A B Hill Constructions Pty Ltd v Queensland Building and Construction Commission [2017] QCAT 391
CITATION: A B Hill Constructions Pty Ltd v Queensland
Building and Construction Commission [2017]
QCAT 391
PARTIES: A B Hill Constructions Pty Ltd
(Applicant)
v
Queensland Building and Construction
Commission
(Respondent)
APPLICATION NUMBER: OCR233-17
MATTER TYPE: Occupational regulation matters
HEARING DATE: 30 October 2017
HEARD AT: On the papers decision
DECISION OF: Member Olding
WRITTEN REASONS
DELIVERED ON:
8 November 2017
DELIVERED AT: Brisbane
ORDERS MADE: The decision of the Queensland Building
and Construction Commission dated 17
October 2017 is stayed, pending the
determination of the application to review or
until further order of the Tribunal, subject to
A B Hill Constructions Pty Ltd (the
Company) undertaking to provide to the
Queensland Building and Construction
Commission:
a. a Minimum Financial Requirements
Report within 28 days of this order; and
b. weekly reporting of its financial
position, including:
i. aged debtors;
ii. aged creditors;
iii. print out of bank account, to show
the current cash at bank;
iv. itemised ATO Portal statements;
v. any correspondence with creditors
regarding payment arrangements
-- 1 of 5 --
2
or any alleged default by the
Company; and
vi. copies of any proceedings by any
creditor, whether by claim or
statutory demand or application to
wind up;
until the determination of the
application to review, or until further
order.
CATCHWORDS: ADMINISTRATIVE LAW – ADMINISTRATIVE
TRIBUNALS – QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL – whether
desirable to make a stay order in respect of a
decision to suspend a builder’s licence – where
applicant failed to meet Minimum Financial
Requirements Policy conditions – where stay
granted subject to applicant’s undertaking to
report financial data to the Queensland Building
and Construction Commission weekly
Queensland Building and Construction
Commission Act 1991 (Qld), s 35, s 48(1)(h)
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 20(1), 22
NGE v Queensland Building and Construction
Commission [2017] QCAT 238
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REPRESENTATIVES:
APPLICANT: represented by Johanson Lawyers
RESPONDENT: represented by Holding Redlich Lawyers
REASONS FOR DECISION
[1] A B Hill Constructions Pty Ltd (the Company) has applied to the Tribunal
for review of the decision of the Respondent Commission to suspend its
builder’s licence on the basis that the Company has failed to satisfy the
Minimum Financial Requirements (MFR) Policy, which is a condition of the
licence.
-- 2 of 5 --
3
[2] The Company also sought a stay of that decision pending the determination
of the review.
[3] I made a stay order on condition that the Company undertakes to provide
an MFR report to the Commission within 28 days, along with weekly reports
of its financial position.
[4] My reasons for granting the stay follow.
Background
[5] The Commission may suspend a licence if the licensee contravenes a
condition to which the licence is subject under the Queensland Building and
Construction Commission Act 1991 (QBCC Act), s 35.1
[6] Under s 35, a contractor’s licence is subject to the condition that “the
licensee’s financial circumstances must at all times satisfy the relevant
financial requirements stated in the [Queensland Building and Construction]
board’s policies”. The relevant policy is the MFR Policy.
[7] The Commission noted that the Company has breached the Policy in two
respects as discussed further below. The issue for determination at the
hearing of the application for review will be whether suspension of the
Company’s licence is the correct and preferable decision.2
The Tribunal’s power to grant a stay
[8] The Tribunal may make an order staying the suspension decision “only if it
considers the order is desirable after having regard to the following:
(a) the interests of any person whose interests may be affected by the
making of the order or the order not being made;
(b) any submissions made to the tribunal by the decision-maker for the
reviewable decision;
(c) the public interest”.3
[9] The Tribunal, in considering stay applications, also takes into account
whether the applicant has an arguable case and the balance of
convenience.4
1 QBCC Act, s 48(1)(h).
2 QCAT Act, s 20(1).
3 QCAT Act, s 22.
4 See NGE v Queensland Building and Construction Commission [2017] QCAT 238 for
an example of the application of the principles applicable to stay applications in the
context of a review of a decision to suspend a builder’s licence.
