Cuthbert v Moreton Bay Regional Council (No 2) [2018] QPEC 40 [2018] QPLER 1198
PLANNING & ENVIRONMENT COURT OF QUEENSLAND
CITATION:
PARTIES:
FILE NO/S:
DIVISION:
PROCEEDING:
ORIGINATING
COURT:
Cuthbert v Moreton Bay Regional Council No. 2
[2018] QPEC 40
HEATHER LORRAINE CUTHBERT
(appellant)
v
MORETON BAY REGIONAL COUNCIL
(respondent)
2283/2015 & 5102/2016
Planning and Environment
Appeal
Brisbane
DELIVERED ON: 31 August 2018
DELIVERED AT: Cairns
HEARING DATE: 6, 7, 8 & 9 March 2017, 27 April 2017.
JUDGE: Morzone QC DCJ
ORDER: 1. In respect of appeal number 2283 of 2015 I order
that the appellant’s revised Site Based
Environmental Management Plan (exhibit 4) is
approved subject to the following changes:
(a) Section 3, ought better identify the noise
sensitive receptors.
(b) Paragraphs 134, 135 and 150 must be modified
to ensure that no spray painting activity
including anti-foul (delivered by airless,
compressed or other spray air guns) is carried
out unless and until the appellant has an
approved spray booth suitable to the task
pursuant to condition (B5).
(c) Paragraphs 172 – 175 ought be modified to
expressly exclude all work on boats longer than
40 feet or 12.2 metres unless the repair work is
-- 1 of 55 --
2
limited to spot repairs and then only above the
interception drain (not inundated by tide).
(d) Paragraphs 29(d), 176, and 178 must be
modified to two 10,000 litre tank capacity, that
is a 10,000 litre settling tank and 10,000 litre
storage tank.
(e) Paragraphs 29(g), 57, and 188 conflict with the
EA in so far as they permit irrigation of the
holding tank water onto the land, and ought be
deleted.
2. In respect of application number 5102 of 2016 I
order on and from 4pm on 14 September 2018 that
the appellant be restrained by injunction from:
(a) Conducting spray painting activity including
anti-foul (delivered by airless, compressed or
other spray air guns) unless and until the
appellant has an approved spray booth suitable
to the task pursuant to condition (B5).
(b) Undertaking any work on boats longer than 40
feet or 12.2 metres unless the repair work is
limited to spot repairs and then only above the
interception drain (not inundated by tide).
(c) Irrigating any land with holding tank water.
3. I will hear further submissions on the appropriate
form of orders and the future conduct of the
proceedings on a date to be fixed.
CATCHWORDS: ENVIRONMENT AND PLANNING – ENVIRONMENTAL
PLANNING – appeal against Environmental Protection Order
imposed by council for environmentally relevant activity –
whether breach of general environmental duty – findings of
breach of conditions of environmental authority –
Environmental Protection Order needed to secure future
compliance – substituted Environmental Protection Order
requiring stormwater management plan and site based
environment management plan to address relevant conditions
of Environmental Authority – further disputation about terms
and conditions of required management plans – determination
by court of site based environmental management plan.
Legislation
Environmental Protection Act 1994 (Qld) ss 9, 319, 430, 431,
505, 531
-- 2 of 55 --
3
Environmental Protection Regulation 2008 (Qld) sch 7 pt 1
Sustainable Planning Act 2009 (Qld) s 232
Sustainable Planning Regulation 2009 (Qld) sch 4 table 5
item 6
Cases
Bermingham v Corrective Services Commission of New South
Wales (1988) 15 NSWLR 292.
Briginshaw v Briginshaw (1938) 60 CLR 336
Cuthbert v Moreton Bay Regional Council [2015] QPEC 63.
Darwen & Anor v Pacific Reef Fisheries (Australia) Pty Ltd
& Ors [2009] QPELR 262
James Hardie & Coy Pty Ltd v Seltsam Pty Ltd (1998) 196
CLR 53.
Kingston v Keprose Pty Ltd (1987) 11 NSWLR 404.
Loader v Moreton Bay Regional Council [2013] QCA 269.
Newcastle City Council v GIO General Ltd (1997) 191 CLR
85.
R v PLV (2001) 51 NSWLR 736.
R v Young (1999) 46 NSWLR 681.
Ravenscroft v Nominal Defendant [2008] 2 Qd R 32.
Tokyo Mart Pty Ltd v Campbell (1988) 15 NSWLR 275.
Warringah Shire Council v Sedevcic (1987) 63 LGERA 361.
Wentworth Securities Ltd v Jones [1980] AC 74.
COUNSEL: A Skoien with D Purcell for the Appellant
S Ure for the Respondent
SOLICITORS: Butler McDermott Lawyers for the Appellant
Thomson Geer Lawyers for the Respondent
-- 3 of 55 --
4
[2] The appellant, found in breach of an Environmental Authority in the use of a slipway
to repair, sand, spray, fibreglass, water-blast and anti-foul boats, continues to be
embroiled in disputation with the respondent council, after failing to agree on an
acceptable Site Based Environmental Management Plan.
[3] The parties now return to the court to determine an appropriate Site Based
Environmental Management Plan foreshadowed by my judgment of 18 December
2015.1
Background
[4] An Environmental Authority (“EA”) continues to govern the facility conducted on
both Lot 1 and Lot 20.2 The environmental authority applies subject to conditions
under the Act. By operation of the Act, and successive planning legislation, the
environmental authority continues in force as a development approval under the
Sustainable Planning Act 2009 (Qld) (“SPA”).
[5] I formed the view that the consequential environmental harm and environmental
nuisance resulting from these breaches would continue to occur unless the appellant’s
management practices and the Environmentally Relevant Activity (“ERA”)
infrastructure is significantly improved. However, I formed the view that the
Environmental Protection Order (“EPO”) issued by the council was unnecessarily
restrictive, prescriptive and onerous, with the potential to derogate from the original
grant of the Environmental Authority (“EA”). I found the temporal requirements in
the EPO both unreasonable and impractical. Further, the imposition of the EPO would
have imposed intolerable immediate material financial implications associated with
the upgrade of the slipway, acoustic treatments and dust and odour mitigation
requirements. In the absence of detailed costs or other economic evidence, I was left
with uncertainty about whether or not the imposition of the EPO will jeopardise the
appellant’s business.
[6] I adopted a course of making an EPO compelling the preparation and implementation
of a site based management plan, which would necessarily but properly confine the
operation of the facility within the scope of the Environmental Authority. To that
end, I made the following orders.
“1. The appeal is allowed in part;
2. The review decision of the council made on 4 May 2015 is set
aside;
3. The Environmental Protection Order dated 31 March 2015 is set
aside;
4. In substitution for the Environmental Protection Order dated 31
March 2015, an Environmental Protection Order will issue,
requiring the appellant to prepare and lodge with the council
within 90 days of the order:
1 Cuthbert v Moreton Bay Regional Council [2015] QPEC 63.
2 Loader v Moreton Bay Regional Council [2013] QCA 269.
-- 4 of 55 --
5
(a) A stormwater management plan for approval by the council
pursuant to Condition C1 of the Environmental Authority
No. 250000301; and
(b) A site based management plan containing reasonable and
practicable measures to prevent or minimise the
environmental harm, including environmental nuisance, in
relation to conditions A2, A5, A10, B1, B2, B3, B6, C1, C2,
C4, C5, D1, E1; F1, F3, and F4 of the Environmental
Authority No. 250000301.”
[7] The appellant lodged with the council a site based environmental management plan
on 31 March 2016. The parties were unable to agree as to the appropriateness of the
terms proposed by the appellant. The appeal has been managed by directions to
facilitate the parties’ negotiation and mediation to agree on a consolidated
management plan. They have been unable to do so. The council prepared its Site
Based Environmental Management Plan dated December 2016 (“council’s plan”).3
In response, on 28 February 2017, the appellant prepared a revised and consolidated
Site Based Environmental Management Plan (“appellant’s plan”).4
[8] In the meantime, the council applied for an injunction to restrain the appellant from
conducting her boat maintenance and repair activities until final determination of the
matter. That application was consolidated with and was heard with this proceeding.
[9] To determine an appropriate Site Based Environmental Plan foreshadowed by the
judgment (being a consolidation of the proposed stormwater management plan and
site based management plan). For the reasons given below, I decline to grant the
interim relief sought by the injunction application.
[10] The council also applies for an injunction restraining the appellant from conducting
boat maintenance and repair activities on the slipway pending this decision and further
requirements under the Site Based Environmental Management Plan.
Jurisdiction
[11] The court’s jurisdiction to determine the Site Based Environmental Management Plan
is in furtherance of the appeal pursuant to s 531 of the Environmental Protection Act
1994 (Qld) (“the Act”) and paragraph 4 of the orders and judgment delivered on 18
December 2015.
[12] The scope of the jurisdiction was set out in my judgment of 18 December 2017.
[13] In relation to the injunction sought by the council, ss 430 and 431 of the Act provide
for enforcement and offences for contravening conditions of an environmental
authority.5 Section 505 of that Act empowers the court to make orders directing an
offender to stop an activity that is or will be a contravention of the Act,6 and other
orders.
3 Exhibit 2.
4 Exhibit 4.
5 Environmental Protection Act 1994 (Qld) ss 430, 431.
6 Environmental Protection Act 1994 (Qld) s 505.
-- 5 of 55 --
6
[14] In proceedings, like this, seeking enforcement orders, injunctive and declaratory relief
predicated on allegations of breach the appropriate standard of proof is “at the higher
end of the civil standard”.7 Having regard to the consequences of the outcome of this
proceeding, in my view, the appropriate standard of proof to be applied is that at the
higher end of the civil standard in accordance with the Briginshaw principles.8
Issues
[15] The parties’ respective contentions are effectively merged in these competing
management plans, as supported by the evidence before the court at the initial hearing
and the further hearing.
[16] Whether the appellant’s management plan provides reasonable and practicable
measures to prevent or minimise environmental harm by securing compliance with
the relevant conditions of the EA (and thereby the general environmental duty), or
whether further or alternative provisions are required as proposed by the council.
[17] The main areas of dispute exposed by the parties respective management plans are
whether reasonable and practicable measures ought include:
(a) An appropriate containment structure or barrier comprised of dense material
surrounding slipway along the Bishops Parade frontage and returns down the
side boundaries;9
(b) Discharge of wastewater from an additional proposed settlement tank to the
land within the area governed by the EA;
(c) A fully enclosed Carcoon containment facility and filtration/ventilation system,
or some similar such containment facility for the Slipway; 10
(d) Monitoring, recording and reporting regime for dust deposition (sample
collection and analysis), air quality, noise (and assessment), wastewater and
stormwater (sampling and analysis) and the receiving environment.11
[18] I will address these in the context of the relevant EA conditions subject of the hearing.
[19] This will also inform whether an injunction should issue to restrain the appellant from
conducting her boat maintenance and repair activities pending implementation of a
site based environmental management plan.
Scope of Site Based Environmental Management Plan
[20] Before embarking upon the substantive issues, it is useful to remark about the scope
of the required site based environmental management plan (“management plan”).
[21] Whilst it is good practice for the appellant to implement a comprehensive
management plan, this is not a merits appeal involving broader considerations about
form and substance of a comprehensive site based management plan attached to a
7 Cf. Darwen & Anor v Pacific Reef Fisheries (Australia) Pty Ltd & Ors [2009] QPELR 262 at 265.
8 Briginshaw v Briginshaw (1938) 60 CLR 336 at 363.
9 Exhibit 2, council’s plan, s 6.5.
10 Exhibit 2, council’s plan, s 10.2.
11 Exhibit 2, council’s plan, ss 21 & 22.
-- 6 of 55 --
7
condition of approval. It seems to me that the court’s consideration of the matter
ought not be at large, nor should it take the role of drafting and imposing a site based
management plan. Instead, in the context of this case, I am less concerned about the
form as I am about the substance of the management plan.
[22] That substance is limited to addressing current and potential environmental harm
consequent upon breaching particular conditions of the EA. These are found in the
judgment delivered on 18 December 2015, where I concluded that the appellant
breached the EA by her failure to comply with conditions A2, A5, A10, B1, B2, B3,
B6, C1, C2, C4, C5, D1, E1; F1, F3, and F4 of the EA.
[23] At the time of my judgment, it seemed to me that the appellant’s compliance with the
EA could be simply achieved by the timely preparation and implementation of an
appropriate site based management plan (including stormwater management)
containing reasonable and practicable measures to prevent or minimise environmental
harm and environmental nuisance that may be caused by the ERA. In this regard the
Site Based Environmental Management Plan,12 and revised stormwater management
plan,13 associated with the previous proceedings remained both contemporary and
relevant to this task. Those plans, with appropriate changes having regard to my
findings, would have satisfied the proposed orders.
[24] The appellant contends that, to the extent those recommendations are not adopted,
they are either:
1. Outside the scope of the conditions of the Environmental Authority; and/or
2. Not reasonable and practicable measures to prevent or minimise
environmental harm with respect to those conditions.
[25] As to the disputed measures now proposed by council’s Plan, the appellant contends
that they are not reasonable and practicable measures, because:
1. they are not practicable for the operation of the appellant’s long standing and
small-scale slipway (even if suitable to other slipways);
2. they involve an unreasonable financial burden (both initially and ongoing) on
this small-scale Slipway; and
3. such measures are really directed toward excluding entirely amenity impacts
upon two residents of the area whose concerns (if honestly and genuinely held)
are not reasonably held.
[26] In the circumstances of this case, the appellant has been found in breach of the EA,
and general environmental duty, by carrying on her activity in a way that causes, or
is likely to cause, environmental harm, in breach of the EA, and her general
environmental duty.14
[27] The management plan must provide for reasonable and practicable measures required
to prevent or minimise environmental harm to assure compliance with conditions A2,
12 Affidavit of Bristow 6 July 2015, Doc. 13, Exhibit DJB-01 Doc G (p 56).
13 Affidavit of Manley 7 July 2015, Doc. 16, Docs F & G in Exhibit CPM-01.
14 Judgment at [122].
-- 7 of 55 --
8
A5, A10, B1, B2, B3, B6, C1, C2, C4, C5, D1, E1, F1, F3, and F4 of and thereby
lawfully operate the activity within the terms of the EA.15 Having regard to the tenor
of my earlier judgment, the management plan must secure compliance with those
conditions without derogating from, or adding to, the original grant of the EA or
compromising the general environmental duty.16 By way of illustration, if the EA
prohibits an activity (to avoid environmental harm), the court ought not allow a
management plan to permit some activity (to ‘minimise’ environmental harm) under
the guise of being a “reasonable and practical measure etc”. Conversely, a
management plan ought allow an activity (to avoid environmental harm) beyond the
scope of the EA and the general environmental duty arising from the ERA.
