DTM Constructions Pty Ltd trading as QA Developments v Poole [2017] QSC 246
SUPREME COURT OF QUEENSLAND
CITATION: DTM Constructions Pty Ltd trading as QA Developments v
Poole & Anor [2017] QSC 246
PARTIES: DTM CONSTRUCTIONS PTY LTD ACN 104 066 462
trading as QA DEVELOPMENTS
(plaintiff)
v
JUSTIN REID POOLE
(first defendant)
DARRYL ROY HOPKINS
(second defendant)
FILE NO/S: No 12855 of 2015
DIVISION: Trial Division
PROCEEDING: Trial – Orders
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 1 November 2017
DELIVERED AT: Brisbane
HEARING DATE: Written submissions received 10, 12 October 2017
JUDGE: Ann Lyons SJA
ORDERS:
1. The First Defendant pay to the Plaintiff the
amount of $1,009,527.13 for the claim together
with interest in the amount of $136,414.12 and
the First Defendant pay the Plaintiff’s costs of
the proceeding to be assessed on an indemnity
basis.
2. The Second Defendant pay to the Plaintiff the
amount of $837,739.13 for the claim together
with interest in the amount of $113,200.95 and
the Second Defendant pay the Plaintiff’s costs
of the proceeding to be assessed on an
indemnity basis.
CATCHWORDS: INTEREST – RECOVERABILITY OF INTEREST – IN
GENERAL – where damages were awarded to the plaintiff for
the defendants’ breaches under general law and under the
Corporations Act 2001 (Cth) – where the plaintiff submits
interest should accrue on damages from date breaches occurred
- where the defendants submit that interest on damages
-- 1 of 4 --
awarded should accrue at the point proceedings were
commenced – whether interest should accrue from date of
breaches or at point proceedings commenced
Civil Proceedings Act 2011 (Qld) s 58
Butler & Ors v The State of Queensland [2014] QSC 19
Cashmere Bay Pty Ltd v Hastings Deering (Australia) Ltd (No.
2) [2011] QSC 134
GEJ & MA Geldard Pty Ltd v Mobbs & Ors (No 3) [2011]
QSC 297
MBP (SA) Pty v Gogic (1991) 98 ALR 193
COUNSEL: P W Hackett with P G Jeffery for the plaintiff
M Lawrence for the first and second defendants
SOLICITORS: Evans Lawyers for the plaintiff
MDR Lawyers for the first and second defendants
Background
[1] On 28 September 2017 I published my reasons in this matter and found that the first and
second defendants had breached some of their duties as a director and officer of the
plaintiff company under the general law and under the Corporations Act 2001 (Cth) (the
Act). Those breaches occurred in circumstances where as a director and officer of the
plaintiff company, the first and second defendants were found to have diverted
opportunities for the plaintiff company to enter into a number of building and
construction contracts. My findings can be summarised as follows:
Contract subject of
claim
Date of
breach
First Defendant Second Defendant
21 Blocks Coronation Hill 31/12/2014 $210,000.00 $210,000.00
19 Hoffman Way 11/05/2015 $35,327.84 $35,327.84
333 Riding Rd 25/05/2015 $159,709.24 $159,709.24
Lot 38 Birdwing Cr 01/06/2015 $31,905.40 $31,905.40
75 Springwood Rd 04/06/2015 $259,472.77 $259,472.77
Lot 2 Hillcrest 04/08/2015 $35,524.74 $35,524.74
Lot 3 Hillcrest 17/06/2015 $35,266.38 $35,266.38
Lot 8 Hillcrest 13/07/2015 $35,266.38 $35,266.38
Lot 21 Hillcrest 11/06/2015 $35,266.38 $35,266.38
29 Hunters St 24/08/2015 $35,327.84 N/A
Total damages $1,009,527.13 $837,739.13
[2] By those reasons I also made the following Orders:
1. The parties are directed to provide short minutes of orders in accordance with
these reasons by 12 October 2017.
-- 2 of 4 --
2. The parties are directed to provide short submissions as to the calculation of
interest and as to costs by 12 October 2017.
