DBI Group Pty Ltd v Wayne Leslie Banks T/A Wayne Banks Concreting [2017] QCAT 348
CITATION: DBI Group Pty Ltd v Wayne Leslie Banks T/A
Wayne Banks Concreting [2017] QCAT 348
PARTIES: DBI Group Pty Ltd
(Applicant)
v
Wayne Leslie Banks T/A Wayne Banks
Concreting
(Respondent)
APPLICATION NUMBER: BDL326-16
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Senior Member Brown
DELIVERED ON: 13 October 2017
DELIVERED AT: Brisbane
ORDERS MADE: 1. DBI Group Pty Ltd must pay Wayne Leslie
Banks T/A Wayne Banks Concreting’s
costs of the proceeding on the standard
basis.
2. Wayne Leslie Banks T/A Wayne Banks
Concreting must file in the Tribunal two (2)
copies and give to DBI Group Pty Ltd one
(1) copy of submissions addressing:
a) the assessment of costs on the
standard basis; and
b) fixing the costs, by:
4:00pm on 23 October 2017.
3. DBI Group Pty Ltd must file in the Tribunal
two (2) copies and give to Wayne Leslie
Banks T/A Wayne Banks Concreting one
(1) copy of submissions in reply, by:
4:00pm on 30 October 2017.
-- 1 of 10 --
2
4. Further orders in relation to costs will be
made by the Tribunal on the basis of the
written submissions by the parties and
without an oral hearing, not before:
4:00pm on 30 October 2017.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN
STATE AND TERRITORY COURTS – COSTS
– GENERAL RULE: COSTS FOLLOW EVENT –
where costs sought by respondent – where
applicant withdrew the application – where no
automatic rule that costs follow the event –
where discretion must be exercised in awarding
costs – where no special or unusual feature as
to allow costs on an indemnity basis – where
costs awarded on a standard basis
Queensland Building and Construction
Commission Act 1991 (Qld), s 77(3)(h)
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 46(1), s 46(2), s 100, s 106,
s 107(1), s 107(2)
Queensland Civil and Administrative Rules 2009
(Qld), r 57A
Uniform Civil Procedure Rules 1999 (Qld),
r 307(2)
Colgate-Palmolive Company v Cussons Pty Ltd
(1993) 46 FCR 225
Johnson v Clancy [2010] NSWSC 1301
Jones v Jones [2012] QSC 342
Jvancich v Kennedy (No 2) [2004] NSWCA 397
LPD Holdings (Aust) Pty Ltd v Phillips, Hickey
and Toigo [2013] QCA 305
Lyons v Dreamstarter Pty Ltd [2011] QCATA 142
Lyons v Dreamstarter Pty Ltd [2012] QCATA 071
Rainbow Builders Pty Ltd v The State of
Queensland through the Department of Housing
and Public Works (No. 2) [2016] QCAT 497
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REPRESENTATIVES:
APPLICANT: represented by BCCS Law
RESPONDENT: represented by James & Co Lawyers
-- 2 of 10 --
3
REASONS FOR DECISION
[1] DBI Group Pty Ltd commenced an application for a domestic building
dispute against Mr Banks as respondent. DBI subsequently withdrew its
application. Mr Banks now seeks his costs of the proceeding.
[2] DBI constructed a home at Dundowran Beach. DBI engaged Mr Banks to
undertake the construction of a driveway at the residence. Mr Banks
performed the building work, however DBI claimed that the work was
defective.
[3] The Queensland Building and Construction Commission became involved
with the building works after a complaint by the homeowner about the
construction of the driveway. The Queensland Building and Construction
Commission (“QBCC”) requested DBI to carry out rectification works.1 The
works included rectification of cosmetic issues with the driveway relating to
the sealed finish, a slip hazard associated with the sealed finish and
cracking to the driveway. Rectification works were carried out however the
homeowner remained unhappy with the result of those works.
