Dyer v Spence [2017] QCAT 211
CITATION: Dyer v Spence [2017] QCAT 211
PARTIES: Rowan John Dyer
(Applicant)
v
Robyn Spence
(Respondent)
APPLICATION NUMBER: BDL285-14
MATTER TYPE: Building matters
HEARING DATE: 9 June and 8 September 2016
Written submissions filed 22 September 2016
HEARD AT: Brisbane
DECISION OF: Member Deane
DELIVERED ON: 19 June 2017
DELIVERED AT: Brisbane
ORDERS MADE: 1. Rowan John Dyer is to pay Robyn Spence
the sum of $138,826.18 by 4:00pm on 31
July 2017.
2. Rowan John Dyer is to pay Robyn Spence
interest at the rate of 10% per annum on
the sum of $138,826.18 on and from 1
August 2017 until and including the day
the sum is paid.
3. Any application for costs is to be made by
filing in the Tribunal one (1) copy and
providing to the other party one (1) copy
of any submissions and evidence as to
costs by 4:00pm 21 July 2017.
4. If an application as to costs is made in
accordance with order 3 then:
a) the other party is to file in the
Tribunal one (1) copy and provide to
the party making the application for
costs one (1) copy of any
submissions and evidence as to
costs in response by 4:00pm 4
August 2017.
b) the application as to costs shall be
determined on the papers and
-- 1 of 22 --
2
without an oral hearing unless a
party requests an oral hearing, not
before 4:00pm 4 August 2017.
5. If an application as to costs is not made in
accordance with order 3 then there shall
be no order as to costs in this proceeding.
6. The Registry is to return Rowan John
Dyer’s original diary to him after the
appeal period expires.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING
AND RELATED CONTRACTS –
PERFORMANCE OF WORK – REMEDIES FOR
BREACH OF CONTRACT – DAMAGES –
MEASURE OF – Domestic Building Dispute –
builder’s failure to comply with statutory
requirements as to variations – claim for refund
of all moneys paid – voluntary payments –
whether builder prohibited from retaining sums
paid – whether builder or owner entitled to
terminate – where defective work – reasonable
costs of rectification – whether owner entitled to
liquidated damages
Domestic Building Contracts Act 2000 (Qld),
s 18, s 84
Queensland Building and Construction
Commission Act 1991 (Qld), s 42
Queensland Building and Construction
Commission and Other Legislation Amendment
Act 2014 (Qld), s 62
Queensland Building and Construction
Commission Regulation 2003 (Qld), s 34B
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 28, s 92, s 93
Bartlett v Contrast Constructions Pty Ltd [2016]
QCA 119
Bellgrove v Eldridge (1954) 90 CLR 613
Chelbrooke Homes Pty Ltd v Russell & Anor
[2011] QCAT 278
Coshott v Fewings Joinery Pty Ltd [1996]
NSWSC 270
Mt Cotton Constructions Pty Ltd v Greer [2017]
QCAT 11
QLine Interiors Pty Ltd v Jezer Construction
Group Pty Ltd & Ors [2002] QSC 088
Ruxley Electronics & Constructions Ltd v Forsyth
[1996] AC 344
-- 2 of 22 --
3
Salam v Henley Properties (Qld) Pty Ltd [2015]
QCATA 118
Shevill v Builders Licensing Board (1982) 149
CLR 620
William George Carlsen t/as W & E Carlsen
Builders v Tresidder [2015] QCAT 260
Willshee v Westcourt Ltd [2009] WASCA 87
APPEARANCES:
APPLICANT: No appearance by Rowan John Dyer
RESPONDENT: Robyn Spence
REPRESENTATIVES:
APPLICANT: No representative for Rowan John Dyer
RESPONDENT: AC Harding of Counsel instructed by Garland
Waddington, Solicitors
REASONS FOR DECISION
Mr Dyer, a licensed builder, entered into a contract to perform building work
for Ms Spence to extend and renovate her home. Mr Dyer commenced
proceedings claiming the sum of $30,146 in respect of moneys owing for
work performed under the contract and in respect of variations and claimed
interest and costs. Ms Spence disputes that moneys are owing to Mr Dyer.
She counterclaims for damages for defective work, liquidated damages and
for the refund of moneys paid in respect of undocumented variation works.
The final hearing of this matter was set down for two days commencing on
9 June 2016. At the commencement of the hearing, Mr Dyer requested,
and I permitted him, an adjournment to allow him to seek advice. The
adjourned hearing was set down for two days commencing on 8 September
2016.
Prior to the adjourned hearing Mr Dyer filed a Notice of Withdrawal of his
claim. The hearing on 8 September 2016 proceeded on the basis that I was
to determine Ms Spence’s Counter-application. Mr Dyer did not appear.
Having regard to the Tribunal’s file, I was satisfied that the Notice of Hearing
was sent to Mr Dyer on 30 August 2016.1 I was also satisfied that through
that notice and the directions made on 22 July 20162 he was aware that the
hearing was to proceed in relation to the Counter-application even though
he had chosen not to continue with his claim. In the circumstances, I
decided to hear and decide the Counter-application in his absence.3 Mr
1 Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act), s 92.
2 Providing an opportunity to Mr Dyer to file a Response to the Counter-application and
listing the Counter-application for hearing.
3 QCAT Act, s 93.
-- 3 of 22 --
4
Dyer did not file a Response to the Counter-application and did not file any
statements of evidence or independent expert reports, which responded to
the specific claims made by Ms Spence or the expert evidence submitted
by Ms Spence. Naturally, at least some of the issues raised by the Counter-
application relate to matters raised by Mr Dyer’s Application.
