Cowen v Queensland Building and Construction Commission [2017] QCAT 416
CITATION: Cowen & Anor v Queensland Building and
Construction Commission & Anor [2017]
QCAT 416
PARTIES: Peter Cowen
Jan Cowen
(Applicants)
v
Queensland Building and Construction
Commission
(First Respondent)
Hinterland Constructions Pty Ltd
(Second Respondent)
APPLICATION NUMBER: GAR044-15; GAR113-16
MATTER TYPE: General administrative review matters
HEARING DATES: GAR044-15:
8, 9 February 2016; 4, 5 May 2016;
14 September 2016
GAR044-15 and GAR113-16:
13, 14, 15, 16, 17, 21, 22, 23 February 2017
HEARD AT: Brisbane
DECISION OF: A/Senior Member Browne
DELIVERED ON: 27 November 2017
DELIVERED AT: Brisbane
ORDERS MADE: In GAR044-15:
1. The decision made by the Queensland
Building and Construction Commission
of 22 December 2014 to decline a claim
for non-completion under clause 1.2 of
the Insurance Policy Conditions is set
aside.
2. The Tribunal substitutes its own decision
that Peter Cowen and Jan Cowen did
validly terminate the contract dated 18
February 2013 and the claim for non-
completion under clause 1.2 of the
Insurance Policy Conditions is accepted.
-- 1 of 64 --
2
In GAR113-16:
1. The decision made by the Queensland
Building and Construction Commission
of 14 February 2017 not to issue a
direction to rectify to Hinterland
Constructions Pty Ltd for items 1(b), 1(c),
1(d), 3, 4(a), 4(d), 4(e), 5, 7, 8, 10, 14, 17,
18(a), 18(b), 18(c), 18(e), 21, 23(a), 25, 26,
27, 28 and 31 referred to in the Scott
Schedule (identified as ‘Exhibit 24’ in
these proceedings) is confirmed.
2. The decision made by the Queensland
Building and Construction Commission
of 14 February 2017 not to issue a
direction to rectify to Hinterland
Constructions Pty Ltd for items 1(a), 1(e),
1(f), 1(g), 2, 4(b), 4(c), 12, 13, 15, 16, 18(d),
23(b) and 23(c) referred to in the Scott
Schedule (identified as ‘Exhibit 24’ in
these proceedings) is set aside.
3. The Tribunal substitutes its own
decision that:
a) For items 1(a), 1(e), 1(f), 1(g), 2, 12,
13, 23(b) and 23(c) referred to in
the Scott Schedule (identified as
‘Exhibit 24’ in these proceedings)
the matter be returned to the
QBCC for reconsideration
pursuant to s24(1)(c) of the
Queensland Civil and
Administrative Tribunal Act 2009
(Qld);
b) For items 4(b) and 4(c), 15, 16 and
18(d) referred to in the Scott
Schedule (identified as ‘Exhibit
24’ in these proceedings) a
direction to rectify should not be
issued to Hinterland
Constructions Pty Ltd.
CATCHWORDS: PROFESSIONS AND TRADES – BUILDERS –
STATUTORY POWER TO REQUIRE –
RECTIFICATION OF DEFECTIVE OR
INCOMPLETE BUILDING WORK – HOME
WARRANTY INSURANCE – where decision
made to decline a claim for non-completion
under clause 1.2 of the QBCC Home Warranty
-- 2 of 64 --
3
Insurance Scheme Policy Conditions – where
homeowner filed an application to review the
decision – whether contract properly terminated
by the homeowner
PROFESSIONS AND TRADES – BUILDERS –
STATUTORY POWER TO REQUIRE –
RECTIFICATION OF DEFECTIVE OR
INCOMPLETE BUILDING WORK – where
decision made not to issue a direction to rectify
to the builder – where homeowner filed an
application to review the decision – whether
items of work are defective work – whether fair
to give a direction to rectify
Queensland Building and Construction
Commission Act 1991 (Qld), s 3, s 20J, s 72,
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 20, s 24
Botros v Freedom Homes Pty Ltd [2000] 2 Qd
R 377
Briginshaw v Briginshaw (1938) 60 CLR 336
Garbutt-Cuttiford v Queensland Building
Services Authority [1999] QBT 80
Hudson Crushed Metals Pty Ltd v Henry [1985]
1 Qd R 202
Kehl v Board of Professional Engineers of
Queensland [2010] QCATA 58
Koompahtoo Local Aboriginal Land Council v
Sanpine Pty Limited (2007) 233 CLR 115
Shepherd v Felt & Textiles of Australia Ltd
(1931) 45 CLR 359
Shevill v Builders Licensing Board (1982) 149
CLR 620
Sunbird Plaza Pty Ltd v Maloney (1989) 166
CLR 245
Taouk v Queensland Building Services
Authority, [2013] QCAT 508
Thunder Corp Pty Ltd v Queensland Building
Services Authority [2011] QCAT 56
REPRESENTATIVES:
APPLICANT: Peter Cowen and Jan Cowen represented by
Mr P Summers of legal counsel, instructed by
Bennett & Philip Lawyers
RESPONDENTS: Queensland Building and Construction
Commission represented by Mr S Formby,
-- 3 of 64 --
4
former in-house legal counsel on 8, 9 February
2016; 4, 5 May 2016; 14 September 2016 and
on 13, 14, 15, 16, 17, 21, 22, 23 February 2017
represented by Mr C Tanzer, Solicitor of
Gadens Lawyers
Hinterland Constructions Pty Ltd represented
by Mr Chris Freeman, Director of Hinterland
Constructions Pty Ltd
REASONS FOR DECISION
[2] Peter Cowen and Jan Cowen decided to renovate their house and garage
at Highgate Hill. One of the reasons for extending the garage was to house
Mr Cowen’s motor vehicles.
[3] The Cowens signed a contract with Hinterland Construction Pty Ltd (the
Builder) to complete the renovations. The contract was signed on 18
February 2013, but work did not commence until January 2014.
[4] There was a dispute during the completion of the works. The Cowens
sought to terminate the contract with the Builder. The Cowens’ legal
representatives sent a final termination of contract letter dated 13
November 2014. The notice of intention to terminate was dated 28 October
2014.
[5] The Builder took steps on 1 October 2014 to suspend the building works
because of alleged interference by the Cowens with workplace health and
safety procedures.
[6] The Cowens made complaints to the Queensland Building and
Construction Commission (the QBCC) about the building work performed
by the Builder on 21 November 2014.
[7] The QBCC inspected the building work.
[8] The QBCC responded to the Cowens’ complaints by making two decisions.
On 22 December 2014, the QBCC made a decision to disallow the Cowens’
claim under the statutory insurance scheme pursuant to clause 1.2 of the
Insurance Policy Conditions because the contract had not been properly
terminated.1
[9] The Cowens sought to review that decision by way of an internal review.
Pursuant to s 86C(3) of the Queensland Building and Construction
Commission Act 1991 (Qld) (the QBCC Act) the decision in the internal
review was taken to be the same as the original decision dated 22
1 Queensland Building and Construction Commission Act 1991 (Qld) (the QBCC Act),
Part 5 and see s 20J(f).
-- 4 of 64 --
5
December 2014. The Cowens then filed an application to review that
decision in the Tribunal (proceeding GAR044-15).
[10] On 27 April 2015, the QBCC issued a direction to rectify to the Builder but
subsequently withdrew it. The QBCC did not issue any further direction.
The Cowens commenced review proceedings (GAR113-16) to review the
QBCC’s decision not to issue a direction to rectify. During the hearing a
decision was made by the QBCC not to issue a direction to rectify, by
consent that decision became the reviewable decision for the purposes of
the review proceeding (GAR113-16).2
[11] Application GAR044-15 proceeded before the Tribunal over four days. On
the fifth day of the hearing, the application was adjourned by consent and
directions made that application GAR044-15 (part heard) proceed to a
further four day hearing together with application GAR113-16.3
[12] On 23 February 2017 directions were made for the parties to file and
exchange written closing submissions in relation to the proceedings.4
[13] All of the parties agree that the reviewable decision before the Tribunal in
application GAR044-15 is the QBCC’s decision to disallow the claim under
the home owners insurance scheme. This requires the Tribunal to answer
the question as to whether the Cowens lawfully terminated the contract.5
[14] All of the parties agree that the question to be determined by the Tribunal
in application GAR113-16 is whether there is defective and/or incomplete
work performed by the Builder; and if there is defective work, whether in all
of the circumstances a direction to rectify should be issued.6
[15] All of the parties rely on expert evidence and their own evidence. The expert
witnesses participated in an experts conclave and gave concurrent
evidence in the hearing.7
[16] So that all of the parties and expert witnesses could properly identify the
issues, the Cowens prepared a schedule of items (the Scott Schedule)
identifying work alleged to be defective and/or incomplete. It is non-
contentious that the Scott Schedule for the purposes of reviewing the
decisions in GAR044-15 and GAR113-16 captures items that formed part
2 Tribunal Decision dated 15 February 2017.
3 Direction by consent dated 14 September 2016. See Directions dated 23 February 2017
and 9 May 2017 for the filing and exchange of submissions.
4 See Directions dated 23 February 2017, 9 May 2017 and 20 June 2017. The applicants’
outline of submissions were filed on 7 April 2017, the QBCC’s written submissions were
filed on 12 May 2017, the Builder’s written submissions were filed on 1 June 2017, the
applicants’ written submissions in reply were filed on 16 June 2017 and the QBCC’s
submissions in response to the applicants’ submissions were filed on 3 July 2017.
5 See agreed background prepared for the purpose of the experts conclave, Exhibit 22
and 23.
6 Ibid.
7 See Tribunal Directions dated 13 February 2017.
-- 5 of 64 --
6
of the Cowens initial complaint to the QBCC and that the QBCC has had
an opportunity to inspect the items and to make a decision about them.8
What is the Tribunal’s power on review and the issues to be determined?
[17] This is a review of the QBCC’s decisions not to accept a claim under the
statutory insurance scheme and not to issue a direction to the Builder to
rectify building work. The Tribunal in exercising its review function
effectively stands in the shoes of the QBCC decision-maker exercising the
same powers under the QBCC Act, to produce the correct and preferable
decision.9
[18] The Tribunal decides the review by way of a fresh hearing on the merits. It
is not necessary to establish any error in either the process or the reasoning
that led to the decision and there is no presumption that the reviewable
decision is correct.10
[19] In arriving at the correct and preferable decision, the Tribunal considers all
of the material including the material that was before the decision-maker
(commonly referred to as the ‘section 21 material’) and fresh material
presented by the parties comprising of expert reports and statements of
evidence.11
[20] In the review proceeding, the QBCC, as the respondent decision-maker has
a duty to assist the Tribunal so that it can make its decision and has a model
litigant role.12 This includes cross-examining the Cowens, the Builder and
each of their respective witnesses giving evidence in the proceeding. The
respondent decision-maker must also ensure that all material relied upon
in making the decision being reviewed has been disclosed.
[21] In assessing the evidence, the Tribunal on review must be satisfied to the
required civil standard on the balance of probabilities that certain factual
matters are proven. In Briginshaw’s case, (commonly referred to as the
‘Briginshaw principle’,13) Dixon J (as he then was) said that the proof of any
fact must be made out to the reasonable satisfaction of the Tribunal and
should not be ‘produced by inexact proofs, indefinite testimony, or indirect
inferences’.14
[22] In conducting a proceeding, the Tribunal on review is not bound by the rules
of evidence,15 but must observe the rules of natural justice and, amongst
8 Tribunal Directions dated 13 February 2017.
9 Queensland Civil and Administrative Tribunal Act 2009 (Qld) (the QCAT Act), s 20.
10 Kehl v Board of Professional Engineers of Queensland [2010] QCATA 58, [9].
11 The decision-maker must file a written statement of the reasons and any material
relevant to the review pursuant to s 21(2) of the QCAT Act (the section 21 material).
12 QCAT Act, s 21.
13 Briginshaw v Briginshaw (1938) 60 CLR 336 at 361 to 362.
14 Ibid.
15 Section 28(b) of the QCAT Act provides that the rules of evidence do not apply other
than to the extent that the tribunal adopts them.
-- 6 of 64 --
7
others, ‘ensure, so far as is practicable, all relevant material is disclosed to
the tribunal to enable it to decide the proceeding with all the relevant facts.’16
[23] In GAR113-16, the QBCC exercised its powers under the QBCC Act to not
direct the Builder to rectify defective or incomplete work.17 Relevantly s 72
of the QBCC Act gives the QBCC and the Tribunal on review the power to
issue a direction to rectify to the Builder if satisfied that the building work is
‘defective or incomplete’; or ‘consequential damage has been caused by, or
as a consequence of, carrying out building work’.18
[24] The power to direct under s 72 of the QBCC Act is discretionary and the
QBCC and the Tribunal on review, may issue a direction after taking into
consideration all of the circumstances it considers are reasonably relevant,
including the terms of the contract. The QBCC and Tribunal on review is not
required to give a direction if satisfied that, in the circumstances, ‘it would
be unfair to the person to give the direction’.19
[25] In Taouk v Queensland Building Services Authority20 the Tribunal said that
the QBCC (then known as the QBSA) has responsibilities under the relevant
legislation, the QBCC Act, to ‘ensure proper standards in the industry and
rectification of building work’.21 The power to issue a direction to rectify is
not for the ‘benefit’ of the homeowner but rather a discharge of the QBCC’s
responsibilities under the Act.22
[26] In making a decision under the QBCC Act, the QBCC (and the Tribunal on
review) is required to, amongst other things, achieve a reasonable balance
between the interests of building contractors and consumers and to provide
remedies for defective building work.23
[27] Part 5 of the QBCC Act is also relevant in this matter because a decision
was made in GAR044-15 to decline the Cowens’ claim for non-completion.
Part 5 of the Act establishes a statutory insurance scheme called the
Queensland Home Warranty Scheme (the statutory insurance scheme).
Claims made under the statutory insurance scheme may be approved by
the QBCC subject to the Insurance Policy Conditions.24 A decision to
disallow a claim under the scheme wholly or in part is a reviewable
decision.25
16 QCAT Act, s 28.
17 QBCC Act, s 72.
18 Ibid, s 72.
19 QBCC Act, s 72(5).
20 [2013] QCAT 508.
21 Taouk v Queensland Building Services Authority, [2013] QCAT 508, [39]; citing Garbutt-
Cuttiford v Queensland Building Services Authority [1999] QBT 80.
22 Ibid.
23 QBCC Act, s 3.
24 Ibid, s 3, s 10, s 19 and s 70(1). See also the Queensland Building and Construction
Commission Regulation 2003, s 34A and the Insurance Policy Conditions Edition 8, 1
July 2009.
25 QBCC Act, s 86(1)(h).
-- 7 of 64 --
8
[28] Relevantly clause 1.2 of the policy for payment for non-completion of work
provides as follows:
1.2 Termination of contract
The QBCC is only liable to pay for loss under this Part when the contract is
for a fixed price and the insured has properly terminated the contract with
the contractor.
[29] Part 11 of the policy refers to ‘properly terminated’ and provides that:
“properly terminated” means lawfully under the contract or otherwise at law,
upon the contractor’s default which extends to, but is not limited to:
(a) The cancellation or suspension of the contractor’s licence;
or
(b) The death or legal incapacity of the contractor; or
(c) The insolvency of the contractor; or
(d) Any breach of the contract by the contractor.
[30] A payment by the QBCC under the insurance scheme has potential
ramifications for a Builder to whom a direction to rectify has been issued.
This is because under s 71 of the QBCC Act the QBCC ‘may recover’ the
amount of the payment ‘as a debt’ from the building contractor by whom the
relevant residential construction work ‘was, or was to be, carried out,’ or any
other person through ‘whose fault’ the claim arose.26
[31] In reviewing the decision to refuse the Cowens’ claim for non-completion
and considering clause 1.2 of the Insurance Policy Conditions, the Tribunal
must look at all of the evidence and the terms of the contract signed by the
parties. The Tribunal must determine whether the Cowens have lawfully
terminated under the contract or otherwise at law.
[32] In Koompahtoo Local Aboriginal Land Council v Sanpine Pty Limited27 the
High Court said that there are two relevant circumstances in which a breach
of contract by one party may entitle the other to terminate. Firstly, where the
obligation with which there has been a failure to comply has been agreed
by the contracting parties to be essential. The High Court said this is
sometimes described as a condition. Secondly, where there has been a
sufficiently serious breach of a non-essential term.28
[33] There is good authority for the proposition that, as a matter of law, a contract
may be validly terminated by relying upon any valid ground at the time of
termination, even though the ground was not relied upon and even though
the ground actually relied upon is later found to be not valid.29
26 QBCC Act, s 71(1).
27 (2007) 233 CLR 115.
28 Ibid, 136-137, [47]-[49].
29 Sunbird Plaza Pty Ltd v Maloney (1989) 166 CLR 245 at [26]; citing Shepherd v Felt
&Textiles of Australia Ltd (1931) 45 CLR 359.
-- 8 of 64 --
9
[34] In the High Court decision of Shepherd v Felt & Textiles of Australia Ltd30
Dixon J said [footnotes emitted]:
…But the rule is of general application in the discharge of contract by breach,
and enables a party to any simple contract who fails or refuses further to
observe its stipulations to rely upon a breach of conditions, committed before
he so failed or so refused, by the opposite party to the contract as operating
to absolve him from the contract as from the time of such breach of condition
whether he was aware of it or not when he himself failed or refused to
perform the stipulations of the contract. “It is a long established rule of law
that a contracting party, who, after he has become entitled to refuse
performance of his contractual obligations, gives a wrong reason for his
refusal, does not thereby deprive himself of a justification which in fact
existed, whether he was aware of it or not”... 31
[35] It is settled law that if there is conduct by one party which evinces an
unwillingness or an inability to render substantial performance of the
contract, such conduct may be described as repudiatory breach of contract.
An innocent party is entitled to accept the repudiation and terminate the
contract.32
[36] In Koompahtoo’s case the High Court said that repudiatory conduct may be
described as conduct of a party which ‘evinces an intention no longer to be
bound by the contract or to fulfil it only in a manner substantially inconsistent
with the party’s obligations’.33 The High Court said the test is whether the
conduct of one party is such as to convey to a reasonable person, in the
situation of the other party, renunciation either of the contract as a whole or
of a fundamental obligation under it. In Koompahtoo’s case the High Court
said there may be cases where a failure to perform, even if not a breach of
an essential term, manifests unwillingness or inability to perform.34
[37] The common law right to terminate for repudiatory conduct may involve a
consideration of more than one breach that, when viewed together, indicate
an intention to no longer be bound by the contract.35
What are the competing submissions to be considered by the Tribunal on
review?