[4] The QBCC subsequently issued a Direction to Rectify.2 In separate
proceedings in the Tribunal, Mr Banks sought to review the decision by the
QBCC to issue the Direction to Rectify.3 Mr Banks withdrew his review
application after the QBCC agreed to withdraw the Direction to Rectify.4
[5] DBI commenced this proceeding in the Tribunal on 16 December 2016. A
response was filed by Mr Banks on 25 January 2017. The response
included a counter application in which Mr Banks sought the dismissal of
the application and the payment of his costs. In reality, what was raised in
the counter application was not a separate claim by Mr Banks against DBI
but rather a prayer for relief.
[6] The Tribunal ordered that the parties have leave to be legally represented
in the proceeding.5 A compulsory conference was held on 23 March 2017
and directions made for the parties to, among other things, file statements
of evidence.
[7] DBI did not file its statements of evidence as directed. Mr Banks filed his
statements of evidence as directed. On 23 June 2017 Mr Banks filed an
application seeking orders striking out the application by DBI as a result of
its non compliance with Tribunal directions.6 As events transpired, the
Tribunal was not required to determine the strike out application. DBI
withdrew its application on 11 July 2017.7
1 Letter QBCC to DBI dated 20.06.16.
2 Direction to Rectify dated 13.10.16.
3 GAR285-16.
4 Notice of Withdrawal dated 30.05.17.
5 Directions made 23.03.17.
6 Application for Miscellaneous Matters filed 23.06.17.
7 Notice of Withdrawal filed 11.07.17.
-- 3 of 10 --
4
[8] On 27 July 2017 Mr Banks filed an application seeking an order that DBI
pay his costs of the proceeding on an indemnity basis or, in the alternative,
on a standard basis.
[9] I do not propose to traverse at length the costs submissions filed by the
parties. Suffice it to say, Mr Banks submits that DBI failed to comply with
Tribunal directions and that its application was without merit and bound to
fail. DBI has filed an affidavit by its director, Mr Boyd. Mr Boyd says that he
formed the view that there was ‘no point in chasing Wayne Banks any
further’.8 Mr Boyd says that he was struggling to cope with the recent death
of his father and instructed his then solicitors to withdraw DBI’s application.
Somewhat tellingly, Mr Boyd says:
At no time whatsoever did Spire Law advise the Applicant that if it withdrew
the Application, it may become exposed to an adverse costs order being
made in the proceeding. If I had been aware of such exposure, I would not
have pursued the withdrawal of the Application by the Applicant but would
have instead engaged alternative solicitors to seek an extension of the times
for the Applicant’s compliance with the timetable directed by the Tribunal and
otherwise have caused the Applicant to progress the Application against the
Respondent (who I still believe was the cause of the loss and damage
suffered by the Applicant in respect of the defective driveway).9
[10] Not unsurprisingly Mr Banks places some reliance upon what Mr Boyd says
about the advice he received, or did not receive, from his solicitors. Mr
Banks says that DBI was legally represented, at least from 14 March 2017,
and that if Mr Boyd was not advised of any potential costs consequences
as a result of withdrawing his application, that is a matter between DBI and
its former solicitors.
Awarding costs – the relevant principles
[11] Other than as provided under the QCAT Act or an enabling Act, each party
to a proceeding must bear the party’s own costs for the proceeding.10 The
relevant enabling Act for the purposes of this proceeding is the Queensland
Building and Construction Commission Act 1991 (Qld). The Tribunal may,
in a building dispute, award costs.11
[12] Of the operation of s 77(3)(h) of the Queensland Building and Construction
Commission Act 1991 (Qld) (“QBCC Act”), which is expressed in general
terms, then Deputy President of QCAT Kingham observed:
A jurisdiction given in general terms allows the Tribunal to make an order as
to costs that is justified in the circumstances. It is a broad general discretion
which must be exercised judicially, not upon irrelevant or extraneous
considerations but upon facts connected with or leading up to the litigation.
