Bielby v Moreton Bay Regional Council [2018] QPEC 50 [2019] QPELR 197
PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND
CITATION: Shannen Jane Bielby v Moreton Bay Regional Council [2018]
QPEC 50
PARTIES: SHANNEN JANE BIELBY
(applicant)
v
MORETON BAY REGIONAL COUNCIL
(respondent)
FILE NO/S: D 141/2018
DIVISION: Planning
PROCEEDING: Application
ORIGINATING
COURT: Maroochydore
DELIVERED ON: Orders made on 19 October 2018, reasons delivered 22
October 2018
DELIVERED AT: Maroochydore
HEARING DATE: 19 October 2018
JUDGE: Long SC DCJ
ORDERS: 1. The non-compliance be excused.
2. The development approval be revived.
3. The currency period of the development approval
be extended to 21 December 2018 to enable the
applicant to make an extension application to the
respondent pursuant to section 86 of the Planning
Act 2016.
4. Each party bear their own costs.
LEGISLATION: Sustainable Planning Act 2009 ss 284, 341, 440
Planning Act 2016 ss 37, 85, 86, 299
CASES: Beerwah Land Pty Ltd v Sunshine Coast Regional Council;
Woodlands Enterprise Pty Ltd v Beerwah Land Pty Ltd &
Anor and; Sunshine Coast Regional Council v Beerwah Land
Pty Ltd (2016) QPEC 55
Devy & Anor v Logan City Council (2010) QPEC 96
Maryborough Investments Pty Ltd v Fraser Coast Regional
Council (2010) QPEC 113
Telstra Corporation Ltd v Brisbane City Council & Ors
(2016) QPEC 37
-- 1 of 7 --
2
CATCHWORDS: ENVIRONMENT AND PLANNING – ENVIRONMENTAL
PLANNING –DEVELOPMENT CONTROL – CONSENTS,
APPROVALS, PERMITS AND AGREEMENTS – LAPSE
OF CONSENT – where the respondent granted the applicant
a development approval (for material change of use) on 14
September 2011 – where the currency period for that
approval was later extended to 15 November 2017 and
permitted to be changed on 1 June 2016 – where the changed
development approval lapsed on 15 November 2017 and
therefore after the commencement of the Planning Act 2016
– where there has been non-compliance with s 86 of the
Planning Act 2016 in the failure to seek extension of the
currency period prior to expiry of the development approval –
– where this application is for excusal of the non-compliance
and revival and limited extension of the approval, pursuant to
s 37 of the Planning Act 2016, in order to allow an
application to the respondent for further extension in
conjunction with the further pursuit of the proposed
development – where the parties agree that the application
should be granted
COUNSEL: C N Wirz (sol.) for the applicant
A J Davey (sol) for the respondent
SOLICITORS: Gantt Legal for the applicant
Moreton Bay Regional Council for the respondent
Introduction
[1] These are the reasons for the orders made in this matter and without opposition,
on 19 October 2018. Those orders were made upon the originating application
filed on 3 October 2018, seeking:
“1. If it is contested, a declaration under section 11(1) of the
Planning and Environment Court Act 2016 that the
development permit for a material change of use (impact
assessable) for multiple dwelling units (10 units) (as amended
by decision notice dated 1 June 2016) in relation to land
situated at 102 Prince Edward Parade, Redcliffe in the State
of Queensland and more properly described as Lot 97 on
RP30443 and bearing the respondent’s reference
DA/24642/2010/VCHG/1 (Development Approval), lapsed
within the meaning of section 341 of the Sustainable
Planning Act 2009 on 15 November 2017.
2. An order under section 37(1) of the Planning and
Environment Court Act 2016 that:
(a) the Development Approval be revived; and
-- 2 of 7 --
3
(b) the currency period of the Development Approval be
extended for a period of 6 months to 19 April 2019,
unless further extended according to law.
3. Such further or other orders as this Honourable Court may
require.”
[2] As may be noted and for the reasons to follow, the orders made on 19 October
2018 do not entirely reflect the terms of that application. However, they did
reflect the agreed position of the parties in resolution of that application.
