Braycroft Pty Ltd v Queensland Building and Construction Commission [2017] QCAT 176
CITATION: Braycroft Pty Ltd v Queensland Building and
Construction Commission [2017] QCAT 176
PARTIES: Braycroft Pty Ltd
(Applicant)
v
Queensland Building and Construction
Commission
(Respondent)
APPLICATION NUMBER: GAR059-17
MATTER TYPE: General administrative review matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Hughes
DELIVERED ON: 22 May 2017
DELIVERED AT: Brisbane
ORDERS MADE: 1. The application to extend or shorten a
time limit or for waiver of compliance
with a procedural requirement is
dismissed.
2. The application to review a decision is
dismissed.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN
STATE AND TERRITORY COURTS – TIME,
EXTENSION, AND ABRIDGMENT – where
home warranty insurance claim declined –
where internal review confirmed original
decision – where applicant disputed decision
with decision-maker instead of applying for
external review
INTERESTS OF JUSTICE – PREJUDICE -
LENGTH OF DELAY – where delay of ten
months disproportionate to prescribed
timeframe of 28 days and contrary to Tribunal’s
ideals of fairness, informality, and expedition
REASONABLE EXPLANATION – where no
-- 1 of 11 --
2
reasonable explanation for initial four months –
where delay due to organising trades to remedy
defects not reasonable as would appear to
breach insurance policy conditions and situation
no different from other homeowner faced with
non-completion and a potential insurance claim
– where applicant did not proceed with external
review due to mistaken view of law – where
extending time for delay caused by fundamental
mistaken view of law would undermine
legislative scheme for review and is contrary to
Tribunal’s mandate to resolve matters
expeditiously
MERITS OF CASE – where applicant did not
provide material for Tribunal to consider
preliminary issue of merit – where not sufficient
to displace prima facie rule that proceedings
commenced outside period will not be
entertained and that applicant show acceptable
explanation for delay – where applicant’s
unilateral acts of completion would appear to
breach insurance policy conditions and prevent
any future assessment of need, scope, and
expenditure required for works and severely
limit its prospects of success on review
Queensland Building and Construction
Commission Act 1991 (Qld), s 86C
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 3, s 4, s 28, s 33
Aon Risk Services Aust Ltd v. Australian
National University (2009) 239 CLR 175
Batch v. Chief Executive, Department of
Employment, Economic Development and
Innovation [2010] QCAT 93
Benson v. Ware [2012] QCATA 24
Bigby v. Queensland Building and Construction
Commission [2014] QCAT 169
Bradley v. Chief Executive, Department of
Employment, Economic Development and
Innovation [2010] QCAT 130
Braunberger v. Assistant Commissioner Les
Hopkins [2014] QCAT 34
Breezeway Developments Pty Ltd v. ADG
Hydraulics Pty Ltd [2010] QCATA 69
Brookes v. Chief Executive, Department of
Employment, Economic Development and
Innovation [2010] QCAT 131
-- 2 of 11 --
3
Brown v. Chief Executive, Department of
Employment, Economic Development and
Innovation [2010] QCAT 128
Burnett v. Nogoa River Flood Plain Board &
Ensham Resources P/L [2010] QCAT 50
Chief Executive, Department of Employment,
Economic Development and Innovation v. Fuchs
[2011] QCAT 29
Cardillo v. Queensland Building Services
Authority [2011] QCAT 574
Creek v. Raine & Horne Real Estate Mossman
[2011] QCATA 226
Crime and Misconduct Commission v. Chapman
[2011] QCAT 229
D Wren Pty Ltd and F Wren Pty Ltd v. Chief
Executive, Department of Employment, Economic
Development and Innovation [2010] QCAT 29
Danes and Anor v. Sulman [2012] QCATA 81
Fuchs v. Chief Executive, Department of
Employment, Economic Development and
Innovation [2010] QCAT 91
Gallagher v. QBSA [2010] QCAT 383
Hunter Valley Developments Pty Ltd v. Barry
Cohen, Minister for Home Affairs [1984] FCA 176
Litzow v. Racing Queensland Pty Ltd [2010]
QCAT 414
Lucic v. Nolan [1982] FCA 217
McClintock v. Queensland Building Services
Authority [2010] QCAT 68
Melksham & Burger v. Body Corporate for Aqua
[2010] QCAT 7
Rayner & Anor v. Trabme Pty Ltd t/as Elders
Redcliffe [2013] QCATA 212
Regal Waters Retirement Community Pty Ltd v.