[38] The Cowens contend that they have properly terminated the contract with
the Builder by issuing a notice pursuant to clause 20.1 of the contract. In
their correspondence to the Builder dated 13 November 2014 (containing
30 Shepherd v Felt &Textiles of Australia Ltd (1931) 45 CLR 359.
31 Ibid, 377-378.
32 Shevill v Builders Licensing Board (1982) 149 CLR 620, 625-626.
33 Koompahtoo Local Aboriginal Land Council v Sanpine Pty Limited (2007) 233 CLR
115, 44.
34 Ibid.
35 Hudson Crushed Metals Pty Ltd v Henry [1985] 1 Qd R 202, 205-208.
-- 9 of 64 --
10
the termination notice), the Cowens also contend that there is a clear
repudiation of the contract (by the Builder) which they accepted.36
[39] In closing written submissions, the refer to, amongst other things, the
Builder’s suspension of the works on 2 November 2014 with no proper
basis, a failure to carry out the works in a workman-like and diligent manner;
and a failure to carry out the works in accordance with the contract.37 The
Cowens also contend that the works were at such a delayed stage that they
would not be completed for four to six months after they were to be brought
to practical completion.38 The Cowens say that such a delay is of a kind that
frustrated the commercial purpose of the contract and as such constituted
repudiation.39
[40] The QBCC disputes that the contract has been properly terminated by the
Cowens. At the hearing, Mr Simon Formby for the QBCC, in his duty to
assist the Tribunal, outlined the relevant issues to be determined by the
Tribunal on review. Mr Formby submits that if the Tribunal finds the
suspension of the work by the Builder was unlawful then that would be a
ground to terminate.40 Mr Formby says however that in having regard to
clause 20.2 of the contract, it is unreasonable to terminate in the
circumstances. Mr Formby also contends that the notice of intention to
terminate was not validly issued and, as at 1 October 2014, the Cowens
have attempted to unilaterally impose conditions into the contract which is
a form of repudiation.41
[41] In closing written submissions, the QBCC submits that the Cowens’ notice
of intention to terminate issued on 28 October 2014 (‘the October notice’) is
invalid and cannot be relied upon by the Cowens for the purposes of clause
20.1 of the contract.42 The QBCC contends that the notice was not
unequivocal.43 The QBCC also contends that by giving the October notice
on 28 October 2014 the Cowens repudiated the contract.44 The QBCC says
that the Cowens were not permitted to terminate the contract pursuant to
clause 20.3 of the contract.45 The QBCC says that the Cowens’ insistence
upon compliance with terms which do not appear in the contract as a pre-
requisite for the Cowens’ future involvement in the contract, the Cowens
have evinced a clear intention to fulfil the contract ‘only in a manner
substantially inconsistent with the [Applicants’] obligations’.46
36 Section 21 material, exhibit 2, p 201.
37 The Cowens’ outline of submissions filed on 7 April 2017.
38 Ibid.
39 Ibid, p 38.
40 Transcript dated 8 February 2016, T1-45.
41 Ibid, T1-47.
42 First respondent’s (the QBCC) submissions on the hearing filed on 12 May 2017.
43 Ibid, p 16. See Dura (Australia) Constructions Pty Ltd v Hue Boutique Living Pty Ltd
[2012] VSC 99 at 395.
44 QBCC’s submissions filed on 12 May 2017 and the QBCC’s submissions in response
filed on 3 July 2017.
45 QBCC’s submissions on the hearing filed on 12 May 2017.
46 Ibid, p 20.
-- 10 of 64 --
11
[42] The QBCC says that even if the Builder is found to have repudiated the
contract by its conduct, the subsequent repudiation by the Cowens
prevented them from validly terminating as they purported to do.47 The
QBCC says that in the event that neither party was able to lawfully terminate
the contract for the others breach, both parties by their conduct treated the
contract as being at an end after 13 November 2014 and the contract was
therefore abandoned.48 The QBCC submits that the Cowens claim for non-
completion must therefore be declined.49
[43] The Builder also disputes that the contract has been properly terminated by
the Cowens. At the hearing, Mr Christopher Freeman representing the
Builder argued, amongst other things, that Mr Cowen regularly walked onto
site unauthorised and wearing inappropriate gear, talked to contractors and
otherwise interfered with the performance of the works.50 Mr Freeman
contends that the contract was unlawfully terminated by the Cowens and
that the Builder has done everything reasonably expected to be done in
relation to the terms of the contract.
[44] In closing written submissions the Builder contends that the purported
termination by the Cowens on 13 November 2014 was illegal.51 The Builder
says that the Cowens were in breach of the contract on several occasions
and refers to, amongst other things, a failure to deposit the security deposit
into the bank, a failure to sign variations, a failure to wear appropriate
clothing when on the construction site; and various delays. The Builder says
that any ‘supposed defects have not been proven to be defects’, were not
brought up at a time when they were completing the work and that there is
unfinished work at the time the dispute arose.52
[45] In this matter, I am required to consider many issues. In determining
whether or not the Cowens have properly terminated the contract (in
GAR044-15), I must make findings about the conduct of the contracting
parties and alleged interference with the performance of the works by the
Builder and the Cowens. This includes, amongst other things, a
consideration as to whether the Builder placed boarding over the doors and
windows in accordance with its obligations as principal contractor under the
contract; whether or not Mr Cowen interfered with the performance of the
works; and whether or not there was non-compliance with the contract.
[46] In determining the issues about whether or not a direction to rectify should
issue (in proceeding GAR113-16), the Tribunal must make findings about
certain items of work performed by the Builder including whether or not the
work is defective or incomplete, after considering all of the evidence
including the expert evidence. The relevant items of work are identified in
47 QBCC’s submissions on the hearing filed on 12 May 2017, p 20.
48 Ibid, p 25.
49 Ibid.
50 Ibid, T1-67.
51 Second respondent’s (the Builder) outline of submissions filed on 1 June 2017.
52 Ibid, p 11.
-- 11 of 64 --
12
the Scott Schedule and all of the parties have given evidence about the
items.
Did the Builder place boarding over the doors and windows in accordance
with its contractual obligations?
[47] It is common ground that the Builder placed boarding over windows and
doors on the upstairs verandah of the Cowens’ property on or about 27
September 2014. The Cowens were not home when this happened and did
not see the boarding until they returned from interstate on 29 September
2014.
[48] Mr Cowen states in his statement that the Builder boarded up access to
areas of their residence ‘making it virtually uninhabitable’.53 Mr Cowen
states that upon their return to Brisbane he and his wife were unable to
access many parts of the house and had to ‘climb up a ladder to retrieve
items from [their] verandah on the riverside’.54 Mr Cowen states that this
was because of the ‘inappropriate’ boarding up of doors.55 Mr Cowen also
states that the boarding was ‘nowhere near any intended construction’ and
left windows and an adjacent door ‘vulnerable’ and unprotected.56 Mr
Cowen also states that the Builder had fixed substantial steel posts and
beams ‘swaying in the breeze, secured by just a couple of nut threads due
to all the fixing posts being cut far too short’.57
[49] Mr Freeman gave oral evidence at the hearing about the placement of
boarding over the doors and windows. Although Mr Freeman was the
Builder responsible for the works performed at the Cowens’ property, he
was not the primary representative for the Builder in terms of the
negotiations that took place between the contracting parties. Mr Freeman
in giving his oral evidence stated that Stephen Reid was responsible for the
design stage of the work.58 Mr Freeman stated that Hugh Findlay was the
company’s in-house draftsman and communications between the Cowens
and the Builder were generally with either Mr Reid or Mr Findlay.59 Mr
Freeman in giving his oral evidence stated that he was fairly involved in the
project and was kept informed of issues by the construction manager, Mark
Kocks.60 The supervisor of the work was Alex Mizanowski.61
[50] It is Mr Freeman’s oral evidence that the boarding was placed up ‘partially
for safety’ and to protect the doors and windows.62 In giving his oral
evidence, Mr Freeman referred to roof rafters coming down near particular
53 Exhibit 4, [193] to [197].
54 Ibid.
55 Ibid.
56 Ibid.
57 Ibid.
58 Transcript dated 15 February 2017, T1-23.
59 Ibid.
60 Ibid.
61 Ibid.
62 Ibid, T1-81.
-- 12 of 64 --
13
doors that were boarded up. Mr Freeman also stated that an area for tools
and equipment is needed. Mr Freeman stated:
…you can’t have a work area and just work in that particular area and have
everything drop down on top of you. You need an exposed area where
you’ve got an area for tools and equipment, for Acrow propos, materials like
that. All those materials present a danger and it would also have opened up
to an open, unsecure, balcony.63
[51] Mr Freeman stated that the Builder is responsible for workplace health and
safety and it is the Builder’s choice where they put protection. Mr Freeman
stated:
And we were responsible for workplace health and safety, no one else is. It
is a Builder’s choice where we put protection and how we do it. At the end
of the day, with a litigious client like Cowen, you can just imagine what would
happen if he got injured; my God.64
[52] Mr Freeman also stated that it (referring to safety) affects the company’s
insurance and obligations to insurance companies.65
[53] Mr Freeman was cross-examined about the boarding with reference to
specific locations on site where construction was to take place. Mr Freeman
maintained his evidence that boarding was placed over the doors and
windows to protect the property and to stop people getting into the
construction site.66 I accept Mr Freeman’s evidence given in relation to the
placement of boarding over the doors and windows.
[54] I have considered all of the evidence relevant to the boarding issue. The
contract signed by the Cowens and the Builder provides that the Builder (as
principal contractor) has obligations under the Workplace Health and Safety
Act 1995 to, amongst other things, ‘ensure the safety’ of persons on the
construction site.67
[55] The evidence shows that the Cowens were not happy with the boarding and
sent emails to the Builder about their concerns.68 The Builder also sent
emails to the Cowens about the boarding. In the emails sent by the Builder,
the Builder refers to ‘Health and safety’ requirements and the prevention of
damage to existing doors.69 I have accepted Mr Freeman’s evidence given
in relation to the placement of boarding over the doors and windows.
63 Transcript dated 15 February 2017, T1-82.
64 Ibid, T1-83.
65 Ibid.
66 Transcript dated 8 February 2016, T1-86.
67 Exhibit 4, p 25, clause 11.12.
68 See exhibit 2, pp 179 to 184.
69 Ibid.
-- 13 of 64 --
14
[56] It is open to me to find that the Builder placed boarding over the doors and
windows for safety and protection in accordance with its obligations as
principal contractor under the contract.
Did the Cowens interfere with the performance of the works and
workplace health and safety – the requests for the ‘SWMS’ and to
remove the boarding?
[57] The Builder contends that the Cowens interfered with the performance of
works and workplace health and safety.70 In written submissions, the
Builder submits that the Cowens kept interfering with the works and
breached safety rules.71 The Builder says ‘[f]or safety’s sake a suspension
of works had to be instigated and [the Cowens] were advised of this and
the reason for it’.72
[58] The Builder says that a suspension of works was necessary predominantly
on the basis that the Cowens interefered with workplace health and safety.
The Cowens contend that they sent an email to the Builder stating that they
would allow the boarding to remain.
[59] The relevant evidence about the boarding contained in the emails
exchanged between the Builder and the Cowens is set out below:
On 30 September 2014 at 9:57 am, Hugh Findlay emailed Mr Cowen
responding to his ‘phone enquiry about construction hoarding over the doors
to the verandah and patio (upstairs and downstairs)’. The email referred to
‘Health and Safety’ requirements and prevention of damage to existing glass
doors ‘before any demolition or construction occurs’. The email also referred
to the general conditions of the contract: part 6 and part 10 and stated as
follows:
It’s the Builders responsibility to secure the construction site to meet
all the statutory requirements. The hoarding will have to stay until the
construction is finished or until the Builder determines that it is safe
to do so under his obligations.73
On 1 October 2014 at 7:56 am, Hugh Findlay emailed Mr Cowen stating that
he is concerned ‘at the level of stress’ that the Cowens are having at this
stage of the work. Mr Findlay (in the email) invited the Cowens to have a
discussion with him about the demolition and list of items to drop from the
contract.74 The email stated:
…there will be more disruption with demolition of the existing
verandah/walls/roof etc. Have sent through a list of items to drop from
the contract for consideration…and if you want to come up to go
through that list with you please let me know. There are some time
70 The Builder’s written submissions filed on 1 June 2017.
71 Ibid, p 2.
72 Ibid, p 2.
73 Exhibit 2, p 184.
74 Ibid, p 182.
-- 14 of 64 --
15
constraints on these items which we could go through and discuss
along with other issue[s] you want to raise…75
On 1 October 2014 at 11:20 am, Mr Cowen emailed Hugh Findlay requesting
that the boarding be removed ‘immediately’. Mr Cowen also stated that they
(the Cowens) have contacted the relevant Government authorities including
the certifier (QBCC) and ‘WH&S officer (Dept. of Justice and Attorney-
General)’. Mr Cowen stated ‘[y]our recent actions are in direct contravention
of the requirements of the WH&S Act…’. Mr Cowen stated ‘[p]lease provide
us with a copy of the relevant ‘SWMS’ [safe work and management system
document] asap?’. Mr Cowen also stated that the boarding up of doors etc
was ‘another act of blatant vindictiveness’. Relevant extracts from the email
are as follows:
I refer to my request per phone at 9:10 yesterday morning that you remove
the complete boarding up of our bedroom doors, fanlight windows, lounge
doors and fanlight windows (on the river side) immediately…
…
…it is obvious the sole reason for the complete boarding up of our bedroom
doors, fanlight windows, lounge doors and fanlight windows (on the river
side) is another act of blatant vindictiveness against us because we had
the audacity to complain about being bullied and tricked into payments
outside of the contract.
We therefore request (yet again) that you remove the boarding up of our
bedroom doors, fanlight windows, lounge doors and fanlight windows (on
the river side) immediately…76
On 1 October 2014 at 11:53 am, Mr Cowen emailed Hugh Findlay referring
to ‘threats and acts of blatant vindictiveness’ and stated ‘yes’ they (the
threats and acts) have ‘certainly taken their toll’. Mr Cowen stated that Mrs
Cowen was ‘out currently investigating houses available (at considerable
expense) to relocate to on a short-term lease’.77 Relevant extracts from the
email are as follows:
…We guess Mark, Chris and Steve must be feeling particularly proud of
themselves with their latest attempts to upset us, finally almost succeeding
in driving us out of our own house!
Yes, we are fearful of what ‘stunt’ you have planned for us next. 78
By email dated 1 October 2014 at 2:06 pm, Chris Freeman emailed Mr
Cowen referring to the emails sent to Mr Findlay regarding the safety
hoardings. Relevant extracts from the email are as follows:
75 Exhibit 2.
76 Ibid, p 183.
77 Ibid.
78 Ibid, p 182.
-- 15 of 64 --
16
We note your emails sent to Hugh [Findlay] today regarding the safety
hoardings placed on your house.
We advise that tomorrow morning we will have carpenters on site to
remove these plywood sheets. The site is then declared unsafe by us, as
we are the ones ultimately responsible for site safety. It is impossible for us
to continue work without safety precautions being in place. As such we are
immediately placing an indefinite suspension on works as of today until all
matters are fully and finally resolved.
It is clear that you have little understanding of building and construction and
you have put endless obstacles in the way of us getting on and doing the
job. With a renovation you must expect that there are going to be
inconveniences, we are not sure how you would deal with it when the walls
are removed and roof taken of [sic].
We would advise you to be very circumspect in any written and oral
statements you make about this company. 79
By email dated 1 October 2014 at 4:40 pm, Mr Cowen emailed Chris
Freeman and stated ‘your actions are clearly based on blatant vindictiveness
against us rather than any claimed safety issue’. Mr Cowen also stated at
the end of the email, ‘PS. We are still waiting [sic] you to provide copies of
the engineer’s certifications to date’. Relevant extracts from the email are as
follows:
…we will allow your complete boarding up of our bedroom doors, fanlight
windows, lounge doors and fanlight windows (on the river side) to remain,
pending further advice after receiving a copy of the relevant ‘SWMS’, which
you have previously been requested to provide asap.
…This is the first time in our lives we have had such unpleasant and costly
bad experiences with a Builder.
We have not put obstacles in the way. Indeed, we have done all that we
possibly could for over a year now to get this job started and finished.
I gather your last sentence is another threat to cause us even more upset
etc if we complain to the QBCC? We are certainly fearful that Mark Kocks
will carry out some of his boasts about some of the very vindictive things
he’s done to clients he didn’t like…80
On 2 October 2014 at approximately 7:00am, two employees of the Builder
attended the site.
By email dated 2 October 2014 at 8:28 am, Chris Freeman emailed Mr
Cowen referring to his instructions that were given to carpenters to remove
the boarding. Mr Freeman stated that Mr Cowen’s email sent at 4:51 pm was
‘outside our advertised business hours’. Mr Freeman referred to Mr Cowen
having broken site rules by entering the construction site and conversing
directly with tradesmen. Mr Freeman also stated that Mr Cowen has ‘verbally
79 Exhibit 2, p 181.
80 Ibid, p 180.
-- 16 of 64 --
17
threatened them and got right up in their face’. Mr Freeman stated that Mr
Cowen ‘ordered them off the site’ and that he (Mr Freeman) requested his
employees and sub-contractors to leave the site. Mr Freeman referred to Mr
Cowen’s ‘erratic behaviour’ and time ‘wasted’ due to Mr Cowen’s ‘ill-
informed statements’ and ‘constant threats and time wasting legal
communications’. Mr Freeman stated that ‘work is immediately suspended
until every issue is fully and finally resolved’. Mr Freeman referred to Mr
Cowen’s ‘unreasonable behaviour and obstruction in us doing our work’.
Some of the relevant extracts from the email are as follows:
…Your constant to and fro attitude to what can and can’t be done according
to you makes the entire job a nightmare beyond belief. Everyone who has
been involved with this project are stunned by your behaviour and several
trades have refused to return to your site because of your actions.
We are taking advice on what our next step should be due to the fact that
you are making the completion of our work virtually impossible.
Our last sentences was a written warning [sic] you be very careful about
statements you make about our company. Already we have copies of
numerous written statements you have made to use that we considered
defamatory and blatant re-writing of history. The warning is that we will be
watching and listening to anything you say to anyone and should they be
considered defamatory appropriate action will be taken. 81
[60] Mr Cowen and Mr Freeman gave evidence about the boarding and the
emails exchanged between them including the requests made by the
Cowens to the Builder to remove the boarding.
