Boral Resources (Qld) Pty Ltd v Gold Coast City Council [2017] QPEC 23
PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND
CITATION: Boral Resources (Qld) Pty Ltd v Gold Coast City Council
[2017] QPEC 23
PARTIES: BORAL RESOURCES (QLD) PTY LTD (ACN 009 671
809)
(appellant)
v
GOLD COAST CITY COUNCIL
(respondent)
FILE NO/S: 3084/2014
DIVISION: Planning and Environment Court, Brisbane
PROCEEDING: Hearing of appeal
DELIVERED ON: 4 May 2017
DELIVERED AT: Brisbane
HEARING DATE: 17 October 2016 – 25 November 2016, 30 January – 3
February 2017 and 22 – 23 February 2017.
JUDGE: RS Jones DCJ
ORDER: 1. The appeal is dismissed.
2. If necessary I will hear from the parties as to any
consequential orders.
CATCHWORDS: APPEAL AGAINST REFUSAL OF DEVELOPMENT
APPLICATION – appeal against a refusal by the respondent
of a development permit for a quarry in the Gold Coast
hinterland – where proposed development involved
development of a large hard rock quarry – where subject land
had been identified for quarrying purposes under a number of
State planning documents – where subject land declared a
key resource area under State planning policies – where at the
time the development application was lodged the
respondent’s 2003 town planning scheme was in force –
where under that planning scheme the subject land was
subject to various designations – part Urban Residential Land
Use Theme; part Park Living Land Use Theme – part Open
Space/Nature Conservation Land Use Theme – where under
the relevant Structure Plan Area the subject land located
partly in Urban Residential Precinct, part Park Living
Precinct and part Open Space/Nature Conservation Precinct –
-- 1 of 127 --
2
where under respondent’s 2016 planning scheme subject land
subject to numerous designations.
WHERE DEVELOPMENT RAISED NUMEROUS ISSUES
– traffic – dust – noise – blasting vibration – geology – air
quality – traffic – ecological/environmental issues –
economic and community need and town planning.
CONFLICT WITH PLANNING SCHEME – where proposed
development said to be in conflict with respondent’s planning
schemes.
NEED – where evidence that there was a need for subject
development – whether that need could be satisfied by
existing and/or other quarries sources – whether in
circumstances where there was conflict with the planning
scheme sufficient grounds existed to warrant approval
notwithstanding conflict.
Environmental Protection Act 1994 (Cth)
Environmental Protection and Biodiversity Conservation Act
1999 (Cth)
Integrated Planning Act 1997 (Qld)
Local Government (Planning and Environment) Act 1990
(Qld)
State Development & Public Works Organisation Act 1971
(Qld)
Statutory Instruments Act 1992 (Qld)
Sustainable Planning Act 2009 (Qld)
Water Act 2000 (Qld)
Alcan (NT) Alumina Pty Ltd v Commissioner of Territory
Revenue (Northern Territory) (2009) 239 CLR 27
Australian Capital Holdings Pty Ltd v Mackay City Council
& Ors [2008] QCA 157
Elan Capital Corporation Pty Ltd & Anor v Brisbane City
Council & Ors [1990] QPLR 209
Grosser v Council of the City of Gold Coast [2001] QCA 423
Holts Hill Quarries Pty Ltd v Gold Coast City Council [1999]
QPELR 415
Isgro v Gold Coast City Council [2003] QPELR 414
Leda Holdings Pty Ltd v Caboolture Shire Council (2006)
QCA 271
Lockyer Valley Regional Council v Westlink Pty Ltd (2011)
185 LGERA 63
-- 2 of 127 --
3
Mackay v Dick (1881) 6 App Cas 251
Meridien AB Pty Ltd v Jackson [2013] QCA 121
Neilsens Quality Gravels Pty Ltd v Brisbane City Council
[2006] QPELR 709
Newing v Silcock [2010] QPELR 692
Parklands Blue Metal Pty Ltd v Sunshine Coast Regional
Council [201] QPELR 479
Prime Group Properties Ltd v Caloundra City Council & Ors
(1995) QPLR 147
Quinn Villages Pty Ltd v Mulherin (2006) QCA 433
Savage v Cairns Regional Council (2016) 214 LGERA 192
Sellars Holdings Ltd v Pine Rivers Shire Council [1988]
QPLR 12
Watts & Hughes Pty Ltd v Brisbane City Council 1998]
QPELR 273
Weightman v Gold Coast City Council [2003] 2 Qd R 441
Woolworths Ltd v Maryborough City Council (No 2) [2006] 1
Qd R 273
Yu Feng Pty Ltd v Brisbane City Council (2007) 156 LGERA
399
Zappala Family Co Pty Ltd v Brisbane City Council (2014)
201 LGERA 82
COUNSEL: Mr D Gore QC with Mr J Lyons for the appellant
Mr R Litster QC with Mr S Fynes-Clinton for the respondent
SOLICITORS: Hopgood Ganim for the appellant
McCullough Robertson for the respondent
-- 3 of 127 --
4
Index
Introduction and background.......................................................................................... 5
The proposal ................................................................................................................... 8
The planning and development history to date............................................................... 12
The lay witnesses ............................................................................................................ 14
Geology .......................................................................................................................... 20
Blasting, air quality and noise ........................................................................................ 25
Traffic ............................................................................................................................. 34
Civil engineering ............................................................................................................ 38
The white bellied sea eagle and koalas........................................................................... 40
Visual Amenity............................................................................................................... 51
Hydrology, water quality, groundwater and soils .......................................................... 61
Terrestrial ecology .......................................................................................................... 70
Aquatic ecology .............................................................................................................. 74
The Planning documents and conflict ............................................................................ 79
Sufficient grounds .......................................................................................................... 106
Quarry management ............................................................................................ 112
Economic evidence .............................................................................................. 119
Conclusions .................................................................................................................... 126
-- 4 of 127 --
5
[1] This proceeding is concerned with an appeal against the respondent’s decision to
refuse the appellant’s development application for the establishment of a quarry at
Burleigh. For the reasons set out below the orders of the court are:
1. The appeal is dismissed.
2. If necessary I will hear from the parties as to any consequential orders.
The parties to the proceeding
[2] Initially, a number of parties elected to become co-respondents in the proceeding, all
of whom were opposed to the proposal. These included Stop the Gold Coast Quarry
Association Inc., Mr I Kennedy, Hammercall Pty Ltd and Gwinganna Lifestyle
Retreat and Spa Pty Ltd.
[3] Mr Kennedy and Gwinganna Lifestyle Retreat and Spa withdrew as parties.
Following other court proceedings which it is not necessary to dwell on here,
Hammercall Pty Ltd also withdrew. Following opening addresses by Mr Gore QC for
the appellant and Mr Litster QC for the respondent, Mr Knox, the solicitor for Stop
the Gold Coast Quarry Association, sought leave for that association to withdraw.
After hearing submissions leave was granted.
Location of the site
[4] The subject land is described as lot 105 on SP 144 215 and comprises an area of 216.7
ha. The land is bisected by lot 901 on RP 907 357. Lot 901 is a reserve (fire track)
administered by the respondent and runs through the western portion of the land
between Tallebudgera creek road and Barden Ridge Road to the west.1 Of the 216.7
ha, the area of land which would be the subject of actual quarrying and associated
infrastructure activities is approximately 65 ha, representing approximately 30 per
cent of the land. The balance of the land would be used for buffering purposes and
the quarrying activities will not interfere with the reserve contained in lot 901. The
land is located west of Palm Beach and west of the Pacific Motorway in the
Tallebudgera/Tallebudgera Valley/Reedy Creek area.2
[5] While, broadly speaking, the land is heavily vegetated with regrowth, it has been the
subject of significant man-made disturbance including that of illegal four-wheel-drive
1 See generally Exhibit 1 p 17.
2 Ibid p 6.
-- 5 of 127 --
6
activity. Not surprisingly, given its location, the land is, to a significant extent,
surrounded by residential development. These developments include more
conventional lot sized subdivisions at Kingsmore Estate, Stocklands Observatory
Estate, Old Burleigh Town and larger rural residential lots in the Tallebudgera Creek
area. To the east of the land and the Pacific Motorway is an existing quarry also
owned and operated by the appellant, a waste management site and to the north-east
an industrial area.3
[6] The topography varies with levels ranging from RL 10m AHD to RL 150m AHD.
The primary frontage is to Old Coach Road which is:
(a) A council-owned arterial road; and
(b) A Key Resource Area (Transport Route).
The secondary frontage is to Tallebudgera Creek Road which is a classified scenic
tourist route.
[7] The land is currently vacant but in the past had been subject to a number of historic
rural uses including grazing and a nursery. By the early 1970s it had been cleared4
but is now extensively covered by mature regrowth.5
[8] Of particular significance is that the land is traversed by a prominent ridgeline that
extends from the Springbrook Range to Burleigh Heads. This ridge is a significant
landform feature in the local context. Three secondary ridgelines also transect the
land and it is also intersected by a number of waterways and at least two watercourses
as defined by the Water Act 2000.
[9] The locality was described by the town planners relied on by the parties, Mr Schneider
for the appellant and Mr Buckley for the respondent, in the following terms:6
“The locality is set amongst vegetated foot hills and the ridges of the
hinterland and is characterised by a mosaic of land uses amongst
fragmented patches of vegetation and open space.
The mosaic of established land uses in the immediate vicinity of the
site comprises:
3 Ibid pp 6, 7, 8 and 11.
4 Ibid p 30.
5 Ibid p 13.
6 Exhibit 29A Town Planner’s joint expert report (JER) Part 1 at p 13.
-- 6 of 127 --
7
(a) Urban residential development;
(b) Major residential communities…;
(c) Educational facilities;
(d) Rural residential development;
(e) Small-scale industrial activities;
(f) A convenience-based retail centre together with a number of
small-scale retail businesses;
(g) Some areas of rural residential development;
(h) Vacant land; and
(i) Patches of open space.
In addition, at a broader scale, the areas of Reedy Creek, Tallebudgera
Valley and West Burleigh are characterised by the presence of:
(a) Pockets of low density residential development
amongst patches of open space
(b) Established rural residential areas…;
(c) Rural activities throughout Tallebudgera Valley;
(d) The established industrial area of West Burleigh;
(e) The existing West Burleigh quarry;
(f) The former quarry now used as the Reedy Creek
Recycling Centre.
The presence of the Pacific Motorway and related service roads,
access ramps and interchanges also affects the character of the locality.
…”
[10] I consider that to be, broadly speaking, an accurate description. However, the locality
west of the highway has a more residential feel or character than that immediately to
the east.
[11] Before preceding further, I should deal with the participation in the joint expert report
(JER) preparation by Mr Brown. Mr Brown was the town planner retained by the Stop
The Gold Coast Quarry Association, the first co-respondent by election.
Notwithstanding the application to withdraw from the proceeding, that association
sought to have me receive the town planning evidence of Mr Brown to support the
respondent’s opposition to the quarry. After hearing submissions by Mr Gore and Mr
Litster I ruled that I would not receive any town planning evidence from Mr Brown
and, insofar as the joint town planning reports were concerned they should be read as
expressing the opinions and conclusions of Mr Schneider and Mr Buckley only. That
is, Mr Brown’s contribution to those reports was ignored, save for where Mr Buckley
-- 7 of 127 --
8
agreed with and adopted his observations and/or opinions.7 That approach was agreed
to by both Mr Gore and Mr Litster.
The proposal
[12] Numerous aspects of the proposed development are discussed in detail when
addressing the evidence of the expert witnesses relied on by the parties. However, for
introductory purposes the following description is sufficient. The disturbance
footprint will comprise an area of approximately 65 ha and be surrounded by a
vegetated buffer of approximately 152 ha.8
[13] The expected life of the quarry is at least 40 years and could extend beyond 60 years
depending on demand. The extracted material is hard rock known as meta-greywacke.
It is intended that the proposed quarry would replace the existing quarry owned and
operated by the appellant which has a current expected operational life of less than
10 years. According to Mr Cooper, general manager of capital projects and project
sponsor of Boral Australia,9 the life of this quarry could be as low as six years.
[14] Current material available for quarrying at the West Burleigh Quarry is estimated at
about 7.5 Mt.10 While at periods of peak demand (e.g. 2008), extraction may have
approached 1.9 Mt p.a., more typically extraction rates were in the order of 1 Mt p.a.
to 1.4 Mt p.a.11 and as low as about 0.96 Mt p.a. in 2015/2016. The proposed quarry
envisages 2 Mt p.a. but it was accepted that actual output was very much demand
driven.
[15] Access to and from the quarry will be via Old Coach Road which, while a designated
haulage route, would require extensive upgrading to accommodate heavy haulage
vehicles. The quarry will not be connected to the respondent’s trunk water, sewerage
or storm water infrastructure. During the establishment and construction phases the
proposed quarry would generate a total of 246 full-time equivalent positions and, once
developed and operational, 24 full time equivalent person positions.
7 T30-78 ll 17-45.
8 Exhibit 1 pp 3 and 15.
9 Exhibit 118, para 32.
10 E.g. Exhibit 6 V7, p 3933.
11 Exhibit 25, p 60.
-- 8 of 127 --
9
[16] In a report prepared by Lambert and Rehbein, the operational processes were
described in the following terms:12
“Overall, the proposed Gold Coast Quarry’s processing plants and
supporting heavy mobile equipment (HME) will comprise:
Mobile crushing plants
…
Fixed plant
…
Mobile fleet
…
There will be a range of equipment on the site for various periods of time. This
equipment includes, amongst others, the following:
• Excavators;
• Graders;
• Front-end loaders;
• Bulldozers;
• Compactors;
• Articulated dump trucks;
• Water trucks;
• Haulage trucks; and
• Cranes.
The quarrying process commences with a survey of the rock face and
bench to be developed (by drilling and blasting)…
Once the rock has been blasted, fragmented rock will be loaded from
the pit floor onto haul trucks, whereas any larger rock fragments
(“oversize”) will typically be broken by a rock breaker before loading.
The load and haul fleet will generally be operated continuously during
the operating hours of the quarry, in order to maintain continuity of
supply for processing.
The primary stage of processing involves the use of a jaw crusher and
vibratory screens, with crushed product being held in an interim
stockpile called a ‘surge pile’. From this stage, material will be
conveyed to several downstream stages of crushing and screening
equipment. After processing, the material will be conveyed to
individual product stockpiles. The processing plant, including primary
and secondary crushers (and screening to separate dust and
aggregates) will be located within the plant and infrastructure area,
near the individual product stockpiles.
The quarry materials are then either loaded directly by front-end
loader… from the stockpiles, or via overhead storage bins at the
plant… to road haulage trucks. The road haulage trucks then proceed
12 Exhibit 6 V3, pp B1327-1328.
-- 9 of 127 --
10
across the weighbridge and through the wheel wash before exiting the
site to deliver quarry materials to the market.”
[17] The quarried material would be used to manufacture concrete, asphalt, drainage
material, road base, bricks, pavers and other products for use in the building and
construction industries. A significant proportion would be used by other Boral assets
including the manufacturing of asphalt and concrete. More will be said about these
matters when addressing the question of the “need” for the quarry.
[18] The proposal would evolve over four distinct stages: Establishment, Construction,
Development and Operation (described in various reports as phases E, C, D and Q).
Some of the details associated with the establishment, construction and development
phases are set out in the Lambert and Rehbein report but it is unnecessary for the
purposes of this proceeding to deal with them in any detail except when dealing with
the issues in dispute.13 Of particular significance though are the phases associated
with the actual quarrying operations. Over the likely life of the quarry, approximately
40 to 60 years plus, it will involve a number of benches14 excavated from at or about
natural ground level to a depth of –RL 66M.15
[19] The life of the proposed quarry is a function of its estimated approved recoverable
resource of 79 Mt.16 The reference to 79 Mt of “resource” needs to be treated with a
degree of caution as it includes some 13 Mt – 14 Mt of overburden,17 the value of
which was very much dependent on market circumstances.
[20] Evidence of Mr Norling, the economist relied on by the appellant which I accept,
indicates that on average, demand from the quarry would grow from about 1.33 Mt
p.a. in 2026 to about 1.5 p.a. in 2031.18 With projected population growth, output at
or about 1.9 Mt p.a. might be reached.19 His uncontradicted evidence was that, even
ignoring any multiplier effects, the value of the resources in 2016 dollar terms was in
the order of $1.4 - $1.5 billion, a matter emphasised by Mr Gore in his final
submissions.20
13 Exhibit 6 V3 pp B1330-1340.
14 Shown conceptually in Exhibit 6 V4 p B2373.
15 Exhibit 6 V3 p B1339.
16 Exhibit 25, p 60.
17 Exhibit 6, V2, pp 737-741: V3 pp 1338-1340.
18 Exhibit 25, p 4, Table 14: Exhibit 167.
19 T25-47-48, ll 17-20 per Mr Norling.
20 T34-62, L 25; see also T26-42 ll 22-27.
-- 10 of 127 --
11
[21] The quarrying phases are described as phases Q1, Q2, Q3, Q4 and Q5. For
approximately the first 25 years of quarrying they will be significantly screened from
view by a series of ridgelines described as R3, J, J4, K and I.21 However, at or about
the 25 to 30 year mark through to the end of the quarry life (phases Q3-Q5) the quarry
benches will become more exposed as the ridge lines J and J4 are quarried. A material
part of ridges J4 and K will be levelled much earlier during the establishment and
construction phases.22 The significance of this is discussed in more detail below when
dealing with the issue of visual amenity.
[22] During the establishment, development and construction phases work would be
conducted on site as follows:
Access (excluding maintenance) 6.00am to 6.00pm Monday-Saturday
Construction activities and site works 6.30am to 6.00pm Monday-Saturday
Sales and dispatch 6.30am to 6.00pm Monday to Saturday
Mobile crushing and screening 7.00am to 6.00pm Monday to Saturday
Maintenance 24 hours Monday to Saturday and 8.00am to 6.00pm Sundays
Blasting 9.00am to 5.00pm Monday to Friday.
During the quarrying phases the operational hours will be:
Access (general operations) 6.00am to 6.00pm Monday to Saturday
Extraction 6.30am to 6.00pm Monday to Saturday
Crushing and screening 6.30am to 6.00pm Monday to Saturday
Sales and dispatch 6.30am to 6.00pm Monday to Saturday
Maintenance 24 hours Monday to Saturday and 8.00am to 6.00pm Saturdays
Blasting 9.00am to 5.00pm Monday to Friday.
[23] Blasting for quarrying purposes (i.e. phases Q1 to the end of Q5) would occur, save
perhaps for exceptional circumstances, once a week and at a set time to establish a set
routine or pattern for those who might in some way be affected by the blasting.23
During the establishment and construction phase this blasting would occur as and
when required (i.e. irregularly) however the size of the blasts would be materially
smaller and of a shorter duration.24
21 See Exhibit 1 P9.
22 E.g. see Exhibit 64, p 2.
23 T6-33, L 25-37.
24 T6-25, L 32-45.
-- 11 of 127 --
12
The planning and development history to date
[24] The land has been identified as a Key Resource Area (“KRA”) for a long time. Old
Coach Road has also been identified as a haulage route. The appellant has already
gained a number of approvals relevant to the development of a quarry and, for all
intents and purposes, approval from the respondent is the final step in the approval
process.
[25] On or about 1 December 2010, the appellant referred the project to the
Commonwealth Minister for the Environment for a “Controlled Action” decision
under the Environment Protection and Biodiversity Conservation Act 1999 (Cth). On
23 January 2014, the Minister for the Environment issued his approval subject to
conditions.25 The proposed quarry was declared a Significant Project (now called a
Coordinated Project) and was the subject of a comprehensive environmental impact
assessment between 27 August 2010 and 20 December 2013. On 20 December 2013,
the Coordinator-General for the state of Queensland issued his evaluation report
recommending that the development proceed subject to conditions.26
[26] On 9 May 2014, the appellant submitted an application for an Environmental
Authority for prescribed Environmentally Relevant Activities to the Department of
Environment and Heritage Protection (“DEHP”). On 16 July 2014 the DEHP
approved the application and issued an Environmental Authority on 16 July 2014
subject to conditions.27
[27] According to the appellant:28
“The fact that these other approvals were granted after substantive
assessment processes is not determinative… but is a relevant factor
and would give the court both comfort and context. This is particularly
so given that the outcome of these application processes is that
conditions have been imposed to mitigate the effects of the quarry and
must be complied with if the quarry project is approved by the
court…”
[28] That these approvals exist and the extent of the scrutiny involved is relevant and does
provide meaningful support for the proposal. In this context, it is significant that the
25 Exhibit 7, Tab 3.
26 Exhibit 5, V 8, Tab 13.
27 Exhibit 8, V 6, Tab 3.
28 Written submissions, p 5, [8]-[9].
-- 12 of 127 --
13
Coordinator-General (COG) process is not just a relevant consideration that “may”
be taken into account, it is a matter “regard” must be had to in the assessment
process.29 In this context, I also accept the submission that, to a very significant
extent, the “extrinsic material” works in favour of the proposal. However, as the
appellant acknowledged, it is in no way “determinative”.
[29] A development permit for a material change of use was lodged with the respondent
on 9 May 2014. Thereafter, it engaged a number of independent experts to carry out
a review and assessment. The consultants retained addressed matters including visual
amenity, development engineering, noise and air quality, traffic and transport,
geological and quarry operations, ecological issues, economic need, community need
and town planning and social planning. The town planners then retained by the
respondent, Buckley Vann, prepared a report for the respondent recommending
approval of the quarry project subject to 100 conditions.30 A relevant officer of the
respondent thereafter prepared a report which, among other things, recommended that
the development application be approved subject to the conditions proposed in the
Buckley Vann report.31 Notwithstanding that recommendation, on 8 July 2014 the
respondent’s City Planning Committee met and recommended that the development
application be refused. On 11 July 2014 at a full council meeting, the respondent
resolved to refuse the development application.32 The council’s decision notice set
out 12 reasons for refusal.33 On 11 August 2014 the appellant commenced its appeal.
[30] In their JER the town planners identified 9 “town planning issues in the Appeal”:34
“(a) The planning intent for the site;
(b) Whether the proposed development will have acceptable impacts on
the amenity of the local area;
(c) Whether the proposed development will maintain the scenic amenity
values, image and form of the city;
(d) Whether the proposed development will have acceptable impacts on
the environmental values of the city and the site;
(e) Whether the proposed development will have acceptable traffic
impacts;
(f) Whether there is a planning need for the proposed development;
29 S 314(3) SPA: s 37(1)(d) State Development Act.
30 Exhibit 6 V 7, Tab 4, pp B4981-5358 and B5089-5132: Exhibit 203A, 203B.
31 Exhibit 6 V 8, Tab 4, pp B4927-4980.
32 Exhibit 6, V 8, Tab 5, pp B5360-5363.
33 Exhibit 6, V8, Tab 6, pp B5366-5368.
34 Exhibit 29A, Part 1, p 18.
-- 13 of 127 --
14
(g) Whether the proposed development is consistent with reasonable
community expectations;
(h) Whether the proposed development complies with the relevant
planning instruments, draft planning instruments and later planning
instruments; and
(i) Whether there are sufficient grounds to justify the approval of the
proposed development despite any identified conflict with the
relevant planning provision.”
[31] Numerous ecological/environmental issues were raised by other experts relied on by
the parties, some of which were closely related to those raised by the town planners,
others were not. The extent of the issues in dispute were identified in an 81 page
document.35
[32] At the time the development permit was applied for the town planning scheme in
place was the respondent’s City Plan (CP 2003). At the time of the hearing of the
appeal, that plan had been replaced with City Plan 2016 (CP 2016).
The lay witnesses
[33] The appellant and the respondent called a number of non-expert witnesses in support
of their respective cases. While those witnesses relied on by the respondent were not
required for cross-examination, those of the appellant were. The appellant’s witnesses
were Mr Grimwood,36 Mr Moreton,37 Mr Donaldson,38 and Mr Bailey.39 Each of
those witnesses were successful businessmen who had longstanding commercial
relationships with the appellant. While the nature of their businesses varied (by way
of example the business of Mr Moreton could be described as being quite modest
whereas, on the other hand, the operations of Messrs Bailey and Grimwood involved
major construction projects, including the construction of seawalls), each of them saw
their business relationship with Boral and, in particular, its operations at Burleigh to
be an important part of their business. Indeed the evidence of Mr Grimwood was that
his company purchased materials from the West Burleigh quarry on virtually a daily
basis and, on average, at an expenditure rate of about $70,000 per month. I found all
four of these witnesses to be honest, forthright and reliable.
35 Exhibit 9.
36 Statement Exhibit 158.
37 Exhibit 159.
38 Exhibit 160.
39 Exhibit 161.
-- 14 of 127 --
15
[34] The evidence of these witnesses, as is indeed the case concerning the lay witnesses
relied on by the respondent, is far from determinative but nonetheless relevant. The
evidence of these four gentlemen was also largely unsurprising. The thrust of their
evidence, when looked at in total, was that while none of them would go out of
business if Boral’s operations in the West Burleigh area ceased, the closure of the
existing quarry without a replacement nearby could have a number of negative
impacts on their businesses. All of these witnesses readily agreed with Mr Litster’s
proposition that their businesses were highly competitive and that in securing future
business they would have to, to use Mr Litster’s term, “sharpen their pencils” when
quoting for contracts. That may well be so, but I accept the evidence to the effect that
the West Burleigh quarry, and therefore most probably the replacement quarry,
produces high quality martial, was very competitive in its pricing and, perhaps more
importantly, was, depending on the location of the project, a convenient and
economical source of quarry product.
[35] While they also readily accepted that alternate quarry sources were available, there
seems little room for doubt that any additional haulage costs would be passed onto
the end consumer. In this context I note that the evidence of these four witnesses was
consistent with evidence given by Mr Gray and Mr Reed, the quarry “management”
witnesses relied on by the parties. Their evidence was to the effect that two of the
major concerns facing the operation of a successful quarry were haulage distances
and the management of overburden.
[36] Not surprisingly, these witnesses were also concerned with the prospect of there being
an increase in the cost of purchasing at least some quarry product due to the reduction
in competition. In my view, while the evidence of these four gentlemen on this aspect
was far from compelling, it was nonetheless consistent with the evidence given by
Mr Cooper, Mr Gray and Mr Norling when addressing the question of need.
[37] Turning then to the evidence of the lay witnesses relied on by the respondent,40 their
evidence was unchallenged and raised a number of expected and legitimate concerns.
Mr Schneider, the town planner called by the appellant, readily accepted that many
40 Mr Brown (Exhibit 182), Mr Stahnke (Exhibit 183), Mr Marynycz (Exhibit 184), Mr Laufer (Exhibit
185), Mr Smith (Exhibit 186), Ms Paul (Exhibit 187), Mr Brisbane (Exhibit 188), Mr Macgregor
(Exhibit 189), Mr Gishkori (Exhibit 190) and Ms McClenahan (Exhibit 191).
-- 15 of 127 --
16
of the concerns they voiced were “rational”. In no particular order of importance, their
concerns centred around the following issues:
The physical impacts of quarry operations and, in particular, noise (including
blasting), blast vibration, dust and air quality generally.
The traffic noise and dust problems created by the haulage trucks.
The added congestion and increased risk of accidents on Old Coach Road
caused by the introduction of haulage traffic.
The inconvenience caused during the upgrading of Old Coach Road under
either upgrading option. That is, with a total road closure of up to 3-4 months
or keeping Old Coach Road open but with restricted traffic movements for
up to 10-11 months.
The impact on wildlife and, in particular, bird life, koalas and wallabies
caused by the removal of vegetation and/or the operation of the quarry.
Impact on land values.
[38] Only two of these lay witnesses expressly referred to the loss of amenity caused by
the quarry being physically visible.41 That of course does not mean that visibility was
of such limited concern as discussed below under the heading “Visual Amenity.”
[39] As will become apparent, the impacts on amenity resulting from noise, air quality and
blasting vibration are capable of being and will be kept within all the applicable laws,
policies and standards. Non-compliance in this regard could of course be fatal to a
development application. On the other hand, compliance need not be determinative.
[40] The concept of amenity is a wide and flexible one not necessarily determinable by
reference to the evidence of experts alone. In Prime Group Properties Ltd v
Caloundra City Council & Ors42 Skoien SJDC said:
“Amenity
I have decided that, as separate components, no unreasonable adverse
impact on the nearby residents in the form of noise, light or unpleasant
odours would be caused by this development. But the concept of
amenity is far broader than that. In Broad v Brisbane City Council &
Anor (1986) 2 Qd R 317 at 326 de Jersey J. said:- ‘There is no doubt
that the concept of amenity is wide and flexible. In my view it may in
a particular case embrace not only the effect of a place on the senses
41 Exhibit 190 at para [32] and Exhibit 185 at para [11]. Statements of Mr Gishkori and Mr Laufer.
42 [1995] QPLR 147.
-- 16 of 127 --
17
but also the resident's subjective perception of his locality. Knowing
the use to which a particular site is or may be put may affect one's
perception of amenity.’