Miller & Ors [2011] QCAT 479
Ren v. Poolworld Pty Ltd [2011] QCAT 706
Surace v. Commisso Enterprises Pty Ltd and
Anor [2011] QCAT 271
The Body Corporate for No. 9 Port Douglas Road
v. McEvoy [2011] QCATA 292
Thompson Residential Pty Ltd v. Hart & Hart
[2014] QDC 132
Whalley v. Queensland Building and Construction
Commission [2017] QCAT 15
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to section 32 of
the Queensland Civil and Administrative Tribunal Act 2009 (Qld).
-- 3 of 11 --
4
REASONS FOR DECISION
What is this Application about?
[1] The Queensland Building and Construction Commission declined
Braycroft Pty Ltd’s claim under the Home Warranty Insurance Scheme
because it found that Braycroft did not properly terminate the contract.
[2] The Commission confirmed its decision on internal review. Braycroft
disputed this was a “new decision” but instead of applying for external
review by the Tribunal, and after a delay of some months, pursued the
Commission to re-consider.
[3] When the Commission refused, Braycroft applied to the Tribunal for
external review. At the same time, Braycroft Pty Ltd applied to the Tribunal
for an order declaring that a letter from the Queensland Building and
Construction Commission dated 29 April 2016 did not constitute a “new
decision”1 and an order requiring the Commission to make a “new
decision” within 28 days.
[4] In the alternative, Braycroft applied to the Tribunal to extend the time limit
to apply for external review.
Background
[5] After the Commission filed submissions in reply to Braycroft’s application
as directed by the Tribunal,2 Braycroft sent an email to the Tribunal with
“brief submissions in reply”,3 without any directions to do so from the
Tribunal and despite already providing submissions with its application.
[6] Braycroft’s further unsolicited submissions could raise issues of
procedural fairness for the Commission, who has not been given an
opportunity to respond. Making unsolicited submissions is contrary to the
Tribunal’s mandate to observe the rules of natural justice and ensure
proceedings are conducted in an informal way that minimises costs to
parties, and is as quick as is consistent with achieving justice.4
[7] Doing the best I can to address these submissions within this context, it
would appear that most of these submissions do not add to Braycroft’s
submissions accompanying its application. They do, however, raise two
further points that can be dispensed with promptly.
[8] Braycroft submitted that the Commission’s submissions should be
“ignored” because they were prepared by an external lawyer without the
Tribunal granting leave for the Commission to be legally represented.
1 Queensland Building and Construction Commission Act 1991 (Qld), s 86C.
2 Directions dated 22 March 2017.
3 Email Lawrie Ward to QCAT dated 9 April 2016.
4 Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 4(c), s 28(3)(a).
-- 4 of 11 --
5
[9] Although the Commission’s submissions are signed by a law firm as
“Solicitors for the Respondent”, this does not equate to representation
requiring leave. It is well established that a party can prepare and
formulate its case and documents with legal assistance, without requiring
the Tribunal’s leave.5
[10] Braycroft also submitted that “the Applicant consented to a decision being
made in a longer period… that consent has not been withdrawn and there
is no time limit on that longer period”.6
[11] Nothing turns on this submission. If Braycroft agreed to a longer period of
90 days from the Commission’s email of 5 February 2016 for the
Commission to complete its review,7 that expired on 5 May 2016.8 If the
Commission did not decide the application by then, it is deemed to have
made the same reviewable decision.9
[12] I will now address the substantive issues.