[61] Mr Freeman, in his statement, states that Mr Cowen was ‘in a rage on the
phone and would not listen to reason’.82 Mr Freeman states that Mr Cowen
‘demanded immediate removal of the offending hoardings’.83 Mr Freeman
states:
We clearly advised that should we do this we cannot possibly proceed with
the work and would have to place an indefinite suspension on works. We
had no option other than to suspend the works due to insufficient safety
being provided, clear in the knowledge that should anything happen to the
owners wellbeing or to their existing property that Cowen, being of a litigious
nature, would obviously take action against us along with us being
prosecuted and fined by Workplace Health and Safety. Cowen notes that
the timber boards “prevented us from accessing our house”. The reality is
that they did not at all, they only prevented him accessing the “construction
site” which he is specifically not permitted to be in at any time. Due to the
extreme behaviour of Cowen we immediately arranged that night for two of
our carpenters to go to the site first thing the next morning to remove the
hoardings.84
81 Exhibit 2, p 179.
82 Exhibit 32, [70].
83 Ibid.
84 Exhibit 32, [70].
-- 17 of 64 --
18
[62] Mr Freeman states that Mr Cowen was going to do everything possible to
‘frustrate our moving forward and completing the job’.85 Mr Freeman states
that when they sent the carpenters to take down the boarding (on 2 October
2014) ‘[Mr Cowen] approached them and basically told them to get off his
site’. Mr Freeman states that the carpenters rang ‘us’ and ‘we’ (meaning the
Builder) told them (meaning the carpenters) to leave. Mr Freeman states:
Knowing [Mr Cowen’s] previous violent outbursts we did not want our
carpenters put in a position of risk of physical attack. At this stage it was
clear to us that things had got to a stage where he [Mr Cowen] did not want
us there and we did not want to be there. We made every effort to get this
project completed and no matter what we did he [Mr Cowen] was never
happy. This is the first time we have ever encountered such erratic and
paranoia behaviour in over ten years of building. We truly felt at this stage
that Cowen had some serious mental illness, be it paranoia or bipolar. This
was not an insult but it was the only conclusion we could come to for such
irrational and bizarre behaviour. It was clear that being able to carry on with
the works was going to be impossible to complete.86
[63] Mr Freeman also states that the Cowens’ actions have ‘made the site
unsafe’ and that there is an ‘indefinite suspension on the job’.87 Mr Freeman
states that it was made clear by Mr Cowen that even if they completed the
job that Mr Cowen was ‘going to take legal action…’.88
[64] It is Mr Freeman’s evidence that the Builder entered into the contract in
good faith and refers to delays attributed to by the Cowens’ planned
overseas trip, a long and protracted dispute and legal battle between the
Cowens and their neighbour and access through the neighbouring
property.89 Mr Freeman refers to Mr Cowen as being a ‘litigious person’ and
that the delays and interference all started when money seemed to become
an issue.90
[65] Mr Freeman’s evidence is that the Builder had ‘every intention of finishing
the job’ and refers to Mr Cowen putting ‘one obstacle after another in our
way’.91 Mr Freeman refers to legal threats with ‘ridiculous claims’, Mr Cowen
using ‘every building organisation’ he could to attempt to get his way, Mr
Cowen’s ‘erratic and violent tendencies’, issues with neighbours and
attempts made by the Builder to compromise that were ‘abused or
ignored’.92 Mr Freeman states that when Mr Cowen compromised safety on
site ‘it was the last straw and we just could not carry on’.93 Mr Freeman
states:
85 Exhibit 32, [71].
86 Ibid, [71].
87 Ibid, [73].
88 Ibid.
89 Ibid, [75].
90 Ibid, [76] to [78].
91 Ibid, [79] to [80].
92 Exhibit 32.
93 Ibid.
-- 18 of 64 --
19
We had every intention of finishing the job or we would not have taken it on
in the first place. The most difficult and involved part of the works was
completed and he [Mr Cowen] was happy with it but then he continued to
put one obstacle after another in our way, threaten us legally with ridiculous
claims and use every building organisation he could to attempt to get his
way. [His] erratic and violent tendencies, issues with neighbours and police
all combined to make this an impossible job to complete. Every attempt we
made to compromise or move forward was abused or ignored. Finally, when
he compromised safety on site it was the last straw and we just could not
carry on. This job has wasted so much of our time and efforts and interfered
with our many other projects which are all on target and mostly completed
as this job could have been.94
[66] Mr Cowen’s evidence is that he sent an email dated 1 October 2014
indicating that the boarding could remain.95 Mr Cowen was cross-examined
at the hearing about the emails exchanged with the Builder on 1 October
2014 including the email sent by the Builder referring to the placement of
an indefinite suspension on the works as at 1 October 2014. Mr Cowen’s
evidence in relation to the Builder’s email suspending the works is that he
was ‘quite sort of shocked and horrified’. Mr Cowen was questioned about
what he wanted to see happen in going forward in the context of having
received the Builder’s email dated 1 October 2014. Mr Cowen said ‘we
wanted to get things fixed up as soon as possible and get things back on
track’.96 The relevant extracts from the transcript is as follows:
Question: …what was your personal reaction to receiving this document?
Mr Cowen: I was quite sort of shocked and horrified. We were in the midst
of negotiating for the door suppliers and things like that. I wouldn’t have
actually received it, I think, until later that day, probably more like 4 o’clock.
The fact that they said that they were immediately placing an indefinite
suspension was a concern. I looked…up the contract and thought, well, what
are the issues we have to deal with, and it wasn’t very clear. I think it was
clear that they’re not supposed to do it by email. They’re supposed to do it
by mail or fax or something, or by hand. I think at that stage I would have –
I think I probably drafted a reply and sent it off and…
…
Questions: …So after receiving this email and having that initial
reaction which you’ve just described, what was your principal or what was
your concerns, or what did you want to see happen in going forward from
here? What did you want to achieve, I guess is…
Mr Cowen: We…wanted to get things fixed up as soon as possible
and get things back on track.
94 Exhibit 32, [79] to [80].
95 Exhibit 4, [204].
96 Transcript dated 5 May 2016, T4-115.
-- 19 of 64 --
20
Question: And when you say get things fixed up as soon as possible and
get things back on track, what things are you talking about?
Mr Cowen: Well, they…immediately placed a suspension on the
works…we wanted to get that immediate suspension taken off.
Question: Yes. Okay. And how did you think you might achieve that goal?
Mr Cowen: By email…by…contacting them as soon as possible and
saying, you know, if…this is really upsetting you, you can leave them
there...97
[67] Mr Cowen was cross-examined at some length about his evidence. When
questioned about the emails sent by him on 1 October 2014 to the Builder
and the highlighting (in red and black) of certain words in relation to the
removal of the boarding, Mr Cowen maintained his evidence. Mr Cowen
said that he ‘requested’ (not demanded) the removal of boarding. Mr Cowen
said that he sends emails ‘all over the world’ with multiple colours.98 Mr
Cowen said during cross-examination that during the telephone
conversation with Mr Findlay (on 30 September 2014) he ‘requested’ that
the boards come down.99
[68] Mr Cowen was cross-examined at some length about his request for the
Builder to provide a copy of the safe work and management system (the
SWMS) referred to in his email to the Builder dated 1 October 2014. Mr
Cowen was questioned about where in the contract it says that he can get
a copy of the relevant SWMS. Mr Cowen said that a representative from
Occupational Health and Safety Queensland told him to ask for the
document. Mr Cowen said that he was referred to Occupational Health and
Safety Queensland by a representative from the QBCC.100 Mr Cowen said:
…when we first complained to him [Lewis Hayes from the QBCC] back in
July about the way we were being treated. When I told him about the
boarding up, he referred me to Occupational Health and Safety,
Queensland. Now, the people at Occupational Health and Safety,
Queensland they’ve obviously told me to – to ask for an SWMS, whatever
that is. I think it’s something to do with scaffolding has to be erected before
you can taken down a verandah railing. So I guess what Occupational Health
and Safety, Queensland were trying to say to me, they need to have this,
whatever it is, SWMS before they can actually restrict the verandah railings,
so I was basically indirectly following QBCC’s own advice, and they were the
one to tell…101
[69] Mr Cowen said that he rang up Workplace Health and Safety (WH&S) and
they had never heard of ‘anyone’ boarding up all of the windows in the
house referring to them (meaning WH&S) as being in ‘disbelief’.102 Mr
97 Transcript dated 5 May 2016, T4-114 to T4-115.
98 Transcript dated 8 February 2016, T1-88.
99 Ibid, T1-85, L43-47 to T1-86.
100 Ibid, T1-89.
101 Transcript dated 8 February 2016, T1-89, L15-24.
102 Ibid, T1-91 to T1-92.
-- 20 of 64 --
21
Cowen maintained his evidence during cross-examination that he
requested a copy of the SWMS be provided by the Builder because ‘that’s
what [he] was told to ask for’.103 Mr Cowen said that he believed he was
‘probably’ entitled to know what was ‘going [on] with workplace health and
safety’ and referred to the contract and his obligation to provide signage
under Part A and item 1.03.104 Relevantly, Schedule Part A of the contract
and item 1.03 provides as follows:
All hoardings, signs and scaffolding provision are the responsibility of the
Contractor unless listed below:
The Owner is responsible for providing the following:
All signage required under Builders OH&S obligations. 105
[70] I accept Mr Cowen’s evidence given in relation to his requests to the Builder
to provide a copy of the SWMS contained in his email dated 1 October
2014. I accept Mr Cowen’s evidence that he was told by a representative
from workplace health and safety to request the SWMS document be
provided by the Builder. I also accept Mr Cowen’s evidence and that he
believed he was entitled to know about workplace health and safety issues
because of his obligation under the contract to provide signage in relation
to ‘OH&S’ as provided in the contract.
[71] I also accept Mr Cowen’s oral evidence given in relation to his email dated
1 October 2014 sent at 4:40pm to the Builder. It is Mr Cowen’s evidence
that by sending the email he would allow the boarding to remain.106 Mr
Cowen’s evidence given during re-examination is that (by sending the email
on 1 October 2014 at 4:40pm) he wanted to the get the suspension taken
off. Mr Cowen said that the words used in his email ‘pending further
advice…’, were not intended to be ‘conditional’.107 Mr Cowen said:
…when I said pending- if I wanted to say conditional, I would have said
conditional. At the time, I wrote this, I wouldn’t have exactly known what was
going to be in the SWMS. My main purpose was to basically get on with the
job, but make sure we complied with the law. I guess that’s the main purpose
of this…108
[72] During re-examination, Mr Cowen was asked to clarify his evidence about
his use of the words ‘pending’ in his email to Mr Freeman. Mr Cowen said
that the intention was that the boards would remain unless there was some
reason that they had to come down and said ‘because the SWMS didn’t
require them there, or whatever’.109
103 Transcript dated 8 February 2016, T1-94.
104 Ibid T1-97 and see exhibit 4, p 37.
105 Exhibit 4, p 37.
106 Transcript dated 9 February 2016, T2-98.
107 Transcript dated 5 May 2016, T4-116 to T4-117.
108 Ibid, T4-125 to T4-126.
109 Transcript dated 5 May 2016, T4-126.
-- 21 of 64 --
22
[73] I am not satisfied to the required standard based on the evidence before
me that the Cowens interfered with workplace site safety and/or the
performance of the works by requesting verbally and/or in writing that the
boarding be removed by the Builder.
[74] I have accepted Mr Cowen’s evidence given about his requests made to
the Builder to provide a copy of the SWMS and that he (Mr Cowen) was
entitled to know about workplace health and safety issues because of his
contractual obligation to provide signage in relation to occupational health
and safety as provided in the contract. I have also accepted Mr Cowens’
evidence given in relation to the email sent by him on 1 October 2014 at
4:40pm to the Builder that (as provided in the email) he would allow the
boarding to remain.
[75] It is open to me to find that the Cowens in sending the email dated 1 October
2014 at 4:40pm were not acting outside the scope of the contract and were
not interfering with workplace health and safety, as contended by the
Builder.
Did the Cowens interfere with the performance of the works and
workplace health and safety – entering the construction site and
speaking to contractors?
[76] I have considered the contentions made by the Builder about Mr Cowen’s
conduct during the performance of the work and at the site on 2 October
2014.
[77] In written submissions, the Builder contends that work site safety is solely
the responsibility of the Builder and the Cowens interfered with the work
and breached safety rules on an ongoing manner contrary to and in breach
of the contract.110 The Builder contends that ‘for safety’s sake’ a suspension
of the works had to be instigated and the Cowens were advised of this and
the reason for it.111
[78] It is non-contentious that two employees (referred to as the carpenters)
attended the site on 2 October 2014 at approximately 7:00am to remove
the boarding. Mr Freeman’s evidence, set out in these reasons at [59]
above, is that on 2 October 2014 Mr Cowen ‘approached [the carpenters]
and basically told them to get off his site’.112 Mr Freeman states that no
matter what the Builder did, Mr Cowen was going to do everything possible
to ‘frustrate our moving forward and completing the job’.113
[79] Mr Freeman in representing the Builder relies on the evidence of Alex
Mizanowski, Carpenter and Mark Kocks, Construction Manager in relation
to the conduct of Mr Cowen on 2 October 2014 and otherwise during the
performance of the works. Mr Freeman also relies on photographs that he
110 The Builder’s written submissions filed on 1 June 2017, p 2.
111 Ibid.
112 Exhibit 32, [71].
113 Ibid, [71].
-- 22 of 64 --
23
says show Mr Cowen on the building site wearing inappropriate footwear
and an email dated 10 July 2014.114 Mr Freeman says that the email dated
10 July 2014 states that (in effect) Mr Cowen entering the construction site
in ‘open toed shoes’ is unacceptable.115
[80] Mr Mizanowski’s evidence contained in his statement is that Mr Cowen
would ‘frequently walk onto the work site unauthorised’ wearing sandals
and no proper personal protection equipment or appropriate gear.116 In
relation to what took place on 2 October 2014, Mr Mizanowski states that
he and ‘Jarrod’ (a first year apprentice) went to the site at approximately
7:00am to remove all of the safety boardings. Mr Mizanowski states that Mr
Cowen came out ‘very disturbed and angry’ and was talking in a
‘threatening manner as though we were going to be in some real trouble’.117
Mr Mizanowski states that Mr Cowen was ‘very confronting’ and ‘we felt
very uncomfortable’ and states that Mr Cowen ‘started saying that we could
take certain ones off but not others’.118 Mr Mizanowski states that Mr Cowen
‘became very threatening and mentioned his son was a “very big burly
bloke” one we wouldn’t want to piss off and that he would be staying in the
house’. Mr Mizanowski states that Mr Cowen ‘demanded we stop working’.
Mr Mizanowski rang Mr Freeman explaining what had happened and Mr
Freeman told them to leave.119
[81] Mr Mizanowski was cross-examined at the hearing about his statement.
After carefully considering Mr Mizanowski’s oral evidence, I am not satisfied
to the required standard that Mr Cowen frequently walked onto the work
site unauthorised and was threatening towards Mr Mizanowski and another
employee on 2 October 2014.
[82] During cross-examination, Mr Mizanowski said that he did have occasion
to tell Mr Cowen to leave the site because he was not wearing proper
protective clothing but could not recall when.120 In relation to what took
place on 2 October 2014, Mr Mizanowski said that he was instructed to
‘remove everything’ by the Builder.121 It is Mr Mizanowski’s evidence that
none of the boarding was removed.122 Mr Mizanowski said the they started
to remove the boarding from downstairs and stated that ‘Mr Cowen came
out and stopped us’.123 Mr Mizanowski refers in his statement to Mr Cowen
being ‘very confronting’ but when questioned at the hearing acknowledged
that he shook Mr Cowen’s hand before he left the site.124
114 See exhibits 33 (attachment 20) and 37.
115 Exhibit 4, p 247.
116 Exhibit 50.
117 Ibid.
118 Exhibit 50.
119 Ibid.
120 Transcript dated 22 February 2017, T7-14.
121 Ibid, T7-16.
122 Ibid, T7-20.
123 Ibid, T7-20.
124 Ibid.
-- 23 of 64 --
24
[83] Mr Mizanowski was questioned about whether Mr Cowen ordered him off
site on 2 October 2014. Mr Mizanowski said:
He didn’t exactly – well, from what I’ve – well, he didn’t exactly order us to
get off site, but he came across very aggressive and very irritated and said
why – why this and why that and I basically told him that we were just – we
were instructed to – we were just following instructions. It just seemed to me
like he was taking it out on us and asking if I was a Builder or [indistinct] sort
of felt a bit threatened at the time. You know, it was the way he came across
and sort of questioning the things we were saying…so I called [Chris
Freeman] and just basically asked him where do we go from here. I told him
about the situation and he said it’s best if we just packed our stuff and left or
avoid any more – any more dramas.125
[84] Mr Mizanowski said that Jarrod (the first year apprentice) calmed Mr Cowen
down and said that he shook Mr Cowen’s hand and said that Mr Cowen
‘just sort of walked in peace or whatever. Just so we didn’t leave on bad
terms’.126 Mr Mizanowski said:
Well, in the meantime, while I was on the phone to Mr Freeman, Jarrod our
first year apprentice was trying to talk to him and sort of calm him down and
explain to him that we were just doing our job and don’t take it out on us sort
of thing. Like, I believe he shook his hand and then I think before I left I’m
like, “Look, I’m sorry about, you know, being – you were upset [indistinct], if
there’s been any misunderstanding or disagreement”. Then I believe I shook
his hand and he just – just sort of walked in peace or whatever. Just we we
didn’t leave on bad terms.127
[85] Mr Kocks’ evidence is contained in diary entries attached to his
statement.128 Mr Kocks’ diary entries refer to work completed at the site and
observations made by him about Mr Cowen on site. Mr Kocks refers to Mr
Cowen walking onto the construction site wearing a pair of thongs despite
the health and safety regulations and warnings from the Builder. Mr Kocks
also refers to Mr Cowen disrupting the contractors from working. Some of
the diary entries made by Mr Kocks are as follows:
[On 29 January 2014]
HGH [Highgate Hill] still removing existing block wall [and] removing rubbish
from site.
Peter Cowen is still just walking onto the construction site at any time he
feels like it [and] only wearing a pair of thongs, despite the health [and] safety
regulations and warnings from us.