…
The resident/objectors gave evidence of their actual perception and the
fears they held of the effect of the development. Their fears were, I
thought, sometimes over-stated, even unlikely. However I accept that
the actual perception which the residents claimed to have is genuinely
held. That perception is one of residential amenity. Provided that
perception can be seen to be reasonably held in an objective sense, it
should be given considerable weight.
…
In deciding what are the reasonable perceptions of amenity of the
residents I am conscious that I must apply "the standards of comfort
and enjoyment which are to be expected by ordinary people of plain,
sober and simple notions not affected by some special sensitivity or
eccentricity". See Rio Pioneer Gravel Co. Ltd v Warringa Shire
Council (1969) 17 LGRA 153 at 168.”
[41] In this case there are a number of significant features in this regard. First, there were
some 4,200 adverse submissions made against the proposal, albeit some 3,829 were
in a pro forma form instigated by an organized opposition association.43
[42] A number of the submitters based their concerns not just upon fear of what might
happen but by reference to actual experience with the existing West Burleigh quarry.
Further, unlike the existing quarry that is situated in an area of mixed uses, including
industrial uses, the proposed quarry is situated in a, relatively speaking, undisturbed
timbered environment surrounded by residential and rural residential subdivisions.44
[43] During the course of the cross-examination of Mr Schneider by Mr Litster, after being
referred to a number of issues including noise, blasting vibration and traffic, the
following exchange took place:45
“Q: And there will be other persistent reminders of the fact
that they have a quarry nearby because, unlike now,
there will be up to 480 trucks a day using Old Coach
Road and passing through the intersection near the
local shopping centre?
A: Yes, there will be quarry trucks on the road.
43 Exhibit 29B p 58, [304].
44 See e.g. Exhibit 1, p 11.
45 T31-60 ll 26-47 to T31-61 ll 1-16.
-- 17 of 127 --
18
Q: All of those things, I suggest to you, are indicia of an
effect on people’s perception about the place in which
they live?
A: They can be, yes.
Q: And knowing the use to which a particular site is or
has been put can affect the perception of amenity that
a person holds; do you agree with that?
A: It can affect their perception, yes.
Q: Would you go so far as to say that the people
expressing concerns about their amenity and
opposition to the quarry for that reason are being
irrational?
A: No.
Q: One would accept that they are behaving quite
rationally. You would accept that?
A: Yes I would accept that it’s quite rational to raise
those concerns.
Q: Right. But your perception of the matter is sufficient
(sic) has been done by complying with output levels
that are set out in the Environmental Policies?
A: Yeah, and I have dealt with the issue of amenity
impacts in – in two categories:
(1) The tangible impacts, which would
include noise, blasting and air quality, and,
yes, I have – I have relied on the
demonstration that the development would
comply with the regulatory limits, together
with the expert advice in this appeal, to
conclude that the – the existing level of
amenity will only be impacted to an
acceptable level. I haven’t relied on the
regulatory limits for the intangible
components of amenity, of course.
Q: Right. You would accept that amenity is not just about
the physical appearance of the surroundings, although
it can be just about the physical appearance of the
surroundings?
A: Yeah, absolutely. It’s a broad – it’s a broad construct.
Q: And it can include the emotional or sentimental
feelings or attachment that people have about a place,
yes?
A: Yes, that’s – that’s related to people’s perception of a
sense of place and – and – and – and the area that they
live, yes.
-- 18 of 127 --
19
Q: And the introduction of a quarry of the size that we’re
talking about is inconsistent with the reasonably held
perceptions of these people; do you not agree?
A: Yes. I – it is inconsistent with the reasonably held
expectations, yes.”
[44] It became tolerably clear during the re-examination of Mr Schneider that his last
answer would not in any meaningful way be affected by the changes made to CP 2003
in CP 2016.
[45] The “size” of the quarry Mr Litster was referring to was not only a reference to its
expected operational life but also to its physical dimensions. In an east-west direction
the disturbance footprint, including the quarry pit, the crushing plant, stockpiling
areas and workshop etc. is between 1.3 and 1.37 km and in a north-westerly direction,
the quarry pit will be in the order of 550 m.
[46] The evidence leaves me in no doubt that notwithstanding being confident that all
relevant environmental guidelines and policies would be met by the appellant, the
proposed development, if it were to proceed, would still have adverse impacts on the
residential amenity of at least some of the residents surrounding the proposed quarry
and particularly those more proximate to not only the quarry, but also Old Coach
Road. The significance of this will be discussed in more detail when dealing with the
evidence of the expert witnesses.
[47] Before turning to the expert witnesses, it is necessary to deal with an aspect of Mr
Gore’s oral submissions. On more than one occasion he seemed to categorise as
“intangible” potential impacts on amenity caused by certain quarry activities in
circumstances where relevant regulations, policies and guidelines were met. That is,
in my respectful view, an inaccurate description. That, by way of example, noise and
vibration falls within prescribed levels does not mean they are intangible if the noise
of a passing truck can be heard and the vibration from a blast felt.
The expert witnesses
[48] During the course of this proceeding evidence was given by 34 expert witnesses
addressing the following issues:
(i) Geology
(ii) Blasting
(iii) Air quality
-- 19 of 127 --
20
(iv) Noise
(v) Traffic
(vi) Koalas
(vii) Quarry management
(viii) Civil engineering
(ix) Visual amenity
(x) Terrestrial ecology
(xi) Need (economic and community)
(xii) Water hydrology
(xiii) Aquatic ecology
(xiv) Soils and groundwater
(xv) Town planning.
Geology
[49] Each of the parties relied on experts in the field of geology. Dr Shorten, by the
appellant, and Mr Major by the respondent. In their JER, Dr Shorten and Mr Major
purported to identify 14 “Geology Points”.46 It is unnecessary to set them out in any
detail as in many instances both defer to the other expert witnesses. In particular,
those concerned with town planning, economic need and quarry management.
Essentially the dispute between Dr Shorten and Mr Major was:47
“We disagree on the following specific points:
Paragraph 1F of the Notice of Appeal; where GS holds that,
within the Southern Gold Coast (South of the Nerang river), as
defined, the land contains a resource that is both the last known
(taken as being already identified within an existing KRA), and
largest development (specifically the case for KRA 96),
whereas JM holds that there still exists a limitless amount of
meta-greywacke; that other larger resources are known in the
Southern Gold Coast but not necessarily within a KRA; and
that the claim in paragraph 1(f) is therefore exaggerated. We
concede the need to defer to other experts, particularly in
reference to need and town planning.
Paragraph 6 of the Consolidated Grounds of Refusal; where
JM holds that there are sufficient existing and potential
sources of meta-greywacke for the Gold Coast City without
Extractive Industry lot 105, whereas GS holds that most
sources are severely restricted and existing sources have not
been shown proven to the same level as the land in question.
We agree, however, on the low level of existing proof, and
46 Exhibit 24, pp 10-18.
47 Ibid, p 26.
-- 20 of 127 --
21
both concede the need to defer to other experts, particularly in
reference to Need”.
[50] In respect of the first point, it is only necessary to determine whether or not Dr
Shorten’s assessment of the size and volume of material available within the subject
land is exaggerated. In his court report he states:48
“The resources of the proposed Gold Coast Quarry site have been
demonstrated to be significant in the geological and structural context
of the region. In general, the reassessment of the work of Huntly
(2013) and the subsequent additional investigations have served to
increase the body of knowledge available for considered development
of the proposed Gold Coast Quarry, and to reduce the uncertainties
identified in Buckley Vann (2013). The quality of the meta-
greywacke is very good and a higher confidence level can now be
applied to the extent, quantity and quality of available resource. In the
author’s opinion, the fuller understanding now gained of the structural
and geotechnical aspects of the proposed GCQ site has the potential to
enable a safer, more efficient and cost-effective extraction of
resource”.
[51] Leaving aside the question of whether or not Dr Shorten has the expertise to speak
about quarrying safety and the cost-effectiveness of the proposed quarry, I otherwise
accept the substance of his evidence. In cross-examination, Mr Major also conceded
that the subject land contained a “large mass of greywacke”.49 And that “as far as an
engineering geologist can make our judgment (sic) on the value of certain deposits,
it is quite likely that a 40-year-old long quarry provides a significant value, yes”.50
Mr Major went so far as to agree that from a purely geological point of view there
was no reason for refusing the development of the quarry.51
[52] I also accept that Dr Shorten’s investigations had a material impact on the level of
certainty that could be attributed to both the quality and the extent of the quarriable
material. The borehole data relied on by Dr Shorten was both relevant and
informative.52 In this context I found Mr Major’s criticisms of those investigations
not only unpersuasive but also difficult to follow in parts.53 In circumstances where
48 Exhibit 37, p 8, para 6.1.
49 T11-7, L 9.
50 T11-7, ll 13-15.
51 T11-10, ll 23-24.
52 E.g. see Exhibit 37, figures 19 and 20 and Exhibit 91, figures 12 and 13.
53 T11-12 to 11-13.
-- 21 of 127 --
22
Mr Reed, the structural geologist and earth scientist relied on by the respondent to
address quarry management issues had not carried out any similar or comparable
investigation, I also found his criticisms of Dr Shorten’s work in this area
unpersuasive. In any event, he deferred to the evidence of Dr Shorten and Mr Major
when it came to geological structural matters.54
[53] As to the second area of relevant dispute between these two witnesses, subject to one
reservation, I again prefer the evidence of Dr Shorten. The reservation I have is that
I conclude that he has overstated things by describing the other relevant resource
sources within KRA 67 as being “severely restricted”.
[54] In his report, Mr Major stated the issue in question by reference to paragraph 6 of the
Consolidated Grounds of Refusal:55
“…there are sufficient existing and potential sites in the City of Gold
Coast from which meta-greywacke can be extracted for the benefit of
residents of the Southern parts of the City of Gold Coast (including
the Reedy Creek area) without development of Extractive Industry, lot
105”.
He later reported:56
“The resource processing area for KRA 67 is approximately 13.5 km
of which the existing four quarries occupy a total of about 2.3 km².
About 9.9 km² of the resource processing area for KRA 67 is in the
Extractive Industry Zone.
The published geological map indicates that greywacke occurs in two
main areas within KRA 67 that together cover about 6.4 km². The
remaining approximately 7.1 km² is underlain by other rock types,
most of which can be considered as hard rock quarry resources, with
some alluvial settlements.
The 7.1 km² underlain by rock types other than meta-greywacke is
largely within the Extractive Industry Zone, except for an area of
approximately 1.5 km² in the South-East of the KRA.
54 RT24-1 - RT24-8.
55 Exhibit 47, para 32.
56 Ibid para 38-44.
-- 22 of 127 --
23
By way of contrast, the proposed quarry site on lot 105 (which is
effectively the resource processing area for KRA 96) is 0.65 km² (i.e.
65 Ha).
The significance of these hard rock quarry resources in the Northern
Darlington Range has long been recognised as described… the
planning policy of the Albert Shire Council was to direct future quarry
development to the Northern section of the Shire on the Darlington
Range and in the Stapylton areas, and no provision was made for
protection of deposits at the Southern end.
The above estimates confirm that the hard rock resources in the as yet
un-developed portion of KRA 67 are significantly larger than the hard
rock resources identified for KRA 96. These resources include meta-
greywacke and other hard rock types”.
[55] There is no doubt that between Beenleigh and Oxenford there are vast volumes of
hard rock (meta-greywacke) either being quarried, approved for quarrying or
otherwise potentially available for future quarrying. This at least was one area upon
which Dr Shorten and Mr Major agreed.57 By way of some examples of this are the
following quarries: Boral (Yatala), Holcim (Beenleigh), Hanson (Wolffdene) and
Boral (Ormeau).58 There are of course significant locational differences, KRA 67
being, broadly speaking, 40 km closer to Brisbane, but the same distance further from
the Gold Coast. These locational differences, in the sense of distance, were not
relevant to the issues canvassed by Dr Shorten and Mr Major but were relevant
considerations for other experts. Their evidence is discussed below.
[56] That there are vast volumes of hard rock within the existing and exploited sections of
other KRAs is by no means the end of the matter. The evidence of Dr Shorten relevant
to this issue was to the effect that his analysis and modelling of the “structural issues”
associated with KRA 67, led him to conclude that not all of the resources within or
about that KRA might be able to be quarried or, at least, not economically quarried.
By way of examples: the northern expansion of the Holcim quarry and the Hanson
quarry at Wolffdene.59 These problems largely being associated with the removal of
overburden, and to a more limited extent, the risk that some of the material within
KRA 67 may be “sterilised.”
57 T9-81, ll 11-28 per Dr Shorten.
58 E.g. see Exhibit 91, figure 1.
59 T9-87; T10-9 ll 5-26; T10-11 ll 30-47; T10-19.
-- 23 of 127 --
24
[57] The overburden issue raised “cost” and other “impediment” ramifications, according
to Dr Shorten, but to use his own words, were not a “showstopper”.60 Also, as I
understand Dr Shorten’s evidence, the extent of the “sterilised” hard rock would be
limited to some 5% to 10% of the total “known quarriable material” in the south-
west section of one of the quarries.61
[58] Mr Cooper provided some support for Dr Shorten’s “structural” concerns regarding
parts of KRA 67.62 Of more weight though in this context was the evidence of Mr
Gray, a mining engineer relied on by the appellant. He agreed that the structural issues
associated with KRA 67 were not “showstoppers” and even went so far as to broadly
equate the physical characteristics of KRA 67 with that of KRA 96.63
[59] During the course of his cross-examination, Dr Shorten’s modelling concerning
sections of KRA 67 and the conclusions he reached based on that modelling were
subject to, if not express, then veiled criticism. I reject those criticisms. Dr Shorten’s
modelling appeared to be soundly based and was not criticised in any meaningful way
by Mr Major. I accept the conclusions reached by him based on his methodology.64
[60] By way of summary, the conclusions that I have reached concerning the evidence
about geology are:
(i) The meta-greywacke underlying the proposed development is
of a good quality, capable of being effectively and
economically quarried and its extent is such that it has the
potential to provide product for some 40 to 60+ years;
(ii) There are some overburden problems associated with
quarrying some of the meta-greywacke within KRA 67 and the
other relevant geographical surrounds, but those problems
would not prevent the vast majority of identified material being
quarried;
(iii) Somewhere in the order of 5% - 10% of the known quarriable
material in one of the quarries located in KRA 67 may be
physically sterilised;
60 RT-10 at T10-7 ll 1-13: and described by Mr Reed as a “hassle.”
61 Ibid T10-7 ll 1-45.
62 T16-80 ll 24-47; T16-81 ll 1-3.
63 RT day 24 p 6.
64 See e.g. Exhibit 91 figures 20-25.
-- 24 of 127 --
25
(iv) There are structural issues associated with KRA 62 that are
likely to make future quarrying within it more difficult than
those likely to be encountered in quarrying KRA 96;
(v) There are still enormous volumes of quarriable hard rock in
KRA 67 and its geological surrounds, including KRA 62.
[61] By way of concluding the expert evidence in this regard, it was noted by both Dr
Shorten and Mr Major that their areas of “disagreement” would be likely to be
materially influenced by the evidence of experts in other fields. Indeed, in respect of
both areas of disagreement, they conceded “the need to defer to other experts,
particularly in reference to Need.” Town planning was also considered relevant to
the first area of disagreement. The questions of Need and town planning are discussed
below in considerable detail. However, for the purposes of this part of the case it is
sufficient to note that I agree with Mr Major’s assessment that, absent a genuine need
for the material located within KRA 96, it is largely a matter of geological interest
rather than constituting a genuine resource.
Acid sulphate and acid rock drainage issues
[62] At the commencement of this proceeding it appeared that the respondent would
contend that in the event that the quarry were to proceed, it would result in adverse
consequences in respect of acid sulphate soil and/or acid rock drainage. However,
following the evidence of Mr Shooter, an environmental scientist and Mr Briese, a
hydrologist relied on by the appellant, Mr Litster accepted that on the basis of that
evidence those issues were no longer contentious.65 Accordingly no further discussion
about them is required.
Blasting, Air Quality and Noise
[63] Quarry blasting raised a number of potential amenity issues; vibration, fly rock, air
quality and overpressure/noise.66 As to a number of those issues, Dr McKenzie, called
by the appellant and Dr Heilig for the respondent, agreed on a number of important
matters. Consistent with their first JER,67 in their second JER they reported:68
65 T14-81, ll 40-47 to T14-82, ll 1-9.
66 The relationship between overpressure levels and noise is discussed in the court report of Dr Heilig,
Exhibit 46, p 2.
67 Exhibit 17, p 1.
68 At pp 2, 3 and 4.
-- 25 of 127 --
26
“Dr McKenzie and Dr Heilig agree that blast-induced vibrations will
be perceptible to some residents surrounding the proposed
Development Application, but that the quarry has sufficient scope to
ensure full compliance with the proposed vibration and over pressure
limits at all existing residents (sic) and all approved lots at all times.
Particular note is made of the reference made in the 660th council
meeting in June 2013 to anticipate a disruption to classroom activities
of a local school during blasting…..
The above considerations, with respect of vibration, over pressure and
fly rock impacts, are predicted on the preparation and implementation
of an improved Blast Management Plan involving both the quarry
operator and an anticipated blasting services provider, in line with
previous practices at the company’s West Burleigh Quarry. It is also
agreed that the Blast Management Plan, and the expected vibration
and over pressure impact contours, should be updated within two years
of the commencement of operational blasting activities once sufficient
monitoring data are (sic) available to permit such an update and that a
five yearly review of the plan by qualified and experienced group or
person is appropriate. Prior to any blasting being undertaken on site,
the Blast Management Plan should be reviewed by the Council.
Finally, it is agreed that Condition Surveys should include at least two
(2) control structures located beyond the impact zone of quarry
blasting operations, in order to identify ‘normal wear and tear’
deterioration of residential and commercial structures.”
Under the heading of areas of disagreement Dr McKenzie and Dr Heilig reported:
“There were no areas of disagreement between Drs McKenzie and
Heilig in relation to the ability of the company to comply with the
proposed impact limits, nor in relation to the liability to safely control
fly rock, nor in relation to the requirements of the Blast Management
Plan.”
[64] Following a request for further information from the town planners, Dr McKenzie
and Dr Heilig prepared a third JER which relevantly provided:69
“… For the sake of clarity, Drs McKenzie and Heilig agree that:
1. The rate of blasting.
This was defined in the Development Application, and
taken in the Blasting Impact Statement to be once per
week on average, with the vibration and over-pressure
effects lasting for approximately two seconds per event.
69 At pp 5 and 6.
-- 26 of 127 --
27
2. Changes to the local environment when blasting occurs.
Drs McKenzie and Heilig are unclear what is meant by
this question…
3. (a) Perceptibility of changes to environment caused by
blasting.
Drs McKenzie and Heilig agree that the issue of
perceptibility lies outside the brief of the Blasting Impact
Study which was focussed on the ability to comply with
statutory regulations rather than to attempt to address the
nebulas and highly subjective value of personal
perception. The experts agree that the statement in section
2.2 of the Blast Impact Statement ‘experience also shows
that some people will find any level of perceptible
vibration to be bothersome and unacceptable.’
(b) Ability to comply with regulatory limits when
blasting.
As stated in the joint expert’s report, Drs McKenzie and
Heilig agree that the blasting operations at the proposed
quarry will be able to comply with Ecoaccess Guidelines
at all times and at all locations within the proposed
blasting areas, and that the methodology used in section
7 of the Blasting Impact Statement to arrive at that
conclusion is the most appropriate methodology to apply.
4. The nature of the impact in terms of amenity of residential
areas.
Drs McKenzie and Heilig agree with the statements in
section 2.2 of the Blasting Impact Statement dealing with
this topic and further agree as per the Joint Expert’s
Report, that the matter of personal amenity is highly
variable subjective and outside the scope of the EIS.”
Under the heading areas of disagreement, the doctors concluded:
“There were no areas of disagreement between Drs McKenzie and
Heilig in relation to the issues raised by the town planners and listed
above.”
[65] Adverse impacts on amenity associated with quarry blasting were also raised in the
oral testimony of both witnesses, including the intermittent blasting during the
establishment, development, construction and quarrying phases already referred to
above. The totality of the evidence concerning blasting leads me to conclude as
follows:
-- 27 of 127 --
28
1. Adverse impacts on amenity from fly rock are highly unlikely.70
2. With appropriate conditions imposed and with appropriate quarry
management practices in place, all relevant regulations, policies and
guidelines will be met.71
3. Notwithstanding that all relevant guidelines and policies would be
met, the amenity of some residents living near the quarry would be
negatively affected as a consequence of vibration and over
pressure/noise caused by blasting.
[66] As to the first of these matters, I accept Dr Heilig’s evidence that some close by
residents might find the vibration caused by blasting to be “bothersome and
unacceptable.”72 However, this impact on amenity has to be considered in context. It
will only be likely to affect a relatively small number of residents with controlled
blasting73 and only for very short periods of time,74 once a week for the life of the
quarry when quarrying operations commence. There was no suggestion that the level
of vibration would be likely to have a negative impact on health or property. As I
understand the evidence, vibration will not be an issue during the establishment and
development phases because of the low level of charge that would be used.
[67] Turning to the issue of noise, Dr Heilig reported:75
“Conventionally, in blast impact assessment, the audible noise level
from the blast may be considered as less significant than the vibration
impacts. Nevertheless, at the closest properties, noise from blasts at
the proposed Boral quarry is unlikely to have reduced to an inaudible
level. Residents are therefore expected to hear the blast.”
[68] Noise was also a matter addressed by engineers relied on by the parties. Mr Brown
for the appellant and Mr King for the respondent. Both of these witnesses, in addition
to addressing noise associated with the quarry per se also addressed the issue of traffic
noise along the haulage route section of Old Coach Road.
70 Exhibit 6 V6, pp 3261-3262; Exhibit 17, p 3.
71 E.g. s 440ZB of the Environmental Protection Act 1994 (“EPA”); Reg 61 of E.P. Regulations:
Ecoaccess Guidelines, Exhibit 68: Refer also to evidence of Dr Heilig at T6-60, T6-61, ll 1-25.
72 T6-63 ll 29-30.
73 Exhibit 65, P 7 “conclusions: Exhibit 46, Plates A & B: T6-19, ll 22-40.
74 T6-15, ll 17-27: T6-17, ll 10-46.
75 Exhibit 46, ll 1-3.
-- 28 of 127 --
29
[69] In their first substantive JER, Mr King and Mr Brown reported that there were no
areas of disagreement between them76 and that with appropriate conditions, measures
and policies put in place “the proposed quarry is predicted to comply with the noise
limits as applied by Mr Brown…”77 That prediction included the noise associated
with the use of Old Coach Road. Mr King however, went on to report:78
“Mr King considers that an appropriate Noise Management Plan for
future site operations needs to be prepared at the time of detail design
and prior to commencement of site operations including establishment
and construction works. The Noise Management Plan should provide
detailed guidance to the operators on noise mitigation requirements for
all considerations and should be updated regularly throughout the life
of operations to ensure appropriate direction is provided in complying
with appropriate noise limits. Mr King considers that summaries of the
Construction Noise Management Plan and Environmental Noise
Management Plan in appendix L of Mr Brown’s report number 08-
033-EIS, ROI provide a suitable basis for the preparation of the Noise
Management Plan. Mr King recommends that the Noise Management
Plan include the requirement for compliance with noise monitoring at
regular intervals to inform the operators as to the effectiveness of noise
control measures and to assist in managing noise from site operations.
Given the requirements for adaptable noise control measures during
the various quarry phases, Mr King considers that regular noise
monitoring is warranted rather than more contemporary noise
monitoring required on the basis of complaints. The Noise
Management Plan should include a schedule of methodology for
regular noise monitoring of quarry operations.”
[70] Mr Brown, on behalf of the appellant, agreed to a noise management plan of the type
advocated for by Mr King. Following an “Information Request” from the town
planners asking for details of the existing amenity and how that amenity may be
negatively impacted during the various phases of the quarry development and
operation, including haulage traffic noise,79 Mr King and Mr Brown responded:80
“The noise experts are of the view that the level of noise from the
establishment phases and operational phases of the quarry can be
controlled so that compliance with the acoustic quality objective of
Schedule 1 of the background creep criteria of clause 10 of
76 Exhibit 15, p 20.
77 At p 19, paras 22-26.
78 At p 20.
79 At p 30.
80 At p 32, paras 10 and 11.
-- 29 of 127 --
30
Environmental Protection (Noise) Policy 2008 will be achieved. In
these circumstances, the acoustical amenity of the community will be
adequately protected.
Finally, the noise experts wish to note that consideration based solely
on the audibility or perceptibility of environmental noise is not the
appropriate test when determining the acceptability or otherwise of
environmental noise emission. Rather, due regard has to be given to
regulatory noise standards, i.e. numerical criteria.”
[71] In respect of three specific questions posed by the town planners, Mr King and Brown
reported further:81
“Q: In the expert’s respective expertise, will the change to the
amenity/environment comply with the acceptable regulatory
limits in the event the proposed extractive industry is
approved?
A: Yes.
Mr King agrees that on the basis of the reporting prepared by
Mr Brown for the Development Application and the Joint
Expert Noise Report (July 2016) compliance is predicted to
be achieved with regulatory limits on the basis of
implementation and continued use of specific noise
mitigation measures.
Q: In the expert’s respective opinion, what is the nature of the
impact on the amenity of nearby residential areas?
A: Mr Brown, none. Because the level of noise from the
operation of the quarry can be controlled so that compliance
with the relevant noise limits can be achieved at all times…
Mr King states that there will be a noticeable change in the
acoustic environment at surrounding areas, at times, as when
perceptible but within compliance limits noise from the
quarry activities can vary over time including high
impact, high level, short duration noise events which (sic)
will can (sic) be out of character with the existing acoustic
environment. Residents along Old Coach Road will
experience noise from quarry road haulage trucks which will
be audible at times and due to the increase in frequency of
heavy vehicle traffic, a noticeable change in noise character
of heavy vehicles will result at times.
Mr King further identifies that the noise experts agreed in the
Joint Report (July 2016) that the proposed quarry is predicted
to comply with the noise limits as adopted. On the basis that
81 At pp 33-34.
-- 30 of 127 --
31
the level of noise from the operation of the quarry can be
controlled so that it is in compliance with the relevant noise
level limits can be achieved at all times, adverse acoustic
amenity impact shall not result at nearby residential areas.”
(Emphasis added).
[72] In circumstances where there is no basis for concluding that the appellant will not
comply with all regulatory requirements and adopt an appropriate noise management
plan, there could be no basis for refusing the application on the basis of noise per se.
That however, in my view, is not the end of the matter, because, notwithstanding that
all appropriate regulatory requirements will be met, any adverse impacts associated
with noise have to be considered in the light of all the negative impacts on amenity
that might flow from the development and operation of the quarry. This is not a case
that can be resolved by looking at each issue in isolation and where compliance on a
“one-by-one” basis is met, concluding that there would be no reason to warrant
refusal.
[73] In this context, in re-examination, Mr King was asked the following questions by Mr
Fynes-Clinton, junior counsel for the respondent: 82
“Q: Mr King, you were just asked in the last couple of questions,
dealing with Old Coach Road, about the change in noise
levels, and you gave some evidence about the change in
character. Can you – are you able to put some descriptive
flesh on the difference in character between the quarry traffic
and the existing traffic?
A: Certainly. So in respect of the residences along the southern
part of Old Coach Road, prior to reaching the quarry land,
Your Honour, which are more removed from the Pacific
Motorway, current daily traffic flows on Old Coach Road
have a heavy vehicle percentage of about- if I remember
rightly, 1.7, 1.8 per cent. With the quarry operating, the
heaving vehicle percentage will increase significantly, up to
potentially 40 truck movements per hour depending upon the
traffic engineer’s advice. The noise of a truck or a laden truck
going past is certainly quite different to a typical motor
vehicle. The increase in the number of trucks is compared to
less than 2 per cent of the daily traffic, will change what
people perceive if they were outdoors necessarily, and aware
of the traffic on the road. So more trucks, more noise of a
82 T4-8, ll 1-18.
-- 31 of 127 --
32
different character, or a more – an increase in the frequency
of occurrences to what occurs now. That would be the
perceived change if people are outdoors and aware of
what’s going on, on the road.” (Emphasis added).
[74] The discussion concerning air quality is similar to that concerning noise. That is, after
identifying the air quality concerns raised by the respondent,83 Mr Welchman for the
appellant and Mr King for the respondent, reported:84
“The experts agree that the Coordinator-General’s Stated Conditions
(if followed) are adequate to ensure that adverse impacts on air quality
will not occur.
The experts agree that EHP’s EA Conditions (if followed) are
adequate to ensure that adverse impacts on air quality will not occur.
No additional conditions are necessary.
Overall comments
The experts are satisfied that the proposed development adequately
addresses potential impacts on air quality. The experts agree that if the
Gold Coast Quarry is conducted in accordance with the commitments
made by the appellant in the EIS and in accordance with the Imposed
Conditions issued by the Coordinator-General and the EA Conditions
issued by EHP, the development will manage and mitigate
unacceptable levels of air quality (especially dust) in surrounding
residential areas in accordance with the Performance Criteria PC 19
and PC 20 of the Emerging Communities Domain Code.