What was the original decision?
[13] On 3 December 2015, Ms Marie-France Wellington, Claims Officer with
the Commission, disallowed Braycroft’s non-completion claim under the
Home Warranty Insurance Scheme on the basis that it had not properly
terminated the contract.
When did the Commission make an ‘internal review’ decision?
[14] It would appear that Braycroft applied for internal review on 30 December
2015.10
[15] On 29 April 2016, Mr Jonathan Pacey, Senior Internal Review Officer with
the Commission, notified Braycroft:
I have reviewed this matter and decided to uphold the original decision on the
basis that you have not provided sufficient evidence to indicate that the
decision was incorrect.11
5 Bradley v. Chief Executive, Department of Employment, Economic Development and
Innovation [2010] QCAT 130 at [30]; Brookes v. Chief Executive, Department of
Employment, Economic Development and Innovation [2010] QCAT 131 at [30];
Melksham & Burger v. Body Corporate for Aqua [2010] QCAT 7 at [25]; Batch v. Chief
Executive, Department of Employment, Economic Development and Innovation [2010]
QCAT 93 at [32]; Brown v. Chief Executive, Department of Employment, Economic
Development and Innovation [2010] QCAT 128 at [30]; D Wren Pty Ltd and F Wren Pty
Ltd v. Chief Executive, Department of Employment, Economic Development and
Innovation [2010] QCAT 29 at [30]; Burnett v. Nogoa River Flood Plain Board &
Ensham Resources P/L [2010] QCAT 50 at [17]; Fuchs v. Chief Executive, Department
of Employment, Economic Development and Innovation [2010] QCAT 91 at [31]; Regal
Waters Retirement Community Pty Ltd v. Miller & Ors [2011] QCAT 479 at [9].
6 Email Lawrie Ward to QCAT dated 9 April 2017.
7 Email Lawrie Ward to QBCC dated 5 February 2016.
8 Queensland Building and Construction Commission Act 1991 (Qld), s 86C(2)(b)
9 Queensland Building and Construction Commission Act 1991 (Qld), s 86C(3).
10 QBCC letter to Braycroft Pty Ltd dated 29 April 2016 refers to a review application
dated 30 December 2015.
-- 5 of 11 --
6
[16] Braycroft submitted that this was not an ‘internal review decision’ because
the review officer did not consider the matter afresh, but merely followed
the previous findings of an adjudicator.
[17] Regardless of the basis for the Commission’s decision on 29 April 2016, it
was a ‘decision’. For the purposes of a review application, a ‘decision’ is
not characterised by its reasoning, but rather by the acting or failing to act
on information to come to a conclusion within the required period.12 Even
a failure to decide an internal review application within the required period
is deemed to be a ‘decision’.13 This shows that reasoning is not relevant to
whether a ‘decision’ has been made: it is the result, not the process that is
relevant.
[18] A decision is still ‘new’ for the purposes of internal review even if it mirrors
the original decision, provided that a new, independent mind of a person
no less senior is brought to the issue.14 Nothing in the material suggests
that this did not occur: the person who decided the internal review
application was not the person who made the original decision and was
more senior.15
[19] The Tribunal is satisfied the letter from the Commission to Braycroft dated
29 April 2016 is an ‘internal review decision’ for the purposes of external
review.
[20] This means that Braycroft’s application for an order declaring that the
Commission’s letter dated 29 April 2016 did not constitute a ‘new decision’
and for an order that the Commission make a new decision must be
dismissed.
[21] Braycroft had 28 days to apply for external review by the Tribunal from
when the Commission notified him of its decision.16 This means that
Braycroft had 28 days from 29 April 2016 to apply to the Tribunal for
external review.
Should the Tribunal extend the time limit?
