Broadbeach Building Pty Ltd v Dennis Said t/as Joinery and Granite Installations [2017] QCAT 410
CITATION: Broadbeach Building Pty Ltd v Dennis Said
t/as Joinery and Granite Installations [2017]
QCAT 410
PARTIES: Broadbeach Building Pty Ltd
(Applicant)
v
Dennis Said t/as Joinery and Granite
Installations
(Respondent)
APPLICATION NUMBER: BDL320-16
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Holzberger
DELIVERED ON: 1 December 2017
DELIVERED AT: Brisbane
ORDERS MADE: 1. Dennis Said t/as Joinery and Granite
Installations pay to Broadbeach Building
Pty Ltd the sum of $30,642.51 by 4:00pm
on 15 December 2017.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN
STATE AND TERRITORY COURTS –
ENDING PROCEEDINGS EARLY – DEFAULT
JUDGMENT – JUDGMENT IN DEFAULT OF
OTHER REQUIRED STEP – where applicant
applied for default judgment following the
respondent’s repeated failure to comply with
directions of the tribunal
CONTRACTS – BUILDING, ENGINEERING
AND RELATED CONTRACTS –
PERFORMANCE OF WORK – REMEDIES
FOR BREACH OF CONTRACT – DAMAGES –
where domestic building dispute – where
unliquidated damages claim – calculation of
damages – where claim for delay costs
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
-- 1 of 3 --
2
REASONS FOR DECISION
[1] Broadbeach Building Pty Ltd made an application for commercial building
dispute to the Tribunal on 13 December 2016 for unliquidated damages for
breach of contract by Dennis Said trading as Joinery and Granite
Installations. Mr Said failed to supply and install a kitchen in residential
premises being refurbished by Broadbeach Building Pty Ltd at unit 2,
Platinum on the Beach, Surfers Paradise.
[2] On 17 January 2017, the Tribunal directed that the application proceed as
an application for domestic building dispute.
[3] Mr Said has failed to comply with other directions issued by the Tribunal on
17 January 2017, 24 March 2017, 15 May 2017 and 14 June 2017.
[4] Broadbeach Building Pty Ltd requests a decision by default. That request
is supported by an affidavit of service filed on 21 March 2017 and a
statement of Simon Barlow, the sole director of Broadbeach Building Pty
Ltd, signed by him and filed on 13 July 2017.
[5] Broadbeach Building Pty Ltd claimed the sum of $50,000 plus interest and
costs particularised as follows:
a) Replacement kitchen $32,523.51
b) Delay cost $26,822.68
[6] That amount was reduced by deducting the sum of $2,196.70, being the
amount unpaid under the contract between Broadbeach Building Pty Ltd
and Mr Said and further reducing the delay cost component to reduce the
total claim to fit within the $50,000 limit for commercial disputes without
consent. There is no similar restriction for domestic building disputes.
[7] I am satisfied that the application has been served in accordance with
QCAT practice direction 8 of 2009 on 22 February 2007 by delivering it
personally to someone, apparently an adult, at 10 Frascati Street, Mermaid
Waters.1
[8] I make the following findings of fact:
a) Broadbeach Building Pty Ltd and Dennis Said entered a contract to
build a replacement kitchen on 15 October 2015 for the price of
$21,967;
b) Broadbeach Building Pty Ltd has paid Dennis Said a sum of $19,770
for those works;
1 Affidavit of service, Part B3.
-- 2 of 3 --
3
c) Dennis Said has breached the contract by failing to supply and install
a kitchen; and
d) Broadbeach Building Pty Ltd has suffered a loss as a result of that
breach.
[9] I am satisfied that the cost of replacing the kitchen is a reasonable and
foreseeable consequence of Mr Said’s breach and that the amount claimed
is reasonable in all the circumstances.
[10] I am not similarly satisfied in respect of the claim for delay costs. The
contract between Broadbeach Building Pty Ltd and the owners of the unit
specified liquidated damages at $50 per day or $350 per week. The amount
claimed, approximately three times that amount, was apparently negotiated
after the parties to these proceedings contracted and could hardly be said
to be a foreseeable consequence of breach.
[11] I am also not satisfied that Mr Said is solely responsible for the delays under
the head contract. The delay costs are said to be for the period from
21 September 2015 to the end of May 2016.
[12] Mr Barlow says that after 3 April 2016 he was ringing Mr Said regularly
because “our building work in the unit was largely finished”.2
[13] Burleigh Building Pty Ltd bears the onus of proving its damages. It has
failed to do so in respect of the delay costs.
[14] I award damages to Broadbeach Building Pty Ltd for the replacement of the
kitchen in the sum of $30,326.81, calculated as the amount claimed of
$32,523.51 less the sum off $2,196.70 unpaid under the contact.
[15] I allow Broadbeach Building Pty Ltd the filing fees of $315.70.
[16] I order that Dennis Said pay Broadbeach Building Pty Ltd the sum of
$30,642.51 by 4:00pm on 15 December 2017.
2 Statement of Simon Barlow, paragraph 12.
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2017/410