Essentially Mr Dyer’s position was that:
a) He performed both the work under the contract and the variation work
requested by Ms Spence to an acceptable standard;
b) Ms Spence, who was well versed in building matters, considered the
work acceptable during the course of the contract and indicated
acceptance of the work by making payments;
c) There were many prime cost items so that where the actual cost was
more, he was entitled to an adjustment in the contract price in his
favour;
d) Ms Spence was not entitled to withhold the enclosed stage progress
payment on the grounds that certification of the frame stage had not
been obtained;
e) He validly terminated the contract on 5 November 2014, prior to
reaching practical completion, relying upon a Notice to Remedy
Breach given by him on 21 October 2014 pursuant to clause 27.2 of
the General Conditions;
f) He should be paid the amount he claimed.
Ms Spence denied that Mr Dyer was entitled to terminate. By letter dated
17 February 2016, she accepted the purported termination as a repudiation
of the contract and purported to terminate the contract. 4
Ms Spence’s Amended Response and Counter-application filed 18
November 2015 claimed:
a) Liquidated damages;
b) Refund of moneys paid under the terms of the contract when not yet
owing;
c) Refund of moneys overpaid for variation work;
d) Refund of moneys paid in respect of materials not used for or
incorporated into the works or the variation works;
e) The costs to rectify defective work and defective variation work;
f) An accounting for and details of calculation of progress payments;
g) Refund of moneys paid for variation work pending approval pursuant
to section 84 of the Domestic Building Contracts Act 2000 (Qld) (DBC
Act);
h) Costs.
4 Exhibit 2, RS34.
-- 4 of 22 --
5
After the oral hearing, written submissions were filed on 22 September
2016, a copy of which Ms Spence’s solicitors advised were sent to Mr Dyer.
In those submissions, Ms Spence claims that the evidence supports her
claim for:
a) Damages for breach of contract quantifiable in the sum of $22,321.16
but to be assessed globally in the sum of $30,000;
b) Refund of amounts paid for variations in the sum of $63,270;
c) Liquidated damages in the sum of $27,250;
d) Interest on amounts payable pursuant to section 34B of the
Queensland Building and Construction Commission Regulation 2003
(Qld) at the rate of 10%;
e) Costs, with additional submissions to be made after the primary
determination of the issues.
It was common ground that a written building contract dated 19 February
2014 for work described as ‘extension/renovation to existing dwelling’ was
entered into by Mr Dyer and Ms Spence.5 The contract provided that:
a) The contract price was for $86,063 (incl GST).
b) The works were to reach practical completion within 150 days after
commencement subject to clause 16, which set out the builder’s rights
to claim extensions of time.
c) Late completion damages were payable at $50 per day.
d) Progress payment claims were to be made at defined stages as
follows:
i) ‘Demolition works’ $10,7306
ii) ‘Footings poured’ $ 8,0007
iii) ‘Blocks & Slab’ $16,833.258
iv) ‘Frame’ $16,833.259
v) ‘Inclosed’(sic) $16,833.2510
vi) ‘Completion’ $16,833.2511
e) ‘Frame stage’ was defined as the stage when a building’s frame is
finished.12
5 Exhibit 2, RS 4.
6 Mr Dyer admits this amount was paid prior to his termination.
7 Mr Dyer admits this amount was paid prior to his termination.
8 Mr Dyer admits this amount was paid prior to his termination.
9 Mr Dyer admits this amount was paid prior to his termination.
10 Mr Dyer claimed this amount prior to his termination but Ms Spence did not pay it.
11 Mr Dyer had not claimed this amount prior to his termination.
12 Schedule 2.
-- 5 of 22 --
6
f) The contractor was to complete the works in accordance with the
contract as set out in the contract documents, which included the
general conditions, special conditions, the specification and plans.13
Prior to filing the Notice of Withdrawal, Mr Dyer set out certain matters in
his Application and in his statements of evidence.14 He did not make himself
available during the hearing to give evidence under oath or affirmation as
to the truth of the matters in the Application and his statements and to be
questioned by Ms Spence’s Counsel or by me.
As set out earlier in these reasons, Mr Dyer did not file a Response to the
Counter-application. Nor did he file any statements of evidence by himself
or any independent expert responding to the specific allegations of defective
work and the costs of rectification.
Whilst the Tribunal is not bound by the strict rules of evidence, it must
observe the rules of natural justice.15
Ms Spence relied upon statements of evidence by Mr Carey, a quantity
surveyor,16 Mr Witt, a building consultant17 and herself.18 Each witness was
available to give oral evidence and to be questioned by me and by Mr Dyer
if he had appeared at the hearing.
In the circumstances, where there is a conflict in the evidence between Mr
Dyer’s evidence and the evidence of Ms Spence, I prefer the evidence of
Ms Spence.
In particular, I find that:
a) Ms Spence had limited knowledge of building matters at the time of the
entering into of the contract and during its performance, contrary to Mr
Dyer’s assertions. I accept Ms Spence gained significant building
knowledge during the course of these proceedings and that in the
course of preparing for it she compiled a number of comprehensive
schedules, which demonstrated the significant extent to which Mr Dyer
had departed from the work required by the contract;
b) During the works Ms Spence complained to Mr Dyer on a regular basis
as to the progress of and quality of the works, contrary to Mr Dyer’s
assertions that she considered the work acceptable;19
c) Mr Dyer provided an oral quote of $188,000, which Ms Spence did not
accept. She asked Mr Dyer to requote the work but to exclude the
work above the garage on the first floor (sheet 3 of the approved plans)
