a declaratory proceeding for a matter under the
Planning Act, chapter 3, part 6, division 3 may be started only
under section 12.
(3) Also, a person may not start a declaratory proceeding for a
matter under the Planning Act, chapter 3, part 6, division 2.
(4) The P&E Court may also make an order about any declaration
it makes.”
[18] As is correctly pointed out for the applicant, reference to s 76(4) of the PECA
confirms the application of s 11(1) to declaratory relief for matters arising under the
SPA and particularly pursuant to s 11(1)(a) in respect of “a matter done, to be done
or that should have been done for” the SPA.
[19] It is unnecessary to attempt to prescribe the precise limits of any power provided to
the Court in s 11(4) and it may be accepted, as was contended for the applicant, that
generally:
“It is inappropriate to read a provision conferring jurisdiction or
granting powers to a court by making conditions or imposing
limitations which are not found in the words used.”32
The problem, however, is in discerning any expression or implication of power from
the generality of the provision, which is also capable of being viewed as simply
making clear that the engagement of the jurisdiction of the Court to grant declaratory
relief of the kind allowed in s 11(1), also enables consequential relief, as might
otherwise be within the jurisdiction of the Court. It must be kept in mind that this
Court is one of statutory creation and that its powers are to be gleaned from the
statutory provisions providing it with jurisdiction to exercise, by express provision or
necessary implication. The distinction to be drawn with a superior constitutional court
is discussed in Grassby v R,33 including by reference to the following observations of
Menzies J:
“Inherent jurisdiction' is the power which a court has simply because
it is a court of a particular description. Thus the Courts of Common
Law without the aid of any authorizing provision had inherent
jurisdiction to prevent abuse of their process and to punish for
32 Oshlack v Richmond River Council (1998) 193 CLR 72, at [21] and the authorities there cited,
including Knight v SP Special Assets Ltd (1992) 174 CLR 178 at 205.
33 (1989) 168 CLR 1 at 15–17.
-- 14 of 25 --
15
contempt. Inherent jurisdiction is not something derived by
implication from statutory provisions conferring particular
jurisdiction; if such a provision is to be considered as conferring more
than is actually expressed that further jurisdiction is conferred by
implication according to accepted standards of statutory construction
and it would be inaccurate to describe it as 'inherent jurisdiction',
which, as the name indicates, requires no authorizing provision.
Courts of unlimited jurisdiction have 'inherent jurisdiction'.”34
[20] Accordingly, it should not be concluded that s11(4) of the PECA, alone, may be
regarded as the source of any power of this Court to grant the relief that is sought.
Has the application of s 440 of the SPA been preserved?
[21] The approach of the applicant in focusing upon s 11(4) of the PECA as the source of
relief, is to be understood in the context that:
(a) First, it is correctly identified that the terms of s 76 of the PECA
are, perhaps, ambiguous as to whether it is intended that the
operation of s 440 of the SPA is preserved for situations of this
type. In this regard particular attention is drawn to s 76(3), as
requiring the application of the PECA, as this is not an instance
contemplated by s 76(1)(a), there being no uncompleted
proceedings commenced under the SPA and before the
commencement;35 and
(b) Secondly, there emerged in the applicant’s position an underlying
concern that, without resort to s 11(4), the applicant’s relief in this
court would not extend to having the changes made to the
approval, which might require a further and separate application
to me made to the respondent as the responsible entity, pursuant
to s 78 of the PA.36
[22] As is correctly noted for the applicant, upon the commencement of the Planning Act,
on 3 July 2016, the SPA was repealed by s 325 of the PA. And s 311 of the PA
relevantly provides:
34 R v Forbes; Ex parte Bevan (1972) 127 CLR 1 at 7.
35 That is subject to s 76(4) and (5), which may be put aside for present purposes, save for noting (as
has been done above at […]) the effect of s 76(4) in respect of reference to the Planning Act in s 11
being taken to include a reference to the repealed SPA.
36 See second supplementary written submissions of the applicant at [33] to [35]; third supplementary
written submissions at [11] and as noted in oral submissions on 14 September 2018.
-- 15 of 25 --
16
“(1) Subject to section 312, this section applies to a matter under the
old Act, if a person—
(a) had started proceedings before the commencement but
the proceedings had not ended before the
commencement; or
(b) had, immediately before the commencement, a right to
start proceedings; or
(c) has a right to start proceedings that arises after the
commencement in relation to—
(i) a statutory instrument mentioned in section 287;
or
(ii) an application mentioned in section 288.