The experts agree that the proposed development provides acceptable
buffer separation differences from adjacent residential areas, such that
amenity of those areas will be protected. This conclusion is on the
basis of the proposed quarry design and air quality control measures.
Areas of disagreement
There are no areas of disagreement.”
83 Exhibit 16, p 5.
84 At pp 19 and 20.
-- 32 of 127 --
33
[75] In response to a number of specific questions raised by the town planners in respect
of impacts on amenity,85 Mr Welchman and Mr King, under the heading “Areas of
Agreement” reported:86
“The perceptibility of the change in the level of an air pollutant is not
a metric that is conventionally used to determine the appropriateness
or otherwise of a development. The appropriateness is determined by
whether compliance with the air quality objectors can be achieved…
...even if the increase is perceptible, the air quality experts agree that
it will not be possible for an individual to differentiate deposited dust
that may be generated from the development from that which may be
generated by other activities in the region…
Visibility of dust is not a metric that is conventionally used to
determine the appropriateness or otherwise of a development. The
experts agree that there is no way to quantify the visibility of dust
within a dispersion modelling assessment. The air quality experts
agree that the development is unlikely to cause dust that is visible
within and close to residential properties. The air quality experts agree
that it is possible that from certain vantage points looking towards the
development and under certain light conditions, dust may be visible in
the vicinity of quarrying activities. The experts agree that such
occurrences would have no consequences from an air quality
perspective…
…the air quality experts agree that the Gold Coast quarry can be
operated in a manner that minimises dust emissions and does not cause
an adverse impact on air quality at sensitive receptors on the basis that
predicted dust levels comply with statutory air quality standards…
The air quality experts agree that the development can be managed
and operated so as not to adversely impact amenity. The air quality
experts agree that the development is likely to increase dust levels at
times.
Areas of disagreement
There are no areas of disagreement.”
[76] There is again no reason that would suggest that the appellant would not comply with
all conditions imposed by relevant authorities. However, as stated in respect of
“noise”, compliance with “statutory air quality standards” is not necessarily the end
85 At p 25, para 3.1.
86 At paras 4.25, 4.28, 4.30, 4.32 and 4.34 (pp 29-30).
-- 33 of 127 --
34
of the matter. The entirety of the evidence concerning air quality has to be considered
in assessing the potential negative impacts on amenity. The evidence of Mr King
was87 that the amenity of the community both in respect of noise and air quality would
be, with the imposition of appropriate conditions, adequately protected at all times.
[77] Unlike the situation concerning the potential impact of noise on urban amenity, Mr
King had no such reservations in respect of air quality.88
[78] Unlike air quality however, the issue of noise needs some further consideration when
addressing the evidence of the town planners. The proposed noise barrier (120m long
and 6m high) adjacent to part of the Observatory Estate to the west89 will be addressed
below when dealing with the “visual impact” aspects of the case.
[79] Before dealing with the issue of traffic, it is necessary to deal with the potential for
dust to be a nuisance to some residents within “sensitive areas”. That is, depending
on location and the weather, particularly wind direction, the amount of dust that might
be deposited on some residences might be measurable. In this context though, I accept
the evidence of Mr Welchman to the effect that dust as any form of nuisance would
be limited to those residents “very close to the quarry.”90 From time to time though,
dust from the quarry would be noticeable to a broader section of the close by
residents: as Mr Litster put it, as a reminder that they lived near a quarry that was not
there before.
Traffic
[80] The disputed traffic issues (other than noise) were initially identified in various
documents,91 but were “summarised” by the traffic engineers, Mr McClurg for the
appellant and Mr Beard for the respondent, in their first JER:92
(i) The site access arrangement, in respect of traffic safety and
operations on Old Coach Road, particularly including any
limitation on the usage of Old Coach Road to that part of the
route north of the site access but quarry haul vehicles;
87 T4-3, ll 36-47 to T4-4, ll 1-7.
88 T4-4, ll 1-7.
89 Exhibit 16, p 26.
90 T3-98, L 45 – T3-99, ll 1-17.
91 E.g. Exhibit 9, pp 38 – 39.
92 Exhibit 23, pp 6-7.
-- 34 of 127 --
35
(ii) Changes to the site access arrangement, if and when the
Bermuda Street Extension is constructed;
(iii) The ability to upgrade Old Coach Road, within the existing
road reservation, between the site and Kingsmore Boulevard
to ensure satisfactory traffic safety and traffic operations;
(iv) Upgrading the intersection of Old Coach Road at Kingsmore
Boulevard and that the system of roads, intersections and
ramps which make up the Reedy Creek Road Interchange…
with the Pacific Motorway to offset any adverse impacts of
development generated traffic on traffic safety and traffic
operations within this traffic system;
(v) Responsibility for the cost of the required site access works;
(vi) Responsibility for the cost of the required Old Coach
Roadwork upgrading works;
(vii) Responsibility for the cost of any required intersection
upgrading works within the subject site and the system of
roads, intersections and ramps which make up the Reedy Creek
Interchange… with the Pacific Motorway;
(viii) The ability to define reasonable and relevant conditions
required to ameliorate any adverse impacts of the development
generated traffic and offset any adverse impacts on traffic
safety and traffic operations, particularly recognising that the
future Bermuda Street Extension might reasonably necessitate
significant and extensive, changes to already completed works.
[81] Road design and cost issues were also identified by the traffic engineers. These
matters will be addressed below when dealing with the evidence of the civil engineers,
Mr Gould for the appellant and Mr McAnany for the respondent.
[82] In their fifth JER, the traffic engineers narrowed down their issues in dispute. Mr
McClurg and Mr Beard agreed that the issues identified in subparagraphs (i), (ii), (v),
(vii) and (viii) would probably be able to be addressed by the imposition of
appropriate conditions of approval.93 As to the financial burden of the cost of
upgrading Old Coach Road to an appropriate physical or structural standard to act as
a haulage road,94 it is now accepted that Boral would bear those costs.95
[83] Turning then to the remaining issues in dispute. While I have a considerable amount
of sympathy for the approach advocated for by Mr Beard, namely that quarry haulage
truck traffic be directed via the proposed Bermuda Street Extension, it is not an option
93 Exhibit 23, pp 46-50; also Exhibit 45, pp 9-11.
94 Traffic issue (vi), at para 82.
95 T8-64 –T8-66, ll 1-27.
-- 35 of 127 --
36
reasonably open on the evidence. Unfortunately, the state of the evidence is that,
notwithstanding that the existing West Burleigh quarry will continue to operate for
the next 6-10 years, there is no evidence to indicate that the intended Bermuda Street
Intersection roadworks would be approved, let alone commenced or completed by
that time.96 Further, even accepting that some temporary arrangement could be put in
place prior to the ultimate planned intersection (which is complex and will be
enormously expensive), the extent and cost of those works would likely render any
condition requiring such works to be completed by the appellant, to be manifestly
unreasonable.
[84] As to the remaining issues, Mr Beard took it upon himself to resolve his concerns
about the speed of the northbound haulage traffic97 by designing an
“acceleration/auxiliary lane.”98 Indeed it would not be unreasonable to say that Mr
Beard played a significant role in solving a number of the traffic planning issues the
proposed development might cause. Mr Beard made it quite clear that his strongly
preferred option was the use of the future Bermuda Street Extension but, in the event
that that option was not accepted by the court, while the proposed roadworks for Old
Coach Road would result in an “undesirable but acceptable” outcome, traffic issues
would, subject to the imposition of appropriate conditions, no longer be a reason for
refusing the application. In this context, during the cross-examination, the following
exchange took place between Mr Gore and Mr Beard:99
“Mr Gore: To that area?
Mr Beard: It’s actually a 60 metre wide road reserve, Mr
Gore, so, you know, it’s probably – I was
satisfied that you could fit it in if you wanted
to anyway.
Mr Gore: Yes, okay. And so, just so it’s clear, your
evidence is that if a – an auxiliary lane, of the
kind that you’ve shown in this figure, was part
of the upgrade, then your concern about this
speed issue for the northbound laden trucks
related to safety issues would disappear?
Mr Beard: It would.
96 T9-57, ll 10-47.
97 Traffic issue (iii), at para 82.
98 Exhibit 89: T9-60, ll 34-40.
99 T9-60, ll 34-47, T9-61, ll 1-12.
-- 36 of 127 --
37
Mr Gore: And is it also your evidence that, with the
disappearance of that issue, there is no ground
for refusal if His Honour were minded to opt
for the upgraded Old Coach Road as the
means of access rather than delaying the
Bermuda Street extension?
Mr Beard: It’s probably not quite as clear-cut as that, Mr
Gore, in that, in my opinion, if His Honour
formed the view that the Bermuda Street
extension was going to happen at some
reasonable time, there would still be very, very
good engineering reasons to go for that
alternative instead. But if you, for example,
were considering this in the context that the
Bermuda Street extension didn’t exist and
would never exist, then, as far as I’m
concerned, I’m sure the answer that you want
to hear is that this would no longer be a reason
to refuse the use of Old Coach Road.
Mr Gore: Yeah. So you would – you’ve pointed out that
there are aspects that you think are undesirable
but not unacceptable?
Mr Beard: Yes.
Mr Gore: To the extent that those aspects exist, absent
any Bermuda Street extension, you would
regard the entire – that entire proposal as
acceptable?
Mr Beard: It – it wouldn’t – there’d no longer be any
basis on which to refuse it, yes. It would be –
it would have to be in the undesirable but
acceptable category.”
[85] While traffic issues might not of themselves be sufficient to warrant refusal, that again
is not the end of the matter. The “undesirable” traffic outcomes referred to by Mr
Beard are significant and need to be considered when deciding whether, when all
relevant matters are taken into account, approval of the proposed development would
be an acceptable or unacceptable community outcome.
[86] In addition to the traffic noise issue identified above, there is also the potential for
congestion at some intersections, particularly during the carrying out of the upgrading
of Old Coach Road. Of particular significance in this regard is that Old Coach Road
-- 37 of 127 --
38
could be effectively closed for months resulting in significant re-routing of traffic100
with adverse impacts on convenience and traffic congestion.
[87] During the course of the appeal the civil engineers investigated the option of
upgrading Old Coach Road while keeping it open to traffic. That option is discussed
below.
[88] Again, while acceptable traffic engineering solutions exist and would be put into
place by Boral, the introduction of up to 450 haulage truck movements per day into
the local roadwork system will, as is the case concerning traffic noise, vibration and
dust, adversely impact on the amenity of some residents. In this context though it will
not be the same residents who experience the same impacts. Who suffers what will
be dependent on location and, at the end of the day, in relative terms these adverse
impacts will affect only a very small proportion of the residents of the Southern Gold
Coast local government area. In this context I accept the submission made on behalf
of the respondent that the introduction of so many haulage trucks into the road
network will be a constant reminder of the quarry to a number of the local residents.
Particularly at locations such as the Kingsmore Road roundabout and, to use Mr
Beard’s words, while traffic issues associated with Old Coach Road would not of
themselves warrant refusing the application they nonetheless result in an “undesirable
outcome”.
The civil engineering evidence
[89] The extent of the work carried out by Mr Gould and Mr McAnany was enormous.101
Thankfully, it was unnecessary for me to drill down into the detail of their
investigations and conclusions because of the level of agreement between them.
[90] At the risk of understating the evidence of the civil engineers, the following was made
tolerably clear:
(i) the timing and costs associated with the Bermuda Street
extension option make it impractical at this time;
(ii) the relevant sections of Old Coach Road could be designed and
constructed to a satisfactory safe haulage road status;
100 See Exhibit 36, pp 8 and 10 per Mr McClurg and Exhibit 45, p 22 per Mr Beard.
101 E.g. Exhibits 22A, 22B, 105 and 108.
-- 38 of 127 --
39
(iii) the existing road works could be carried out largely within the
existing road reserve; and, where not, will be largely confined
to the appellant’s own land;
(iv) two options exist for the upgrading of Old Coach Road. First,
as originally envisaged, closing the road for a period of 3-4
months. The second option was to keep Old Coach Road at
least partially open during the upgrading. Not surprisingly, this
option would extend the construction phase, inconveniencing
traffic for up to 10 months according to Mr Gould and 11
months according to Mr McAnany.
[91] The cost of the road works runs into many millions of dollars. To use Mr Litster’s
words, they are “high order” costs. Under the “open road” option, costs would be in
the order of $6.5 million to $7.2 million, which is about $1.5 million more than the
option involving closing the road.
[92] Fortunately, it is not necessary for me to resolve disputes concerning costs of
construction as they will be borne by the appellant. Nor is it necessary for me to
resolve whether construction should occur with the road closed or partially open. That
would be a matter for a later day in the event of approval.
[93] That said, either option would result in significant disruption either as a consequence
of delays on Old Coach Road or diversions of the type envisaged by the traffic
engineers.102
[94] It was also identified during the course of the evidence of the engineers that the
proposed roadworks would be likely to require additional clearing including that of
some designated endangered species. However, insofar as this matter is concerned, I
accept the evidence of Mr Francis, an environmental scientist relied on by the
appellant, which was to the effect that the amount of endangered species likely to be
affected would be very small (about 0.01 ha) and would be readily offset by additional
planting within the buffer area surrounding the proposed quarry or by the payment of
monetary compensation.103
102 E.g. Exhibit 23 at pp 43-45.
103 T17-66, ll 15-47, T17-67, ll 1-30.
-- 39 of 127 --
40
The White Bellied Sea Eagle and Koalas
[95] A considerable amount of evidence was given by a number of witnesses dealing with
the potential environmental/ecological impacts that might result as a consequence of
the proposed quarry. However, the potential impacts on the koala population and the
white bellied sea eagle were given particular attention.
[96] Located just outside the southern boundary of the quarry footprint is a magnificent
nest of the white bellied sea eagle.104 The evidence is that this nest is one of two
maintained by breeding white bellied sea eagles. Significantly, the best evidence is
that the nest also has a successful breeding history. The location of the second nest is
unknown.
[97] While very proximate to the southern boundary of the disturbance footprint, the tree
in which the nest is constructed is in the order of 100m from the nearest south-eastern
corner of the quarry pit itself.105 Once that degree of separation was pointed out to Dr
Watson, the flora and fauna expert relied upon by the respondent, he accepted that
there was little or no risk to the breeding pair of eagles arising out of fly rock
generated from blasting.106 I am also satisfied that the eagle would not be physically
placed at risk by fly rock caused by blasting during the establishment and
development phases. The evidence in that regard is that while blasting might be more
frequent, it would be at a materially lower level of intensity.
[98] That the eagles would not be under any physical threat from fly rock is, of course, not
the end of the matter. The operations associated with the quarry, particularly during
the establishment and development phases, would be likely to cause the breeding pair
to abandon this nest, or at the very least, be likely to interfere with breeding. That
concern was obvious from the evidence of Mr Agnew, an expert on fauna related
matters relied on by the appellant. His concern was such that he favoured various
measures, including netting, to dissuade the breeding eagles from using the tree for at
least the first two or three years of development.107 Such netting exercises have
resulted in uncertain outcomes and are not guaranteed of success.
104 See Exhibit 146.
105 Exhibit 1, p 34 and T20-37, ll 13-16.
106 T20-39, ll 37-47; T20-40, ll 1-3.
107 T19-37.
-- 40 of 127 --
41
[99] There was no direct evidence that the subject nest was the eagle’s primary nest
however, there was evidence that it had been successfully used for breeding, and it
seems more likely than not that it is the primary nest given its known breeding record.
Often the secondary nest is less developed, being something ranging from
“rudimentary through to something that is more of an intermediate advanced
development.”108 In this context, in response to a question from me, Mr Agnew
responded:109
“Q: If they were dissuaded from using their primary nest,
assuming the nest that we saw on the inspection was
the primary nest, and I think – I don’t think there has
been any evidence given thus far, but there was some
comment on-site that they had bred in that nest. If that
was netted for two or three years, might not the
secondary nest become the primary nest?
A: Well, that’s what we would – would hope for, would
potentially be a positive outcome rather than allowing
the birds then to return to that existing nest, with
monitoring – we’d have to monitor the birds during
that period. Take a quick step back. We don’t actually
know what the – the breeding success is on – on the
site now. There have been observations of nestlings,
but we don’t know how well – what success they’ve
had on the site, but we presume that they have – they
have bred and they’ve continued to use the site for a
number of years. So we would want to monitor an
alternative site, and were there a view that an
alternative site was successful, then in my view I think
we should permanently dissuade them from using the
nest site on the subject land.”
[100] Even accepting the limited amount of knowledge concerning the white bellied sea
eagles and their breeding habits, it is very likely that in the event the quarry was to
proceed, the breeding pair, either of their own volition or through human intervention,
would abandon this nest. On this topic, I also accept Dr Watson’s evidence to the
effect that once abandoned there would be a real possibility that the breeding pair
would never return to the subject nest.110
108 T19-36, ll 23-40.
109 T19-37, ll 43-47; T19-38, ll 1-9.
110 T21-10, ll 1-8.
-- 41 of 127 --
42
[101] I am not persuaded that in the event that the subject plan was developed in accordance
with the Reedy Creek Structure Plan, the same outcome would be likely. During the
course of cross-examination the following exchange took place between Mr Gore and
Dr Watson:111
“Q: Yes. And all I’m suggesting to you is that even with
those larger (buffer) distances involved, because
we’re talking about human behaviour, and potentially
quite large numbers of people if the plan area was
fully developed, that would cause a disturbance to the
bird – birds?
A: Well, in accordance with that plan. And this Reedy
Creek overlay, that area is – is all identified as a green
- as a proposed open space and nature conservation.
Q: I agree. But do you not agree that there would still be
issues about the proximity of residential
development? If you don’t agree just say so?
A: I don’t – I don’t believe there would be.”
I accept Dr Watson’s evidence on this topic.
[102] Potential nest trees have been located in the general locality.112 However, given the
lack of knowledge concerning the behaviour and habits of these large raptors, it is far
from certain that the breeding pair would relocate to any of the trees identified.
[103] The evidence such as it is concerning these birds is that, should the quarry proceed,
there is a significant risk that the breeding pair would abandon the subject nest. In
circumstances where it is not known where the secondary nest is, that might mean
that that breeding pair would be lost from this locality. That would be a very
unfortunate consequence. However, in circumstances where there was no suggestion
that the birds would not continue to breed, albeit elsewhere, this outcome would not
warrant refusal.
[104] Before leaving the topic of birds and turning to the koalas, reference was made during
the course of the evidence to the glossy black cockatoo. There is no doubt that feed
trees for these cockatoos will be lost as a consequence of the construction of the
quarry. That consequence was investigated by Mr Agnew who carried out a study and
111 T21-11, ll 36-45.
112 See Exhibit 146.
-- 42 of 127 --
43
prepared a feed map.113 According to him the loss of those trees would amount to a
“low-impact” consequence.114 As I understood the evidence on this topic, over the
entire site there were 27 feed trees and of those, six would be destroyed during the
development of the quarry. While the loss of those feed trees was a matter Mr Agnew
was questioned about by Mr Litster, his conclusions on the topic were not seriously
challenged. Also, Dr Watson did not seriously challenge Mr Agnew’s evidence on
this topic. The evidence concerning the glossy black cockatoo leads me to conclude
that while there will be a loss of feed trees associated with the development and
operation of the quarry, that loss would be able to be offset if necessary by
propagation of the relevant species within the indented buffer area.
[105] Turning then to the issue of Koalas. The proposed quarry, when fully developed,
would result in the destruction of 23,247 non-juvenile koala habitat trees (NJKHT).
Those experts dealing in particular with the existing koala population, Dr Carrick and
Mr Saunders, relied on by the appellant, and Dr Ellis, relied on by the respondent,
identified a number of issues to be addressed before reaching their final conclusions.
In their first JER, they reported:115
“A key element in consideration of the Koala issues in the Appeal is
the effect of the proposal on native vegetation constituting Koala
habitat on the site. The Ecology (Koalas) experts will need to rely on
the Ecology (Terrestrial Flora) experts to quantify the non-juvenile
Koala habitat trees that will unavoidably be removed for quarry
operations. The Ecology (Terrestrial Flora) experts will then need to
provide for assessment by this group [Ecology (koalas)], information
on the number and location of any proposed replacements…”
[106] It was also identified that input might be required from the civil engineers to provide
information concerning safe crossings for koalas and other fauna, together with
information about fencing the site to protect koalas from various hazards including
roaming dogs. In their relevant JER, Dr Watson and Dr Francis provided their input.
After identifying the relevant issues raised in the Notice of Appeal, they reported:116
“We agree that most of these issues can be grouped as (a) those that
relate to potential loss of habitat required to support Koalas on the site
113 Exhibit 147.
114 T19-40, ll 10-27.
115 Exhibit 18, pp 2-3 at [7].
116 Ibid, pp 5-6, paras [5] and [6].
-- 43 of 127 --
44
(loss of non-juvenile koala habitat trees…) or (b) those that relate to
potential loss of connectivity on and through the site. Other matters (c)
relate to potential changes to vehicular traffic on the road network
onsite and offsite, predator control, as well as changes to the
designation of the buffer areas of the site to secure their environmental
values in the long term.
We also agree that the loss of Koala habitat trees that would inevitably
be removed for the quarry pit and associated processing plant if the
proposal is approved would constitute a residual impact on Koalas, to
be compensated for in accordance with the Koala habitat offset policy
applicable at the time of such approval. (b) Furthermore, we agree that
the appropriate compensation for loss of NJKHTs in developing and
operating the quarry is to establish replacement trees - not simply
change the tenure of existing habitat without re-establishing trees…”
[107] In their second JER, Dr Carrick, Mr Saunders and Dr Ellis identified what they
described as a number of critical “environmental offsets” for the impacts resulting
from the destruction of the NJKHT. These included117 the planning of replacement
trees at a ratio of 3:1 (i.e. in the order of 70,000 trees) over an area of approximately
70 ha, which need not consist of one site only.118 Offset planting would be
synchronised with the evolution of the quarry. Other issues included management of
roving dog populations, fencing, connectivity with other NJKHT areas, appropriate
bushfire management and monitoring.
[108] Significantly, the experts agreed that:119
“We agree that providing loss of Koala habitat is offset as above and
potential connectivity impacts are mitigated…”
Conclusions
As long as the measures detailed in this Joint Report are adopted, we
agree that potential impacts to Koalas arising from the proposed
development can be managed and a net benefit to Koalas will result,
as per item 45(i) in the Notice of Appeal dated 11 August 2014.
Points of disagreement
There are no points of disagreement” (Emphasis added).
117 At pp 8-11.
118 RT21-22, ll 33-37.
119 Exhibit 18 at pp 9-11.
-- 44 of 127 --
45
[109] Notwithstanding those conclusions, these experts were then asked to specifically turn
their minds to a number of potential issues arising as a consequence of the operation
of the State Planning Policies and/or the South East Queensland Regional Plan and/or
the respondent’s town planning schemes CP 2013 and/or CP 2016. Pursuant to that
request for additional information, these experts prepared a “Supplementary Report.”
[110] After substantial individual input, including disquiet expressed on the part of Dr
Carrick about what he considered to be active involvement of “…the legal
representatives of one of the parties…”120 Dr Carrick and Dr Ellis concluded:121
“Consensus statement
We share broad agreement on various issues in attachment A of the
court order dated 16 September 2016, but to drill down as to the
specifics of how each of these various provisions affect the Boral
proposal with respect to Koalas requires legal certainty as to (a) the
hierarchy of the various provisions (and what effect this has on what
appear at face value to be significant inconsistencies or
incompatibilities as to their applicability to the proposal), as well as
(b) any effect arising by way of what weight can be accorded
seemingly inconsistent provisions…. These are not matters that lie
within the area of expertise of the Koala Experts. When the Town
Planning Experts achieve a consensus on the application of the
provisions… that deal directly or indirectly with Koala conservation,
or perhaps more likely, when His Honour’s findings on the legal
arguments by the Appellant’s and Respondent’s legal teams on the
application of these provisions become available, the Koala Experts
will be in a position to confer again to assist the Court (by providing
our evaluation of the opportunities for achieving a satisfactory
outcome for koalas within the context of provisions that we can be
assured actually do apply to the Boral proposal). Depending on which
provisions are found to be operable, an outcome essentially as
provided for in Koala JER 20160715 would appear to be possible; or
alternatively if, for example, offsetting the unavoidable impacts of
the proposal on Koala habitat on the site is actually found to be
precluded by the ‘protected in situ’ requirements of parts of City Plan
2016, the proposal would not appear to us to be possible at all.
Points of disagreement
120 At p 67.
121 At pp 68-69.
-- 45 of 127 --
46
Whilst the Koala Experts have recorded a substantial number of
individual comments these are not so much ‘disagreements’ as
expressions of ‘uncertainties as to whether or not agreement is
possible’ – due to the lack of legal certainty as to the hierarchy of the
various provisions and implications by way of what weight can be
accorded seemingly inconsistent provisions of different GCCC
Planning Schemes and State planning instruments, as alluded to
above.”
[111] The reference to the phrase “protected in situ” in Dr Carrick and Dr Ellis’ “consensus
statement” is a reference to where those words are used, in the respondent’s CP 2016.
Pursuant to s 8.2.6.2, the purpose of the Overlay code is described in these terms:122
“(1) The purpose of the Environmental significance Overlay code
is to identify and protect matters of environmental
significance and ensure that development is consistent with,
and contributes to, the achievement of the objectives of the
Nature Conservation Strategy.
(2) The purpose of the code will be achieved through the
following overall outcomes:
(a) matters of environmental significance are identified,
protected in situ and enhanced to maintain flora
and fauna diversity within….”
The phrase “protect in situ” is then defined to mean:123
“For the purposes of the Environmental significance overlay code,
matters of environmental significance must not be damaged or
removed, and the matter cannot be offset.” (Emphasis added).
[112] While clearly not lawyers, a matter that both Dr Carrick and Dr Ellis are no doubt
pleased about, their observations are correct. That is, if the NJKHT on the site cannot
be cleared, then the proposed development would not be able to proceed. In this
context I also express the concern and disappointment that after having completed
what they understood they were required to do, they were then asked to embark on an
exercise which they clearly found difficult, and on the part of Dr Carrick, frustrating
and arguably meaningless.
122 Exhibit 11A, p 194.
123 Ibid p 304.
-- 46 of 127 --
47
[113] Koalas are a listed vulnerable species and as the NJKHT habitat supports an existing
koala colony, it is a habitat of national, state and local significance. However, the
extant koala population is quite small. Given the difficulty in quantifying just exactly
how many koalas might be present, Dr Carrick’s “best guess” was between 3 to about
10 koalas over the entire site (217 ha) and between 1 and about 6 habituating the
disturbance area (65 ha).124
[114] It is unfortunately the case that even if the proposed quarry did not proceed but instead
some form of residential development took place, the existing koala population would
be placed under stress. In his court report, Dr Carrick referred to a further study
carried out by ddwfauna in March 2005. Dr Carrick reported:125
“Prior to my inspection of the site in 2009, a ‘Basic Fauna Assessment’
of the site was undertaken by ddwfauna in March 2005 (see appendix
B). With respect to koalas, the ddwfauna report recorded observations
consistent with subsequent studies of the site. ‘Only limited evidence
of koalas were received on site. Fresh faecal pellets were located under
three mature trees’ and no koalas were observed. The authors
concluded that: ‘this suggests that the area does not support a large
population of koalas, although further surveys may record a greater
level of activity than currently estimated. The removal of (a) large
number of suitable shelter and fodder trees, increased disturbance in
the form of traffic, noise and domestic dogs will reduce the quality of
the bushland for this species in the immediate area. There is, however,
little reason to suggest that this species will not continue to utilise the
bushland surrounding the proposed quarry or residential
development.’ And ‘in conclusion, it is fair to state that while both of
the possible proposed developments will negatively impact the faunal
diversity onsite, they will do so in different ways. The residential
development will probably have a greater long-term influence due to
the associated effects and increases in traffic.”
[115] Of particular concern to Dr Carrick about residential development was the
introduction of dogs.126 Dr Carrick’s evidence about this was not challenged and I
accept it.
[116] Before proceeding further, it is important to note the level of residential development
likely to occur under CP 2013 would have been significantly more extensive than
124 Exhibit 40, p 3, paras 7-9; RT21-51 ll 5-47, RT21-52 ll 1-7.
125 Exhibit 40, p 2, para 5.
126 RT21-42, ll 20-45 and RT21-44, ll 13-29.
-- 47 of 127 --
48
could occur under CP 2016. The latter, according to Mr Litster, is a planning regime
designed to preserve the existing SKRA or even to permit a quarry, albeit materially
smaller than that proposed. More will be said about these matters when dealing with
the evidence of the economists and town planners. Also, as Dr Carrick
acknowledged, koalas can co-exist with residential development with appropriate
planning and design.127
[117] Both in his report and in cross-examination, Dr Carrick, consistent with the views of
Dr Ellis, expressed the opinion that “koala habitat offset should always be the last
resort (after avoid and minimise), not the first.”128 As already noted though, Dr
Carrick, Dr Ellis and Mr Saunders all agreed that with proper management the
development of the quarry and its consequential offsets could result in a “net benefit
to koalas.” During the course of his cross-examination, I expressed the view that there
appeared to be a tension between offsets being of last resort and yet resulting in a net
benefit to koalas. When I raised this apparent tension with Dr Carrick, he
responded:129
“Yes. I understand that bit of it, your Honour. I think the net benefit,
as I think I alluded to a bit earlier on, first zero out for the loss. So the
offsets, at a minimum, do that. The previous title was offsets for a net
gain in koala habitat, and the offset policy apparently is designed –
and it says that, it’s designed to generate an increase in koala habitat
in south east Queensland. So once that’s done, one can argue there’s a
net benefit from that in the first instance. On top of that, the other
measures on the site of predator control is going to benefit the koalas
that remain there. Fire – better fire management is likely to benefit the
koalas that remain there. Vegetation management of the buffer area is
likely to benefit the koalas that remain there. So the – as long as the
loss of the actual trees they depend on is offset, then the addition of
these other things, in our view, would contribute to a net benefit for
koalas. Not on the site. It will be to koalas in south east Queensland.”