[28] In deciding the reasonable and practicable measures in the management plan to
prevent or minimise harm pursuant to the Court ordered EPO, regard ought be had to
the relevant factors in set out in s 319(2) of the Act, namely:17
(a) The nature of the harm or potential harm; and
(b) The sensitivity of the receiving environment; and
(c) The current state of technical knowledge for the activity; and
(d) The likelihood of successful applications of the different measures
that might be taken; and
(e) The financial implications of the different measures as they would
relate to the type of activity.
[29] Even though I was satisfied about each of factors (a) to (d) in relation to the challenged
EPO, at the time of judgment, the parties rely upon further evidence about the relevant
factors, including any financial implications of the required measures in relation to
the proposed management plans.
Site Operations
[30] The scope of the required management plan must be considered in the context of the
appellant’s particular operations comprising the ERA.
[31] The Slipway comprises a concrete ramp with steel rails. A wheeled cradle on the
Slipway is used to draw boats from the water, up the Slipway for maintenance and
repair works.
[32] The appellant describes the slipway operational activities in s 5 of the appellant’s
plan,18 which I accept as a matter for her to define the scope of her business.
[33] Current operations include:
1. Anti-fouling of boats using high water pressure;
2. Application of anti-foul paint with roller and airless spray gun;
15 Appellant’s submissions, at [20].
16 Judgment at [123]-[126].
17 Environmental Protection Act 1994 (Qld), s 319(2).
18 Exhibit 4, appellants plan, s 5.
-- 8 of 55 --
9
3. Occasional sanding and painting of above hull and upper deck areas with roller
and airless spray gun; and occasional boat repair including fibre glassing.
4. Spot abrasive blasting using dry or wet methods is limited to three times yearly
by an independent licensed contractor.
5. Periodic outboard motor maintenance and repair is undertaken by a separate
contractor.
[34] The business services mainly fibreglass boats, but timber and steel boats are also
slipped, with an estimated 90% of the work being anti-fouling services resulting in
applying new anti-fouling to the hull of a boat below the waterline. The gross profit
from trading of the Slipway operations for the two preceding financial years is only
$49,000.19
[35] The anti-fouling service comprises:
(a) ramp cradle is lowered into the water;
(b) a boat is then driven over the cradle with the vertical side arms in
p1ace as guides (for monohull boats - arms are removed for
multihulls as required).
(c) when in position, the boat can be tied to the cradle;
(d) the electric motor driven winch is then activated and the cradle is
drawn up the ramp, the winching process is low speed and takes
between 6 and 10 minutes to draw the boat/cradle up the ramp.
The speed of winching is determined by boat size and whether
single line or double line pull is used;
(e) the winching operations produce little noise;
(f) when the cradle reaches the top of ramp, winch is disengaged and
hold down chain is attached around cradle frame and secured to
winch base as secondary hold in addition to winch gear/brake;
(g) boat hull is inspected prior to water blasting to check for any
issues;
(h) water blaster is wheeled into place;
(i) normal operations employ an electric high pressure, low volume
water blaster;
(j) water blaster is used to wash slime from hull;
(k) time taken for a 28-foot boat is normally approximately 15 to 30
minutes;
19 Affidavit of DR Cuthbert 28 February 2017, Doc. 94, Exhibit DRC-1, sales less cost of goods sold
(excluding ordinary business expenses).
-- 9 of 55 --
10
(l) depending upon size of boat and whether monohull or multihull,
time to water blast can take 30 to 45 minutes approximately;
(m) all runoff from water blaster operation falls onto ramp and will run
into the First Flush Collection Drain, or failing that, the Existing
Collection Drain;
(n) when water blasting is complete, the water blaster is packed away
to shed;
(o) where necessary, barnacles and similar growths are manually
scraped from hull and running gear (i.e. propellers, shafts, stern
drive legs, rudders and anodes) by hand;
(p) this hull scraping operation can take between 30 minutes and 1
hour, depending upon site of boat and extent of growths needing
removal;
(q) following this stage, it is generally determined whether any other
maintenance tasks are required (i.e. do sacrificial anodes need
replacing, do propellers need repair and the like);
(r) it is normal when anti-fouling a boat to replace sacrificial anodes
at the same time;
(s) anode replacement is generally conducted by Toorbul Marine;
(t) any propeller repairs and/or checking of gear oil in stem drive legs
(if fitted) is conducted by an external mechanic;
(u) the boat is allowed to dry off before commencing anti-foul
application;
(v) anti-foul application is preceded by masking of hull water line
using removable masking tape and masking over any anodes not
being replaced to prevent paint covering their surface;
(w) drop sheets are placed beneath the boat to catch any paint drips
from anti-foul application;
(x) anti-foul is applied to the hull by hand roller by 1 or 2 persons on
the Slipway;
(y) the antifoul application would generality take around 1 hour,
depending upon size of boat;
(z) anti-foul is allowed to dry and then a second coat is again applied
by hand;
(aa) anti-fouling of running gear can require a different anti-foul
product to that applied to hulls i.e. fibreglass hulls as compared to
metal running gear;
-- 10 of 55 --
11
(bb) running gear (i.e. shafts, rudders, propellers and stern drive legs
(where fitted) have appropriate anti-foul applied by hand or using
airless spray gun (airless spray gun is used for stem drive legs to
get best coverage of components);
(cc) drop sheets are in place for all anti-foul applications;
(dd) following anti-foul application, anodes are replaced, masking tape
etc. is removed and placed into bins;
(ee) where removed, propellers are refitted with new anti-foul having
been applied by hand in the workshop prior to fitting back onto
boat running gear;
(ff) when anti-foul is dry and the tide is at the appropriate height, the
boat is returned to the water and the Toorbul Marine work is
complete;
(gg) a boat on the slip for anti-foul operations as described above will
generally be on the slip for two to three days;
(hh) the length of time is dependent upon the time of suitable high tides
and whether any parts needed (i.e. anodes, propeller repairs) can
be sourced and the time taken for these parts to be acquired and
transported to site for fitting.
[36] The appellant offers incidental repair services, such as minor paint touch up, minor
fibreglass repairs and polishing of boats whilst out of the water.
[37] The painting activities are described as being “more for minor touch up painting”, for
small repairs, where damage has been sustained to the boat and the damage requires
surface repair (i.e. filling and sanding and then repainting). Paint would be applied
on the slipway by either hand or airless spray. The appellant is prepared to repaint
timber hulled boats using hand rolling and brushing, if required, but does not propose
whole of boat repaints using compressed air paint guns.
[38] Repair to timber work, steel work or fibreglass comprise
1. For a timber hulled boat - replacement of damaged timber planking or ply
work, which may require removal and replacement of the damaged element or
simply cleaning, filling and then sanding prior to painting;
2. For fibreglass sheathed timber hulled boats - removal of damaged fibreglass,
timber repairs, reapplication of fibreglass sheathing and then painting.
3. For steel hulled boats - areas may need cleaning out or cut out and new steel
plating welded into place before surface finishing and painting.
[39] Major structural repair jobs are not conducted on the slipway. Smaller boats may be
removed into the shed for work. Similarly, boat parts will be removed and repaired
in the shed and then reinstalled on the slipway.
-- 11 of 55 --
12
[40] The slipway operational hours are limited to 7am to 6pm Monday to Friday and 8am
to 5pm on weekends, except for emergency. Boats may be moved on and off the
slipway on the high tide at any time between 7am and midnight or in emergencies.
[41] The appellant’s plan provides for general site management activates, restricted
activities, and related measures, which will be relevantly discussed later.
Sensitive Receptors
[42] Elimbah Creek is listed under the RAMSAR Convention as a Wetland of International
Importance, as well as being identified under the QLD State Planning Policy as a
wetland of high ecological value, a wildlife habitat, marine park (conservation zone)
and declared fish habitat. The creek is linked to Pumicestone Passage, which forms
an important part of Moreton Bay Marine Park.
[43] Elimbah Creek and Pumicestone Passage downstream support a range of rare and
threatened species of both marine life and avifauna. These species are listed for
protection under local, state, commonwealth and international legislation, regulation
and / or convention / treaties. Habitats in the waterways include significant areas of
mangroves, saltmarsh, seagrass and intertidal flats. These have significant
conservation value, and also serve as a conduit to the incorporation of contaminants
into shellfish, fish and birds. The area is used for recreational and commercial fishing,
including the taking of crabs, prawns and oysters for human consumption.
[44] The nearest sensitive residential receptors for air quality (particulate matter i.e. dust
and volatiles) and noise are the existing residences on Bishop Parade, Toorbul and the
public areas around the Slipway, including Elimbah Creek. The nearest residences
are approximately 20 m to 25 m south of the Slipway.
[45] The appellant’s plan in section 3, ought better identify the noise sensitive receptors.
Potential Impacts
[46] The appellant acknowledges that without adequate containment of the liquid and solid
wastes from slipway operations, there is a high potential for the release of
contaminants due to wind, rain and tidal inundation, which poses high risk to the
ecosystem health of both Elimbah Creek and the Moreton Bay Marine Park.20
[47] The appellant’s activities and equipment that may cause environmental impact are:
1. Noise – vehicle and boat movements, using power tools, hammering,
grinding/cutting, the operation of marine motors (outboard motors), sanding,
scraping, spray painting, water pressure cleaning, shouting, filling and
emptying waste bins, reversing beepers, alarms, air compressors, fans,
winches and airless spray units.
2. Dust - sanding, grinding, blasting (wet or dry), and fairing activities;
3. Fumes & odour using solvent based paints, anti-fouling, associated solvents,
varnish, paints, anti-fouling or other materials or products used at the site,
20 Exhibit 4, appellant’s plan, at [20].
-- 12 of 55 --
13
and/or applied either by hand, airless spray or compressed air spray gun; and
Fibreglass repair operations;
4. Stormwater – wastewater and residuals/particulates associated with operations
including high-pressure water blasting, hand-scraping, paint stripping, cutting,
sanding and grinding, and anti-fouling and other painting, and rain and tidal
inundation of the slipway.
[48] In the context of these operations of the ERA, sensitive receptors and potential
impacts, I now consider the contentious parts of the parties’ competing management
plans cognisant of the findings made in the judgment and additional evidence.
Maintenance of Plant and Equipment
[49] Condition (A2) of the EA provides that:
“(A2) The holder of this environmental authority must ensure that:
(i) All plant and equipment necessary to ensure compliance with
the conditions of this environmental authority is installed; and
(ii) such plant and equipment is maintained in a proper and
efficient condition; and
(iii) such plant and equipment is operated in a proper and efficient
manner.
In this condition, “plant and equipment” includes:
(i) plant and equipment used to prevent/and or minimise the
likelihood of environmental harm being caused;
(ii) devices and structures to contain foreseeable scapes of
contaminants or waste; and
(iii) fuel burning equipment.”
[50] The competing management plan provisions proposed by the parties are short and
substantially similar. Section 7.6 of the appellant’s plan provides that:
“7.6 Maintenance of plant and equipment
85. As part of ordinary operations the Slipway Manager will review the
performance specifications of each piece of equipment to identify
any equipment malfunction or abnormal operation which could
result in excessive noise emissions.
86. In the event of such equipment malfunction or abnormal operation
the Slipway Manager is to ensure that use of such equipment ceases
and is not resumed until such equipment is either replaced or
serviced to remove any malfunction and abnormal operation.
87. The Slipway Manager is to ensure plant and equipment is:
-- 13 of 55 --
14
(a) operated in accordance with its use specifications; and
(b) periodically assessed to determine whether it is operating
efficiently and cost effectively, and with minimal
environmental impact.”
[51] By comparison, s 6.1 of the council’s proposed management plan is in these terms:
“6.1 Plant &equipment
The Site Manager will monitor the performance of equipment daily to identify
malfunctions or abnormal operations which could result in excessive
emissions.
In the event of equipment malfunction or abnormal operation, the Site
Manager will ensure that use of the equipment ceases and is not resumed until
it is either replaced or repaired.
The Site Manager will ensure plant and equipment is:
Operated in accordance with this management plan;
Operated in accordance with its use specifications.”
[52] It seems to me that the appellant’s proposal will sufficiently assure the implementation
of reasonable and practicable measures to prevent or minimize the environmental
harm, including environmental nuisance, in relation to condition (A2) of the EA.
Monitoring and Records
[53] In relation to records, conditions (A3), (A5) and (F4) of the EA provide that:
(A3) A copy of this environmental authority must be kept in a prominent
location readily accessible to persons involved in the activity. …
(A5) Copies of any record or document required to be kept by a condition of
this environmental authority must be provided to any authorised person
or administering authority on request.
…
(F4) Where waste is taken off site, the holder of this environmental
authority must monitor and record the:
(i) date, quantity and type of wastes removed;
(ii) waste receiving operator that removed the wastes off-site;
and
(iii) destination of the waste.
[54] The appellant’s plan incorporates the EA by annexure A, and variously prescribes
monitoring and record keeping requirements in compliance with the conditions, and
more, including:
-- 14 of 55 --
15
1. Responsibility of the Slipway Manager and any employees;21
2. Incidents and failures;22
3. Chemical storage;23
4. Spillage prevention and cleanup;24
5. Abrasive blasting;25
6. Painting and spray painting;26
7. Anti-foul preparation and application;27
8. Fibreglass repair work;28
9. Waste, including wastewater disposal;29
10. Wind speed and direction monitoring;30
11. Keeping of records, forms and retention;31
12. Training given to the Slipway Manager and any employees;32
13. Complaints.33
[55] In contrast the respondent proposes a very detailed, sophisticated, and extensive
monitoring and record maintenance in s 21 & 22 (and related provisions) regarding:34
1. Weather forecast monitoring;
2. Onsite wind monitoring;
3. Dust deposition monitoring (sample collection and analysis);
4. Air quality monitoring;
5. Noise monitoring;
6. Wastewater and stormwater system monitoring;
21 Exhibit 4, appellant’s plan, s 1.4, at [9].
22 Exhibit 4, appellant’s plan, s 7.3, at [75].
23 Exhibit 4, appellant’s plan, s 9.1, at [101] – [103].
24 Exhibit 4, appellant’s plan, s 9.2, at [110].
25 Exhibit 4, appellant’s plan, s 14.1, at [132].
26 Exhibit 4, 4ppellant’s plan, s 15.1, at [135], [136], s 16.2, at [154], [155].
27 Exhibit 4, appellant’s plan, s 16.1, at [145], [146], s 16.2 at [154], [155].
28 Exhibit 4, appellant’s plan, s 17.0, at [161] – [162].
29 Exhibit 4, appellant’s plan, s 20.0, at [195] – [196].
30 Exhibit 4, appellant’s plan, s 21.0, at [200].
31 Exhibit 4, appellant’s plan, s 22.1, at [202] – [205].
32 Exhibit 4, appellant’s plan, s 23.0, at [206] – [207].
33 Exhibit 4, appellant’s plan, s 24.0, at [208] – [209].
34 Exhibit 2, council’s plan, s 22.
-- 15 of 55 --
16
7. Receiving environment monitoring;
8. Employees and contractors;
9. Any induction & training given to the Site Manager and any employees;
10. Induction of contractors or short term visitors;
11. The boats that are cleaned and repaired and the types of activities undertaken
in respect of each boat including: date and time; duration, and materials and
equipment used.
