Casco Civil Construction Pty Ltd v Yeo & Co Pty Ltd (Administrators Appointed) [2017] QSC 226
SUPREME COURT OF QUEENSLAND
CITATION: Casco Civil Construction Pty Ltd v Yeo & Co Pty Ltd
(Administrators Appointed) & Ors [2017] QSC 226
PARTIES: CASCO CIVIL CONSTRUCTIONS PTY LTD ACN 103 558
774
(applicant)
v
YEO & CO PTY LTD (ADMINISTRATORS APPOINTED)
ACN 071 325 427
(first respondent)
CPB CONTRACTORS PTY LTD ACN 000 893 667
(second respondent)
F. K. GARDNER & SONS PTY LTD ACN 010 136 053
(third respondent)
FILE NO: BS 9228 of 2017
DIVISION: Trial
PROCEEDING: Application
DELIVERED ON: 27 September 2017 (ex tempore)
DELIVERED AT: Brisbane
HEARING DATE:
JUDGE:
27 September 2017
Atkinson J
ORDERS: 1. Pursuant to section 440D of the Corporations Act 2001
(Cth), the Applicant has leave nunc pro tunc to
commence and proceed with District Court proceeding
2782/16 against the First Respondent in respect of its
claimed debt and charge claimed under the
Subcontractors’ Charges Act 1974 (QLD).
2. Pursuant to section 440D of the Corporations Act 2001
(Cth), the Applicant has leave nunc pro tunc to
commence and proceed with Magistrate Court
proceeding 0052825/16 against the First Respondent in
respect of its claimed debt and charge claimed under
the Subcontractors’ Charges Act 1974 (QLD).
3. Further to Orders 1 and 2, to the extent necessary the
First Respondent has leave pursuant to s 444E(3)(c) of
the Corporations Act 2001 (Cth).
4. No order as to costs.
-- 1 of 7 --
2
CATCHWORDS: CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES –
BUILDING ENGINEERING AND RELATED CONTRACTS
– REMUNERATION – SUBCONTRACTORS’ CHARGES
ACT (QLD) – where the first respondent was a company under
administration – where the applicant was a secured creditor by
virtue of s 5 of the Subcontractors’ Charges Act 1974 – where
the applicant sought an order pursuant to s 440D of the
Corporations Act 2001 for leave, nunc pro tunc, to commence
and proceed with District Court and Magistrates Court
proceedings against the first respondent in respect of its claimed
debt and charge claimed under the Subcontractors’ Charges Act
1974 – whether leave should be granted
Corporations Act 2001 (Cth), s 440D, s 444B, s 444D, s 444E, s
444F
Subcontractors’ Charges Act 1974 (Qld), s 5, s 10, s 11
BBC Hardware Limited v GT Homes Pty Ltd [1997] 2 Qd R 123,
cited
Belmadar Constructions Pty Ltd v Environmental Solutions
International Ltd [2005] VSC 24, cited
Ex Parte Pavex Constructions (1979) Qd R 318, cited
Foxcroft v The Ink Group Pty Ltd (1994) 15 ACSR 203, cited
Geoff Sharpe Pty Ltd v M&E Fitzgerald Holdings Pty Ltd (No.
2) [2010] QSC 231, cited
Modcol v National Buildplan Group [2013] NSWSC 380, cited
Re QMT Constructions Pty Ltd [2000] 1 Qd R 284, followed
Re Stockport (NQ) Pty Ltd [2003] 127 FCR 291, cited
Sun Engineering (Qld) Pty Ltd v Dynac Pty Ltd (in liq) [2000]
QSC 213, cited
COUNSEL: E V Mastyuk (sol) for the applicant
P Jeffery for the respondents
SOLICITORS: Rostron Carlyle Lawyers for the applicant
JHK Legal for the respondents
[1] This is a hearing of two matters. This judgment will deal with both matters, but will be
published, of course, in each matter. The first involves Civcrush Pty Ltd (“Civcrush”),
as applicant, the first respondent is Yeo & Co Pty Ltd (Administrators Appointed), and
the second respondent is CPB Contractors Pty Ltd. In the second originating application,
the applicant is Casco Civil Construction Pty Ltd (“Casco”), the first respondent Yeo &
Co Pty Ltd (Administrators Appointed), the second respondent CPB Contractors Pty Ltd,
and the third respondent is FK Gardiner & Sons Pty Ltd.
