Barns v Commissioner, Queensland Fire & Emergency Services [2017] QCAT 263
CITATION: Barns v Commissioner, Queensland Fire &
Emergency Services [2017] QCAT 263
PARTIES: James Thomas Barns
Lynette Joy Barns
(Applicants)
v
Commissioner, Queensland Fire & Emergency
Services
(Respondent)
APPLICATION NUMBER: GAR028-17
MATTER TYPE: General administrative review matters
HEARING DATE: 31 July 2017
HEARD AT: Brisbane
DECISION OF: Member Olding
DELIVERED ON: 7 August 2017
DELIVERED AT: Brisbane
ORDERS MADE: 1. The Respondent’s application to
strike out a proceeding, filed on 22
May 2017, is dismissed.
2. Each party is to bear their own costs
of the application.
3. The application for review is to be
listed for a directions hearing at a
date to be advised.
CATCHWORDS: ADMINISTRATIVE LAW – ADMINISTRATIVE
TRIBUNALS – QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL – where
Commissioner decided not to accept late
application for compensation – whether
Tribunal has jurisdiction to review decision
Acts Interpretation Act 1954 (Qld), s14A, s
14B, s 35
Disaster Management Act 2003 (Qld), s 125
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 100, s 102
CIC Insurance Ltd v Bankstown Football Club
Ltd (1997) 187 CLR 384
-- 1 of 13 --
2
Dyankov v Minister for Immigration and Border
Protection [2017] FCAFC 81
The Owners of the Ship “Shin Kobe Maru” v
Empire Shipping Company Inc (1994) 181
CLR 404
APPEARANCES:
APPLICANT: James Thomas Barns and Lynette Joy Barns
RESPONDENT: Commissioner, Queensland Fire & Emergency
Services
REPRESENTATIVES:
APPLICANT: represented by Ms K M Riedel of Counsel,
instructed by Condon Charles Lawyers
RESPONDENT: represented by Mr M J Woodford of Counsel,
instructed by Crown Law
REASONS FOR DECISION
[1] A person who suffers loss or damage because of the exercise or
purported exercise of certain powers under the Disaster Management Act
2003 (Queensland) (“the Disaster Management Act”)1 is, subject to certain
conditions, entitled to be paid just and reasonable compensation under
that Act.2
[2] An application for compensation must be made to the Respondent
Commissioner within 90 days after the loss or damage is suffered.3
However, the Commissioner may accept an application made more than
90 days after the loss or damage is suffered if satisfied that it would be
reasonable to do so.4
[3] The Applicants, Mr and Mrs Barns, applied to the Commissioner for such
compensation. Their application was made outside the 90-day period. The
Commissioner, not being satisfied that it was reasonable to accept the
late application, did not accept, and therefore did not consider, the
application or pay any compensation.
[4] The Commissioner says the only decision that has been made is to not
accept the late application. The Tribunal does not have jurisdiction to
review that decision, the Commissioner says, and therefore the
Applicants’ application for review should be struck out.
1 All legislative references are to the Disaster Management Act, unless otherwise
indicated.
2 Section 121(1).
3 Section 121(2).
4 Section 121(5).
-- 2 of 13 --
3
[5] The Applicants argue that the Tribunal does have jurisdiction and
therefore the Commissioner’s application to strike out their application for
review should be dismissed, and also that the Commissioner should pay
their costs of the strike out application.
[6] I have decided that the Tribunal does have jurisdiction to hear and decide
the application for review and therefore the strike out application should
be dismissed, but that the Applicants are not entitled to costs. My reasons
follow.
Legislative framework
[7] The only source of the Tribunal’s jurisdiction to review the Commissioner’s
compensation decisions is section 125 of the Disaster Management Act,
which reads:
125 Review of a decision to pay compensation
An applicant for the payment of compensation under this division who is
dissatisfied with the chief executive’s decision to refuse to pay compensation or
about the amount of compensation may apply, as provided under the QCAT
Act, to QCAT for a review of the decision.