12. Wind speed and direction;
13. Maintenance of plant and equipment;
14. Records of all incidents and remedial / corrective actions;
15. Chemicals used and stored on Lot 20;
16. Waste management;
17. Monitoring records of wind speed and direction, dust deposition, noise
(including assessment reporting), wastewater and stormwater and the
receiving environment;
18. Any written or oral complaint received in respect of the operations of the
Slipway.
[56] The assessed cost of conducting the monitoring programme proposed by the council
is $44,500 (ex GST) per annum plus $1,700 ex GST capital expenditure, comprising:
(a) $1,900/month for routine monthly water and sediment monitoring;
(b) $4,400/annum for annual water, sediment and biological monitoring;
(c) $500 for weather station;
(d) $5,300/annum for dust depositional monitoring plus $1,200 to establish
deposition stations; and
(e) $12,000/annum for daily monitoring in employee costs.
[57] In my view, with comparison to the scope of the EA, the council’s prescriptive
recording and monitoring requirements substantially overreach and fall outside the
limited recording required by conditions (A3), (A5) and (F4_ of the EA. There are
no conditions under the EA that impose monitoring of the impact of the activity to the
extent sought by council, including for example s 21.4.2 of the council’s plan which
seeks to impose regulatory monitoring where a health-related complaint is made, or
if requested by council.
[58] Further, I think that the scope and terms of the council’s proposed requirements are a
disproportionate response to implement the EA having regard to the nature and extent
of the appellant’s operation, and risks of environmental harm subject of the appeal. I
-- 16 of 55 --
17
do not accept that it is necessary to prescribe the day-to-day practicalities of observing
the weather and wind speed in the conduct of the activity.
[59] To the extent that the monitoring and record keeping is incidental to assure the
implementation of reasonable and practicable measures to prevent or minimize the
environmental harm arising from other provisions, I prefer the appellant’s proposal.
[60] It seems to me that the appellant’s proposed monitoring and record keeping is
appropriate and within the bounds of the EA.
Air Quality & Noise
[61] As to odour, dust, noise and air quality generally, the relevant conditions of the EA
are:
Nuisance
(A10) Notwithstanding any other condition of this environmental
authority, this environmental authority does not authorise
any release of contaminants, which cause or are likely to
cause an environmental nuisance beyond the boundaries of
the licensed place.”
Noxious or Offensive Odour
(B1) Notwithstanding any other condition of this environmental
authority no release of contaminants from the licensed place is to
cause a noxious or offensive odour beyond the boundaries of the
licensed place.
Dust and Particulate Emissions
(B2) No dust or particulate matter shall be permitted to emanate beyond
the boundaries of the licensed place which can have an adverse
effect on people living in or using the surrounding area.
(B3) All traffic areas must be kept clean or maintained in a manner so
as to minimise the release of dust and particulate matter to the
atmosphere.
Spray Painting
(B6) No spray painting is permitted in the open. Spray painting must be
carried out within a spray booth approved by the administering
authority.
….
Emission of Noise
(E1) In the event of a complaint about unreasonable intrusive noise being
made to the administering authority, and the administering authority
considers that the complaint is not frivolous or vexatious, then the
-- 17 of 55 --
18
emission of the noise from the licensed place must not result in levels
greater than those specified in Table 1 of the Noise Schedule.
SCHEDULE E TABLE 1
NOISE LEVELS AT A NOISE SENSITIVE PLACE
PERIOD NOISE LEVEL AT A NOISE
SENSITIVE PLACE MEASURED AS
THE ADJUSTED MAXIMUM SOUND
PRESSURE LEVEL
7:00 AM – 6:00 PM Background noise level plus 5 dB(A)
6:00 PM – 10:00 PM Background noise level plus 5 dB(A)
10:00 PM – 7:00 AM Background noise level plus 3 dB(A)
NOISE LEVELS AT A COMMERCIAL PLACE
PERIOD NOISE LEVEL AT A NOISE
SENSITIVE PLACE MEASURED AS
THE ADJUSTED MAXIMUM SOUND
PRESSURE LEVEL
7:00 AM – 6:00 PM Background noise level plus 10 dB(A)
6:00 PM – 10:00 PM Background noise level plus 10 dB(A)
10:00 PM – 7:00 AM Background noise level plus 8 dB(A)
…
(G9) “commercial place” means –
a place used as an office or for business or commercial purposes.
(G10) “environmental harm”
(1) is any adverse effect, or potential effect (whether temporary or
permanent and of whatever magnitude, duration or frequency)
on an environmental value, and includes environmental
nuisance.
(2) may be caused by an activity -
(a) whether the harm is a direct or indirect result of the
activity; or
(b) whether the harm results from the activity alone or from
the combined effects of the activity and other activities or
-- 18 of 55 --
19
factors.
(G11) “environmental nuisance” is unreasonable interference or likely
interference with an environmental value caused by—
(a) noise, dust, odour, light; or
(b) an unhealthy, offensive or unsightly condition because of
contamination; or
(c) another way prescribed by regulation.”
(G12) “intrusive noise” means –
noise that, because of its frequency, duration, level, tonal
characteristics, impulsiveness or vibration -
(a) is clearly audible to, or can be felt by, an individual; and
(b) annoys the individual.
In determining whether a noise annoys an individual and is
unreasonably intrusive, regard must be had to Australian Standard
1055.2 – 1997 Acoustics – Description and Measurements of
Environmental Noise Part 2 – Application to Specific Situations.
(G13) “noise sensitive place” means any of the following places –
(a) a dwelling; …
(G14) “noxious” means –
harmful to health or physical well being.
(G15) “offensive” means –
causing unreasonable offense, is unreasonably disagreeable to the
sense; is disgusting, nauseous or repulsive.
[62] Section 9 of the Act defines “Environmental value” as follows:35
“Environmental value” is –
(a) a quality or physical characteristic of the environment that is
conducive to ecological health or public amenity or safety; or
(b) another quality of the environment identified and declared to be an
environmental value under an environmental protection policy or
regulation.”
35 Environmental Protection Act 1994 (Qld) s 9
-- 19 of 55 --
20
[63] There is a continuing dispute between the parties about the appellant’s activities
including evident paint and anti-foul residue.36 The tarpaulin arrangement used by the
appellant has proved ineffective. So much was establish by the expert evidence of Mr
Galvin, corroborated by complaint evidence of affected residents at the first hearing.
There is no doubt, and I found, that dust, noxious or offensive odours and noise will
potentially escape the land boundaries and affect surrounding residents.
[64] The appellant identifies performance and mitigation measures about air quality at
sections 4.1, 4.2, 4.3 and 4.4 of her plan. Measures to clean and maintain traffic areas
for condition B3 are largely uncontroversial and identified in 7.2 of the appellant’s
plan and 6.3.1 of the Council’s plan.37
[65] The controversy arising from the parties competing plans is the use of containment
facilities to manage spray painting, and other dust, noxious or offensive odours and
noise.
Containment of odour, dust and noise
[66] The appellant acknowledges the sources of potential acoustic impacts and impacts on
air quality her proposed plan including:38
(a) dust generation from sanding, grinding, blasting (wet or dry) and
fairing activities;
(b) fumes generated by use of solvent based paints, anti-fouling,
associated solvents and other materials applied either by hand,
airless spray or compressed air spray guns;
(c) odours generated by the use of varnish, paints, anti-fouling or other
materials or products used at the site;
(d) odour generated by fibreglass repair operations;
(e) noisy activities such as vehicle and boat movements, sanding,
abrasive blasting, shouting, filling and emptying waste bins,
reversing beepers, alarms, grinding and cutting steel; and
(f) noisy machines located outside of buildings and close to sensitive
receptors, including air compressors.
[67] Historically, rails running between the slipway on Lot 1, across the road, and into the
shed on Lot 20 enabled work to be done within the containment formed by the shed
on lot 20. Although the shed has been replaced with a newer larger shed, the rails
have now been removed, and the practice has ceased.
[68] Both parties propose different containment structures to surround the work area.
[69] Mrs Cuthbert maintains that her proposed 3.5 m high containment structure with a
canvass partition density of 600g/m2, fixed around three sides of the work area, and a
36 The evidence is referred to in the councils Submissions at [13]-[43].
37 Judgment at [34], [36]-[42], [44]-[45], [46], [50]-57], [60]-[62] & [66]-[69].
38 Exhibit 4, appellant’s plan, at [22], [24].
-- 20 of 55 --
21
canvass gate partition to close the fourth side of the boat upon slipping, leaving only
the roof exposed, is a sufficient measure.39
[70] The council contends that at least a 4m high barrier, in accordance with Mr
Goodfellow’s design, having a density of 15kg/m2 with negligible gaps and being
20m long along the Bishop Parade frontage of Lot 1 with 15m returns located on the
north-west and south-east boundaries of the slipway, would cost in the order of
$45,000.40 Additionally, the council contends that its proposed Carcoon containment
facility will also serve as an effective control to address the other air quality conditions
(not just spray painting). For dust and odour containment, a custom made 14m long
x 6m x 6m high inflatable workstation (Carcoon) without the fixed floor would cost
some $30,000.
[71] With the other operational measures in mind, the parties respectively contend that
their containment facility provides reasonable and practicable measures to prevent or
minimise environmental harm by securing compliance with the relevant conditions of
the EA. I turn to those now.
Spray Painting
[72] Spray painting is expressly subject of Condition (B6) which prescribes that spray
painting must be carried out within a spray booth approved by the administering
authority. The council as the “administering authority” is charged with the power to
approve an effective spray booth for the purposes of condition (B5).
[73] The issue is not whether a spray booth is required but rather what type of booth is
effective having regard to the booth’s purpose and the scope work.
[74] It seems to me that the purpose of the prescribed spray booth is multifactorial,
including paint fumes, odours, and airborne particulates.
[75] Council’s plan requires an inflatable Carcoon containment facility with three sides
and the roof sealed, with ventilation and filtration systems operational. Mr Galvin
describes the Carcoon facility as follows:41
“51 A more reasonable and practical solution which was also considered was
a large self supporting Workstation made by Carcoon Australasia. The
systems are an inflatable working environment, similar in concept to a
spray booth but is not as expensive nor does it involve permanent fixtures.
Examples of the system in use elsewhere are shown in Figure 2 and
Figure 3. In Figure 3, a material floor can be seen. The supplier can
modify the floor depending on the end use. In the case of the slip, the
floor could be split and folded back while the boat was being slipped and
then placed back under the boat once operational, or a second separate
tarp system could be placed on the floor and used to capture particulate
matter which would also be beneficial with regards to conditions B3 and
B4.
39 Exhibit 4, appellant’s plan, – Annexure “C”.
40 Affidavit of DJ Bristow 23 December 2016, Doc. 87, at [27].
41 Affidavit of G Galvin, Doc. 89, at [51] – [53].
-- 21 of 55 --
22
52 The system can be inflated on the slip and constructed in a way in which
boats can be slipped while the system is inflated. Should work stop, the
system can be deflated and left to sit over the boat until it was ready to
be worked on again. To check how the system works, I watched a number
of videos on YouTube which showed that the system is relatively easy to
place and inflate.
53 Another benefit is that the Carcoon inflatable system makes use of a
ventilation fan (1.5 m3/s) to inflate the system, and a second fan (1.5 m3/s)
to horizontally draw air through the system which is filtered through both
paint arrest filters (i.e. filters which trap overspray) and then carbon
filters (filters that trap odorous material). The use of filters as
recommended by the supplier in combination with the processes of a
properly detailed SBEMP would reduce the risk of environmental harm
and nuisance.”
[76] Mr Galvin provides a cost estimate for a suitable Carcoon booth to be approximately
$30,000 (ex GST) for a custom Carcoon spray booth to $37,900 ex GST for a standard
Carcoon 15.5 workstation.42
[77] The appellant argues that the imposition of a Carcoon booth is disproportionate to the
scale and commerciality of her 55 year old facility, and is a measure more suited to
large scale industrial operations.43 In this vain the appellant contends that the Carcoon
is not a reasonable and practical measure because it imposition would necessitate
abandonment of spray painting. It is submitted that:44
“75. In the event that the Court determines that, to satisfy condition
(B6), spray painting under the SBEMP must only occur in the
Carcoon facility, or some similar such enclosed facility, Mrs
Cuthbert’s operations will need to be limited to hand brushing
and roller applications of paint and anti-foul …”
[78] She also argues that that infrequent activities releasing odour from anti-foul (being
90% of the activities at the Boating Maintenance and Repair Facility) would occur for
an hour or so each time a boat is slipped. So, she argues, even if a boat was slipped
every 2 days, the potential odour would be no more than three hours or so over an
entire week.45
[79] The appellant relies upon Mr Galvin’s, acceptance that such a measure may better suit
particular operations such as spray painting cars to protect the paint and finish, and
their usual location in or adjacent to numerous sensitive receptors in dense urban
areas. She submits that Mr Galvin “accepted, the use of the existing tarpaulin
arrangement (which do not yet reflect the more formal design of four sided,
engineered enclosure in the revised SBEMP) already contain ‘overspray’ as is evident
from the aerial photographs”. However, Mr Galvin went on to say:46
42 Affidavit of G Galvin, Doc. 89, at [54].
43 T2-39/46 to T2-40/8.
44 Appellant’s submissions, at [75].
45 Appellant’s submissions, at [77].
46 T2-61/3-6.
-- 22 of 55 --
23
“I did prepare this part of the affidavit in response to the suggestion that the
containment facility would contain everything. The point being that whether
or not that gurney was directed upward or at a boat that whatever was going
on inside wouldn’t be totally contained.”
[80] Mr Galvin also disposed that such a measure is not usual for the boat business because
unlike the unusual circumstances where the appellant works close to the water on the
slipway itself, spraying work in like operations are usually removed from those
sensitive areas.47 Dr Thorogood aptly described the importance of the containment of
contaminants in the appellant’s facility as follows: 48
“As has been previously established, the slipway adjoins and in-part lies
within Elimbah Creek, a sensitive receiving environment of acknowledged
ecological and conservation significance. This presents significant technical
challenges relating to the containment of contaminants and affords no
‘second chance’ to capture or recover contaminants that escape the
work-area. Consequently, both the infrastructure and management of the
slipway must be capable of preventing the escape of contaminants, and also
able to be implemented with a very high degree of reliability.”