and the second floor (sheet 4 of the approved plans) on the basis that
this work could be done at a later date. I accept that Ms Spence
13 Exhibit 2, RS 4, Clause 1.1, Clause 37.1, Schedule1 Item 12.
14 Filed 7 May 2015 and 9 February 2016.
15 QCAT Act, s28.
16 Exhibit 3.
17 Exhibit 4 and Exhibit 5, a bundle of photographs.
18 Exhibit 2 and Exhibit 1, which replaced some attachments to Exhibit 2.
19 Exhibit 2 at [266].
-- 6 of 22 --
7
stressed to Mr Dyer that it was very important that the structural
elements of the works had to be sufficient to support the extension
work, which would be done at a later time;
d) Mr Dyer provided an oral quote of $88,063 for this work. Mr Dyer
subsequently prepared the written contract, which stated the contract
sum was $86,063 (incl GST) and requested Ms Spence to pay $2,000
in respect of the preparation of the quotations;
e) Ms Spence signed the written contract and paid Mr Dyer $2,000 on or
about 19 February 2014. In these circumstances, I find that the
payment of the $2,000 should not be regarded as a part payment of
the contract price of $86,063;
f) The contract20 was contained in:
i) A HIA Alteration, Addition and Renovation Contract comprising
Schedules 1 – 5 (pages i – ix) and General Conditions (pages 1
– 39);
ii) 9 pages of plans titled ‘proposed extension’ being the redrawn
approved plans, which Ms Spence had drawn in September 2013
to depict the works completed by her husband together with
additional work;21
iii) the original 11 pages of engineering drawings drawn by STA
Consulting Engineers (date of issue 15 October 2010);
iv) the original 9 page Foundation Design Report dated 20 July 2010.
g) At the time Mr Dyer and Ms Spence signed the contract they had
agreed that the works would not include the underpinning of the slab
as shown on page 2 of the Foundation Design Report but instead the
demolition of the old beach house would include its footings and slab
and therefore new footings and slab were to be constructed. This
change was made at Mr Dyer’s request with Ms Spence’s agreement
and was subsequently recorded in the further Foundation Design
Report issued 17 March 2014. I, therefore, find that the contract price
was not based upon the reuse of the existing footings and that there
was no variation of the works in respect of the footings, contrary to Mr
Dyer’s assertions;22
h) Mr Dyer had discussions with the engineer, which lead to revised
drawings being issued. Mr Dyer excluded Ms Spence from these
discussions. The engineer did not inform Ms Spence about the
discussions and therefore Ms Spence did not approve variations
depicted in the Foundation Design Report issued on 17 March 2014
(except to the extent referred to above) or revised drawings issued on
26 March 2014;
20 Exhibit 2, RS4.
21 The works to be performed did not include the extension depicted on sheet 3 and sheet
4 of the plans.
22 Exhibit 2, RS5.
-- 7 of 22 --
8
i) There was only one Prime Cost item in the contract;23
j) Progress claims:
i) were to be made upon completion of each stage;24
ii) were to state the amount claimed for the stage and the amount of
any addition or deduction for variations or due to a prime cost
item;25
k) The payment of progress claims, other than the final claim, are on
account only so that payment by Ms Spence of amounts demanded by
Mr Dyer did not amount to acceptance of the work;26
l) Invoice no 47227 in respect of the demolition stage progress claim was
not delivered to Ms Spence until Mr Dyer provided a copy in these
proceedings and therefore Ms Spence was denied the opportunity to
question Mr Dyer about the notation about finalising Prime Cost
allocations in respect of excess refuse and excavation given that there
was only one Prime Cost item in the contract;
m) Mr Dyer was not entitled to or required to adjust the contract sum as if
many items of work under the contract were Prime Cost items. In
particular, Mr Dyer issued invoices where he claimed there were prime
cost allowances, which required adjusting given the actual cost alleged
to have been incurred. I also accept Ms Spence’s evidence that copies
of supporting invoices to support such claimed adjustments were not
provided;
n) Amounts claimed in Invoice no 475, Prime Cost adjustments, were not
validly claimed. For the same reason the credit adjustment in Invoice
no 477 was not required to be given;
o) Mr Dyer demanded and Ms Spence made a cash payment of $2,500
in respect of asbestos removal. There is no sufficient evidence before
me to suggest that this was a valid variation. In those circumstances,
such work ought to have formed part of the demolition stage claim
work. Ms Spence paid the demolition stage claim in full in addition to
this sum;
p) In or about mid-March 2014 Ms Spence and Mr Dyer agreed to vary
the work required to be performed to add work on level 1 and level 2
of the dwelling directly above the existing workshop on the ground floor
at the request of Ms Spence. The additional work was to add on level
1 a bathroom and a small deck and on level 2 a bathroom, a small
deck and sun room (the Variation Works);
q) The Variation Works were agreed to be charged at cost for materials
upon production of invoices and at $50 per hour for Mr Dyer and $40
per hour for his employees upon production of timesheets. At that
23 Exhibit 2, RS 4, Schedule 4 sets out one Prime Cost item, Windows and front door in
the sum of $4,000.
24 Exhibit 2, RS 4, Clause 4.3.
25 Exhibit 2, RS 4, Clause 4.4.
26 Exhibit 2, RS 4, Clause 4.8.
27 Exhibit 2, RS9.
-- 8 of 22 --
9
time, Mr Dyer indicated the likely costs of the Variation Works would
be in the order of $20,000. The Variation Works were to be completed
as Mr Dyer completed the work under the contract;
r) The Variation Works requested by Ms Spence were not so urgent that
it was not reasonably practicable for Mr Dyer to record them in
accordance with the terms of the contract and the DBC Act before
carrying out the work;
s) Mr Dyer demanded payments without providing documentation
including in respect of progress claims contrary to the terms of the
contract and when Ms Spence attempted to resist payment Mr Dyer
wrongly threatened to suspend work;
t) On 2 October 2014 Mr Dyer delivered numerous invoices for the first
time bearing different dates, including invoice no 486 dated 1 July 2014
in respect of the frame stage, which indicated that $20,000, which had
been paid had been applied to the frame stage claim of $16,833.25
and the balance to ‘extra framing’;
u) As at 1 September 2014 the frame stage was incomplete because the
framing had failed an inspection by STA Consulting Engineers. In
these circumstances, I find that the frame stage was not ‘finished’ as
at 1 July or 1 September because I am satisfied that failing to perform
the work required to achieve certification and obtain a form 16 was not
a minor defect or omission and therefore the right to payment of the
frame stage payment had not arisen;28
v) As at 7 October 2014 the frame stage remained incomplete because
the framing had failed a second inspection by STA Consulting
Engineers. For the reasons outlined above the right to payment of the
frame stage payment had not arisen;29
w) Ms Spence paid to Mr Dyer or at his request the following amounts:
i) $2,000 in cash on 19 February 2014 in respect of the preparation
of the quotations.