[8] The question for determination is whether the Commissioner’s decision
not to accept Mr and Mrs Barns’ application, which had the consequence
of no compensation being considered or paid, is a “decision to refuse to
pay compensation”.
[9] This question must be considered in the context of the surrounding
provisions of the Act, which include those extracted below.
[10] Section 121 relevantly provides:
121 Applying for compensation
(1) A person who suffers loss or damage because of the exercise, or
purported exercise, of a power under section 77, 78, 111 or 112 may
apply to the chief executive for compensation for the loss or damage.
(2) The application must be made in writing within 90 days after the person
suffers the loss or damage.
(3) . . .
(4) . . .
(5) Despite subsection (2), the chief executive may accept a person’s
application for compensation made more that 90 days after the person
suffers the loss or damage if the chief executive is satisfied it would be
reasonable in all the circumstances to accept the application.
[11] Section 123 provides:
-- 3 of 13 --
4
123 Deciding application
(1) The chief executive must consider and decide an accepted application
within 60 days after the last of the following to happen-
(a) the chief executive receives the application;
(b) the chief executive receives all necessary information to decide the
application.
(2) If the chief executive has not decided an accepted application within the
period stated in subsection (1) for the application, the chief executive is
taken to have refused to pay compensation.
(3) In this section-
accepted application means an application made under section 121(2) or
an application the chief executive accepts under section 121(5).
[12] Section 124 provides:
124 Notice about decision
As soon as practicable after deciding the application, the chief executive must
give the applicant a written notice stating all of the following-
(a) the decision and the reasons for it;
(b) if the chief executive decides to pay compensation-
(i) details of the amount and how the amount was assessed; and
(ii) if the amount is less than the amount claimed– the matters
mentioned in the QCAT Act, section 157(2)(c) to (e);
(c) if the chief executive decides not to pay compensation- the matters
mentioned in the QCAT Act, section 157(2)((c) to (e).
Summary of the Commissioner’s submissions
[13] The Commissioner’s argument is straightforward:
(1) For late applications, the provisions create a two-step process
requiring two distinct decisions.
(2) First, the Commissioner as chief executive decides under s 121(5)
whether to accept the late application.
(3) Next, if the Commissioner decides to accept the late application, the
Commissioner must consider and decide the application.
(4) This, so the argument goes, is clear from s 123, which is only
concerned with “accepted applications”, an expression defined in
-- 4 of 13 --
5
s 123(3) to mean a late application that the chief executive accepts
(and applications lodged on time).
(5) The Commissioner argues that there is no provision for the Tribunal
to review of the first decision – whether to accept a late application –
because a decision not to accept a late application is not, according
to the Commissioner, a decision to refuse to pay compensation.
(6) Only the second decision – whether to pay compensation, and if so
how much, in relation to an accepted application – has that character,
according to the Commissioner.
Summary of Applicants’ submissions
[14] The Applicants argue that, considered in its context, the expression
“decision to refuse to pay compensation” in section 125 covers any case
where an applicant applies for compensation and does not receive it,
whether because the application was considered and refused or, as in this
case, it was not accepted as a late application.
Construction of section 125
[15] This matter raises a difficult question of statutory construction.
[16] As the High Court regularly reiterates,5 the construction of section 125 is
to be derived from its text, context and purpose.
Textual and contextual considerations
[17] The Commissioner’s argument has considerable force. Taken together, in
the order the provisions appear, the more natural reading is that:
(1) Section 123 requires the Commissioner to consider and decide an
“accepted application”;
(2) As soon as possible after deciding “the application” – that is, as the
Commissioner would say, the accepted application referred to in the
immediately preceding section – section 124 requires notice of “the
decision” to be given – again, the decision on the accepted
application referred to in the immediately preceding section; and
(3) Section 125 provides a review right for “the chief executive’s decision
to refuse to pay compensation or about the amount of the
compensation” – that is, the decision on the accepted application
5 Reiterated recently by Nettle J in Talacko v Bennett [2017] HCA 15, [82]. See also the
authorities referenced by his Honour at footnote 85.
