Cherwell Creek Coal Pty Ltd v BHP Queensland Coal Investments Pty Ltd & Ors (No 17) [2018] QLC 45
LAND COURT OF QUEENSLAND
CITATION: Cherwell Creek Coal Pty Ltd v BHP Queensland Coal
Investments Pty Ltd & Ors (No 17) [2018] QLC 45
PARTIES: Cherwell Creek Coal Pty Ltd
(ACN 063 763 002)
(applicant)
v
BHP Queensland Coal Investments Pty Ltd
(ACN 063 763 002)
QCT Resources Pty Ltd
(ACN 010 808 705)
BHP Coal Pty Ltd
(ACN 010 595 721)
Mitsubishi Development Pty Ltd
(ACN 009 779 873)
QCT Investments Pty Ltd
(ACN 010 487 831)
Umal Consolidated Pty Ltd
(ACN 000 767 386)
QCT Mining Pty Ltd
(ACN 010 487 840)
(respondents)
FILE NO: MRA1332-08
DIVISION: General division
PROCEEDING: Request from experts for further information in Court
Managed Expert Evidence (CMEE) process
DELIVERED ON: 3 December 2018
DELIVERED AT: Brisbane
HEARD ON: Heard on the papers; written submissions closed 27
November 2018.
HEARD AT: Brisbane
PRESIDENT: FY Kingham
ORDERS: 1. By 4pm on Monday 7 January 2019, the
respondents must provide the geology and mine
planning experts who made the request for
-- 1 of 9 --
2
information with categories 3, 4, 5, 7 & 8 of the
Additional Mining Information (as described
in the request for information in the email
attached to the CMEE Convenor Report dated
19 November 2018).
2. The costs of and incidental to the expert
witnesses’ request for information are costs in
the cause.
CATCHWORDS: CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – PROCEDURE – whether a
request for information made by expert witnesses
during a meeting of experts in a Court Managed
Expert Evidence (CMEE) process is an “inappropriate
procedure” – where experts have a primary duty to
assist the court – where the court expects the experts
to consider whether they require further information
to prepare their joint report – where the experts must
state in their report that they have made all
appropriate enquiries – where the request was made
and maintained by the experts engaged by both
parties in two disciplines – where the court directed
the party in possession of the information to provide it
to the experts
EVIDENCE – EXPERT EVIDENCE – where the
experts engaged by both parties in two disciplines
made and maintained a request for information during
a meeting of experts – where the information related
to key facts relevant to issues in dispute – where the
experts all asked for the information, although some
placed different weight on information about a
particular topic – where the delay was unlikely to be
significant or to defer the commencement of the trial
– where the court directed the party in possession of
the information to provide it to the experts
Land Court Rules 2000, r 22, r 24, r 24A, r 24C
APPEARANCES: G Gibson QC, with J Chapple and N Loos (instructed
by Holding Redlich Lawyers) for the applicant
S Doyle QC, with A Stumer and F Lubett (instructed
by Allens) for the respondents
-- 2 of 9 --
3
Background
[1] This judgment is about a request for information by geologists and mine planning
experts engaged by the parties to give evidence at trial.1 The request emerged from a
meeting convened by Member Stilgoe, acting in her capacity as the Convenor of the
Court Managed Expert Evidence process for this case.2
The information request
[2] The expert witnesses identified nine categories of information about BMA’s mining
of an area that they described as being “within and adjacent to the MDLA 364 eastern
boundary”.3 They say it will (or may):
1. confirm the size and general location of the coal resource; and
2. provide better information on the extent of oxidised coal in the resource.
[3] The likely extent and quality of the MDLA364 coal resource are key facts for
Cherwell Creek’s claim for loss of the opportunity to commercialise that resource.
Those facts are relevant to a number of issues, including the likelihood that Cherwell
Creek would have developed and operated the mine and the value of its lost
opportunity to do so.
[4] The expert witnesses identified nine categories of information, which the parties have
been referring to as the Additional Mining Information. BMA has already supplied
three categories (1, 2 & 9),4 has advised it does not have category 6, and is unwilling
to provide the remaining categories (3, 4, 5, 7 & 8).
[5] BMA has not disputed the Court’s power to direct it to provide the Additional Mining
Information.5 However, the Convenor can only make directions with the consent of
1 Barry Saunders (CCC) and Kerry Whitby (BMA) – geology; Ken Stapleton (CCC) and Greg Maiden
(BMA) – mine planning.
2 Practice Direction 3 of 2018 – Procedure for Court Managed Expert Evidence.
3 The email is an attachment to the Convenor’s report. In accordance with Practice Direction 3 of 2018,
the Convenor prepared her report in consultation with the parties and filed it when she provided it to
me.
4 It advised the Convenor that it had previously disclosed the information described as categories 1 & 2
to CCC, although it appears that was not conveyed to CCC’s experts.
5 Outline of Submissions for the Respondents: Mining Information Request filed 20 November 2018,
[6]; Land Court Act 2000, s22(3); Cherwell Creek did not address this in its submission.