[81] I agree. It seems to me that an appropriate spray painting booth for the facility in this
location should be completely enclosed to effectively contain the airborne
contaminants from spray painting. The Carcoon booth or similar enclosed facility
would satisfy this, but the same cannot be said of the appellant’s proposal.
[82] The attendant cost imposition depends on the scale and commerciality of the
appellant’s activity. If the appellant proposed wholesale spray painting of hulls or
large areas of a hull, then a Carcoon booth or like booth is warranted with all its
attendant costs. However, the appellant does not propose activities of spray painting
the whole or substantial part of slipped boat but accepts spray painting is proposed for
smaller discrete sections of a slipped boat. In these circumstances, a booth of the
Carcoon type or magnitude would be incongruous with, and therefore, overkill for the
appellant’s operations. It seems to me that the proposed spray painting of small
discrete sections of a slipped boat would require a much smaller fully enclosed mobile
booth that could abut and isolate the work area, but I refrain from further speculation
about design. Even so, such a booth requires council approval.
[83] Since no other booth is proposed, or approved, paragraphs 134, 135 and 150 of the
appellant’s plan must be modified to ensure that no spray painting including anti-foul
(delivered by airless, compressed or other spray air guns) is carried out unless and
until she has a spray booth suitable to the task and approved by council pursuant to
condition (B5).
[84] In the meantime, the appellant must limit her activity to hand brushing and roller
applications of paint and anti-foul.
Noxious or Offensive Odour
[85] I remain satisfied that the appellant released contaminants, which caused a noxious or
offensive odour beyond the boundaries of her premises in breach of condition (A10)
47 Affidavit of G Galvin 23 December 2016, Doc. 89, at [25], contrast Exhibits 6, 7, 8, 9 & 10.
48 Affidavit of JA Thorogood. Doc. 90, at [11].
-- 23 of 55 --
24
and (B1_ of the EA.49 It is that status quo which the appellant tries to address by her
proposed plan.
[86] Mr Galvin preferred council’s proposed fully enclosed and air filtered Carcoon
facility as being “the minimum reasonable and practical measure to ensure
compliance with the conditions of the EA and to minimise nuisance and/or harm.”50
In contrast, he testified that the appellant’s containment facility would not sufficiently
prevent or minimise environmental harm in the context of odour (including odorous
painting activities). He opined that containment facility would be unlikely to provide
any real mitigation against the release of contaminants outside the property apart from
large particles which drop out close to their source in any case.51 He considered that
the appellant’s proposed facility does not constitute a valid air quality control device
as it does not physically enclose the source of released material and odours nor does
it filter them.52
[87] The council also relied upon photographs showing a plume of water spray escaping
from the top of an open top tarpaulin arrangement.53 Mr Galvin extrapolated from the
behaviour of the heavier water droplets that smaller potential odorous matter/gas
molecules would be even more likely to escape the tarpaulin arrangement.54 The
appellant argues that her proposed facility will be effective, especially since she seeks
to ensure that “plume” effects on odours are removed or limited, due to the absence
of wind within the containment facility.
[88] Unlike, spray painting, the EA does not proscribe odour-generating activities in the
absence of an approved spray booth. Nevertheless, the focus must be on reasonable
and practicable measures to prevent or minimise environmental harm resulting from
noxious or offensive odour. The appropriate measure is not required to address all
odour, or even completely eliminate all odours beyond the boundary. The relevant
odour must be noxious in the sense of being harmful to health or physical well being,55
and/or offensive in the sense of causing unreasonable offense, being unreasonably
disagreeable to the sense; or disgusting, nauseous or repulsive.56
[89] This requires consideration of subjective and objective perception. I had the
advantage of hearing evidence from lay witnesses including proximate residents,
Mr Ross and Mrs Hudson, about past impacts.
[90] Mr Ross, a former owner of the ERA, testified about odours from paints/anti-fouls
being sprayed on to boats with visible overspray escaping into the surrounding
environment.57 He deposes that fumes and odour caused by the operation since
December 2015 was very offensive, and that he needs to close his house to escape the
smell.58 He testified that the odour has been ‘certainly’ excessive and ‘very
annoying’, and rejected the suggestion that his perception was biased by personal
49 Judgment at [34], [36], [40]-[42].
50 Affidavit of G Galvin 23 December 2016, Doc. 89, at [58].
51 Affidavit of G Galvin 23 December 2016, Doc. 89, at [45].
52 Affidavit of G Galvin 23 December 2016, Doc. 89, at [10(e)].
53 Affidavit of AW Ross 23 December 2016, Doc. 86, pp. 48 to 50; and Affidavit of G Galvin 23
December 2016, Doc. 89, at [10].
54 Affidavit of G Galvin 23 December 2016, Doc 89, at [10(e)].
55 EA, (G14).
56 EA, (G15).
57 Affidavit of AW Ross 23 December 2016, Doc. 85, at [8]; Affidavit of AW Ross, Doc. 86, at [9].
58 Affidavit of AW Ross 23 December 2016, Doc. 85, at [8.11].
-- 24 of 55 --
25
animosity with the appellant and her husband.59 Mr Ross was particularly concerned
about his medical diagnosis of kidney cancer.60 Ms Hudson has experienced non-
offensive odour nearer to the slipway boundary.61 Other local residents were less
perturbed by the operations.
[91] It seems to me that, in windy conditions, the appellant’s proposed containment facility
will have a negligible capacity to contain odious fumes and gases, and quell
complaints. In the absence of a fully enclosed work area, the reality for the appellant
is that odious activities must be suspended when conditions are likely to emit noxious
or offensive odour beyond the property boundaries. As I mentioned above, the
appellant might consider a much smaller fully enclosed mobile booth that could abut
and isolate the work area.
[92] In the circumstances, and although likely to be more effective than the appellant’s
proposal, I am not satisfied that a facility of the Carcoon cost, type or magnitude is
reasonable and practical. Again, I think it is incongruous with, and overkill for the
appellant’s operations. Otherwise, I accept the appellant’s other planned measures.
Dust and Particulate Emissions
[93] I remain satisfied that, in the course of the operation of the ERA, the appellant has
released dust/particulate matter beyond the boundaries of the premises in breach of
conditions (A10), (B2) and (B3) of the EA.
[94] It is accepted by both parties that a containment facility bounding the work area is
required in addition to the measures proposed by the appellant’s plan.
[95] The appellant acknowledges the potential impacts in paragraph 24 of her proposed
plan include dust generation from sanding, grinding, blasting (wet or dry) and fairing
activities. She asserts that her proposed 3.5 m high containment structure enclosed
by canvass partitions (but no roof) is a sufficient measure to address those potential
impacts.62 I note that the design has its creek side below the catchment drain, and
material caught by the screen could contact the slipway on the waterside of the drain.
[96] The council contends that at least a 4m (to 5m) high barrier, in accordance with
Mr Goodfellow’s design, with solid walls extending 20m long along the road frontage
and with 15m returns along. Additionally, the council maintains that the proposed
Carcoon containment facility will also serve as an effective control to address dust.
[97] Again, I reject council’s argument that the Carcoon facility is reasonable and practical
in the circumstances of the appellant’s operations. I discuss later the impact of dust
and particulate on water quality. Further, it seems to me that the issue of noise will
largely govern the nature and scope of an appropriate containment facility in any
event.
Noise
59 Ross, T3-35/45 – 36/3.
60 Ross, T3-35/3-10.
61 Affidavit of ME Hudson 28 August 2015, Doc. 50, T3-7/36-44.
62 Exhibit 4, Appellant’s plan – Annexure “C”.
-- 25 of 55 --
26
[98] I also remain satisfied that the appellant has failed to comply with conditions (A10)
and (E1) of the EA in the conduct of the ERA.
[99] Relevant acoustic considerations and control measures incorporated in the appellant’s
proposed plan are:
(a) restrictions on hours of operations;
(b) improved acoustic shielding across the southern boundary of the Slipway
abutting Bishop Parade, Toorbul providing increased acoustic amenity to
sensitive receptors;
(c) utilisation of portable acoustic screens;
(d) introduction of a new electric winch system;
(e) utilisation of a new electric water blaster;
(f) time limitation on use of electric water blaster and hammering;
(g) restriction on activities related to paint/anti-foul stripping and hull
preparation within the containment facility;
(h) fitting of exhaust silencers on all pneumatic tools; and
(i) erection of signage discouraging excessive noise.
Operating Times
[100] The appellant is willing to confine noisy work to 7 am to 6 pm from Monday to Friday,
and 8am to 5pm on Saturday and Sunday (including on public holidays), no work
between those times, except for movement of boats between 7 am and midnight or in
emergencies.63
[101] However, the council’s proposed plan imposes further limits in operating hours,64
especially the for the use of airless or compressed air guns to 7am to 6pm Monday to
Friday, and 8am to 5pm on Saturday.65
[102] Critically, the EA noise parameters do not discriminate between weekdays and
weekends, or between particular days of the week, including Saturday and Sunday.
There is no basis for the court to derogate from the EA, except where the appellant
voluntarily imposes self-restraint. The operations will nevertheless harnessed by the
noise emissions parameters set by (E1) of the EA.
[103] I accept the appellant’s self-imposed restrictions prescribed in the appellant’s plan.
Noise Barrier
[104] A fence bounds Lot 1. I have found that it had gaps, had insufficient density to be
classed as an acoustic barrier and was of insufficient height to mitigate intrusive noise
63 Council’s plan, s 5.5, paras 52, 53 & 54.
64 Council’s plan, s 5.2.
65 Council’s Plan, ss 5.2 & 6.6.
-- 26 of 55 --
27
impacts at sensitive receivers across Bishop Parade. I concluded that it provided no
real effective acoustic shielding or screening of the noise generated by the operations
on the slipway. So much is consistent with the continuing complaints of proximate
residents.
[105] The appellant is not required to silence all noise likely to emanate from the operations.
[106] Condition (E1) of the EA is in curious terms. The acceptable upper noise levels are
predicated upon “the event of a complaint about unreasonable intrusive noise … not
frivolous or vexatious”. In that event, in respect of residents, condition (E1) of the
EA permits noise emissions of levels not greater than the “Background noise level
plus 5 dB(A)” measured at the dwelling, even if subject of a sincere complaint of
“unreasonable intrusive noise”.66
[107] It is therefore necessary to consider the efficacy of the competing proposals and
determine whether one or both will (in the event of genuine complaint) reasonably
and practically attenuate the noise in the appellant’s particular operations. Both
parties seeks to mitigate acoustic impacts using sufficiently dense barriers blocking
the line of sight between the source and sensitive receptors.67
[108] The appellant proposes the 3.5 metre-high canvass containment facility surrounding
the work area with a density of 600g/m2 partition, fixed around three sides, with a
further canvass gate partition closing the fourth side of the boat upon slipping, leaving
only the roof exposed.68
[109] In contrast, council’s plan seeks to impose Mr Goodfellow’s design of a 4m high
barrier with a higher density of 15kg/m2 and negligible gaps, extending 20m along
the road frontage of Lot 1 with 15m returns along the north-west and south-east
boundaries of the slipway.69
[110] Mr Goodfellow opines that this form of noise barrier is an essential part of the
minimum noise mitigation requirements.70 A gate can be designed and constructed
consistent with the fabrication of the noise barrier, with negligible gaps and sealed
when closed. Mr Goodfellow deposed that:71
“In my view, if the 4m acoustic barrier is not installed then the operations
from the slipway cannot continue, as they will continue to have unreasonable
impacts on the surrounding receptors and will be operating without all
reasonable and practical mitigation measures.”
[111] He concludes in his affidavit sworn 3 March 2017 that:72
“12. It is my view that if the DRC SBEMP (or the earlier SBEMP put forward
on behalf of Ms Cuthbert that was the subject of my SBEMP affidavit –
DOC.88) was to be implemented then unacceptable acoustic impacts
would result for the surrounding receiving environment as a result of
66 EA, conditions (E1), (G5), (G12) & (G13).
67 Cf. Goodfellow, T2-13/15-45.
68 Exhibit 4, Appellant’s plan, p 79 Annexure “C”, and Appellant’s submissions, para 67.
69 Affidavit of DJ Bristow, Doc. 87, at [27].
70 Affidavit of MR Goodfellow 23 December 2016, Doc. 88, Figure 2, at [15].
71 Affidavit of MR Goodfellow 6 March 2017, Doc. 98, p 2, Table 1, Response 1.
72 Affidavit of MR Goodfellow 6 March 2017, Doc. 98, at [12]-[13].
-- 27 of 55 --
28
inadequate screening and inadequate control on noisy activities and
equipment.
13. In my view, the DRC SBEMP (and the earlier SBEMP put forward on
behalf of Ms Cuthbert was that the subject of my SBEMP affidavit –
DOC.88) does not contain reasonable and practicable measures to
prevent or minimise the environmental harm, including environmental
nuisance, relevant to my area of expertise and, as such, does not comply
with the requirements of the Judgment of the Court of 18 December 2015.”
[112] The appellant argues that the premise underpinning Mr Goodfellow’s
recommendation is flawed because:73
(a) he remains totally reliant upon untested data collected by a third
party to establish his ‘predicted noise levels’ in the absence of
undertaking any acoustic monitoring himself of current activities;
(b) he has not taken the appropriate modelling exercise to determine
what level (height) of screening might otherwise cut the line of
sight from the Slipway to the receptors or impact on the proximity
of acoustic measures to the source, so as to affect the transmission
of noise, a key determinant in the acoustic attenuation measures;74
(c) he has not actually undertaken any investigation or modelling to
support the conclusions he seeks to draw from his ‘predicted noise
levels’ in terms of residual exceedance;
(d) he has not performed assessment of ‘background noise level’
(against which any exceedance ought to be properly measured
under condition (E1) of the Environmental Authority) without
regard to the first limb of the definition of “background noise
level” in Schedule G, Definitions (G5) of the Environmental
Authority.
[113] The EA defines “Background noise level” disjunctively and in the alternative as
follows:
“(G5) “Background noise level” means either –
LA90,T being the A-weighted sound pressure level exceeded for 90
percent of the time period not less than 15 minutes, using Fast
response; or
Labg,T being the arithmetic average of the minimum readings measured
in the absence of the noise under investigation during a representative
time period of not less than 15 minutes, using fast response.”
[114] The council relies upon the accepted evidence of the affected residents, and the expert
acoustic evidence of Mr Goodfellow to support the 4m high barrier.