ii) $590 on 17 March 2014 in respect of the hire of a skip bin used
in the demolition work. Mr Dyer contends that Ms Spence used
the bin for removal of her own rubbish. I find Ms Spence put two
items of her own in the skip bin and only at the last minute. There
is no evidence before me that the removal of the demolished
materials would have cost less if these items were not placed in
the bin for removal. Mr Dyer was obliged to remove the
demolished materials from site as part of the works under the
contract. This amount ought to have formed part of the demolition
stage payment but was claimed and paid in addition to it.
iii) $2,500 in cash on 21 March 2014 in respect of demolition works
and not in order to secure a discount as alleged by Mr Dyer.
Demolition was not a Prime Cost item under the contract and
28 Exhibit 2, RS18.
29 Exhibit 2, RS19.
-- 9 of 22 --
10
therefore the actual cost was of no concern to Ms Spence. This
amount ought to have formed part of the demolition stage
payment but was claimed and paid in addition to it.
iv) $10, 730 by cheque on 26 March 2014 in respect of the demolition
stage although no written progress claim was provided to her until
after the proceedings commenced and there was no allowed
deduction for the amounts previously paid by Ms Spence in
relation to this stage.
v) $916.55 for BSA Insurance and $162 for Q-Leave premium on 1
April 2014. The contract does not expressly state which party is
to pay these charges. They are not specified as excluded items
in Schedule 3 for which the owner is responsible. I accept Ms
Spence’s evidence that the usual practice is for such fees to be
built into the contract price30 and that Mr Dyer attended to the
payment of the increase in BSA Insurance premium due to the
increased value of the works.31 In these circumstances, I find that
it is more likely than not that the fees were included in the contract
price and Mr Dyer wrongly demanded Ms Spence attend to
payment in addition to the contract price.
vi) $9,757.25 on or about 16 April 2014 in respect of invoices 475
and 477. Having regard to the description of work on invoice 475,
I accept Ms Spence’s evidence that it related to the demolition
stage. Mr Dyer wrongly purported to make adjustments as if work
claimed related to Prime Cost items, when they did not. Having
regard to the description of work on invoice 477, I accept it was
in substance the footings poured stage claim.
vii) $16,833.25 on 30 April 2014 in respect of invoice 478, in respect
of the blocks and slab stage claim.
viii) $2,000 on or about 6 May 2014 in respect of a concrete slab in
the undercroft of the ground floor works, which Ms Spence
accepts was an undocumented variation to the works required
under the contract.
ix) $290 for additional Q-Leave premium on or about 29 May 2014.
For the reasons indicated earlier in these reasons in respect of
the first Q-Leave premium payment, I find that it is more likely
than not that the fees were included in the contract price and Mr
Dyer wrongly demanded Ms Spence attend to payment in
addition to the contract price.
x) $10,000 on 13 June 2014 upon wrongful demand by Mr Dyer and
without any substantiation.
xi) $20,000 on 1 July 2014 upon wrongful demand by Mr Dyer and
without any substantiation. I accept Ms Spence’s evidence that
it is more likely than not that Mr Dyer has applied this amount in
payment of the frame stage claim for $16,833.25 in invoice 486
30 Such evidence is consistent with my experience in this jurisdiction.
31 Exhibit 2, RS12.
-- 10 of 22 --
11
dated 1 July 2014 but received by Ms Spence on or about 2
October 2014.
xii) $20,000 on 25 July 2014 upon wrongful demand by Mr Dyer and
without any substantiation.
xiii) $600 in cash on 12 August 2014, upon demand by Mr Dyer so he
could pay his labourer. There is insufficient evidence to find that
this amount was due to Mr Dyer under a collateral contract or in
respect of any undocumented variations. I find that it is more
likely than not that Mr Dyer wrongly demanded Ms Spence attend
to payment in addition to the contract price.
xiv) $10,000 on 14 August 2014 upon wrongful demand by Mr Dyer
and without any substantiation.
xv) $850 in cash on 29 August 2014, upon demand by Mr Dyer so he
could pay his labourer. There is insufficient evidence to find that
this amount was due to Mr Dyer under a collateral contract or in
respect of any undocumented variations. I find that it is more
likely than not that Mr Dyer wrongly demanded Ms Spence attend
to payment in addition to the contract price.
xvi) $20,000 on 5 September 2014 upon wrongful demand by Mr
Dyer and without any substantiation.
xvii) $1,200 in cash on 12 September 2014, upon demand by Mr Dyer
so he could pay his labourer. There is insufficient evidence to
find that this amount was due to Mr Dyer under a collateral
contract or in respect of any undocumented variations. I find that
it is more likely than not that Mr Dyer wrongly demanded Ms
Spence attend to payment in addition to the contract price.
xviii) $330 on 22 September 2014 upon wrongful demand by Mr Dyer
and without any substantiation.
x) Ms Spence requested and Mr Dyer agreed to carry out work to
construct a mezzanine floor in the back of the garage on the basis of
Mr Dyer’s oral advice that there would be no additional charge for
labour and that the materials would cost in the order of $200. This
work was an undocumented variation to the contract work. Mr Dyer
purported to claim $1,500 for this work in invoice 495 delivered on 2
October 2014 but Ms Spence did not pay this amount.
