Cidneo Pty Ltd v Department of Transport and Main Roads (No 3) [2017] QLC 45
LAND COURT OF QUEENSLAND
CITATION: Cidneo Pty Ltd v Department of Transport and Main Roads
(No 3) [2017] QLC 45
PARTIES: Cidneo Pty Ltd
ACN 105 454 064
(applicant)
v
Chief Executive, Department of Transport and Main
Roads
(respondent)
FILE NO/s: AQL325-10
DIVISION: General Division
PROCEEDING: Determination of compensation under the Acquisition of
Land Act 1967
DELIVERED ON: 24 August 2017
DELIVERED AT: Brisbane
HEARD ON: 22, 23, 24 February 2016
Submissions closed 4 March 2017
HEARD AT: Brisbane
MEMBER: WL Cochrane
ORDER/S: Compensation is payable by the respondent to the
applicant for the taking on 22 February 2008 of an area
of 8.385 hectares being Lot 1 on SP 218520 being part of
the land contained in title reference 50553649, County of
Stanley, Parish of Oxley in the sum of Six Million Three
Hundred and Seventy-Seven Thousand Eight Hundred
Dollars ($6,377,800).
CATCHWORDS: REAL PROPERTY – compulsory acquisition of land –
compensation – proceedings for compensation – resumption
of land – valuation methodology – contribution for traffic
infrastructure – before and after method – remitted hearing.
Acquisition of Land Act 1967, s 20
-- 1 of 42 --
2
Boland v Yates Property Corporation Pty Ltd [1999] 74
ALJR 209
Brisbane City Council v Mio Art Pty Ltd & Anor [2011]
QCA 234
Chief Executive, Department of Transport and Main Roads
v Cidneo Pty Ltd [2015] QCA 96
Cidneo Pty Ltd v Chief Executive, Department of Transport
and Main Roads [2011] QLC 18
Cidneo Pty Ltd v Chief Executive, Department of Transport
and Main Roads [2013] QLC 47
Cidneo Pty Ltd v Chief Executive, Department of Transport
and Main Roads [2014] QLAC 3
Clarke v Japan Machines (Australia) Pty Ltd [1984] 1 Qd R
404
Commissioner of Succession Duties (SA) v Executor Trustee
and Agency Company of South Australia Ltd [1947] 74 CLR
358
Gregory v FCT [1971] 123 CLR 547
Heavey Lex No 64 Pty Ltd & S Paino v Chief Executive,
Department of Transport [1999] QLC 133
Heavey Lex No 64 Pty Ltd & S Paino v Chief Executive,
Department of Transport (2001) 22 QLCR 177
Leichhardt Council v Roads and Traffic Authority (NSW)
(No 2) [2008] NSWLEC 1
APPEARANCES: MD Hinson QC (instructed by Anderssen Lawyers) for the
applicant
DR Gore QC , with J Brien of Counsel (instructed by
Clayton Utz Lawyers) for the respondent
Assessment
[1] This is a matter which has been remitted back from the Court of Appeal via the
Land Appeal Court for determination in accordance with grounds which were
successfully appealed against in the original decision.
[2] On 26 July 2013, I delivered a judgment ordering that the compensation payable by
the respondent to the applicant for a resumption which occurred on 22 February
2008 was $6,900,000.1
1 Cidneo Pty Ltd v Chief Executive, Department of Transport and Main Roads [2013] QLC 47.
-- 2 of 42 --
3
Land Appeal Court proceedings
[3] Subsequently, Cidneo appealed to the Land Appeal Court in respect of three
grounds of appeal.
[4] The Department of Transport and Main Roads (“DTMR”) cross appealed.
[5] In the event, the Land Appeal Court allowed the appeal by Cidneo in respect of
three grounds.
[6] The first ground of appeal as set out in the Land Appeal Court reasons is articulated
as follows:
“The first ground of appeal was that the learned Member erred in
determining, for the purpose of the cash flow analysis, that the appropriate
figure to adopt for a contribution for road works (other than on Boundary
Road) was $3,000,000. In relation to that ground it was submitted for
Cidneo that the learned Member erred in law by disregarding relevant
evidence...”2
[7] The Land Appeal Court upheld the first ground of appeal.
[8] In the Land Appeal Court judgment the Court said:
“For DTMR it was submitted that the valuation which the learned Member
adopted of the land retained by Cidneo was correct, because the road works
contributions payable to DTMR were likely to be the same in the before
and after cases. A number of its other submissions seem to have been
directed to supporting this proposition. The point of the submission
appears to have been that, on that basis, since neither party suggested a
significant contribution for external road works in the before case, the
learned Member was right to reach the conclusion he reached for the after
case. That does not address the question whether the learned Member
considered relevant evidence, and gave adequate explanations for his
reasons, nor does it address the question whether he erred in the conclusion
he reached about the value of the retained land. Cidneo’s submissions may
cast doubt on the correctness of the assumptions about contributions, and
on the value of the land, in the before resumption case; but these matters
were not in issue in the appeal.” 3
[9] The Land Appeal Court further commented:
“Ground 2 of the Notice of Appeal alleged that the Land Court erred in not
accepting and acting on evidence called in Cidneo’s case that, in assessing
the value of its retained land after resumption, an additional period of six
months should have been allowed for the time assumed to be taken to
develop and sell lots resulting from the subdivision of the land. The
written submissions for Cidneo supported this ground. The submissions
identified the six month period as being an extra six months in part
occasioned by the need for a further traffic analysis, but also by the need to
2 Cidneo Pty Ltd v Chief Executive, Department of Transport and Main Roads [2014] QLAC 3 at [25].
3 Ibid at [66].
-- 3 of 42 --
4
redesign the estate in relation to the construction of Boundary Road, and
the hydraulics associated with Bullockhead Creek. It was orally submitted
that the evidence in support of this longer period was uncontradicted, but
not referred to in the reasons of the learned Member. It was submitted that
the reasons identified the issue, but did not resolve it. Alternatively, if the
issue was taken to be implicitly resolved by the adoption of Mr Brett’s
valuation, then the Land Court erred in failing to give reasons for doing
so.”4
[10] The second ground of appeal was also upheld by the Land Appeal Court:
“There was a real issue between the parties on this question. It was raised
by the differences in the cash flow analyses, and was the subject of
submissions on behalf of Cidneo in the Land Court. The matters raised by
Mr Viney and Mr Cumming in support of the longer period are not
obviously without substance, so that a failure to discuss them might be
explained on that basis. The reasons for judgment provide no basis for
thinking that the learned Member considered this issue, and decided to
accept the approach taken by Mr Brett on the basis of such a consideration.
So far as is apparent from the reasons, the opposite is true.
The submission made on behalf of DTMR that the matter is covered by the
assumption, apparently derived from Spencer, that the parties are aware of
all relevant facts, is novel. No authority was cited in support of it. It is
difficult to see how the assumption would account for the existence of a
traffic study, no doubt to be presented in support of a development
application. The submission should not be accepted.”5
[11] The third ground of appeal was expressed as follows:
“Ground 3 of the Notice of Appeal alleged that the Land Court erred in
adopting Mr Brett’s period of 62 months for the development and sale of
the land in the post-resumption case. Mr Hamilton’s cash flow analysis
assumed a period of 76 months. The submissions for Cidneo made clear
that, of the 14 months’ difference, six months was accounted for by the
period the subject of Ground 2. In relation to the balance (8 months), it
was submitted that the Land Court erred in particular in accepting Mr
Brett’s evidence as to his rate of sale for lots produced in Stage 3, being
two sales per month. It was submitted that the Land Court Member erred
in failing to take into account evidence from Mr Whitelaw and Mr
Hamilton criticising this rate of sale; as well as Mr Brett’s own
acknowledgement that in February 2008 it could be expected that credit
(and, if it be different, finance) was tightening. It was also submitted that
Mr Brett in his cash flow analysis assumed an overlap in the construction
of stages of the development (thus reducing the time required for the
project); which he acknowledged might not be the approach of the prudent
purchaser’ but the learned Member failed to deal with this evidence.”6
[12] The Land Appeal Court allowed the third ground of appeal:
“Ground 4 of the Notice of Appeal alleged that the Land Court erred in
accepting Mr Brett’s evidence that in February 2008 a low internal rate of
return was acceptable for his cash flow analysis. The submissions for
4 Ibid at [29].
5 Ibid at [74] to [75].
6 Ibid at [30].
-- 4 of 42 --
5
Cidneo in relation to this ground of appeal criticised Mr Brett’s approach of
deriving an internal rate of return from a cash flow analysis, rather than
adopting such a rate as an input for the analysis. It was submitted that his
explanation that in February 2008 the market was speculative, was
inconsistent with the agreed highest and best use of the land for
development for industry and warehouse purposes; as this use did not
include land banking. It was submitted that these matters were not dealt
with in the reasons for judgment.”
[13] From the Land Appeal Court determination, DTMR appealed to the Court of
Appeal against the Land Appeal Court’s confirmation that the Land Court could not
take into account the transport infrastructure contribution actually required when
assessing the just amount of compensation. That actual figure was $1,087,110 not
the $3,000,000 which was initially relied upon in the Land Court. As the Court of
Appeal observed:
“In DTMR’s cross appeal it contended that the Land Court erred in law in
concluding that it could not take into account the transport infrastructure
contribution actually required when assessing the just amount of
compensation. DTMR contended that, using the known cost of $1,087,110
instead of the estimated cost of $3,000,000, compensation should have
been less than the amount determined in the Land Court. Upon that
footing, and assuming that an assessment using a combination of the before
and after method and cash flow analyses was appropriate, DTMR
contended that the amount of compensation should be reduced to
$6,377,800 in accordance with Mr Brett’s Further Supplementary Report.