73 Appellant’s submissions, at [143].
74 T2-8/14-46 - T2-9/ 1-9.
-- 28 of 55 --
29
[115] The appellant argues that properly construed, the LA90,T test under the first limb of
condition (G5) does not expressly exclude, therefore includes, the noise under
investigation from the “background noise level”, whereas the Labg,T test in the second
limb, expressly excludes the noise under investigation. Therefore, it is asserted that
Mr Goodfellow’s measurement isolates the background noise.
[116] I do not accept the appellant’s construction argument, which in my respectful opinion
is incongruous with the cognate second limb and leads to an absurd outcome of
conflating the background and activity noise derogating from the purpose of condition
(E1) and Table 1 of the Noise Schedule. In my view, properly construed, the first
limb of the definition is a measurement of background noise levels, which by
necessary implication excludes the activity subject of the investigation. Even so, I
accept that the potential unmitigated noise levels from the machinery typical of the
appellant’s slipway operations are likely to attract genuine complaints from closer
households of unreasonable intrusive noise that exceeds the maximum levels calculated
in accordance with Table 1 of the Noise Schedule.
[117] The concerns and locations of Ms Hudson and Mr Ross are different as between them,
and also when compared to other witnesses. The evidence of Mr Ross, which (along
with some of Ms Hudson’s evidence) stands in stark contrast to the testimony of Mr
Evans and Mr Haynes who live adjacent to the slipway at a similar distance to that of
Mr Ross. Mr Ross did not identify the relevant dates and timeframes in which his
complaints relate, and the particular noise he says is causing him nuisance. In cross-
examination Mr Goodfellow accepted that Ms Hudson was unlikely to be affected by
noise, other than in respect of certain activities, including infrequent abrasive blasting
and water blasting, subject to meteorological conditions, such as wind direction and
speed and pressure inversion which would ordinarily be typically less in the daytime
(and ordinarily seen in the morning or evenings).75 However, he indicated that he had
not actually undertaken those calculations in detail76 and that his calculations did not
account for the existing fence having some ameliorative effect.77
[118] On my reckoning the lay evidence lacks sufficient precision to enable an assessment
under condition (G12) of whether the complained noise, in terms of frequency,
duration, level, tonal characteristics, impulsiveness or vibration, was unreasonably
intrusive, having regard to the Australian Standard 1055.2–1997 Acoustics –
Description and Measurements of Environmental Noise Part 2 – Application to
Specific Situations.78
[119] At the first hearing, I accepted Mr Goodfellow’s evidence critical of the appellant’s
existing boundary treatment in reliance on his recollection of unrecorded background
noise, noise limits, typical noise level ranges for some of the operations of the slipway,
estimates of the potential noise levels of the sensitive receiver locations (the three
closest residences) absent any noise mitigation.79 Mr Goodfellow took his L90
background noise measurements between 2 and 7 December 2016 by the installation
of a noise monitor at sensitive receptor 2, namely Mr Ross’s property.80 Whilst, the
noise levels were not recorded I accepted that Mr Goodfellow has a reliable
75 T2-26/39 - T2-28/6; T 2-29/4-6.
76 T2-26/45-46.
77 T2-28/7-21; T2-28/34-36.
78 T2-25/33-41; T2-29/8-10.
79 Judgment, at [63]-[67].
80 T2-15/36-47.
-- 29 of 55 --
30
recollection of them.81 The background noise level environment surrounding the
premises is low in the order of 36 to 37 dB(A) during the daytime (7 am to 6 pm), 28
to 30 dB(A) during the evening (6 pm to 10 pm) and night time (10 pm to 7 am).82
[120] Based on this and cognate evidence, I found that the appellant’s unmitigated operation
releases noise at such a level as to be likely to result in environmental harm; and it is
highly likely that the acoustic levels prescribed in condition (E1) are exceeded by the
appellant’s operations.83
[121] The second hearing did not afford me much more additional assistance by way of site
specific measurements vis-à-vis line of sight, specific modelling or ground truthing
of the noise mitigation measures as proposed by either party, especially the appellant’s
proposal.
[122] Mr Goodfellow did not take actual measurements of the noisy activities sourced from
the appellant’s actual activities and machinery to isolate background noise otherwise
based on his own measurements, and he did not model the effect of the appellant’s
proposed 600g/m2 vinyl tarpaulin.
[123] Mr Goodfellow opted for typical slipway noisy activities drawing upon the MRG
Environmental Measurement Database, AS2436-2010 Appendix A and DEA Draft
Environmental Guidelines for Boat Building and Maintenance 1994,84 for example,
water pressure cleaning, grit blasting, grinding, hammering etc. He tabulated his
predicted noise levels and the residual daytime exceedance at the sensitive house sites
with no barrier, a 4m high barrier, and a 5m high barrier against a daytime background
from 7 am to 6 pm.85 By comparing the component and potential noise levels for
ERA activity, Mr Goodfellow’s predicted noise levels from the operations of the
slipway mitigated council’s 4m proposal ranges from 16dB(A) for hull scraping up to
72 dB(A) for grit blasting.44 Compared to the averaged tolerance threshold of
41dB(A) (using the lower background noise level plus 55dB(A)) annoyance is
predicably significant for some activates including:
(a) water pressure cleaning 46 dB(A);
(b) grit blasting 72 dB(A);
(c) grinding 53 dB(A);
(d) forklift 53 dB(A);
(e) outboard engine test 56 dB(A);
(f) chainsaw 63 dB(A);
(g) airless spray 46 dB(A);
81 T4-48/5-37.
82 Affidavit of MR Goodfellow 6 July 2015, Doc. 14, at [20]. These were also based on Savery and
Associates Pty Ltd Report ‘Noise impact assessment Toorbul Slipway 48A Bishop Parade Toorbul’ in
evidence in P&E Appeal 1664 of 2010.
83 Affidavit of MR Goodfellow 6 July 2015 Doc. 14, at [22].
84 Affidavit of MR Goodfellow 23 December 2016, Doc. 88, Table 2, at [16].
85 Affidavit of MR Goodfellow 23 December 2016, Doc. 88, Table 3, at [14.1]; [17].
-- 30 of 55 --
31
(h) circular Saw 45 dB(A).
[124] He deposed that the existing fence height and addition of the vinyl would provide
negligible acoustic mitigation of site noise impacts to the most exposed surrounding
sensitive receivers.86 He deposed that the appellant’s proposed 600g/m2 density is
well below the required density to be classed as an acoustic barrier, which he opines
typically requires a minimum surface density of 10-12.5kg/m2.87 Whilst
Mr Goodfellow accepted the use of 600g/m2 vinyl tarpaulin would give some acoustic
attenuation,88 he maintained the need for a 4m high acoustic fence with 15kg/m2
material density.89 In the absence of any modelling using the appellant’s proposed
600g/m2 vinyl tarpaulin, Mr Goodfellow testified that with a reduction in the height
of the council’s proposed 4m barrier, attenuation would be reduced, and that the
exceedance would increase.90
[125] As I said in my last judgment, the council bears the onus of proof governed by the
civil standard of proof, being the balance of probabilities but having regard to the
“sliding scale” described in Briginshaw v Briginshaw (1938) 60 CLR 336.91 Having
regard to the consequences of the outcome of this proceeding, in my view, the
appropriate standard of proof to be applied is that at the higher end of the civil standard
in accordance with the Briginshaw principles.
[126] It seems to me that the council’s approach, indicative of likely contravening
annoyance at sensitive receptors, lacks appropriate precision supporting the design
and construction of an acoustic mitigation barrier of the magnitude and costs
proposed. It seems to me that the imposition of condition (E1) and related tables
necessitates actual measurement of background and component noise relevant to the
complaint. It is not enough, to point to predictions based on general industry standards
and imprecise measurement.
[127] The parties also dispute whether the proposed structures will be subject of further
town planning and building approvals. The appellant relies upon uncertainty about
requisite approvals and consents for council’s proposed 4m high acoustic barrier. The
appellant’s counsel argues that:92
“It remains unknown whether such approvals and consent could possibly be
obtained and, therefore, were such a prescriptive requirement be imposed
under any SBEMP, it might be practically prohibitive on the continuation of
the existing lawful use, unless an exception was granted should those
approvals and consents not be obtained.”
[128] On the contrary, the council argues that the submission is founded on a misconception.
The council argues that the requirement for the 4m high acoustic barrier in the
management plan results from a direction under an order and therefore is exempt
development.93
86 Affidavit of MR Goodfellow 6 March 2017, Doc. 98, p 8.
87 Affidavit of MR Goodfellow 23 December 2016, Doc. 88, at [9].
88 T2-14/5-36.
89 T2-8/1-13.
90 T2-35/27-40.
91 Judgment, [15]-[20].
92 Appellant’s submissions, at [172].
93 Council’s reply submissions, at [7].
-- 31 of 55 --
32
[129] Item 6 of Table 5 of Schedule 4 of the Sustainable Planning Regulation 2009 (Qld)
provides that “All aspects of development a person is directed to carry out under a
notice, order or direction made under a State law” is development that cannot be
declared to be a development of a particular type.94
[130] Section 232 of the Sustainable Planning Act 2009 provides relevantly:-
“232 Regulation may prescribe categories of development or require
code or impact assessment
(1) …
(2) Also, a regulation may prescribe development that a planning
scheme, a temporary local planning instrument or a
preliminary approval to which section 242 applies can not
declare to be self-assessable development, development
requiring compliance assessment, assessable development or
prohibited development.
(3) …”
[131] The effect of the section and the schedule to the Regulation is that all aspects of
development a person is directed to carry out under a notice, order or direction made
under a State law is exempt development.
[132] In this case, the Court has ordered on 18 December 2015:-
“1. The appeal is allowed in part;
2. The review decision of the Council made on 4 May 2015 is
set aside;
5. The Environmental Protection Order dated 31 March 2015
is set aside;
6. In substitution for the Environmental Protection Order dated
31 March 2015, an Environmental Protection Order will
issue, requiring the appellant to prepare and lodge with the
Council within 90 days of the order:
(a) A stormwater management plan for approval by the
Council pursuant to Condition C1 of the
Environmental Authority No. 250000301; and
(b) A site based management plan containing reasonable
and practicable measures to prevent or minimise the
environmental harm, including environmental
nuisance, in relation to conditions A2, A5, A10, B1, B2,
B3, B6, C1, C2, C4, C5, D1, E1; F1, F3, and F4 of the
Environmental Authority No. 250000301.
94 Sustainable Planning Act 2009 (Qld) s 231(2)
-- 32 of 55 --
33
7. Each party will bear their own costs of the appeal unless
either party applies for a different order within 14 days.”
[133] Whilst it is true that an EPO is an order made pursuant to a State law, namely the
Environmental Protection Act 1994 (Qld), the order merely directed the appellant to
deliver and obtain approval of a plan. The parties have since acceded to this court to
determine the dispute about its contents.
[134] I do not accept that the order’s direction to deliver a management plan for council
approval made the provisions of the plan a direction under an order and therefore is
exempt development.95 If it were as contended by the council, that the structure is
exempt development, it would be incumbent on the count at this juncture to properly
consider engineering, building and town planning matters. At best, council seeks to
impose a requirement to engineering certification of the noise (acoustic) barrier and
enclosures.96
[135] In the end, I am unpersuaded, in the absence of this site specific evidence, that the
appellant’s proposed 3.6 m high 600g/m3 containment facility will be effective for the
appellant’s operation, or whether councils’ proposal ought be accepted as to
reasonably and practically attenuate the noise in the appellant’s particular operations.
Further, in my view, the acoustic mitigation structure ought be subject of engineering
and building regulatory requirements.
[136] In these circumstances, where the appellant self imposes limitations, I am not in a
position to reject the containment facility as prescribed in the appellant’s plan.
Above Deck Limitations
[137] The council seeks to limit the appellant’s activities to below deck level with the
exception of non-powered hand tools (which allows the use of spanners, screw
drivers, hand sanding, etc., but excludes noisy impact hand tools, such as hammers).97
[138] It seems to me that such a measure would derogate from the grant of the EA, and
impermissibly limit the appellant’s operations wherein 90% of the activities are
undertaken below the deck in relation to anti-foul. Further, the nuisance of any on
deck activities will be ameliorated by the appellant’s planned containment facility.
[139] In the result, I am not persuaded that the council’s proposal is practical and reasonable.
Certification of the Noise (Acoustic) Barrier and Acoustic Enclosures
[140] The council seeks to impose a requirement to engineering certification of the noise
(acoustic) barrier and enclosures.98
[141] It may well be that the preferred planned containment facility may require building
approval and engineering certification. But these are matters for proper design, town
planning application, assessment and approval by the council.99
95 Council’s reply submissions, at [7].
96 Exhibit 2, Council’s plan, s 6.5.
97 Exhibit 2, Council’s plan, s 5.1.
98 Exhibit 2, council’s plan, s 6.5.
99 Under the Sustainable Planning Act 2009 (Qld) and the Building Act 1975 (Qld).
-- 33 of 55 --
34
[142] It is not within the scope of this proceeding to pre-judge proper assessment and
certification to implement reasonable and practical measures.
Limitation on the use of Pneumatic Tools
[143] The council also seeks to prohibit the use of pneumatic tools in the appellant’s
operations.100 This is not the subject of Mr Goodfellow’s gaze, and the appellant’s
plan prescribes exhaust silencers for all pneumatic tools.101 I accept the appellant’s
proposal as practical and reasonable.
Limitation on Noisy Hand Tool Operation and Electric Water Blaster
[144] I am similarly unpersuaded by the council’s plan to limit noisy hand tool operation
(i.e. grinding, orbital sanding, routing, timber planer, chainsaw, circular saw,
spraying, and polishing) to no more than one hour continuous operation, cumulative
in any four-hour period.102 In contrast, the appellant seeks to limit that noisy hand
tool operation to no more than one hour in any three-hour period,103 which I accept as
practical and reasonable.
[145] Similarly, the council also plans to limit water pressure cleaning with an electric water
blaster to no more than one hour in any day,104 whereas the appellant proposes to limit
that use to no more than three hours in any day, given its use not only in slipway
operations but also in clean-up.105 It seems to me that the appellant’s planned course
is practical and reasonable.
Limitation on Abrasive Blasting
[146] The council asserts that abrasive blasting should be limited to once or twice a year,106
whereas appellant plans for such blasting up to three times a year.107 Abrasive
blasting is an irregular activity of short duration, and I prefer the appellant’s planned
measure as practical and reasonable.
Water Quality
[147] The appellant operates the facility immediately adjacent to Elimbah Creek near the
Pumicestone Passage. More widely, it is surrounded by a sensitive environment part
of the Ramsar Convention Wetland, which includes a high ecological significance
wetland, a wildlife habitat, a marina park and a declared fish habitat. It is part of the
coastal management district, proximate to protected areas and is in a conservation
zone.