…
8 Affidavit of Anthony John Boyd sworn 04.09.17.
9 Ibid, 4 [12].
10 QCAT Act, s 100.
11 QBCC Act, s 77(3)(h).
-- 4 of 10 --
5
There is a clear inconsistency between a provision that confers on the
Tribunal a broad and general discretion to award costs (QBSA Act, s77(1)(h))
and one which states that, unless otherwise provided each party must bear
their own costs (QCAT Act, s 100).12
[13] Then QCAT President Alan Wilson J subsequently considered s 77(3)(h),
finding:
In building cases that have elements of complexity, the Queensland Court of
Appeal has suggested that costs awards will not be surprising. That case
concerned, however, costs provisions in different legislation governing
QCAT’s predecessor Tribunal.
In any event, the power to award costs under the QBSA Act, while expressed
in succinct terms, indicates that the question of costs is to be addressed in
markedly different terms from s 100 of the QCAT Act.
The High Court has said that there is no automatic rule that costs ‘follow the
event’ (i.e., the outcome of the proceeding) or that the unsuccessful party
must compensate the successful one. The discretion to award costs starts
with the proposition that it is just and reasonable that a party who causes
another to incur costs should reimburse the other party for them. Otherwise,
the factors affecting the discretion will vary in each case.13 (footnotes omitted)
[14] Alan Wilson J identified as one of the relevant factors that the appellant had
been successful in his appeal on all grounds.
[15] The discretion to award costs must be exercised judicially and in
accordance with established principles. A successful litigant is, generally
speaking, entitled to an order of costs, and to deprive a successful party of
their costs (in circumstances where there is an entitlement to such costs) is
an exceptional measure.14 Whilst a successful party to a building dispute in
the Tribunal has no entitlement to costs, in the exercise of the discretion to
award costs pursuant to the power conferred by s 77(3)(h) of the QBCC Act,
the principle that costs usually follow the event has some significance as
one of the relevant discretionary factors.
[16] If the Tribunal makes a costs order, the Tribunal must fix the costs if
possible15. If it is not possible to fix the costs, the Tribunal may make an
order requiring the assessment of the costs under the rules.16
12 Lyons v Dreamstarter Pty Ltd [2011] QCATA 142, 7 [33], [37] citing Oshlak v Richmond
River Council (1998) 193 CLR 72 at 88 and Latoudis v Casey (1990) 170 CLR 534 at
557.
13 Lyons v Dreamstarter Pty Ltd [2012] QCATA 071, 3 [9]–[11] citing Tamawood Ltd v
Paans [2005] QCA 111, per Keane JA at [32], Foots v Southern Cross Mine
Management Pty Ltd (2007) 234 CLR 52 at [26], Latoudis v Casey (1990) 170 CLR 534
and Donald Campbell & Co v Pollak (1927) AC 732 at 811-12.
14 Rainbow Builders Pty Ltd v The State of Queensland through the Department of
Housing and Public Works (No. 2) [2016] QCAT 497.
15 QCAT Act, s 107(1)
16 Ibid s 107(2).
-- 5 of 10 --
6
Consideration
[17] Unlike the rules relating to the discontinuance of proceedings under the
Uniform Civil Procedure Rules 1999 (Qld) (“UCPR”),17 the QCAT Act and
the Queensland Civil and Administrative Rules 2009 (Qld) (“QCAT Rules”)
are silent on the issue of costs where an application is withdrawn. This is
perhaps unsurprising given the general contraindication regarding the
awarding of costs found at s 100 of the QCAT Act.
[18] An applicant in the Tribunal may file a Notice of withdrawal of an application
or referral at any stage of a proceeding before the matter is heard and
decided.18 Certain applications or referrals may only be withdrawn with the
leave of the Tribunal.19 The withdrawal of an application for a building
dispute does not require leave. To withdraw an application for a building
dispute an applicant must file and serve on each other party to the
proceeding a notice in the approved form.20 Once an applicant complies
with the requirements under the QCAT Act and Rules for withdrawal, the
proceeding is at an end. The Tribunal may however award costs under the
QCAT Act or an enabling Act at any stage of a proceeding or after the
proceeding has ended.21
[19] The consequences of the withdrawal of an application for a building dispute
may include an application for costs by the other party.