-- 5 of 13 --
6
referred to in section 123 and, as the argument goes, also in section
124.
[18] There is, though, an alternative construction of the provisions that is
reasonably open. On a broader reading of section 125, where an
applicant makes an application for compensation outside the 90-day
period, which the Commissioner declines to accept, the Commissioner
could be said to “refuse to pay compensation”. Certainly, from an
applicant’s perspective, the applicant has applied for compensation and
the Commissioner has declined (refused) to pay it.
[19] In favour of that construction, section 125 refers to an “applicant”, which is
not defined. Referring back to section 121, an applicant must be a person
who applies for compensation. There is nothing in the terms of section
125 that expressly limits it to applicants who claim within the 90-day
period. A late applicant is an applicant.
[20] Further, section 125 uses the phrase “refuse to pay compensation”
whereas in section 124 the expression “decides not to pay compensation”
appears. Ordinarily, but not always, it is to be expected that when the
legislature uses different expressions this will point to an intention that the
expressions have different meanings. Although not determinative, this
favours the Applicants’ construction, that is, that section 125 is not limited
to decisions under section 124 “not to pay compensation”.
[21] Ms Riedel, who appeared for the Applicants, noted that headings to a
section of an Act form part of the section.6 The heading to section 125 –
“Review of a decision to pay compensation” – is misleading or at least
incomplete, since the section is about decisions to refuse to pay
compensation or the amount of compensation. In referring to a “decision”
it provides some little support for the Commissioner’s construction based
on the sequential reading of the provisions, but is otherwise unhelpful.
Purpose
[22] An interpretation of a provision that will best achieve the purpose of an Act
is to be preferred to any other interpretation.7
[23] In that regard, Ms Riedel pointed to sections 3, 4 and 5 of the Disaster
Management Act, which set out respectively the main objects of the Act,
how the objects are to be primarily achieved and guiding principles
according to which the Act is to be administered.
[24] Ms Riedel particularly noted that:
(1) The main objects include to “help communities . . . effectively
respond to, or recover from, a disaster or an emergency situation”.8
6 Acts Interpretation Act 1954 (Queensland) (“Acts Interpretation Act”), s 35C(1).
7 Acts Interpretation Act, s 14A.
8 Section 3(a)(iii).
-- 6 of 13 --
7
The cognate expression “recovering from a disaster” is defined to
include “providing relief measures to assist persons affected by the
disaster who do not have the resources to provide for their own
financial and economic wellbeing”;9
(2) How the objects are to be primarily achieved includes making
provision about “ensuring communities receive appropriate
information about preparing for, responding to and recovering from a
disaster”;10 and
(3) The guiding principles include that disaster management should be
planned across four phases, the third and fourth of which respectively
include taking appropriate measures “to respond to an event,
including action taken and measures planned in anticipation of,
during, and immediately after an event to ensure that its effects are
minimised and that persons affected by the event are given
immediate relief and support”11 and appropriate measures “to recover
from an event, including action taken to support disaster-affected
communities in the reconstruction of infrastructure, the restoration of
emotional, social, economic and physical wellbeing . . .”12
[25] I do not, with respect, find reference to those objects and how they are to
be achieved, or the guiding principles, particularly helpful in construing
section 125. Neither construction would be inconsistent with these
provisions. The nature of the review available for compensation is
considerably removed from these factors. The most that could be said is
that the Applicants’ construction is more favourable to those recovering
from disasters.
Legislative history
[26] The Tribunal’s jurisdiction in compensation matters under the Disaster
Management Act was introduced by an amendment to the Act contained
in the Queensland Civil and Administrative Tribunal (Jurisdictional
Provisions) Amendment Act 2009 (Queensland).13
[27] Before the amendment, subdivision 3 included the following provisions:
125 Who may appeal
An applicant for the payment of compensation under this division who is
dissatisfied with the chief executive’s decision to refuse to pay compensation or
about the amount of compensation may appeal against the decision.