[148] In the absence of an appropriate site and storm water management plan, the risks of
the release of the contaminants from the slipway are obvious from uncontrolled and
ill-managed runoff and/or stormwater release from the slipway particularly when that
runoff or release is laden with contaminants. Relevant contaminants include solids,
100 Exhibit 2, council’s Plan, s 6.5.
101 Exhibit 4, appellant’s plan, at [124(c)].
102 Exhibit 2, council’s Plan, s 6.5.
103 Exhibit 4, appellant’s plan, at [124].
104 Exhibit 2, council’s plan, ss 6.5, 12.
105 Exhibit 4, appellant’s plan, at [120].
106 Exhibit 2, council’s plan, s 11.
107 Exhibit 4, Appellant’s plan, at [128].
-- 34 of 55 --
35
endemic and introduced plants and animals, and chemicals, including heavy metals,
Tributyltin, paint and paint chips, anti-foulant, oil and fuel, and their by-products such
as polyaromatic hydrocarbons. All of these are likely to cause environmental harm.
108
[149] The lay witness and expert testimony showed that contaminant laden wastewater has
escaped from the slipway for decades including during the appellant’s tenure. I found
that the appellant had not implemented sufficient practical measures to prevent or
minimise the release of contaminants into the waters, bed or bank of Elimbah Creek.
The operations seemed ad hoc and haphazard in the absence of any stormwater
management plan. Indeed, through wind, uncontained post-clean-up washing and
unintentional stormwater flushing, unlawful contamination of the creek was almost
inevitable. Whilst, the contamination of Elimbah Creek has occurred chronically over
many years, I found that it has continued since the appellant acquired the facility in
2002, and more likely in the last five years.109
[150] The appellant has never sought nor obtained council approval of a Stormwater
Management Plan pursuant to condition (C1(i)). Similarly, there has never been any
agreement to release contaminants to any sewer pursuant to condition (C1(i)). It must
then follow that, in the absence of a requisite management plan or agreement, any
contaminated runoff from the appellant’s operation breaches condition (C2).
[151] I remain satisfied that the appellant’s operation of the slipway causes or permits
contaminants to be directly and indirectly released into Elimbah Creek in breach of
condition (C1) and condition (C2) of the EA and that actual harm is being caused.110
[152] The relevant conditions of the EA are conditions (C1), (C2), (C4) and (C5), which
provide:
“Release of Contaminants to Waters
(C1) Contaminants must not be directly or indirectly released from the
licensed place to any waters except:
(i) as permitted under a Stormwater Management Plan approved by
this administering authority; or
(ii) to a sewer as permitted or otherwise agreed from time to time by
Caboolture Shire Council’s Caboolture Water Unit.
Stormwater Management –
Contamination of Rainfall and Stormwater Runoff
(C2) Except as otherwise provided by the conditions of the Water Schedule for
this environmental authority, the environmentally relevant activity must
be carried out by such practical means necessary to prevent and/or
minimise the release or likelihood of release of contaminated runoff from
the licensed place to any stormwater drain or waters or the bed or banks
108 Affidavit of DJ Bristow 6 July 2015, Doc 13, at [17].
109 Affidavit of DJ Bristow 31 August 2015, Doc. 61, at [12.4].
110 Judgment, at [70]-[98].
-- 35 of 55 --
36
of any such waters. ‘Contaminated runoff’ for the purposes of this
condition means any waters, (and included stormwater and/or
stormwater runoff) that contains contaminants that may cause
environmental harm.”
Clean-up of spillages
(C4) Any spillage of wastes, contaminants or other materials must be cleaned
up as quickly as practicable. Such spillages must not be cleaned up by
hosing, sweeping or otherwise releasing such waters, contaminants or
material to any stormwater drainage system, roadside gutter or waters.
Bunding
(C5) All chemical tanks must be bunded so that the capacity of the bund is
sufficient to contain at least 100% of the largest storage tank plus 10%
of the second largest storage tank within the bund.
[153] The appellant’s plan identifies the relevant water quality performance and mitigation
measures in ss 4.5 and 4.6 as follows:111
“4.5 Performance measures – Stormwater
27 Slipway operations with stormwater impact potential include the
following:
(a) wastewater and residuals/particulates associated
Slipway operations including the clean-up of abrasive
blasting, painting, paint stripping and hull preparation, and
anti-fouling operations;
(b) cloudburst and tidal inundation of operational Slipway areas.
28 The relevant water quality criteria applicable to consideration of site
operations are:
(a) Environmental Protection (Water) Policy 2009; and
(b) Any other relevant Water Quality policies recommended by
the Department of Environment and Heritage Protection in
lieu of Queensland specific criteria/guidelines.
4.6 Mitigation measures – Stormwater
29 Relevant stormwater considerations and control measures
incorporated in this SBEMP are summarised as follows:
(a) a new automated first flush collection drain and system;
(b) new bund wall immediately downstream to the first flush
collection drain to prevent tidal inundation and boat wash into
the drain;
111 Affidavit of DR Cuthbert 28 February 2017, Doc. 94, Exhibit DRC-4.
-- 36 of 55 --
37
(c) diversion of external catchment run-off through bunding and
pit capture;
(d) introduction of 5,000L first flush and 5,000L overflow storage
tanks for additional storage capacity;
(e) installation of a rain gauge;
(f) treatment of run-off to allow for separation and disposal of
solid wastes as regulated waste;
(g) a water re-use and irrigation system to ensure that there is no
discharge to the creek of untreated run-off;
(h) clean up procedure to include full wash down of Slipway at
completion of daily works, including:
(i) vacuuming or sweeping of all hardstand areas; and
(ii) wash down to remove any dust and particulate
matter;
(i) general restriction on operations to above the First Flush
Collection Drain and the Existing Drain.”
[154] The differences between measures proposed by both parties for the prevention of the
release of contaminants to waters and management of contamination of rainfall and
stormwater runoff are largely a matter of sophistication and degree.
[155] The respective provisions relating to bunding of chemicals and spill prevention and
clean up are contained within ss 8.1 and 8.2 of council’s plan and ss 9.1 and 9.2 of the
appellant’s plan.
[156] It seems to me that the appellant’s plan, by ss 9.1 and 9.2, implement reasonable and
practicable measures to prevent or minimize environmental harm in relation to
conditions (C4) and (C5) of the EA.112 The prevention of the release of contaminants
to waters and management of contamination of rainfall and stormwater runoff, are
contained in s 18 of both council’s plan and the appellant’s plan.
[157] Sections 4.6, 7, 16 and 18 of the appellant’s plan seek to address conditions (C1) and
(C2) to prevent the release of contaminants to waters and management of
contamination of rainfall and stormwater runoff.
[158] Section 7.2 retains the existing collection drain, and introduces a new first flush
collection drain as follows:
“7.2 General requirements for cleanliness of the Slipway
68 The existing collection drain (Existing Collection Drain) is to
be retained.
112 Compare exhibit 2, council’s plan, ss 8.1, 8.2.
-- 37 of 55 --
38
69 A new collection drain (First Flush Collection Drain) is to be
constructed above the Existing Collection Drain and above
the level of the highest astronomical tide on the Slipway,
generally in accordance with the Boat Slipway Layout Plan
attached as Annexure D to this SBEMP.
70 At the conclusion each day’s operations, the Slipway
Manager is to ensure that all operational areas of the Slipway
are maintained in a clean, uncontaminated and trafficable
condition, and that any contaminants and residues are
removed from all footwear, tools and appliances prior to
removal from the Slipway.
71 At the conclusion each day’s operations all operational areas
of the Slipway are to be swept and any particulate matter
bagged and contained for disposal in accordance with the
regulated waste protocols under this SBEMP. The
operational areas of the Slipway are to be washed at the end
of each day’s operations.
72 The required post-work cleaning (as detailed above) is to only
occur within the Containment Facility, with all sides fully
enclosed.
73 The First Flush Collection Drain and the Existing Collection
Drain are to be empty prior to the commencement of each
day’s operations.
74 The First Flush Collection Drain and the Existing Collection
Drain are to be pumped out at the conclusion of each day’s
operations.”
[159] The prevention of the release of contaminants to waters and management of
contamination of rainfall and stormwater runoff, are contained in s 18 of the
appellant’s plans.
[160] Section 18 provides as follows:
“18 Stormwater Management
163 The implementation of the operations procedures above will
contribute significantly to reducing potential for release of
contaminants from Slipway operations to the waters of
Elimbah Creek.
164 In addition, the Slipway is required to incorporate
appropriate rainwater and stormwater control measures to
minimise the risk of residual pollutants releasing to Elimbah
Creek.
18.1 First Flush Collection System
-- 38 of 55 --
39
165 The First Flush Collection Drain with an automated first flush
pump diversion system will operate concurrently with the
Existing Collection Drain and pump system on the Slipway.
The Existing Collection Drain shall, therefore, act as fail-safe
and redundancy drainage
166 The First Flush Collection Drain is to have a minimum
capacity of 1200 litres, having sufficient capacity to divert the
first flush of water, which may contain any residual
contaminants, from a rain event from entering Elimbah
Creek.
167 The First Flush Collection Drain will incorporate the
automated First Flush Rain Diversion system (FF600) in
accordance with the specifications as attached as Annexure E
to this SBEMP.
168 The process and operation of the FF600 is described as
follows:
169 ‘FF60 is suitable for use where it cannot be guaranteed that
an area will be left free of contaminants at the end of a
washdown operation. Runoff is presented to the FF600
chamber via the grated inlet and silt basket. During a wash
operation all runoff is diverted to a holding tank for treatment
or proper disposal.
170 During a rain event if no washdown is taking place, the level
in the chamber will rise as the diversion valve is closed. At a
point just below the stormwater outlet a float will activate,
opening the diversion valve and diverting the pit contents to
the Treatment tank. This procedure will continue until the
required 'First Flush' volume has been diverted. After the
First Flush has been taken discharge of the runoff will be
through the stormwater outlet pipe.
171 This arrangement eliminates the larger volumes of runoff that
are normally collected with a conventional First Flush
capture system.’
172 Save for works on large boats that cannot be placed entirely
above the First Flush Collection Drain (Large Boats), to a
maximum of 15 such Large Boats per year, all works are to
be completed on boats sitting above the First Flush Collection
Drain and, therefore, the drain will collect all run-off from
the Slipway operational area.
173 In relation to works on Large Boats, such works are to be
performed with the Containment Facility fully enclosed, save
that the Elimbah Creek side will only be closed as far as
possible. When such work is performed, the entire Slipway
must be completely covered by tarpaulins (ie from the side of
-- 39 of 55 --
40
the Containment Facility to the other side of the Containment
Facility) from the First Flush Collection Drain down to a
point at least 2 metres below the outermost projection of the
Large Boat. Any paint spray and particulate matter is to be
captured by the tarpaulins, with those tarpaulins rolled and
taken above the First Flush Collection Drain for cleaning.
174 Work on parts of a Large Boat below the First Flush
Collection Drain must cease upon the tide (ie the level of
Elimbah Creek) reaching a point that is 3 metres below the
outermost projection of the Large Boat.
175 At the completion of works on a Large Boat (including
mandatory cessation of works due to the incoming tide), in
addition to the general requirements regarding the
cleanliness of the operational areas of the Slipway, the
Slipway Manager is to ensure that the area between the First
Flush Collection Drain is examined for any particulate
matter, dust or other waste (which waste shall be immediately
removed and the drain cleaned, if any particulate matter, dust
or other waste is observed).
176 The water from the FF600 is to be pumped to a 5,000 litre
storage tank (First Flush Tank), which is to be located on site
in accordance with the Boat Slipway Layout Plan attached as
Annexure D to this SBEMP.
177 The Slipway Manager is to regularly monitor water levels to
ensure that sufficient capacity is maintained to take the first
flush of a rainwater event after work on the Slipway.
178 A second 5,000 litre storage tank (Storage Tank) is to be
located on site in accordance with the Boat Slipway Layout
Plan attached as Annexure D to this SBEMP, to act as
overflow containment for the First Flush Tank.
179 There is to be an automatic pump to transfer water from the
First Flush Tank to the Storage Tank.
180 There is to be no release of wastewater from the First Flush
Tank, other than to the Storage Tank.
181 The First Flush Collection Drain and Existing Collection
Drain are to be pumped out to the First Flush Tank after each
wash down required after activities on each operational day,
to avoid potential release from overflow, and any residual
solids within the collection drains are to be removed by hand
instrument or vacuum, to be bagged for proper disposal as
regulated waste.
18.2 Bunding
-- 40 of 55 --
41
182 In addition to existing bunding on the Slipway, there shall be
created and maintained the following additional bunding in
accordance with the Boat Slipway Layout Plan attached as
Annexure D:
(a) a 200mm high barrier (whether by bund or by a combination
of bund and rise in levels) along the entire road frontage of
the Slipway (but not the boat ramp) to avoid overland flow
from the roadway down the Slipway;
(b) a 100mm bund along the eastern boundary of the Slipway,
dividing the Slipway and the boat ramp, which will sit outside
the Containment Facility, to create a self-contained area
potentially exposed to contaminants from Slipway operations;
and
(c) 100mm bund immediately below the First Flush Collection
Drain.”
[161] Mr Bristow deposed that the appellant’s plan is deficient because:
1. It does not include any supporting drawings, technical specification sheets,
diagrams, log sheets and forms as provided in the earlier version.113
2. It reduces the size of the treatment tanks from 2 x 10,000l to 2 x 5,000l which
reduces the treatment and storage capacity and capability of the system.114
3. The lack of engineering detail detracts from a proper understanding of what
the systems will practically consist of and how they’ll be arranged and
performed.115
4. The site monitoring and contingency plans are lacking to non-existent, and
qualitative at best and would not provide adequate information and controls to
manage the environmental (water quality) risks practically.116
5. It does not acknowledge the Australian Standard for Storage and Handling
Chemicals; prohibit the disposal of stored slipway wash water to land and
continues to direct its disposal to Lot 20 contrary to the slipway’s EA; provide
controlled impacts of tidal inundation of the work site; prohibit work on boats
on the water; cause work to cease if anticipated storms would interrupt work
nor provide contingency measures during storms; limit the size of vessels
slipped; provide emergency clean-up procedures; provide for spray painting
in an approved containment facility; and require large boats to be fully
contained against Elimbah Creek.117
6. Further, it does not “provide complete cohesive and measurable management
in monitoring provisions to reasonably and practically control, monitor and
113 Affidavit of DJ Bristow 6 March 2017, Doc 95, at [106]
114 Affidavit of DJ Bristow 6 March 2017, Doc 95, at [108].
115 Affidavit of DJ Bristow 6 March 2017, Doc. 95, at [109].
116 Affidavit of DJ Bristow 6 March 2017, Doc. 95, at [110].
117 Affidavit of DJ Bristow 6 March 2017, Doc. 95, at [111]
-- 41 of 55 --
42
manage the operation. The location of the slipway in a sensitive environment
and the nature of its operation, in which the toxic chemicals are removed and
reapplied to boats in an open air work area beside and connected to Elimbah
Creek mandate that the activity be properly and appropriately managed,
monitored and controlled”.118
[162] Much of Mr Bristow’s criticism exposes how the appellant’s plan is not
comprehensive and lacks sophistication and monitoring. I have already commented
on monitoring, and some of the criticism relate to detailed design that, in my view, is
beyond the scope of this proceeding. The test ought focus on whether the appellant’s
plan (by comparison with the council’s contentions) if implemented would province
reasonable and practical measures to minimise or prevent environmental harm in
respect of conditions.
