Dyer v Spence (No 2) [2017] QCAT 375
CITATION: Dyer v Spence (No 2) [2017] QCAT 375
PARTIES: Rowan John Dyer
(Applicant)
v
Robyn Spence
(Respondent)
APPLICATION NUMBER: BDL285-14
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Deane
DELIVERED ON: 6 November 2017
DELIVERED AT: Brisbane
ORDERS MADE: 1. Rowan John Dyer is to pay Robyn
Spence’s costs of and incidental to the
proceedings fixed in the sum of
$118,211.44 by 8 December 2017.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN
STATE AND TERRITORY COURTS – COSTS
– GENERAL MATTERS – POWER TO
AWARD GENERALLY – Where applicant
acted in such a way as to unnecessarily
disadvantage the other party – where
applicant repeatedly non-compliant with
Tribunal directions – where costs sought on an
indemnity basis – where applicant withdrew
application immediately before final hearing –
where respondent awarded costs awarded on
an indemnity basis
Queensland Building and Construction
Commission Act 1991 (Qld), s 77
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 100, s 102, s 105, s 107
Queensland Civil and Administrative Tribunal
Rules 2009 (Qld), r 86
Ascot v Nursing & Midwifery Board of Australia
[2010] QCAT 364
-- 1 of 7 --
2
Colgate Palmolive Co v Cussons Pty Ltd
(1993) 46 FCR 225
Donald Campbell & Co v Pollak (1927) AC 732
Fuge v Queensland Building and Construction
Commission [2014] QCAT 383
Latoudis v Casey [1990] HCA 59
Lyons v Dreamstarter Pty Ltd [2011] QCATA
142
Lyons v Dreamstarter Pty Ltd [2012] QCATA
71
Thiess Pty Ltd v FLSMIDTH Minerals Pty Ltd
(No 2) [2010] QSC 120
Todrell Pty Ltd v Finch (No 2) [2008] 2 Qd R
95
APPEARANCES:
APPLICANT: No appearance by Rowan John Dyer
RESPONDENT: Robyn Spence
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REPRESENTATIVES:
APPLICANT: No representative for Rowan John Dyer
RESPONDENT: Self-represented
REASONS FOR DECISION
[1] On 19 June 2017, I ordered Mr Dyer, a builder, to pay Ms Spence
$138,826.18 in respect of her claims against him arising out of a domestic
building contract between them. I also made directions for the making of
any application for costs.
[2] On 21 July 2017, in accordance with my directions, Ms Spence made an
application for her costs. Mr Dyer was given the opportunity to make
submissions in response but none have been filed. It is appropriate to
decide the costs application on the papers, as there has been no request
for an oral hearing.
[3] Ms Spence seeks costs on a full indemnity basis for all her costs of and
incidental to this dispute on the grounds that Mr Dyer unnecessarily
caused her significant prejudice and disadvantage. Ms Spence claims
she incurred costs in the sum of $141,957.71, an amount more than the
amount awarded to her by my decision of 19 June 2017. Ms Spence
provided copies of invoices from her solicitors, counsel, experts and other
outlays to substantiate the costs incurred.
-- 2 of 7 --
3
[4] I previously ordered Mr Dyer to pay Ms Spence’s costs thrown away by
his request for a late adjournment of the final hearing in the sum of
$22,856.27. She now seeks an order for the balance, $119,101.44.
[5] As at 21 July 2017, Mr Dyer had not paid Ms Spence’s costs thrown
away, which were ordered to be paid by 28 October 2016.
[6] The QCAT Act provides, ‘other than as provided under this Act or an
enabling Act, each party to a proceeding must bear the party’s own costs
for the proceedings.’1
[7] The Tribunal’s discretion to award costs in a building dispute2 is a broader
and more general discretion than the one conferred by the QCAT Act3
because there is an express power to award costs conferred by the
Queensland Building and Construction Commission Act 1991 (Qld)
(‘QBCC Act’), the relevant enabling Act. Unlike in the QCAT Act, there is
no strong contra-indication in section 77 of the QBCC Act against a costs
order.
[8] It remains necessary to consider whether an award of costs is justified in
the circumstances.
[9] In Lyons v Dreamstarter Pty Ltd4 the then President, Justice Wilson stated
at [11]:
The discretion to award costs starts with the proposition that it is just and
reasonable that a party who causes another to incur costs should
reimburse the other party for them.5 Otherwise, the factors affecting the
discretion will vary in each case6.