(2) For proceedings that were started in the Planning and
Environment Court, Magistrates Court or the Court of
Appeal—
(a) the old Act continues to apply to the proceedings; and
(b) this Act applies to any appeal in relation to the
proceedings as if the matter giving rise to the appeal
happened under this Act.
…
(4) For proceedings mentioned in subsection (1)(b) or (c),
proceedings may be brought only under this Act.”
[23] The provisions of s 312 are not relevantly engaged and therefore the applicant, who
may be regarded as able to engage s 311(1)(b), on the basis of having had a right,
immediately before the commencement, to start proceedings to obtain excusal of the
omission to have done so before the expiry of the approval and revival of the approval,
so that it might be the subject of a permissible change pursuant to s 369 of the SPA.
However, the problems then actually confronting the applicant are that, in the
application of the PA pursuant to s 311(4);
(a) the applicant’s ability to make a change application pursuant to
s 78 of the PA, would be dependent upon there being a remedy to
effect the revival of the expired approval, so that it could be so
changed; and
(b) although s 37 of the PECA, is clearly intended to replace s 440 of
SPA, it may not be engaged, as s 37(1) requires non-compliance
with the PECA or an “enabling Act”, which does not include the
SPA.37
[24] However, the respondent concedes the preserved availability of s 440 of the SPA in
aid of the relief that the applicant seeks. And it may be accepted that such is indeed
37 See Jakel Pty Ltd & Ors v Brisbane City Council & Anor [2018] QPEC 21 at [51].
-- 16 of 25 --
17
the intended effect of s 76 of the PECA. This is because of the apparent effect of
s 76(6):
(a) First, s 76(6) may be noted to be a provision that is entirely
unnecessary “to remove any doubt” as to the application of the
SPA, including s 440, to the circumstances contemplated in s
76(1)(a), as this is the express effect of s 311(2) of the PA;
(b) Secondly, the effect of s 76(6)(b)(i) is “that [the application of]
repealed SPA s 440 … is not limited to - circumstances in relation
to a court proceeding under repealed SPA or a current P&E Court
proceeding.” This appears to be a clear indication that the
operation of s 76(6) is not limited to the circumstances that are
contemplated in s 76(1)(a) and intended as an acknowledgement
of the applicability of s 76(6) to the circumstances contemplated
in s 76(1)(b) and (c);
(c) Thirdly, and to the extent that ambiguity, or conflict with s 76(3)
may be perceived, it is permissible to have regard to the relevant
explanatory notes,38 and it may be noted that:
(i) In respect of the general achievement of policy objectives
and under the heading “discretion to deal with non-
compliance”,39 it is observed:
“The Bill continues a provision to deal with
non-compliance where the Planning and
Environment Court finds there has been
noncompliance with a provision of this Act or
an enabling Act. In these instances, it is
intended that the Planning and Environment
Court may deal with the matter in the way it
considers appropriate. In addition, recent
case law has identified issues with the current
equivalent provision in SPA, which have also
been rectified by this Bill. The inbuilt
flexibility of this clause continues to enable
the parties to achieve a range of outcomes,
premised on the position that legal
technicality should not defeat appropriate
development, unless in the court’s discretion
there are reasons to do so.”
38 See explanatory notes for the Planning and Environment Court Bill 2015.
39 At pp 4–5.
-- 17 of 25 --
18
(ii) The specific notes in relation to clause 37, which became s
37 of the PECA, indicates an approach to “ensure a
person’s rights to a hearing are not compromised on the
basis of technicalities concerning processes” and that the
provisions of s 37(2) and (3), which are repeated in s
76(6)(a), (b)(ii) and (c), are calculated to provide for a
broad power of excusal and remedy for prior
noncompliance with statutory obligations and “to address
these identified issues, to ensure the Planning and
Environment Court has appropriate excusatory powers”,
and as particularly demonstrated by the statement:40
“The intent of the clause is that the Planning
and Environment Court may deal with the
matter in the way it considers appropriate.
The inbuilt flexibility of this clause enables
the parties to achieve a range of outcomes,
premised on the position that legal
technicality should not defeat appropriate
development, unless in the court’s discretion
there are reasons to do so.”