-- 3 of 9 --
4
all parties.6 After a case management conference about the request,7 and in
consultation with the parties, the Convenor provided a report about the experts’
request and the parties’ responses to it.8 I also allowed the parties to make further
written submissions to me about how the Court should respond to the experts’ request.
The expert evidence process
[6] Before turning to the arguments made in those submissions, I will deal with BMA’s
suggestion the experts’ request involves an “inappropriate process”.9 It submitted the
joint reporting process is not an opportunity for the experts to engage in inquisitorial
fact finding in order to supplement the material on which they prepared detailed
reports. To deal with that submission, I will identify some relevant features of the
Court’s rules and procedures.
[7] Firstly, the rules and procedures of the Court reinforce the duty of the expert witnesses
to assist the Court. That duty overrides any obligation owed to any party to the
proceeding.10
[8] Secondly, the Court recognises an expert may identify further information that would
assist them to fulfil their duty. That is important at each stage of preparation of expert
evidence. However, it has particular significance for the meeting of experts, who must
discuss and attempt to reach agreement about their evidence in relation to an issue in
dispute as it relates to their area of expertise.11
[9] In their meeting process, the experts are not constrained by the information provided
by the party who engaged them or by the opinions expressed in their initial report,
however detailed. After discussions with a peer, an expert may qualify, alter or even
abandon an opinion earlier expressed. The experts may identify that they each formed
their opinions on different information. Alternatively, they may identify further
6 Practice Direction 3 of 2018 – Procedure for Court Managed Expert Evidence, [19](b)(iii).
7 Mr Thatcher, a mine planner engaged by Cherwell Creek, also attended the Case Management
Conference, with the four experts who made the request, but he is not one of the experts requesting
the information.
8 As required by Practice Direction 3 of 2018– Procedure for Court Managed Expert Evidence, [22],
[23].
9 Outline of Submissions for the Respondents: Mining Information Request filed 20 November 2018,
8.
10 Land Court Rules 2000, r 24C.
11 Land Court Rules 2000, r 22.
-- 4 of 9 --
5
information, which neither has access to, that would assist them to finalise their
report.
[10] Although a party engages an expert to give evidence in their case, the role of an expert
witness is to assist the Court on matters within their area of expertise, not to advocate
for the client. The Court will obtain limited assistance from an expert whose opinion
does not address relevant and available information.
[11] The information on which the experts base their opinions is, therefore, fundamental
to the discussion about their evidence. The following requirements for the meeting
and reporting process reinforce the importance of the experts having access to
sufficient information:
1. Before a meeting of experts, the parties must give the expert witnesses enough
information and opportunity to adequately investigate the facts in relation to
the issues in dispute.12
2. During their meeting, the expert witnesses may ask all parties to respond to
an inquiry made jointly of all parties.13 The Court expects the experts to
consider this in their discussions and to make a request if they think it is
necessary to do so.14 A meeting of experts may be adjourned so further
information can be obtained.15
3. The experts must confirm in their statements of evidence, which includes a
joint report,16 that they have “made all enquiries considered appropriate”.17
[12] The request by the experts is not an “inappropriate process”; rather, it conforms to the
Court’s rules and procedures, which require the experts to be properly informed in
developing and articulating their opinions.
[13] Turning to the merits of the request, the parties have made arguments about the utility
of the information to the experts’ reports and the consequential delay in finalising
them. BMA submits the Court should not direct it to provide information only
12 Land Court Rules 2000, r 24.
13 Land Court Rules 2000, r 24A(2).
14 Guidelines for Expert Evidence in the Land Court issued 30 April 2018, [9(f)], [43].
15 Guidelines for Expert Evidence in the Land Court issued 30 April 2018, [43] (a)-(c).
16 Land Court Rules 2000, r 24(2).
17 Land Court Rules 2000, r 24(3)(b).
-- 5 of 9 --
6
marginally relevant. Providing the information will delay reports in an already very
lengthy pre-trial process. CCC submitted it would be unusual for a court to refuse a
unanimous request for relevant information made by expert witnesses engaged by
both parties. Although there will be some delay, that is not a principled reason for
declining the request.
The utility of the information
[14] BMA raised a number of questions about the utility of the information.
[15] Firstly, the experts say the information would be “nice” but “not critical”. This relates
to categories 1 to 4. BMA has already provided categories 1 & 2.
[16] The geology experts doubt the information they have requested will provide
unexpected results and expect it will confirm their assumptions and views, at least as
to the size and location of the resource. BMA submitted providing the information
would, therefore, “have the effect of satisfying the intellectual curiosity of the
geologists, but will make no difference to the outcome of the case, unless there is an
‘unexpected result’.”18
[17] The experts will give evidence on key facts derived from modelling based on limited
drilling information on and adjacent to the area of former MDLA364. BMA
complained that it has already significantly supplemented the information otherwise
available to Cherwell Creek because of its inadequate exploration of the area. That
may be so, but the Court’s concern is about the evidence on which it must determine
the issues in dispute.