[10] The Tribunal, in exercising its general discretion to award costs, may
consider the factors referred to in section 102(3) of the QCAT Act.
[11] The then Deputy President, Judge Kingham in Ascot v Nursing &
Midwifery Board of Australia7 stated at [9]:
The considerations identified in s 102(3) are not grounds for awarding
costs. They are factors that may be taken into account in determining
whether, in a particular case, the interests of justice require the tribunal to
make a costs order.
[12] Those considerations are largely in the nature of what may be regarded as
‘entitling’ or ‘disentitling’ factors.
1 QCAT Act, s 100.
2 Queensland Building and Construction Commission Act 1991(Qld) (QBCC Act),
s 77(3)(h); Lyons v Dreamstarter Pty Ltd [2011] QCATA 142.
3 QCAT Act, s 100, s 102.
4 [2012] QCATA 71.
5 Latoudis v Casey [1990] HCA 59.
6 Donald Campbell & Co v Pollak (1927) AC 732, 811-12.
7 [2010] QCAT 364.
-- 3 of 7 --
4
Is it in the interests of justice to exercise the discretion to award costs?
[13] I find that it is in the interests of justice to award Ms Spence costs in these
proceedings. If the Tribunal makes a costs order, it is to fix the costs if
possible. 8
[14] Ms Spence’s submissions do not expressly address the factors in section
102(3) of the QCAT Act.
Whether a party acts in a way that unnecessarily disadvantages another party9
[15] I find that Mr Dyer acted in a way that unnecessarily disadvantaged Ms
Spence. This is a factor in favour of an award of costs to Ms Spence.
[16] Ms Spence’s submissions particularly rely upon this factor.
[17] By letter dated 29 October 2014 to Mr Dyer, Ms Spence’s solicitors sought
details about Mr Dyer’s claims for payment so that she could ascertain
whether monies were due to Mr Dyer or a refund was due to Ms Spence.
In late November 2014, Mr Dyer commenced these proceedings claiming
$30,146.00 in respect of moneys owing for work performed under the
contract and in respect of variations, having failed to provide the
information requested.
[18] On 9 January 2015, Ms Spence filed a Response seeking the claim be
dismissed with costs.
[19] On 18 November 2015, Ms Spence filed an Amended Response and
Counter-application, which sought orders that Mr Dyer pay significant
sums to Ms Spence on various bases together with her costs.
[20] On 6 April 2016, the application was listed for a final hearing on 9 and 10
June 2016.
[21] On 9 June 2016, Mr Dyer sought and I granted an adjournment to allow
him to obtain legal advice. The application was re-listed for final hearing
on 8 and 9 September 2016.
[22] Quite unusually, on 13 July 2016, Mr Dyer filed a Notice of Withdrawal of
his claim. This action necessitated a further directions hearing on 22 July
2016.
[23] From a review of the file, it is apparent that Mr Dyer failed to comply with
numerous directions, in particular failing to file and serve statements of
evidence including expert reports. Mr Dyer never filed any expert’s
reports. I accept that such failure lead to additional directions hearings,
delay and cost to Ms Spence.
8 QCAT Act, s107
9 Ibid, s 102(3)(a).
-- 4 of 7 --
5
[24] The documents filed purporting to be statements of evidence on 7 May
2015 and on 9 February 2016 were quite voluminous as they attached
copies of a large number of primary documents such as supplier invoices.
The statements did not clearly explain the relevance of the documents. I
accept that the state of Mr Dyer’s evidence would have increased Ms
Spence’s costs because it lead to further correspondence and further
directions to seek to clarify the evidence. A possible explanation for the
state of Mr Dyer’s evidence is that he was self-represented for most of the
proceedings.
[25] Unfortunately, some non-compliance with directions is not unusual.
However, I accept that the extent and degree of non-compliance and the
withdrawal of the claim in July 2016 after pursuing the claim since
November 2014 is evidence that Mr Dyer’s conduct unnecessarily
disadvantaged Ms Spence. As Ms Spence points out Mr Dyer’s pursuit of
his claim delayed her ability to make and/or to have determined a claim
under the home owners insurance scheme operated by the Queensland
Building and Construction Commission. Ms Spence contends that but for
Mr Dyer commencing the proceedings she would not have made a
counter-application and would have pursued her claim under the home
owners insurance scheme. She has been put to considerable expense
and inconvenience in having to defend Mr Dyer’s claims.