126 Starting an appeal
9 Schedule, “recovering from a disaster”.
10 Section 4(c).
11 Section 4A(a)(iii).
12 Section 4A(a)(iv).
13 Queensland Civil and Administrative Tribunal (Jurisdictional Provisions) Amendment
Act 2009 (Queensland), s 99 – s 101.
-- 7 of 13 --
8
(1) An appeal may be started at–
(a) the Magistrates Court nearest the place where the person lives or
carries on business; or
(b) a Magistrates Court at Brisbane.
(2) The notice of appeal . . . must be filed with the registrar of the court within 28
days after-
(a) if the person is given notice of the decision under section 124– the
day the person is given the notice; or
(b) if paragraph (a) does not apply– the day the person otherwise
becomes aware of the decision.
(3) . . .
[28] Ms Riedel submitted that these provisions allowed for an appeal to the
Magistrates Court in respect of both a decision on the application for
compensation and a decision not to accept a late application.
[29] I understood this submission to be made on the basis that a decision not
to accept a late application would be covered by s 126(2)(b) – and
therefore must have been covered by the then section 125 – because
such decisions were not covered by the section 124 requirement to give a
notice of a decision. Since section 125 in both its former and current form
adopted the phrase “refuse to pay compensation”, it would follow, on this
view, that the current provision extends to a decision not to accept a late
application.
[30] The difficulty with this submission is that the then section 126 was itself
susceptible to more than one interpretation. Contrary to Ms Riedel’s
submission that s 126(2)(b) covered cases where no notice is required, Mr
Woodford submitted that it only applied where notice of a decision on an
accepted application, although required by section 124, was not in fact
given, but the person “otherwise becomes aware of the decision”.
[31] Neither counsel identified any decision or material that would cast light on
the construction of the former section 126.
[32] In the end, I have drawn little assistance from the legislative history. The
key provision – section 125 – is relevantly in the same terms in its current
and former forms.
Extrinsic materials
[33] Section 125 being ambiguous, as I accept, Ms Riedel submitted, that I
may have regard to extrinsic materials;14 in particular, the Explanatory
14 Acts Interpretation Act, s 14B.
-- 8 of 13 --
9
Notes to the Queensland Civil and Administrative Tribunal (Jurisdictional
Provisions) Amendment Bill 2009.
[34] Clauses 99 to 101 of the Bill dealt with the transfer of jurisdiction from the
Magistrates Court to the Tribunal. Unfortunately, the paragraphs in the
Explanatory Notes referring to those clauses are unhelpful, as they merely
restate, in virtually identical terms and without elaboration, the wording in
the clauses of the Bill. The Explanatory Notes to the relevant clauses of
Disaster Management Bill 2003 take a similarly unhelpful form.
[35] Ms Riedel particularly drew attention to the statement in the Explanatory
Notes to the Queensland Civil and Administrative Tribunal (Jurisdictional
Provisions) Amendment Bill 2009 suggesting that the Bill sought to
achieve “increased access for the community through a single point of
entry.”15 However, an objective stated at that level of generality, and
relating to the Bill as a whole, is of limited assistance in construing a
particular provision, especially one that for relevant purposes essentially
reproduces the terms of a former provision.16
A remedial provision?
[36] Ms Riedel submitted that section 125, being remedial in nature, should be
given a liberal and beneficial construction, citing the recent decision of the
Full Federal Court in Dyankov v Minister for Immigration and Border
Protection17 for the proposition that “a provision dealing with jurisdiction is
plainly a remedial provision”.
[37] However, the paragraph of the judgment said to contain that proposition is
in fact a recitation of the applicant’s submissions rather than a statement
by the Court.18 The Court in referring to this submission stated “[w]e
consider the contextual considerations relating to the purpose of the
provisions and the structure of the scheme to provide a more persuasive
indication of the legislative intent” in that case.19
[38] The High Court has stated that it is “quite inappropriate to read provisions
conferring jurisdiction or granting powers to a court by making implications
or imposing limitations which are not found in the express words”.20 But
this is not a case where the Commissioner’s construction would involve
reading down the otherwise beneficial meaning of a provision.