[2] An application is made by the applicant in each matter under section 440D of the
Corporations Act 2001 for leave to proceed against the first respondent, Yeo & Co Pty
Ltd (Administrators Appointed). During the hearing, it was suggested by the respondent
that leave might need to be granted under section 444E and the applicants applied, should
it be necessary, to amend their application to include the grant of leave under that section.
-- 2 of 7 --
3
It is not suggested that there would be any prejudice to the first respondent by that
application to amend being granted, and should it be necessary I give leave for the
applicant to so amend its application. It is not suggested that any different matters would
need to be considered.
[3] In the matter where the applicant is Civcrush, an order was sought that, pursuant to
section 440D of the Corporations Act, the applicant have leave, nunc pro tunc, to
commence and proceed with District Court proceeding 2781 of 2016 against the first and
second respondents in respect of its claimed debt and charge claimed under the
Subcontractors’ Charges Act 1974. It should be noted that no leave is required for the
applicant to proceed against the second respondent. It is not in liquidation or
administration and the applicant is entitled to proceed against it without leave.
[4] In the matter where Casco is the applicant, the orders sought are that:
(1) pursuant to section 440D of the Corporations Act 2001, the applicant have leave,
nunc pro tunc, to commence and proceed with District Court proceeding 2782 of
2016 against the first and second respondents, in respect of its claimed debt and
charge claimed under the Subcontractors’ Charges Act 1974; and
(2) pursuant to section 440D of the Corporations Act 2001, the applicant have leave,
nunc pro tunc, to commence and proceed with Magistrates Court proceeding
0052825 of 2016 against the first and third respondents in respect of its claimed debt
and charge claimed under the Subcontractors’ Charges Act.
[5] Again, I note that it is not necessary for leave to be granted with regard to the applicant
proceeding in those proceedings against the second and third respondents. So the only
question is whether or not leave should be granted to proceed against the first respondent.
[6] When a company is under administration, as is the first respondent, the ordinary rule is
that creditors’ rights, particularly those of unsecured creditors, are dealt with under the
administration. There is also some effect on certain types of other third parties who have
property rights. Those matters are set out in sections 444D and 440B of the Corporations
Act. Subsection 444D(2) of the Corporations Act provides that subsection (1) does not
prevent a secured creditor from realising or otherwise dealing with the security interest
except so far as:
(a) the deed so provides in relation to a secured creditor who voted in favour of
the resolution of creditors because which the company executed the deed; or
(b) the Court orders under subsection 444F(2).
[7] Section 444F provides that when a company is under administration, the Court may order
a creditor of the company not to realise or otherwise deal with the security interest except
as permitted by the order. There are certain matters to which a Court must have regard
if it is to limit the rights of the secured creditor. No application has been made to limit
the rights of the secured creditor, so I need not consider that section any further.
[8] The matters referred to in subsection 444D(2)(a) were dealt with in the deed in this way:
the applicant, who is a secured creditor by virtue of the Subcontractors’ Charges Act, did
-- 3 of 7 --
4
not attend the meeting, did not vote and so was governed by clause 5.5 of the deed which
provides, under subsection (a), subclause (a):
Nothing in this deed shall affect, in any way, the rights of secured creditors who
did not vote in favour of the resolution to execute the deed in relation to the
enforcement of their securities during the deed period or their interest in the
assets of the company over which they have security.
[9] It appears there are only two other secured creditors of the company, the first respondent,
are banks or entities associated with banks.
[10] The applicants are secured creditors by virtue of statute. The statute involved is the
Subcontractors’ Charges Act 1974, a Queensland Act which in common with similar but
not exactly the same legislative provisions in other States and jurisdictions is said by its
long title to make better provision for securing the payment of money payable to
subcontractors and for other purposes. It is notorious that in the building industry, prior
to that Act, subcontractors were often left as the persons to whom moneys were owed
and who could not secure payment, particularly when the contractor, as is the case here,
went into administration or liquidation.
[11] The Subcontractors’ Charges Act gives a right to a subcontractor to make a claim against
what is therein referred to as the employer, that is, the person above the contractor who
had contracted with the contractor for the performance of work in respect of land or a
building. Subsection 5(1) of the Subcontractors’ Charges Act provides in those
circumstances:
Every subcontractor of the contractor is entitled to a charge on the money
payable to the contractor or a superior contractor under the contractor’s, or
superior contractor’s, contract or subcontract.