125 Transcript dated 22 February 2017, T7-26.
126 Ibid, T7-27.
127 Ibid, T7-27.
128 Exhibit 48.
-- 24 of 64 --
25
He [Mr Cowen] is also disrupting all the contractors [and] stopping them from
doing their job effectively because of his storries [sic] that he feels he has to
share with everyone.
…
[On 12 September 2014]
Pouring concrete at HGH. Of course Peter [Cowen] was up to his same old
tricks telling us it was all wrong. Hugh [Finlay] had to drive up from the office
to calm him down…
[On 1 October 2014]
Didn’t work crook with bronchitis.
…
Mr Cowen was up to his same tricks saying we had no right to board off his
windows. That man is insane they are there for his own safety.
[On 2 October 2014]
Alex [and] Jarrod at HGH to take down the safety boarding that Mr Cowen
insisted [and] demanded to be taken down for the last 2 days. …But when
Alex [and] Jarrod arrived on site Mr Cowen immediately came out abusing
[and] threatening them both [and] kicked them off the job saying they had no
right being there. Unbelievable…
I still didn’t work, crook with bronchitis.129
[86] Mr Kocks was cross-examined at the hearing about his diary entries
contained in his statement. After carefully considering Mr Kock’s oral
evidence, I am not satisfied to the required standard that Mr Cowen
frequently walked on to the work site unauthorised and was threatening
towards Mr Mizanowski and another employee on 2 October 2014. Mr
Kocks accepted during cross-examination that he did not witness the
events alleged to have taken place with Mr Cowen on 1 and 2 October 2014
because he was off work sick.130 Mr Kocks accepted when questioned that
his diary entry on 1 October 2014 reflects what he was told from the workers
on the site.131 Mr Kocks accepted when questioned about his diary entry on
2 October 2014 that he did not hear or observe any of Mr Cowen’s conduct
on site because he was not there in person.132
[87] In relation to Mr Cowen walking onto the site, Mr Kocks referred to this
happening ‘practically every day’ but accepted that he was not on site every
day.133 During cross-examination by the QBCC, Mr Kocks said that he did
129 Exhibit 48.
130 Transcript dated 21 February 2017, T86.
131 Ibid.
132 Transcript dated 21 February 2017, T88.
133 Ibid, T96.
-- 25 of 64 --
26
not make a diary note of every day of the job.134 In relation to the entry made
on 12 September 2014, Mr Kocks confirmed that he was not present to
witness Mr Cowen being on site and said that ‘it happened after I left site’.135
Mr Kocks said that he got phone calls from the office and the contractors to
say that ‘he’s [Mr Cowen] really blowing up’.136 During cross-examination
Mr Kocks accepted that he kept diary notes of Mr Cowen entering the
site.137 Mr Kocks accepted that the only diary entry made by him in relation
to witnessing Mr Cowen walking onto site in sandals was made by him (Mr
Kocks) on 29 January 2014 together with the photographs taken by him on
or about the same date.138 The relevant extracts from the transcript is as
follows:
Q…on Friday, 12 September [2014], when you say Peter was up to his same
old tricks and that’s- and you described what you meant by that there. Were
you on site to witness those things that you just described there or did that
happen after you’d left the site for the day?
A It happened after I left the site.
Q…And how did you come to know – how did you come to prepare this diary
note? What information are you basing the diary note on?
A When I’d left the site I got phone calls from the office and the contractors.
The concreters that were on site and from the office to say that he’s really
blowing up. It’s- you’re doing it all wrong. Are you over there? And I said, no,
I’m not. I was over at [indistinct] then…so that’s why Hugh came…Mr Cowen
preferred to talk to Hugh rather than anyone else.
Q And you said the day before on the Thursday there may have been some
similar circumstances occurring but, again, you weren’t there for that?
A No.
Q You weren’t there to witness that?
A No139
…
Q Mr Kocks, is there any other record anywhere that makes reference to Mr
Cowen being on site in sandals in such a way that it creates a workplace
health and safety issue?
A Not directly
134 Transcript dated 21 February 2017.
135 Ibid, T96.
136 Ibid.
137 Ibid, T111.
138 Ibid, T114. See exhibits 48 and 37.
139 Transcript dated 21 February 2017, T96-97.
-- 26 of 64 --
27
Q… and given that you’ve said it’s important to keep these records for
workplace health and safety reasons, I put it to you that if he had been, you
would have kept a record of it. You’d accept that?
A Having a record like the 29th of January [2014]…
Q …there’s no other record referencing him…?
A Just because I didn’t write it in my diary doesn’t mean that it didn’t happen.
…
Q Your evidence earlier that you reviewed your diaries in preparing these
notes. And so am I, therefore to take it that if there had been such a record,
you would have transcribed it into the first two typed pages?
A I wasn’t going to write down every time that I was on site at Highgate Hill
I saw Mr Cowen on site in inappropriate footwear.
…140
[88] Mr Cowen gave evidence in relation to what took place on site on 2 October
2014. In his statement, Mr Cowen states that two new employees were on
site and had ‘no idea’ and started to remove the wrong boards.141 Mr Cowen
states:
After unsuccessfully attempting’ to contact the Contractor we requested that
the two workers go away and obtain clarification or corrected instructions
from their supervisor about the correct work to be carried out.142
The Contractor had not performed any work on site since 26 September
2014, apart from the clean-up and rectification work in October 2014
requested by Workplace Health and Safety Officers to make the site safer.143
[89] Mr Cowen was cross-examined about the alleged interference with site
safety and the performance of the work. In particular Mr Cowen was
questioned in relation to whether or not he regularly entered the workspace
without the permission of the Builder. Mr Cowen said ‘no’ not on a ‘regular
basis’.144 Mr Cowen clarified his evidence and said ‘only by invitation or
perhaps necessity’.145 Mr Cowen said that the ‘bricklaying gang’ asked him
to make them cups of tea so on that occasion he took the tea to them.146
Relevant extracts of the transcript are as follows:
140 Transcript dated 21 February 2017, T113-115.
141 Exhibit 4, [205] to [208].
142 Ibid.
143 Ibid.
144 Transcript dated 9 February 2016, T2-57.
145 Ibid.
146 Ibid, T2-58.
-- 27 of 64 --
28
Q I put it to you that you went into the work space in the downstairs works
made pursuant to the contract on more than one occasion; is that correct or
not?
A Only by invitation or perhaps necessity.
…
Q I put it to you that you have entered into that work space on a number of
occasions without being invited, yes…
A No.
Q So your evidence is you have never entered that work space where the
Builders are working pursuant to the contract without being invited; is that
your evidence?
A I just told you before it was only by necessity or if I was asked. For
example, the bricklaying gang asked me to make them cups of tea, right, so
on that occasion, I took down the tea to them…and I would call that being
invited.
…
Q I also put it to you that you have entered the work space on a number of
occasions wearing inappropriate clothing for example, open-toed shoes; is
that correct?
A Basically, yes.
…
Q In addition, you regularly spoke to Builders and subcontractors in relation
to their work?
Q Well, obviously, you have to…Well, they come – I’m in the middle of doing
things and they come and ask you to borrow tools or they come and ask you
what do you want done here? Is it all right to leave those crooked, as – that
was one of the very first things that was asked by Mark Kocks, is it okay to
leave this door frame crooked? I said, yes, it’s – that doesn’t worry me. It’s
in – it’s in the workshop.147
[90] I found Mr Cowen to be honest and open in giving his evidence. Mr Cowen
accepted when questioned that he entered the work space wearing
‘inappropriate clothing’ for example open-toed shoes.148 Mr Cowen also
accepted when questioned that he spoke to subcontractors referring to
them borrowing tools and asking him about what had to be done.149 Mr
147 Transcript dated 9 February 2016, T2-58 to 2-59.
148 Ibid.
149 Ibid, T2-59.
-- 28 of 64 --
29
Cowen’s evidence is that the contract permitted the Cowens to remain living
in the house.150
[91] I am not satisfied to the required standard, having considered all of the
evidence, that the Cowens interfered with work site safety or the
performance of the work. I am not satisfied to the required standard that Mr
Cowen interfered with the work or work site safety by entering the
construction site without permission and that he would hold up contractor’s
work by talking to them.
[92] Mr Freeman accepted during cross-examination that the Cowens lived on
site from the start of the works.151 Mr Freeman also accepted during cross-
examination that other than the email to Mr Cowen dated 10 July 2014, the
Builder did not issue any notice under the contract to the Cowens requiring
them to remedy any alleged breach.152 I accept Mr Cowen’s evidence that
he spoke to subcontractors when they asked him questions about
borrowing tools or (as stated) ‘what had to be done’. I accept Mr Cowen’s
evidence that he did not enter the site on a regular basis and entered the
worksite wearing inappropriate clothing (footwear) when invited to do so by
the contractors working onsite.
Did the Cowens interfere with the performance of the works – other
alleged conduct and delays to the work?
[93] The Tribunal has considered other issues concerning Mr Cowen’s conduct
and alleged delays to the work.
[94] Mr Freeman, on behalf of the Builder, contends that there were delays to
the works attributed to by the Cowens as a result of latent conditions
including, amongst others, the electrical cable buried under the dirt on the
eastern side of the block; and the sewer.153 Mr Freeman says that the costs
and quotes were organised and requests to sign variations for work were
sent to the Cowens. Mr Freeman says that the owner has a responsibility
under clause 14.4 of the contract to consent to a reasonable or necessary
variation. Mr Freeman also says that the Cowens failed to pay the security
deposit under the contract as required and made requests for a schedule
of works.
[95] Mr Freeman gave oral evidence at the hearing about his dealings with Mr
Cowen and the renovation work. Mr Freeman accepted when questioned
that the relationship between the Builder and the Cowens was good in the
early part of the contract and stated that from around 21 February 2014
things changed and stated there were ‘difficulties’.154 Mr Freeman referred
150 Transcript dated 9 February 2016, T2-60.
151 Transcript dated 21 February 2017, T29, L30-31.
152 Ibid, T131, L31-36.
153 See the transcripts dated 8 February 2016 and 15 February 2017; and the Builder’s
written submissions filed on 1 June 2017.
154 Transcript dated 15 February 2017, T1-24 to T1-27, see T1-27, LL6-15; and the
Builder’s written submissions filed on 1 June 2017.
-- 29 of 64 --
30
to difficulties getting agreement on items that needed to be changed, not
answering requests, not completing variation forms and failing to put a
security deposit into the bank in accordance with the contract.155 When
questioned about when the relationship between the Builder and Mr Cowen
‘started to sour’ Mr Freeman gave evidence that it was when Mr Cowen
‘challenged payments’.156 Mr Freeman stated that Mr Cowen sent a legal
letter asking us (the Builder) to give him back the entire previous claim and
stated ‘that’s when it soured’.157
[96] Mr Freeman stated that work commenced in January 2014 referring to the
cutting out of an existing wall and the start of the excavation on the western
side of the property (referred to as the right hand side or higher side when
facing the property from the street).158 Mr Freeman accepted that the
ground works were to be split by completing ground and slab work on the
western side (the right hand side) and then the eastern side.159
[97] Mr Freeman’s evidence is that the works to the western side of the property
were completed by 24 February 2014.160 Works to the eastern side
commenced between 28 February 2014 and 20 March 2014.161 Mr
Freeman stated that it was during that time (between 28 February 2014 and
20 March 2014) that the Builder discussed issues with the sewer, issues
with some electrical pipes and an error with the plans for the driveway.162
[98] Mr Freeman accepted when questioned that from about 25 March 2014 the
Builder did not perform any work on site for approximately 5 months.163 Mr
Freeman in giving his evidence referred to the Builder dealing with issues
during this time in relation to the sewer.164 Mr Freeman accepted when
questioned that it was during this time that a number of disputes started to
arise between the Builder and Mr Cowen.165
[99] The contract sets out the stages of the work to be performed. The payments
for each of the stages were to be claimed by the Builder when the works
were completed. Mr Freeman accepted when questioned that the schedule
of payments in the contract did not reflect what the Builder did.166 Mr
Freeman accepted that when he issued a payment for the second stage of
work as provided under the contract on 14 February 2014 he had not done
all of the work under the contract for the footings and retaining wall stage.167
155 Transcript dated 15 February 2017 T1-24 to T1-27, see T1-27, LL6-15; and the
Builder’s written submissions filed on 1 June 2017.
156 Ibid.
157 Transcript dated 15 February 2017, T1-39, L35-38.
158 Ibid, T1-32, L 31-35.
159 Ibid, T1-36.
160 Ibid, T1-40.
161 Ibid, T1-42.
162 Ibid, T1-45.
163 Ibid, T1-48.
164 Ibid, T1-48.
165 Ibid, T1-48.
166 Ibid, T1-36.
167 Ibid, T1-38.
-- 30 of 64 --
31
Mr Freeman accepted when questioned that Mr Cowen paid for that stage
of work and for the other stages of work performed to the groundwork and
carport stage. Mr Freeman accepted that he had not done the eastern side
work for those works but had issued the full payment claim to the Cowens.
In relation to the third payment claim in the amount of $36,086, Mr Freeman
again accepted that he had issued the full payment claim but had not
completed all of the level slab stages.168
[100] It is non-contentious that Mr Cowen and Mr Freeman agreed that in relation
to the third payment claim, Mr Cowen would only pay 50% because Mr
Cowen had raised an issue about the eastern side not having been
started.169
[101] In relation to payment of the security deposit, Mr Freeman accepted during
cross-examination that Mr Cowen responded to the breach notice and paid
the money (in about August or September 2014), in Mr Freeman’s words
‘extremely reluctantly’.170
[102] Mr Freeman accepted when questioned that by 10 July 2014 all of the
disputes relating to deposits and variations had been resolved by Mr
Cowen.171 It is Mr Freeman’s evidence that the Builder advised the Cowens
on 7 August 2014 that they would be starting work on 12 August 2014.172
Mr Freeman did not accept when questioned that the works were only 50%
complete at that stage.173 When questioned about the stage claims issued
to the Cowens for payment, Mr Freeman accepted that the first three stages
(about 50% of the job) had been issued. Mr Freeman accepted that he had
not yet got to the framing and steel beam stage and the enclosed stage.174
It is Mr Freeman’s evidence that as at August or September 2014 it was the
Builder’s ‘hope and expectation’ that the works would be completed by 27
October 2014 (the revised date).175 Mr Freeman gave oral evidence that
everything was ‘lined up ready to go’. Mr Freeman stated that ‘we were
prepared to hit hard right there and then until we were once again
interrupted’.176
[103] In relation to completing the contracted works, Mr Freeman stated that ‘we
[the Builder] were unhappy’.177 Mr Freeman accepted when questioned that
by 1 October 2014 the Builder attempted to reduce the scope of works. Mr
Freeman stated:
…we thought if we could make it easier and get it finished quicker…remove
items that weren’t important, because Mr Cowen had actually, in fact,
168 Transcript dated 15 February 2017, T1-39.
169 Ibid, T1-39.
170 Ibid, T1-49.
171 Ibid, T1-55.
172 Ibid, T1-56.
173 Ibid, T1-56.
174 Ibid, T1-57.
175 Ibid, T1-67.
176 Ibid, T1-67 to T1-68.
177 Ibid, T1-68.
-- 31 of 64 --
32
already flagged that he wanted to change items, particularly on the top of
the suspended slab…178
[104] Mr Freeman accepted when questioned that the scope of works was not
reduced by 1 October 2014 and that there was as at that date only 26 days
remaining in which to complete the works. Mr Freeman did not accept
however that the reason why the Builder was ‘trying to drop’ some items of
work from the scope of works was because there were 26 days remaining
to complete the contract works.179
[105] It is common ground that an agreement was not reached between the
Cowens and the Builder to reduce the scope of works. Mr Freeman’s
evidence is that the Builder was keen to get the job done.180
[106] In relation to providing a schedule of works, Mr Freeman accepted when
questioned that he volunteered to provide this to the Cowens.181 Mr
Freeman’s evidence is that on 7 August 2014 the Builder sent the Cowens
notice indicating that the date for completion of the works was 26 October
2014.182 Mr Freeman accepted when questioned that the Builder had not
complied with clause 8.2 of the contract that requires the Builder to give
written notice of when the work commenced and the date for practical
completion.183
[107] It is Mr Freeman’s evidence that Mr Cowen put ‘obstacle, obstacle,
obstacle’ in front of the Builder.184 Mr Freeman stated that Mr Cowen told
Hugh Findlay that even if the Builder completed the job he would be taking
legal action. Mr Freeman stated that ‘that’s why we went to the QBCC’.185
[108] It is open to me to find, based on the evidence before me, that on 7 August
2014, notwithstanding any interference with the works or breaches of the
contract by the Cowens (as alleged by the Builder), the Builder elected to
proceed with the contract. On 7 August 2014, the Builder gave notice of its
intention to start work and provided to the Cowens an adjusted date for
practical completion.186
[109] In an email dated 7 August 2014, the Builder advised the Cowens, through
their legal representatives, that the Builder would require ‘unrestricted
access to the building site from 12 August 2014’.187 On 11 September 2014
the Builder confirmed its position with the Cowens that it intended to work
towards the completion date of 26 October 2014. In an email sent to the
Cowens’ legal representative dated 11 September 2014, Mr Freeman refers
178 Transcript dated 15 February 2017, T1-68, L44-47.
179 Ibid, T1-70.
180 Ibid, T1-72.
181 Ibid, T1-57.
182 Ibid, T1-60.
183 Ibid, T1-61.
184 Ibid, T1-109.
185 Ibid, T1-112.
186 Exhibit 33, attachment 23.
187 Ibid, attachment 22.
-- 32 of 64 --
33
to previous delays by the Cowens and states that ‘[s]hould we exceed this
date [26 October 2014] by any small margin there are liquidated damages
figures stated in the Residential Building Contract’.188 The relevant extract
from the email is as follows:
…To avoid having this statement repeated we no longer make any
statements regarding dates of work. The only statement we make is that the
completion date is 26 October 2014 and that is what we are working towards.
Should we exceed this date by any small margin there are liquidated
damages figures stated in the Residential Building Contract.
It should be noted that all works were completed in an extremely diligent
manner (as even referred to in an email received from your client) right up
until your client caused these delays with entirely unnecessary actions,
mediation meetings, legal letters and the like. Had we been left alone to
complete our works as “The Builders” this job would have been completed
months ago. He is detailing delays of a few days but his action have caused
delays of months. Seriously, if he wants the job done, stop interrupting us
and let us focus on doing the job, not talking about it.
