Aveo Clayfield Pty Ltd v Brisbane City Council [2017] QPEC 60 (2018) QPELR 139
PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND
CITATION: Aveo Clayfield Pty Ltd v Brisbane City Council [2017] QPEC
60
PARTIES: AVEO CLAYFIELD PTY LTD (ACN 087 435 827)
(applicant)
v
BRISBANE CITY COUNCIL
(respondent)
FILE NO/S: 2199 of 2017
DIVISION: Planning and Environment Court at Brisbane
PROCEEDING: Application
ORIGINATING
COURT: Planning and Environment Court at Brisbane
DELIVERED ON: 26 October 2017
DELIVERED AT: Brisbane
HEARING DATE: 16 October 2017
JUDGE: Everson DCJ
ORDER: Application dismissed.
CATCHWORDS: PLANNING AND ENVIRONMENT – APPLICATION –
joinder of parties – permissible change application – whether
proposed second respondents are directly affected by the
relief sought
Planning Act 2016 s 311
Sustainable Planning Act 2009 ss 367 and 445.
Planning and Environment Court Rules r 8
Brisbane City Council v Brook [2015] QPELR 63
Dillon v Douglas Shire Council [2004] QPEC 50
Donovan v Brisbane City Council [2016] QPELR 779
Novadeck Pty Ltd v Brisbane City Council [2016] QPELR 951
Project Blue Sky Inc v Australian Broadcasting Authority
(1998) 194 CLR 355; [1998] HCA 28
Zappala Family Co Pty Ltd v Brisbane City Council & Ors
[2014] QCA 147
-- 1 of 8 --
2
SOLICITORS: Connor O’Meara for the applicants for joinder
Brisbane City Legal Practice for the respondent
MinterEllison for the applicant for permissible changes
Introduction
[1] This is an application in pending proceeding whereby Allan David Catterick and
Jennifer Annette Catterick (“the Cattericks”) seek an order pursuant to r 8 of the
Planning and Environment Court Rules 2010 (“PECR”) that they be joined as co-
respondents by election in this proceeding.
[2] In this proceeding, Aveo Clayfield Pty Ltd (“Aveo”) seeks orders changing various
aspects of a development approval for a retirement village on land situated at 469
Sandgate Road at Albion (“the site”). The development approval arises as a
consequence of an order of the court made on 23 July 1999 as changed by subsequent
orders of the court made on 9 June 2000, 10 December 2004, 18 May 2005, 16
February 2015 and 12 February 2016.
[3] Aveo filed its originating application on 21 June 2017. Accordingly pursuant to s
311 of the Planning Act 2016, the Sustainable Planning Act 2009 (“SPA”) continues
to apply to the proceeding.1
The scope of a permissible change application
[4] Aveo asserts that the changes it wishes to make to the development approval are a
permissible change pursuant to s 367 of SPA. It provides:
“367 What is a permissible change for a development approval
(1) A permissible change, for a development approval, is
a change to the approval that would not, because of
the change—
(a) result in a substantially different development;
or
(b) if the application for the approval were remade
including the change—
(i) require referral to additional
concurrence agencies; or
(ii) for an approval for assessable
development that previously did not
require impact assessment—require
impact assessment; or
(c) for an approval for assessable development
that previously required impact assessment—
be likely, in the responsible entity’s opinion,
to cause a person to make a properly made
1 Section 311(2)(a).
-- 2 of 8 --
3
submission objecting to the proposed change,
if the circumstances allowed; or
(d) cause development to which the approval
relates to include any prohibited development.
(2) For deciding whether a change is a permissible
change under subsection (1)(b) or (d), the planning
instruments or law in force at the time the request for
the change was made apply.”
[5] The procedure for changing a development approval is set out in Chapter 6, Part 8,
Division 2, Subdivision 2 of SPA. While s 372 requires that a copy of the request be
given to various “entities” and s 373 gives such an entity the opportunity to indicate
whether it objects to the request to change a development approval, the ultimate
decision is made by the entity which issued the development approval (called the
“responsible entity”), having regard to a number of matters.2
[6] The responsible entity decides the request, taking into account the matters set out
above and the definition of a permissible change in s 367 of SPA. Significantly, third
parties do not have a right to be heard in this process. Where the responsible entity
is the court, as is the case on the facts before me, a copy of the request to change the
development approval is to be given to the assessment manager and any concurrence
agencies for the original application.3 Whilst they have the opportunity to indicate
whether or not they object to the change being made and the reasons for any such
objection, submitters or other third parties are not afforded this opportunity.