Where there is a conflict in the evidence between the generic evidence of
Mr Dyer, that he performed the work to an acceptable standard and the
specific evidence of Mr Witt and Mr Carey I prefer the specific evidence of
the independent experts.
In particular, I accept Mr Witt’s evidence that:
a) There were 32 items identified in respect of the ground floor work
which were defective, not in accordance with the contract/plans or
incomplete work of which only item 6.14 could be regarded as
incomplete work.
-- 11 of 22 --
12
b) There were 7 items identified in respect of the first floor work which
were defective, not in accordance with the contract/plans or
incomplete work of which items 7.04 and 7.06 could be regarded as
incomplete work.
c) There were 4 items identified in respect of the second floor work which
were defective, not in accordance with the contract/plans or
incomplete work of which items 8.01 and 8.04 could be regarded as
incomplete work.
d) There were 8 other items identified which were defective, not in
accordance with the contract/plans or incomplete work of which items
9.03 and 9.05 could be regarded as incomplete work.
e) There were 58 items of work not built in accordance with the STA
Consulting Engineering drawings, that the extent of omissions and
variations is significant and has compromised the structural soundness
of the dwelling requiring an engineer to inspect to assess the structural
integrity of the works.32 No such engineering evidence was before me
such that I am not able to make findings in respect of the extent to
which the structural soundness has been compromised.
f) The overall workmanship was below average and not to a standard
expected from a licensed builder;
g) Rectification of substandard work will require significant repairs;
h) All renovated areas of the dwelling are incomplete and require
significant work for finishing.
Mr Dyer did not file any evidence as to the reasonable costs of rectification
either from himself or from an independent expert.
Given the state of Mr Dyer’s evidence and that he was not available to be
questioned at the hearing, I prefer Mr Carey’s evidence and accept his
evidence that:
a) The reasonable costs of rectification of the garage work i.e. the work
under the contract, for items he has quantified, is $24,178.75 (excl
GST).
b) The estimated saving to Mr Dyer from departing from the contract
requirement for external walls to be block work is $12,867(excl GST).
c) The estimated saving to Mr Dyer from departing from the contract
requirement for a deck to the workshop wall ($1,100 excl GST),
balustrading to the deck ($1320 excl GST), a 2400 x 1400 pivot door
($2500 excl GST) and waterproofing to block walls ($930 excl GST)
totals $5,850 (excl GST).
d) The above calculations do not take into account a number of defects,
which would be difficult to rectify short of demolition:
32 Exhibit 4, at [10.04].
-- 12 of 22 --
13
i) Mr Dyer’s change to the external walls does not allow for the
extensions to the upper floors to be built at a later date;
ii) the entry slab is not correct;
iii) the slab to the storage area is at the incorrect height;
iv) the wall to the storage area is missing;
v) the new extensions do not line up with the rest of the house;
vi) the setback at the entrance way is incorrect so that the door
cannot fit;
vii) the windows to the garage are in the wrong place.
e) The estimated costs to rectify the Variation Works is $13,225 (excl
GST).
f) The reasonable value of the Variation Works performed by Mr Dyer is
$31,277 (excl GST).
g) The reasonable value of the variation work to construct the mezzanine
in the garage area is $2382 (excl GST). I accept Mr Carey’s evidence
that the size of the joists used is excessive and therefore the estimate
is high for a storage area particularly when regard is had to Ms
Spence’s evidence that Mr Dyer estimated $200 for this work. Mr
Carey’s report does not separately set out the reasonable value of
another undocumented variation to the ground floor requested by Ms
Spence i.e. concrete slab in the undercroft for which Mr Dyer
demanded and Ms Spence paid $2000. In view of the evidence
regarding the mezzanine and Mr Dyer’s failure to provide evidence as
to the items in the counter-application, I accept the amount of $2382
(excl GST) as the reasonable value of both ground floor variations.
h) The reasonable costs to complete the works under the contract is
$37,202.50 (excl GST).33
Is Ms Spence entitled to recover amounts paid to Mr Dyer for variation
work?
I find that Ms Spence is not entitled to recover amounts paid voluntarily to
Mr Dyer for variations.
As set out earlier in these reasons, Ms Spence and Mr Dyer agreed that Mr
Dyer would perform the Variation Works and two other variations to the
ground floor work.
Ms Spence contends that this work was sought by her within the meaning
of that term in section 84 (2) of the DBC Act. Although the DBC Act has
33 Although Mr Carey’s report refers to this amount as the estimate to ‘finish the garage
and other stage 2 items’ I am satisfied that this amount is separate from his estimate to
finish levels 1 & 2, which is a reference to the Variation Works.
-- 13 of 22 --
14
been repealed, it continues to apply to domestic building contracts entered
into before 1 July 2015.34
The DBC Act limits the right of builders to recover amounts for variations.
The undisputed evidence before me is that Mr Dyer did not reduce
variations to writing as required by clause 19 of the General Conditions of
the contract nor as required by section 79 of the DBC Act.
The Appeal Tribunal has previously accepted that a builder is required to
apply to the Tribunal for an order pursuant to section 84 of the DBC Act
before the Tribunal may approve that an amount is payable.35 Even before
Mr Dyer filed his Notice of Withdrawal, no such application had been made.
Ms Spence contends that in the absence of such an application by Mr Dyer
he is not entitled to retain the benefit of amounts paid in respect of variations
because he is prohibited from recovering an amount for variation work and
that the sums paid for variation work must be repaid. No specific authority
was advanced for this proposition. Ms Spence contends that amounts
totalling $63,270 were paid in respect of variations and that such sum ought
to be repaid. Given the way in which Mr Dyer claimed and Ms Spence paid
amounts there is some doubt as to whether amounts paid were under the
contract, for variations or otherwise.