[20] Rule 307(2) of the UCPR provides that if a party discontinues or withdraws
with the court’s leave, the court may make the order for costs it considers
appropriate. In Jones v Jones22 McMeekin J, in considering the issue of
costs pursuant to s 307(2) of the UCPR, referred to the ‘comprehensive
summary of the considerations that should influence the exercise of the
discretion in a case where one party withdraws’ found in Johnson v
Clancy.23 Not all of the considerations identified in Johnson are relevant to
proceedings for building disputes in the Tribunal, however (and subject to
some appropriate modification) they include:
a) Costs discretions are truly discretionary and there are no absolute
rules; the discretion must be exercised judicially;
b) The purpose of a costs order is to compensate, or indemnify, the
person in whose favour it is made, not to punish the person against
whom it is made;
17 UCPR, r 307.
18 QCAT Act, s 46(1).
19 Ibid, s 46(2).
20 QCAT Rules, r 57A.
21 QCAT Act, s 106.
22 [2012] QSC 342.
23 [2010] NSWSC 1301.
-- 6 of 10 --
7
c) Generally, there must be some proper justification, sound positive
ground, or a good reason, for departing from the ordinary position that
a successful party is entitled to recover their costs of a proceeding;
d) Circumstances which might support a departure from the ordinary
position include where the proceedings have been rendered
unnecessary by circumstances beyond the applicant’s control; where
the applicant achieved practical success in the proceedings; or where
costs have been significantly increased by the unreasonable conduct
of the respondent. If there is to be a departure from the ordinary
position regarding costs, it should be done in a particularized, and
principled way;
e) Where the proceedings are discontinued prior to any hearing on the
merits, the Tribunal cannot try a hypothetical action between the
parties to determine the question of costs. At the time of withdrawal,
usually it will be impracticable to assess the eventual prospects of
success in the action;
f) It may be necessary to analyse the whole of the proceedings to
determine the appropriate costs order. A relevant consideration is
whether the applicant acted reasonably in commencing the
proceedings and whether the respondent acted reasonably in
defending them; all the relevant circumstances, and not just the fact of
discontinuance, should be considered; thus, the reasons for the
discontinuance can bear heavily on the exercise of the discretion as to
costs;
g) In a particular case, it might be appropriate for the Tribunal, in its
discretion, to consider the conduct of the respondent prior to the
commencement of the proceedings where such conduct may have
precipitated the litigation;
h) It is important to draw a distinction between cases in which one party,
after litigating for some time, effectively surrenders to the other, and
cases where some supervening event, or settlement, so removes, or
modifies, the subject of the dispute that, although it could not be said
that one side has simply won, no issue remains between the parties
except that of costs. In the former type of case, there will commonly be
lacking any basis for an exercise of the Tribunal’s discretion otherwise
than by an award of costs by the successful party. It is the latter type
of case that usually creates problems, since there may be difficulty in
discerning a clear reason why one party, rather than the other, should
bear the costs;
i) Where the proceedings are discontinued after interlocutory relief has
been granted, the Tribunal may take into account the fact that that
interlocutory relief has been granted;
j) There is a risk that the subjective motivations of the applicant in
discontinuing may be put forward as a basis for some other order.
-- 7 of 10 --
8
Except to the extent that such views may have been put before the
respondent, for example as a basis for settlement, and are established
as such on the evidence, subjective considerations of one party will
generally be immaterial, so that the discretion will be exercised on the
basis of the objective circumstances established on the evidence;
k) The Tribunal is required to make such order as it thinks just in the
particular circumstances of the case.
[21] Although the above considerations arise out of the provisions of the UCPR,
rule 307(2) is concerned with the exercise of the discretion to award costs
where a proceeding is discontinued or withdrawn. Accordingly, the
discretionary considerations are directly relevant and applicable in
proceedings in the tribunal in circumstances where the tribunal is required
to exercise a broad general discretion, judicially, and not upon irrelevant or
extraneous considerations but upon facts connected with or leading up to
the litigation.