[22] The Tribunal must consider the interests of justice to decide whether to
extend time.17 This requires considering whether another party will be
prejudiced, the length of the delay, whether the applicant has a
reasonable explanation for the delay, and the merits of its case.18
11 QBCC letter to Braycroft Pty Ltd dated 29 April 2016.
12 Queensland Building and Construction Commission Act 1991 (Qld), s 86C(1), s 86C(3).
13 Queensland Building and Construction Commission Act 1991 (Qld), s 86C(3).
14 Queensland Building and Construction Commission Act 1991 (Qld), s 86C(4); Whalley
v. Queensland Building and Construction Commission [2017] QCAT 15 at [73].
15 Queensland Building and Construction Commission Act 1991 (Qld), s 86C(4).
16 Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 33(3), s 33 (4).
17 Cardillo v. Queensland Building Services Authority [2011] QCAT 574 at [18], citing with
approval Gallagher v. QBSA [2010] QCAT 383; CMC v. Chapman & Anor [2011] QCAT
229.
18 Cardillo v. Queensland Building Services Authority [2011] QCAT 574 at [18], citing with
-- 6 of 11 --
7
Is the Commission prejudiced by the delay?
[23] The Commission conceded that it has not been prejudiced by the delay.
How long is the delay?
[24] Braycroft did not apply to the Tribunal to review the internal review
decision until 16 March 2017, some ten months after the 28-day time
limit.19 I do not accept Braycroft’s submission that this is not such a long
time “in the bigger scheme of this matter”.20
[25] This is because granting an extension for such a lengthy period is
disproportionate to the prescribed timeframe of 28 days and other cases in
the Tribunal where extensions of only a few days or weeks have been
granted,21 and is contrary to the Tribunal’s ideals of fairness, informality,
and expedition.22
Is there a reasonable explanation for the delay?
[26] Braycroft submitted that following the Commission’s refusal of its claim, it
had been “consistently and repeatedly” informing the Commission that the
original decision and internal review decision were incorrect and not
properly made. It submitted that it had decided not to proceed with an
application for review by the Tribunal, while liaising with the Commission
to reconsider its decision of 29 April 2016.
[27] The Commission conceded that it had discussed with Braycroft whether it
was able to reconsider the decision between 16 November 2016 and 16
February 2017.
[28] However, this does not explain the delay before this: from the decision of
29 April 2016. The evidence does not show ongoing communications or
negotiations between Braycroft and Commission following the internal
review decision of 29 April 2016.
[29] Following the Commission’s internal review decision on 29 April 2016,
Braycroft emailed the Commission on the same day taking issue with
aspects of the decision and then did not contact the Commission again
approval Gallagher v. QBSA [2010] QCAT 383; CMC v. Chapman & Anor [2011] QCAT
229
19 Queensland Civil and Administrative Tribunal Act 2009 (Qld) s 33(3); Application to
review a decision dated 16 March 2017.
20 Unlike Bigby v. Queensland Building and Construction Commission [2014] QCAT 169,
where a delay of three to five months in filing the application for review was in the
context of a delay of nine years between completion of the work and the home owner
first complaining to the Commission.
21 Litzow v. Racing Queensland Pty Ltd [2010] QCAT 414 (eight days); Crime and
Misconduct Commission v. Chapman [2011] QCAT 229 (one day); Chief Executive,
Department of Employment, Economic Development and Innovation v. Fuchs [2011]
QCAT 29 (one day); Surace v. Commisso Enterprises Pty Ltd and Anor [2011] QCAT
271 (one week); The Body Corporate for No. 9 Port Douglas Road v. McEvoy [2011]
QCATA 292 (one month).