The Tribunal has recently considered whether homeowners were entitled to
recover moneys paid for variations where no application under section 84
of the DBC Act had been made. In Mt Cotton Constructions Pty Ltd v
Greer36 Member Howe considered whether section 84 of the DBC Act had
a similar prohibitive effect on a builder’s right to payment as section 42 of
the Queensland Building and Construction Commission Act 1991 (Qld)
(QBCC Act), which prohibits an unlicensed builder from receiving
remuneration.37 Member Howe set out at some length the authorities
concerning the construction of section 42 of the QBCC Act and compares
and contrasts the wording in section 84 of the DBC Act.38 I respectfully
agree with that reasoning, that the wording is different39 such that:
there is no clear intention to be derived from the wording of s84(3) and (4)
that the builder’s right to retain payment of monies made to it voluntarily for
variations which fail to comply with the requirements of the Act is intended to
be abrogated so as to entitle the owners to subsequently recover monies so
paid.40
Ms Spence’s evidence is that she felt compelled to pay Mr Dyer. Given the
mirror provisions in the contract and the DBC Act there can be no assertion
that the payments were made under a mistaken belief that there was a legal
obligation to pay, which might arise in respect of payments to an unlicensed
34 Queensland Building and Construction Commission and Other Legislation Amendment
Act 2014 (Qld), s 62.
35 Salam v Henley Properties (Qld) Pty Ltd [2015] QCATA 118.
36 [2017] QCAT 11. I note that the decision is under appeal, including on this point in
APL044-17.
37 Given the submissions are that Mr Dyer is ‘prohibited’ from retaining the amounts paid
for variations I understand that this is the basis for that claim.
38 [2017] QCAT 11, [73] – [90].
39 Ibid, [82].
40 Ibid, [88].
-- 14 of 22 --
15
builder prior to discovering the builder was not licensed. As in the Greer’s
case Ms Spence paid the amounts ‘pursuant to a course of compromise
and conciliation’.41
I find that the payments were made voluntarily and cannot now be
recovered under this ground.
In the alternative, Ms Spence contends orders ought to be made for Mr Dyer
to provide an account of the progress payments claimed and paid by Ms
Spence including an account of the labour performed and the materials
incorporated into the works and the variation work and that her loss is at
least $45,218 calculated as follows:
a) The amount paid to the builder in the sum of $63,270;
b) Less the value of the variation work assessed as $31,277;42
c) Plus the estimated cost to rectify the variation work assessed as
$13,225.43
In view of Mr Dyer’s failure to participate in these proceedings:
a) By withdrawing his Application;
b) Not filing any Response to the Counter-application, which included a
claim for an accounting for and details of calculations of progress
claims;
c) Not filing any evidence in response to Ms Spence’s claims; and
d) Failing to appear at the hearing,
I consider Mr Dyer is unlikely to comply with any directions to him to provide
an account.
As the Tribunal is required to attempt to expedite resolution of
proceedings,44 I assess Ms Spence’s loss below.
Did Ms Spence validly terminate the building contract?
I find that Ms Spence validly terminated the contract by accepting Mr Dyer’s
repudiation of the contract.
Mr Dyer contends that Ms Spence was in breach of the contract and that he
was entitled to terminate the contract.
On or about 29 September 2014 Mr Dyer sought to make the enclosed
stage progress claim in the sum of $16,833.25.45 As stated above, on 2
October 2014 Mr Dyer delivered numerous other invoices.
By email dated 6 October 2014 Ms Spence:
41 Ibid, [89].
42 Exhibit 3, page 2, item 1.
43 Ibid, page 3, item 2 and oral evidence of 15% builders margin on $11,500.
44 QCAT Act, s 28(3).
45 Invoice no 494.
-- 15 of 22 --
16
a) Confirmed that she did not want Mr Dyer to return to site until ‘we have
sorted out what is to be paid to you in respect of your current claims’;
b) Confirmed that the engineer was to inspect the works the following
day;
c) Sought invoices and receipts in respect of the materials claimed and
timesheets in respect of the labour claimed;
d) Disputed that the enclosed stage had been reached.
Mr Dyer contended that:
a) Ms Spence’s exclusion of him from the site was a breach of the
obligation to provide the builder exclusive possession46 and a
substantial breach.47
b) Failure to pay the enclosed stage claim, when that stage was
complete, was a substantial breach.
c) There was no right to withhold the amount of the enclosed stage claim
on the basis of a dispute over amounts paid for variation works as
payment constituted acceptance of the work and a waiver of any rights.
d) There was no right to withhold the amount of the enclosed stage claim
on the basis of the lack of certification of the frame stage, as:
i) the work to be inspected by the engineer was not defective, the
issue being investigated by the engineer was a minor issue and
he was agreeable to installing additional ply if the engineer
considered it necessary.
ii) any issue the engineer had with the frame stage was irrelevant to
the enclosed stage claim payment and that he was ready, willing
and able to carry out the minor enhancements to the frame at Ms
Spence’s cost as the enhancements had arisen as a result of
variations requested by her.48
e) By email dated 17 October 2014, Mr Dyer requested evidence of Ms
Spence’s capacity to pay.49
f) By email dated 21 October 2014, Mr Dyer delivered a Notice to
Remedy Breach, which claimed that Ms Spence was in substantial
breach by failing to pay the enclosed stage progress claim,50 failing to
provide evidence of capacity to pay 51 and failing to give possession.52
The notice called for Ms Spence to remedy the breaches within 10
working days.
46 Clause 10.1.
47 Clause 27.2 (g).
48 Email Rowan Dyer to Robyn Spence dated 14 October 2014.
49 Clause 7.3.
50 Clause 4.
51 Clause 7.
52 Clause 10.1.
-- 16 of 22 --
17
g) By letter dated 5 November 2014, Mr Dyer terminated the contract
relying upon the Notice to Remedy Breach given by him on 21 October
2014.