[22] Turning then to the relevant considerations, the matter has not been
resolved as between the parties such that DBI could be said to have
achieved practical success in the proceeding nor is there any evidence
before me to suggest that costs have been increased as a result of any
unreasonable conduct by Mr Banks.
[23] Mr Banks in his submissions places some reliance on what he says were
DBI’s relatively poor prospects of success in the proceeding. It is not
possible to assess the parties eventual prospects of success in the
proceeding particularly as only Mr Banks had filed his statements of
evidence.
[24] DBI could not be said to have acted unreasonably in commencing the
proceeding nor did Mr Banks act unreasonably in defending the proceeding.
That the QBCC withdrew the Direction to Rectify was not determinative of
whether work carried out by Mr Banks was defective. This was ultimately a
matter for the Tribunal to determine. Nor could it be said that the conduct of
Mr Banks precipitated the application by DBI. Mr Banks maintained that the
work he carried out was not defective. He considered the actions by the
QBCC in withdrawing the Direction to Rectify lent support to his position. It
was not unreasonable that he did so.
[25] This is clearly a case in which DBI has surrendered to Mr Banks rather than
there having occurred a supervening event or settlement removing or
modifying the subject of the dispute. There remains an issue in dispute
between the parties regarding the building works performed by Mr Banks.
This much is made clear by Mr Boyd in his affidavit in which he states that
he still considers the work performed by Mr Banks to be defective and had
he known of the possible costs consequences flowing from the withdrawal
of the application he would not have discontinued the proceeding.
[26] The subjective considerations referred to by Mr Boyd for withdrawing the
application, principally the difficulties experienced by Mr Boyd in coping with
-- 8 of 10 --
9
the death of his father, are irrelevant. There is no evidence before me to
suggest that these were matters raised with Mr Banks before the filing of
the Notice of Withdrawal or that Mr Banks had any knowledge of Mr Boyd’s
subjective motivations in discontinuing the proceeding.
[27] As the QCAT Appeal Tribunal has observed, in building disputes the
Tribunal may make an order for costs that is justified in the circumstances.
An order that costs follow the event can be consistent with the overall justice
of the case.24
[28] In my view, weighing all of the relevant considerations, it is appropriate that
DBI should pay Mr Banks’ costs.
Should costs be on the standard or indemnity basis?
[29] Mr Banks seeks his costs on the indemnity basis. Circumstances which
might give rise to an order for indemnity costs were identified by Sheppard
J in Colgate-Palmolive Company v Cussons Pty Ltd:25
a) where allegations of fraud have been made knowing them to be false
and the making of irrelevant allegations of fraud;
b) evidence of particular misconduct that causes loss of time to the court
and to other parties;
c) the fact that the proceedings were commenced or continued for some
ulterior motive or in wilful disregard of known facts or clearly
established law;
d) the making of allegations which ought never to have been made or the
undue prolongation of a case by groundless contentions;
e) an imprudent refusal of an offer to compromise.
[30] As Sheppard J noted in Colgate-Palmolive, the question is whether the
particular facts and circumstances of the case in question warrant the
making of an order for payment of costs other than on a party and party
basis. The justification for an award of indemnity costs requires some
special or unusual feature of the particular case.26
[31] For the reasons I have set out, the circumstances do not warrant the making
of an order for costs on the indemnity basis. Mr Banks is entitled to recover
his costs of the proceeding on the standard basis and I order accordingly.
24 Jvancich v Kennedy (No 2) [2004] NSWCA 397.
25 (1993) 46 FCR 225.
26 LPD Holdings (Aust) Pty Ltd v Phillips, Hickey and Toigo [2013] QCA 305.
-- 9 of 10 --
10
Assessing the costs
[32] The Tribunal should fix costs if possible.27 It is not possible, in the absence
of further submissions from the parties, for me to do so. I direct the parties
to file submissions on the assessment and fixing of costs in accordance with
these reasons. Upon the filing of those submissions, final orders will be
made in relation to the costs of the proceeding.
27 QCAT Act, s 107(1).
-- 10 of 10 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2017/348