Body Corporate for Lakes Villas v M & A Ross Pty Ltd [2017] QCAT 277
38206_170008_088.dot
CITATION: Body Corporate for Lakes Villas CTS 31637 v
M & A Ross Pty Ltd [2017] QCAT 277
PARTIES: Body Corporate for Lakes Villas CTS 31637
(Applicant)
v
M & A Ross Pty Ltd
(Respondent)
APPLICATION NUMBER: BDL205-16
MATTER TYPE: Building matters
HEARING DATE: 22 June 2017
HEARD AT: Townsville
DECISION OF: Member Carey
DELIVERED ON: 11 July 2017
DELIVERED AT: Townsville
ORDERS MADE: 1. The Application is dismissed.
2. No order as to costs.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING
AND RELATED CONTRACTS –
PERFORMANCE OF WORK – GENERAL –
where domestic building dispute completed –
where dispute arose as to rectification of defects
– where defective application of sealant was
alleged – whether applicants were aware of the
use of the sealant
Briginshaw v Briginshaw (1938) 60 CLR 336;
[1938] HCA 34
TNT Management Pty Ltd v Brooks (1979) 53
ALJR 267
APPEARANCES:
APPLICANT: Body Corporate represented by Ms Vicki
Bullimore as agent for the Body Corporate
RESPONDENT: Mr Andrew Ross and Ms Megan Ross
REASONS FOR DECISION
-- 1 of 4 --
2
[1] The Applicant engaged the Respondent to reseal approximately 2,300
square metres of driveway at the Lakes in Townsville in 2014.
[2] The Applicant complains that the work was poorly executed and requires
rectification.
[3] The Applicant also complained to the Queensland Building and
Construction Commission (“QBCC”), a representative of which conducted
an inspection and on 18 July 2016. The QBCC report (Exhibit 2 in the
proceedings) reveals that Mr Kevin Cameron deemed this to be a category
2 defect but did not order rectification of the defect as the time limit under
QBCC policies for so doing had expired. That inspection was carried out
almost 20 months after the work was completed.
[4] The work was completed on 30 October 2014. The Applicant notified the
Respondent of its opinion that there were defects in the work on 26 October
2015 and a complaint was made to QBCC on 18 July 2016.
[5] The Applicant requests an order that the Respondent rectify the work at its
cost.
[6] The Applicant and the Respondent were unrepresented at the hearing.
Given that, and the provisions of section 95 of the Queensland Civil and
Administrative Tribunal Act 2009 (Qld) (the Act), I have given appropriate
latitude to the parties as to how evidence was presented to the Tribunal and
the matters to which I have had regard. In particular, both parties provided
statements of evidence in accordance with Tribunal directions. They were
statements from people said to be experts. None of the experts was called
to give oral evidence at the hearing. It may have assisted the Tribunal
further had these witnesses been called.
[7] Notwithstanding non-compliance with the practice direction in respect of a
joint expert’s report which is required to be submitted after an expert’s
conclave (which was held) I have allowed into evidence the statements of
Martin Brook, Alan Church, Chris Murphy and Carl Grimmer. Mr Grimmer
was not held out as an expert. He attended the hearing and gave oral
evidence in addition to his statement.
[8] His evidence was to the effect that he was the person who applied the
sealant and that he applied it correctly. Mr Grimmer was not cross
examined by the Applicant. I accept his evidence.
[9] The experts could not agree. The experts for the Applicant stated the work
was defective. Unsurprisingly, the experts for the Respondent stated that it
was not.
[10] The product statement which the Respondent says it provided to the
Applicant with its quote to perform the works states that the sealant needs
to be reapplied every 12 months.
-- 2 of 4 --
3
[11] The Applicant denied receiving a copy of this product statement. The
Respondent states that it was given to the Applicant. The Applicant states
that they would not have proceeded with the quote for use of that product
had they been aware of the requirement for re-application every 12 months.
[12] The Applicant has the burden of proving its claim to the civil standard on
the balance of probability. The civil standard is not applied as a
mathematical or scientific exercise but as a reasonable search for the truth
in the circumstances of each particular case.1 As Dixon J (as His Honour
then was) explained in Briginshaw v Briginshaw:2
... when the law requires the proof of any fact, the Tribunal must feel an
actual persuasion of its occurrence or existence before it can be found...
reasonable satisfaction is not state of mind it is obtained or established
independently of the nature and consequence of the fact or facts to be
proved.
It is also important to keep in mind that in cases like these the standard test
for weighing and applying the evidence is not one of mathematical or
scientific exercise, but based on a reasonable search for the truth in the
circumstances of each particular case.3
[13] Section 28 of the Act requires the Tribunal to act fairly and according to the
substantial merits of the case whilst observing the rules of natural justice
and informing itself in any way that it considers appropriate.
[14] In accordance with sections 28(4) and 95 of the Act I have admitted the
statements into evidence notwithstanding that only one witness was
available to give oral evidence and notwithstanding that the practice
direction in relation to joint experts report had not been complied with.
[15] On balance, and taking into consideration the submissions made by the
Applicant and the Respondent, I find that the Applicant was given a copy of
the product statement by Mr Andrew Ross.
[16] I find that it would not be reasonable in the circumstances to direct the
Respondent to reapply the coating at its expense, for the following reasons:
a) The length of time that has elapsed from application, to notification of
defects, to complaint to the QBCC to the date of this hearing. Some 2
½ years has passed since the product was allegedly defectively
applied. It would not be reasonable in the circumstances for the
Respondent to be put to the expense of repair now, especially
considering that the product statement requires re-application every
12 months.
b) The QBCC declined to direct rectification on the basis of the length of
time that had elapsed between completion of the work and their
1 TNT Management Pty Ltd v Brooks (1979) 53 ALJR 267.
2 (1938) 60 CLR 336, 361-2.
3 TNT Management Pty Ltd v Brooks (1979) 53 ALJR 267.
-- 3 of 4 --
4
inspection. I do not believe it would be appropriate for the tribunal to
do so now.
[17] For those reasons the application is dismissed. There will be no order as to
costs.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2017/277