The Cattericks and their contentions
[7] The Cattericks own land adjoining the site. They purchased their land well after the
site was approved for use as a retirement village.4 They contend that the changes the
subject of the Aveo application will result in unacceptable traffic impacts on them
including increased vehicle traffic in Highland Street where they and Aveo share a
frontage. They also allege that they will suffer unacceptable amenity impacts
including from overlooking and excessive noise as a consequence of the proposed
changes to the development approval.5
[8] The Cattericks do not have any right to be heard in respect of these concerns, having
regard to the specific provisions of SPA noted above. As the development approval
for a retirement village was issued by the court, the vehicle for changing the
development approval is by filing an originating application, pursuant to the PECR.6
Rule 8 of the PECR relevantly states:
“(1) An originating application must name as a respondent the
entity directly affected by the relief sought.”
2 Sections 374, 375.
3 Section 372(b).
4 Affidavit of Jennifer Annette Catterick, filed 11 September 2017, para 7.
5 Ibid, para 11(f).
6 Section 6.
-- 3 of 8 --
4
[9] The Cattericks assert that they are directly affected by the changes the subject of the
originating application because they “will suffer direct impacts if the proposed
changes are approved, including privacy, amenity, traffic and potential acoustic
impacts”.7
Are the Cattericks directly affected by the relief sought in the originating
application?
[10] In Brisbane City Council v Brook8 this court considered the ambit of r 8 of the PECR
in the context of an originating application brought by the Brisbane City Council
seeking declarations and enforcement orders pursuant to SPA. It was alleged that
premises at 121 Besham Parade Wynnum were not being used lawfully as a house.9
An application for joinder was brought by a number of individuals who owned land
in the vicinity of the respondent who had received Enforcement Notices making
similar allegations.10 The court applied an earlier decision in the following terms:11
“[5] In Dillon v Douglas Shire Council [2004] QPEC 50, the effect
of Rule 8 was considered by Skoien SJDC in the following
terms:
‘The word ‘directly’ is a common word in the English
language and, to my mind, it is well understood. Relevantly,
it means ‘immediately’ or ‘straight away’. If an originating
application seeks an order that a person do something or
refrain from doing something, that person is directly
affected. Here, the council is directly affected because
immediately the court declares the meaning of the
provisions, the council will be bound to administer them in
a way consistent with the interpretation and declarations.
However, the declarations which the court may make, if it
makes any, will not require [the applicant] immediately to
do or not to do anything.’
[6] The same may be said of the proposed second respondents in the
application before me. They are not “directly affected by the
relief sought” and there is no obligation under Rule 8 to name
them as respondents in this proceeding. Accordingly, the first
ground of relief sought by the proposed second respondents
fails.”
[11] A different approach was taken by this court in Donavan v Brisbane City Council12
in circumstances where the applicants for joinder who were owners of neighbouring
7 Outline of Submissions of the Cattericks, para 31(a).
8 [2015] QPELR 63.
9 Ibid at [1].
10 Ibid at [2].
11 Ibid at [5] and [6].
12 [2016] QPELR 779.
-- 4 of 8 --
5
land alleged that they would suffer amenity impacts as a consequence of the relief
sought in a permissible change application. Relevantly the court stated:
“[14] But the test laid down in Dillon is peculiar to the relief therein
sought, namely declaratory relief. The test is not of universal
application whatever the relief sought. That is not the only
manner in which a person may be directly affected by relief
sought. In Dillon, the relief sought was a declaration relating to
certain provisions of the relevant legislation. In determining
whether the appellant was directly affected for the purposes of
rule 8 of the P&E Court Rules, the Court first considered the
nature of the relief sought and concluded that the applicant, was
not directly affected because it was not required to do anything
or refrain from doing anything.
[15] Here, the relief sought is quite different. If granted, it will entitle
the Applicant to proceed with the proposed construction. One
should proceed on the basis that any approval granted will be
pursued and exploited to the intent that construction will take
place. The mere fact that the Applicants for Joinder will not be
immediately required to partake or forgo some course of action,
as the test in Dillon suggests, does not mean they are not directly
affected by the relief sought by the Originating Application.
[16] The Applicants for Joinder have submitted that the proposed
changes, as a result of the permissible change to the development
approval in the Originating Application will directly affect their
use and enjoyment of their property, namely Lot 6.”13
[12] In attempting to reconcile these two approaches, it is necessary to have regard to
principles for construing statutes. They were considered recently by the Court of
Appeal in Zappala Family Co Pty Ltd v Brisbane City Council & Ors14 where in
giving the leading judgment of the court, Morrison JA stated, inter alia:
“The High Court in Project Blue Sky Inc v Australian Broadcasting
Authority said:15
‘[69] … Thus, the process of construction must always
begin by examining the context of the provision that
is being construed.
[70] A legislative instrument must be construed on the
prima facie basis that its provisions are intended to
13 Ibid paras [14] – [16].
14 [2014] QCA 147 at [52].
15 Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355; [1998] HCA 28, at
381, 382, 384 (footnotes omitted).