(iii) The specific notes for clause 76, which became s 76 of the
PECA, where after noting that the clause “provides for
transitional arrangements for proceedings under the
repealed SPA or an enabling Act”, it is stated:41
“Also, the clause provides for how the
Planning and Environment Court is to deal
with noncompliance under repealed SPA
section 440. This is intended to ensure the
Planning and Environment Court has as much
flexibility as is necessary to adequately
dispense with matters.”
[25] Accordingly, and by reference to these materials, it is possible to discern an
interpretation and statutory intent that s 76(6) is to apply to appropriately preserve the
operation of s 440 of the SPA and where such excusatory power of this court may be
required in respect of past noncompliance with the SPA. And to overcome any sense
40 At p 24.
41 At p 35.
-- 18 of 25 --
19
of ambiguity as to the application of the sub-section,42 and, more particularly, to
confirm an interpretation, consistently with the apparent purpose of the provision, that
s 76(6) is intended to operate and apply separately and notwithstanding the
application of s 76(3) otherwise.43
[26] Clearly, that position may have been more readily achieved by an express statement
that s 76(3) is “subject to sub sections (4), (5) and (6)”. However, it would appear to
be the most sensible implication of the specific addition of the words “a court
proceeding under repealed SPA” in s 76(6)(b)(i), in contrast to the analogous
provision in s 37(2)(b)(i), that the legislative intention is to preserve the operation 440
of the SPA, with the noted clarifications, for any circumstances where it may be
appropriate to engage the powers to excuse past non-compliance with the SPA and
not limited to where there were proceedings commenced, in such respect, under the
repealed SPA prior to the commencement. Such a conclusion is also supported by the
further contrast with s 37(2) of the PECA and the use of the word “Also”, rather than
the words “Without limiting sub section (1)”.
[27] It is also notable that in further contrast to s 37(2)(a) of the PECA, the declared
continuing application of “repealed SPA section 440” is expressed in s 76(6)(a), to be
“also for a development approval that has lapsed”, without repetition of the
comparable reference that appeared in s 440(3) of the SPA and which now appears in
s 37(2)(a) of the PECA to a development application that has not been properly made.
That may be seen to differ from the effect of s 311(2) of the PA as to the entire
preservation of the SPA in existing proceedings at the commencement. Such an
approach may be seen as broadly consistent with the effect of s 286(1) and (2) of the
PA, in continuing the validity of documents, including approvals, in effect at time of
repeal of the SPA, and so as to additionally allow for the continued application of the
repealed s 440 of the SPA and therefore, the potential application of the excusal power
and appropriate remedy of revival of an approval, notwithstanding the prior lapsing
of it due to non-compliance with the SPA.
[28] However and in contrast to the situation in respect of proceedings commenced under
the SPA, prior to 3 July 2016, and the preservation of all of the SPA in reference to
42 Acts Interpretation Act 1954; s 14B(1)(a).
43 Ibid; s 14B(1)(c) and s 14A.
-- 19 of 25 --
20
such proceedings by s 311(2) of the PA, the effect of s 76(6) of the PECA is only to
preserve the relevant operation of s 440 of the SPA.
What relief is available to the applicant?
[29] Accordingly, s 11 of the PECA is appropriately engaged by the applicant and, to the
extent that it may be necessary or appropriate to do so, declaratory relief, in order to
identify the non-compliance with the SPA, is permitted by s 11(1) read with s 76(4)
of the PECA. Further and as has been noted and in terms of consequential relief
pursuant to s 11(4) and s 76(6) of the PECA and s 440 of the SPA, the court is
empowered to deal with “the matter in the way the court considers appropriate”.
[30] However, the further problems confronting the applicant are that the lapsing or expiry
of the approval was not of a kind that was expressly dealt with in s 341 of the SPA,
or now dealt with in s 85 of the PA.44 Notwithstanding this, it should not be concluded
that the reference to “a development approval that has lapsed” in s 76(6)(a) and s 37
of the PECA, is any impediment to the application of that provision to the lapsing or
expiry of an approval because of the terms of a condition of the approval. For each
of the express statutory references to “lapsing” of approvals, the express contextual
limitation is to a “currency period” for relevant commencement of the approved
development, rather than a currency period in the sense of a time limit for the
continuation of an approved use of land, without further consideration of it. However,
it would not be consistent with the broad approach adopted under s 440 of the SPA,
which, in the first instance, was not seen as preventing the application of that power
to lapsed approvals, notwithstanding the express reference only to “a development
application that has lapsed or is not a properly made application” in s 440(3), to
necessarily regard the excusal power to be limited to the expressly recognized
instances of lapsed approvals. And that was not the view taken in the Agnes Bridge
decision and in respect of the lapsing or expiry of an approval pursuant to a similar
type of condition of an approval.45
[31] Notwithstanding these conclusions, there still remains the distinction with the
situation in the Agnes Bridge decision, in that the Court was, there, ultimately able to
consider and allow the application for permissible change to the approval, as an
44 Cf: Bielby v Moreton Bay Regional Council [2018] QPEC 50 as to the situation in respect of the
lapsing of an approval granted under the SPA, subsequently to the commencement of the PA.