By letter dated 29 October 2014 Ms Spence sought information as to the
basis of various claims made by Mr Dyer and stated that there was
‘significant uncertainty as to whether any monies are payable to you or
whether, in fact, a refund is due.’
I find that as at 21 October 2014, Mr Dyer was in substantial breach of the
contract. The notice was therefore ineffective and he was not entitled to
rely upon it in terminating, even if Ms Spence was in breach.53
The contract contemplates that the parties’ common law rights arising from
the other’s breach are not affected by the termination clause.54 Ms Spence
was not limited to seeking to terminate the contract by delivering a Notice
to Remedy, under clause 27.
I am satisfied that Mr Dyer was in substantial breach of the contract as he
had repudiated the contract by showing that he intended to fulfil the contract
only in a manner substantially inconsistent with his obligations and not in
any other way.55
In particular, Mr Dyer:
a) As referred to earlier in these reasons, made oral demands for
payment rather than making written progress claims as required by
clause 4;
b) Made written demands for payment, which were not in accordance with
clause 4 including because he sought adjustments to the contract sum
as if items of work were Prime Cost items when they were not;
c) Did not give variation documents to Ms Spence in breach of clause 19;
d) Departed from the terms of the contract, without Ms Spence’s
approval, including by constructing the frame of the garage with timber
rather than block work as specified;56
e) Failed to achieve finalisation of the frame stage despite having
effectively demanded and received payment for it. The engineer
inspected the framing work twice57 and was not prepared to issue the
necessary form 16 as the work required was incomplete as at 7
October 2014;
f) Demanded payment of the enclosed stage claim, when the work
required had not been completed. Mr Dyer contended that it was not
necessary to have obtained certification of the prior frame stage in
order to have achieved the enclosed stage. Having regard to the
53 Clause 27.7.
54 Clause 27.9.
55 Shevill v Builders Licensing Board (1982) 149 CLR 620, 625 – 627 (Gibbs CJ).
56 Exhibit 2, RS17 at sheets 11, 12 and 13.
57 On 1 September 2014 and 7 October 2014.
-- 17 of 22 --
18
definitions of the stages58 and clause 4 of the contract, I am satisfied
that the preferable construction of the contract is that the stages are to
be regarded as consecutive and not independent. This is also
consistent with the prohibition on starting the next stage of work until
a builder has been given a certificate of inspection for the relevant
stage stating that the stage complies with the building development
approval if a builder has given a notice for inspection for a stage of
assessable building work.59 As set out earlier in these reasons, I am
not satisfied that the frame stage was ‘finished’ apart from minor
defects or omissions and therefore the subsequent enclosed stage
could not have been achieved;
g) Failed to complete the work within the building period, a period of 150
days since commencement on 5 March 2014, such that it had expired
a number of months before the Notice to Remedy breach was
delivered. Having regard to Mr Carey’s estimate to complete the
contract works ($37,202.50 excl GST) when compared with the
contract price ($86,063 incl GST) there remained a significant amount
of work to be performed. Mr Dyer had not made any claims for
extensions of time in accordance with clause 16 of the contract or at
all. As he did not comply with clause 19 of the contract in respect of
variations, he had not indicated whether variations were likely to cause
delay.
The purported termination was repudiatory conduct as Mr Dyer again
evinced an intention not to be bound by the terms of the contract.60 Ms
Spence was entitled to accept Mr Dyer’s repudiatory conduct and terminate.
Where there is a wrongful repudiation of a building contract, the owner’s
measure of damages has been held to be the difference between the
contract price less any amount for progress claims paid and less the costs
to complete the works and rectify any defective works.61 In Chelbrooke
Homes Pty Ltd v Russell & Anor62 liquidated damages were also deducted.
The measure of damage is usually described as the amount of money that
will put the owner in the same position as if the contract had been
performed. Where an owner sues for damages the calculation is also to
take into account any benefit acquired by the owner. In calculating the
amount payable, the Tribunal recently considered the authorities and took
into account the reasonable value of variation work performed although the
builder did not comply with the DBC Act and no application under section
84 of the DBC Act had been made.63
To what damages is Ms Spence entitled?
58 Schedule 2.
59 Building Regulation 2006 (Qld), s 28.
60 Shevill v Builders Licensing Board (1982) 149 CLR 620.
61 QLine Interiors Pty Ltd v Jezer Construction Group Pty Ltd & Ors [2002] QSC 088,
[112].
62 [2011] QCAT 278.
63 Mt Cotton Constructions Pty Ltd v Greer [2017] QCAT 11.
-- 18 of 22 --
19
I find that Ms Spence’s loss before liquidated damages is $ 111,326.18.
Ms Spence claims that her loss for Mr Dyer’s breach of contract is at least
$22,321.16 and that having regard to a number of items of defective work
for which Mr Carey was unable to quantify rectification costs and his
conservatism in the quantification of other items damages should be
assessed globally in the sum of $30,000. No specific authority is provided
for this ‘rounding up’.
In Bellgrove v Eldridge64 the High Court found that a builder in breach of
contract would usually have to pay damages necessary to achieve
conformity with the contract subject to the qualification that
Not only must the work undertaken be necessary to produce conformity, but
that also, it must be a reasonable course to adopt.65
Where a defect can only be rectified by demolition but is relatively minor in
nature an award of damages on the basis of the cost of rectification by
demolition will not be made because doing so is not a reasonable course to
adopt. Where demolition is not reasonable, owners may lead evidence
which seeks to quantify the loss e.g. as to the diminution in value. No
evidence as to diminution in value was placed before me.