Background
[3] By correspondence dated 14 September 2011, the respondent gave a decision
notice approving a development application for a development permit for a
material change of use (impact assessment) for multiple dwelling units (11
units) in relation to land located at 102 Prince Edward Parade, Redcliffe, in the
State of Queensland and more properly described as Lot 97 on RP30443 and
bearing the respondent’s reference DA/24642/2010/DA (“development
approval”).1
[4] On 6 October 2015, the applicant, who is the owner of the subject land,2 lodged
a request with the respondent to extend the relevant period of the development
approval for a further 2 years.3 By correspondence dated 12 November 2015,
the respondent gave a decision notice approving the applicant’s request to
extend the relevant period of the development approval for a period of two years
until 15 November 2017.4
[5] On 28 January 2016, the applicant lodged a request with the respondent to make
a permissible change to the development approval. By correspondence dated 1
June 2016, the respondent gave a decision notice approving the applicant’s
request to change the development approval (“changed development
approval”).5
[6] Each of the development approval given on 14 September 2011, the decision to
extend the relevant period of the development approval made on 12 November
1 Affidavit of Drew Westbrook, filed on 15 October 2018, at [7] and DW–1 at p 41.
2 Affidavit of Drew Westbrook at [10].
3 Affidavit of Drew Westbrook at [16] and DW–1 at pp 117–127.
4 Affidavit of Drew Westbrook at [18] and DW–1 at pp 128–139.
5 Affidavit of Drew Westbrook at [24] and DW–1 at pp 227–273.
-- 3 of 7 --
4
2015 and the changed development approval given on 1 June 2016, was given
or made pursuant to the Sustainable Planning Act 2009 (“SPA”).
[7] Subsequently to the commencement of the Planning Act 2016 (“PA”), on 3 July
2017,6 and on 28 August 2017, Inertia Engineering lodged with the respondent
a development application for a related approval to the changed development
approval, namely a development application for a development permit for
operational works (stormwater).7 And on 22 December 2017, Inertia
Engineering lodged with the respondent, a further development application for
a related approval to the changed development approval, namely a development
application for a development permit for operational works (stormwater).8
[8] In about mid-January 2018, the applicant was informed by the applicant’s
development consultant that the respondent was unable to assess the
development application for operational works because the material change of
use development approval had lapsed on 15 November 2017.9 Until then the
applicant had overlooked the need to attend to the prospect of the lapsing to the
changed development approval on 15 November 2017, as explained in the
evidence, due to reliance on her husband and his ill health and the death of the
applicant’s architect who had been undertaking the project management role for
the applicant.10
[9] It is the impediment of the lapsing of the development approval on 15 November
2017, which is the primary subject of the relief sought in this Court.
Relevant Statutory Considerations
[10] Upon the commencement of the PA, the changed development approval (with
the extended currency period) was to be taken to be a development approval
under the PA and as remaining effective according to its terms.11 Accordingly,
s 86 of the PA may have been engaged by the applicant in order to seek a further
extension of the development approval, before it lapsed. That is so
6 And therefore the repeal of the SPA by s 284 of the PA.
7 Affidavit of Drew Westbrook at [25] and DW–1 at pp 274–298.
8 Affidavit of Drew Westbrook at [28] and DW–1 pp 303–377.
9 Affidavit of Damion Bielby, filed on 15 October 2018, at [36].
10 Ibid at [37].
11 See PA s 286.
-- 4 of 7 --
5
notwithstanding the effect of s 299 of the PA, in excluding the operation of s 85
of the PA to a development approval given under the SPA. It may be noted that
the effect of s 299(2) is to instead preserve the operation of s 341 of the SPA and
so as to determine the relevant currency period of such an approval. In this
instance, the effect of the history of the current development approval was that
the currency period was determined to expire on 15 November 2017, in
accordance with s 341(1)(b).
[11] It is therefore appropriate to accept the applicant’s submission that s 37 of the
Planning and Environment Court Act 2016 (“PECA”) can be utilised in the
circumstances of this case to excuse the non-compliance with s 86 of the PA, in
the sense of the failure to make a request of the respondent, to extend the
currency period of the development approval before it lapsed. And to revive the
development approval, so that such a request may now be made.