45 See paragraph [ ],above.
-- 20 of 25 --
21
application that had been made to the Court prior to but not within sufficient time to
allow for determination of it, before the lapsing or expiry of the approval. But what
needs to be understood is that in instances of this kind, all considerations as to excusal
as to the absence of sufficient attention to such time limitation of the currency of an
approval, must necessarily be in respect of the making of a change to the relevant
approval, rather than simply allowing for an extended currency of an approval and so
as to then allow for an appropriate change application.46 Further, it may also be noted
that even under the SPA and without the additional complications of the
commencement of the PA and the PECA and when s 440 was so invoked, the available
relief could only be by allowing a change to the condition which provided for the time
limitation of the approval. Or put another way, there could be no effective excusal of
non-compliance and revival of the approval, without the determination of the change
application. The effect would be that the despite the excusal power pursuant to s 440
of the SPA (now s 37 of the PECA) being vested solely in the Court, that power could
not be exercised where the Court was not the “responsible entity” for any change
application that should have been made and where it is the failure to appropriately do
so which may otherwise be excused.
[32] In these circumstances, it would simply not be consistent with the history of the
approach of this Court as to the breadth of the discretion allowed by s 440 of the SPA
and particularly as now recognised, reinforced and clarified by the enactment of s 37
and s 76(6) of the PECA, to deny an ability of this Court to grant the type of relief
that is sought, if that were considered to be an appropriate exercise of discretion. And
entirely consistent with the reservation of the application of the declaratory power in
s 11(1) of the PECA, to matters arising under the repealed SPA, to recognize the
power of this Court to grant appropriate relief, to be derived from the combined effect
of s 11(4) and s 76(6) of the PECA and s 440 of the SPA.
[33] Accordingly and having regard to the limited effect of s 76(6), in preserving only the
operation of s 440 of the SPA for this purpose, and the context of s 76(3) in requiring
the application of the PA to circumstances which fall within s 76(1)(b), an appropriate
conclusion is that the court may consider the matter as if it were “a change
application” made pursuant to s 78 of the PA.
46 See: Bielby v Moreton Bay Regional Council [2018] QPEC 50.
-- 21 of 25 --
22
Discretionary Considerations
[34] Such conclusion accommodates the approach of the applicant at the outset of this
matter, as demonstrated by the submission that:
“The Applicant seeks an excusal of the noncompliance and seeks minor
changes to the approval to facilitate its revival.”47
And that approach has been to provide material in order to effectively pursue such a
change application.
[35] As further explained in those submissions, the relief sought, with the agreement of
the respondent, has been negotiated, in that:
“27. While the Originating Application sought to have condition 4
deleted, after discussions with the Respondent, the Applicant now
seeks to have condition 4 amended so that the approval is extended
until 31 December 2030.
28. The Applicant also seeks minor consequential changes to the
approval which:
a) delete references to the mining leases and superseded
Local Law 34;
b) update the conditions to reflect contemporary laws,
policies and standards;
c) allow for alternative access to Seventeen Mile Road;
and
d) update conditions 10 and 34 to refer to the new
Environmental Authority for ERA 16 (extraction and
screening).”48
[36] As to any implications as to potentially interested parties and as may arise from ss 78
to 80 of the PA, it may be noted that:
(a) there is evidence that the consent of the owner of the land, has
been given for this application;49
(b) no changes are proposed to any referral agency conditions; and
(c) the Chief Executive of the Department of State Development,
Manufacturing, Infrastructure and Planning was given notice of
this application and did not elect to join this proceeding.50
47 Applicant’s written submissions, filed on 10 August 2018 at [26].
48 Those changes are discernible as being marked in red in the attachment to the written submissions of
the applicant, filed on 10 August 2018.