-- 3 of 5 --
4
Consideration
[10] The Commission did not contest that declining to make a stay order would
adversely affect the Company and its owners. The Company also provided
several statements from customers asking for the suspension to be lifted
because of the impact on their projects.
[11] However, the Commission submitted that it is not in the interests of the
public or the building industry for a company that is breach of the MFR
condition to continue to hold a licence.
[12] The Commission also submitted that the Company’s prospects of success
in the application for review are poor, pointing to the two breaches of the
MFR.
[13] The first is a failure to notify the Commission that the Company’s net
tangible asset position had decreased by more than 30% from its previously
notified position and to provide a new declaration or MFR report to the
Commission within 30 days of that occurring.
[14] The second is a breach of the requirement to pay all undisputed debts as
they fall due and within industry norms. The Commission noted that there
had been two dishonoured payments under the statutory insurance scheme
and other third party debts not paid as they fell due. The latter included six
notified to the Commission in recent “Monies Owed Complaints”.
[15] The Company did not deny that the breaches occurred but pointed to steps
taken, and anticipated receipts, that should remedy the Company’s financial
position, which its director, Adrian Brendan Hill, in a declaration filed in
support of the application, said reflects the “ebbs and flows” of the industry.
[16] One of those steps is that on 27 October 2017 the Company engaged its
accountant to prepare a new MFR report. It is a concern that this has only
now occurred without any explanation for the delay in attending to this
requirement. Mr Hill’s references to the “ebbs and flows” of the industry are
no doubt correct, but this should not have prevented compliance with the
requirement to notify the Commission of the reduction in net tangible assets
and update its MFR status.
[17] These factors raise a concern regarding the Company’s commitment to
meeting the conditions of its licence and may weigh against the Company
in the hearing of the application for review.
[18] The instances of failure to pay debts as they fall due are also of concern
and may also weigh against the Company on the hearing of the review. On
the other hand, information provided by the Company indicates that the
aged debts have now been cleared or payment arrangements entered into
and that a significant net inflow of funds from four projects is anticipated in
the near future. Additionally, information was provided regarding pending
sales of properties, although specific detail of the net amounts likely to be
realised and available to the Company was not.
-- 4 of 5 --
5
[19] In these circumstances, I cannot conclude that the Company has poor
prospects of success in the review. If it provides a new MFR report and the
anticipated funds materialise, having regard to all the circumstances at the
time of the hearing the Tribunal may be persuaded that suspension would
not be the correct and preferable decision at that time.
[20] The risk to the public and the industry in the meantime is a significant factor
weighing against a stay where, as in this case, there have been various
instances of failure to pay debts as they fall due. However, I am satisfied
that, balancing the drastic impact on the Company and its customers of not
granting the stay, that risk would be sufficiently mitigated by the reporting
and other conditions attached to the stay order. If the circumstances
change, such that further risk emerges, it will be open to the Commission
to apply to the Tribunal for variation or withdrawal of the stay.
[21] In those circumstances, it is my view that the balance of convenience
favours granting the stay subject to the reporting and other conditions. The
Company sought fortnightly, rather than weekly, reporting because:
“it will take 2 weeks at least for works to be restarted and a (sic) progress
claims to be made and processed by the owners’ bank. A weekly reporting
condition will show little change for the first weeks.”5
[22] I was not persuaded that the absence of significant change in the
Company’s financial situation for the first few weeks after the stay is a
reason for fortnightly rather than weekly reporting for the whole of the period
in which the Company may be trading pending the determination of the
review. In circumstances where the Company has a recent history of not
meeting its debts as they fall due, involving some six complaints to the
Commission in a few months, weekly reporting is appropriate.
[23] Accordingly, I concluded that it is desirable to make a stay order, but subject
to the reporting and other conditions set out in the order.
5 Applicant’s submissions dated 28 October 2017, paragraph 6.
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2017/391