Any further communications regarding scheduling will be ignored…189
[110] I am not satisfied to the required standard having considered all of the
evidence that after July or August 2014, there was a failure by the Cowens
to pay money owing under the contract, requests for a schedule of works
and other alleged conduct resulting in delays to the completion of the work.
Mr Freeman accepts that by 10 July 2014 all of the disputes relating to
deposits and variations had been resolved.190 I find that even if there was
conduct by the Cowens, as alleged by the Builder, the evidence shows that
all disputes were resolved by 10 July 2014 and the Builder elected to
proceed with the contract by giving notice to the Cowens on 7 August 2014
of the adjusted date for practical completion.
Did the Builder lawfully suspend the works?
[111] Clause 16 of the contract provides that the contractor may suspend
performance of the works where the owner is in substantial breach of a term
of the contract. The contractor must give written notice to suspend the works
and the owner must remedy any breach within ten (10) business days. The
contractor must recommence the works within ten (10) business days of the
owner remedying the breach.
[112] The evidence shows that the Builder did not give notice to the Cowens as
required by clause 16 of the contract. The evidence also shows that no
boarding that was related to the safety issue (upstairs) was removed prior
to the Builder suspending the works. The Builder did not remove any
boarding upstairs after receiving the Cowens’ email dated 1 October 2014
188 Exhibit 4, p 263.
189 Ibid.
190 Transcript dated 15 February 2017, T1-55.
-- 33 of 64 --
34
(sent at 4:40pm) and after the carpenters were sent to the site on 2 October
2014.191
[113] Mr Freeman accepted during cross-examination that the Builder was only
declaring the site unsafe the moment the boarding came down.192 Mr
Freeman accepted when questioned that the Builder responded to Mr
Cowen’s email on 1 October 2014 (at 2:06 pm) by declaring the works to
be unsafe and that the Builder was immediately placing an indefinite
suspension on the works.193 Mr Freeman stated that ‘we are anticipating
this is going to be a safety issue, so we would have to do that until it’s
resolved’.194 Mr Freeman maintained his evidence that the Builder was
suspending the works by email dated 1 October 2014 and stated ‘in
conjunction with the fact we’re saying we’re removing the hoardings’.195 Mr
Freeman accepted when questioned that the Builder was not removing the
boarding until the following day (2 October 2014).196
[114] During cross-examination Mr Freeman was referred to the Builder’s email
dated 1 October 2014 (sent at 2:06pm) and was questioned about what
matters needed to be resolved in relation to the suspension of the works as
stated in the email. Mr Freeman stated ‘all matters of safety and access’.197
Mr Freeman referred to continual interference, breaches of the contract by
Mr Cowen in talking to subcontractors, walking onto the construction site
without permission and without gear.198
[115] Mr Freeman accepted when questioned that the Builder had not issued a
notice under clause 16 of the contract. When questioned about whether Mr
Cowen was in breach of the contract at the time the Builder suspended the
works, Mr Freeman stated, ‘not formally in breach’.199 The relevant extract
from the transcript is as follows:
Q…You didn’t issue a notice under clause 16 of the contract, suspending
the works did you?
A No
Q And Mr Cowen was not in breach of the contract at the time you
suspended the works, was he?
A Not formally in breach.200
[116] During cross-examination Mr Freeman was referred to Mr Cowen’s email
dated 1 October 2014 (sent at 4:40pm). Mr Freeman was questioned about
whether he accepted that Mr Cowen withdrew his request to have the
191 Transcript dated 15 February 2017, T-119, L6-15 and T1-116.
192 Ibid, T1-97.
193 Ibid.
194 Ibid, T1-97.
195 Ibid T-98.
196 Ibid.
197 Ibid, T-98.
198 Ibid.
199 Ibid, T-99.
200 Ibid, T-99, L25-35.
-- 34 of 64 --
35
boarding taken down on 1 October 2014. Mr Freeman stated ‘not prior to
our people being on site’.201 Mr Freeman’s evidence is that the Builder’s
business shuts at 4:00pm and that he does not choose to do business
outside of business hours.202 Mr Freeman does not dispute that Mr Cowen
sent his email on 1 October 2014 (at 4:40pm) withdrawing his request to
remove the boarding of ‘those specific doors’.203 Mr Freeman stated
however, that Mr Cowen’s request was made with ‘other conditions as well
which he’s not entitled to ask for’.204 Mr Freeman referred to Mr Cowen’s
statement (in the email) ‘pending further advice’. Mr Freeman stated ‘which
means until he [Mr Cowen] decides that that’s okay or not’.205 Mr Freeman
referred to Mr Cowen’s request to provide an SWMS and stated that he (Mr
Cowen) is making conditions on that (referring to the request) and stated
that the Builder is not obligated under the contract to provide it.206
[117] Mr Freeman accepted when questioned that even after he received Mr
Cowen’s email dated 1 October 2014, the Builder maintained its
suspension. Mr Freeman stated however that Mr Cowen agreed to leave it
(the boarding) there temporarily and stated ‘until he sees otherwise’.207 Mr
Freeman was questioned about other options available to the Builder (other
than suspending the works). Mr Freeman stated that the Builder is
responsible for workplace, health and safety and that ‘we deemed that was
the appropriate action’.208 When asked if Mr Freeman would have sent the
carpenters to site had he read Mr Cowen’s email he stated: ‘No, I don’t
imagine I would have’.209
[118] Mr Freeman was cross-examined about his statement in relation to the
suspension that (as stated) ‘…it was clear to us that things had got to a
stage where he did not want us there and we did not want to be there.’210
Mr Freeman accepted when questioned that he did not want to be there
from that day onwards and stated ‘no one wanted to be there.
Subcontractors didn’t want to be there. Our people didn’t want to be
there…I told them in no uncertain terms we had to be there...’.211
[119] Mr Freeman was cross-examined about the basis for the suspension. Mr
Freeman accepted when questioned that had the Builder given a notice to
Mr Cowen under the contract Mr Cowen would have 10 days to remedy any
breach. Mr Freeman did not accept however that leaving the boards up
201 Transcript dated 15 February 2017, T-100.
202 Ibid.
203 Ibid, T-100.
204 Ibid.
205 Ibid.
206 Ibid, T1-101.
207 Ibid, T1-103.
208 Ibid, T-104.
209 Ibid, T-109.
210 Exhibit 32, [71], see Transcript dated 15 February 2017, T1-110.
211 Ibid, T1-111.
-- 35 of 64 --
36
would have remedied the situation and stated that it would only have
remedied ‘part of the situation’.212
[120] It is Mr Freemans’ evidence that the works were suspended on the basis of
the safety issues and on the basis of the interference the Builder was getting
in relation to carrying out the job.213 Mr Freeman was cross-examined at
some length about the continuation of the suspension after 2 October
2014.214 Mr Freeman maintained his assertion that the Cowens would not
follow instructions and would not comply with the contract.215 The relevant
extract from the transcript is as follows:
Q All right. So again, there was no basis for suspending the works because
of safety issues associated with the hoarding, was there?
A Well, there was in the first instance.
Q That’s not an answer to my question?
A Okay. In the second instance no.
Q And you continued the suspension regardless…?
Q Yes, because he kept breaching to the construction site as well, which is
a breach.
Q You continued the suspension regardless of what was happening and
what you said about the boardings?
A Yes, because-because he would not follow instructions. He would not
comply with the contract.
Q Mr Freeman, you’re not on site. How do you know what instructions he’s
not complying with? You hadn’t been on site?
A We’ve got photographs of him on site- constantly on site.
Q These are photographs you took?
A Photographs people took, not myself.
…
Q After 1 October [2014]?
A It’s a continual pattern of interruption and interference and failure to
comply with safety regulations, and this was just….216
212 Transcript dated 15 February 2017, T1-116.
213 Ibid, T1-117.
214 Ibid, T1-119.
215 Ibid, T1-119.
216 Ibid, T1-119 to T1-120.
-- 36 of 64 --
37
[121] Mr Freeman was cross-examined about the Builder’s email to the Cowens’
legal representatives dated 23 October 2014. In the email, the Builder refers
to the works as being suspended indefinitely and states that no resumption
of work will occur until the QBCC process has been completed and a
resolution of all issues has been agreed.217 The relevant extract from the
email sent by Hugh Findlay (for the Builder) appears as follows:
Hi Peter
As I understand it [sic] a Indefinite Suspension means there is indefinite
extension for the “Date for Practical Completion” and so no date can be given
to you as it depends on decisions/processes etc. by others that are out of
our control. No resumption of works will occur until the QBCC process has
been completed and a resolution of all issues has been agreed. I suggest
you seek advice on these matters from the QBCC as I have no knowledge
of the duration of this process other than a general information email from
the “Minister for Housing and Public Works”.…218
[122] Mr Freeman was questioned about whether he believed that filing the
complaint with the QBCC permitted him to suspend the works under the
contract while that dispute was being assessed thorough the QBCC. Mr
Freeman stated:
We were certainly hoping that we would get guidance from, them as to
what…was the appropriate action to take.219
[123] Mr Freeman was questioned about whether or not the contract entitles the
Builder to suspend the works because they have referred a dispute to the
QBCC. Mr Freeman stated:
No, I think our feeling was that the suspension was valid on the basis of
Workplace Health and Safety issues, which were paramount.220
[124] Mr Freeman accepted when questioned that in the email dated 23 October
2014 the Builder communicated to the Cowens that because the matter had
been referred to the QBCC, no resumption of work would occur and there
has been a new suspension or a continuation of the suspension. Mr
Freeman stated:
Yeah, I do concur with that, that we…believed that when the process was
put to the QBCC as a dispute, that it would- we would hold the work in
suspension until it resolved.221
[125] Mr Freeman accepted that the complaint was lodged with the QBCC on 15
October 2014. Mr Freeman stated that they were waiting for a response
from the QBCC.222 Mr Freeman accepted when questioned that for 15 days
217 Exhibit 4, p 318.
218 Ibid.
219 Transcript dated 15 February 2017, T1-121, L34-37.
220 Ibid, T1-122, L10-12.
221 Ibid, T1-123, L1-5.
222 Ibid, T1-123, L21.
-- 37 of 64 --
38
during which the construction period ended the Builder lodged the QBCC
dispute and suspended or continued the suspension of the works and then
did nothing. Mr Freeman stated ‘[t]hat’s right because it was in the hand[s]
of the QBCC’.223
[126] Mr Freeman was cross-examined about correspondence sent by the
Cowens’ legal representatives (to the Builder) dated 28 October 2014 (the
breach notice). In the letter, the Builder is referred to suspending the works
indefinitely on 1 October 2014 and an allegation that the Builder had left the
site ‘in an unsafe condition’ and workplace health and safety officers
ordered the Builder to carry out substantial rectification work to ensure the
site was safe.224 Mr Freeman accepted that the Builder suspended the
works indefinitely on 1 October 2014 and was required to do some work
following receipt of a direction from workplace health and safety.225 It is non-
contentious that workplace health and safety inspected the site on or about
15 October 2014.226
[127] Mr Freeman was further cross-examined about the Builder’s suspension of
the works the following day of the hearing (on 16 February 2017). Mr
Freeman accepted when questioned that he did not inspect the site on 1 or
2 October 2014 to determine if the site was safe for workers. Mr Freeman
was questioned about whether or not the removal of the boarding on the
upper verandah was no longer a safety issue after Mr Cowen withdrew his
request to remove the boarding (by email dated 1 October 2014). Mr
Freeman stated:
No, because he was aggressive with them onsite that morning and we
deemed it appropriate to get off the site because of his previous outbursts
and police visits…His conduct during the entire process of the building was
one of an obstructive manner, interfering with the works, which is in
substantial breach of the contract, as you will well know.227
[128] Mr Freeman maintained his evidence that the Builder continued the
suspension on the basis of (as stated) ‘the workplace health and safety and
the fact that we had gone to the QBC for guidance’.228 Mr Freeman in giving
his evidence referred to Mr Cowen ‘constant[ly] ignoring our demands that
he stay off site’.229 Mr Freeman was questioned about the continuation of
the suspension after the QBCC notified the Builder that it was unable to
assist with the complaint or resolution process on 11 November 2014. Mr
Freeman accepted that the Builder was no longer able to maintain the
suspension from 11 November 2014.230 Mr Freeman’s evidence is that the
Builder did not lift the suspension because it already had a notice of
223 Transcript dated 15 February 2017, T1-123, L29-31.
224 Exhibit 4, p 334.
225 Transcript dated 15 February 2017, T1-133.
226 Ibid, T1-136.
227 Transcript dated 16 February 2017, T1-32.
228 Ibid, T1-34.
229 Ibid, T1-38.
230 Transcript dated 16 February 2017, T1-56.
-- 38 of 64 --
39
intention to terminate.231 Mr Freeman was questioned about why in the two
days before the Cowens issued its notice of intention to terminate the
Builder did not lift the suspension. Mr Freeman stated:
…Firstly, we hadn’t had confirmation of the intention to pay and or capacity
to pay, and secondly, we still believed there were workplace health and
safety issues…which is the reason we started it.232
[129] It is open to me to find that the Builder did not lawfully suspend the works
under the contract. The Builder did not give the Cowens notice of the
suspension of the works as required under the contract. I have found that
Mr Cowen withdrew any request he previously made to the Builder to
remove the boarding and the Builder’s carpenters did not remove any
boarding from the site (upstairs) on 2 October 2014.
[130] I have made findings about the contentions raised by the Builder including
the issues of safety, interference with the works, delay and Mr Cowen’s
alleged conduct on 2 October 2014 at the site. I have accepted Mr Cowen’s
evidence given by him in response to the contentions raised by the Builder
about site safety, the email sent by Mr Cowen on 1 October 2014 and other
alleged interference with the works.
[131] I have also considered Mr Freeman’s evidence in relation to the suspension
of the works and the lodgement of a resolution process with the QBCC. Mr
Freeman’s evidence is that the suspension of the works was continued
because of the ongoing QBCC dispute and the workplace health and safety
issues. Mr Freeman’s evidence is consistent with what was communicated
in writing to the Cowens by the Builder.233
[132] There is no provision under the contract to suspend the work because of
an ongoing dispute or complaint having been lodged with the QBCC. I have
made findings about the contentions raised by the Builder about site safety,
delay and interference. The evidence shows that the Builder was notified
on 11 November 2014 by the QBCC that the file had been closed and
notwithstanding the Builder maintained the suspension of the works. The
Cowens did not elect to terminate the contract until 13 November 2014. It
is open to me to find that there was an opportunity for the Builder from 11
November 2014 after receiving notification from the QBCC about the file
closure to lift its suspension and respond to the Cowen’s notice of intention
to terminate.
[133] I find that the Builder’s continuation of the suspension of the works after 11
November 2014 was conduct which ‘evinc[ed] an intention no longer to be
bound by the contract or to fulfil it only in a manner substantially inconsistent
231 Transcript dated 16 February 2017, T1-56.
232 Ibid, T1-57.
233 See emails dated 23 October 2014 and 10 November 2014, Exhibit 4, p 318 and
Exhibit 22, attachment 33.
-- 39 of 64 --
40
with the party’s obligations’.234 The Cowens were entitled to accept the
repudiation and terminate the contract.235
Did the Cowens validly terminate the contract with the Builder?
[134] The contract signed by the parties contains specific clauses about the
homeowners (the Cowens) and the Builder’s obligations including
exercising any right to terminate the contract by either party where one party
is in substantial breach of the contract.
[135] In this matter, the Cowens issued a notice of intention to terminate dated 28
October 2014 and a termination notice dated 13 November 2014. The
Builder effectively accepted the Cowens’ termination of the contract in
writing on 14 November 2014. In the Builder’s correspondence to the
Cowens’ legal representatives, the Builder maintained that the Cowens
‘caused the last indefinite suspension’.236
[136] Under clause 20 of the contract the homeowner has a right to serve a notice
of intention to terminate if the Builder fails to, amongst other things, proceed
with the works with due diligence or in a competent manner; unlawfully
suspends the carrying out of the works; refuses or persistently neglects to
remove or remedy defective work or improper materials, so that the works
are adversely affected; is unwilling to complete the works or abandons the
contract; or is in substantial breach. If the contractor fails to remedy the
breach, the owner may terminate the contract under clause 20.2.
[137] The Cowens’ legal representatives by letter dated 28 October 2014 gave
notice of this intention to terminate the contract pursuant to clause 20.1 (the
October notice). The October notice refers to clause 20.1 of the contract
and provides that the Builder is required within 10 business days to provide
amongst other things, a plan, a schedule of work, any certified rectification
plan; and acknowledge that the suspension of the works was improper.237
The October notice refers to the suspension of the works by the Builder and
states that ‘[t]his can hardly be said to be proceeding with the works in a
workmanlike or diligent manner’.238
[138] The QBCC say that the October notice is invalid and cannot be relied upon
by the Cowens for the purpose of clause 20.1 of the contract.239 The QBCC
says that the provision of the notice by the Cowens amounts to an unlawful
repudiation of the contract at common law. The QBCC contend that by
giving the notice the Cowens repudiated the contract on 28 October
2014.240 The QBCC also contend that the requirements placed on the
Builder in the October notice would not have resulted in works being
234 Koompahtoo’s case, 44.
235 Shevill’s case, 625-626.
236 Exhibit 2, p 267.
237 Exhibit 2, pp 57-58.
238 Ibid.
239 QBCC’s written submissions filed on 12 May 2017.
240 QBCC’s written submissions filed on 12 May 2017.
-- 40 of 64 --
41
resumed.241 The QBCC says that it would simply have resulted in the
provision of plans and acknowledgments by the Builder to the Cowens,
none of which have any basis in the contract.242
[139] The QBCC relies on the principles in Botros v Freedom Homes Pty Ltd243
that were applied in Thunder Corp Pty Ltd v Queensland Building Services
Authority.244 The QBCC say that there are similarities in this matter to
Botros’ case.245 The QBCC say that the Cowens insisted upon the
performance of certain terms in the Cowens’ October notice which had no
basis in the contract.246 The QBCC refer to Mr Cowen’s evidence given at
the hearing and submits that Mr Cowen maintained that compliance with
these terms was required if the Cowens were not to terminate the
contract.247 The QBCC say that by insisting that the Builder comply with
terms which have ‘no contractual warranty or authority’, and maintaining
that insistence right up until the hearing of this matter, the Cowens
repudiated the contract.248
[140] In Thunder Corp’s case, the Tribunal found that a notice of intention to
terminate was not a valid notice under the contract. The Tribunal in Thunder
Corps’ case applied the principles in Botros’ case that found a party cannot
unilaterally impose requirements for which there is no contractual warrant
or authority.249 The Tribunal found that the owner’s conduct in delivering a
notice of intention to terminate, when there had been no default under the
contract and when he had no entitlement to seek the matters set out in the
notice is a repudiation of the contract. The Tribunal found that a party who
has repudiated a contract cannot terminate for the other’s breach. The
Tribunal said:
…The facts in this case are consistent with the decision in Freedom Homes,
and with the conclusion that the owner has repudiated the contract by
evincing an intention not to perform the contract except on impermissible
terms...
