Davis v Gray [2017] QCAT 120
CITATION: Davis v Gray [2017] QCAT 120
PARTIES: Vicki Davis
(Applicant)
v
John Norman Gray
(Respondent)
APPLICATION NUMBER: BDL067-16
MATTER TYPE: Building matters
HEARING DATE: 19 January 2017
HEARD AT: Brisbane
DECISION OF: Member Gordon
DELIVERED ON: 31 March 2017
DELIVERED AT: Brisbane
ORDERS MADE: The application is dismissed.
CATCHWORDS: CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – PARTIES – GENERAL
PRINCIPLES - where a written contract in which
parties were clear was replaced by a written
contract where parties were unclear – where
subsequent conduct suggested a possible
change of party – whether there was a change
of party
Pico Holdings, Inc v Wave Vistas Pty Ltd [2005]
HCA 13
Ermogenous v Greek Orthodox Community of
SA Inc [2002] HCA 8
APPEARANCES:
APPLICANT: Self-represented
RESPONDENT: Self-represented
-- 1 of 8 --
2
REASONS FOR DECISION
In this application Vicki Davis claims a total of some $55,024.31 from John
Gray in a commercial building dispute. She limits her claim to $50,000
which is the Tribunal’s financial limit in such a dispute.1
The resolution of this claim turns on whether Mr Gray had any obligations
to Mrs Davis. There is some uncertainty as to whether it was he, or his
company Qualitybuild Pty Ltd ACN 129 312 456,2 that contracted to provide
building services to Mrs Davis. Qualitybuild was clearly the party on the
original contract. But that contract was replaced by a contract where the
party was unclear. And some later events suggest it was possible that Mr
Gray personally became the contracting party instead. All work ceased in
October 2014, and then Qualitybuild was deregistered on 5 July 2015. So
when Mrs Davis made the application to the Tribunal on 14 March 2016 she
sued only Mr Gray.
The claim is in two parts:-
a) A claim for $16,480 for defective work.
b) A claim for $38,544.31 being money paid to Mr Gray but which was
an overpayment.
Claim a) turns in the first instance on the question whether Mr Gray was a
party to the contract with Mrs Davis. If it was Qualitybuild and not Mr Gray
who owed the duty to do the work properly, then this claim will not succeed
against Mr Gray.
Claim b) in theory could be good against Mr Gray even if he was not a party
to the contract. This could be, for example, if Mrs Davis entrusted him with
her money as contractual payments but he misappropriated it.
Whether a person is a contracting party should be determined in
accordance with the objective theory of contract. This means that the
question to ask is who a reasonable person in the position of the known
contracting party would think was the other contracting party.3 Sometimes
this question is closely allied to whether there was a contract at all, or
whether the proposed other contracting party intended to create legal
relations, both of which are also objective tests.4 The objective test means
that the subjective belief of Mrs Davis as to the person with whom she was
contracting is irrelevant.
1 The financial limit can however, be enlarged with consent of the parties: section 78
Queensland Building and Construction Commission Act 1991.
2 Of which he was the sole director and shareholder.
3 Pico Holdings, Inc v Wave Vistas Pty Ltd [2005] HCA 13.
4 In the case of intention to create legal relations: Ermogenous v Greek Orthodox
Community of SA Inc [2002] HCA 8.
-- 2 of 8 --
3
In late 2012, Qualitybuild gave an undated quote to Mrs Davis for the sum
of $299,960 plus GST for renovation work at the Beenleigh Pet Motel which
was operated by her. The work involved extensions and alterations to the
main dwelling, with landscaping and drainage work and a driveway and car
parking area.5
On 20 December 2012 Qualitybuild’s contract on the Master Builders’
Commercial Building Contract form was signed by Mrs Davis. This was for
“alterations and upgrade to existing kennels” by reference to plans as
identified in the contract. When signed, it contained a contract sum of
$350,000 with payment claims to be submitted fortnightly.6 The contract
showed an intention to finance the work with a loan of $350,000. The
contract sum was later altered by Mrs Davis on her copy to $285,000 and
at the same time she also altered the loan amount to $285,000.7 There is
a difference between the parties about the motive for making this change
or whether Mr Gray was aware of it, but this is not relevant to the issue I
have to decide.
The important thing about the contract is that the contracting parties were
clearly Qualitybuild Pty Ltd and Mrs Davis.
Over the next few months although there was some delay in starting the
work, there was some progress towards it. There was a compliance
assessment from Logan City Council for landscaping works on 29 August
20138 and the Master Builders’ insurance for the work to be done by
Qualitybuild was put in place on 22 October 2013. Qualitybuild did some
work on site from December 2013 but started in earnest in January 2014.
The parties did not stick to the payment arrangements in the contract dated
20 December 2012. Instead of invoicing fortnightly, Qualitybuild invoiced
Mrs Davis weekly, showing labour and materials to date, and she paid these
invoices. She also paid Qualitybuild’s sub-contractors directly.9 This
arrangement was formalised when Mr Gray asked Mrs Davis to sign a
Master Builders Commercial Cost Plus Contract form which he had
prepared. They both signed this on 10 February 2014.10 In this document
the payment obligations were stated to be:-
The owner and the contractor agree that the contractor is to be paid
weekly upon invoice being given to owner.