[39] Even if the provision for compensation itself is properly characterised as
remedial, I do not consider that any principle of beneficial construction
15 Explanatory Notes to the Queensland Civil and Administrative Tribunal (Jurisdictional
Provisions) Amendment Bill 2009, 5.
16 As I have not found the Explanatory Notes to either provision to be potentially helpful, I
have not addressed in detail the matters in s 14B(2) of the Acts Interpretation Act.
17 [2017] FCAFC 81.
18 Ibid, [37].
19 Ibid, [57].
20 The Owners of the Ship “Shin Kobe Maru” v Empire Shipping Company Inc (1994) 181
CLR 404, 421.
-- 9 of 13 --
10
necessarily extends to provisions conferring jurisdiction to review
compensation decisions. Such provisions involve a legislative choice as to
the form and venue for review of decisions. While the provisions plainly
involve a remedy for applicants who consider they have been unjustly
treated, I doubt that the legislature’s choice of one form and venue for a
remedy over another has a remedial dimension that would attract the
principles applying to construction of remedial legislation.
Conclusion on the jurisdiction issue
[40] The Commissioner’s construction has at its heart the proposition that a
decision to refuse to pay compensation may only be made in respect of
an “accepted application”.
[41] The only provision in which the concept of an “accepted decision” appears
is section 123. Despite its heading “Deciding application”, the only work
of section 123 is to deem the chief executive to have “refused to pay
compensation” if an accepted application is not decided within 60 days.
[42] If the Commissioner is tardy in deciding an accepted application, deemed
decision under section 123 to refuse to pay compensation will enliven
review rights under section 125. Otherwise, section 123 has no work to do
in relation to the jurisdiction of the Tribunal.
[43] Elsewhere in subdivision 2, where these provisions appear under the
heading “Application and decision about compensation”, no distinction
is drawn between accepted applications and other applications. The
provisions simply refer to the “applicant” and the “application”. Other than
in accordance with section 123, there is no reason to limit those
expressions to accepted applications.
[44] The Commissioner’s construction would have the result that the only
avenue for an applicant wishing to challenge the Commissioner’s decision
not to accept a late application would be an application to the Supreme
Court for judicial review on the basis of legal error. Merits review of that
decision would not be available.
[45] Assuming success for the applicant in that litigation, but that the
Commissioner then, on considering the application, decided not to pay
compensation, an applicant seeking review of that decision would have to
commence another proceeding in the Tribunal.
[46] The improbability that the legislature intended to create this inconvenient,
costly and time-consuming, bifurcated process favours the Applicants’
construction.21
[47] Further, the Commissioner’s construction of section 125 would be
incongruous with other provisions in subdivision 3. If the view that
21 CIC Insurance Ltd v Bankstown Football Club Ltd (1997) 187 CLR 384, 408.
-- 10 of 13 --
11
“application” and “applicant” in section 124 are limited to accepted
applications and applicants whose applications are accepted – and that is
the link between section 123 and 125 required to take a similar view of
section 125 – an incongruity in the notice provisions would apply. The
Commissioner would be required to notify applicants whose applications
are accepted of the outcome of their application, but not required to notify
applications whose applications are not accepted.
[48] Against that, the Applicants’ construction has the incongruity that section
123 provides a mechanism for enlivening appeal rights if the
Commissioner is tardy in deciding an accepted application but not for
tardiness in deciding whether to accept a late application.
[49] Approaching the section in a practical way having regard to subdivision
3’s evident object of providing a review avenue for applicants who are
refused the compensation they seek, I consider that section 125 is broad
enough to bear the construction that provides for external review by the
Tribunal whether a late applicant is denied compensation because the
Commissioner does not accept the application or because the
Commissioner, having accepted the application, decides not to pay
compensation. The practical effect of either decision is a refusal by the
Commissioner to pay compensation.22
[50] Section 125 is concerned with the result – refusal to pay compensation or
the amount of the compensation. There is nothing is section 125 directing
attention to the process by which the refusal to pay, or the amount of
compensation, was arrived at. That a refusal to pay arises not because
the Commissioner considers the application and “decides not to pay
compensation” as section 124 contemplates, but because the
Commissioner does not accept and therefore does not consider the
application, does not change the character of the outcome.