[118] The planting of future NJKHT at a ratio of 3:1 in land adjacent to other existing koala
colonies is of course a fundamental part of any offsetting program. In his cross-
examination, Dr Ellis maintained the opinion he expressed in the JER that the
proposed development, with appropriate offsets and management, can result in a net
127 RT21-39 ll 43-45.
128 Exhibit 40, p 5, para 10.5; RT21-22, ll 27-30.
129 RT21-33, ll 7-18.
-- 48 of 127 --
49
benefit to koalas in south east Queensland. He also agreed with the proposition
advanced by Mr Gore, to the effect that provided appropriate conditions were
imposed which reflected and ensured the offset program identified in the JER, an
acceptable outcome insofar as koalas were concerned could be achieved.130
[119] Turning briefly to the evidence of Mr Saunders, his involvement was essentially
limited to identifying what parcels of land might be available to facilitate the
offsetting program identified by Dr Carrick and Dr Ellis. In that regard, he submitted
a report identifying a number of potential sites.131 During his cross-examination by
Mr Litster, it became apparent that at least one of his sites was no longer available as
a consequence of proposed residential development. On balance though, the evidence
establishes that it is likely that suitable sites would be able to be acquired by the
appellant to accommodate the necessary offsets. Neither Dr Carrick nor Dr Ellis
expressed any reservation about the ability to acquire a suitable area or areas of
appropriately located land.
[120] An obvious difficulty with any offsetting program is that any planting regime cannot
result in the immediate replacement of NJKHT, even when utilising more advanced
planting. As Dr Carrick identified, there was a “real issue for the koalas with some
time lag between when the trees go in the ground and when they are of any use to
koalas.” According to him, that time lag could be as much as 20 years, but was more
likely to be in the order of 10 years.132 In the third JER Dr Carrick reported:133
“In the case of the Boral proposal, (a) there will be a replacement for
the NJKHT removed on the site, (b) the removal will be staged over
the 40+ years of the operational life of the quarry and (c) the trees will
be progressively replaced with offset plantings in accordance with the
State policy…”
[121] To address the “time lag” problem, the offsetting program envisaged would see, once
appropriate alternate sites have been identified and acquired, progressive planting
over the life of the quarry. Over the establishment and development phases some 47%
of the entire quarry site would be cleared. By the completion of the construction phase
65% of the quarry site would be cleared. Depending of course on demand for the
130 Exhibit 18, pp 5-8, paras 10-12: RT21-58 l; 29-46.
131 Exhibit CB.
132 RT21-24, ll 23-30.
133 Exhibit 18, p 7.
-- 49 of 127 --
50
quarried material, further clearing will then occur during the operational phase of the
life of the quarry. On current projections, by the beginning of phase Q1 78% of the
site would be cleared, by the beginning of phase Q2 80%, by the beginning of phase
Q3 93% and by the beginning of phase Q4 100% of the site would be cleared.134
[122] The difficulties associated with addressing the lag time were raised with Dr Carrick
during his cross-examination.135
“Q: And so by the time the project’s about 5 or 6 years in,
64% of the clearing – the ultimate footprint will be
cleared?
A: Yes.
Q: And that would really mean that a substantial amount
of planting needs to happen straight away on
approval, if it’s to go anywhere close to providing any
sort of sensible offset?
A: I agree, and I would hope that should His Honour
approve the – or allow the appeal, that that would be
a condition that the next stage of construction – or
development of the site wouldn’t happen until a start
had been made on the plantings for the – that tranche
of clearing.”
[123] Dr Carrick later went on to say:136
“…the kind of – yes, far be it from me to dictate to the court. But that
would be my hope that, if this were to proceed it would be on the basis
that these offsets have to actually be delivered, and that – not only that
they’ve been started, but by the time – five years down the track when
the next round of clearing needs to be done and, therefore the next
round of offsets has to be started beforehand, there will be some ability
to assess how – what the progress has been on earlier phases. And
that’s why I think the staged approach has that merit as well because
if the goods are not being delivered then that could prove to be quite
inconvenient to say the least, to a quarry operator.”
[124] That offset planting should commence prior to clearing commencing on the site and
be commensurate with the evolving impact on the site was a matter recognised by
both Dr Carrick and Dr Ellis in their second JER.137
[125] The evidence concerning koalas has led me to the following conclusions:
134 Refer to Exhibit 6 V3, pp B1337-1340.
135 RT21-28, ll 4-13.
136 RT21-43, ll 38-47.
137 Exhibit 18 p 8, para 10.1(f).
-- 50 of 127 --
51
(i) The proposed development will result in the eventual
destruction of in excess of 23,000 NJKHT and, as a direct
consequence, will have a direct and adverse impact on the
extant koala colony.
(ii) Notwithstanding the philosophical starting point that the best
solution is maintaining existing habitat, appropriate offsetting
can result in a net benefit to the wider koala population in
South-East Queensland.
(iii) While mortality cannot be ruled out, given the relatively low
koala population and the staging of the clearing of the site with
proper onsite management (including koala spotting) that
mortality rate, if not able to be eliminated, can be minimised.
(iv) In the event that the development were to be approved, that
approval would be subject to a number of conditions of the
type identified by both Dr Carrick and Dr Ellis and, in addition,
conditional upon evidence of the securing of appropriate offset
sites and a “head start” planting regime of the type identified
by Dr Carrick. In this context it is also of significance that
koala habitat would remain, by virtue of the intended buffer
area and surrounding habitat areas.138
Visual amenity
[126] The scale and nature of what would occur on the land has already been identified. I
agree with Mr McGowan, relied on by the respondent, that, broadly speaking, the
following aspects of the proposal are the most likely to generate impacts on the
“visual environment”139:
Removal of vegetation and ridgelines.
Visible structures (including acoustic barrier), plant and/or
infrastructure.
Visible benches or walls.
Road upgrades and haulage movements along Old Coach Road.
[127] As to the last of those matters, I do not consider it to be of any real significance in the
scheme of things. It is true that during the upgrading of Old Coach Road there will be
unsightly roadworks and, upon completion, the introduction of a large number of
haulage trucks. The roadworks will be, under either the full or partial closure options,
only temporary and roadworks are but an inconvenient and unsightly but necessary
product of urban living. In this context it is also of some relevance that at least for
138 E.g. see exhibit 1, p23.
139 Exhibit 19A p 101, para 287.
-- 51 of 127 --
52
some, roadworks will be required on Old Coach Road sometime in the future. As to
the haulage trucks, their visual presence will be intermittent, albeit regular, and, apart
from those persons travelling on the road, visible to only a relatively few number of
residents. Traffic noise of course is a separate issue.
[128] Broadly speaking, the visual impacts of the proposal has, in my view, three significant
aspects. Its visibility to those living relatively close by, visibility from more distant
view points and the visual impact on the green backdrop to the Gold Coast, the theme
of which is the green (the hinterland) behind the gold (the sandy beaches).
[129] In their second JER, Mr Chenoweth and Mr McGowan agreed on a number of
principles considered to be applicable in this case. They are, in no particular order of
priority:140
Scenic preference ratings indicate that the community typically prefers
views of bushland and rural scenery over views of development and
landscape disturbance.
…
Scenic preference ratings need to be considered in combination with
the likely visibility of proposed development.
Views which have structure and legibility (foreground, mid ground,
background, focal points etc.) are preferred over poorly structured
views, and views that take in diversity and a range of visual interests
are preferred over simple outlooks.
Panoramic views with a number of distinctive elements are more
attractive and desirable than narrow view corridors or views of single
elements.
Viewing distances are an important factor affecting visual impacts –
the greater the distance from the viewpoint, the smaller an object
appears, the greater the field of view, and less discernible is the detail.
…
To be clearly visible from this distance (20km) any changes to the site
would need to be substantial (in scale) and of high contrast to the
existing condition.
140 Ibid p 61, para 131.
-- 52 of 127 --
53
Viewpoint (including private and public places) typically have
primary views in one direction… and secondary views in other
directions. Primary views are typically of greater value than secondary
views.
Views from public spaces… assume greater importance than private
residential views. Although as a general principle, nobody has a ‘right’
to a view, private residential views (as well as public viewpoints) are
taken into account in visual impact assessment, especially where a
planning scheme requires or encourages protection of such views.
Understanding the significance of visual impacts depends on a number
of considerations. In this case the most relevant are:
The nature and quality of the visual environment that will be
affected…
The visibility of the proposal… and the number and
sensitivity of visual receptors…
The magnitude of change that the proposal will impose on the
visual environment… compared to development that is
otherwise expected or intended to affect the visual
environment.
The sensitivity of particular receptors is typically dependent on a
combination of factors including:
The type of receptor and the interest in the visual
environment…
Accessibility of views and viewing opportunities…
The quality or extent of the view and the prominence of the
subject site within the view…
Availability of alternative views.
Impact magnitude and significance are evaluated for the proposal,
with and without mitigation measures… based on variables such as:
The extent of the proposal that would be visible
The proportion of the visible parts of the proposal to the entire
field of view
The nature and intensity of the impacts
-- 53 of 127 --
54
Whether key features that would be obscured or affected
That (sic) would be obscured or affected
The geographic extent of the impacts
The duration and reversibility of particular impacts, the
likelihood of occurrence of impacts and the likely
effectiveness of mitigation measures.
In general, the acceptability of visual impacts should be considered in
relation to both the existing condition of the site as well as the nature
and extent of development which is reasonably expected to occur on
the site… This hypothetical alternative is considered as part of a
baseline visual environment against to which potential changes can be
compared.
[130] Visual receptor sensitivity was then given three rankings: high, moderate and low.
Examples of receptors falling into the high rating would include travellers along
scenic routes or visitors to scenic lookouts and residents within 2.5km of the site with
an interest in the landscape or particular views. Examples of those falling within the
moderate rating would include travellers along road and rail routes within 2.5km of
the site, which are not scenic routes but offer clear and quality views. Residents or
workers beyond the immediate vicinity (2.5km – 6km) of the site with an interest in
the landscape or particular views. Examples of those falling within the lowest
category would be travellers along road and rail routes beyond 2.5km of the site which
are not scenic routes but offer clear and quality views and residents or workers beyond
6km of the site where clear quality views to the site are achieved.141
[131] Visibility points or receptor groups and locations were identified in various
documents.142 The closest receptor group is that located at Barden Ridge Road, Reedy
Creek, being 0.2km from the disturbance footprint and the furthest being the Pacific
Fair Shopping Centre at Broadbeach which is 9.1km from the proposed disturbance
footprint.
[132] In their second JER, Messrs Chenoweth and McGowan expressed a number of
opinions. Mr Chenoweth observed:143
141 Ibid p 59.
142 E.g. Exhibit 19B and Exhibit 19A p 63.
143 Exhibit 19A p 94, paras 268-269.
-- 54 of 127 --
55
“A condition could be imposed such that staging is adjusted to allow
for the terminal position of upper rock faces (those modelled as likely
to become visible when Ridge J is removed) to be achieved earlier in
the sequence, in order to revegetate these benches as early as possible,
and allow maximum time for tree and shrub growth prior to the
removal of Ridge J. Consideration should also be given to a condition
requiring that visual impact mitigation measures on the upper 5 or 6
benches be monitored and independently verified as showing
satisfactory progress towards an agreed proportion of screening.
However, AC does not consider that a condition should be imposed to
the effect that approval of stages Q3-Q5, including the removal of
Ridge J, be conditional on the achievement of screening of quarry rock
faces exposed in stages Q1 and Q2. In his opinion, the volume of rock
to be excavated in stages Q3-Q5 should not be sterilised or deferred
due to a relatively minor risk that parts of the quarry rock face will
be visible to a relatively small number of residents after 25-30
years of quarrying. Instead, he is confident that monitored trials
on the existing Boral quarry and management of revegetation for
10 years or more on terminal QT benches on the subject site, will
ensure that the quarry rock faces will not be visibly intrusive.
Additional assurance is provided by the viewing distance (>1.8km),
the orientation of the rock face is such that they will be mainly in
shadow, the retention of a forested skyline and the relatively small
proportion of field-of-view which will be affected.” (Emphasis
added).
[133] Mr Chenoweth expressed his conclusion in the second JER in the following terms:144
“The impact on visual amenity arising from the visibility of the upper
exposed faces, as seen from a limited number of residences at viewing
distances of 1.4km, and only after many years of quarry
commencement, and only after many years of quarry commencement,
is considered to be relatively minor.”
[134] Mr McGowan disagreed:145
“Whilst there seems to be a lack of clarity on when certain impacts
may occur and for how long they may last (and thus a lack of certainty
about the significance of some impacts), the assessment summarised
in this report, and that prepared by Cardno for the EIS indicates that
there is a clear risk of significant visual impacts for a fairly wide range
and geographically broad visual catchment. It also indicates that the
144 Ibid p 97, para 278.
145 Ibid p 102.
-- 55 of 127 --
56
disturbance that will result from the project cannot be entirely hidden
by the site topography and vegetation.
Many of these impacts, particularly those that result in the removal of
high-valued natural landscape features (such as Ridge J and visible
vegetation) and those that result in scarring of the natural landscape,
are the type of impacts the planning provisions (identified above)
attempt to avoid. Such impacts erode the landscape character of the
city, impact on views and visual amenity, and ultimately affect the
city’s identity and sense of place. Whilst it is clear that other forms of
development (that might occur if the quarry didn’t proceed) may result
in visible changes to the site, the planning provisions would ensure a
much more sympathetic extent and form of development for the site’s
landscape qualities and result in far less visual impacts.
Regarding the types of impacts identified (for the proposal) I recognise
that the project incorporates a range of measures which attempt to
mitigate the magnitude of impacts (as summarised at s 3.5 above). I
note also that a number of further mitigation measures have also been
explored (resequencing excavation of potentially visible high walls,
and performance controlling the rehabilitation process). I accept that,
if these measures are appropriately employed (and particularly if the
program of quarrying was contingent on achievement of particular
screening/revegetation performance indicators) they could be
effective in reducing impacts particularly in relation to visual impacts
generated by the visibility of high walls and benches. I accept also that
localised impacts (such as those from the acoustic barrier adjacent
Barden Ridge Road; and potential impacts from the construction and
traffic movements along Old Coach Road (could possibly be mitigated
through more detailed design or more tailored mitigation measures).
As it stands however, these further mitigation measures have not been
employed so there remains risk of visual impacts from visible high
walls and benches, from acoustic barriers, and from the upgrade and
traffic along Old Coach Road. There also remains the significant
impacts that will result in the removal of Ridge J and vegetated
slopes which cannot be practically mitigated. As such the proposal
as it stands would generate significant adverse visual impacts for
a range of moderately and highly sensitive receptors….”
(Emphasis added).
[135] It is clear that from the outset the appellant has expended considerable time, effort
and money in trying to ensure that any visual impacts caused by the proposal, if not
eliminated, are minimised. I also accept that the appellant would adopt best practices
-- 56 of 127 --
57
(as they evolve over time) to minimise visual impacts. I also accept that the visual
impact resulting from exposure to the quarry itself at the more distant receptors (e.g.
Palm Beach, Miami and Elanora) could fairly be described as minor if not
inconsequential.
Even in respect of more proximate receptors, many of the visual amenity issues
identified could be largely addressed by the imposition of appropriate conditions; a
matter Mr McGowan fairly acknowledged.146 However, even with the best of
intentions and practices, some residual visual impact would result. This was also
accepted by Mr Chenoweth. In his court report under the heading “Conclusions” he
summarised:147
“In summary, the proposal is acceptable in terms of visual impact and
landscape character changes because:
(a) the subject land is a key Resource Area (KRA 96) designated
for resource extraction;
(b) the proposed operations have been planned to maximise the
screening offered by the existing topography;
(c) although the Burleigh Ridge (a complex series of forested
ridges and hillside) has significant landscape value in the
Southern Gold Coast, one of the secondary ridges (Ridge J)
can be removed while still retaining the local ‘green
backdrop’ and forested skyline;
(d) most nearby and surrounding residents will be completely
screened from view and will see no evidence of quarrying.
The few residents who will see some part of the quarry rock
faces will do so at a distance (at least 1.5km and up to 9km),
only after several decades have elapsed and then only as a
minor proportion of an extensive green backdrop of forested
hills.”
[136] A number of matters arise out of those assertions by Mr Chenoweth. First, I fail to
see the significance of the first two matters raised. They may provide some context
or backdrop for the visual impacts but they do not address the extent and nature of
impacts per se. As to the third and fourth of those matters, while it is true that the
clearing of the disturbed area will be largely screened by the timbered buffer area and
that the major ridgelines, Ridge R3 and Ridge I, will not be disturbed during the life
of the quarry, all but the western most portion of Ridge J, the southwestern section of
146 T5-72 ll 1-40.
147 Exhibit 32 p 8.
-- 57 of 127 --
58
Ridge K and the whole of Ridge J4 will be removed.148 Notwithstanding the retention
of Ridges R3 and I, the removal of at least Ridge J would result in a removal of part
of the “green backdrop.” That was a matter acknowledged by Mr Chenoweth, but, in
his opinion, the loss was only “minor.”149
[137] The removal of these ridges raises two other more significant issues which are inter-
related. First, the exposure of benching to some receptors at or about 25-30 years.
Second, it is clear that Mr Chenoweth underestimated the impacts on visual amenity
that could occur during the earlier stages of establishment, development and
construction (i.e. in the order of 5 to 6 years).
[138] It was revealed during the course of the cross-examination of Mr Chenoweth that he
misinterpreted some of the data and, accordingly, underestimated the visual amenity
ramifications associated with levelling the eastern section of Ridge J (J4). No doubt
based on the EIS material and the input of Mr Chenoweth, during his opening Mr
Gore said in part:150
“…and your Honour will see the note above Ridge J ‘forested skyline
of Ridge J to be retained for 25-30 years then removed.’ So the effect
of the quarry development program is that Ridge J will be in place to
mask the main quarry pit to the rest of it for 25-30 years, during which
time the quarry bench faces which are developed. And your Honour
sees to the right of the identification of Ridge I a note ‘terminal quarry
bench face is 12m.’ And your Honour can see vegetation conceptually
shown on the bench faces. Those benches will be revegetated during
the 25-30 year period that we’re talking about.”
[139] The “concept” to which Mr Gore was referring, is represented diagrammatically in
Figure A5 of Mr Chenoweth’s court report.151 To the right hand side of Figure A5
reference is made to “views from old Burleigh Town for first 25-30 years of quarry
operations – e.g. RECEPTOR 21 (65m AHD).” The views from old Burleigh Town
after Ridge J has been removed is also shown diagrammatically. That receptors to the
east of the proposal (e.g. old Burleigh town) would not be exposed to any quarry
benching for 25-30 years was revealed to be incorrect.152
148 E.g. see Exhibits 53 and 62.
149 T4-41; also T5-29 ll 10-17.
150 T1-9, ll 5-14.
151 Exhibit 32, p 28.
152 T4-45 – T4-57 and T4-61.
-- 58 of 127 --
59
[140] After referring to the relevant transcript passages, it was submitted on behalf of the
respondent:153
“…as cross-examination demonstrated, close analysis of the proposed
staging details for the quarry… does not admit of that claim. And
indeed, Mr Chenoweth eventually came to acknowledge that his
‘generalised’ figure doesn’t illustrate what is happening on the ROM
pad and the benches behind it during the first five or six years (i.e.
during the development and construction phase). It emerged that a
benched faces (sic) of 150m length and 36m high above the ROM pad
(itself at RL55) would be revealed by completion of stage D3 within
2 to 3 years of commencement and would remain visible for 12-14
years.”154
[141] In the appellant’s supplementary reply, the following response was articulated:155
“Visual Amenity
6. In paras 266-268, the Council raises issues about Mr
Chenoweth’s prior appreciation of exposure of the benches
behind the ROM pad. These submissions fail to take into
account that Mr Chenoweth had dealt with the matter with
clarity in the 2013 VIA. Figure 4-9 in the 2013 VIA showed
both a plan view and a section view of those benches, and the
text of the VIA explained:
‘(a) Development Phase D4
As shown in Figure 4-8 and Figure 4-9, the upper
east-facing rock faces on the western side of the
Plant Site (the south-eastern end of Ridge ‘J’) will
progressively become visible from elevated parts of
old Burleigh Town as Phases D3 and D4 are
developed. The most visually prominent will be three
12m high fences stretching approximately 200m,
with a total area of exposed rock face at D4
estimated at 8,000m² above 62m AHD, as follows
(coded for cross-reference):
Face D4/62: the 12m face above a 150m long
curved bench varying in elevation between 60
and 64m AHD at Phase D4;
Face D4/74: above a 150m long curved bench
varying in elevation between 72 and 76, AHD;
and
153 Respondent’s written submissions p 74, para 268.
154 See also at T4-61, ll 24 – 31.
155 At p 2 paras 6-9.
-- 59 of 127 --
60
Face D4/86: a short uppermost face above a
bench varying in elevation between 84 and
88m AHD
However because the benches and faces will be
curved, and the upper rock face (below the hill
crest) is shorter than the two below, it is unlikely
that any single viewpoint will be within view of the
entirety of all three faces. The upper rim of the cut
hillside (Ridge ‘J’) will remain as a forested
ridgeline (see Figure 4-9), and as seen from Old
Burleigh Town the higher Ridge R3 behind will
remain as a vegetated skyline.”
7. Table 4-1 dealt with “visibility of quarry components from
sensitive visual receptors”, and with respect to the highest
part of Fenton Drive (PP01) and Phase D4, recorded:
“Upper 3 faces on the western side of the ROM
pad (above benches at average elevations of 62,
74m and 86m AHD) and wall behind stockpile
platform; exposed from phase D3 (within 2-3
years of commencement) to Q3 (possible time of
14 years), then removed.”
8. These features were dealt with in Mr Chenoweth’s evidence,
including that it would take about 5 to 6 years to reach stage
D4.
9. Moreover, any visibility of these rock faces has no adverse
impact on the proposal’s compliance with s.3.5.5.1(10)(c) of
CP 2016, because “the green backdrop provided by
ridgelines is not reduced…”, given that the upper rim of
Ridge J will remain as a forested ridgeline, and the higher
Ridge I and Ridge R3 behind (up to greater than RL150:
ex.54) will remain as a vegetated skyline.”
[142] Accepting the assertions of fact in paragraphs 6, 7 and 8 to be factually correct does
not, in my view, make a significant difference to the extent of the concessions made
by Mr Chenoweth in cross-examination nor to the consequences articulated in the
respondent’s written submissions to which I have just referred and largely accept.
[143] The evidence concerning visual amenity leads me to reach the following conclusions:
1. The visual consequences arising from the road works and haulage trucks are
largely inconsequential in the greater scheme of things.
2. The visual impact on more distant receptors i.e. at or about 4 to 5km distance
will be minor.
-- 60 of 127 --
61
3. The visual impact of the noise amelioration fence will introduce a material
visual impact to some of the residents in and users of Baden Ridge Road.
However, over time with the maturity of screening, that impact will
significantly reduce.
4. Even with the adoption of best practices, various physical elements of the
quarry, in particular the processing plant and the quarry benches will be
visible to a range of moderate to high receptors,156 albeit over different time
frames. Some receptors will not see the quarry benches for in the order of 25
years.
5. Notwithstanding that the retention of Ridges R3 and I will largely retain the
impression of the “green backdrop”, particularly from more distant
viewpoints, the removal of, in particular, Ridge J with its vegetated slopes,
will result in a not insignificant alteration to the existing appearance of ridge
lines west of the Pacific Highway. In this context I am unable to accept Mr
Chenoweth’s evidence which was to the effect that, taking all relevant matters
into account, the loss of Ridge J was a minor consequence.
[144] The consequences of these factual findings are dealt with below when dealing with
the relevant planning instruments.
Hydrology, water quality, groundwater and soils
[145] An enormous amount of evidence has been gathered during the evolution of this
proposal concerned with its impact, in the event that it were to proceed, on surface
and groundwater behaviour, and the consequences that would flow therefrom.
Consistent with that, during the course of this proceeding no less than 6 witnesses
were called to address these matters. Mr Collins for the appellant and Mr Bristow for
the respondent dealing with surface water. Messrs Briese, Shooter and Gimber for the
appellant and Mr Sutherland for the respondent dealing with groundwater and soil.
[146] Leaving aside any dispute about whether a waterway was or was not also a
“watercourse” for the purposes of the Water Act 2000 (a dispute it is unnecessary to
resolve for the purposes of this proceeding), it is beyond dispute that the proposed
development would result in the loss of a material number of waterways.157
156 Refer to Exhibit 57.
157 See e.g. Exhibit 54 and Exhibit 59 pp 40 and 48.
-- 61 of 127 --
62
[147] To the east of Ridge R3, and between Ridge I and Ridge J, runs Oyster Creek. To the
east of Ridge R3 and to the north of Ridge J runs Stony Creek. In the context of this
proposal, Oyster Creek is the most significant watercourse and it, to a significant
extent, flows in a west to east direction in close proximity to the southern side of
disturbance footprint.158
[148] It was agreed that by 1 to 2 km downstream the effect of the proposed quarry on
waterway flow would be insignificant irrespective of whether an environmental flow
release strategy was implemented or not.159
[149] In the JER of Mr Collins and Mr Bristow, Mr Bristow reported:160
“…the development proposes to significantly change the hydrological
regime of Stoney (sic) Creek and Oyster Creek and as a consequence
will likely have a negative impact on the habitat of the attendant creek
line ecology due to a change in water supply for those habitats.”
[150] This was a view repeated by Mr Bristow in his court report.161 Mr Collins did not
disagree with Mr Bristow’s opinion that the proposal would significantly change the
hydrological regime of Stony Creek and Oyster Creek. Indeed, he seemed to accept
that assessment but then went on to consider whether the existing environmental
flows could be artificially replicated. In this context, he said:162
“However, based on the environmental flow analysis I have carried
out, there is ample water capacity in the site water supply dam to
provide dedicated environmental flow releases, in a variety of forms
to a range of locations across the site, if this is deemed to be required
by the Court. Similarly, additional piping can be installed to allow
additional releases to Oyster Creek in the south and less additional
flow to Stoney Creek in the north, if there is concern about additional
release days and volumes to the northern catchment.”
[151] That alternate environmental flow options existed seemed to be a matter of
agreement:163
“Despite the divergence in views of the groundwater experts, we agree
that there is sufficient on-site water supply and a range of delivery
options to enable environmental flow releases (if required) to both the
Stoney Creek (sic) catchment and the Oyster Creek catchment if
158 Exhibit 20, p 279.
159 Ibid p 17, para 8.
160 Ibid p 29.
161 Exhibit 59 p 26.
162 Exhibit 20 p 30.
163 Ibid p 20.
-- 62 of 127 --
63
deemed necessary to provide additional ecological water supply to
either of these site catchments…”
[152] By reference to the court reports of Mr Collins and Mr Bristow, it is clear that there
were many areas of agreement, and that the key areas of disagreement were more
concerned with what descriptions ought be given to the waterways and how
environmental flow discharge ought be addressed. In his court report under the
heading “Conclusions”, Mr Bristow reported:164
“The extent of watercourses on the site has been understated and in
my opinion an additional 1100-1200m of watercourses in both the
Oyster Creek catchment and the full length of Stony Creek should be
acknowledged.
The proposed quarry development will change the hydrological
regime of the catchments of Stony Creek and Oyster Creek.
This change in basic terms will reduce the water supply to the creek
riparian communities by approximately 40%.
The change will reduce the peak flows in the catchment though not
duration and form of the flood flows.
The pit provides a significant detention capacity and coupled with the
quarry water supply dam, will capture sufficient water to meet the
quarry water supply needs and have water available for return to
attempt to reconcile the change in hydrological regime.
It is likely that with detailed design and ongoing monitoring and
maintenance, the hydrological regime can be replicated.
The current proposal and suggested environment return flows do not
replicate the hydrological regime. At best they will see increased
annual flows to Stoney Creek of 76% over the pre-existing condition
and 62 flow days caused by dam overflows. Oyster Creek is more
balanced at 11% increase in annual flow volumes, with only 6 flow
days due to overflows.
The proposal to return environmental flows to the head of Stoney
Creek as a pump flow during the life of the quarry is supported.
The proposal to return environmental flow to Oyster Creek part of the
way along its length as pumped is not supported.