[12] That charge, of course, created security which gives the subcontractor a secured interest.
Section 5(2) provides that:
The charge of a subcontractor secures payment in accordance with the
subcontract of all money that is payable or is to become payable to the
subcontractor for work done by the subcontractor under the subcontract.
[13] Various means of enforcing such a secured interest or charge are set out in the
Subcontractors’ Charges Act. Section 10 provides that:
A subcontractor who intends to claim a charge on money payable under the
contract to the subcontractor’s contractor, or to a superior contractor, must
give notice to the employer or superior subcontractor by whom the money is
payable specifying the amount and particulars that the claim certified,
prescribed by a qualified person and stating that the subcontractor requires
the employer, or superior contractor, as the case may be, to take the necessary
steps to see that it is paid or secured to the subcontractor.
[14] This section, gives rights to the subcontractor against an employer with whom it is not
itself in a contractual relationship. The consequences of notice of a claim of charge are
set out in section 11. It provides that:
-- 4 of 7 --
5
If a notice of claim of charge is given pursuant to section 10, the person to whom
it is given must retain, until the Court in which the claim is heard directs to
whom and in what manner the same is to be paid, a sufficient part of the money
that is or is to become payable by the person under a contract to satisfy the
claim.
[15] Subsection 11(3) provides that within 14 days after the notice of the claim of charge is
given to the contractor to whom the money is payable, the contractor must give to the
employer or superior subcontractor by whom the money is payable, and to the
subcontractor giving notice of the claim of charge, a notice in the approved form that the
contractor either accepts liability to pay the amount claimed; or disputes the claim; or
accepts liability to pay the amount stated in the contractor’s notice, but otherwise disputes
the claim.
[16] No such notice has been given by the contractor in this case, although I was informed in
Court that the contractor does wish to dispute all or part of the claim made by the
subcontractor and, indeed, may well counterclaim.
[17] Subsections 11(5) and (6) provide that:
(5) An employer or superior contractor may, at any time after notice of claim of
charge has been given to the employer or superior contractor, pay into Court
the amount that the employer or superior contractor is required to retain under
this section.
(6) A payment made pursuant to this section discharges the employer or
superior contractor, as the case may be, of all further liability in respect of the
amount paid and of the costs of any proceeding in relation to the amount paid.
[18] Importantly, under subsection 11(7), money paid into Court under section 11 may be paid
out only under an order of the Court.
[19] That is important in this case because proceedings have, in fact, been started in the
District Court, those proceedings for which leave is now sought nunc pro tunc, and all
the moneys, said to be owing, have been paid into Court by the employer or superior
contractor, except with regard to the Magistrates Court case. Accordingly, those moneys
may only be paid out of Court under an order of the Court. Importantly, also, under
section 15 of the Subcontractors’ Charges Act, a person, such as the applicant in the case,
who has made a claim of charge, must commence proceedings after a notice of claim of
charge has been given. If it does not, the claim is extinguished.
[20] So important rights are given to subcontractors by the Subcontractors’ Charges Act 1974,
which makes a subcontractor, if they make an appropriate claim, a secured creditor who
is obliged to bring proceedings to maintain that security. As I have said, the applicant
may proceed against all of the current defendants in the District Court and Magistrate
Court proceedings without leave, apart from the first defendant in those proceedings, the
company under administration, for which leave is now sought.
[21] Essentially, the argument put against leave being granted is that when a company is under
administration, all debts should be dealt with by the administrator and frozen while the
administrator does his or her job to try to get the company back on foot. The protection
-- 5 of 7 --
6
of the company’s property, when it is under external administration, is provided for under
the Corporations Act.
[22] However, this case has some rather different qualities. In this case, the applicant is
required to commence proceedings to protect its secured rights and it would be a severe
curtailment of a subcontractor’s rights, given to it by legislation, to prevent it from doing
so or not allow it to do so and, therefore, to turn what was a secured interest into an
unsecured interest and make it an unsecured creditor, which would be completely
contrary to the purposes of the Subcontractors’ Charges Act.
