Blonk v Flanagan t/as Flanagan Builders [2017] QCAT 408
CITATION: Blonk v Flanagan t/as Flanagan Builders
[2017] QCAT 408
PARTIES: Jonathon Andre Blonk
(Applicant)
v
Wade Peter Flanagan t/a Flanagan Builders
(Respondent)
APPLICATION NUMBER: BDL073-17
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Holzberger
DELIVERED ON: 22 November 2017
DELIVERED AT: Brisbane
ORDERS MADE: 1. Wade Peter Flanagan t/a Flanagan
Builders must pay to Jonathon Andre
Blonk the sum of $3,796.90 by 4:00pm on
2 January 2018.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN
STATE AND TERRITORY COURTS –
ENDING PROCEEDINGS EARLY – DEFAULT
JUDGMENT – JUDGMENT IN DEFAULT OF
OTHER REQUIRED STEP – where respondent
repeatedly failed to comply with directions
made by the Tribunal – where the applicant
applied for default judgment
CONTRACTS – BUILDING, ENGINEERING
AND RELATED CONTRACTS –
PERFORMANCE OF WORK – REMEDIES
FOR BREACH OF CONTRACT – DAMAGES –
MEASURE OF – domestic building dispute –
failure to complete work – breach of contract
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
-- 1 of 3 --
2
REASONS FOR DECISION
On 21 April 2017, Mr Blonk made an application to the Tribunal claiming
the sum of $2,680 from Wade Peter Flanagan trading as Flanagan Builders.
With the application, Mr Blonk provided a copy of correspondence to him
from the Queensland Building and Construction Commission, dated
21 March 2017, confirming that its dispute resolution process had been
finalised.
Mr Flanagan has failed to comply with directions made by the Tribunal on
15 May 2017, 6 July 2017 and 2 August 2017.
On 23 July 2017, Mr Blonk filed a request for decision by default. That
request is supported by a document tilted “affidavit for claim of unliquidated
damages” dated 31 July 2017, an affidavit of service of the original
application dated 15 May 2013 and a document titled “statement for
directions hearing” filed on 21 August 2017.
I am satisfied that the application was served on Mr Flanagan on
11 May 2017 by posting it to his last known business or home address and
that the request for default judgment was served by the same method on
21 June 2017.
I make the following findings of fact:
a) In July 2015, Mr Blonk contracted with Mr Flanagan for the
construction of a block wall at Mr Blonk’s property at 2 Corinthia Court
Noosaville for a total amount of $22,456.50.
b) Mr Blonk paid Mr Flanagan progress payments totalling $13,579.50 in
July and August 2015.
c) Mr Flanagan completed the block work by August 2015 but did not
core fill, render or paint the wall as the contract required. Repeated
attempts to have him complete the works failed.
d) Mr Blonk completed the core fill, rendering and painting in mid-2017
and incurred the following costs:
i) Boral concrete – concrete to core fill - $2,491.90;
ii) Noosa concrete – concrete pumping - $682;
iii) Quality rendering – render and colour - $9,500; and
iv) Total - $12,673.90.
e) The balance payable under the contract between Mr Blonk and Mr
Flanagan is $8,877. After deduction of that amount, Mr Blonk has
suffered damage in the sum of $3,796.90.
-- 2 of 3 --
3
f) Accordingly, I order that Mr Flanagan pay to Mr Blonk the sum of
$3,796.90 by 4:00pm on 2 January 2018.
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2017/408