164 Exhibit 59, p 26.
-- 63 of 127 --
64
A diffuse flow returned into the northern slope of Oyster Creek from
the confluence with stream OT4 to the extent of the watercourse at
OT9, would better mimic the water supply to the creek riparian
community.”
[153] Mr Collins, in his court report, stated:165
“My key conclusions are as follows:
1. (Mr Bristow) and I agree on several key items related to the afore
mentioned aspects of the project including:
(a) water quality-related matters have been (or can be)
appropriately addressed in existing or appropriately revised
documentation;
(b) the effect of the proposed quarry on waterway flows is
insignificant by 1 or 2km downstream of the site; and
(c) the water supply dam can provide environmental flow releases
(to mitigate hydrologic impacts from the proposed quarry).
2. DB and I disagree on the following topics:
(a) the way by which potential environmental flow discharges to
Oyster Creek should be provided;
(b) whether waterways within the extent of the proposed works are
watercourses.”
[154] As I have already indicated, the second point of disagreement identified by Mr Collins
is not one that has to be resolved in this proceeding. As to the first matter, I am
sufficiently satisfied that an appropriate alternate environmental flow regime could
be designed and implemented to the satisfaction of both Mr Collins and Mr Bristow.
The quarry dam where water would be stored and from which environmental flows
would be distributed is situated between the disturbance area and Stony Creek.166
[155] For the reasons given, my conclusions concerning the evidence of Messrs Collins and
Bristow is as follows:
1. A material number of waterways will be destroyed as a consequence of the
proposal.
2. The loss of those waterways will have a significant detrimental impact to the
hydrological regime of the catchments of Stony Creek and Oyster Creek.
3. It is more likely than not that the existing hydrological regime could be
replicated.
165 Exhibit 33, p 13.
166 E.g. see Exhibit 20 at p 279.
-- 64 of 127 --
65
4. The effect of the proposal on waterway flows is insignificant within 1 or 2km
downstream of the site.
[156] The ramifications of these conclusions are dealt with in more detail when dealing
with the issues of the environmental/ecological consequences and conflicts with the
respondent’s planning schemes.
[157] Turning then to the question of groundwater, four witnesses gave evidence on this
topic. Messrs Briese, Shooter and Gimber for the appellant and Mr Sutherland for the
respondent. In their first JER the following issues in dispute were identified:167
“Issue 1
The potential for groundwater draw down beyond the site boundary
and subsequent impacts on mapped or (otherwise) acid sulphate
soils…
Issue 2
The presence of pyrite in the rock (to be quarried or otherwise
impacted) and the potential for associated acid generation otherwise
known as ‘acid mine drainage’ and the potential associated water
quality management and product impacts…
Issue 3
Near surface groundwater impacts and the potential for interactions
with site water courses and effect on associated soil profiles and
seepage zones…
Issue 4
Surface water and groundwater impacts and the potential for effects
on mapped or unmapped Groundwater Dependent Ecosystems and
Wetlands within and beyond the site and effects on proposed site
management measures…
Issue 5
Surface water, groundwater and recharge and the potential for changes
to the near surface hydrological regime and contributions to
downgradient systems beyond the site…”
[158] Issues 1 and 2 are no longer matters of dispute. In relation to the remaining three
issues, while there was a significant level of disagreement between the experts about
the extent of the impacts that might result from the alteration to the groundwater
167 Exhibit 21, pp 1 and 2.
-- 65 of 127 --
66
regime caused by the quarry, there was agreement that insofar as there were harmful
environmental consequences, engineering solutions could be put into place to address
those consequences. In their second JER Messrs Briese and Shooter and Mr
Sutherland, under the heading “Points of Disagreement” recorded:168
“There are a number of points of disagreement between us (as
articulated in our appendices 5 and 6 (relating to specific aspects of
soil mapping and near surface groundwater movement. However, we
agree that there are solutions to overcome these differences, they may
not be considered to be significant by others.
Given that we have explored, in detail, solutions overcoming each
issue, our differences, to an extent, may fall away.
We consider that adopting this approach in preparing this joint report
is the best way that we can, collectively assist the court.”
[159] During Mr Sutherland’s cross-examination, following a number of questions, it was
put to Mr Sutherland:169
“Q: Yes. So it’s fair to say, is it not, Mr Sutherland, that it’s your
position that provided the court imposes a condition or
conditions which reflect the solution that’s described in the
JER, or some agreed or determined equivalent, you don’t
point to any reason for refusal of this application from within
your field of expertise?
A: That’s correct.”
[160] The “conditions” referred to by Mr Gore are set out in paragraph 24 of the second
JER. It is unnecessary to set them out here. According to the respondent, if I were to
decide that the quarry should be approved, the solution/conditions identified in
paragraph 24 of the second JER should be imposed on the basis that a precautionary
approach was warranted, as it would “remove uncertainty by establishing whether
there is a change to the downslope hydrological regime that warrants mitigation, and
provides for appropriate introduction of measures to return water to the landform, if
warranted.”170
[161] It was submitted on behalf of the appellant that the conditions were unnecessary,
having regard to the evidence of Messrs Briese, Shooter and Gimber. The key point
of difference between the experts for the respective parties centred around the nature
and behaviour of groundwater within the subject landform. Or, to adopt the words of
168 Ibid, p 10, [38]-[40].
169 T16-33, ll 10-15.
170 Respondent’s written submissions at [446].
-- 66 of 127 --
67
Mr Sutherland, “The way in which water moves through the soils in the landscape on
the subject land.”171
[162] According to Mr Sutherland:172
“On this site, the extremely weathered material between the soil and
the parent rock (or saprolite) overlies rocks of varying densities and
permeabilities. The saprolite, or extremely weather material between
the soil and the underlying rock, potentially acts a significant water
store and movement pathway downhill.”
And,173
“Depending on the number and frequency of rainfall events, water
flows as ‘pulses’ of soil moisture moving through the profile, as
wetting fronts. It is for this very reason that drainage is often
deliberately introduced into soil profiles to intercept and manage such
wetting fronts.”
[163] Mr Briese, with the advantage of the evidence of Mr Shooter, strongly disagreed with
Mr Sutherland’s opinions. For reasons that will become apparent below, it is not
necessary for me to finally resolve the competing views of Mr Sutherland and Messrs
Briese and Mr Shooter. However, for the sake of completeness I would observe that,
on balance, I prefer the evidence of the latter experts. In my view, their opinions were
supported by more thorough and logical investigation, and their evidence was not
materially shaken in cross-examination. On the other hand, I found some aspects of
the evidence of Mr Sutherland, on some apparently important matters, to be
somewhat unconvincing. In his evidence in chief, Mr Sutherland relied, at least in
part, on the shape of certain trees located on the land as supporting his theory174 and
on the presence, or lack thereof, of other vegetation.175 Insofar as Mr Sutherland’s
reliance on vegetation is concerned, I much preferred the evidence of Mr Francis
concerning the explanation for the presence, or otherwise, of vegetation and, in
particular, his more likely explanations for the existence of “kinked” trees on the
land.176
171 Exhibit 52, p 41.
172 Exhibit 51, p 68, [79].
173 Ibid, at [35].
174 Exhibit 52, p 98: T16-9, ll 24-47 – T16-10.
175 T16-11 – T16-12.
176 T17-58 – T17-60.
-- 67 of 127 --
68
[164] I also found Mr Sutherland’s evidence dealing with an existing dam/pond located in
the western section of the land to be less convincing than the explanation provided by
Mr Briese. In his court report Mr Sutherland stated:177
“…this dam is located on the top of a ridge line and has a small
upstream catchment with little surface water inflow. The pond/dam
water levels do not appear to exhibit significant fluctuations. These
features, together with the hydrochemistry, indicate to me that this
pond/dam is groundwater fed.” [Footnotes omitted].
That proposition was repeated by Mr Sutherland in his evidence in chief.178
[165] According to Mr Briese, it was highly improbable that the pond/dam was groundwater
fed. That was so for at least two reasons. First, the groundwater would have to
effectively flow uphill.179 The second was that the electrical conductivity of the water
was more consistent with the pond/dam being rain-fed than being sourced from
groundwater.180 Mr Briese gave evidence critical of Mr Sutherland’s theory
concerning the pond/dam,181 which Mr Sutherland heard firsthand or had his attention
drawn to prior to him giving evidence. During the course of his cross-examination, it
was suggested he found Mr Briese’s evidence to be “convincing”. Mr Sutherland
responded:182
“What I would do is probably– I’ll be responsive and say ‘not quite.’
I have an enormous amount of respect for Mr Briese, but my point
remains this is an unusual feature which you wouldn’t normally expect
to see in a landform. That the chloride in the dam is pretty much the
same as it was a year previously. I accept that the dam receives surface
water from rainfall. But in my careful examination of the catchment
feeding into that dam, it’s very small and it’s too– too small to
consistently maintain that level within the dam, in my view. Now, I’m
saying that based on aerial photographs. I don’t know– there’s no data
that I’ve seen looking at the fluctuation in the dam which would
influence that conclusion. But the– every time– if you look at an aerial
photograph, it appears to be full all of the time, which is unusual in
itself. It’s a very unusual position in the saddle in the landform, and
the chloride results indicate to me that it– it does have a component of
groundwater in it, and depending on the amount of surface water
reporting to that dam, those– those ratios may change. So I’m not–
177 Exhibit 52, p 17.
178 T16-15, ll 15-28.
179 Mr Briese’s supplementary report: Exhibit 100, pp 11-12.
180 Ibid.
181 T13-25 – T13-28.
182 T16-53, ll 5-28.
-- 68 of 127 --
69
I’m not dismissing Mr Briese’s proposition that he says it’s
impossible; it’s just that I have a different view.” (Emphasis added).
[166] Mr Sutherland was then asked, “Where would the water be coming from?” and he
responded:183
“Well, that– that I don’t know. I suspect there’s a contribution of
groundwater into that dam, and I suspect that there’s some surface
water run-off feeding it– sorry, direct rainfall feeding it as well, as well
as what is now a very small catchment on the western side.”
[167] Later in his cross-examination, Mr Sutherland seemed to not want to put too much
weight on the dam, considering it to be “part of the jigsaw (that) adds weight to my
conclusion and I’m not putting it any higher than that. I would like more data.”184
[168] Finally on this topic, I should record the respondent’s position concerning hydrology.
Insofar as CP 2003 is concerned it was asserted that while engineering solutions for
restoring flows in Oyster Creek and Stony Creek may exist, “that does not change
the fact that the evidence in relation to surface water demonstrates that a significant
proportion of waterways…will be obliterated by the development footprint.” It is then
asserted that the “obliteration” of so many waterways is the “antithesis” of what CP
2003 contemplated.185
[169] In dealing with CP 2016, the respondent submitted:186
“Council’s position on matters of hydrology in connection with CP
2016 may also be shortly stated.
It may be accepted that evidence in relation to surface water now
demonstrates that acceptable outcomes in terms of water quality,
including downstream of lot 105 can be achieved. That will require,
for example, that the erosion and sediment control plan and overall
site storm water management plan be reworked…
And subject to the implementation of appropriate engineered
solutions, flows can be restored in Oyster Creek and Stoney Creek.”
[170] The respondent’s written submissions then go on to contend that notwithstanding the
existence of engineering solutions, the impact on the waterways was in “stark
183 T16-53 ll 32-35.
184 T16-55, ll 23-24.
185 Written submissions at [432]-[435].
186 Ibid, [436], [437] and [438].
-- 69 of 127 --
70
conflict” with the objects of CP 2016. The issue of that asserted conflict is dealt with
below.
Terrestrial ecology
[171] In total the experts concerned with terrestrial ecology were involved in the preparation
of no less than four JERs. The appellant relied on Mr Francis who addressed terrestrial
flora and Mr Agnew in respect of terrestrial fauna. The respondent relied on Dr
Watson who addressed both flora and fauna. It should also be noted that terrestrial
and aquatic ecology was also extensively examined not just for the purpose of this
proceeding, but also during the EIS coordinated projects material and the
Commonwealth approval phases. As to the latter, Dr Watson accepted that generally
speaking, the Commonwealth tended to scrutinise the potential environmental
impacts associated with projects such as this carefully.187
[172] Not surprisingly, all three experts were concerned about the impact the proposed
development might have on groundwater dependant ecosystems (“GDE’s”) and
riparian ecosystems outside the disturbance footprint.
[173] Insofar as the GDE’s were concerned they agreed that provided adequate remedial
practices and procedures were adopted to redistribute hydrological flow, it would be
“unlikely” that the proposal would have an adverse impact on those ecosystems. In
their third JER it was recorded:188
“In summary, we accept the agreement by the experts in Soils and
Groundwater that the contribution of regional groundwater to the
GDE’s (sic) and wetlands on and immediately adjacent to the site can
safely be discounted, i.e. the quarry is unlikely to have an adverse
impact on the groundwater supply to those GDE’s (sic).
We also accept that there are mechanisms available to redistribute
hydrological flows through the landscape, to a number of
communities/ecosystems not necessarily only related to mapped
GDE’s and wetlands. These measures are reported to have the
potential to maintain the hydrological regimes within the catchment.
However, JW notes that the proposed ‘mechanism to redistribute
hydrological flows’ has not been confirmed and, as identified by DB,
does not address all the hydrological requirements of the catchment
and or ecosystems. I accept that modifications, as suggested by the
187 T20-41.
188 Exhibit 27 p 149, paras 2.1.1.13 – 2.1.1.15.
-- 70 of 127 --
71
hydrological experts, has the potential to assist in appropriately
maintaining the hydrological regime.
We acknowledge that the aquatic ecology experts are likely to provide
further comment with respect to GDE’s. Our conclusion regarding
mapped GDE adverse impact is based on our understanding of the
agreement reported within the Soils and Groundwater JERs.”
[174] That there was similar agreement in respect of the riparian ecosystems was less than
clear.189 While Dr Watson seemed prepared to accept that provided appropriate
remedial steps were taken, impacts on the wider riparian ecosystems may be unlikely,
he remained concerned about the more proximate ecosystems. In his court report Dr
Watson stated:190
“The buffer (setback) to Oyster Creek is narrow, and given changes to
the local topography… the ecosystems associated with the creek will
be modified, with a loss of integrity and biodiversity. It is also noted
that there is no buffer (setback) to any of the drainage lines associated
with Oyster Creek as these areas will be removed for the quarry.
The term ‘edge effects’ refers to a variety of degrading effects which
have potential to occur within a zone of disturbance from the outer
edge of a habitat area. Ecosystem degrading impacts (e.g. changes in
nutrient levels, exposure to solar radiation and wind) change the
dynamics of the community and in turn alter the faunal and floral
assemblages…
The quarry and associated infrastructure will create an edge between
existing vegetation/habitat and the development. In regards to the
quarry, the staging over time (decades) will create new habitat edges
associated with the progression of each major phase.
Changes to the vegetation community due to the significant landform
changes will exacerbate edge effects, which will change vegetation
structure and composition…
As noted by the EIS Reports, State mapping and ground truthing (site
observations), these communities are not common and provide a
diversity of habitat and resources for fauna and flora. These
communities are dependent on a number of factors, soil moisture being
one. In addition to understanding the soil water mechanics, it is
important to note that the proximity of the proposed disturbance
189 Ibid pp 149-152.
190 Exhibit 48, pp 7-8 paras 37-42 and 48.
-- 71 of 127 --
72
footprint to the drainage lines/creeks, not only has the potential to
exacerbate the impacts to and losses of soil moisture, but also increase
edge effects and compromise the functioning of associated
ecosystem.”
[175] At one stage Dr Watson seemed to be suggesting that the “literature” indicated that
there should be a 250m setback or buffer between the disturbance footprint and Oyster
Creek to “conserve the broadest suite of bird species…”191 The proposed setback is
30m from the northern bank of Oyster Creek. On balance I found Dr Watson’s
evidence on this topic to be somewhat confusing in parts but, at the end of the day,
consider that his concerns would be met with a buffer or setback from the centreline
of Oyster Creek of 150m. That figure is comprised of 100m of buffer/setback plus a
further 50m to address “the edge effects.”192 However, even that figure seemed to be
within “a range which might assist in achieving a balance.”193
[176] For reasons given below, it is not necessary for me to finally determine what the
appropriate setback from Oyster Creek should be. That said, I can see no basis, having
regard to the definition of “edge effects” given by Dr Watson, for increasing a 100m
buffer by an additional 50m. It is also of significance that the Council’s own
requirement is that the setback be no less than 30m, a matter acknowledged by Dr
Watson.194 Also, notwithstanding Dr Watson’s explanation for the situation at the
Hansen (Wolfdene) quarry, I consider the evidence that a 50m buffer was thought to
be adequate there to be of some relevance. While expressing no final view on the
matter, it strikes me that an appropriate buffer width would be no less than 30m and
up to 50m+ in more sensitive areas.
[177] While acceptable terrestrial outcomes would in all likelihood be achieved outside the
disturbance footprint, with the notable exception of the pair of white bellied sea
eagles, to use the respondent’s language, the existing landscape within the disturbance
footprint would be effectively “obliterated”. Or to use the words adopted by Mr
Francis, the removal of the ridgeline “would irreversibly alter the landscape.”195
191 T21-3, ll 5-15; T20-36, ll 25-30.
192 T20-27, ll 2-15; T21-5, ll 1-46; T21-6, ll 1-44.
193 T21-6, L 22.
194 T21-6, L 15.
195 T19-13, ll 36-42.
-- 72 of 127 --
73
[178] The impact on the environment within the development footprint could only be
described as catastrophic. Not only would ridgelines and gullies disappear, but so
would a number of waterways and in the order of 30,000 trees including 23,000
NJKHT and other vegetation.
[179] In the second JER, Mr Agnew stated:196
“There is no apparent disagreement that the 66 ha development
footprint supports habitat for a variety of native fauna and species of
significance. Similarly, there is no apparent disagreement that 151 ha
buffer supports habitat for native wildlife, threatened fauna and
species of local significance.”
Elsewhere in the JER, Mr Agnew said:197
“Whilst the proposed disturbance footprint (66 ha) does support
habitat which may be used by threatened fauna, the dominant habitat
– advanced dry sclerophyll regrowth – does not support high quality
conditions and/or resources for those species. The proposed
development will result in habitat loss, though on balance, it is
concluded that the proposed retention and management of habitat
within the buffer area (151 ha) would be sufficient to maintain ongoing
habitat values for those species previously recorded within – or
considered likely to occur within – habitats of the site.”
[180] It is of course significant that the balance area would be sufficient to maintain ongoing
habitat values but that does not alter the fact that more than 60 hectares of habitat that
may be used by native fauna and species of significance will be lost, even if it is of
an inferior quality to the balance area. Later in the JER, Mr Agnew expressed the
opinion that the quarry footprint would not result in a significantly different outcome
to fauna when compared to a development outcome that might be delivered under the
Reedy Creek Structure Plan, which extends over an area in the order of 76 ha. I
cannot agree with that conclusion. Proposed development under that plan would not
see the destruction of ridges, gullies and waterways nor the clearing of 20,000 plus
NJKHT.
[181] Turning then more particularly to flora, Mr Francis acknowledged that the existing
drainage lines and creeks involve floristic diversity.198 As already identified, Mr
196 Exhibit 27 p 107, para 7.2.1.16.
197 Ibid p 108, para 7.2.1.17.
198 T19-9, ll 19-28.
-- 73 of 127 --
74
Francis also accepted the obvious, namely that if developed the quarry will
irreversibly alter the existing landscape.
[182] Finally in respect of this topic, I am satisfied that threatened species (the Slender
Milkvine) and all locally significant plant species that do or might exist are capable
of being translocated and propagated within the balance buffer area and that the
balance buffer area will be better managed under management plans that will address,
among other things, landscape rehabilitation, bushfire risks and feral animals etc.
Aquatic ecology
[183] The aquatic ecologists, Dr Thorogood for the appellant and Ms Thorburn for the
respondent prepared three JERs.199 Under the heading “matters of disagreement” Dr
Thorogood and Ms Thorburn said:200
“We disagree on:
The significance of the permanent loss of ephemeral drainage
lines/waterways;
The nature and significance of impacts to aquatic ecology, both
on-site and immediately downstream of the site, as a result of
changes to hydrology;
(Potentially) the significance of impacts to groundwater
(including on areas that may be surface-expression
groundwater-dependant ecosystems (“GDEs”)); and
The degree/extent to which the project will offset negative
impacts to aquatic ecology, and result in benefits to
downstream waters.”
[184] As was the case with the terrestrial ecology experts, Dr Thorogood and Ms Thorburn
needed to have regard to the conclusions reached by the hydrology and groundwater
experts. In their third JER, they set out their “revised views” flowing from a
consideration of the opinions of those experts. That JER was particularly concerned
with changes to the magnitude and pattern of flow in both Oyster and Stony Creeks
with and without mitigation scenarios and, of course, the ecological consequences of
predicted changes in flow of both Oyster and Stony Creek.
[185] During his cross-examination, Dr Thorogood summarised the three areas of
disagreement of significance. First, the value or significance of the waterways and
199 Exhibit 28.
200 Ibid p 23, para 37.
-- 74 of 127 --
75
wetlands that would be or potentially could be affected by the proposed development.
Second, the likelihood and severity of changes to the hydrologic regimes of Oyster
Creek and Stony Creek as a result of the removal of that part of their upstream
catchment which would become the quarry pit. Third, the significance of the benefit
(if any) of the mitigation works which would be carried out by the appellant and, in
particular, the benefit of reinstating and repairing riparian habitat resulting from
improved water quality.201 Dr Thorogood’s summary was accepted by the respondent.
[186] In my view, only the first of the three matters identified by Dr Thorogood is of any
real consequence in the circumstances of this appeal. That is so for the following
reasons. First, for reasons already given I am sufficiently satisfied that catchment
flows lost by the development of the quarry could be replaced, albeit artificially.
Second, as was identified when dealing with the topic of hydrology, water quality and
groundwater, the effect of the proposal on waterway flows is essentially insignificant
by 1 or 2km downstream of the site. And, while debate may still exist about the extent
of the downstream benefits that might result from the water quality control measures
proposed by the appellant, it is tolerably clear that there will be some water quality
benefits.202 Or, perhaps more significantly, no adverse impacts.
[187] During the course of his cross-examination by Mr Fynes-Clinton, Dr Thorogood was
taken to various extracts from the aquatic ecology report prepared in the EIS
process.203 In that report, it was said:204
“The current condition of freshwater aquatic ecosystems within the
project area are generally in the moderate to good condition, and
consistent with the ecological condition of aquatic ecosystems
throughout the wider catchment.”
[188] Later in the report205 the biological values of the aquatic ecosystems were described
as being “moderate to excellent and consistent with those of the wider catchment.”
A description Dr Thorogood agreed seemed to be a more “glowing endorsement.”206
201 T27-6; respondent submissions at para 290.
202 For example in the lower eastern area near Oyster Creek where illegal 4 wheel drive activity occurs.
203 Exhibit 5 V5, p A3165.
204 Ibid p 3302.
205 At p A3292.
206 T27-23, ll 38-45.
-- 75 of 127 --
76
[189] After being referred to those descriptions, Dr Thorogood said that he would prefer to
place greater weight on the more detailed studies. After making that observation, the
following exchange took place:207
“Q: Alright. And we’ll get to those. But just – you’re not
– or just in terms of what appears on page A3292, if
one were to accept the proposition that the subject site
had aquatic ecological values which were moderate to
excellent, one would necessarily accept the
proposition that the site, as an aquatic ecologist, and
forgetting about other things, one would necessarily
accept the proposition that the site is one worthy of
conservation and protection?
A: Firstly, I would encourage you not to take particular
sentences and seek to build a picture around those out
of the context of the balance of material ---
Q: So do I ignore moderate to excellent? I don’t mean to
catch you up. I don’t want to waste time?… I’m sorry.
Do I just ignore the conclusion on page A3292 that
the biological values of aquatic ecosystems are
moderate to excellent?
A: No, I’m not saying you should ignore it.
Q: Right?
A: But I am encouraging you to read that in the context
of the other material that’s been presented, and come
to a conclusion based on the balance of that material,
the increasingly detailed justifications and
explanations that are provided.
Q: Alright?
A: But that’s my first response. My second response, that
is more directly to your question, is that if that was
accepted, as it were, at face value, would it then justify
the conservation of those waterways?
Q: Well, my question to you specifically was as an
aquatic ecologist… and for the moment ignoring
anything else. If land possessed those characteristics,
namely, moderate to excellent biological values…
that would be land which is worthy of conservation
and protection?
A: Well, I’d encourage you to then read the following
clause of that sentence, because there it indicates that
whatever the qualities are exhibited by the waterways
on site, they are consistent with those of the wider
207 T27-24 to T27-25.
-- 76 of 127 --
77
catchment, and that’s something that the further more
detailed work that I’ve been involved in supports…
and indeed Ms Thorburn has expressed an opinion
that supports that… And on that basis we’d return to
the conclusion that what’s on site is not exceptional.
Q: No?
A: So, on what justification do we conserve it? If we look
at the guidelines, for example, that, you know, various
government agencies and instruments promulgate,
one of the things we would be looking for is that it is
not just great, but its better, or a particularly good
example of its type. And I don’t think there’s anything
in the whole of the material that I’ve been involved in
presenting that suggests that’s the case.
…
Q: Right. But if something is – on your approach, if
something is merely an example of habitat which has
ecological values, but those values are shared over a
much larger area than the particular parcel you’re
focusing on, is not, in itself, worthy of conservation
or protection?
A: I think that’s correct. What you’ve put to me…
doesn’t justify its conservation per se.
Q: Alright. And is that because the habitat has no value,
or because there will be lots more of the same habitat
leftover?
A: Well, I think just following the train of thought that
we have been pursuing, if this is the particular criteria
we’re considering, our reason for – in that column of
the ledger, so to speak, for not – not favouring
conservation, would indeed be that it is not – sorry.
That it is well represented beyond the project site.”
[190] As Dr Thorogood acknowledged, the quarry footprint would result in the destruction
of approximately 2.5km of “ephemeral drainage lines and waterways” which “by
definition… are at times aquatic habitat.”208
[191] In her court report,209 Ms Thorburn seemed to take strong exception to Dr
Thorogood’s description of the waterways being ephemeral; that is, only lasting or
208 T27-31 ll 44-46, T27-32 ll 1-5.
209 Exhibit 51, p 36.
-- 77 of 127 --
78
existing for a few days, or to use her words, “only flowing for a matter of days each
year.” Ms Thorburn said:210
“These assumptions have influenced the surface water and
groundwater impact assessments which have both assumed (based on
advice from Dr Thorogood and his team) that the waterways on the
site are ephemeral, only flowing for a matter of days each year, and
that there is no base flow in the waterways. This advice has affected
the way that models have been developed and the assessment of
groundwater impacts.
My evidence as presented in this report does not support the above
paradigm. Rather, my observations, supported by the results of site
surveys, indicate that:
The proposed development footprint contains minor (stream
order 1 and 2) tributaries to Oyster and (to a lesser extent)
Stony Creeks that are in good condition and have a diverse
range of aquatic habitat types. These tributaries have small
pools and flows for a period of days to weeks after rainfall,
which support aquatic species including diverse
macroinvertebrate communities that contain some sensitive
taxa…” (Emphasis added).
[192] As already identified, while Dr Thorogood did not consider that the waterways to be
lost held “exceptional” biological value, he was prepared to accept a range of between
moderate to excellent. Also, apart from the lower areas of Oyster Creek affected by
illegal 4 wheel drive activity, I did not take Dr Thorogood’s evidence to be at odds
with the description of the waterways being in good condition and providing a diverse
range of habitat.
[193] As to Ms Thorburn’s assertion that the waterways/tributaries are anything other than
ephemeral but have “small pools and flows for a period of days to weeks after
rainfall”, the evidence does not support such a conclusion. Indeed, in this context I
found Ms Thorburn’s evidence to be somewhat confusing. At the very outset of her
cross-examination and in the JER process, she was prepared to accept that the
waterways on the site were ephemeral,211 a description not only accepted by the
respondent’s counsel during the cross-examination of Dr Thorogood but also in its
written submissions.212 As I understand it, the term “ephemeral” does not necessarily
210 Ibid paras 87 and 88.
211 T29-59 L 1.
212 At para 289.
-- 78 of 127 --
79
exclude pooling and small stream flows for days after a significant rain event,213 but
it would exclude flows “for weeks” after such an event.
[194] Ms Thorburn also agreed that there were no matters of national environmental
significance relevant to aquatic ecology that would be affected by the proposed
development. And, that there were no matters under the State Planning Policy, or
matters of state environmental significance including rare or threatened aquatic
species, relevant to aquatic ecology that might be affected by the proposed
development.214
[195] I also accept that there was no meaningful evidence that the removal of the waterways
within the disturbed area would have anything other than a negligible effect on the
downstream macroinvertebrate and fish communities referred to by Ms Thorburn. A
matter about which she seemed to agree.215 Also, while I accept the caveat placed by
Ms Thorburn, the evidence (such as it is) strongly indicates that no endangered
vulnerable or near-threatened species of aquatic flora or fauna have been recorded
from or are likely to occur in the waterways of the disturbed area.216
[196] By reference to the matters dealt with above, the evidence makes it tolerably clear
that the destruction of the waterways within the disturbed area will not have any
meaningful effect on downstream aquatic flora and fauna and that the aquatic flora
and fauna within those waterways are not of themselves so unique or exceptional to
warrant a strong preference or desire for conservation. That said, the inescapable
conclusion is that the loss of some 2.5km of waterways will remove habitat or
otherwise destroy aquatic ecosystems within the disturbance footprint which could be
described as falling within the range of moderate to excellent.