The work described in the cost plus contract was described as “car park
and shed, extension to residence and offices, sound limiting to dog
5 Page 23 of the documents attached to the claim.
6 Marked “A” in the documents attached to the response.
7 The amended version can be seen on page 24 of the documents attached to the claim.
8 Page 51.
9 The extent of the direct payments to sub-contractors can be seen from the Beenleigh
Pet Motel ledger attached to Mrs Davis’s statement of 12 August 2016.
10 Marked “F” in the documents attached to the response. There is a fuller version of this
document attached to Mrs Davis’s statement of 12 June 2016.
-- 3 of 8 --
4
kennels”. Nothing turns on the difference in the description of the work here
with that in the original contract. Both sides agree that the same work was
in the two contracts: it was just described differently.
The parties to the cost plus contract were given on the first page in a section
of the document headed “between”. The names appeared in this way:-
Contractor: John Gray
Trading as: Qualitybuild Pty Ltd
The words “Contractor” and “Trading as” were already printed on the form,
and Mr Gray had inserted his own name and the name of the company as
above. The question here is whether Mr Gray was the contracting party
since his name appeared against the work “contractor”.
In reaching a conclusion on this, I need to take into account that it is often
the case that directors of small companies will regard themselves as
operating through the company, as Mr Gray told me he did. Viewed in this
way, Mr Gray’s entries on the form do not seem odd at all – he was doing
the work but through his company (colloquially, “trading as” his company).
The answers are legalistically incorrect, but when considering how a
reasonable person in the position of Mrs Davis would consider this, I think
she would regard it the same way as Mr Gray, and would consider that she
was contracting with Qualitybuild and not Mr Gray personally.
This is particularly so I think, because the existing contract was clearly
between Qualitybuild and Mrs Davis and the cost plus contract was merely
to change the arrangements for payment, not the nature or extent of the
work which was to be done. For the parties to the contract to change
therefore, would have required some discussion and agreement about the
change of party, which did not happen.
In the circumstances I have no doubt that the parties to the costs plus
contract were Mrs Davis and Qualitybuild and that Mr Gray was not a party
to it.
Work continued under the costs plus contract, and invoices were paid in the
way that had been agreed.
The parties then altered the arrangement slightly. Instead of Mrs Davis
paying the sub-contractors directly, it was agreed that Mr Gray would
generally pay the sub-contractors himself or from his company. Mrs Davis
would then reimburse him for his outlay. The reason for this change was
that some sub-contractors were loading their bills for Mrs Davis which Mr
Gray was anxious to stop happening.
This change happened in about the middle of June 2014 and it was about
the same time that Mr Gray informed Mrs Davis that he was “getting rid of
Qualitybuild”. Unknown to Mrs Davis at that time, he had decided not to
-- 4 of 8 --
5
renew Qualitybuild’s QBCC licence beyond 30 June 2014 and it expired on
that date. However, he continued to hold a builder licence in his own right.
He told me that after the expiry of Qualitybuild’s licence the company could
continue the work relying on his personal licence.11
There are a substantial number of invoices given to Mrs Davis for payments
under the contract over the course of the work. It may be significant
whether those invoices were given by Qualitybuild or by Mr Gray. They
were only given by Qualitybuild in the early stages. From 22 February 2014
they were given by Mr Gray, with no mention of Qualitybuild. However, Mrs
Davis was aware that Qualitybuild was still involved in engaging sub-
contractors and purchasing materials right up to the cessation of work in
October 2014.
As for the destination of payments made by Mrs Davis, some payments
were made directly into Qualitybuild’s account by direct debit, right up to the
very last payment on 6 October 2014.12 A number of payments were made
to Mr Gray personally when he requested this, mostly by cheque but there
were also two direct debits into his personal bank account.
As the manner in which the payments were recorded in Mrs Davis’s
accounting system, they were all shown as Qualitybuild. There is no ledger
entry showing a payment to Mr Gray.
There was another document which may be important – this was a Master
Builders “Confirmation of Variation/Instruction” document dated 5 August
2014 which purported to increase the contract sum by $45,000.13 In this
document Mr Gray was named as the “contractor”. It was signed both by
Mrs Davis and Mr Gray. From what the parties told me, I do not think this
document was intended by them to act as a contractual variation. Both
sides agree that the document did not affect the extent of the work which
was to be done (there is no description of work on the document), and there
was no contract sum which it could vary. I accept Mr Gray’s evidence that
it was produced so that Mrs Davis could obtain more funds from the bank.
Despite the running down of Qualitybuild, Mr Gray kept open Qualitybuild’s
bank account, continued to use its headed paper from time to time, and
permitted subcontractors to bill Qualitybuild. He continued to use
Qualitybuild’s suppliers’ accounts, which provided a discount on purchases.
At the time, Qualitybuild had no other work which it was completing.
11 This appears to be a reference to the head contractor’s exemption in section 8 of
Schedule 1A of the Queensland Building and Construction Commission Act 1991,
which applied from 1 December 2013.
