1770 Nominees Pty Ltd v Gladstone Regional Council [2017] QPEC 59 (2018) QPELR 136
PLANNING & ENVIRONMENT COURT OF
QUEENSLAND
CITATION: 1770 Nominees Pty Ltd v Gladstone Regional Council [2017]
QPEC 59
PARTIES: 1770 NOMINEES PTY LTD
(applicant)
v
GLADSTONE REGIONAL COUNCIL
(respondent)
FILE NO/S: D48 of 2017
DIVISION: Planning and Environment
PROCEEDING: Application
ORIGINATING
COURT: Planning and Environment Court, Maroochydore
DELIVERED ON: 25 August 2017 (orders)
25 October 2017 (reasons)
DELIVERED AT: Maroochydore
HEARING DATE: 25 August 2017
JUDGE: Long SC DCJ
ORDER: Application granted
CATCHWORDS: ENVIRONMENT AND PLANNING – APPLICATION –
Where an application was filed seeking orders, pursuant to s
440 Sustainable Planning Act 2009 (“SPA”), excusing non-
compliance with a provision of that Act, in particular, in
relation to an approval for material change of use that has
lapsed and to effectively grant an extension of that approval –
Whether it is appropriate to grant such relief
LEGISLATION: Planning Act 2016 s 311(2)(a)
Sustainable Planning Act 2009 ss 341(1); 341(4); 341(7);
383; 383(3)(d); 383(4); 440
COUNSEL: A Williams (sol) for the applicant
J Brennan (sol) for the respondent
SOLICITORS: p&e Law for the applicant
MRH Lawyers for the respondent
-- 1 of 4 --
2
[1] What follows are the reasons for the findings and orders made in this matter, on 25
August 2017.
[2] By originating application filed on 5 May 2017, the applicant sought declarations (or
findings) and orders in respect of an issued development permit, allowing a material
change of use (marina berths) for land situated at 535 Captain Cook Drive Seventeen
Seventy, described as Lot 14 on SP 210496 and Lots 29 and 30 on SP 234769.
[3] The necessity for the application is to be understood from the following
circumstances:
(a) In or around September 2007, the applicant lodged a code assessable
material change of use application, under the now superseded Miriam
Vale Shire Planning Scheme, for eight additional berths in a marina
that had been operated as a family business for approximately 30
years;
(b) On 17 December 2007, the applicant entered a lease of Lots 29 and 30
on SP 234769 for use as a marina;
(c) The respondent approved the development, subject to conditions, on
19 December 2008 and after negotiations and on 22 April 2009, the
respondent issued a negotiated decision notice, approving the
development, subject to conditions. That approval was for the
standard currency period of four years, in accordance with s 3.5.21 of
the Integrated Planning Act 1997;
(d) Accordingly, the first change of use under the approval was to occur
before 22 April 2013. However and after approving a change to the
approval, on 13 September 2011, the respondent approved the
following extensions to the approval:
(i) On 24 April 2013, an extension to 22 April 2014; and
(ii) On 21 February 2014, an extension to 22 April 2015;
(e) On 26 February 2014, the applicant applied for relevant operational
works permits for the purpose of effecting the material change of use,
which, on 15 August 2014, were granted by the respondent, with a
currency period of two years until 15 August 2016.
[4] Accordingly and because they were not applied for within two years of the start of
the relevant period, the operational works permits were not within the meaning of
-- 2 of 4 --
3
“related approvals” in s 341(7) of the Sustainable Planning Act 2009 (“SPA”), s
341(4) of the SPA was not engaged and the approval for the material change of use
lapsed on 22 April 2015. The uncontested evidence is that this occurred as the
applicant misunderstood the effect of the operational works approval and neglected
to apply for a further extension of the approval for material change of use. And this
was notwithstanding that the operational works continued to completion around
November 2016 and in accordance with permits obtained under the Marine Parks
Regulation 2006, so as to enable berth extension and dredging, and that the use then
commenced.
[5] As is not unusual in such circumstances, the applicant applied, pursuant to s 440 of
SPA, for orders excusing the non-compliance with s 341(1) of SPA (in that the first
change of use under the approval for the material change of use had not occurred
before that approval had expired) and to effectively grant an extension of that
approval, as might have been granted by the respondent, upon application made
pursuant to s 383 of SPA, before that approval had lapsed.
[6] When that application came before the Court for hearing, on 2 June 2017, it was
appropriately recognised that the discretionary factors favouring the relief that was
sought, included that:
(a) This would be for an approval to extend an existing and unique loading
facility for commercial and private vessels in its locality and where
there was increasing demand for marina berths;
(b) In circumstances where the delays in carrying out the development
before the approval lapsed, were mainly due to changing economic
circumstances and the process of operational works application and
assessment and that significant additional costs added upon those
already incurred in carrying out the completed operational works,
would be incurred if a new development application was required. And
that this would be likely to be a substantial financial burden on the
applicant;
(c) The respondent was in favour of the relief sought and was prepared to
consent to the application; and
(d) The application was necessary due to misunderstanding of the effect
of the operational works approval and oversight of the need for a
-- 3 of 4 --
4
further application to the respondent in respect of the currency of the
approval for the material change of use.
[7] However and at the hearing on 2 June 2017, it was identified that the material then
placed before the Court, did not include any indication of the consent of the owners
of the leased land, Lots 29 and 30 on SP 234769, and as would have been necessary
to obtain the respondent’s consent pursuant to s 383(3)(d). Accordingly and as there
was no application of the kind referred to in s 383(4), and at the applicant’s request,
this application was adjourned to a date to be fixed for the obtaining of the necessary
additional material.
[8] Such consent was ultimately obtained, after some requirements of the owner of the
leased land, were satisfied. But and as it transpired, when the matter again came
before the court for further hearing, on 25 August 2017 the SPA had been replaced
by the Planning Act 2016, the latter Act relevantly coming into effect on 3 July 2017.
Notwithstanding that eventuality and pursuant to s 311(2)(a) of the Planning Act
2016, the application remained to be decided pursuant to the provisions of SPA and
to which reference has already been made. And for these reasons and on 25 August
2017 the following findings and orders were made:
“UPON THE COURT BEING SATISFIED that the requirements
of the Sustainable Planning Act 2009 have been satisfied in relation to
service of this application,
AND UPON THE COURT FINDING that there has been non-
compliance with Section 341 of the Sustainable Planning Act 2009
because the first change of use under the material change of use
approval (Marina Berth) (DA/4414/2007) did not occur within the
relevant period,
IT IS ORDERED THAT
1. The non-compliance is excused.
2. The relevant period for the material change of use approval be
extended to 1 December 2016.”
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2017/059