[163] It seems to me that the critical matters of water quality exposed by the competing
plans are:
1. The relative size of vessel for the size of the slipway;
2. Whether the capacity of the Frist Flush Collection Drain ought be 2400 litres
as opposed to the appellant’s 1200 litre capacity;
3. Whether two 10,000 litre tanks is preferred to two 5000 litre storage or settling
tanks;
4. Whether an oil water separator system ought be employed;
Relative Size of vessels to managed work area
[164] Mr Ross deposes to seeing large boats on the slip overhanging the catchment drain
and/or overhanging the eastern edge of the formed area of the slipway.119 There was
no protected or enclosed workspace for longer vessels that, because of their size, have
to overhang the interceptor drain.
[165] Paragraphs 172 to 175 of the appellant’s plan seek to manage slipping and work on
large boats that overhang the catchment drain to the Creek side.120 The plan limits
work for up to 15 large boats per year that sit over or below the First Flush Collection
Drain.121 The conditions require that the works are to be undertaken within Mrs
Cuthbert’s proposed containment facility, fully enclosed except the Elimbah Creek
side will ‘only be closed as far as possible’, with the Slipway entirely covered in
tarpaulins down to 2m from the outermost projection of the subject boat beyond the
First Flush Collection Drain.122 Further, works on a large boat must cease upon the
tide reaching a point that is 3m below the outermost projection of the boat, that is 1m
below the tarpaulin.
[166] This can be compared to s 17 of the Council’s plan.
118 Affidavit of DJ Bristow 6 March 2017, Doc. 95, at [113]
119 Affidavit of AW Ross 23 December 2016, Doc. 85, at [39(vii)].
120 Exhibit 4, appellant’s plan, at [171] – [172].
121 Exhibit 4, appellant’s plan, at [173] – [176].
122 Exhibit 4, appellant’s plan, at [174].
-- 42 of 55 --
43
[167] Council seeks to impose a limitation that all works on boats of a length that
necessitates them overhanging the First Flush Collection Drain (i.e. boats over 40 feet
or 12.2m) are to be undertaken entirely above the First Flush Collection Drain and
within the containment facility, unless an approved full-sealed containment system is
in place to both prevent wastewater runoff from entering Elimbah Creek and exclude
tidal waters from penetrating above the containment system.123 Further, council seeks
to limit such works to spot repairs and then only above the inspection drain.
[168] The starting point ought be that no vessel ought extend beyond the slipway boundaries
adjacent to Elimbah Creek and road frontage, and work should never be permitted
over the water. All work on the vessel ought be so contained to prevent both
wastewater runoff entering Elimbah Creek and tidal waters from breaching the first-
flush collector drain. I have already remarked that an approved spray painting booth
that fully encloses and isolates the area is a pre-requisite to all spray painting. I have
also remarked about my uncertainty about the efficacy of a noise attenuating
containment facility. However, suffice it to say, that a containment facility ought
contain the work area, and I think it is unacceptable that the creek side ‘only be closed
as far as possible’.
[169] It seems to me that the appellant’s plan at paragraphs 172 – 175 ought be be modified
to expressly exclude all work on boats longer than 40 feet or 12.2 metres unless the
repair work is limited to spot repairs and then only above the interception drain (not
inundated by tide).
First Flush Collection Drain Capacity
[170] The council’s plan requires a combined capacity of 2,400 litres for the first-flush
collection drain, sump and pump pit, whereas the appellant plans for a capacity of
1,200 litres.
[171] As I apprehend it, the First Flush Collection Drain will comprise the lineal drain, sump
and pump pit with a combined minimum capacity of 1200 litres located generally in
accordance with the Boat Slipway Layout Plan being Annexure D to the appellant’s
plan. Its utility ought be considered in relation to the Highest Astronomical Tide
(HAT), being the highest high tide level predicted to occur under average
meteorological conditions and any combination of astronomical conditions.
[172] It seems appropriate that the First-Flush collection drain be placed above the HAT to
limit the risk of tidal inundation, and the need to pump out additional sea water. On
this basis, I accept the appellant’s contention that a 1,200 litre drainage capacity is apt
for the proposed bunded dimensions of the slipway, and sufficient to divert the first
flush of stormwater (up to a depth of 20mm) from any rain event.124
Oil water separator & media filter
[173] It is uncontroversial that the water collected through the first flush system is reused
on-site for wash down and pressure cleaning to reduce the volume of water to be
removed off-site.
123 Exhibit 2, council’s plan, ss 6.7, 17.
124 12 metres length x 5 metres width x .02 metres depth = 1.2m3 or 1,200 litres.
-- 43 of 55 --
44
[174] However, the council’s plan imposes an oil-water separator component to the First-
Flush System, so that the water is pumped from the sump to the storage tank via an
oil-water separator, which will pre-treat the pumped water.125 From there council
proposes that the pre-treated water, once settled, is then pumped through a sand filter
and an activated carbo filter to a second storage tank.126 The water from the second
storage can be re-used in operations.
[175] It seems to me that these measures are unreasonable and impractical in the proposed
self contained wastewater system destined for regulated waste disposal.
[176] Further, I note that Mr Bristow dealt with this circumstance if the appellant’s painting
operations were limited to hand brushing and rolling without a Carcoon facility as
follows:127
“93 If spray painting/antifouling was to be genuinely discontinued
as claimed by the Cuthberts, then some of the investment in
these controls might be able to be reduced. The Carcoon
containment facility might fall away as essential, and the
acoustic wall fitted instead with a sailcloth roof to protect
against generating contaminated stormwater in substitution.”
[177] I do not accept that the evidence warrants modification of the appellant’s containment
facility to incorporate a sailcloth roof as contemplated by Mr Bristow to protect
against generating contaminated stormwater. Instead, I accept the measures proposed
by the appellant are reasonable and practical in the absence of a sail roof.
Capacity of the storage/settling tank.
[178] The appellant proposes two 5,000L tank, where as the council proposes two 10,000
litre treatment tanks.
[179] It seems prudent to ensure a generous storage capacity and capability of the self-
contained First-Flush System. I prefer the council’s two 10,000 tank capacity, that is
a 10,000 litre settling tank and 10,000 litre storage tank. The appellant’s plan ought
be modified accordingly.
[180] With these modifications, together with the appellant’s proposed monitoring,
recording and training, I am satisfied that the First-Flush System and bunding
proposed by the appellant is reasonable and practicable to minimise or prevent
environmental harm in respect of conditions (C1) and (C2) of the EA.
Land
[181] In my judgment, I concluded that the irrigation of the tank water from the drain and
pit constitutes a release, or likely release, of contaminated water onto the land in
breach of condition (D1) of the EA. Condition (D1) of the EA, which provides:
“Release of contaminants to land
125 Exhibit 2, council’s plan, s 18.1(c).
126 Exhibit 2, council’s plan, s 18.3.
127 Affidavit of DJ Bristow 6 March 2017, Doc. 95, at [93].
-- 44 of 55 --
45
D1 There must be no release nor likely release of any contaminants
to land.”
[182] Despite this, the appellant submits that irrigation of the water from the holding tank,
even in its current form, does not breach this condition. The appellant’s management
plan permits the irrigation of Lot 20 using the tank water in paragraphs 29(g), 57, and
188 as follows:128
“29 Relevant stormwater considerations and control measures
incorporated in this SBEMP are summarised as follows: …
(g) a water re-use and irrigation system to ensure that
there is no discharge to the creek of untreated run-off;
…
…
57 No wash downs are to occur unless the holding tanks have at
least one-third of their combined storage capacity available
before the wash-down commences. To achieve this buffer
capacity, irrigation discharge should be carried out, only
from the Storage Tank, after settling.”
…
188 Only water from the storage tanks may be disposed of to land,
and then only to land on Lot 20 and not within 24 hours of
any transfer of water from the First Flush Tank.”
[183] The appellant argues that irrigation of the water from the holding tank does not breach
this condition because:
(a) the reference to release of contaminants is, properly construed, a
reference to unlawful release;
(b) the results of testing of the water from the activities show it meets
ANZECC guidelines for short term irrigation to land (20 years,
although the test results show that it would satisfy the irrigation
standard for almost 35 years); and
(c) the reference to release is, properly construed, a reference to
release to land outside of the Licensed Premises being both Lot 20
on RP72941 and Lot 1 on AP2986 PO210992.
(d) Appropriate irrigation management measures can be put in place
to ensure any compounding or aggregate accumulation of metals
is properly managed.
[184] The appellant proposed reading an additional qualifying term of “unlawful” in relation
to the term “release”. The result sought by the appellant is, by that qualification, the
ANZECC guidelines would apply.
128 Affidavit of DR Cuthbert 28 February 2018, Doc. 94, Exhibit DRC-4.
-- 45 of 55 --
46
[185] In appropriate cases, the court is entitled to read a provision by implying additional
or clarifying words in order to give effect to the legislative purpose.129 In Wentworth
Securities Ltd v Jones [1980] AC 74,130 Lord Diplock formulated the following three
stage test:
“First, it was possible to determine from a consideration of the provisions of
the Act read as a whole precisely what the mischief was that it was the
purpose of the Act to remedy; secondly, it was apparent that the draftsman
and Parliament had by inadvertence overlooked, and so omitted to deal with,
an eventuality that required to be dealt with if the purpose of the Act was to
be achieved; and thirdly, it was possible to state with certainty what were the
additional words that would have been inserted by the draftsman and
approved by Parliament had their attention been drawn to the omission before
the Bill passed into law. Unless this third condition is fulfilled any attempt
by a court of justice to repair the omission in the Act cannot be justified as
an exercise of its jurisdiction to determine what is the meaning of a written
law which Parliament has passed. Such an attempt crosses the boundary
between construction and legislation. It becomes a usurpation of a function
which under the constitution of this country is vested in the legislature to the
exclusion of the courts.”
[186] The test was applied by McHugh JA (then in the New South Wales Court of Appeal)
in Kingston v Keprose Pty Ltd,131 where he said:
“Once the object or purpose of the legislation is delineated, the duty of the
Court is to give effect to it in so far as, by addition or omission or
clarification, the relevant provision is capable of achieving that purpose or
object.”
[187] In my respectful view, the premise of the argument is fatally flawed. The condition
is in plain and clear terms, which provide for “no release nor likely release” of
contaminants to land. It is a strict approach warranted by the nature and purpose of
the environmental authority. It does not give rise to any uncertainty, absurdity,
injustice or anomaly. The reality is that the condition is purposely clear; consistent
with condition (F1) regarding the release of ‘waste’, and can be contrasted with the
exceptional permission in condition (C1) for the release of contaminants to water. I
am not persuaded that there is any need to introduce any qualification in condition
(D1) as contended by the appellants. Therefore, I affirm my conclusion in the
judgment.
[188] The appellant also challenged the finding of the contamination of the tanked water.
[189] Since the hearing, Paula Duke of Duke Environmental undertook testing of the water
collected by qualified personnel from Australian Laboratory Services in accordance
with AS/NZS 5667 – Water Quality Sampling and transported samples directly to a
129 Newcastle City Council v GIO General Ltd (1997) 191 CLR 85, 113; James Hardie & Coy Pty Ltd v
Seltsam Pty Ltd (1998) 196 CLR 53, 82; R v Young (1999) 46 NSWLR 681, 687, 690, 740; R v PLV
(2001) 51 NSWLR 736, 743-744; Ravenscroft v Nominal Defendant [2008] 2 Qd R 32, 51.
130 Wentworth Securities Ltd v Jones [1980] AC 74, 105-106. Applied in Kingston v Keprose Pty Ltd
(1987) 11 NSWLR 404; Bermingham v Corrective Services Commission of New South Wales (1988) 15
NSWLR 292; Tokyo Mart Pty Ltd v Campbell (1988) 15 NSWLR 275, 283.
131 Kingston v Keprose Pty Ltd (1987) 11 NSWLR 404, 424.
-- 46 of 55 --
47
NATA accredited laboratory for testing.132 The results of that laboratory analysis
indicated that levels of metals detected in the samples were below the ANZECC
trigger values for short term (20 years) irrigation.
[190] Clearly enough, the tests showed contamination albeit under the ANZECC levels.
[191] I also accept, Dr Thorogood’s evidence exposing the shortcomings of the recent
testing. He deposed that:133
“8 the dissolved concentration of copper and zinc which is what
has been reported is several orders of magnitude above the
trigger values provides by ANZECC for slightly to moderately
disturbed marine ecosystems. The dissolved concentration of
lead is also above the ANZECC guideline.
9 That is, the stored wash down water is significantly
contaminated … .
….
12 The reported results address only the dissolved
concentration. The concentration of contaminants in the
sediment at the base of the tank is likely to be significantly
greater.”
[192] Similarly, Mr Bristow deposed as follows:134
“41 The toxicity of the copper to soil fauna has been ignored. At
the concentrations reported, the water would pose a real and
direct threat to aquatic ecosystems, algae, and soil fauna
(worms/nematodes etc.) and an indirect threat to insects. The
presence of zinc, lead and other metals and hydrocarbons
simply adds to the toxic contaminant load that the water
presents to any living thing.
42 Whilst I acknowledge copper and zinc are essential trace
elements for health plants, the concentrations reported,
applied without strict monitoring and management, would not
be beneficial to plant growth and, rather, would by phytotoxic
over time.
43 It is wrong to conclude that the holding tank waters are
suitable for irrigation and it is my view that without specialist
soil management or very well draining deep sand soils, spray
or soaker hose irrigation of plants with this water would
result in the death of the plants from salinity and contaminant
contamination (including heavy metal contaminants).