[12] As noted for the applicant, relevantly, s 37 of the PA is in comparable terms to
s 440 of the SPA and in respect of which, this Court had recognised, as providing
a broad12 and untrammelled13 discretionary power to excuse non-compliances
and to deal with the matter in a way the Court considers appropriate.14
Discretionary Considerations
[13] There are a number of considerations which favour granting relief pursuant to s
37 of the PECA, in the circumstances of this case:
(a) The non-compliance may be accepted to be the product of a
combination of:
(i) the applicant experiencing delays with the original
architect in preparing architectural plans of the
proposed development to a standard that would be
sufficient to obtain a development permit for building
works and which necessitated the engagement of an
alternative architect;
12 Beerwah Land Pty Ltd v Sunshine Coast Regional Council; Woodlands Enterprise Pty Ltd v
Beerwah Land Pty Ltd & Anor and; Sunshine Coast Regional Council v Beerwah Land Pty Ltd
[2016] QPEC 055 at [38].
13 Maryborough Investments Pty Ltd v Fraser Coast Regional Council [2010] QPEC 113 at [30].
14 Devy & Anor v Logan City Council [2010] QPEC 096 at p 3; Telstra Corporation Ltd v Brisbane
City Council & Ors [2016] QPEC 037 at [16].
-- 5 of 7 --
6
(ii) the applicant also experiencing significant delays with
engineering consultants in designing the structural
engineering works and preparing and lodging the
development application for operational works for
stormwater;15 and
(iii) the unexpected death of applicant’s architect on 6 July
2017 who had been undertaking the project
management role for the applicant and the applicant’s
husband’s ill health, 16 which resulted in the
applicant’s husband and who had primary
responsibility for this matter, being distracted and
overlooking the prospective lapsing of the
development approval and a request to extend the
currency period of the development approval prior to
15 November 2017;17
(b) The applicant has otherwise demonstrated a desire and
willingness to pursue the development and has incurred
considerable expense, estimated to be approximately $200,000
in that pursuit.18And the applicant would be prejudiced, to at
least some of that extent, if forced to make a new development
application; and
(c) The application is supported by uncontested evidence from a
town planner, expressing views that the current zoning of the
land is consistent with the intent of the zone applying to the
land at the time of granting the development approval on 14
September 2011, the development approval is consistent with
the current planning intent and outcomes for the land expressed
through the current planning scheme, the development remains
impact assessable, the building height of the development
approval is consistent with the relevant provisions in the current
planning scheme, the development approval remains
15 Affidavit of Damion Bielby [16]–[18].
16 Ibid at [25] and [37].
17 Ibid at [19]–[25].
18 Ibid at [47]–[48].
-- 6 of 7 --
7
compatible with the current key relevant planning
considerations applying to the land, if a new development
application were made there would be no referral agencies
triggered, and there is no town planning or other reason why
the request to revive and extend the development approval
ought not the approved;19 and
(d) Significantly, the respondent supported the making of the
orders.20 And it is to be noted that the anticipated effect is only
the provision of the entitlement of the applicant to seek a further
extension of the currency period of the approval, particularly
because of an anticipated accompanying further application for
change of the development approval.
Conclusion
[14] Accordingly and where there are circumstances explicable of the oversight
sought to be excused and the outcome sought is no more than to now put the
applicant in the position that may have been availed, absent that oversight, the
appropriate conclusion was a favourable exercise of the Court’s discretion
pursuant to s 37 of the PECA, to excuse the oversight and revive the
development approval and extend the currency period of the development
approval to 21 December 2018, to enable the applicant to make an extension
application to the respondent pursuant to s 86 of the PA.
19 Affidavit of Drew Westbrook at [35]–[38], particularly [37] (g)–(l) and DW–1 at p 430–446.
20 Affidavit of Drew Westbrook at [31] and [33] and DW–1 at pp 382, 385–429.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2018/050