The planning documents and conflict
[197] Pursuant to s 80 of the SPA, a planning scheme is a statutory instrument under the
Statutory Instruments Act 1992. Accordingly, the construction of planning documents
must begin with the consideration of the text used and the application of the ordinary
principles of statutory interpretation. As was observed by Muir JA in Meridien AB
213 Ibid para 305.
214 T29-58 ll 35-43.
215 T29-64 ll 6-20.
216 T29-64 ll 22-40.
-- 79 of 127 --
80
Pty Ltd v Jackson217 the starting point for those principles may be extracted from the
judgment of the High Court in Alcan (NT) Alumina Pty Ltd v Commissioner of
Territory Revenue (Northern Territory)218:
“This court has stated on many occasions that the task of statutory
construction must begin with a consideration of the text itself.
Historical considerations and extrinsic materials cannot be relied on to
displace the clear meaning of the text. The language which has
actually been employed in the text of legislation is the surest guide to
legislative intention. The meaning of the text may require
consideration of the context, which includes the general purpose and
policy of a provision, in particular the mischief it is seeking to
remedy...” (Citations omitted).
[198] However, as has been repeatedly recognized, planning schemes need to be read as a
whole and as intending to achieve a balance between often conflicting desirable
outcomes. In 2010, Rackemann DCJ said:219
“The Court has taken a similar approach to the interpretation of
provisions dealing with other kinds of impacts.
This approach is also consistent with the well settled principles of
construction of planning schemes, which are largely the work of town
planners, not parliamentary counsel. Those principles include that they
should be construed broadly, rather than pedantically or narrowly and
with a reasonable, practical approach. Given the nature of planning
schemes, it should not readily be inferred from the absence of an
express qualification that the relevant provision requires no impact at
all, no matter how insubstantial, trivial or insignificant. That applies
even though a qualification may be expressed in other parts of the
planning document….” (Citations omitted).
[199] In 2010 the Court of Appeal in Lockyer Valley Regional Council v Westlink Pty Ltd220
said:
“…phrases such as ‘maintain and preserve’ and ‘preserve and
enhance’ must be read in context and bearing in mind that when any
development occurs some amenity impairment will generally result…
planning schemes should be construed broadly, rather than
pedantically or narrowly, and with a sensible, practical approach…”
(Citations omitted).
217 [2013] QCA 121.
218 (2009) 239 CLR 27 at [47].
219 Newing v Silcock [2010] QPELR 692 at [62] – [63].
220 (2011) 185 LGERA 63.
-- 80 of 127 --
81
[200] To a similar effect was the judgment of the Court of Appeal in Zappala Family Co
Pty Ltd v Brisbane City Council221:
“The fact that planning documents are to be construed precisely in the
same way as statutes still allows for the expressed view that such
documents need to be read in a way which is practical, and read as a
whole and as intending to achieve balance between outcomes…”
(Citations omitted).
[201] Bearing those principles in mind, it is then necessary to turn to the issue of conflict.
Allegations of conflict with the planning schemes loom particularly large in this case.
Indeed, the appellant concedes that there is conflict with CP 2003222 and more will be
said about that below. In this context, s 326(1) of the SPA relevantly provides:
“326 Other decision rules
(1) The assessment manager’s decision must not conflict
with a relevant instrument unless—
(a) the conflict is necessary to ensure the decision
complies with a State planning regulatory
provision; or
(b) there are sufficient grounds to justify the
decision, despite the conflict…”
Here of course, this court stands in the position of the “assessment manager”.
Sufficient grounds for the purposes of s 326(1)(b) means matters of public interest
and does not include the personal circumstances of an applicant, owner or interested
party.223
[202] In Weightman v Gold Coast City Council224 Atkinson J (with the other members of
the court agreeing) said:
“In order to determine whether or not there are sufficient planning
grounds to justify approving the application despite the conflict, as
required by s. 4.4(5A)(b) of the P & E Act, the decision maker should:
1. Examine the nature and extent of the conflict;
2. Determine whether there are any planning grounds which are
relevant to the part of the application which is in conflict with
the planning scheme and if the conflict can be justified on
those planning grounds;
221 (2014) 201 LGERA 82 at [56]; see also Savage v Cairns Regional Council (2016) 214 LGERA 192.
222 T34-3 ll 35-44.
223 SPA Schedule 3.
224 [2003] 2 Qd R 441 at [36].
-- 81 of 127 --
82
3. Determine whether the planning grounds in favour of the
application as a whole are, on balance, sufficient to justify
approving the application notwithstanding the conflict.”
[203] In addition to articulating the necessary “tasks” to be considered in cases involving
conflict, Her Honour said:225
“The proposal must be refused in such a situation if there are not
sufficient planning grounds to justify the approval despite the conflict.
The discretion, as White J observed in Grosser v Council of the
City of Gold Coast is couched in negative terms, that is, the
application must be dismissed unless there are sufficient grounds.
This is a mandatory requirement. If there is a conflict, then the
application must be rejected unless there are sufficient planning
grounds to justify its approval despite the conflict. The primary
judge wrongly held that it was directory only…
The first task required of the decision maker, as the learned primary
judge recognised, is to consider the nature and extent of the
conflict. The conflict may be minor or major in nature or indeed
anywhere on the continuum between those two extremes. The conflict
in this case is a major one, arising as it does from an absolute
prohibition on the height of any development exceeding the maximum
stipulated height of three storeys...
The second question the decision maker has to consider is whether
there are any planning grounds on which to approve, or which
militate against approval of, that part of the application which is in
conflict with the planning scheme. The nature and extent of the
conflict may be such as to suggest that there are significant planning
considerations against that part of the application.
The decision maker should then consider other aspects of the
development and determine whether they are consistent with proper
planning grounds. Those are the planning grounds which apply
whether or not the conflict exists.
It is only after consideration of all of these matters that the decision
maker is able properly to assess whether or not the planning grounds
in favour of the application as a whole are, on balance, sufficient to
justify approving the application notwithstanding the conflict.”
(Emphasis added)
225 At paras [35]-[37], [44]-[46].
-- 82 of 127 --
83
[204] In Woolworths Ltd v Maryborough City Council (No 2)226 Fryberg J (with McMurdo
P and Holmes J as she then was agreeing), when considering the then provisions of s
3.5.14 of the Integrated Planning Act, expressed the view that “conflict” in this
context means to be at variance or disagreement with and, that in resolving a contest
between conflict and grounds of justification, it may not be necessary for the decision
maker to formally identify and set out each area of conflict and that “the purely
mechanical application of the Weightman dictum should be avoided…”
[205] More recently the Court of Appeal endorsed the three step approach adopted in
Weightman in Lockyer Valley Regional Council where it was said:227
“The Council’s attempt at construing Weightman so as to add another
layer of explication to Atkinson J’s explanation of the section (in its
earlier form) should be rejected. There is no warrant in s 3.5.14(2)(b)
itself for applying different weight to different grounds. To do so
would be to impose an entirely artificial set of fetters on the decision-
making required. The importance of the ground must depend on what
it is, not where it falls in the three-step approach in Weightman.”
[206] The section referred to in Lockyer Valley is a reference to the relevant provision under
the then Integrated Planning Act 1997 which has been repealed and replaced by s326
of the SPA.
[207] In Australian Capital Holdings Pty Ltd v Mackay City Council & Ors,228 in
considering a section under the then Local Government (Planning and Environment)
Act 1990, which was to materially the same effect as s 326 of the SPA, the Court of
Appeal said:
“The primary judge, having concluded that there were conflicts with
‘relevant strategic plan(s)’ was required to decide if there were
‘sufficient planning grounds to justify approving the application
despite the conflict.’ In this case that exercise required the
identification of ‘planning grounds’; an assessment of the role and
importance to the planning scheme of the provisions which would be
infringed should the application be approved; the adverse
consequences, if any, which might flow from such infringement and
the competing merits and weight of the planning grounds relied on to
justify approval…”
226 [2006] 1 Qd R 273 at [55].
227 [2012] QCA 370 at [21].
228 [2008] QCA 157 at [60].
-- 83 of 127 --
84
[208] However, it is equally well recognised that this court should adopt a “self-limiting
approach, at least when considering town planning matters…”229 That it is not the
function of this court to substitute planning strategies has also been stated in a number
of cases. In Elan Capital Corporation Pty Ltd & Anor v Brisbane City Council &
Ors230 the court said:
“It should not be necessary to repeat it but this Court is not the
Planning Authority for the City of Brisbane. It is not this Court’s
function to substitute planning strategies (which on evidence given in
a particular appeal might seem more appealing) for those which a
Planning Authority in a careful and proper (sic) has chosen to adopt….
Adopting the phraseology of those cases which deal with non-
derogation (sic) principle, I feel that to allow this appeal would be to,
‘cut across’, in quite (sic) unacceptable manner, a planning strategy
which has been adopted by the Planning Authority and publicly
exhibited for community comment.”
[209] In Australian Capital Holdings Pty Ltd v Mackay City Council, Muir JA (with
Holmes JA, as she then was and White J, as she then was, agreeing), after citing with
approval a number of cases and, in particular, Grosser v Council of the City of Gold
Coast231 also went on to cite with approval the reasoning of Jerrard JA in Leda
Holdings Pty Ltd v Caboolture Shire Council & Ors:232
“Those authorities were cited to show that conflict between a
development application and strategic plan was often fatal to the
application, even prior to the introduction of s 4.13(5A) and its
counterparts in 1992…(As has been said repeatedly, this Court is not
the planning authority for this area and it is my view that it would be
inappropriate for the court to approve a proposal which is squarely in
conflict with the formally expressed planning strategies of that
authority…the Strategic Plan and the Strategic Plan Map are
legitimate planning tools adopted by a Local Authority for the future
planning of the Local Authority Area. The Local Authority in those
circumstances is planning ahead and endeavouring to direct its future
planning process in an orderly manner…The Court has however,
repeatedly stressed the importance of strategic planning and the need
to respect and support the integrity of the important planning tool
which the Strategic Plan is. There may be cases where a departure
from the Strategic Plan could be justified; where, for example, the
planning strategies which it represents, having been overtaken by
229 Grosser at [38].
230 [1990] QPLR 209 at 211.
231 At [55].
232 [2006] QCA 271.
-- 84 of 127 --
85
events (or for some other reason), clearly no longer have any
application; or where it can be demonstrated plainly the land has been
given a designation on the basis that was and remains invalid… (The
significance of strategic planning, particularly on rezoning
applications, has been recognised by the Court on many occasions.
Since the forward planning documents of a Local Authority are
indicative of the intent of a planning authority as to the future preferred
form of development that it sees for its Local Authority area,
considerable weight ought to be given to the provisions of forward
planning documents of a Local Authority).” (Citations omitted).
[210] After a consideration of the nature of the conflict, the sufficient grounds asserted on
behalf of the developer and the relevant case law his honour concluded that the
“considerations, taken in combination, warrant the conclusion that the primary judge
failed to apply the principles referred to…above and thus erred in law.” Accordingly
his Honour concluded that the appeal ought to be allowed and the decision of the
primary judge set aside.233
[211] White J (as she then was) after agreeing with the reasons for judgment of Muir JA in
Australian Capital Holdings went on to say:234
“(I) agree with his Honour in finding that there were insufficient
planning grounds to justify approval of the development application
by the Judge below departing, as he did, from the well-established
principle that a planning court ought not substitute its own preferred
planning strategies in place of carefully developed schemes of the
planning authority, particularly where the schemes have recently been
reviewed.”
CP 2003
[212] That the appellant concedes conflict with CP 2003 is not surprising, given that under
that scheme and, in particular, the Reedy Creek Structure Plan, CP 2003 essentially
provided for residential development consistent with residential development of the
type already existing, and otherwise focused on recognising and protecting the
environmental qualities and features of the subject land. Under CP 2003 the land had
the following designations:
(a) Planning strategy:
(i) Part Urban Residential Land Use Theme;
(ii) Part Park Living Land Use Theme; and
233 At [69].
234 At [73].
-- 85 of 127 --
86
(iii) Part Open Space/Nature Conservation Land Use Theme;
(b) Domain:
(i) The Emerging Communities Domain and in particular, the
Reedy Creek Structure Plan Area.
(c) Under the RCSP, the subject land fell within:
(i) The Urban Residential Precinct;
(ii) Part Park Living Precinct; and
(iii) Part Open Space/Nature Conservation Precinct;
(d) The subject land was also the subject of the following overlays:
(i) Natural Wetland and Waterway Areas; and
(ii) Conservation Strategy Plan.
[213] Given the appellant’s concession concerning CP 2003, I do not consider it necessary
to particularise each and every conflict. It is sufficient to identify that, under the
relevant Table of Development 3.0 for the Emerging Community Domain, which,
read in conjunction with Part 5, Division 1, Chapter 2, s 4.6.1, identified that the
proposal would be considered as being an undesirable and/or inappropriate outcome
for the land. That the proposed development would result in an undesirable and/or
inappropriate outcome immediately places it in serious and significant conflict.
[214] The appellant does not shy away from such a categorisation of the level of conflict,
but instead submits to the effect that CP 2003, insofar as it impacts on the subject
land, should largely be ignored, notwithstanding the fact that it was the planning
scheme in force at the time the application was lodged.
[215] It will be recalled that the appellant’s application for a development permit for a
material change of use to establish the quarry was lodged with the respondent on 19
May 2014. On 11 July 2014, the respondent refused the application and the appellant
lodged its appeal on 11 August 2014. CP 2016 came into force on 2 February 2016.
[216] After referring to State Planning Policy 2/07 (“SPP 2/07”) which identified the
subject land as a Key Resource Area (“KRA 96”), the appellant then went on to say
that CP 2003 was not amended so as to identify that KRA. The appellant then
submitted:235
“As noted above the 2003 PS was never updated so as to reflect that
the subject land had been designated as a KRA as required by the state
planning documents.
235 Written submissions paras [177]-[180].
-- 86 of 127 --
87
In this regard it is relevant that when dealing with the provisions of the
2003 PS, the Coordinator-General’s evaluation report states:
‘As the Gold Coast City Council has not amended the
planning scheme in accordance with SPP 2/07 and the
SEQRP, the town planning assessment identified
conflicts within the land use themes presented in the
planning scheme.’
This is relevant to the nature and extent of conflicts with provisions of
the 2003 PS.
The provisions in the SEQRP and the SPP prevail over the 2003 PS to
the extent of any inconsistency.” (Footnotes omitted).
[217] Under the heading “Implementing SPP 2/07”, that policy provided:236
“SPP 2/07 will influence land use planning and development decisions
within KRAs. In particular, it will help shape planning schemes of
local governments with KRAs in their areas.
While SPP 2/07 endorses the principle of extractive industry
development in a resource/processing area of a KRA and identifies
appropriate transport routes, development applications for new
extractive industry operations in a KRA will be subject to the normal
assessment process under the ‘Integrated Development Assessment
System’ (IDAS).
Therefore, the assessment would include not only SPP 2/07, but also
detailed consideration of the relevant environmental, amenity and
traffic policies and the requirements in the applicable local
government planning scheme and other relevant considerations under
IDAS… People will continue to have the opportunity to make
submissions on development applications that are subject to impact
assessment, and those submissions must be considered in the
assessment.
Accordingly, SPP 2/07 does not guarantee that a particular
development application for an extractive industry in a KRA will be
approved. However, of the 100 KRAs listed by the policy, 90 already
have current extractive industry development approvals, and the SPP
can be used to protect these KRAs from incompatible development
where such development is not already committed.
236 Exhibit 3, Tab 1 p 4.
-- 87 of 127 --
88
Reflecting the SEQ Regional Plan
This State Planning Policy is consistent with the SEQ Regional Plan,
which aims to protect extractive resources for potential future
extraction and their associated transport corridors. The SEQ Regional
Plan relies on the SPP to provide the detailed basis for achieving this
aim.”
[218] Under the heading “APPLICATION OF THE POLICY”237, SPP 2/07 went on:
“State Planning Policy and State Planning Policy Guideline
(1) The State Planning Policy… is a statutory instrument under
the Integrated Planning Act 1997…
(2) The State Planning Policy Guideline… provides advice about
implementing the Policy, and is declared to be extrinsic
material under the Statutory Instruments Act 1992…
(3) Under the Integrated Planning Act 1997, the policy has effect
when development applications are assessed, when planning
schemes are made or amended and when land is designated
for community infrastructure…
(4) Terms used in the Policy and the Policy Guideline have the
same meaning as defined in the Integrated Planning Act
1997…”
[219] In December 2013, SPP 2/07 was replaced by SPP 2013 (“SPP 13”) which was
intended to replace a “dozen” separate policies and to provide “a clear consolidated
and comprehensive view of the State’s interest in land use planning and development
in one place.” It also purported to deal with 16 State interests arranged under five
“broad themes”:
Liveable communities and housing;
Economic growth;
Environment and heritage;
Hazards and safety; and
Infrastructure.
[220] Of significance is that the policy does not prioritise one state interest over another at
a state-wide level.238 That this is so is consistent with a number of other elements of
the policy. By way of some examples:
“…it encourages flexible and locally appropriate approaches to
planning that reflect the state’s interests while meeting the needs and
priorities of local government and their communities.”239
237 Exhibit 3, Tab 1, p 5.
238 Exhibit 3, Tab 5, p 10.
239 Ibid at p 6.
-- 88 of 127 --
89
And
“Interests will not always be applied in the same way in a state as large
and diverse as Queensland, and there may even be differences in how
interests are integrated within a local government area…. The SPP
articulates a number of different state interests and associated policies
– in some circumstances these interests will compete or even conflict.
Therefore, specific regional and local circumstances must be
considered when determining how to resolve these at a local level.”240
And
“It is the responsibility of local government in preparing a planning
scheme, to firstly consider all of the state interests and the SPP in its
entirety. The local government must then determine which state
interests are relevant to it, and determine how best to apply these
interests in a planning scheme. Where the state’s interests can be met
using a range of methods, local government is encouraged to apply
alternative, innovative and performance-based approaches that
provide the necessary certainty and meet local and regional
circumstances.”241
[221] Under the heading “Mining and Extractive Resources” it also provided:242
“The resources industry is a key driver of the Queensland economy
and the state’s largest export earner…
The supply of extractive resources such as sand, gravel, rock, clay and
soil is essential to the health of the construction industry and the
delivery of infrastructure. Given the high-volume, low-value nature
of extractive resource products, it is generally necessary to source
extractive resources close to markets. Such locations are often also
subject to encroachment from sensitive land uses.
The state has an interest in ensuring that mining and other resources
activities are considered in land use planning…. This interest
acknowledges that development decisions will require the careful
consideration of competing interests.” (Emphasis added).
[222] Following SPP 2/07, but prior to SPP 13, the South East Queensland Regional Plan
2009 – 2031 was introduced (“SEQRP”).243 A relevant principle under the SEQRP
was to:
240 Ibid at p 10.
241 Ibid.
242 Ibid p 23.
243 Exhibit 12.
-- 89 of 127 --
90
“Manage the region’s natural economic resources to sustainably and
efficiently meet the needs of existing and future communities.” 244
It was also said:245
“State Planning Policy 2/07: Protection of Extractive Resources (“SPP
2/07) ensures the long-term availability of extractive recourses of state
or regional significance, and provides the basis for identifying and
protecting key resource areas in local government Planning Schemes.
Future iterations of SPP 2/07 and local government Planning Schemes
will continue to identify and protect the additional resources required
to ensure supply. Planning Schemes must define relevant and use
zones in a way that permits resource development where
appropriate.” (Emphasis added).
[223] Bearing those policies and plans in mind, it was submitted on behalf of the
appellant:246
“The conflict that arises must be viewed having regard to the
following:
(a) s.25 of the SPA which states that if there is an inconsistency
between a SPP and a local planning instrument, the SPP
prevails to the extent of the inconsistency;
(b) s.36 of the SPA which states that if there is an inconsistency
between a regional plan and a local planning instrument, the
regional plan prevails to the extent of the inconsistency;
(c) the 2003 PS is inconsistent with the single SPP and the
SEQRP as it does not reflect the designation of the subject
land as a KRA under the single SPP and an Extractive
Resource Area under the SEQRP and accordingly has been
overtaken by events.
933. Any conflict between the quarry project and the 2003 PS is a
direct result of the fact that the 2003 PS has not been amended
to reflect that the SPP and SEQRP in this regard.
934. A plain reading of the 2003 PS confirms that it is inconsistent
with the single SPP and the SEQRP as it does not reflect the
designation of the subject land as a KRA (under the single
SPP) and an Extractive Resource Area (under the SEQRP).
244 Ibid p 68.
245 Ibid p 69.
246 At paras 932-940.
-- 90 of 127 --
91
935. It appears to be accepted by the Council that the 2003 PS is
inconsistent with the single SPP and the SEQRP having
regard to the following matters…
…
937. The 2003 PS is also relevantly inconsistent with CP 2016.
[224] That CP 2003 ought be effectively ignored or given little weight, was said to be so
for three reasons:
(i) the failure to take into account relevant State policies and
plans;
(ii) that by the time following from that CP 2016 becomes the
more dominant scheme because “it reflects, if you like,
compliance with the most recent thinking”247;
(iii) because it would be unfair to permit the respondent to rely on
CP 2003 in circumstances where that would be tantamount to
allowing the respondent to take advantage of a “wrong”. That
wrong being the failure to incorporate and apply the relevant
State policies and plans.
[225] In respect of the last of those matters, I was referred to the judgment of Cullinane J
(with McMurdo P and Holmes JA (as she then was) agreeing) in Quinn Villages Pty
Ltd v Mulherin248where his Honour said:
“Whilst the respondent in argument on this issue relied upon Mackay
v Dick and his Honour referred to this judgment in his reasons, it seems
to me that in dealing with this matter he invoked a broader principle,
namely that a party cannot take advantage of its own non-compliance
with the contract.
This principle has the support of high authority and is of long standing
and predates Mackay v Dick…” (Citations omitted).
[226] The relevant passage from Mackay v Dick is as follows:249
“as a general rule…, where in a written contract it appears that both
parties have agreed that something shall be done, which cannot
effectually be done unless both concur in doing it, the construction of
the contract is that each agrees to do all that is necessary to be done on
his part for the carrying out of that thing, though there may be no
express words to that effect. What is the part of each must depend on
circumstances.”
247 T34-5 ll 1-6.
248 [2006] QCA 433 at [23] and [24].
249 (1881) 6 App Cas 251.
-- 91 of 127 --
92
[227] During final submissions, Mr Gore in this context submitted as follows:250
“…this court doesn’t leave ordinary principles behind, and one that’s
very important to this case is that – and it pervades all areas of the law
– is that ‘a person cannot take advantage of their own wrong’ or, as it
is sometimes put, ‘a wrongdoer cannot advantage from its own
conduct’, and I’ll give your Honour a decision of the Court of Appeal
shortly that deals with that, a case where it was applied in the context
of a contractual provision.
That might be its most ordinary area of operation – that a party to a
contract can’t take advantage of its own wrong, but it applies in other
areas of the law – in the law of negligence, for example. ‘Volenti non
fit injuria’ is really Latin for, you know, you can’t take advantage of
your own wrong. If you take on a wrongful course of conduct and you
get hurt, that’s your problem… I was going to come to equity. You
must come – ‘he who comes to equity must come with clean hands’,
and it is buried under that basic principle. I’ll give your Honour that
case now. It’s not in our bundle, but it’s a decision of the Court of
Appeal in Quinn Villages… Your Honour might recall from university
days the Council here failed to comply with its obligation under the
Integrated Planning Act to amend its 2003 Planning Scheme to bring
it into line with the regional plan…’”
[228] In my view, the misconduct argument must fail. Quinn Villages and the cases referred
to therein are dealing very much with the situation under the law of contract. Further,
with respect, I do not consider the equitable principles relied upon are applicable.
Volenti is concerned with the ancient principle “to a willing person it is not a wrong.”
That is, a person who is not wronged by that to which he or she consents.251 That
maxim cannot apply here. Turning then to the “clean hands” maxim it is more
concerned with, generally speaking, the court, as a matter of public policy, refusing
to grant relief to those involved in intentional bad conduct. Here, while not finally
deciding the matter, it seems to me that it would be highly unlikely that a local
government authority would fall as accountable under this doctrine or maxim in
circumstances where it is not seeking relief but seeking to defend a decision made
prima facie in the best interests of its constituency. There may well have been a failure
to comply with the Integrated Planning Act, but this is not a case where there has
been a course of deliberate, deceptive and/or illegal conduct.
250 T34-7 ll 7-47.
251 Black’s Law Dictionary, 10th Ed. p 1805.
-- 92 of 127 --
93
[229] As to the second matter relied on by the appellant it was, broadly speaking, agreed
with by the respondent. It was acknowledged that CP 2016 is “deserving of weight”
for a number of reasons.252 In this context, the respondent did not take issue with Mr
Gore’s observation that the proper construction to be given to s 3.5.1(10) of CP 2016
“on each side’s case, is central to the outcome.” Indeed, Mr Litster said:253
“…and, your Honour, then may take into account, and in our
submission, you should take into account – you should take into
account 2016. It is the most recent statement of planning intent not
only by the Council but also by the State Government. Because the
State Government has said about that scheme that it integrates the
State interest…. But it’s the latest statement about the forward
planning intentions for the Gold Coast. And you would seriously
consider that it is something that you would not look to cut across in
the context of making a decision in this case.”
I agree. The proper construction to be given to CP 2016 is a critical matter in the
context of this proceeding.
[230] Before proceeding, I should finally deal with the appellant’s submissions concerning
the operation of ss 25 and 36 of the SPA:
“25 Relationship with regional plans and local planning
instruments
If there is an inconsistency between a State planning policy
and a regional plan or local planning instrument, the State
planning policy prevails to the extent of the inconsistency.”
And
“36 Relationship with other instruments
…
(2) If there is an inconsistency between a regional plan
and a local planning instrument, the regional plan
prevails to the extent of the inconsistency.”
[231] Section 314(d) of the SPA also relevantly provides:
“314 Impact assessment—generally
(1) This section applies to any part of the application
requiring impact assessment.
(2) The assessment manager must assess the part of the
application against each of the following matters or
252 Respondent’s written submissions at pp 3-4.
253 T33-14 ll 17-30.
-- 93 of 127 --
94
things to the extent the matter or thing is relevant to
the development—
…
(d) State planning policies, to the extent the
policies are not identified in—
(i) any relevant regional plan as being
appropriately reflected in the regional
plan; or
(ii) the planning scheme as being
appropriately reflected in the planning
scheme;”
[232] As the respondent quite properly acknowledged, it was uncontroversial that CP 2003
did not reflect SPP 2013 within the meaning of s 314(2)(d) of the SPA, and that the
application ought properly have been assessed under that policy to the extent that it
was relevant.254
[233] The significance and relevance of SPP 2013, and its precursor SPP 2/07 is identified
in the SEQRP 2009-2031.255 As already identified, it expressly provides for the need
to identify and protect key resource areas. It also provides that:256
“…future iterations of SPP 2/07 and local government planning
schemes will continue to identify and protect the additional resources
required to ensure supply. Planning schemes must define relevant land
use zones in a way that permits resource development where
appropriate.” (Emphasis added).
[234] The inescapable conclusion is that CP 2003 is in direct conflict with SPP 2013.
Neither SPP 2013 nor the SEQRP attempt to prioritise any particular state interest
and recognise that the advancement of some of these interests are very likely to cause
tension with other interests (e.g. economic growth v protection of environmental
assets). That said, the Reedy Creek Structure Plan under CP 2003 not only failed to
protect the subject key resource area, it effectively ignored its existence. Significant
parts of the quarry area itself was designated for low-density urban residential and
park living development.257
254 Respondent’s written submissions at paras 47-48.
255 E.g. Exhibit 12 p 69.
256 Exhibit 12 p 69.
257 By way of example compare Exhibit 11B pp 31-35 and p 39 with Exhibit 10B at p 49.
-- 94 of 127 --
95
[235] As I understood the position of the respondent, it was contended that there was no
genuine conflict between the CP 2003 and the SPP 2013 and/or the SEQRP,258 as,
“An assessment under the CP 2003 without regard to SPP 2013 would
have proceeded on no different basis than the assessment which is to
be carried out under both SPP 2013 and CP 2003.”
and,
“Consistent with assessment against SPP 2013, SEQRP requires
recognition of the existence of the recourse and its consideration as
part of the present assessment. Nothing in the SEQRP is inconsistent
with CP 2003.”