Given these findings it is not necessary to consider further whether the
owner validly terminated the contract at common law. It is a general principle
that a party who has repudiated a contract cannot terminate for the other’s
breach.250
[141] I do not accept the QBCC’s submission that Mr Cowen in giving his
evidence maintained that compliance with all of the terms in the October
notice was necessary by the Builder. Mr Cowen was cross-examined about
241 QBCC’s written submissions filed on 12 May 2017.
242 QBCC’s submissions in response (reply) filed on 3 July 2017.
243 [1999] QCA 150; [2000] 2 Qd R 377.
244 [2011] QCAT 56.
245 QBCC’s written submissions filed on 12 May 2017, p 20.
246 Ibid.
247 Ibid, p 20.
248 Ibid.
249 Thunder Corps’ case, [121].
250 Ibid, [128].
-- 41 of 64 --
42
the notice and the request for the Builder to provide certain things such as
the plan, schedule of work and the certified plan. Mr Cowen in answering
questions about the notice referred to the contract and in another instance
stated ‘you’d have to ask my solicitor’.251 Mr Cowen was questioned about
the suspension of works and was asked to acknowledge that the
suspension is a legal conclusion.252 Mr Cowen accepted when questioned
that he required the Builder within 10 business days to acknowledge that
the suspension of the works was improper.253 Mr Freeman accepted when
questioned at the hearing that he understood the October notice was
complaining about the validity of the suspension and the Cowens’ intentions
were to get the Builder back to work.254
[142] I have considered the relevant cases and the submissions advanced by the
QBCC and the Builder. I do not accept the QBCC’s submission that there
are similarities in this matter to Botros’ case. I have made findings about the
conduct of the parties and the suspension of the works by the Builder. I have
found that Mr Cowen’s intention in sending the email on 1 October 2014 at
4:40pm was to have the Builder complete the works. I have also found that
there was repudiatory conduct by the Builder in continuing the suspension
of the works after receiving notice from the QBCC on 11 November 2014,
and that the Cowens were entitled to accept the Builder’s repudiation and
terminate the contract. Because of my findings, the decision in Thunder
Corp’s case that applied the principles in Botros’ case can be distinguished
on the facts of this matter.
[143] It is open to me to find having considered all of the evidence, that the
Cowens’ conduct in issuing the October notice was an honest attempt to
apply clause 20 of the contract to achieve the goal of having the Builder
resume the work by lifting the suspension under the contract and to bring
the works to practical completion. The notice refers to clause 20.1 of the
contract and clearly identifies the suspension of the works and a failure to
proceed with the works in a workmanlike manner.255 The notice relevantly
provided that the Builder is amongst other things, required within 10
business days to ‘acknowledge that the suspension of the works was
improper’.256
[144] I find that the Builder failed to remedy the breach identified in the notice
dated 28 October 2014 by continuing the suspension of the works. I find
that the termination notice dated 13 November 2014 was properly given by
the Cowens. The termination notice provides that no work had been
completed by the Builder since 1 October 2014 when the works were
‘indefinitely suspended over workplace health and safety concerns’.257 The
251 Transcript dated 4 May 2016, T3-117.
252 Ibid.
253 Ibid.
254 Transcript dated 16 February 2017, T1-48 to T1-49.
255 Exhibit 2, pp 57-58.
256 Ibid.
257 Exhibit 4, p 336.
-- 42 of 64 --
43
notice also refers to a failure to rectify any of the issues addressed in the
notice of intention to terminate dated 28 October 2014.258
[145] I find that the Cowens lawfully terminated the contract by giving notice to
the Builder on 13 November 2014. I also find that the Builder’s repudiatory
conduct by continuing the suspension of the works was accepted by the
Cowens by giving notice to the Builder on 13 November 2014.
[146] The Tribunal has also considered the oral submissions made by Mr Formby
on behalf of the QBCC at the hearing that the Cowens have acted
unreasonably in issuing the notices in October and November 2014.
[147] Mr Formby says that the Builder was ready and willing and able to perform
the contract and had referred the matter to the QBCC to try to get the
contract back on foot.259 Mr Formby says that the October notice was issued
too early and was therefore unreasonably given in the circumstances
because there were other remedies available to the Cowens for delay.260
Mr Formby refers to s 90 of the former Domestic Building Contracts Act
2000 (Qld) and says that at the relevant time that Act gave a statutory right
to terminate.
[148] I do not accept this submission having considered all of the evidence before
me. It is open to me to draw the reasonable inference based on the expert
evidence given in the hearing that as at 1 October 2016 the Builder was not
in a position to complete all of the contracted works by the date for
completion (26 October 2014). Mr Freeman accepted during cross-
examination that he attempted to reduce the scope of works in early
October 2014 and that the Builder was unhappy. Notwithstanding the
evidence about the scope of works, Mr Freeman’s evidence was that the
Builder wanted to complete the work.
[149] There is expert evidence before me in relation to an estimate of the time
remaining to complete the contracted work as at the date of suspension (1
October 2014). Andrew Morse, building consultant and Jeffrey Pratt,
licensed Builder gave concurrent evidence about the works and agreed that
there was approximately four to six months (as stated by Mr Morse) or three
to five months (as stated by Mr Pratt) of work to be completed having regard
to the stages of work under the contract. The relevant extract from the
transcript is as follows:
Q If you were…a building company and you were to dedicate all of your
resources to this one particular job and try and basically get this – or these
stages complete as quickly as possible, that’s what’s left to be completed?
Mr Morse Yes
258 Exhibit 4, pp 59-60.
259 Transcript dated 8 February 2016, T1-42.
260 Ibid, T1-47.
-- 43 of 64 --
44
Q How long do you think, in a best case scenario, quickest case scenario do
you think it could be done?
Mr Morse I think you would still be in a four to six months. You can only get
so much site – work – like, materials on site and so many workers on site
without causing a safe – workplace health and safety issue.
Q And, Mr Pratt?
Mr Pratt I would probably go three to five or something along those lines.
…
Mr Pratt It surprised me that all the timber there is for the whole of the job
and, as I said earlier, probably three months. It might be a bit less but I would
think it would be, you know, two and a-half to three months. 261
[150] I accept the evidence of Mr Morse and Mr Pratt. It is open to me to find that,
as at 1 October 2014 when the Builder unlawfully suspended the work, the
time remaining to complete the contracted works would not have been
sufficient even if the Builder were to dedicate all of its resources to the job
to get the stages completed as quickly as possible.
[151] I find that the Cowens have not acted unreasonably in issuing the October
notice and exercising their contractual and legal right to terminate on 13
November 2014. The adjusted date for completion of the works as notified
by the Builder to the Cowens was 26 October 2014. The Cowens did not
issue their notice to terminate until 28 October 2014, being a date after the
adjusted date for completion.
[152] I find that the correct and preferable decision is that the contract has been
validly terminated by the Cowens under the contract and otherwise at law.
In proceeding GAR044-15 the decision made by the Queensland Building
and Construction Commission of 22 December 2014 to decline a claim for
non-completion under clause 1.2 of the Insurance Policy Conditions is set
aside. The Tribunal substitutes its own decision that Peter Cowen and Jan
Cowen did validly terminate the contract dated 18 February 2013 and the
claim for non-completion under clause 1.2 of the Insurance Policy
Conditions is accepted.
What is the evidence about the relevant items in the Scott Schedule –
application GAR113-16?
[153] Steve Morley, licensed building certifier and Greg Dempster, building
certifier prepared a joint report262 following an experts conclave about items
261 Transcript dated 23 February 2017, T115 to T117.
262 Exhibit 29.
-- 44 of 64 --
45
numbered 2, 3, 4, 5, 7, 8, 10, 18 and 23. The experts gave concurrent
evidence at the hearing about items 7, 3, 2 and 4.
[154] Andrew Morse, independent building consultant, licensed Builder and
carpenter and Jeffrey Pratt, licensed Builder and carpenter prepared a joint
report263 following an experts conclave about items numbered 1(a), 1(b),
1(c), 1(d), 1(e), 1(f), 1(g), 2(a), 2(b), 2(c), 8, 12, 14, 17, 18, 23(a), 23(b),
23(c) and 31. The experts gave concurrent evidence at the hearing about
items 1(a), 1(b), 1(c) and 1(d). The experts also gave further evidence about
a new item identified at the on-site conclave as the ‘step-down’ or ‘fall issue’
that is relevant to item 1(e).264
[155] Alex Milligan, structural and civil engineer and Tom Kalaja, structural and
civil engineer prepared a joint report265 following an experts conclave about
items numbered 1, 2, 4, 5, 7, 8, 10, 12, 13, 14, 15, 16, 17, 21, 23, 25, 26 27
and 28. The experts gave concurrent evidence at the hearing about items
2 and 4.
[156] The Cowens contend that items 1(a), 1(e), 1(f), 1(g), 2, 4(b), 4(c), 12, 13,
15, 16, 18(d), 23(b), 23(c) are defective works.266 The Cowens say that they
will provide access to the Builder to enable the defects to be remedied.
[157] The Cowens in their written submissions have not addressed the balance
of the items in the Scott Schedule. The Cowens have filed no written
submissions in response to the QBCC’s contention that the Tribunal should
disregard the balance of the items in the Scott Schedule in determining
GAR113-16.267 The QBCC submit that the balance of the items may be
disregarded by the Tribunal in determining GAR113-16 as the Cowens
have made no submissions in relation to those matters and do not maintain
that the QBCC ought to issue a direction to rectify in respect of those
items.268
[158] All of the parties have been given an opportunity to file and exchange
written submissions. In the absence of a written submission from the
Cowens to contend otherwise, I accept the QBCC’s submission that the
Cowens do not maintain for the purposes of the review application (in
GAR113-16) that the QBCC should issue a direction to rectify for the
balance of the items from the Scott Schedule, being items 1(b), 1(c), 1(d),
3, 4(a), 4(d), 4(e), 5, 7, 8, 10, 14, 17, 18(a), 18(b), 18(c), 18(e), 21, 23(a),
25, 26, 27, 28 and 31. The QBCC’s decision not to issue a direction to rectify
in relation to those items that are no longer an issue for the purposes of the
263 Exhibit 35.
264 Further concurrent evidence was given on 23 February 2017.
265 Exhibit 40.
266 Cowens’ outline of submissions filed on 7 April 2017, [190].
267 QBCC’s written submissions filed on 12 May 2017, p 28. Balance of items from the Scott
Schedule are identified as 1(b), 1(c), 1(d), 3, 4(a), 4(d), 4(e), 5, 7, 8, 10, 14, 17, 18(a),
18(b), 18(c), 18(e), 21, 23(a), 25, 26, 27, 28 and 31.
268 QBCC’s written submissions filed on 12 May 2017, p 28.
-- 45 of 64 --
46
review proceeding in GAR113-16 should be confirmed. I make orders
accordingly.
[159] The Tribunal will now consider the remaining items for the purposes of the
review proceeding GAR113-16 referred to in the Cowen’s written
submissions, that is items 1(a), 1(e), 1(f), 1(g), 2, 4(b), 4(c), 12, 13, 15, 16,
18(d), 23(b) and 23(c).
Item 1(a) – below ground new block walls (waterproofing)
[160] The Cowens contend that the Builder failed to adequately waterproof the
blockwork wall on the western side of the property.269 The Cowens contend
that the failure of the waterproofing on the external side of the block wall is
raised in item 1(a) of the Scott Schedule. The Cowens invite the Tribunal to
prefer the evidence of Mr Morse and to find that the waterproofing on the
external side of the block wall had failed.270 The Cowens say that Mr Pratt
and Mr Morse agree that if the waterproofing had failed, it would be
considered a defect.271
[161] The QBCC say that Mr Pratt and Mr Morse agree that the garage structure
where the waterproofing is situated is a class 10 structure for the purposes
of the Building Code of Australia.272 The QBCC says that Mr Pratt and Mr
Morse agreed that the Building Code does not require waterproofing to be
carried out to a class 10 structure, although Mr Morse believed
waterproofing to be a requirement under the contract.273 The QBCC says
that the Tribunal is required to determine whether it is satisfied that
defective building work has been performed by the Builder pursuant to the
Building Code of Australia.274 The QBCC says that the detail provided by
Mr Milligan and Mr Kalaja in their joint report indicates that they did inspect
the relevant wall in some detail at their conclave. The QBCC submits that
Mr Milligan and Mr Kalaja’s evidence in their joint report is a more reliable
contemporaneous account of the condition of the wall at the time of the
hearing. The QBCC contend that the Tribunal should find that the alleged
defect in item 1(a) is incomplete work and not defective work.275
[162] Mr Milligan and Mr Kalaja agree that that there is evidence of water leaching
from the interface of the underside of the slab and the internal wall on the
western and northern sides.276 In their joint report Mr Milligan and Mr Kalaja
agree that the work is not defective and state that it is incomplete.277
269 The Cowens’ outline of submissions filed on 7 April 2017, p 26.
270 Ibid, pp 26 to 27.
271 Ibid.
272 QBCC’s written submissions filed on 12 May 2017, pp 30 to 31.
273 Ibid.
274 Ibid.
275 Ibid, p 31.
276 Exhibit 40.
277 Ibid.
-- 46 of 64 --
47
[163] The experts Mr Pratt and Morse agree that there has been water ingress.278
In their joint report Mr Pratt says the water ingress is because of unsealed
gaps.279 Mr Pratt says this is incomplete work and not a defect because it
can be completed to a satisfactory standard. Mr Morse says the water
ingress is because of a failed waterproofing membrane.280
[164] In giving their oral evidence both Mr Pratt and Mr Morse agreed that at some
stage a waterproofing certificate for the block wall would be issued. Both
experts agreed that they have not seen a waterproofing certificate.281
[165] It is Mr Morse’s evidence that he understands there is a water proofing
membrane installed. Mr Morse queried, however, how it was installed to
stop the water from migrating through. Mr Morse states:
I’m not sure how they did it. I understand there is a membrane there. As to
how they got to the bottom of the wall at a three-metre heights, I don’t know.
More importantly, how it would be returned down to the base of the wall and
then out over the footing system and the down the face of the footing system
to stop water migrating through. If it is – if the waterproofing membrane is
stopped at the bottom of the block on the footing, there’s a chance for
moisture to migrate through at the base course.282
[166] Mr Pratt’s evidence is that if there is no waterproofing on the backside the
work would be defective because the work has been backfilled.283 Mr Pratt
accepted when questioned that if waterproofing was there and failed the
work would be defective.284 Mr Pratt stated that it would be defective
because it’s allowing water egress into that area. Mr Pratt stated that there
is no requirement under the Building Code for it to be waterproofed because
it is classified class 10. Mr Pratt stated that it is his understanding that the
contract required it to be waterproofed.285 Mr Morse also accepts that the
Building Code of Australia does not require a class 10 building to be
waterproofed.286
[167] Both Mr Morse and Mr Pratt agreed at the hearing that a waterproofing
product had been applied to the block work.287 Mr Pratt gave evidence at
the hearing that ‘defective’ means ‘not done correctly’ and stated ‘allowing
water egress into that other area’.288 Mr Pratt’s evidence is that he did not
think there was any evidence of any failure other than rain water coming
down over the top of the western wall, spreading along the thicker wall and
278 Exhibit 35.
279 Ibid.
280 Ibid.
281 Transcript dated 17 February 2017, T5-58.
282 Ibid, T5-69.
283 Transcript dated 17 February 2017, T5-70
284 Ibid.
285 Ibid, T5-78.
286 Ibid, T5-80.
287 Ibid, T5-74.
288 Transcript dated 17 February 2017.
-- 47 of 64 --
48
coming down. Mr Pratt stated that only the northern wall showed a potential
failure of the membrane in relation to water leaks.289
[168] Both Mr Morse and Mr Pratt agreed when questioned that during their
independent inspections they saw watermarks or effervescence from
watermark spots above the shelf on the western wall.290
[169] Mr Pratt inspected the wall on 17 August 2015 and Mr Morse inspected the
wall on 19 May 2015. Both experts inspected the wall at the onsite conclave
prior to the hearing. In relation to the onsite conclave inspection of the wall,
Mr Pratt stated ‘we looked at it a bit the other day, but I don’t recall going
into any detail’.291
[170] Mr Milligan and Mr Kalaja state in their joint report that that the work is not
defective but is incomplete.292 Mr Milligan states however that the water
proofing membrane was exposed by an excavation on an earlier site. Mr
Milligan ‘questions’ whether the membrane was inspected and certified
before the earth was backfilled. Mr Milligan and Mr Kalaja were not
questioned about item 1(a) at the hearing.
[171] It is open to me to prefer the evidence of Mr Morse in relation to item 1(a).
Mr Morse was questioned at some length about his evidence and his
opinion in relation to the waterproofing. I accept Mr Morse’s evidence that
during his inspection he saw evidence of water ingress through the block
wall and in his opinion this would suggest that the waterproofing had failed.
Mr Pratt accepted when giving his concurrent evidence that if there was a
patch observed by him in the same location as the patch observed by Mr
Morse then it probably is a failure which would be defective work.293
[172] It is not in dispute that waterproofing was installed by the Builder. In written
submissions the Builder says that any waterproofing work done was
additional work done by the Builder ‘over and above what is required’.294 Mr
Morse accepted in giving his concurrent evidence that waterproofing had
been installed by the Builder.
[173] It is open to me to find, based on the evidence, that the waterproofing
installed may have been damaged by the placing of backfill against the wall
and nails being used to secure the corflute material.295 Mr Morse identified
from a photograph in giving his evidence that there was a nail piercing the
membrane.296 Mr Morse stated:
The waterproofing membrane is applied, obviously, to protect the material
behind it, being the block work and obviously to stop transference of
289 Transcript dated 17 February 2017, T5-86.
290 Ibid, T5-90.
291 Ibid, T5-97.
292 Exhibit 40.
293 Transcript dated 17 February 2017, T5-95.
294 The Builder’s written submissions filed on 1 June 2017, p 5.
295 Transcript dated 17 February 2017, T6-68, T6-132, T6-131 and T6-137.
296 Ibid, T5-131.
-- 48 of 64 --
49
moisture into, obviously, the habitable side or the internal side of this
structure. The corflute is applied simply to protect the membrane from, as
stated earlier, rocks and sharp objects that are being backfilled against the
wall. So here is a nail inserted through the corflute in through the membrane.