22 Danes and Anor v. Sulman [2012] QCATA 81 at [15].
-- 7 of 11 --
8
until an email of 22 August 2016. Braycroft’s email of 22 August 2016
relevantly stated:
I refer to my unacknowledged email below, in response to your attached letter. I
have been occupied navigating the tortuously time consuming defect
rectification process. Now that is nearing a successful conclusion, I revisited
your review.23
[30] By this time, the 28-day period to apply for external review had already
passed. Given the lack of communication between Braycroft and
Commission between 29 April and 22 August 2016, the Tribunal does not
accept that communications between Braycroft and the Commission
explains the delay of four months.
[31] Braycroft said that following its termination of the contract on 15 October
2015, it had been very busy organising trades to remedy defects and
complete the work, and dealing with other issues created by the builder.
This cannot be a reasonable explanation as it would appear to breach the
insurance policy conditions.24
[32] Moreover, the Tribunal does not accept this as a reasonable explanation
for a delay of some 10 months. Braycroft’s situation was no different from
any other homeowner faced with non-completion and a potential claim
under the statutory insurance scheme. At most, this might explain a delay
of days or weeks. The review application form is six pages in length, is not
difficult to understand,25 and would not require an inordinate period to
complete.
[33] Braycroft did nothing for four months and then contacted the Commission
requiring it to perform its “statutory duty”.26 The Commission had already
done that on 29 April 2016. It would appear that Braycroft did not proceed
with external review because it (mistakenly) believed the Commission’s
letter of 29 April 2016 was not an internal review.27 Unfortunately for
Braycroft, it “nailed its colours to the wrong mast”.28
[34] If Braycroft believed the Commission’s decision to be incorrect or even not
properly made,29 then the Legislature has specifically provided for external
review. Braycroft did not do this and thereby failed to act in its own best
interests:
The statutory regime places obligations upon parties themselves to take care in
their dealings with Tribunal matters, and to act in their own best interests.
23 Email Lawrie Ward to Internal Review dated 22 August 2016.
24 See reasons under heading ‘Does the application for review have merit?’.
25 Rayner & Anor v. Trabme Pty Ltd t/as Elders Redcliffe [2013] QCATA 212, per Wilson J
at [46].
26 Email Lawrie Ward to Internal Review dated 22 August 2016.
27 Email Lawrie Ward to Internal Review dated 29 April 2016.
28 Thompson Residential Pty Ltd v. Hart & Hart [2014] QDC 132, per McGill SC DCJ at
[85]; See reasons under heading ‘When did the Commission make an internal review
decision?’
29 Queensland Building and Construction Commission Act 1991 (Qld), s 86C(3).
-- 8 of 11 --
9
QCAT’s resources for the resolution of disputes are in high demand and serve,
as the High Court has recently observed in relation to court resources, ‘… the
public as a whole, not merely the parties to the proceedings’.30
[35] Braycroft’s communications with the Commission quoted relevant
provisions of the Act, provided an interpretation, and cited case law.
Within this context, it is difficult to envisage how Braycroft could not have
read or understood the provisions providing for external review and what
constitutes an ‘internal review’.
[36] Extending time for delay caused by an applicant’s fundamental mistaken
view of the law in these circumstances would undermine the legislative
scheme for review and is contrary to the Tribunal’s mandate to resolve
matters expeditiously:31
In the context of the legislation and the demands upon public resources like
those which fund QCAT it is not unreasonable to impose, upon a party, an
expectation and an obligation that it will ensure it acts in its own best interests,
or accept the consequences; and that mistakes like those made here, while
attracting sympathy, can no longer prevail over statutory and practical
constraints on available resources for dispute resolution.32
[37] The Tribunal does not accept Braycroft’s disagreement with the
Commission’s internal review decision provides a reasonable explanation
to not apply to the Tribunal for external review.
[38] The Tribunal cannot find a reasonable explanation for the delay.
Does the application for review have merit?
[39] The Commission declined Braycroft’s insurance claim because Braycroft
failed to make a fixing stage payment when it purported to terminate the
contract. Braycroft submitted that it correctly terminated the contract
because the builder did not complete the fixing stage.