[236] I cannot accept that argument for the reasons given. Accordingly, I consider CP 2003
and, in particular, the Reedy Creek Structure Plan to be, while still of some relevance,
far from being a determinative matter. That is to be contrasted with the situation
concerning CP 2016 which, to use Mr Litster’s words, “is the most recent statement
of planning intent not only by the Council but also the State Government… because…
it integrates the State interest…” (i.e. SKRA 96). 259
[237] Under the CP 2016 Strategic Framework, the subject land is identified as:
(a) Designated Urban Area: Non-Urban Area;
(b) Settlement Pattern: Natural Landscape; and
(c) Focus Areas for Economic Activity: Non-Committed Resource
Areas. (Emphasis added).
[238] The subject land is also included within the Rural Zone and under that zoning, also
within a specific Landscape and Environment Precinct. It is also identified in the
following mapping overlays:260
(i) Environmental Significance Overlay - Biodiversity Areas;
(ii) Environmental Significance Overlay - Priority Species;
(iii) Environmental Significance Overlay - Vegetation
Management;
(iv) Environmental Significance Overlay – Wetlands and
watercourses;
(v) Extractive Resources Overlay.
[239] To the extent that the proposal would be in conflict with CP 2016, that conflict is
manifestly more serious under CP 2003. That is so because under the current Planning
258 Respondent’s written submissions at para 68.
259 T33-14 L 20; also T33-42 ll 1-24.
260 Exhibit 11B.
-- 95 of 127 --
96
Scheme, the key resource area is at least recognised. Under the “Extractive resources
overlay map – map 4” KRA 96 is identified as a “resource area/processing area”, the
balance of the subject land as a “separation area” and Old Coach Road to the north as
a “transport route” and a “100m transport route separation area.”261
[240] According to Mr Litster, while the proposal was the “antithesis” to the objectives
under CP 2003, the resource was now preserved for future use if required. At one
stage Mr Litster even went so far as to say that even today a smaller quarry use might
be approved by the respondent. During final submissions, the following exchange
took place between myself and Mr Litster:262
“Q: In that context then, there’s a distinct
difference between the subject land as treated
under City Plan 2003 and 2016.
A: Yes.
Q: But we heard from the town planners – and I
forgot which town planner it was, probably Mr
Buckley – and I – or at least it was a response
to a question from me, because the – Boral’s
town planner effectively said: ‘if I don’t
approve this site for quarry use, it’ll be – that
resource will be lost forever.’ Mr Buckley said
‘not so’, because under its current designation
– City Plan 2016… it’s a protected resource.
A: It is.
Q: But that then begs the question, doesn’t it,
because the additional criticism is a valid one
in the sense that it’s never going to get any
easier, with the passage of time, for Boral to
quarry the site.
A: Well, with the greatest respect, we don’t – it
may not get any easier to quarry the site with a
quarry the size they want to undertake on the
site. Don’t forget they determined that they
wanted to design the quarry so that they’d fall
within the 5mm per second vibration line at the
closest residence… They’ve pushed to the
limit on that point. Maybe something else…
Q: Maybe something that keeps ridge J in place, is
that what you’re…
261 Exhibit 11B, p 34.
262 T34-14 ll 33-46; T33-15 ll 1-45.
-- 96 of 127 --
97
A: Well, something that may, in fact, keep parts of
ridge J in place and is invisible would meet the
test. Something – now, part of the problem
here, however, is, of course, because there’s a
matter of state environmental significance, or
matters of environmental significance, on the
land. We didn’t – that wasn’t known before this
case. It was mapped as Koala habitat. But the
extent and – of the Koala habitat trees – as long
as you have koala habitat trees – weren’t
known until Mr Saunders did his transects.
You see, it would have – it is quite possible –
it would have been quite possible, potentially,
that there was no part – there were parts of the
land that are not affected in that fashion. And
in that circumstance, if you developed in those,
it might be possible to meet the test of
conserve, protect, enhance… and manage the
matters of environmental significance.
Q: But the in situ component --- is going to be the
enquiry.
A: Well, it is on what we know now; it is on what
we know now. But that may be something that
has to be revisited at the time that the scheme
comes up for review. The State may well say:
‘no, no. We think that the balance has fallen
away from biodiversity on that site and should
favour the--- the resource or otherwise.’ But
until such time as a change is made to the
scheme, the resource is protected…”
[241] As to the potential approval of even a smaller quarry, having regard to the way the
respondent conducted its case in this proceeding, it would be difficult for any such
application to be approved during the life of CP 2016. That is, it is difficult to imagine
that even with a smaller quarry that maintained all or part of Ridge J, while perhaps
meeting the visual amenity criteria, it would otherwise fall foul of the respondent’s
concerns about koala habitat, terrestrial and aquatic ecology, traffic and noise etc.
[242] Turning then to some of the more relevant provisions of CP 2016 itself. In the
Introduction to the scheme, after identifying that it was prepared in accordance with
the SPA “as a framework for managing development in a way that advances the
purpose of the Act”, it then goes on to identify that while the plan has been prepared
-- 97 of 127 --
98
with a 20 year horizon, it was intended to be reviewed to ensure that “it responds
appropriately to changes of the community at a local, regional and state level.” In
this context, reference is made to relevant state planning policies and the SEQRP.263
[243] Relevant to this proceeding, CP 2016 has two components. State planning provisions
and the strategic framework. In the introduction to the strategic framework it is
identified that it is intended to set policy direction that will help to “protect and
enhance the Gold Coast outstanding lifestyle by ensuring appropriate and
sustainable development occurs within the City Plan area for the life of the City
Plan.” The introduction then goes on to identify six “City shaping themes that play
an important role in shaping the future growth and managing change across the city,
and collectively represent the policy intent of the City Plan:
(i) creating liveable places;
(ii) making modern centres;
(iii) strengthening and diversifying the economy;
(iv) improving transport outcomes;
(v) living with nature;
(vi) a safe, well-designed city.”264
[244] Strategic outcomes include that “natural resources are sustainably managed for
current and future generations and leveraged to support the growth of nature based
tourism in a sustainable manner.”265
[245] Section 3.5.5 of the strategic framework is concerned with the element of natural
resources. Pursuant to s 3.5.5.1, the relevant specific outcomes are:266
“(1) The prudent use of renewable and non-renewable natural
resources supports long-term community needs and only
occurs where any immediate or long-term environmental and
social impacts can be managed to an acceptable level.
(2) Natural resource areas of economic value and associated
haulage routes are protected from encroachment by activity
that would compromise the ability to utilise the resource
effectively and sustainably. Natural resource areas of
economic value include:
(a) rural production areas…
(b) extractive resource areas (committed and non-
committed).
263 Exhibit 11A p 2.
264 Ibid p 15.
265 Ibid p 61(9).
266 Ibid pp 69-70.
-- 98 of 127 --
99
…
(7) Committed and non-committed extractive resource areas
and their associated haulage routes are protected from
encroachment from incompatible development. Surrounding
development minimises views into resource areas.
(8) In committed areas, the extraction and haulage of the
resource protects environmental values on the land as far as
practicable prevent significant impacts on nearby sensitive
users including the use of appropriate separation
areas/buffering; and does not scar vegetated ridgelines and
elevated land when viewed from outside the resource area.
…
(10) In the non-committed areas at Reedy Creek… operations
only extend into the non-committed areas if it can be
demonstrated that:
(a) the amenity of nearby residential land is maintained;
(b) critical corridors are accommodated and matters of
environmental significance are conserved,
protected, enhanced and managed; and
(c) the green backdrop provided by ridgelines is not
reduced when viewed from major roads and
surrounding residential land…” (Emphasis added).
[246] The construction of s 3.5.5.1(10) contended for by the appellant and the respondent
could not be more opposed. According to the appellant, the words “maintained”,
“conserved”, “protected”, “enhanced” and “not reduced” should be read in a practical
way to achieve balance between competing outcomes and, accordingly, should be
read down by inserting words such as “appropriate” and “to an acceptable level”267.
In this context, two of the experts relied on by the appellant, Mr Francis and Mr
Agnew prepared further reports. Mr Francis, on the basis that:268
“I have also been asked to assume that the term ‘conserve’ and
‘protect’ should not be read in an unqualified way, but rather should
be read with a qualification such as ‘to an acceptable or reasonable
degree’. Similarly, I have been asked to assume that the terms
‘enhance’ and ‘manage’ should be read with the word ‘reasonably.’”
(Emphasis added).
And in the case of Mr Agnew:269
267 Appellant’s written submissions para 904-906; also T34-15 - T34-26.
268 Exhibit 125.
269 Exhibit 145.
-- 99 of 127 --
100
“In providing my advice, and consistent with the approach taken by
David Francis in addressing flora matters, I have assumed the terms
‘conserved’ and ‘protected’ should not be read in an unqualified way
but rather should be read with a qualification such as ‘to an
acceptable or reasonable degree.’” (Emphasis added).
[247] On the other hand, Mr Litster submitted that it would be impermissible to read down
the scheme’s objectives concerning non-committed areas. According to him:270
“…unfortunately, this document is designed to be construed strictly.
We make no apology about it, because that is what it does and the way
that it’s been drafted is indicative that there was clear attention paid to
where do we place our priorities. Where do we place our priorities?
And they place their priorities – and it would be impermissibly
rewriting the scheme to qualify those priorities…”
[248] According to Mr Gore, after referring to the other provisions of s 3.5.5.1, the word
“unreasonably” or some similar qualification has simply been omitted as a
consequence of a “mistake” on the part of the draftsperson.271 I cannot accept that
submission. It is quite clear to me that when CP 2016 was being drafted a clear
distinction was intended to be made regarding the way committed resource areas (i.e.
either existing or approved) were to be treated in the approval process when compared
to non-committed areas. To construe subsection (10) in the manner contended for on
behalf of the appellant would, to a significant extent, see non-committed areas having
to be treated in much the same manner as committed areas. That subsection (1) of s
3.5.5.1 refers to impacts being “managed to an acceptable level” does not advance
the appellant’s case. When the scheme was being drafted, it seems tolerably clear that
what was intended, was that an acceptable outcome in respect of committed areas,
would not or need not be acceptable in respect of non-committed areas.
[249] Under subsection (8), concerned with committed areas, the emphasis is on the
practicality of preventing significant impacts. That significant impacts might occur
because it is impracticable to prevent them is contemplated. In such cases, that
significant impacts occur might nonetheless, when circumstances warrant or dictate,
be an acceptable outcome. Under subsection (10), significant impacts on amenity,
critical corridors and matters of environmental significance etc. are not contemplated
and would result in an unacceptable outcome.
270 T33-88 ll 9-14.
271 T34-16 ll 27-34.
-- 100 of 127 --
101
[250] I accept that the terms used in subsection (10) should not be construed too strictly. To
do so would result in an effective ban or prohibition on any meaningful quarrying on
the land. However, it would be an error to treat the subsection as merely involving
some sort of balancing act. That is, by way of example, to say it would be reasonable
to accept (or unreasonable to reject) the loss of a significant number of NJKHT and/or
waterways because the loss of the trees could be offset and the waterways artificially
replicated. The construction contended for by the appellant fails to have regard to the
distinction between committed areas where the test is whether it is practicable to
prevent significant adverse impact, whereas in respect of non-committed areas
residential amenity is to be maintained and matters of environmental significance are
to be conserved, protected, etc.
[251] Any application for development within a non-committed area would of course have
to be treated on its own merits. No doubt there will be locations where there would
be either no or only insignificant impacts on the matters identified in subparagraphs
(a), (b) and (c) of subsection (10). Unfortunately for the appellant, that is not the case
here. There are a number of significant impacts which places the proposal in serious
conflict with s 3.5.5.1(10). Before proceeding further, having regard to the way the
respondent dealt with, or perhaps more accurately failed to deal with, KRA 96 in the
2003 Planning Scheme and the wording of s 3.5.5.1(10), one could not be blamed for
being somewhat suspicious that the current drafting was intended to make any
development of a quarry near the size of that proposed extremely difficult, if not
impossible, within KRA 96. In this context I agree with the appellant’s submission
that the construction of 3.5.5.1(10) advocated for by the respondent would “severely
restrict if not prohibit quarrying on the subject land.”
[252] On balance, for the reasons given above, I do not consider that the proposal ought be
refused by reference to the following matters either alone or in combination: aquatic
ecology, terrestrial ecology, noise (from whatever source), air quality and vibration.
While it is no doubt true that some of the residents closely located to the proposal
would have their amenity affected, I am satisfied that, at least in respect of these
matters, the amenity of nearby residential land would be maintained to an acceptable
level and that the ecological issues would not warrant refusal.272
272 See p 118.
-- 101 of 127 --
102
[253] The same could not be said, in my view, in respect of the traffic issues, nor in respect
of the “green backdrop provided by ridgelines.” As I have already indicated, the
visual impact on more distant receptors (i.e. at or about 4-5km distance) would be
minor/insignificant. However, elements of the quarry, in particular processing plant
and the quarry benches will be visible to a range of moderate to high receptors. To
that extent, the green backdrop identified in subsection (10)(c) is negatively impacted
upon in a material way.
[254] In respect of traffic, the extent of the roadworks proposed and the impact resulting
from the introduction of 450 heavy haulage vehicles per day onto Old Coach Road
will materially impact on the amenity of nearby residential areas. The roadworks may
cause only temporary impacts, 3 to 11 months depending on which construction
option were adopted. However, the haulage trucks will be operating effectively for
the lifetime of many of the local residents. Of course the level of impact on amenity
would be dependent on how often any given nearby resident used that section of Old
Coach Road, but even in the absence of any specific evidence on that point, it is
tolerably clear that there would be a perceptible adverse impact.
[255] As I observed earlier, that all relevant policies and guidelines can be met need not be
a determinative matter. In this proceeding I am satisfied that there would be tangible,
negative impacts on residential amenity arising from the visibility of the
development, blasting, the introduction of heavy traffic and, to a lesser extent,
periodic dust issues. These would be a constant reminder to many of the local
residents of the quarry’s existence. A use that would fall outside of the reasonable
expectations of residential amenity under both CP2003 and CP2016.
[256] For the reasons given, the proposal is in material conflict with SO 3.5.5.1(10)(a) and
(c).
[257] Turning then to SO 3.5.5.1(10)(b), the conflict is even more serious. The land is
specifically identified in the extractive resources overlay273 however, somewhat
incongruously, it also falls within the Landscape and Environment Precinct and is
identified on the environmentally significant overlays identified previously.274
273 Exhibit 11B p 39.
274 Ibid pp 31, 32 and 33.
-- 102 of 127 --
103
[258] I am able to accept that the loss of waterways would not put the proposal in serious
conflict with CP 2016. I also accept that, leaving aside the question of koala habitat
for the moment, other flora of significance within the disturbance area could be
located and replanted within the buffer area and that a meaningful and effective fauna
corridor could be maintained.
[259] That said, the impact on the existing koala habitat is significant. The clearing of 67
ha is in stark conflict (at variance or disagreement) with 3.5.5.1(10)(b). It is not to the
point that the buffer would “provide for a large area of habitat suitable for movement
of a wide range of fauna including species of significance…”275 nor that the impacts
on the flora might be able to be dealt with by appropriate “offsets”.
[260] Mr Francis expressed the following views:276
“In terms of flora ecology only the second part of point (b) are
relevant, that is, ‘matters of environmental significance are conserved,
protected, enhanced and managed.’ My interpretation of each of the
terms conserve, protect, enhance and manage follow:
Conserve – to conserve something it is necessary to prevent
it from permanent loss. Conceivably, this allows for
translocation or offsetting of the ecological value.
Protect – the term is similar to conserve, but subtly different.
I take it to mean that the value is permanently retained. Again,
the value could conceivably be protected once it had been
translocated or offset so long as there is a mechanism in
place for its permanent retention.
Enhance – this would only apply to degraded areas. An area
that is already integral could not be enhanced. Enhancement
would include ecological restoration activities.
Manage – areas that are retained are subject to a management
regime. This would likely include pest management and fire
management…” (Emphasis added).
[261] That matters of environmental significance might “conceivably” be conserved and
protected by offsets is, again, not to the point.
[262] The words used in 3.5.5.1(10)(b) should be given their natural and ordinary meaning
but be construed in the context of contemplated extractive industry occurring. As
275 Exhibit 145, p 3.
276 Exhibit 125, p 1.
-- 103 of 127 --
104
was identified in the Westlink judgment that is so particularly when dealing with
phrases such as “preserve and enhance” and “maintain and preserve”.
[263] The clearing of 62 ha of koala habitat could not be sensibly reconciled with the object
of conserving, protecting and enhancing matters of environmental significance. In
this context I would observe that no document of the type produced by Messrs Agnew
and Francis (Exhibits 125 and 145) was prepared by Dr Carrick who was relied on by
the appellant to deal specifically with issues concerning koalas. Perhaps not
surprisingly given his evidence that koala habitat offsets should always be the last
resort after avoid and minimise.277
[264] Habitat offsets may well lead to a better overall income for the koala population in
the wider Southeast Queensland area. That however provides no resolution of the
conflict identified above. It also fails to have regard to the provisions of CP 2016 that
require matters of environmental significance within biodiversity areas to be
protected “in situ”. Koala habitat is a matter of environmental significance278 within
a biodiversity area. “In situ” is defined to mean that “matters of environmental
significance must not be damaged or removed and the matters cannot be offset.”279
The proposal is therefore also in conflict with Strategic Outcome 3.7.1(4)280 and
Specific Outcome 3.7.4.1(4).281
[265] For essentially the same reasons, the proposal is also in conflict with Performance
Outcomes 13, 17 and 19 of Part C – Assessable Development Criteria.282
[266] In respect of the issue of protecting habitat “in situ”, it was submitted on behalf of the
appellant:283
“In construing CP 2016 the ordinary rules of statutory interpretation
apply.
The orthodox rules of statutory provision include that a specific
provision overrides a general provision.
277 Exhibit 40, p 5; RT21-22 ll 27-30.
278 In CP 2016 koala habitat is specified to be a priority species – Exhibit 11A, p 193.
279 Exhibit 11A, p 304.
280 Ibid p 79.
281 Ibid p 84.
282 Ibid pp 200-201.
283 Written submissions at p 233.
-- 104 of 127 --
105
By application of these orthodox principles, it is clear that Specific
Outcome 3.5.5.1(10) is the dominant provision. This Specific
Outcome refers only to two specific areas within the whole of the
Council’s local government area, whereas the provisions relied upon
by the Council are general provisions which refer generically to land
mapped extensively throughout the whole of the Council’s local
government area.
Specific Outcome 3.5.5.1(10) is also to be contrasted with Specific
Outcome 3.5.5.1(9) which clearly indicates a preference for
agricultural values over extractive industry values. No such preference
is contained within Specific Outcome 3.5.5.1(10).” (Footnotes
omitted).
[267] While I accept that the “ordinary rules of statutory interpretation apply”, I do not
accept that SO 3.5.5.1(10) is the “dominant” provision to the extent of rendering
Outcomes 3.7.1(4) and 3.7.4.1(4) effectively of no consequence. It is true that
3.5.5.1(10) is concerned with only two specific areas (the Reedy Creek and Northern
Darlington ranges non-committed areas) but, insofar as the subject land is concerned
it is, by virtue of its natural features, also a matter of environmental significance,
particularly so in respect of koalas. It would be, with respect, a rather bizarre result
that outcomes specifically designed to deal with important environmental habitat
areas had to be effectively ignored.
[268] The proposal is in material conflict with CP 2016, that conflict involving the adverse
impacts on residential amenity caused by the traffic, visual amenity and the relevant
intended environmental outcomes identified above.
[269] In this context I am also unable to accept much of Mr Schneider’s evidence
concerning the level of conflict the proposal creates with CP 2016. It is clear that he,
like Messrs Francis and Agnew, read down the purpose and effect of s 3.5.5.1(10) to
an unacceptable level. The effect of his evidence was that he saw CP 2016 treating
development within committed areas of extractive resource no differently than that
for development within non-committed areas, to the extent that the loss of 23,000
NJKHT from the subject land could be compensated by way of offsets.284
[270] As I have already indicated, insofar as CP 2003 is concerned the proposal, as the
appellant itself concedes, is in even more serious conflict albeit for different reasons.
284 T31-37, L 10 to T31-40.
-- 105 of 127 --
106
To put it bluntly, if the proposal does not succeed under CP 2016, its prospects under
CP 2003 are even more unlikely.
Sufficient grounds
[271] Given the level of conflict involved it is necessary to consider whether there are
sufficient grounds to justify approval despite the conflict. I have already dealt with
and expressed my findings concerning the lay witnesses called by the appellant on
this issue.
[272] Section 326(1)(b) of the SPA is concerned with the concepts of conflict and sufficient
grounds in the context of their application to a “relevant instrument.” Pursuant to s
314(2), a relevant instrument here would include a “planning scheme.” As has
already been identified, CP 2003 was in force when the subject application was
lodged. Accordingly, in a proceeding such as this, pursuant to s 495(2)(a) of the SPA,
it must be decided “based on the laws and policies applying when the application
was made,” here that would be CP 2003. However, any new laws and policies may
be given weight to the extent the court considers appropriate. Given the substantial
weight placed on CP 2016 in this proceeding I have concluded that, largely consistent
with the approach adopted by the parties, the issue of conflict should be addressed by
reference to CP 2016 rather than CP 2003. To perhaps put it another way,
notwithstanding the fact that CP 2003 is the relevant instrument for the purposes of s
326(1)(b) of the SPA, CP 2016 is the planning instrument that ought be accorded
most weight.
[273] For the reasons already identified,285 had the “sufficient grounds” test or balancing
exercise been carried out against CP 2003, the level of conflict would have been much
more serious and, to put it bluntly, it would have been an even more difficult task to
establish sufficient grounds to justify approval.
285 See e.g. paras 212-213 and paras 234-239.
-- 106 of 127 --
107
[274] As the SPPs and the SEQRP identify, a readily available source of hard rock is a vital
component of Queensland’s building and infrastructure development. And,
accordingly, there is a need to ensure that such resources are identified, protected and
exploited when appropriate. Also, as the appellant pointed out, hard rock of the type
involved here is a finite resource for which there is at present, and for the foreseeable
future, no viable alternative and there is no choice but to exploit the resource where
it exists. The last point was neatly articulated by Quirk DCJ in Sellars Holdings Ltd
v Pine Rivers Shire Council:286
“…remembering that it is a characteristic of extractive industry that it
can be practically located only where suitable deposits (which can be
worked in an economically viable way) are to be found, it is in the
community's interests that such deposits be availed of wherever
possible.”
[275] That a valuable state resource exists, however, does not mean that it must necessarily
be exploited at this particular point in time. The benefit of exploitation at this time
has to be balanced against other state interests such as biodiversity, water quality,
agriculture and liveable communities. As SPP 2013 recognises, the exploitation of
extractive resources sometimes “…will require the careful consideration of
competing interests.”287
[276] The sufficient grounds relied on by the appellant to warrant approval are identified in
a number of documents.288 Mr Schneider, the town planner relied on by the appellant,
also provided a summary of the grounds of approval:289
“(a) the proposed development will provide benefits to the
community;
(b) there is a planning need for the proposed development;
(c) the proposed development presents a rare opportunity to
secure access to a highly valuable, non-renewable resource
without unacceptable impacts;
(d) the proposed development maintains the city image and
scenic amenity of the city;
(e) the proposed development makes efficient use of the site
whilst effectively balancing the extent of development with the
286 [1988] QPLR 12; see also Holts Hill Quarries Pty Ltd v Gold Coast City Council [1999] QPELR 415
at 418 per Hanger DCJ.
287 SPP 2013 at p 23.
288 Exhibit 9, Issues Bundle, pp 67-68 and at pp 13-17 and pp 74-75.
289 Exhibit 29B pp 73-75.
-- 107 of 127 --
108
need to conserve, protect, enhance and manage existing
environmental values;
(f) the proposed development maintains and secures the
connectivity of environmental corridors;
(g) the proposed development retains and protects part of the site
identified for development under the 2003 Planning Scheme
in the vegetation buffer;
(h) the proposed development will deliver a substantial
environmental offset;
(i) the proposed development will have a net benefit for koalas;
(j) the proposed development will generate employment
opportunities;
(k) an Environmental Authority has been granted by the
Department of Environment and Heritage Protection and the
proposed development can comply with all regulatory limits,
particularly with respect to air quality, noise and blasting;
(l) the proposed development reflects a project that is of State
significance;
(m) the proposed development is consistent with State interests;
(n) the proposed development gives effect to State planning
instruments;
(o) Extractive Industry Overlay Map OM23 in the 2003
Planning Scheme has been overtaken by events;
(p) the 2003 Planning Scheme does not incorporate relevant
State planning instruments;
(q) the 2003 Planning Scheme is inconsistent with the City Plan
2016;
(r) the City Plan 2016 contemplates the development of
extractive industry on the site;
(s) if the Court decides to approve the development applications,
it will lead to enforceable obligations upon the Appellant to:
(i) carry out rehabilitation to achieve environmental
benefits; and
(ii) carry out works that will improve the safety and
efficiency of the external road network.
(t) the proposed development is consistent with reasonable
community expectations that:
(i) the site will not remain undeveloped;
(ii) the existing amenity of nearby residential areas will
be maintained; and
(iii) the ongoing supply of extractive resources close to
market is secured.” (Emphasis added)
[277] As can be readily appreciated, there is a degree of overlap associated with a number
of those grounds. Also, the appellant accepted that sub-paragraphs (k), (m), (o), (p),
-- 108 of 127 --
109
(q), (r) and (t) are “more directly relevant to the issue of the nature and extent of the
conflict, than with positive matters of public interest per se. Otherwise, Boral submits
that the grounds identified have been established on the evidence.”290
[278] At the heart of the appellant’s case in this context is the following submission:291
“The primary grounds obviously relate to matters of need, and, in that
regard, the court is referred to earlier submissions under the headings
of need, quarry management and geology. Many of the other
disciplines are also relevant, and the court is particularly referred to
earlier submissions under the headings of traffic, civil engineering,
water quality and hydrology, and koalas.
In the result, any conflict that arises is overcome by the matters of
public interest relied upon by Boral.”
[279] For the reasons already given, I consider it only necessary to give further
consideration to the issues of “quarry management/supply” and “need.”
[280] The present day value of the resource is estimated at about $1.5 billion. Further, there
can be no doubt of the appellant’s commitment to the exploitation of this site. That is
clearly evident by reference not only to this proceeding but also the approval
processes identified above. It is also clear that the exploitation of this resource would
dovetail very neatly with the impending exhaustion of the West Burleigh Quarry.
While Boral’s personal commercial interests are not directly relevant they are, in my
view, of some significance for the reasons identified above. That is, in providing a
source of high quality product in the Southern Gold Coast area and the associated
potential impacts on the cost of transportation and competition and pricing.
Additional costs will almost inevitably be passed on at least to some extent to the end
user and that would not be in the public interest.
[281] Notwithstanding its failure to identify, let alone protect, the subject key resource area,
CP 2003 did at least provide some planning strategy for natural resources and, in
particular:292
“This strategy therefore seeks to ensure the wise use of existing
recourses of economic value within the City. Accordingly, where it
can be shown that there is an overriding community benefit, extractive
industry development may be an appropriate use in areas of significant
nature conservation value.”
290 Appellant’s written submissions at para 948.
291 Ibid paras 949 and 950.
292 Exhibit 10A, p 67.
-- 109 of 127 --
110
[282] As is the case here, when confronted with phrases in town planning documents such
as “protect and enhance”, phrases such as “an overriding community benefit” must
also be construed in the context of the planning scheme as a whole which will almost
inevitably involve objects, some of which will be on their face inconsistent with, if
not in direct conflict with, other objectives.
[283] In Parklands Blue Metal Pty Ltd v Sunshine Coast Regional Council293 Robertson
DCJ, in dealing with a quarry case, said:
“The question of whether a need is shown to exist is to be decided
from the perspective of the community and not that of an appellant, or
even objectors. A community consists of more than just particular
members of it. The concept of planning need does not mean pressing
or critical or urgent need or widespread desire or anything of that
nature.”
[284] In Yu Feng Pty Ltd v Brisbane City Council294 the Court of Appeal, when concerned
with a large shopping centre, said:
“[Overwhelming need] is not on its face prescriptive. It is more in the
nature of a ‘motherhood’ statement and what will constitute an
‘overwhelming need’ will vary enormously. There would almost be an
infinite variety of facts which could impact upon the decision whether
or not there was an ‘overwhelming need’ for a proposal under
consideration.”
[285] “Need”, in the town planning sense does not require a pressing critical or even a
widespread need or desire. In Watts & Hughes Properties Pty Ltd v Brisbane City
Council295 it was observed:
“…need does not connote a pressing urgency but relates to the
wellbeing of the community. A use would be needed if it would, on
balance improve the services and facilities available in a locality”.
[286] In Isgro v Gold Coast City Council296 Wilson SC DCJ (as he then was) after citing
with approval the above passage from Watts & Hughes Properties went on to say:
“Need, in planning terms, is widely interpreted as indicating a facility
which will improve the ease, comfort, convenience and efficient
lifestyle of the community… there is a latent unsatisfied demand
which is either not being met at all or is not being adequately met…”
293 [2014] QPELR 479 at [245].
294 (2007) 156 LGERA 399 at [26].