The nature and complexity of the dispute10
[26] Both parties were granted leave to be legally represented.11
[27] I accept that the proceeding involved some complex factual and legal
issues, which warranted legal representation.
[28] This is a factor in favour of an award of costs but it is not determinative.12
The relative strengths of the claims13
[29] Mr Dyer withdrew his claim before it was determined. He did not file a
Response to Ms Spence’s counter-application and he failed to appear on
the adjourned final hearing date. Some of the evidence he had filed in
support of his claim related to some of Ms Spence’s heads of counter-
claim. Ms Spence was substantially successful. In this sense, Ms
Spence’s claims were stronger on the matters on which she succeeded.
[30] This is a factor in favour of an award of costs.
10 QCAT Act, s 102(3)(b).
11 Direction dated 23 March 2015.
12 Fuge v Queensland Building and Construction Commission [2014] QCAT 383, [21].
13 QCAT Act, s 102(3)(c).
-- 5 of 7 --
6
The financial circumstances of the parties14
[31] On balance, this is a factor in favour of an award of costs to Ms Spence.
[32] Ms Spence submits that her financial circumstances have been
significantly depleted by these proceedings and Mr Dyer’s defective work.
The evidence before me, which I accept, is that Ms Spence’s husband
died a short time prior to her engaging Mr Dyer to perform the building
work. Ms Spence’s submissions outline that after her husband’s death she
was left a non-paid homemaker and that she has had to rely upon her
personal savings, which are now exhausted and borrowings to fund her
defence of these proceedings.
[33] There is little evidence of Mr Dyer’s financial circumstances before me.
Ms Spence contends that Mr Dyer remains a licensed builder and
continues to earn an income.
[34] A search of the QBCC website confirms Mr Dyer holds a current site
supervisor’s licence and has earning capacity.
Anything else the Tribunal considers relevant15
[35] A factor, which is sometimes relevant, is whether or not either party sought
to protect itself through the making of offers to settle.16 Ms Spence did
not refer me to any relevant settlement offers.
[36] On 9 June 2016, I ordered the Registry to remove attachment ‘S’ to Mr
Dyer’s statement filed 9 February 2016 and place it in a sealed envelope,
which was not to be opened until after the substantive decision in the
matter was made. I have now viewed attachment ‘S’, which consists of
correspondence between Mr Dyer’s then solicitors and Ms Spence’s
solicitors.
[37] Relevantly on 9 April 2015, Mr Dyer offered to settle all claims between
them on the basis that Ms Spence pay him $21,000.00. The outcome of
the proceedings reveal that Ms Spence was justified in not agreeing to
settle on that basis.
[38] I note that Ms Spence filed her Counter-application some months after this
offer was made.17
[39] The costs Ms Spence has incurred in securing the benefit of the decision
will significantly erode her success if she is not awarded costs.
14 Ibid, s 102(3)(e).
15 QCAT Act, s102(3)(e)
16 Ibid, s 105; Queensland Civil and Administrative Tribunal Rules 2009 (Qld) (‘QCAT
Rules’), r 86.
17 Filed 18 November 2015.
-- 6 of 7 --
7
Indemnity costs
[40] Ms Spence seeks costs on a full indemnity basis for all her costs of and
incidental to this dispute.
[41] The applicable principles, as to whether to order indemnity costs, were
summarised in Colgate Palmolive Co v Cussons Pty Ltd.18 Essentially
there needs to be some special feature to justify the exercise of the
discretion. The special feature has been described as something
‘irresponsible’ or ‘unreasonable’ on the part of the other party.19
[42] I am satisfied that, in the current circumstances, commencing proceedings
and then choosing to abandon them immediately before the final hearing
is a special or unusual feature.
[43] I have reviewed the invoices and the individual claims. I am not satisfied
that items 6 and 19, each for $445.00, in respect of Coastal Building
Certifications charges are in the nature of costs and so disallow those
claims. They relate to fees paid to extend the Council building approval.
[44] Having regard to my previous order for costs, I fix Ms Spence’s costs of
the proceeding in the sum of $118,211.44. It is appropriate to allow some
time for payment.
18 (1993) 46 FCR 225.
19 Todrell Pty Ltd v Finch (No 2) [2008] 2 Qd R 95 at 96; Thiess Pty Ltd v FLSMIDTH
Minerals Pty Ltd (No 2) [2010] QSC 120.
-- 7 of 7 --