The parties’ submissions
[3] Short minutes of orders together with submissions were received from counsel for the
plaintiff and defendants on 10 and 12 October 2017 respectively. The parties agree that
the total amount of damages owed to the plaintiff by each defendant for the breaches
found is as appears in the table above. The parties also agree that, pursuant to r 360(1) of
the Uniform Civil Procedure Rules 1999 (Qld) (UCPR), the defendants are to pay the
plaintiff’s costs calculated on the indemnity basis given that the plaintiff obtained a
judgment no less favourable than offers made to each defendant.
[4] The parties disagree however on the point of time at which interest should accrue on
damages awarded. Counsel for the plaintiff submits that interest in respect of each claim
should accrue from the date of breach to the date of judgment. Counsel for the defendants
submits that it is not appropriate for interest to be calculated from the date of each breach,
given that there is no evidence that the plaintiff would have received any money for the
contracts on those dates. Rather, counsel for the defendants argue that because payments
for construction contracts are typically made in stages, the plaintiff’s losses for each
diverted contract were staggered and on this basis, submits that interest on each claim
should be calculated from the date proceedings were commenced.
[5] The rate of interest to be awarded is not contested as between the parties.
At what point should interest accrue on damages awarded?
[6] Section 58(3) of the Civil Proceedings Act 2011 (Qld) provides that the Court “may order
that there be included in the amount for which judgment is given interest at the rate the
court considers appropriate for all or part of the amount and for all or part of the period
between the date when the cause of action arose and the date of judgment”.
[7] The High Court in MBP (SA) Pty v Gogic1stated that “The function of an award of interest
is to compensate a plaintiff for the loss or detriment which he or she has suffered by being
kept out of his or money during the relevant period”. In determining the correct point at
which interest should accrue, recent decisions of this court have considered the nature of
the damages awarded to the successful party2 and the date at which the relevant loss was
sustained.3 There can be no doubt that that Courts have adopted a flexible approach given
the wide discretion afforded by r 58(3).
[8] Here, the plaintiff was awarded damages to compensate it for lost opportunities to enter
into building and construction contracts that were diverted from it to third parties by the
defendants, in breach of their duties. Damages were assessed with reference to the loss
of potential profit to the plaintiff company, which was calculated according to the
contract price for each diverted opportunity.
1 (1991) 98 ALR 193.
2 See Cashmere Bay Pty Ltd v Hastings Deering (Australia) Ltd (No. 2) [2011] QSC 134; Butler & Ors v
The State of Queensland [2014] QSC 19.
3 See GEJ & MA Geldard Pty Ltd v Mobbs & Ors (No 3) [2011] QSC 297.
-- 3 of 4 --
[9] The evidence provided at trial4 is consistent with the defendants’ submission that
payment for these contracts would have been received in stages and as such, had the
plaintiff had the opportunity to enter into each of the diverted contracts, it would not have
received all monies owing under the contracts on the date the breaches occurred.
[10] As noted above the first breach was 31 December 2014 and the last breach was 24 August
2015. These proceedings were commenced on 18 December 2015. I note that in the
decision of Cashmere Bay Pty Ltd v Hastings Deering (Australia) Ltd (No. 2) it was
common that “the sensible approach was to allow interest to run from the midpoint of the
period”.5 I consider that a similar approach should be adopted here. I also consider that
the mid-point should be 30 June 2015.
[11] Calculated at the default rate, the interest payable by the first defendant on the amount of
$1,009,527.13 for the claim from 30 June 2015 to 1 November 2017 is $136,414.12.
[12] Calculated at the default rate, the interest payable by the second defendant on the amount
of $837,739.13 for the claim from 30 June 2015 to 1 November 2017 is $113,200.95.
[13] I therefore make Orders in the following terms:
1. The First Defendant pay to the Plaintiff the amount of $1,009,527.13 for the
claim together with interest in the amount of $136,414.12 and the First
Defendant pay the Plaintiff’s costs of the proceeding to be assessed on an
indemnity basis.
2. The Second Defendant pay to the Plaintiff the amount of $837,739.13 for the
claim together with interest in the amount of $113,200.95 and the Second
Defendant pay the Plaintiff’s costs of the proceeding to be assessed on an
indemnity basis.
4 See for example DTM Constructions P/L trading as QA Developments v Poole & Anor [2017]
QSC 210 at [179]-[182].
5 At [26].
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2017/246