So the membrane is now defective at the top there because it’s been
beached.297
[174] Mr Pratt also accepted when giving his concurrent evidence earlier in the
hearing that backfill has sharp edges on it that as stated can ‘penetrate
through the waterproof membrane’.298 In relation to Mr Morse’s evidence
about the picture of the nail piercing the corflute, Mr Pratt accepted that
there was a nail depicted in the photograph and agreed with Mr Morse.299
[175] Having accepted the evidence of Mr Morse and his observations of the wall
during his inspection, I am satisfied to the required standard that the water
proofing installed by the Builder on the block wall has failed and is defective
work.
Should the Builder be directed to rectify the work?
[176] The QBCC or the Tribunal on review is not required to give a direction to
rectify if satisfied that, in the circumstances, it would be unfair to the person
to give the direction.300 An example for why the QBCC or the Tribunal on
review may exercise its discretion not to issue a direction to rectify is as
provided in s 72(5) where the owner refuses to allow the building contractor
to return to the owner’s home. The example in s 72(5) provides as follows:
Example for subsection (5)-
The commission might decide not to give a direction for the rectification of
building work because an owner refuses to allow a building contractor to
return to the owner’s home…
[177] In this matter, the Cowens say that they will provide access to the Builder
to come on to the property to remedy any defects.301 The Builder, in written
submissions, says that a direction to rectify is only necessary if the QBCC
deem work should be done and the contractor refuses to do it.302
[178] The QBCC say that the Cowens’ willingness to allow the Builder access
‘does not resolve the issue’.303 The QBCC say that if a direction to rectify is
issued, the Builder will suffer the detriment of receiving a direction to rectify
297 Transcript dated 17 February 2017, T5-137.
298 Ibid, T5-132.
299 Ibid, T5-138.
300 QBCC Act, s 72(5).
301 Applicants’ outline of submissions filed on 7 April 2017, p 40.
302 The Builder’s submissions filed on 1 June 2017, p 11.
303 QBCC’s submissions on the hearing filed on 12 May 2017, p 42.
-- 49 of 64 --
50
in circumstances where the Builder was willing to carry out rectification work
without the need for a formal direction.304
[179] The QBCC says that it would be unfair to the Builder to issue a direction to
rectify in circumstances where the Builder was willing to carry out
rectification work to any items determined by the QBCC to be defective, but
where the Cowens did not permit the Builder access to the property to carry
out those rectifications.305 The QBCC says, and I accept, that in those
circumstances, the Builder would be subjected to a detriment even though
the Builder was willing to carry out rectification work without a formal
direction to rectify being issued.306
[180] The Builder says that any supposed defects were not brought up at the time
when the work was being completed.307 The Builder says that the Cowens
terminated the contract, as such the work is ‘unfinished’ work and unpaid
work.308
[181] The evidence shows that the QBCC did contact the Cowens by
correspondence and email on various occasions between September 2015
and December 2015 advising the Cowens that the Builder was willing to
return to site to rectify items.309 In the various emails and correspondence
sent to the Cowens, the QBCC requested that the Cowens confirm that they
would allow access to the property for the Builder.310
[182] The evidence given by Mr Cowen at the hearing in relation to whether he
would have allowed the Builder access to the property is unequivocal. Mr
Cowen’s evidence is that he was willing to allow access to the Builder to
rectify defective work if a formal direction to rectify is issued by the
QBCC.311 Mr Cowen was questioned at the hearing by the QBCC about
whether he would raise ‘relatively promptly’ something that he considered
to be defective or not in accordance with the contract. Mr Cowen stated
‘certainly not’. Mr Cowen stated that he would get an independent Builder
to look at the ‘problem’. Mr Cowen stated that he would not mention the
problem to the Builder because it would ‘give them an excuse to walk
away’.312
[183] Mr Cowen’s evidence given at the hearing is that ‘as a rule’ issues were not
raised with the Builder by the Cowens. Mr Cowen stated that the reason for
not raising issues with the Builder was because ‘we just wanted to get the
job finished basically’.313 Mr Cowen stated that they were intending to raise
304 QBCC’s submissions on the hearing filed on 12 May 2017, p 42.
305 Ibid, p 41.
306 Ibid.
307 The Builder’s submissions filed on 1 June 2017, p 11.
308 Ibid.
309 Exhibit 46, “SOR-18”, p 121.
310 Ibid.
311 Transcript dated 21 February 2017, T73 to T74.
312 Ibid, p 24.
313 Transcript dated 21 February 2017, T29, L6 to L10.
-- 50 of 64 --
51
some issues in early July 2014 when the Builder returned to site and stated
‘they [the Builder] didn’t’ (meaning the Builder did not return to site).314 Mr
Cowen stated that they had some talks with the QBCC in July 2014 and put
in a complaint to the QBCC about the work.315
[184] Mr Cowen accepted when questioned that he did not raise the issue of
defective work with the Builder prior to November 2014.316 Mr Cowen gave
evidence about the items referred to in the Scott Schedule and identified
the items that he said were brought to the Builder’s attention prior to the
termination of the contract in late November 2014. Mr Cowen identified
items 3, 4 and 5.317 Mr Cowen also identified some items as having been
discussed at a meeting with the Builder in early May 2014 but stated that
for some items he could not be sure.318
[185] Mr Freeman was questioned about whether he was ever made aware of
any conversations occurring between Mr Cowen and any of the Builder’s
employees or contractors regarding any of the defects as they appear in
the Scott Schedule. Mr Freeman stated ‘nothing of item 1 whatsoever’. Mr
Freeman stated that the first he heard about the issues was after Mr
Milligan’s report was provided in 2015.319 Mr Freeman’s evidence
effectively remained unchanged when he was questioned about the other
items in the Scott Schedule. I accept Mr Freeman’s evidence.
[186] I accept the QBCC’s submission that the decision not to issue a direction
to rectify should be set aside and the matter returned to the QBCC for
reconsideration in relation to Item 1(a) that I have found to be defective. I
accept the QBCC’s submission that neither witness Mr Freeman nor Mr
Cowen gave evidence of any clear notification of any defects. I also accept
the submission advanced by the QBCC that it would be unfair to issue a
direction to rectify to the Builder in all of the circumstances such as the
unequivocal evidence given by Mr Cowen about whether the Builder was
made aware of the defects and whether the Builder was given an
opportunity to rectify the item.
[187] The correct and preferable decision is to set aside the decision made by
the QBCC not to issue a direction to rectify to the Builder for item 1(a) and
to return the matter to the QBCC for reconsideration according to the
findings made by the Tribunal. In returning the matter to the QBCC,
consideration should be given by the Commission to allowing the Builder
an opportunity to attend to rectification of the work that I have found to be
defective based on the evidence before me.
314 Transcript dated 21 February 2017, T29.
315 Ibid.
316 Ibid, T32, L41.
317 Ibid, T39.
318 Ibid, T43 to T44.
319 Transcript dated 22 February 2017, T7-144.
-- 51 of 64 --
52
Item 1(e), 1(f), 1(g) and new stepdown issue- new lower western slab
[188] It is non-contentious that the position of the slabs on the western side is
defective because it has insufficient fall pursuant to the Building Code of
Australia.320
[189] Both experts, Mr Pratt and Mr Morse, identified the new defect following an
inspection of the completed works. Mr Pratt and Mr Morse agreed that the
item identified as the concrete path outside the new garage extension on
the western side of the ground floor does not comply with the Building Code
of Australia. I accept their evidence.
[190] The remaining items (1(e), 1(f) and 1(g)) relate to the floor slab western side
and (as particularised in the Scott Schedule) where the old slab and new
internal slab join.
[191] There is evidence before me that the construction is certified to a Class 1a
standard based on the Form 16 produced at the hearing.321 It is open to me
to prefer the evidence of Mr Morse in relation to the western slab (items
1(e), 1(f) and 1(g)). Mr Morse gave evidence to the effect that the
development application and aspect certificate for the work certify the
construction as a Class 1a and a vapour barrier should have been installed.
Both Mr Morse and Mr Pratt agreed that no damp course was laid on the
western slab before the footings were poured. Both Mr Morse and Mr Pratt
accepted that this would be necessary to comply with a Class 1a
construction.322
[192] It is also open to me to prefer, and I accept, Mr Morse’s evidence in relation
to whether water proofing was required for the construction given that the
structure (as constructed) is in fact a Class 10 and not Class 1a. Mr Morse’s
evidence was that there was no vapour barrier between the existing slab
and the new slab to be poured, and that such protection was necessary to
prevent water penetration from the new slab to the existing slab.323 Mr
Morse in giving his evidence referred to s 3.2.2.6 of the Building Code of
Australia and the requirement that a vapour barrier should be installed for
the purposes of ‘continuous’ meaning from where the existing residential
slab meets the new structure. It is open to me to accept Mr Morse’s
evidence and find that there is no vapour barrier between the existing slab
and the new slab to be poured. It is open to me to find that the work is non-
compliant with the Building Code of Australia and is defective.
Should the Builder be directed to rectify the work?
[193] I have made findings in relation to whether the Builder was aware of any of
the defects in relation to item 1(a) above. Item 1(a) also relates to the
320 Submissions of the QBCC filed 12 May 2017, [137]; and the Cowens’ outline of
submissions filed on 7 April 2017, p 27.
321 Exhibit 19.
322 Transcript (23 February 2017)-31, L28 to T1-33, L 19.
323 Transcript (23 February 2017)-7, L41-43.
-- 52 of 64 --
53
western side of the property and similar issues and evidence given in
determining item 1(a) is relevant in respect of items 1(e), 1(f), 1(g) and the
new stepdown issue.
[194] I have accepted Mr Freeman’s evidence that he did not know anything
about item 1 until 2015.324 I have found that Mr Cowen’s evidence about
whether he would allow the Builder access to the property is unequivocal.
[195] I accepted the QBCC’s submission that it would be unfair to the Builder to
issue a direction to rectify to the Builder in circumstances where the Builder
was willing to carry out rectification work to items found to be defective but
was not permitted access to the property by the homeowner to carry out the
rectification. I accepted the QBCC’s submission that in those circumstances
the Builder would be subjected to a detriment even though the Builder was
willing to carry out rectification work without a formal direction to rectify
being issued. In this matter, I am required to make the correct and
preferable decision in relation to items 1(e), 1(f) and 1(g) and the step-down
issue (new item). I have found that the work for these items is defective.
[196] The correct and preferable decision is to set aside the decision made by
the QBCC not to issue a direction to rectify to the Builder for items 1(e), 1(f)
and 1(g) and the step-down issue (new item); and to return the matter to
the QBCC for reconsideration according to the findings made by the
Tribunal. In returning the matter to the QBCC, consideration should be
given by the Commission to allowing the Builder an opportunity to attend to
rectification of the work that I have found to be defective based on the
evidence before me.
Item 2 – water proofing and whether works not constructed to a Class 1a
structure
[197] It is non-contentious that a Class 10 structure does not require damp and
vapour proof protection. The experts agree that what is built is a Class 10
structure.
[198] I have preferred and accepted the evidence of Mr Morse in relation to
whether a vapour barrier is required. Mr Morse’s evidence was that the slab
was continuous with the existing slab and under the Building Code of
Australia this was required to be a Class 1a slab.325
[199] The evidence shows that not all of the footings were protected (with show
damp course) before the slab was poured on the western side. Both Mr
Morse and Mr Pratt accept that this would be required for a Class 1a
structure. Both experts also agree that damp course would be required over
all of the footings to comply with a Class 1a construction.
324 Transcript dated 22 February 2017, T7-144.
325 Transcript (23 January 2017) page 7, L45 to page 8, L34; Transcript (23 February
2017) page 20, L14 – 136??? JB to check.
-- 53 of 64 --
54
[200] It is open to me to find that the construction is not compliant with the Building
Code of Australia having preferred and accepted the evidence of Mr Morse.
I find that water proofing is required where the slab is continuous with the
existing slab for the purposes of s 3.2.2.6 of the Building Code of Australia.
It is open to me to find that this item of work is defective.
Should the Builder be directed to rectify the work?
[201] I have made findings in relation to whether the Builder was aware of any of
the defects in relation to item 1(a) above. Item 1(a) also relates to the
western side of the property and similar issues and evidence given in
determining item 1(a) are relevant in respect of this item.
[202] I have accepted Mr Freeman’s evidence that he did not know anything
about item 1 until 2015. Mr Freeman, in giving his evidence, indicated that
his response for item 2 was the same as for item 1.326 I have found that Mr
Cowen’s evidence about whether he would allow the Builder access to the
property is unequivocal.
[203] I accepted the QBCC’s submission that it would be unfair to the Builder to
issue a direction to rectify to the Builder in circumstances where the Builder
was willing to carry out rectification work to items found to be defective but
was not permitted access to the property by the homeowner to carry out the
rectification. I accepted the QBCC’s submission that in those circumstances
the Builder would be subjected to a detriment even though the Builder was
willing to carry out rectification work without a formal direction to rectify
being issued. In this matter, I am required to make the correct and
preferable decision in relation to item 2. I have found that the work for this
item is defective.
[204] The correct and preferable decision is to set aside the decision made by
the QBCC not to issue a direction to rectify to the Builder for item 2 and to
return the matter to the QBCC for reconsideration according to the findings
made by the Tribunal. In returning the matter to the QBCC, consideration
should be given by the Commission to allowing the Builder an opportunity
to attend to rectification of the work that I have found to be defective based
on the evidence before me.
Items 4(b) and 4(c) – eastern slab and footings
[205] These items relate to the eastern slab and the reinforcement footings. Both
Mr Milligan and Mr Kalaja gave concurrent evidence about these items of
work. Mr Morley and Mr Dempster also gave concurrent evidence about the
issuing of a form 16 that is relevant to these items of work.
326 Transcript dated 22 February 2017, T7-144.
-- 54 of 64 --
55
[206] The Cowens contend that Mr Kalaja’s evidence ought not be accepted, or
alternatively given little weight.327 The Cowens contend that no reliance
ought to be placed on the Form 16 that certifies an aspect of slab work.
[207] The Cowens say that the Builder has made modifications to the slab
reinforcing in the area of the landing near the rear steps, after the engineers
inspection and without notifying the engineer of these changes.328 The
Cowens say that the slab was then poured with a step-down to the landing
area, contrary to the plans and Mr Cowen’s intended use, namely to be able
to move his cars around the area.329
[208] The Cowens also raise other issues in their written submissions in relation
to the slab such as whether it (the slab) can be certified.330 The Cowens
contend that Mr Kalaja accepted in cross-examination that he was not
entitled to issue certification for the entire footing and slab stage. The
Cowens also content that the Builder accepted that it relied on the Form 16
as being for the whole of the footings and slab stage and poured the
footings and slab in reliance on it.331
[209] Both parties have had an opportunity to present evidence in relation to
items 4(b) and 4(c). It is open to me to make findings based on the evidence
before me. I must arrive at the correct and preferable decision as to whether
a direction to rectify should issue to the Builder based on my findings made.
[210] Mr Milligan accepted, in giving his evidence, that his concerns regarding
these items of work were addressed at the experts conclave by sighting the
Form 16 for this work. The relevant extract from the transcript is as follows:
Mr Kalaja advised me that he’d inspected the site, and that specific area,
which I wasn’t aware of at the time of generating my reports. The footings
were deepened in that area to account for the different soil conditions. It was
an area of fill material compared with the opposite end of the building, which
was in rock, and I think it’s true to say the bulk of the footings were excavated
in rock, apart from this area that I’ve circled on the plan. Mr Kalaja also
actually drew my attention to a photograpgh contained in one of my reports
where he explained that the form work or boxing, it’s sometimes referred to,
is seen to be deeper than in other sections of the footing preparation. Those
statements and that discussion, together woth Mr kalaja issuing a form 16,
which in effect is his statement of fact pertaining to compliance of the
pepared construction work in accordance with the documents led me to
agree that the concerns I’d raised in my report would be removed or were
satisfied, whichever is the most appropriate wording.332
[211] Mr Milligan’s evidence is that it is not common practice to carry out invasive
investigations to check certain aspects of foundations where a Form 16 has
327 Applicant’s outline of submissions dated 7 April 2017, p 33.
328 Ibid.
329 Ibid.
330 Ibid.
331 Ibid p 32; Transcript 22 February 2017, p 39 L32 to p 40, L1.
332 Transcript dated 16 February 2017, T1-151, LL34-46.
-- 55 of 64 --
56
been issued by a qualified engineer.333 Mr Milligan gave evidence about the
importance of the Form 16. Mr Milligan said that the Form 16 is a ‘critical
document’ and referred to it as being a ‘legally binding statement of fact’.
The relevant extract from the transcript is as follows:
…a From 16 is one of those critical documents. It’s a legally binding
statement of fact, is my understanding, that testimony that the works have
been inspected and are fully in accordance with the requirements of the
design and the applicable codes and it’s for that reason that I –well, that I
defer to Mr Kalaja’s role as the engineer responsible for that project.334
[212] Mr Milligan gave evidence to the effect that the concerns he had raised in
his report could be removed or were satisfied following his inspection and
discussions with Mr Kalaja.335 Mr Milligan gave evidence to the effect that
he was not in any position to suggest that there is a defect.336 Mr Milligan
was questioned about whether his view was changed in regards to his
evidence about the Form 16 after hearing the concerns pertaining to Mr
Kalaja’s evidence being raised by the Cowens’ legal counsel. Mr Milligan
confirmed that his evidence with respect to the engineering matters was
unchanged.337 Mr Milligan also accepted in giving his evidence that there
does not appear to be anything about the slab which is indicating to him
that it is not performing.338
[213] Mr Morley was given an opportunity at the hearing to respond to the issues
raised about Mr Kalaja and the issuing of the Form 16 – in particular, about
Mr Kalaja’s alleged inconsistent statements about his inspection of the work
and the issuing of a Form 16.339
[214] It is open to me to accept Mr Milligan’s evidence given at the hearing that a
Form 16 issued by an engineer in respect of the foundation stage is a critical
document and is effectively evidence that the works have been inspected
and are in accordance with the requirements of the design and the
applicable codes.340 I accept Mr Milligan’s evidence given in relation to
items 4(b) and (c).