-- 5 of 8 --
6
give effect to harmonious goals. Where conflict
appears to arise from the language of particular
provisions, the conflict must be alleviated, so far as
possible, by adjusting the meaning of the competing
provisions to achieve that result which will best give
effect to the purpose and language of those provisions
while maintaining the unity of all the statutory
provisions. Reconciling conflicting provisions will
often require the court ‘to determine which is the
leading provision and which the subordinate
provision, and which must give way to the other’.
Only by determining the hierarchy of the provisions
will it be possible in many cases to give each
provision the meaning which best gives effect to its
purpose and language while maintaining the unity of
the statutory scheme.
…
[72] However, the duty of a court is to give the words of a
statutory provision the meaning that the legislature is
taken to have intended them to have. Ordinarily, that
meaning (the legal meaning) will correspond with the
grammatical meaning of the provision. But not
always. The context of the words, the consequences
of a literal or grammatical construction, the purpose
of the statute or the canons of construction may
require the words of a legislative provision to be read
in a way that does not correspond with the literal or
grammatical meaning…”
[13] The legislative framework in SPA only affords a limited right for third parties to be
heard in the court in relation to the impacts of lawful development.16 To participate
in an appeal, it is necessary to have first made a properly made submission in
circumstances where a development application requires impact assessment.17 The
consequences of this in the context of an application for a permissible change were
considered by the court in Novadeck Pty Ltd v Brisbane City Council18 where the
court observed:19
“[18] The applicability of the rules of natural justice is subject to
the relevant statutory law that applies. Pursuant to SPA,
Beriley does not have a right to be heard in the determination
of the application brought by Novadeck. This is
16 Sections 461, 462, 463 and 464.
17 Section 314.
18 [2016] QPELR 951.
19 Ibid at [18].
-- 6 of 8 --
7
uncontentious. It is not the intention of SPA that those
wishing to make a submission in respect of a development
application necessarily have a right to be heard in a
subsequent court proceeding. An obvious example is a code
assessable development application. The exercise which must
be undertaken by the court pursuant to Novadeck’s
application is prescribed by s 367. It is a confined inquiry
which is informed by the subsequent provisions of SPA noted
above. Significant constraints are placed upon the
circumstances in which a change to a development approval
can occur… There is nothing before me which suggests that
the court cannot undertake the task mandated by the
legislative framework when comparing the further changes
the subject of the Novadeck application to the Modified
Approval without including Beriley as a party to the
proceeding... Conversely there is a prospect that the parties to
the Novadeck application would incur additional unnecessary
costs should Beriley be included as a party.”
[14] Conversely, s 445 of SPA makes provision for the PECR. Relevantly it is stated:
“…
(3) The procedures of the court are governed by the rules.
…
(5) The rules are subordinate legislation.”
Applying the principles of statutory construction in Project Blue Sky quoted above, it
is not the legislative intent that the PECR, which are subordinate to the substantive
legislative provisions in SPA, expand the rights of parties who otherwise do not have
a right to be heard in respect of a request to change a development approval. As noted
in Novedeck, the assessing of a permissible change application is a confined enquiry
which is informed by the relevant provisions of SPA. The fact that the responsible
entity, pursuant to s 369 of SPA is the court, does not warrant an interpretation of r 8
of the PECR which entitles a third party, who does not otherwise have a right to be
heard in respect of this type of application, such an opportunity simply because the
procedure for making the request to change the development approval necessitates
the filing of an originating application. Rule 8 is subordinate to the relevant
provisions of SPA. It does not confer rights not contemplated by them. A literal
interpretation of r 8 which may suggest otherwise should be avoided.
[15] Moreover, a factual analysis of the consequences of the relief sought in the originating
application does not bear out the submission of the Cattericks that they are directly
affected by the relief sought in the originating application. Should Aveo be successful
in obtaining the relief sought in the originating application, this will result in a change
to the conditions of approval which apply to the site. Aveo will be directly affected
as its development rights will have changed. The respondent will be directly affected
as it will be bound to administer the development approval in its changed form.
-- 7 of 8 --
8
However, until any building work ultimately takes place pursuant thereto, the traffic
and amenity affects alleged by the Cattericks will not arise. There is therefore an
intermediate step between a court order approving a request to change a development
approval and any adverse impacts being experienced by third parties who own
adjoining land. Therefore, on the facts before me the Cattericks are not directly
affected by the relief sought in the originating application. This is made abundantly
clear when it is considered that not all development approvals are acted upon.
Conclusion
[16] It does not accord with the legislative framework of SPA that r 8 of the PECR be
interpreted in such a way that it gives the Cattericks a right to be heard in respect of
the originating application which is not contemplated when a request to change a
development approval is made pursuant to SPA.
[17] On the facts before me, the Cattericks are not an entity directly affected by the relief
sought in the originating application in any event.
[18] To the extent that Donovan suggests otherwise, it ought not be followed.
[19] I dismiss the application for joinder.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2017/060