295 [1998] QPELR 273 at 275.
296 [2003] QPELR 414 at paras [21] & [26].
-- 110 of 127 --
111
[287] While it can be readily accepted that there could be a wide range of levels of need
that might warrant approval despite conflict, it is uncontroversial that the greater the
conflict the higher the level of need that must be established to justify approval. In
this case, the level of conflict is of a higher order.
[288] Before going on to consider in more detail the evidence of the economists and the
“quarry management” experts, I should deal with two preliminary matters raised by
the appellant. The first of these matters is the criticism of the respondent’s use of
unapproved potential resource deposits in attempting to rebut the need case.
Particular reference was made to another quarry case decided by Robertson DCJ,
Neilsens Quality Gravels Pty Ltd v Brisbane City Council.297 In Neilsens, his Honour
observed:298
“I think Council’s submission to the effect that the designation of the
site in KRA 60 by SPP02/07 ‘merely protects the land from
encroachment by inappropriate development and preserves access to
it’, understates the importance of this fact in the assessment process.
It goes further in its terms, but does not ‘guarantee’ an approval which
will be subject to impact assessment against the relevant planning
scheme provisions.”
His Honour also observed:299
“In my view, nothing much turns on this because the reliance upon
unapproved sites in relation to availability of like resources is at best
speculative, and, in any event, Council’s economic need expert…
accepted that there is a significant difference in considering need,
between approved resources for extraction, and simply the presence of
resources in the ground, and that if one wants to properly evaluate
need, the relevant test is approved sites and not unapproved sites;
including unapproved sites in a KRA. That approach is consistent with
the approach I took in Parklands Blue; which was not criticised on
appeal…”
[289] I have no doubt that in the context of that case his Honour’s observations were correct.
However I, with respect, do not take his Honour to be saying that in every instance
reference to an unapproved KRA would invite impermissible speculation. Each case
will turn on its own facts and, depending on the evidence, it may well be established
297 [2016] QPELR 709: see also Parklands Blue Metal Pty Ltd v Sunshine Coast Regional Council
[2014] QPELR 479 at [268].
298 At [211].
299 At [153].
-- 111 of 127 --
112
that an existing KRA, even though unapproved for extraction at the time, is
nonetheless a relevant consideration in determining whether or not another quarry in
the vicinity is needed.
[290] The second preliminary matter raised by the appellant was to the effect that the
conduct of the respondent was inconsistent with that of a “model litigant” and
involved a course of conduct that ought be discouraged. In this context it was
submitted:300
“If the approach of seeking disclosure from commercial competitors
to defeat a need case based upon matters including the ‘future plans’
of non-party competitors was to become the norm in this court (in
either quarry cases or litigation more generally) it would result in a
number of undesirable outcomes including putting parties to greater
expense and increasing the length of trials.
Both outcomes would be contrary to Rule 4 of the Planning and
Environment Court Rules 2010, which seeks to facilitate the just and
expeditious resolution of the real issues in a proceeding at a minimum
of expense by avoiding and, inter alia, undue delay and expense…”
[291] Unwarranted disclosure and indeed unnecessary requests for further and better
particulars etc. must be discouraged. It wastes time, money and valuable court time.
That said, there will always be cases where disclosure, including non-party
disclosure, is necessary to ensure justice is done between the parties. In my view,
while I express no final view about it, whilst the non-party disclosure may have been
more limited than it was, some was necessary not only for the “quarry management”
experts but also for the economists. It is difficult to see how the respondent could
have met any need case advanced by the appellant without some detailed knowledge
about the availability of hard rock from other sources within reasonable proximity to
the Gold Coast and, in particular, the Southern Gold Coast area. That some of the
quarries and/or potential quarries might lie outside the respondent’s local government
area is not really to the point.
Quarry management
[292] Mr Gray was retained by the appellant and Mr Reed for the respondent. In the initial
approval process, Mr Gray had been engaged by the respondent and had
300 Appellant’s written submissions at paras 733-734.
-- 112 of 127 --
113
recommended approval of the development subject to conditions. Both Mr Gray and
Mr Reed primarily focused upon providing insights and details concerning the
capacities and capabilities of other hard rock quarries that might potentially fill any
supply void that might be created in the event that the subject application did not
proceed. That information was then utilised by the economists called by each of the
parties to address the question of need.
[293] For the reasons already given under the heading of “geology”, I am satisfied that the
subject land contains high quality hard rock which could be efficiently won to meet
demand well into the foreseeable future. It would also make a significant contribution
to employment opportunities in the Southern Gold Coast area, particularly during the
establishment and construction phases.
[294] In addition to contributing to the JER process, Mr Gray and Mr Reed also prepared
individual court reports. Mr Gray’s report is Exhibit 38 in redacted form and Exhibit
CC in un-redacted form. Mr Reed’s individual court report is Exhibit 63 in redacted
form and Exhibit CE in un-redacted form. The un-redacted exhibits contain sensitive
commercial information not only of the appellant but also of commercial competitors.
Mr Gray’s opinion about the proposal is neatly summarised in his court report:301
“I am of the opinion that the subject site (KRA 96) is a standout
resource to provide continuity of supply (when West Burleigh quarry
closes) of high quality greywacke quarry products into the Gold Coast
and Northern New South Wales region because of its:
(a) source of rock quality;
(b) size of recoverable resources; and
(c) favourable geographic location in Southern Gold Coast
City close to Pacific Motorway in an urbanised region soon
to be depleted of local hard rock alternatives.
To the best of my knowledge no other undeveloped available hard rock
deposits in the central and Southern Gold Coast City regions or in the
Tweed district are known to possess these attributes of fortuitous
geology and geography.
From a supply site perspective, I am of the opinion that in the absence
of locally available suitable alternatives, there exists a community
need in Gold Coast City and the Far Northern NSW region, for the
development of the Reedy Creek greywacke quarry.
301 Exhibit 38 paras 69-71.
-- 113 of 127 --
114
It is submitted that evidence of the quarry management experts
confirms the public interest and benefits that would occur through
approval of the quarry project and does not provide any basis upon
which to refuse the quarry project.”
[295] Mr Gray’s evidence was not seriously shaken in cross-examination.
[296] While clearly not as enthusiastic about the proposal as Mr Gray, the evidence of Mr
Reed was to the effect that he could see some benefit in the project proceeding at least
insofar as it had the potential to provide good quality material. During his cross-
examination by Mr Gore, the following exchange took place between myself and Mr
Reed:302
“Q: So are you saying that this site fails to meet the
commercial, technical or environmental criteria or
fails to meet all three or does it meet all three but
there’s another reason why it shouldn’t go ahead?
A: No. I don’t think it’s up to me to comment on whether
or not it meets the environmental criteria.
Q: Alright. Well, let’s look at the commercial… and
technical criteria.
A: Yes.
Q: Does it tick those boxes?
A: Yes.
Q: Yes it does?
A: Technically I think it’s – the rock is good. The – the –
the modelling and the work that’s been done by
groundwork on the – on the quarry planning etc. etc.,
is of a fairly high order. I do question the distance
between the back high wall and I think it’s the Bardon
Ridge Road houses. I thought that was incredibly
close, but that aside, so I think it would be probably –
I’d probably tick it on those boxes.”
That exchange continued:303
“Q: Look, remember the – and this goes back to the
exchange that you and I had yesterday. Remember I
was expressing some difficulty in understanding your
relationship between supply and demand?
A: Yes.
Q: Does it come down to this: that you don’t dispute that
when the West Burleigh quarry closes there will be a
demand for hard rock in the south Gold Coast area?
302 T25-11 ll 11-23.
303 T25-12 ll 5-46.
-- 114 of 127 --
115
A: No, there will be a demands – there will be a demand
for hard rock in the south Gold Coast area, yes.
Q: Right. But your proposition as I understand it is that
there’s no need for this quarry because the supply
could come from those quarries predominantly
located in the KRA67 area?
A: Your Honour, to a large extent it already does.
Q: Well, no---?
A: Yes.
Q: But is that right, that the quarry – if the quarry – the
subject quarry doesn’t go ahead the supply of the
southern Gold Coast market would be met by – I know
you’ve mentioned some south of the border, but
predominantly by those quarries KRA67, Holcim
Boral, Yatala Boral, Ormeau, Fulton and the Hogan
quarries?
A: Oxenford and Nerang, yes.
Q: Yes. So am I right so far?
A: Yes, your Honour. Yes, you are.
Q: Well, that brings me back then to the very first
question that – the very – one of the very first answers
you gave; in quarrying the two big ticket items are
overburden and transport. Put overburden to one side?
A: Yes.
Q: There’s a 40 kilometre distance between KRA67 and
West Burleigh?
A: Yes.
Q: So I’m struggling with that tension between that
answer you gave very early in the piece and---?
A: No, I understand, your Honour, and that’s why I say
through my report you’d need quantitative analysis.
It’s for this reason: 60 per cent or more of – let’s start
again. Less than 35 per cent of West Burleigh’s
current sales go into the south and central Gold Coast,
right. So that means that the other 55 per cent is
transported predominantly to concrete plants further
away. So that transport advantage obviously doesn’t
attach to those tonnes. If you look at the 35 or 31 to
35, depending whether you take five year or seven
year average, 31 to 35 per cent that’s sold into the
south and central Gold Coast, greater than 60 per cent
of that is then reloaded. It’s either covered in bitumen
that’s asphalt and reloaded or it goes through Gold
Coast City Council and it’s transported elsewhere
within the Gold Coast. So I say that only about 18 per
-- 115 of 127 --
116
cent maximum of what comes out of West Burleigh
has a transport advantage into the local area. Okay. Do
want me to go through the---”
[297] Following that exchange, Mr Gore continued:304
“Q: Mr Reed, you gave me the impression in some of
those exchanges that it’s not your position that this
application should be refused; you could see merit in
it?
A: Uh-huh.
Q: You’re simply giving some evidence to assist his
Honour to make that decision. Is that a fair summary
of your position?
…
Q: Is that a fair summary of your position?
A: Could you just repeat it exactly then, please?
Q: It’s not your position… that this application should be
refused. You recognise that that’s entirely a matter for
his Honour?
A: That’s for the court, yes.
Q: And you can see merit from a technical perspective in
the proposal?
A: Yes.
Q: You therefore simply give evidence about some
supply and supply and demand issues for his Honour
to take into account in deciding whether to approve or
refuse?
A: That’s correct with the caveat that the supply issues
are just as I mentioned from A to X on page 5 of my
– of my report.”
[298] The reference to the “caveats” concerning “supply issues” identified by Mr Reed are,
when read objectively, not caveats at all. They really provide a summary of what Mr
Reed considered to be the “major supply related issues.”305 Under the heading
“conclusions”, Mr Reed stated:306
“Areas of general agreement between myself and Mr Gray are
summarised at Table 1 and can be further summarised as follows:
304 T25-13 ll 9-29.
305 Exhibit 63 p 5.
306 Exhibit 63 p 20.
-- 116 of 127 --
117
(i) There are currently 9 hard rock quarries operated by
five major construction materials companies within
GCC.
(ii) Between them these quarries have in excess of 635*
million tonnes of approved resources with substantial,
currently un-approved, additional hard rock resources
under and/or adjacent to approved extraction
footprints.
*Agreement subject to Mr Gray accepting resource
figures presented in non-party disclosures – the figure
agreed in JER1 was 533M +5%.
(iii) Of these nine quarries, six will remain as long term
suppliers of quarry products after about 2025 when
remaining services of hard rock will be exhausted at
the West Burleigh, Yatala and Stonemaster quarries.
(iv) Existing GCC quarries have produced and sold
between 5.6M and 10.4M (average 7.75M) tpa of
processed hard rock products during the period 2000-
2016.
(v) Approximately half of these sales (averaging say
3.86Mtpa) have been made and delivered to GCC
markets with the balance exported to NNSW and
[predominantly] into other areas of SSEQ, ie, outside
of GCC.
(vi) NNSW currently has at least four (and DR says six)
established quarries, with currently approved
resources of about 30Mt, supplying into regional
markets which consume 1.2M to 1.3M tpa. However
Mr Gray and myself differ on quarry numbers and
relevancy.
(vii) SSEQ (excluding GCC) currently has 8 established
quarries (with approved resources of about 300Mt)
producing and selling 3.8M to 8.3M tpa. DR adds that
recent approval has been granted to five quarry
operators to increase production by five to six million
tpa. Once again, Mr Gray and myself disagree about
relevancy.”
[299] Following discussion involving the use of commercially sensitive material, Mr Reed
reached the following conclusions:307
“Assuming Boral upgrade their Ormeau quarry to produce 2Mtpa (as
per the 2012 development approval), there will be no specific GCC
community need for the proposed Reedy Creek quarry.
307 Ibid p 22.
-- 117 of 127 --
118
Existing/remaining GCC quarries will have ample production capacity
to meet local and regional demand for product.
It is difficult to see the community need or financial justification
for the 2Mtpa quarry proposed for the site.” (Emphasis added).
[300] The fundamental difference between the evidence of Messrs Gray and Reed is that
Mr Gray considers there is community need/benefit in the proposal proceeding and
Mr Reed does not, on the basis that there is sufficient supply capacity in existing
operating and/or potential quarry capacity.
[301] The respondent’s position in this context was stated in the following terms:308
“The council’s position is that the City has extensive approved
reserves of hard rock that are able to, and do, produce hard rock,
substantially in excess of demand within the City. Having regard to
the focus of the evidence (cf Exhibit 9 p 107), the Council’s position
is that none of the City of Gold Coast and Southeast Queensland (as
limited) and Northern New South Wales (as limited) are undersupplied
with hard rock and to the extent that some demand for the hard rock
might be established, it does not justify a hard rock quarry on (the
subject land).
If the council’s position is correct, there cannot be a strong need for
the project.
It follows that consideration should be directed to the productive
capacity of the City’s approved reserves; whether they produce hard
rock substantially in excess of demand within the City; and whether
there is an undersupply within the City, Southeast Queensland (as
limited) and Northern New South Wales (as limited).
…
The court can be comfortably satisfied that the City has extensive
approved reserves of hard rock that are able to, and do, produce hard
rock, substantially in excess of demand within the City and that none
of the City of Gold Coast and Southeast Queensland (as limited) and
Northern New South Wales (as limited) are undersupplied with hard
rock.”
[302] The reference to geographical areas being “as limited” is a description of the agreed
supply or catchment area for the proposed quarry which extends into the north-eastern
corner of New South Wales.309
308 Written submissions paras 526-528 and 555.
309 See Exhibit 26 at pp 12 and 13 and Exhibit 64 at pp 14, 22 and 23.
-- 118 of 127 --
119
[303] Finally, in respect of this evidence, while both Mr Gray and Mr Reed expressed
opinions about both the supply of and demand for hard rock, they were clearly of the
opinion that the issue of the level of need, in the sense of community/economic need,
was a matter to be addressed by the economists, and that their evidence was more
concerned with the “supply side” of the equation.310
The economic evidence
[304] Mr Norling was retained by the appellant to address the issue of community/economic
need and Mr Duane by the respondent. Apart from participating in the JER process,
both Mr Norling and Mr Duane produced individual court reports. Mr Norling
Exhibits 39 and CD and Mr Duane Exhibits 64 and CF. As was the case with the
quarry management experts, the un-redacted exhibits contained commercially
sensitive information.
[305] The evidence of the lay witnesses, who gave evidence on behalf of the appellant,
together with that of the economists, leaves me satisfied that there is a need for the
proposal. In that sense, there is a “ground” in support of approval. It would maintain
the competitive status quo and the efficient supply of high quality material from a
location convenient to the southern end of the Gold Coast. However, as identified
above, in the case of conflict with a planning scheme there must be “sufficient
grounds to justify the decision despite the conflict.” The determination of this contest
requires an abstract form of a cost benefit analysis, made all the more difficult because
on one side of the scales is the economic benefit to the community and on the other,
the less tangible benefits associated with maintaining biodiversity and amenity. In
this context the relevant “community” is wider than the inhabitants of the Gold Coast
local government area. For there to be sufficient grounds in this context, the enquiry
need not be confined to only those positive aspects, flowing from a proposal, that
occur within the subject local government area.
[306] In his conclusions expressed in the JER process, Mr Norling stated that there was a
“strong level of community, economic and planning need…” for the proposal. He
then went on to say why. At the risk of repetition, they could be summarised as:311
It would provide an essential product to the community.
310 See e.g. Exhibit 25, p 12, para 11; p48, paras 150-151 per Mr Gray, and p 49, para 160 per Mr Reed.
311 Exhibit 26 pp 49-50.
-- 119 of 127 --
120
Given the high volume low value nature of the product, location is particularly
important given the sensitivity of transport costs.
Any increase in transport costs would be likely passed onto end users which,
in turn, would have negative cost ramifications to the wider community.
It is but one of only two Gold Coast resources assessed as being of State
significance.
There is a diminishing supply of available hard rock resources to conveniently
and economically service the Gold Coast at Tweed Shire.
Approval of the development would allow the appellant to maintain its annual
operating capacity and geographical presence which would be of a community
benefit.
Should the proposal not proceed, competition would reduce, introducing the
risk of higher prices being passed on to an industry dominated by a smaller
number of operators.
Demand for extractive material in Southeast Queensland generally is
projected to continue to increase and that is particularly so in the subject local
government area.
The proposal would benefit the local and regional economies, particularly by
extending the life of an existing long-established business, supporting the
continued employment of 24 full-time employees on site (and even more
during the establishment and development phases).
[307] As to the town planning evidence, while not sharing the same level of support for the
proposal as Mr Schneider, it is clear that Mr Buckley also saw not only a community
benefit in exploiting a non-renewable resource but the potential for a community dis-
benefit arising in the event that the resource was rendered unrecoverable.312 A clear
example of how this could occur would be through ill-considered town planning
decisions. The evidence of all the witnesses concerned with quarry management,
economics and town planning considered it to be in the community interest not to
have this SKRA effectively sterilised by inappropriate future planning.
[308] I accept the positive community outcomes identified by Mr Norling, as set out above,
would be likely to occur. On this topic the case was made a particularly difficult one
to decide because there were many aspects of Mr Duane’s evidence that were no less
convincing. It is clear from a number of exchanges that occurred during his cross-
312 T32-50.
-- 120 of 127 --
121
examination that he saw a number of positive outcomes that might occur if the
proposal went ahead. During his cross-examination, the following exchange took
place:313
“Q: Mr Duane, although the exercise might be a difficult
one to carry out, the thrust of your evidence is that
there can be no doubt that it would be a positive
outcome, in the sense that an approval of this
application would involve a saving in transport costs?
A: Most likely for that central and southern sector, yes.
At the high level. It just depends on what happens
with the product that might have been redirected from
Ormeau, but I am happy to concede for that central
southern sector there would be transport advantages.
Q: Well, can we perhaps shorten things this way. From
an economic perspective you cannot point to any
negative aspect of an approval in (sic) this application.
You can only point to positive aspects, and it’s the
degree of the public benefit that we may have a debate
about.
A: That would be right.”
[309] Mr Duane’s evidence was, like that of Messrs Norling, Schneider and Buckley, to the
effect that it was an important planning outcome that, at the very least, this significant
resource should be preserved to permit future exploitation.314
[310] In his court report Mr Duane stated:315
“The key issue in dispute in relation to the subject quarry is best
described as follows:
(a) Gold Coast quarries have capacity to produce and supply
around 10 million tonnes of hard rock quarrying product
annually;
(b) the Gold Coast market is projected to demand approximately
4.3 million tonnes of hard rock material currently, growing
to 6 million tonnes over the period to 2031; and
(c) there are enough quarries on the Gold Coast to service the
Gold Coast market over time and still allow 4 million tonnes
to be directed elsewhere.
There is no need for the subject quarry to service the hard rock
demands of the Gold Coast on this basis.
313 T26-61 L 35 – T26-62 L 15.
314 E.g. T26-59 L 45 – T26-60 L 20.
315 Exhibit 64, p 3, paras 7.1-7.3.
-- 121 of 127 --
122
The question then becomes, is further hard rock quarrying material
produced on the Gold Coast required to service areas outside the Gold
Coast on an ongoing basis…”
[311] In the appellant’s written submissions it was contended that Mr Duane’s analysis was
flawed because he limited “the question to the need for the quarry to service the hard
rock demands of the Gold Coast.” It was said that this was a careful choice of
language.316 To an extent, Mr Duane seemed to concede that he had so limited his
analysis.317 Had he done so it would have been a mistake. The subject resource is a
state key resource intended for the benefit of all Queensland, but at a more practical
level for Southeast Queensland. However, on balance it seems tolerably clear to me
that when viewed in context, Mr Duane, like Mr Norling, considered the question of
supply and demand beyond the local government boundaries of the respondent.318
[312] During the JER process, agreement was reached in respect of a number of matters
including:319
The appellant is a highly vertically integrated corporation with extensive
presence in Southeast Queensland and on the Gold Coast where it operates
three quarries, an asphalt plant and five premix concrete batching plants.
The appellant’s Northern Gold Coast quarries (Yatala and Ormeau) primarily
service the greater Brisbane area (88%), with its West Burleigh quarry
primarily servicing the Gold Coast market (76%) Northern NSW (18%) and
greater Brisbane (6%).
The Gold Coast City is the dominant producer of quarry material in Southeast
Queensland generating almost 40% of total production. Its annual production
has recently ranged from 7.4Mt to 12.1Mt.
Approximately 55% of the Gold Coast City’s production of quarry material is
exported to other regions, mainly Brisbane and Logan resulting in production
exceeding demand by a factor of about two.
There are 9 operating quarries within the respondent’s local government area,
having a collective resource capacity of about 530Mt and an annual
production range of 7-10Mt. Three of these quarries are expected to cease
316 Appellant’s written submissions at para 789.
317 E.g. T26-57 ll 15-40.
318 T26-59 ll 4-42.
319 Exhibit 39, pp 5-6.
-- 122 of 127 --
123
operations within the next 10 years, reducing the annual production range to
5.4 - 7.5Mt. Two of the three quarries to close are operated by the appellant.
Annual demand for quarry material on the Gold Coast is projected to increase
from 5.1Mt currently to 7.0Mt in 2031.
There has been a trend for hard rock quarries to generate an increase in
proportion of quarry materials.
If approved and operating, the proposal would achieve production levels of at
least 1.0Mt per annum over its first 10 years of operation.
[313] According to Mr Norling:320
“…approval of the proposed expansion would therefore provide
savings to the community through the provision of a lower cost
product and in avoiding the negative impacts that trucking of
alternative product from further afield would have on the community.
Extraction of the proposed Gold Coast Quarry resource would provide
cost savings to the construction industry of about $270m, based upon
the following assumptions:…”
[314] For the reasons expressed by Mr Duane,321 I consider Mr Norling’s evidence on this
matter to be, with all due respect, something of a best guess but nonetheless a well-
informed one dealing with a very complex issue. As Mr Norling himself effectively
acknowledged, one could make any number of assumptions that might affect the final
outcome but, according to him, the $270m estimate was “in the order of magnitude”
that might be expected.322 It emerged during cross-examination that bringing into
account quarries in Northern New South Wales, which ought to be done, those cost
savings might have had to be reduced by about 10% to 20%. However, after further
consideration Mr Norling thought the adjustment would be less than 10%.323
[315] According to Mr Duane the figure of $270m was speculative and would be an
“absolute maximum.”324 Given the number of variables involved including the
competitive nature of the industry and the degree of vertical integration involved in
the appellant’s corporate structure,325 Mr Duane may well be correct. However, for
320 Exhibit 26, p 44, para 170.
321 Ibid p 45 para 172.
322 T26-7 ll 14-22.
323 T26-45 ll 20-37.
324 T26-53 ll 16-37.
325 In the Gold Coast region the appellant’s quarries supply an asphalt plant, 5 concrete batching plants
and a concrete batching plant at Chinderah, Northern New South Wales.
-- 123 of 127 --
124
the purpose of the exercise I will adopt Mr Norling’s figure adjusted by 10%. That is
$243 million in current day dollar terms.326
[316] As I understand the evidence, those savings would be spread over the life of the
quarry. If 40 years, that would result in a saving of about $6m p.a. and if 60 years,
then just under $4m p.a. It also needs to be borne in mind that any associated
economic costs may not be permanent in the sense that those savings may be
recovered, at least in part, in the event that the resource was quarried sometime in the
future.
[317] In any event, while these cost savings are a relevant consideration, they are in no way
determinative.
[318] Having regard to the totality of the evidence concerning existing and approved quarry
capacity, it seems tolerably clear that there is more than sufficient capacity to meet
any demand for hard rock within the respondent’s local government area into the
foreseeable future, albeit with costs ramifications. I have reached this conclusion
without bringing into account as yet unapproved resources.
[319] The evidence also satisfies me that up until at or about 2031, there will be sufficient
capacity to supply not only the Gold Coast City area but also the existing Southeast
Queensland and Northern New South Wales markets. The operating quarries within
the Gold Coast City area have a collective resource capacity of about 530Mt with an
annual production range of between 7-10Mt. The lower end of that range currently
exceeds the existing demand for hard rock in the Gold Coast City area (5.1Mt) and
the upper end of that range materially exceeds the projected demand of 7.0Mt in 2031.
It is true that between now and at or about 2026 three of those quarries will cease
operations, reducing annual production to between 5.4 – 7.5Mt.327 The lower end of
that range falls below the projected 2031 demand and, at the upper end, is only
marginally above the 2031 demand. However, this has to be seen in the context of Mr
Reed’s evidence that when existing and approved extractive industry are looked at
together, “between them these quarries have in excess of 635 million tonnes of
approved resources…”328 It is clear that provided sufficient resources exist quarry
operators will ramp up output to match demand.
326 T26-41 L 33.
327 See Exhibit 26 at para [88] and Table 10 at p 34.
328 Exhibit 63, p 20, para 113(ii).
-- 124 of 127 --
125
[320] According to Mr Gray, Mr Reed’s assessment of 635Mt was “within the realms of
reasonableness.”329
[321] During the course of Mr Duane’s cross-examination, the following exchanges took
place:330
“Q: It’s going to have a real benefit. It’s a significant
resource that’s going to be there for a long time?
A: That resource would be there for a long time if it was
approved, so yes, it would add to the supply in the
market over a period of time. This is 2031, so yes,
post-2031, if that’s what was – if nothing else was
approved by that time, having another quarry
approved at any level would have some benefit, yes.”
And then later:331
“Q: It’s a resource that should be protected: it’s
vulnerable, being so close to the Gold Coast, as we
know so?
A: I suppose the best way to summarise it, your Honour,
is what I’m saying is, from a supply and demand
assessment, there’s no need for this over the period
we’ve looked at to 2031, 2040, 2050, there might be
a need, a greater need, and it might be a more pressing
need for this sort of resource. So from an economist’s
point of view, would you protect that if it can be
extracted in a manner which would be economic, yes
you would.”
[322] The quarry management and economic evidence has led me to conclude that it is more
likely than not that the earliest that there might be a supply issue, and therefore a more
pressing need for an additional hard rock quarry, would be at or about 2031, but more
likely at or about 2040.
[323] In this context, while Mr Norling identified a number of community benefits that
would flow from the proposal if approved, and a number of negatives if it was not, at
no stage did I understand him to be saying the proposed quarry was necessary to meet
or remedy an undersupply situation.
329 T22-22, ll 35-46.
330 T26-67 ll 15-18.
331 T26-68 ll 8-19.
-- 125 of 127 --
126
[324] The evidence of the “quarry management” experts and the economists leads me to
reach the following conclusions:
(i) there is a need for the quarry in the sense that it would ensure
a continuation of supply of good quality hard rock material in
the Southern Gold Coast area;
(ii) in the event that the proposal did not proceed there is a realistic
risk of competition reducing with consequential price
increases, and there will be additional costs to the community
of in the order of $240 million over the life of the quarry;
(iii) notwithstanding the above, approved resources located within
the respondent’s local government area would be sufficient to
meet demand within that area for decades and meet demand
within the wider Southeast Queensland region and Northern
New South Wales for at least another 15 years; and
(iv) it is in the interest of the broader Southeast Queensland
community that this key resource be protected to ensure its
availability for exploitation when appropriate.
Conclusions
[325] The evidence presented during the course of this proceeding establishes three
fundamental things. First, the subject land contains a significant volume of a resource
of State significance. Second, there is a level of current need for the proposal to the
extent identified above. Third, the proposal is in material conflict with important
objects and outcomes of the respondent’s planning scheme, particularly in respect of
the protection of the biodiversity value of the site and its surrounds, the green
ridgeline backdrop and urban amenity.
[326] I found this case to be quite a difficult one to decide but, on balance, I have come to
the conclusion that I am not satisfied that there are sufficient grounds to justify
approval. In that context I agree with the submission made by Mr Litster to the effect
that, under the relevant planning regime, the balance currently favours refusal of the
application. That said, there can be no doubt based on the evidence of all of the
relevant experts that this significant resource should be protected for future
exploitation when appropriate.
-- 126 of 127 --
127
[327] For the reasons given the appeal must be dismissed.
Orders
1. The appeal is dismissed.
2. If necessary, I will hear from the parties as to any consequential orders.
-- 127 of 127 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2017/023