[18] Information about the results of mining in and adjacent to the area will supplement
the information base for the experts’ modelling. That is not merely a matter of
intellectual curiosity for the experts. If it confirms their current modelling, the
information has value for the Court as it will increase the experts’ certainty in their
opinions. If the information produces an unexpected result, its value is in allowing
the experts to refine their opinions. In either case, the requested information will
provide the experts, and the Court, with increased confidence in their opinions on key
facts.
18 Outline of Submissions for the Respondents: Mining Information Request filed 20 November 2018,
[45].
-- 6 of 9 --
7
[19] Secondly, BMA raised the utility of providing the information in categories 3, 4, 5, 7
& 8, given the experts’ differing views about the importance of knowing the extent
of oxidised coal. Further, in the absence of the category 6 information, BMA
questioned whether the experts would be able to determine its extent.
[20] As I understand it, oxidisation relates to coal quality and, therefore, the value of the
MDLA coal resource. The mine planning experts place different weight on this
consideration. Cherwell Creek’s expert says it very important. BMA’s expert does
not agree it is very important, because the geologists now agree about the ash content
of the coal. However, both geologists consider the information would be useful, so
there is no dispute between them about that. Even though there is a difference about
the weight they place on this information, the experts all joined in the request,
including BMA’s mine planning expert who also said he would like to have it.
[21] The experts said that, in the absence of category 6 information, they were “less
confident” the remaining information would assist them in assessing the extent of the
oxidised coal. However, they did not abandon their request. I can only infer from that
there is some real utility in allowing the experts to consider the remaining
information.
[22] Finally, BMA asserted the mining identified by the experts has only taken place on
its mining lease adjacent to the eastern boundary of the former MDLA 364, not within
it. The geologists appear to be in dispute about the precise boundaries of the
MDLA364 area.19 I am not in any position to determine this question, nor to consider
its relevance to any issue in the proceedings.
[23] Assuming all the information relates to mining outside the MDLA364 area, BMA
submitted its only relevance is to provide a basis for drawing inferences about the
MDLA364 coal resource. Unless MDLA364 is mined, the experts’ opinion is,
necessarily, based on drawing inferences. BMA has already provided, and the experts
have already drawn inferences from, the results of drilling in the area adjacent to
MDLA364.
19 Supplementary Joint Expert Report of Mr Saunders and Mr Whitby filed 5 March 2014, section 2.3
and figure 2.3.
-- 7 of 9 --
8
[24] The location of the mining is not a reason to refuse the experts’ request. If the precise
location of mining is significant to the experts’ opinions, I expect them to explain that
in their reports. In any case, the parties can probe the question when the experts give
their evidence at trial.
[25] While the Court expects expert witnesses to co-operate about requests for
information,20 if there is a dispute between them about whether the request is relevant
or necessary, they can note that in the request.21 Here, the experts have joined in and
maintained a request for information, knowing category 6 information is not
available, and some or all of the mining is outside the former MDLA364. In those
circumstances, I am satisfied the experts consider there is some real utility in
considering the information they have requested.
Delay
[26] The time taken to respond to the experts’ request has already delayed them from
finalising their reports. It will take BMA a month to provide the information. There
will be consequential delays for the joint expert reports of the geologists, mine
planners and, possibly, the coal quality experts.
[27] Any delay in this case is regrettable. However, it is likely to be minimal. Once they
have the information, the experts do not expect the delays to be significant, unless the
information produces an unexpected result. If there is an unexpected result, a longer
delay is justified because the opinions relate to key facts for the claim.
[28] Further, the delay in finalising these reports is unlikely to delay the commencement
of the trial. The CMEE process has just commenced for the Caval Ridge mine
allegations in BMA’s defence. The meeting of the mine planners for those allegations
awaits a report from BMA’s expert, due by 30 April 2019. The CMEE process in this
case cannot conclude before that joint expert report is filed.
[29] Although I have reserved dates in my calendar from late September 2019, if the case
is ready for trial earlier, I will do what I can to accommodate an earlier start. However,
I am unlikely to make a firm trial listing until I have all the joint expert reports.
20 Guidelines for Expert Evidence in the Land Court issued 30 April 2018, [46].
21 Guidelines for Expert Evidence in the Land Court issued 30 April 2018, [49].
-- 8 of 9 --
9
[30] In those circumstances, delay is not a reason to refuse the experts’ request.
[31] Before concluding, in a letter from its solicitors to the CMEE Convenor, BMA
asserted the commercial sensitivity of the information. If the parties cannot agree
beforehand about the need for or form of arrangements to preserve the confidentiality
of the information, I will make directions at the next review, tentatively listed for 14
December 2018.
Orders
[32] I make the following orders:
1. By 4pm on Monday 7 January 2019, the respondents must provide the geology
and mine planning experts who made the request for information with
categories 3, 4, 5, 7 & 8 of the Additional Mining Information (as described
in the request for information in the email attached to the CMEE Convenor
Report dated 19 November 2018).
2. The costs of and incidental to the expert witnesses’ request for information
are costs in the cause.
FY KINGHAM
PRESIDENT OF THE LAND COURT
-- 9 of 9 --
Official source: https://www.sclqld.org.au/caselaw/QLC/2018/045