132 Affidavit of P Duke 28 February 2017, Doc. 93, Exhibit PD2.
133 Affidavit of JA Thorogood 6 March 2017, Doc. 96, at [8] - [9], [12].
134 Affidavit of DJ Bristow 6 March 2017, Doc. 95, at [41] – [44]
-- 47 of 55 --
48
44 I remain of the opinion that the land disposal of this relatively
untreated wastewater poses potential and real environmental
harm and should not occur.”
[193] In my view, the appellant’s past and continued irrigation of the holding tank water
onto Lot 20 is in breach of condition (D1) of the EA.
[194] Therefore, paragraphs 29(g), 57, and 188 in the appellant’s proposed plan conflict
with the EA in so far as they permit irrigation of the holding tank water onto the land,
and ought be deleted.
Waste Management
[195] This waste generated by the appellant’s operations is “regulated waste” pursuant to
Schedule 7 Part 1 of the Environmental Protection Regulation 2008 (Qld) as it
includes waste from the use of paint, copper and hydrocarbons.135
[196] The relevant EA conditions provide:
“(F1) Waste must not be released to the environment, stored, transferred
or disposed of contrary to any condition of this environmental
authority.
…
(F3) All waste shall be removed to an approved waste disposal facility
or approved waste recycling facility by a licensed waste
transporter.
(F4) Where waste is taken off site, the holder of this environmental
authority must monitor and record the:
(i) date, quantity and type of wastes removed;
(ii) waste receiving operator that removed the wastes off-site;
and
(iii) destination of the waste.”
[197] I found, that the appellant’s waste management arrangements breach condition (F3)
of the EA. Further, in breach of condition (F4), the appellant had insufficient records
of waste being taken off site.136
[198] Apart from the release of water to land, which I have dealt with above, there is little
difference between the parties’ respective plans.137 On this basis, reasonable and
practical measured are reflected in the appellant’s plan.
Injunction
135 Affidavit of CP Manley 28 August 2015, Doc. 49, at [11]; T5-77/38.
136 Affidavit of HL Cuthbert 26 August 2015, Doc. 46, at [43(i)]; Exhibit 9 pp 44.9 & 45.1.
137 Exhibit 4, appellant’s plan, ss 19.0, 20.0; Exhibit 2, council’s plan ss 19, 20.
-- 48 of 55 --
49
[199] The council has applied for an injunction to restrain the appellant from conducting
her boat maintenance and repair activities until final determination of the matter. That
application was heard with this proceeding.
[200] The Environmental Protection Act 1994 (Qld) provides relevantly:
“430 Contravention of condition of environmental authority
(1) This section applies to a person who is the holder of, or is acting
under, an environmental authority.
(2) The person must not wilfully contravene a condition of the authority.
Maximum penalty – 6250 penalty units or 5 years imprisonment.
(3) The person must not contravene a condition of the authority.
Maximum penalty – 4500 penalty units.
(4) In a proceeding for an offence against subsection (2), if the court is
not satisfied the defendant is guilty of the offence charged but is
satisfied the defendant is guilty of an offence against subsection (3),
the court may find the defendant guilty of the offence against
subsection (3).
431 Environmental authority holder responsible for ensuring conditions
complied with
(1) The holder of an environmental authority must ensure everyone
acting under the authority complies with the conditions of the
authority.
(2) If another person acting under the authority commits an offence
against section 430, the holder also commits an offence, namely,
the offence of failing to ensure the other person complies with the
conditions.
Maximum penalty – the penalty under section 430(2) or (3) for
the contravention of the conditions.
(3) Evidence that the other person has been convicted of an offence
against section 430 while acting under the authority is evidence
that the holder committed the offence of failing to ensure the
other person complies with the conditions.
(4) However, it is a defence for the holder to prove –
(a) the holder issued appropriate instructions and used all
reasonable precautions to ensure compliance with the
conditions; and
(b) the offence was committed without the holder’s knowledge;
and
-- 49 of 55 --
50
(c) the holder could not by the exercise of reasonable diligence
have stopped the Commission of the offence.”
[201] Section 505 of the Environmental Protection Act empowers the court to make an order
directing an offender to stop an activity that is or will be a contravention of the Act,
and other orders, as follows:
“505 Restraint of contraventions of Act etc
(1) A proceeding may be brought in the Court for an order to remedy or
restrain an offence against this Act, or a threatened or anticipated offence
against this Act, by –
(a) the Minister; or
(b) the administering authority; or
(a) someone whose interests are affected by the subject matter of the
proceeding;
…
(5) If the Court is satisfied –
(a) an offence against this Act has been committed (whether or not it
has been prosecuted); or
(b) an offence against this Act will be committed unless restrained;
the Court may make the orders it considers appropriate to remedy or
restrain the offence.
(6) An order –
(a) may direct the defendant –
(i) to stop an activity that is or will be a contravention of this Act;
or
(ii) to do anything required to comply with, or to cease a
contravention of, this Act; and
(b) may be in the terms the Court considers appropriate to secure
compliance with this Act; and
(c) must specify the time by which the order is to be complied with; and
(d) may include an order for the defendant to pay the costs reasonably
incurred by the administering authority in monitoring the
defendant’s actions in relation to the offence.
(7) The Court’s power to make an order to stop an activity may be exercised
whether or not –
-- 50 of 55 --
51
(a) it appears to the Court the person against whom the order is made
intends to engage, or to continue to engage, in the activity; or
(b) the person has previously engaged in an activity of that kind; or
(c) there is danger of substantial damage to the environment if the
person engages, or continues to engage, in the activity.”
[202] Kirby P helpfully set out a number of guidelines for the exercise of discretion in
Warringah Shire Council v Sedevcic,138 which relevant for this case the council
submits are:
(i) there is an indicated legislative purpose of upholding, in the normal case, the
integrated and coordinated nature of planning (and environmental law). Unless
this is done, equal justice may not be secured. Private advantage may be won
by a particular individual which others cannot enjoy. Damage may be done to
the environment, which it is the purpose of the orderly enforcement of
environmental law to avoid;
(ii) the instant application is made by the local government. The local government
is seen as the proper guardians of public rights. The Council's interest is deemed
to be protective and beneficial, not private or pecuniary;
(iii) the relief sought here is not against a "static development" (e.g. the erection of
a building) the removal of which would occur at great cost or inconvenience,
but against a continuing breach by conduct; and
(iv) the breach is not merely a technical breach, but is having significant adverse
amenity impacts on the environment and surrounding residents in the locality
and impacts on the environment as noted in the evidence before this Court.
[203] The council argues that the appellant and her husband have irresponsible and cavalier
attitudes to the EA conditions, including:139
(a) Irrigation and contamination onto Lot 20 in flagrant breach of condition
(D1).140
(b) Letting tarpaulins which are used to trap contaminants lie on the slipway
and be inundated by successive tides for at least a week.
(c) Using a chainsaw to cut a large timber beam contaminated by layers of
anti-foul with no attempt to capture or control the contaminated dust
generated.141
(d) Undertaking work on boats that are not on the Slipway and are moored in
Elimbah Creek.142
138 Warringah Shire Council v Sedevcic (1987) 63 LGERA 361, 365.
139 Council’s submissions at [49].
140 Affidavit of DR Cuthbert 28 February 2017, Doc. 92 at [20]; T4-18/36.
141 Affidavit of AW Ross 23 December 2016, Doc. 85, at pp 41-43.
142 Affidavit of DJ Bristow 21 July 2015, Doc. 20, at [22] – [23].
-- 51 of 55 --
52
(e) Bringing boats onto the slipway that overhang the catchment drain (to the
Creek side) and undertaking work on boats on the Creek side of the
catchment drain.143
(f) Utilising a tarpaulin arrangement that does not attempt to completely
enclose the boat on all sides (or at the top).144
(g) Undertaking works without drop sheets in place on the slipway.145
(h) Failing to make appropriate adjustments to the operational practices of the
business to eliminate breaches of conditions of the EA in respect to the
Judgment of the Court of 18 December 2015.
Discussion
[204] The appellant has carried on the business of a boat maintenance and repair facility
since 2002 at 48 Bishop Parade at Toorbul, comprising Lot 20 on RP 7294 and Lot 1
on AP 2986. The facility is adjacent to Elimbah Creek near the Pumicestone Passage.
[205] Overlayed aerial photographs show Lot 1 as an extension of Lot 20 across Bishop
Parade and into Elimbah Creek. Lot 20 is a freehold lot improved by a house and a
shed. The shed fronts Bishop Parade and is adjacent to Lot 1 over which the applicant
holds a permit to occupy. Lot 1 is unallocated State land improved by a boat ramp,
slipway and jetty.
[206] Several owners operated the facility without formal environmental controls for 34
years between 1962 and 1996. After the introduction of the Act, the facility was
identified as an environmentally relevant activity, and in 1996 an environmental
authority issued under the Act.
[207] Over time, a new larger shed on Lot 20 replaced an old one, rails between the slipway
on Lot 1 and into the shed on Lot 20 were removed, and the slipway was improved
with grated drainage, new railing, concreting, fencing and a reoriented winch.
Generally speaking, the type of boat repair and maintenance work has been similar
over the years with evolving work and environmental practices.
[208] An environmental authority continues to govern the facility conducted on both Lot 1
and Lot 20.146 The environmental authority applies subject to conditions under the
Act. By operation of the Act, and successive planning legislation, the environmental
authority continues in force as a development approval under SPA.
[209] Some local residents have made persistent and numerous complaints about the
facility; particularly about the appellant’s use of a slipway to repair, sand, spray,
fibreglass, water-blast and anti-foul boats.
[210] In the wake of previous proceedings, council officers inspected the facility on 13 May
2014. The council decided, through its delegate Craig Manley, to issue the EPO on
143 Exhibit 4, appellant’s plan at [172] – [173]; Affidavit of LJ Abbott 21 July 2015, Doc. 18, at [19(d)].
144 Affidavit of G Galvin 6 March 2017, Doc. 97, pp 20-28; T4-21/35-39; T4-22/4-8.
145 Examples: Affidavit of G Galvin 6 March 2017, Doc. 97, pp 20-28; Affidavit of AW Ross, 6 March
2017, Doc. 22, Exhibit AWR-04, Documents G – I, in proceeding 5102/16; Affidavit of W Henry 28
February 2017, Doc. 12, Exhibit WH-1, in proceeding 5102/16.
146 Loader v Moreton Bay Regional Council [2013] QCA 269.
-- 52 of 55 --
53
31 March 2015 in relation to acoustic amenity, air quality, water quality, and
stormwater and aquatic ecology. The protection order prescribed 57 requirements “to
secure compliance by [the appellant] with the conditions of the Environmental
Authority and with the general environmental duty".
[211] The appellant sought an internal review on the imposition of the protection order, but
it was affirmed. Her subsequent appeal to this court was determined by judgment
delivered on 18 December 2015. I concluded that the appellant breached her general
environmental duty to the same extent that she has breached the EA, in particular:
(a) Schedule A, conditions (A2), (A5) and (A10);
(b) Schedule B, conditions (B1), (B2), (B3) and (B6);
(c) Schedule C, conditions (C1), (C2), (C4) and (C5);
(d) Schedule D, condition (D1);
(e) Schedule E, condition (E1); and
(f) Schedule F, conditions (F1), (F3), and (F4).
[212] I formed the view that the consequential environmental harm and environmental
nuisance resulting from these breaches would continue to occur unless the appellant’s
management practices and the ERA infrastructure is significantly improved.
[213] However, I formed the view that the EPO issued by the council was unnecessarily
restrictive, prescriptive and onerous, with the potential to derogate from the original
grant of the EA. I found the temporal requirements in the EPO both unreasonable and
impractical. Further, the imposition of the EPO would have imposed intolerable
immediate material financial implications associated with the upgrade of the slipway,
acoustic treatments and dust and odour mitigation requirements. In the absence of
detailed costs or other economic evidence, I was left with uncertainty about whether
or not the imposition of the EPO will jeopardise the appellant’s business.
[214] I adopted a course of making an EPO compelling the preparation and implementation
of a site based management plan, which would necessarily but properly confine the
operation of the facility within the scope of the EA
[215] The appellant’s activities and obligations under the EA have been clouded in
significant uncertainty for almost a decade amidst continuing complaints and
litigation. Of most significance was the nature and extent of an appropriate painting
booth and containment facility, about council has not satisfied their onus. Otherwise,
the disputation has now merged in this decision and the preferred appellant’s site
based environmental and stormwater management plan, subject to the modifications
in accordance with this judgment.
[216] It seems to me that for the most part the appellant ought be permitted a reasonable
time to implement her Site Based Environmental Management Plan (as modified),
except where continuing activity will breach the EA as I have found in relation to:
(a) Conducting spray painting activity including anti-foul in the
absence of an approved spray booth pursuant to condition (B5).
-- 53 of 55 --
54
(b) Undertaking any work on boats longer than 40 feet or 12.2 metres
in certain circumstances.
(c) Irrigating any land with holding tank water.
[217] I propose to make an order directing the appellant to stop these activities that will be
a contravention of the Act, and my orders.
Conclusion
[218] For these reasons, I propose to make the following orders:
1. In respect of appeal number 2283 of 2015 I order that the appellant’s revised
Site Based Environmental Management Plan (exhibit 4) is approved subject
to the following changes:
(a) Section 3, ought better identify the noise sensitive receptors.
(b) Paragraphs 134, 135 and 150 must be modified to ensure that no
spray painting activity including anti-foul (delivered by airless,
compressed or other spray air guns) is carried out unless and until
the appellant has an approved spray booth suitable to the task
pursuant to condition (B5).
(c) Paragraphs 172 – 175 ought be modified to expressly exclude all
work on boats longer than 40 feet or 12.2 metres unless the repair
work is limited to spot repairs and then only above the interception
drain (not inundated by tide).
(d) Paragraphs 29(d), 176, and 178 must be modified to two 10,000
litre tank capacity, that is a 10,000 litre settling tank and 10,000
litre storage tank.
(e) Paragraphs 29(g), 57, and 188 conflict with the EA in so far as they
permit irrigation of the holding tank water onto the land, and ought
be deleted.
2. In respect of application number 5102 of 2016 I order on and from 4pm on 14
September 2018 that the appellant be restrained by injunction from:
(a) Conducting spray painting activity including anti-foul (delivered by
airless, compressed or other spray air guns) unless and until the
appellant has an approved spray booth suitable to the task pursuant to
condition (B5).
(b) Undertaking any work on boats longer than 40 feet or 12.2 metres
unless the repair work is limited to spot repairs and then only above the
interception drain (not inundated by tide).
(c) Irrigating any land with holding tank water.
3. I will hear further submissions on the appropriate form of orders and the future
conduct of the proceedings on a date to be fixed.
-- 54 of 55 --
55
DP Morzone QC DCJ
-- 55 of 55 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2018/040