[23] Further, the moneys in dispute have been paid into Court by the employer. The company
under administration has no access to those moneys, so it is not as if the applicant is not
given leave, those moneys would go to the first respondent, those moneys are either, at
present, available for the applicant subcontractor or they belong to the employer and only
by Court order can those moneys be paid out of Court. In my view, the orderly
administration of the company under administration requires, and, indeed, so much was,
in effect, conceded by the company, that it be a party to the proceedings in the District
Court and the Magistrates Court so that it can put its case as to why those moneys, that
have been paid into Court, should or should not be paid to the applicant and, so far as the
Magistrates Court is concerned, why the employer or head contractor should not pay
moneys to the subcontractor rather than to the contractor.
[24] I am fortified in that view by a number of cases under Queensland legislation. There are
some cases under interstate legislation which might suggest a different result but that
legislation is different and I prefer to be guided by the cases which have previously been
decided in Queensland, which are all one way. I refer, in particular, to a decision of
Wilson J in Re QMT Constructions Pty Ltd [2000] 1 Qd R 284 where her Honour dealt
with an application for leave, nunc pro tunc, for a subcontractor to bring proceedings
against a company that was subject to a deed of company arrangement. In that decision,
her Honour followed a decision of this Court, Ex Parte Pavex Constructions (1979) Qd
R 318, the only distinction being that in the earlier case the company was in liquidation,
but in QMT Constructions, as in this case, the company was under administration.
[25] I see no reason at all to distinguish the decision reached by Wilson J in QMT
Constructions and intend to follow it. It should be noted that it was followed by
Mansfield J in the Federal Court in Re Stockport (NQ) Pty Ltd [2003] 127 FCR 291 where
his Honour was considering the Queensland legislation. It is also consistent with the
decision of Wilson J in Geoff Sharpe Pty Ltd v M&E Fitzgerald Holdings Pty Ltd (No.
2) [2010] QSC 231 where, again, the first defendant was placed in voluntary
administration. In that case, her Honour referred to a decision of Thomas J, as his
Honour then was, in BBC Hardware Limited v GT Homes Pty Ltd [1997] 2 Qd R 123 at
126 to 127 where his Honour acknowledged that different considerations apply according
to whether the plaintiff is a secured or an unsecured creditor. He said that in
circumstances where the plaintiff is an unsecured creditor in most cases leave would tend
to interfere with the orderly disposition and control of unsecured creditors. But,
conversely, when the plaintiff is a secured creditor the rights of the plaintiff generally
stand outside those to be administered with respect to the unsecured creditors.
[26] It is not necessary for me to refer to other cases, but I note also the decision of Holmes J,
as her Honour then was, in Sun Engineering (Qld) Pty Ltd v Dynac Pty Ltd (in liq) [2000]
QSC 213.
-- 6 of 7 --
7
[27] I have had careful regard to the decisions, to which I was referred by the respondent. In
particular, the ex tempore judgment of McDougall J in Modcol v National Buildplan
Group [2013] NSWSC 380, but it can be seen from the body of that judgment that it was
dealing with legislation that is demonstrably different from the Subcontractors’ Charges
Act, which I have had to consider. It is significant that his Honour said at paragraph 42:
Clearly, a payment which would have the effect of giving a significant
advantage to one unsecured creditor over others would not be consistent with
the scheme of the Act for winding-up on insolvency.
[28] That is true, but it does not apply to this case. I have also had regard to the decision in
the Victorian Supreme Court of Byrne J in Belmadar Constructions Pty Ltd v
Environmental Solutions International Ltd [2005] VSC 24 but, again, that is under a
Victorian Act which apparently was based on the New South Wales Act and is not
decisive in this case.
[29] In Foxcroft v The Ink Group Pty Ltd (1994) 15 ACSR 203, Young J propounded what
might be considered – or what had been considered in later cases – controversial views
about administration About which it is not necessary for me to form a considered view.
He may well be right. But that case dealt with unsecured creditors and not as we are
dealing with here, a subcontractor who has become a secured creditor because of a statute
passed for the purpose of protecting interests of subcontractors by making them secured
creditors but requiring them to commence litigation to protect their interests, as the
applicant has done in these cases.
[30] Accordingly, having regard to all of the circumstances, I grant leave for the applicant in
each case to commence and continue proceedings against the first respondent pursuant
to section 440D of the Corporations Act 2001 and, to the extent necessary, pursuant to
section 444E.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2017/226