12 This appears from the company bank statements submitted to the Tribunal on 16
February 2017.
13 Document “E”.
-- 5 of 8 --
6
That Mr Gray regarded the contract as continuing is shown by the fact that
he terminated the contract on 7 October 2014.14 After that, he prepared a
final account and presented this to Mrs Davis, together with a bundle of
bills. This document was on Qualitybuild’s headed paper.15
I have already decided that after the costs plus contract was signed on 10
February 2014 the contracting parties were Qualitybuild and Mrs Davis. I
have to decide whether this changed over the next eight months up to the
time when Mr Gray terminated the contract on 7 October 2014.
Apart from contractual provisions permitting a change of party, in law there
are two ways in which the parties to a contract can change: by assignment
or novation.
There was no assignment here. The costs plus contract of 10 February
2014 required the written consent of Mrs Davis to an assignment by
Qualitybuild of its rights and obligations to Mr Gray,16 and this did not
happen.
A novation would require an agreement supported by consideration
whereby the existing contract was wholly or partially discharged and
replaced with another contract.17
There was certainly no express agreement here that Qualitybuild’s rights
and obligations under the contract should be taken over by Mr Gray.
I do not think any such agreement can be implied either. Mrs Davis was
unaware that Qualitybuild’s QBCC licence had expired at the end of June
2014. Mr Gray relied on his own personal builder licence as permitting the
company to continue the contract. Even if he was wrong about this, the
contract with Qualitybuild could continue (it was not voided by the ending
of licence). As I have found, the “variation” document of 5 August 2014 was
not for the purpose of varying the contract between Qualitybuild and Mrs
Davis and certainly not to change the parties to that contract. A reasonable
person in the position of Mrs Davis would assume that Mr Gray had inserted
his own name as contractor on that document either by mistake or for the
sake of brevity or informality.
As for the requests by Mr Gray for personal payment to him on several
occasions, a reasonable person would suppose that he was taking
director’s drawings from the company, as often happens with small
companies.
In any case, any possibility of an agreement being implied from these
events is negated by the fact that Mrs Davis continued to make payments
14 By email, document “D”.
15 Document “C”.
16 Clause 4(a).
17 As explained by Julian Bailey in the Journal of Contract Law (1999) 14 JCL 189.
-- 6 of 8 --
7
directly into the Qualitybuild account, was aware that Qualitybuild continued
to engage sub-contractors for work on her site, and was aware that
Qualitybuild continued to purchase materials for use on her site. In addition
to this, the final account of 21 November 2014 was on Qualitybuild’s headed
paper.
Any significance in the billing by Mr Gray instead of Qualitybuild is
diminished by the fact that it had continued since February 2014, and
therefore spanned a period over which there was no question that
Qualitybuild was the contracting party. Clearly this was done by Mr Gray
to reduce formality or for the sake of brevity.
I conclude therefore, there was no legal mechanism which operated to
change the parties to the contract after the signing of the costs plus contract
of 10 February 2014 and the parties to the contract remained Mrs Davis
and Qualitybuild.
The claim under a) relates to defective work on the path and to the step
outside the kennels. In the light of my findings above, this claim can only
be against Qualitybuild and cannot be against Mr Gray personally since he
did not have any contractual responsibility to construct these things. It must
follow that the claim under a) fails.
Turning to the claim under b), it is calculated as follows:-
Amount paid: $232,219.82
Amount invoiced: $189,331.94
Difference: $ 42,887.88
Less cheque received: $ 4,343.57
$ 38,544.31
The cheque received is an amount which was paid by Mr Gray to Mrs Davis
when he did his own reconciliation, after terminating the contract.18 He
accepted that there was an amount which had been paid which exceeded
the invoices but he had reached a figure of $4,343.57.
This claim turns on whether there is some way that Mr Gray can be
personally liable to return any overpayment, bearing in mind that he was
not the other contracting party.
Both parties agree that all work done by the builder was governed by the
10 February 2014 contract. Since all payments were made with the
intention of paying for such work, it follows that all payments were made
18 It can be seen from Qualitybuild’s bank statements submitted on 16 February 2017 that
the source of this money was from the Qualitybuild account.
-- 7 of 8 --
8
under the 10 February 2014 contract. This means that any overpayment
which may have occurred would be a payment made to Qualitybuild. In so
far as those payments were made to Mr Gray personally, he would have
been acting as agent for Qualitybuild when receiving those payments.
There is no scope here for saying that he received this money from Mrs
Davis in his personal capacity. This is because all the payments were made
under, and because of, the 10 February 2014 contract. He may well have
kept the money to himself, but if this did happen it would have been received
by him in his personal capacity as directors fees. Therefore no money could
be recovered back from him by Mrs Davis if she managed to show that she
had overpaid Qualitybuild.
Mrs Davis also points to some corrections which ought to be made to the
final account, which arise from the invoices and receipts which Mr Gray
handed to Mrs Davis at the time he gave her his reconciliation. Again for
the reasons given for claim b) these are matters between Mrs Davis and
Qualitybuild and not between Mrs Davis and Mr Gray.
It follows that claim b) fails as well and so I must dismiss the application.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2017/120