[51] On balance, having concluded that section 125 is reasonably capable of
bearing the broader construction, and having particular regard to the
improbability that legislature intended that applicants aggrieved by a
decision of the Commissioner would be forced to make separate
applications to the Supreme Court and to this Tribunal, I prefer the
applicants’ construction.
[52] I conclude that the Tribunal has jurisdiction to decide this matter.
Costs
[53] Under section 100 of the Queensland Civil and Administrative Tribunal Act
2009 (Queensland) (“QCAT Act”), the starting point is that each party
bears their own costs. However, the Tribunal may make an order
22 This practical approach has some parallels with the approach of the Tribunal in another
context in Murphy v Queensland Building and Construction Commission [2017] QCAT
164, in which the Tribunal held that a decision to withdraw a direction to remedy a
defect was a decision not to issue a direction to rectify.
-- 11 of 13 --
12
requiring a party to pay all or a stated part of the costs of another party if
the interests of justice require it to do so s 102(1).
[54] In doing so, the Tribunal may have regard to a number of factors listed in
s 102(3). Considering each of those factors in turn:
(1) s 102(3)(a) – there is nothing in the conduct of the Commissioner that
could be said to be “acting in a way that unnecessarily
disadvantages” the Applicants; Ms Riedel did not suggest otherwise;
(2) s 102(3)(b) – the strike out application raised a difficult statutory
construction issue. There is nothing otherwise in the “nature and
complexity” of the dispute that warrants a costs order;
(3) s 102(3)(c) – in relation to “the relative strengths of the claims made
by each party to the proceeding”, I consider the issue raised to be
finely balanced;
(4) s 102(3)(d) – whether the Applicants “were afforded natural justice”
or “genuinely attempted to enable and help” the Commissioner to
make the decision do not arise in this case.
(5) s 102(3)(e) – Ms Riedel argued that the Applicants were in difficult
financial circumstances. I do not consider that this factor, even if it
could be established by appropriate evidence, is sufficient in itself to
warrant a costs order when balanced against the factor discussed at
paragraphs 55 and 56 below.
(6) s 102(3)(f) – “anything else the tribunal considers relevant”, which is
discussed further below.
[55] The Commissioner’s application raised a real and significant issue for
determination, which it was not inappropriate for the Commissioner to
raise at an early stage in the proceeding. Indeed, it might be said that,
having regard to the Commissioner’s duty under section 21 of the QCAT
Act to help the Tribunal in making its decision, the Commissioner was
duty-bound to raise the issue.
[56] Further, dealing with the matter by a separate application was an efficient
and appropriate way to proceed. The alternative of leaving the issue for
determination at the hearing of the application for review would have run
the risk of wasted time and expense both for the parties in preparing for
the hearing, and for the Tribunal, if the Tribunal had concluded that there
is no jurisdiction to decide the application for review.
[57] Ms Riedel also argued that I should take into account that the underlying
issue of compensation had been agitated by the Applicants for some
years since the events said to give rise to the entitlement to compensation
which occurred in 2011. The application for review by this Tribunal was
made on 31 January 2017. Any earlier agitation was not at this Tribunal. I
do not consider that to be relevant to the claim for costs.
-- 12 of 13 --
13
[58] I am not persuaded that the interests of justice require the Tribunal to
make an order for costs against the Commissioner.
Concluding remarks
[59] The appropriate orders are that the strike out application be dismissed
and that each party bears their own costs relating to that application.
[60] I record my appreciation of the parties’ comprehensive written
submissions and the helpful oral submissions of both counsel.
-- 13 of 13 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2017/263