[215] I have also considered the evidence given by Mr Morley and Mr Dempster
in relation to the Form 16. Both experts Mr Morley and Mr Dempster agreed
that a Form 16 issued by a competent person could be relied upon by a
certifier in order to certify the foundations.341 Mr Dempster accepted in
333 Transcript dated 16 February 2017, T1-156, L12.
334 Ibid, T1-157, LL33-39.
335 Ibid, T1-151, L34-36.
336 Ibid, T1-159, LL4-9.
337 Ibid, T1-146 to T1-147.
338 Ibid, T1-158, L21.
339 Ibid, T1-139.
340 Ibid, T1-157.
341 Transcript dated 14 February 2017, T2-103 to T2-105.
-- 56 of 64 --
57
giving his evidence that Mr Morley (the certifier) had deemed Mr Kalaja to
be a competent person to issue a certificate.342 Mr Dempster stated:
…The certifier has deemed him [Mr Kalaja] competent….based on this, the
certifier is allowed to rely on it, and those aspects are certified.343
[216] It is open to me to find that items 4(b) and (c) are not defective. I accept that
a Form 16 has been issued and that Mr Morley as certifier deemed Mr
Kalaja to be a competent person.
[217] I am satisfied, having considered all of the evidence before me, that items
4(b) and 4(c) are not defective work. The correct and preferable decision is
that a direction to rectify should not be issued to the Builder for these items
of work because the work is not defective. The decision made by the QBCC
not to issue a direction to rectify for items 4(b) and 4(c) (eastern slab and
footings) is confirmed.
Item 12 – Steel posts on the eastern side
[218] This item relates to work performed by the Builder on the eastern slab.
[219] Both experts Mr Milligan and Mr Kalaja agreed that the issues identified in
relation to item 12, such as the steel beams and posts installed, are
defects.344 Both experts agreed that all of the matters could have been
corrected had they been identified ‘before handover’.345
[220] The QBCC submits, and I agree, that in light of the expert witnesses’
findings, it is appropriate for the Tribunal to make a finding that those items
of work concerning item 12 are defective.346 I accept the evidence of Mr
Milligan and Mr Kalaja and find that Item 12 is defective.
Should the Builder be directed to rectify?
[221] I have made findings in relation to whether the Builder was aware of any of
the defects in relation to item 1(a) above. I have accepted Mr Freeman’s
evidence that he did not know anything about the items in the Scott
Schedule. When giving his evidence about item 12 in the Scott Schedule,
Mr Freeman stated that they were ‘only just erecting [the posts]’ when they
‘got stopped’.347 Mr Freeman referred to the relevant time as being in
September or October 2015 and stated that they could have easily gone
back to rectify and stated ‘but we were not on site so we didn’t get to that’.348
[222] I have found that Mr Cowen’s evidence about whether he would allow the
Builder access to the property is unequivocal. I accepted the QBCC’s
342 Transcript dated 14 February 2017, T2-105, L37.
343 Ibid.
344 Exhibit 40.
345 Ibid.
346 Submissions of the QBCC filed on 12 May 2017.
347 Transcript dated 22 February 2017, T7-148.
348 Ibid, T7-148.
-- 57 of 64 --
58
submission that it would be unfair to the Builder to issue a direction to rectify
to the Builder in circumstances where the Builder was willing to carry out
rectification work to items found to be defective but was not permitted
access to the property by the homeowner to carry out the rectification. I
accepted the QBCC’s submission that in those circumstances the Builder
would be subjected to a detriment even though the Builder was willing to
carry out rectification work without a formal direction to rectify being issued.
[223] In this matter, I am required to make the correct and preferable decision in
relation to item 12. I have found that the work for this item is defective. The
correct and preferable decision is to set aside the decision made by the
QBCC not to issue a direction to rectify to the Builder for item 12 and to
return the matter to the QBCC for reconsideration according to the findings
made by the Tribunal. In returning the matter to the QBCC, consideration
should be given by the Commission to allowing the Builder an opportunity
to attend to rectification of the work that I have found to be defective based
on the evidence before me.
Item 13 – Steel posts (base plates)
[224] This item relates to the base plates of steel posts that are undersize and
(as contended) do not comply with the ‘Alternative Base Plate Details’
provided by the engineer.
[225] The experts Mr Milligan and Mr Kajala agree that the base plates are
undersized. They report, however, that ‘the manner in which it is installed it
does perform properly’.349
[226] The experts Mr Pratt and Mr Morse also considered this item in their
respective reports. Mr Pratt reports that the bolts to the posts were too short
‘in that they did not fully engage the thread in the nuts’.350 Mr Pratt reports
that the posts and beams had been temporarily braced and nailed in
position by the owner. Mr Pratt also reports that that that builder was sent
off site whilst erecting the posts and frame and ‘had no time to install the
temporary fixings’. Mr Pratt reports:
[Mr Freeman] said they were aware the bolts had been installed too short
and were going to drill the bolts out and use chemical anchors of the correct
length.351
[227] Mr Morse also reports that the beams, posts and the steel columns are not
compliant with the Building Code of Australia. Mr Morse reports:
Along this garage slab area structural steel columns and beams have been
installed and partly bolted to the new slab directly above this unprotected
349 Exhibit 40.
350 Exhibit 35.
351 Ibid.
-- 58 of 64 --
59
cold joint to the slabs and as such fails to comply with 3.1.3.7-(a) & (b) & (c)
[of the Building Code of Auatralia].352
[228] It is open to me to accept the evidence of Mr Milligan and Mr Kajala that the
bolts to the posts are too short. I also accept the evidence of Mr Pratt and
Mr Morse in relation to this item of work. Mr Freeman does not dispute that
the bolts installed are too short as reflected in Mr Pratt’s report. I find that
the bolts to the posts are too short. I am satisfied based on the evidence
before me that item 13 is defective work.
Should the Builder be directed to rectify?
[229] I have made findings in relation to whether the Builder was aware of any of
the defects in relation to item 1(a) above. I have accepted Mr Freeman’s
evidence that he did not know anything about the items in the Scott
Schedule. When giving his evidence about item 13, Mr Freeman stated that
he knew nothing about that item ‘at all’.353
[230] I have found that Mr Cowen’s evidence about whether he would allow the
Builder access to the property is unequivocal. I accepted the QBCC’s
submission that it would be unfair to the Builder to issue a direction to rectify
to the Builder in circumstances where the Builder was willing to carry out
rectification work to items found to be defective but was not permitted
access to the property by the homeowner to carry out the rectification. I
accepted the QBCC’s submission that in those circumstances the Builder
would be subjected to a detriment even though the Builder was willing to
carry out rectification work without a formal direction to rectify being issued.
[231] In this matter, I am required to make the correct and preferable decision in
relation to item 13. I have found that the work for this item is defective. The
correct and preferable decision is to set aside the decision made by the
QBCC not to issue a direction to rectify to the Builder for item 13 and to
return the matter to the QBCC for reconsideration according to the findings
made by the Tribunal. In returning the matter to the QBCC, consideration
should be given by the Commission to allowing the Builder an opportunity
to attend to rectification of the work that I have found to be defective based
on the evidence before me.
Items 15 and 16 – Steel posts
[232] This issue relates to a steel post that was alleged to have been erected in
the incorrect place.
[233] It is non-contentious that the steel post has been removed. The experts
report:
352 Exhibit 35.
353 Transcript dated 22 February 2017, T7-148.
-- 59 of 64 --
60
Item 15 - This post has now been removed. The experts do not know if it had
originally been erected in the correct place in accordance with the contract
drawings.
Item 16 - It is agreed that if the post in 15 is erected in a different place then
the cleats will have to be moved to suit.354
[234] I accept the evidence of Mr Milligan and Mr Kajala. I cannot be satisfied to
the requisite standard based on the evidence that items 15 and 16 are
defective work because the post has been removed. The correct and
preferable decision is that a direction to rectify should not be issued to the
Builder for this item of work. The decision made by the QBCC not to issue
a direction to rectify for items 15 and 16, the steel posts, is confirmed.
Item 18(d) – plumbing works issue
[235] This issue relates to a drawing for plumbing work, in particular, a failure of
the Form 4 to show the new overflow relief gully at the boundary.
[236] The Cowens rely on an email from the Brisbane City Council (the BCC) that
refers to an audit inspection carried out on 15 December 2016 and the
defect items noted as being outstanding.355 The email refers to action taken
following the audit inspection that identified defect effect as being ‘still
outstanding’. The email states:
…I have contacted the plumber to inform him of these defects, unfortunately
he didn’t answer his phone but I was able to leave him a voice message to
return my call…356
[237] Mr Gregory Moore, Senior Plumbing Investigator with the QBCC, gave
evidence about this item and the legislative requirements as to what the ‘as
constructed diagrams’ accompanying a Form 4 is to show.357 Mr Moore’s
evidence is that the Form 4, amongst other things, does show a future
overflow relief gully on the boundary and is not required to show aspects of
sewers or other drainage which is maintained by Queensland Urban
Utilities.358 Mr Moore accepted, when questioned about his evidence at the
hearing, that the BCC had the power to audit QBCC decisions and to ensure
notices to rectify plumbing contractors in respect of notifiable plumbing
work. This power to take actions referred to by Mr Moore in his evidence is
against plumbing licensees.359
[238] I accept the QBCC’s submission that it would not be fair to take action
against the Builder in relation to a matter for which the BCC is already taking
action against a plumbing licensee, particularly when there is no evidence
354 Exhibit 40.
355 Exhibit 54, document 7, p 141.
356 Ibid.
357 Exhibit 54 at [10].
358 Ibid, [11(d)].
359 Transcript 22 February 2017, p 7-123.
-- 60 of 64 --
61
before me as to whether or not the matters raised in the BCC
correspondence have already been addressed by the plumbing licensee.360
[239] Notwithstanding, the issue complained of by the Cowens concerns the
Form 4 ‘as constructed diagram’ for which, based on Mr Moore’s evidence,
there is no legislative requirement as to what the diagram accompanying a
Form 4 is to show. I accept Mr Moore’s evidence. I accept the QBCC’s
submission that a direction to rectify should not be issued to the Builder
even if the work, as identified by the BCC following an inspection, is found
to be defective.361 The correct and preferable decision is that the QBCC’s
decision not to issue a direction to rectify to the Builder for item 18(d) is
confirmed.
Items 23(b) and 23(c) - termite protection
[240] These items of work relate to the installation of a termite barrier on the lower
western side and the east side in accordance with the contract.
[241] The Cowens contend that no certification for termite protection has been
issued for the eastern slab.362 The Cowens rely on the evidence of Mr
Morse and Mr Pratt and say that the experts identified a number of areas in
respect of which the termite protection was defective.
[242] Both Mr Morse and Mr Pratt agreed that there is no termite barrier installed
having viewed photographs.363 Mr Pratt stated however that he is satisfied
from the fact that a certificate has been issued for the western side that
there is no defect. Mr Morse did not agree with Mr Pratt about this issue
and stated, in the joint report, that the termite barrier should have been
installed by the current stage of construction.364 In relation to item 23(c) both
Mr Pratt and Mr Morse agreed that there is a physical barrier visible in some
areas.365
[243] Mr Morse and Mr Pratt gave concurrent evidence about items 23(b) and
23(c) at the hearing. Mr Morse and Mr Pratt both agreed that the termite
barrier has been breached by a post sitting against the existing house,
constituting a defect.366 Mr Morse stated at the hearing that that aspect of
the work was not compliant with section 3.1.3.5 of the Building Code of
Australia.367 Mr Morse also identified a gap or void between the slab and
the existing ant capping of the house on the lower western slab that was
not compliant with the Building Code of Australia. Mr Morse stated:
360 QBCC’s written submissions filed on 12 May 2017, p 38.
361 Ibid, p 38.
362 Transcript 22 February 2017, p 93, L23-26; See Applicant’s submissions dated 7 April
2017, p 34.
363 Exhibit 35.
364 Exhibit 35.
365 Ibid.
366 Transcript dated 23 February 2017, T13-65 to T13-69.
367 Ibid, T13-69, L 16.
-- 61 of 64 --
62
…there is some protection…in the original dwelling but the manner in which
the slab is…up there, I think creates a problem. That void- there is no visual.
The termites could simply go straight over the membrane with their mud pack
and they’re in that void and they’re away. So that- that issue there would
have to be addressed in line with the certificate and then addressing the
issue up behind the post for him to issue a certificate. I do accept Mr Pratt’s
version that it was put in place there, some fabric. And then the slab is
poured and subsequently the post has come up there and that breaches it.
And that breaching is the failure to comply under our three. So attachments
of item adjacent to buildings, so it fails to comply with 3660. So the builder
needs to have addressed that.368
[244] The QBCC submit that based on the expert evidence before the Tribunal it
is appropriate that the Tribunal make a finding that the termite barrier is
defective insofar as posts on both the eastern side and western side abut
the house.369 I accept this submission based on the evidence of Mr Morse
and Mr Pratt that I also accept.
[245] In relation to the lower western slab, I accept the evidence given by Mr
Morse in relation to the gap or void between the slab and the existing ant
capping of the house. I also accept the evidence of Mr Morse in relation to
the location of the post on the western side.
[246] In relation to the eastern side, both Mr Morse and Mr Pratt agreed that at
the time of the hearing a Form 16 for termite protection had not been
provided or sighted by them. Mr Pratt’s evidence is that the work can be
compliant with termite protection requirements once the work is completed
and therefore does not consider the eastern side termite protection to be
defective (save for where the posts abut the existing house).
[247] Mr Pratt gave evidence that the hole adjacent to the eastern slab on the
corner of the existing dwelling was incomplete work, predominantly on the
basis that a builder would not just leave that hole there unless the works
are incomplete.370 There is no evidence before me in relation to the eastern
slab that a termite barrier has been installed.
[248] It is open to me to find based on the evidence of Mr Morse that the work in
in relation to item 23(b) on the western side is defective where the post
abuts the house and where there is a void (with respect to ant capping).
Both Mr Morse and Mr Pratt agreed there was no termite barrier visible from
the photographs they had sighted of the slab. Both experts agreed the
termite protection was defective where posts abutted the existing
dwelling.371 I accept their evidence and make findings accordingly.
[249] It is open for me to find, having accepted the expert evidence of Mr Morse
and Mr Pratt, that item 23(c) in regards to the termite protection on the
eastern side is defective. Both experts had not sighted a Form 16 and Mr
368 Transcript dated 23 February 2017, T13-77, LL16-27.
369 QBCC’s submissions filed on 12 May 2017, p 39.
370 Transcript 22 February 2017, p 13 – 64.
371 Transcript 23 February 2017, p 64, L8-25.
-- 62 of 64 --
63
Morse’s evidence is that the termite protection on the eastern side should
be in place at the current stage of construction. Both experts agree the work
is defective where posts on the eastern side abuts the existing dwelling.372
I find items 23(b) and 23(c) are defective.
Should the Builder be directed to rectify?
[250] I have made findings in relation to whether the Builder was aware of any of
the defects in relation to item 1(a) above. I have accepted Mr Freeman’s
evidence that he did not know anything about the items in the Scott
Schedule. When giving his evidence about item 23(b) and 23(c), Mr
Freeman stated that ‘termite treatment certification was not brought up at
all’.373
[251] I have found that Mr Cowen’s evidence about whether he would allow the
Builder access to the property is unequivocal. I accepted the QBCC’s
submission that it would be unfair to the Builder to issue a direction to rectify
to the Builder in circumstances where the Builder was willing to carry out
rectification work to items found to be defective but was not permitted
access to the property by the homeowner to carry out the rectification. I
accepted the QBCC’s submission that in those circumstances the Builder
would be subjected to a detriment even though the Builder was willing to
carry out rectification work without a formal direction to rectify being issued.
[252] In this matter, I am required to make the correct and preferable decision in
relation to item 23(b) and 23(c). I have found that the work for this item is
defective. The correct and preferable decision is to set aside the decision
made by the QBCC not to issue a direction to rectify to the Builder for item
23(b) and 23(c) and to return the matter to the QBCC for reconsideration
according to the findings made by the Tribunal. In returning the matter to
the QBCC, consideration should be given by the Commission to allowing
the Builder an opportunity to attend to rectification of the work that I have
found to be defective based on the evidence before me.
Other items that fall outside the Scott Schedule
[253] The Cowens have identified in their written submissions other items that fall
outside of the Scott Schedule. I have not considered those items for the
purposes of determining the correct and preferable decision in GAR113-16.
The parties have had an opportunity to present submissions and respond
in reply. I have accepted the QBCC’s submission that the Tribunal should
only make findings in relation to the items identified in the Cowens’
submissions with reference to the Scott Schedule identified as items 1(a),
1(e), 1(f), 1(g), 2, 4(b), 4(c), 12, 13, 15, 16, 18(d), 23(b) and 23(c).374 It
would not be fair to the builder and the QBCC to make findings about these
items that fall outside the Scott Schedule because the items do not form
372 Transcript 23 February 2017, p 64, L8-25; Transcript 23 February 2017, p 68, L39 to p
69, L47.
373 Transcript dated 22 February 2017, T7-149.
374 Applicant’s outline of submissions dated 7 April 2017, para [190].
-- 63 of 64 --
64
part of the review proceedings and the parties have not been given an
opportunity to present evidence and respond to the issues in relation to the
items.
Conclusion
[254] I have made findings of fact in relation to GAR044-15 about the conduct of
the parties, in particular whether or not the allegations made by the Builder
about Mr Cowen’s alleged interference with the performance of the work
were proven based on the evidence before me. I found that the contract
was properly terminated by the Cowens. I found that, based on the
evidence before me, the Builder unlawfully suspended the works on 1
October 2014 and by continuing the unlawful suspension after 11
November 2014 evinced an intention to no longer be bound by the contract.
I found that the Cowens were entitled to accept the Builder’s repudiatory
conduct. I found that the correct and preferable decision is that the contract
has been properly terminated by the Cowens under the contract and
otherwise at law.
[255] In relation to GAR113-16 I have found that items 1(a), 1(e), 1(f), 1(g), 2, 12,
13, 23(b) and 23(c) are defective work. I made findings about the evidence
given by the Cowens and Mr Freeman in relation to the items of work and
whether or not the Builder was made aware of the items I found to be
defective and whether or not the Builder was given an opportunity to rectify
the defects. I determined that the correct and preferable decision is for each
of the items of work I found to be defective was to refer the matter back to
the QBCC for reconsideration.
[256] For items 4(b), 4(c), 15, 16 and 18(d), I found that the work is not defective
work and the correct and preferable decision is not to issue a direction to
rectify to the builder.
-- 64 of 64 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2017/416