[40] In its application to extend time, Braycroft referred to statutory
declarations, an expert’s report, and photographs to show that fixing stage
was not reached. Whether any of this has value depends on whether:
1. completion of the work to fixing stage was a condition precedent to
payment; and
2. what has in fact been done can be said to constitute satisfaction of the
definition of “fixing stage” in the contract – if any.33
30 Creek v. Raine & Horne Real Estate Mossman [2011] QCATA 226, per Wilson J at
[13].
31 Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 3, s 4.
32 Breezeway Developments Pty Ltd v. ADG Hydraulics Pty Ltd [2010] QCATA 69 at [12].
33 Thompson Residential Pty Ltd v. Hart & Hart [2014] QDC 132, per McGill SC DCJ at
[72].
-- 9 of 11 --
10
[41] However, Braycroft did not provide any contract alleged to have been
relied upon or other material for the Tribunal to consider either of these
issues - not in in the Application to extend, substantive Application for
review, or later unsolicited submissions.
[42] Whether Braycroft properly terminated the contract would require
consideration of the terms of the contract, including whether completion of
the work to fixing stage was a condition precedent to payment.34 Because
of the lack of material and in particular, any contract alleged to have been
relied upon, the Tribunal was unable to consider even this preliminary
issue of merit.
[43] Braycroft also submitted that by declining its claim, the Commission
“forced” Braycroft into arranging and already paying for completion of the
building and defects.35 However, the appropriate course would have been
for Braycroft to apply for external review without delay.
[44] Moreover, Braycroft’s unilateral acts of completion would appear to breach
the insurance policy conditions requiring the Commission’s written
approval.36 By proceeding to completion without approval, Braycroft has
prevented any future assessment of the need, scope, and expenditure
required for the works. This would severely limit its prospects of success
on review.
[45] Within the context of proper case management and the proper use of
public resources,37 Braycroft has not established any merit sufficient to
displace the prima facie rule that proceedings commenced outside the
prescribed period will not be entertained and that it is a precondition to the
exercise of discretion in the applicant’s favour that the applicant show an
acceptable explanation for the delay.38
Do the interests of justice warrant an extension of time?
[46] The Tribunal does not consider the interests of justice are served by
extending time39 because of the disproportionate length of the delay,40 the
lack of a reasonable explanation for the delay,41 and Braycroft’s failure to
show merit in its application for review42.
34 Thompson Residential Pty Ltd v. Hart & Hart [2014] QDC 132.
35 Application to extend dated 16 March 2017, Part B at [18].
36 QBCC Insurance Policy Conditions (Edition 8), section 7.1 as cited in Submissions In
Response dated 4 April 2017, paragraph 4.19.
37 Ren v. Poolworld Pty Ltd [2011] QCAT 706 at [8], citing with approval Aon
Risk Services Aust Ltd v. Australian National University (2009) 239 CLR 175.
38 Cardillo v. Queensland Building Services Authority [2011] QCAT 574 at [33], citing with
approval Lucic v. Nolan [1982] FCA 217 and Hunter Valley Developments Pty Ltd v.
Barry Cohen Minister for Home Affairs [1984] FCA 176 at [18]; Bigby v. Queensland
Building and Construction Commission [2014] QCAT 169 at [23] to [24].
39 Benson v. Ware [2012] QCATA 24 at [9].
40 Braunberger v. Assistant Commissioner Les Hopkins [2014] QCAT 34 at [9].
41 McClintock v. Queensland Building Services Authority [2010] QCAT 68 at [4].
42 McClintock v. Queensland Building Services Authority [2010] QCAT 68 at [4];
-- 10 of 11 --
11
What are the appropriate Orders?
[47] The appropriate Orders are that:
1. The application to extend or shorten a time limit or for waiver of
compliance with a procedural requirement is dismissed; and
2. The application to review a decision is dismissed.
Braunberger v. Assistant Commissioner Les Hopkins [2014] QCAT 34 at [9]
-- 11 of 11 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2017/176