49 Exhibit HCS-2.
50 Exhibit AKW-1, noting that pursuant to s 944A of the SPA the Chief Executive was taken to have
imposed the concurrence agency conditions. It may also be noted to satisfy the requirement under
s 13 of the Planning and Environment Court Rules 2018 to notify the Chief Executive, where
declaratory relief is sought.
-- 22 of 25 --
23
[37] In circumstances where there is evidence of some oversight of the time limit on the
currency of the approval imposed by the condition, in the context of evidence of some
confusion in dealing with related permits, any absence of strength of extenuation may
be overcome by the level of support of the respondent and as to what is accepted
before this Court as an appropriate ongoing use of the subject land and the acceptance
of the applicant of both a further limitation as to the currency period of that use and
that such occur under contemporary standards and conditions and such as might have
been expected to be imposed upon a further application for development approval.
[38] Further, that support may be seen as of assistance to the primary issue for the exercise
of the discretion of the Court and as to whether or not the allowance of the changes
sought, may be seen as consistent with the requirements of either s 81 or s 82 of the
PA. In this instance, the common contention, which may be accepted, is that the
proposed changes may be allowed as being consistent with minor changes under s 81
of the PA and as supported by the uncontested evidence from a town planner, in that
regard. Relevantly, it may be noted:
(a) the Court may be satisfied that the change would not result in
prohibited development, referral to additional referral agencies
other than the chief executive or cause a referral agency for the
original application to assess against, or have regard to matters
under the regulation, other than those matters assessed against and
considered when the application was made; and
(b) Assisted by Mr Harries’ assessment of the other matters listed in
Schedule 1 of the Development Rules, the Court may be satisfied
that the change will not result in substantially different
development and that there is relevantly, only minor change. In
particular, it may be accepted that that while the changes will not
introduce new impacts or increase the severity of known impacts,
the proposed change will prolong known impacts created from the
use and that:
“(i) The conditions imposed within the
development approval and associated
environmental authority will apply, which
ensure that there will be no environmental
-- 23 of 25 --
24
nuisance from noise, dust or odour at sensitive
receptors caused by the development;
(ii) Whilst the continued use of the land for
extractive industries may result in additional
use of Seventeen Mile Road, that road is
identified in the planning scheme as a
transport route within the key resource area
and provides connection to the state-
controlled road system. As the road is a
transport route for extractive industries, the
continued use of the road by the development
will not introduce or increase the severity of
known impacts;51
(iii) The development, including the extension, is
consistent with the now superseded Planning
Scheme of the Shire of Gatton 1995 and is
consistent with the current Gatton Shire
Planning Scheme 2007;
(iv) The Land is within the Rural General Zone
and is mapped within the Helidon key
resources area. And that reading the Rural
General Zone Code and Extractive/Mineral
Resources and Transportation Route Overlay
Code, it is clear that the planning scheme
contemplates extractive industry uses on the
Land. And that the Rural General Zone Code
allows extractive industry uses to occur in that
zone.
(v) The use is regulated by an updated
environmental authority dated 28 November
2014 which is consistent with current
regulatory requirements under the
Environmental Protection Act 1993; and
51 MH-2, page 7.
-- 24 of 25 --
25
(vi) Whilst there were 35 properly made
submissions in relation to the development
application, with the main issues raised in the
submissions relating to: noise, operating
hours, vibration, blasting, dust, vehicle traffic
and road maintenance, site rehabilitation,
visual amenity, environmental impacts and
run-off concerns, it is to be noted that those
submissions were made in respect of an
application that did not propose limitation
upon the currency of the approval and the
changes now proposed would not alter the
operation of the site and that the conditions
continue to adequately address the impacts
raised in those submissions.52
Conclusion
[39] Accordingly, it is appropriate to make the following orders:
IT IS DECLARED, pursuant to s 11(1) of the Planning and Environment Court Act
2016, that:
1. The subject development permit has lapsed.
2. There has been non-compliance with the requirements of s 369 of the
Sustainable Planning Act 2009 in that the applicant failed to apply for a
permissible change to condition 4 of the development prior to it lapsing.
IT IS ORDERED, pursuant to s 11(4) and 76(6) of the Planning and Environment
Court Act 2016 and s 440 of the Sustainable Planning Act 2009, that:
1. The non-compliance is excused.
2. The development permit be revived and amended in accordance with the
conditions attached hereto and marked “A”, contained at pages 1–41.
52 Exhibit MH-2 at pp 8-10.
-- 25 of 25 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2018/051