I accept Mr Carey’s evidence as to the savings, which Mr Dyer would have
achieved by not building in accordance with terms of the contract, is some
measure of the loss Ms Spence suffered as it is akin to an adjustment to the
contract sum by way of negative variation.
Ms Spence’s submissions that I should effectively round up the loss on her
calculation of at least $22,321.16 to a global loss of $30,000 appears to be
essentially a submission that Ms Spence seeks compensation for ‘solatium’.
The NSW Court of Appeal in Coshott v Fewings Joinery Pty Ltd66 found that
it was appropriate to award a natural person the amount of $5,000, where
there was a finding of a breach of the building contract but the rectification
was not both necessary and reasonable. This amount, referred to as
‘solatium’ or as ‘loss of amenity’ by the House of Lords in Ruxley Electronics
& Constructions Ltd v Forsyth67 was to compensate for inconvenience and
disappointment that the owner was not receiving the result for which the
owner contracted. The Western Australian Court of Appeal also allowed
the amount of $5,000 in similar circumstances in Willshee v Westcourt Ltd.68
The Tribunal considered the various authorities on claims for ‘solatium’ in
William George Carlsen t/as W & E Carlsen Builders v Tresidder69 and in
that case awarded $1,500.
64 (1954) 90 CLR 613.
65 Ibid, 618.
66 [1996] NSWSC 270.
67 [1996] AC 344.
68 [2009] WASCA 87.
69 [2015] QCAT 260, [233] – [252].
-- 19 of 22 --
20
In view of the number of departures from the contract documents and the
potential seriousness of the change to the external walls not allowing for the
extensions to the upper floors to be built at a later date, I allow $5,000.
Even if Mr Dyer had validly terminated the contract, Ms Spence would be
entitled to damages being the reasonable and necessary costs to rectify
defective work under the contract and the variations.
I calculate Ms Spence’s loss as follows:
a) Contract price including GST $ 86,063.00
b) Plus value of variations as assessed70 $ 37,024.90
c) Sub-total $123,087.90
d) Less money paid to builder71 $126,759.05
e) Sub-total ($ 3,671.15)
f) Less cost of rectification of the contract works72 $ 26,596.08
g) Less adjustment to reflect savings to builder73 $ 20,588.70
h) Less ‘solatium’ $ 5,000.00
i) Less costs of rectification of the Variation Works74 $ 14,547.50
j) Less costs of completion of the contract works75 $ 40,922.75
k) Owner’s loss before liquidated damages $ 111,326.18
Is Ms Spence entitled to liquidated damages?
I find that Ms Spence is entitled to liquidated damages in the sum of
$27,250.
Ms Spence claims liquidated damages at the rate of $50 per day until she
accepted Mr Dyer’s repudiation on 17 February 2016, the day the contract
was ended. Ms Spence’s submissions claim that period is 545 days.
Clause 31.1 of the contract provides that the owner is entitled to liquidated
damages for each day after the end of the building period to and including
the earlier of:
a) The date of practical completion;
b) The date the contract is ended; or
c) The date the owner takes control of, possession of, or uses the site or
any part of the site.
70 $31,277 plus $2382 plus GST.
71 Excludes the $2,000 paid on 19 February 2014 in respect of quotes.
72 $24,178.25 plus GST.
73 $18,717 plus GST.
74 $13,225 plus GST.
75 $37,202.50 plus GST.
-- 20 of 22 --
21
I accept Ms Spence’s evidence that:
a) The building period commenced on 5 March, 2014;76
b) Item 10 of the contract schedule provided that the works must reach
practical completion within 150 calendar days after commencement;
c) The building period expired on 2 August 2014;
d) Mr Dyer did not seek any extensions of time within which to perform
the work under the contract nor in respect of variations;
e) The works did not reach practical completion by 2 August 2014;77
f) The works remained incomplete at the time Mr Dyer purported to
terminate the contract on 5 November 2014;
g) The works remained incomplete as at 17 February 2016.
There is no evidence before me that Ms Spence took control of, possession
of or used the site or part of it prior to accepting Mr Dyer’s repudiation.
The DBC Act provides a builder with a limited right to apply to the Tribunal
for extensions of time where the contract is varied but the builder has not
complied with the variation provisions in the contract or the DBC Act.78
As previously stated in these reasons, Mr Dyer did not reduce the variations
to writing as required by clause 19 of the General Conditions of the contract
nor as required by section 79 of the DBC Act.
Even before Mr Dyer filed his Notice of Withdrawal, no application to the
Tribunal under the DBC Act had been made.
The Court of Appeal in Bartlett v Contrast Constructions Pty Ltd79 held that
the obligation to act reasonably and to mitigate one’s loss does not apply to
a claim for liquidated damages unless the contractual provision requires the
owner to act reasonably. In that case, as in this, the owner sued on the
builder’s promise to pay liquidated damages on a specified event occurring
and the event had occurred.
On my calculation there is at least 545 days in the period between 3 August
2014 and 17 February 2016. Ms Spence is therefore entitled to liquidated
damages as claimed.
Is Ms Spence entitled to interest?
I find that Mr Dyer is to pay interest on the sums awarded to Ms Spence at
the rate of 10% per annum from the day after the day that the damages are
payable until and including the day the amount is paid.
Ms Spence claims interest at the rate of 10% on the amount awarded
pursuant to section 34B of the Queensland Building and Construction
76 Clause 2.7.
77 Even on Mr Dyer’s evidence, the works had only reached the enclosed stage in or
about late September 2014.
78 The DBC Act, s 18.
79 [2016] QCA 119.
-- 21 of 22 --
22
Commission Regulation (Qld) 2003. The contract did not provide a relevant
agreed rate for amounts owing to the homeowner and therefore the
applicable rate is 10%.
Costs
It is appropriate to make directions in respect of submissions as to costs.
-- 22 of 22 --