DTMR also contended in its cross appeal that the Land Court erred in
failing to prefer a method of assessment which separately assessed each
head of Cidneo’s loss under s 20 of ALA. DTMR argued that the before
and after method would not produce a fair assessment of compensation and
that (any) injurious affection or severance damage should have been
separately assessed with reference to the actual amount of the transport
infrastructure contribution. Under that ground of the cross appeal DTMR
contended that the compensation should be reduced to $6,100,000 in
accordance with the “check valuation” in Mr Brett’s “Further
Supplementary Report” which separately valued the resumed land at
$4,533,954 and “injurious affect” at $1,530,405.
In relation to that issue the Land Appeal Court held that if Cidneo’s appeal
was allowed the submission that the use of the before and after method
would result in an unfair assessment of compensation was somewhat
speculative. Furthermore, because the contribution was relevant to the
value of the land at the resumption date its amount was not to be
determined by reference to knowledge of subsequent events except where
they demonstrated the existence of facts known to the parties at the
resumption date; it followed that the assessment of compensation would
not unfair despite subsequent events turning out to be different from those
known, or taken to be likely, at the date of the resumption.”7
7 Cidneo Pty Ltd v Chief Executive, Department of Transport and Main Roads [2015] QCA 96 at [18],
[20] and [21].
-- 5 of 42 --
6
[14] DTMR expressed its grounds of appeal in the following terms:
“1. The Land Appeal Court erred in law in deciding:
(a) That, for the purposes of s 20(1) of the Acquisition of Land Act 1967
(reprint no 5A) (“ALA”), in considering the damage (if any) caused to the
retained land of the Respondent, the Land Court was not entitled to take
into account events subsequent to the resumption on 22 February 2008, in
particular, the cost of external roadworks agreed between the Applicant and
the Respondent on 6 December 2011 (“the external roadworks costs”);
(b) That neither the external roadworks costs nor any estimated transport
infrastructure contributions were relevant to, or came within, severance
damage or injurious affection damage, for the purposes of s 20(1) of the
ALA;
(c) That, where the before and after approach is used to determine
compensation, in the assessment of the value of the retained land in the
after case, either s 20 of the ALA or the decision in Brisbane City Council
v Mio Art Pty Ltd [2011] QCA 234; [2012] 2 Qd R 1 (“Mio Art”) requires
that the quantum of any costs must be fixed at the date of resumption,
without taking into account any known subsequent increase or decrease in
such costs;”8
Court of Appeal proceedings
[15] The Court of Appeal considered only the first ground of appeal.9
[16] In the course of his decision, Fraser JA (with whom the other members of Court
agreed) said:
“DTMR also argued that the Land Appeal Court should have allowed
DTMR’s cross appeal and assessed compensation in accordance with Mr
Brett’s Further Supplementary Report. The argument was based upon the
circumstance that the compensation of $6,900,000 determined in the Land
Court (taking into account the estimate of $3,000,000 for the transport
infrastructure contribution) exceeded the assessment of $6,377,800 in Mr
Brett’s Further Supplementary Report (which took into account the
transport infrastructure contribution of $1,087,110 actually required). In
response, Cidneo pointed to Mr Hamilton’s opinion that if the transport
infrastructure contribution actually required should be taken into account,
so too should DTMR’s demand in 2010 for a contribution of $13.7 million
and the time and cost required to achieve the reduction in the transport
infrastructure contribution be taken into account in the cash flows. As I
have mentioned, upon that basis Mr Hamilton’s evidence implied an
assessment of compensation of $27,350,000 (based on a pre-construction
phase of 33 months) or $22,250,000 (based on a pre-construction phase of
25 months).
The exercise conducted by Mr Hamilton appears to involve contestable
valuation judgments and assumptions, including an assumption that
Cidneo’s holding costs (which apparently account for most of the amounts
mentioned by Mr Hamilton) would not have been incurred but for the delay
in reaching agreement upon the amount of the contribution. Neither the
Land Court nor the Land Appeal Court has addressed those issues or made
8 Ibid at [25].
9 Ibid at [29].
-- 6 of 42 --
7
any determination with reference to the calculations in Mr Brett’s Further
Supplementary Report. If it becomes necessary to do so, the Land Court,
as the specialist tribunal established to resolve issues of that kind, should
determine them. For that reason, I would hold that the Land Appeal Court
was correct in not determining compensation in an amount claimed in the
cross appeal. Instead, the matter should have been remitted to the Land
Court for the determination of compensation.”
The current proceedings
[17] Accordingly, the matter was remitted to this Court for determination in accordance
with the Land Appeal Court’s determination relating to grounds of appeal 2 and 3
and the Court of Appeal’s determination in respect of the first ground of appeal
brought by the Department in that Court.
[18] At the remitted hearing, the parties tendered an agreed bundle of documents
including valuation reports prepared by Mr Hamilton and by Mr Brett, traffic
engineering reports prepared by Mr Viney and Mr Beard, and affidavits of Peter
McGregor and Majella Pollard.
[19] The valuation reports of Mr Hamilton included two reports which post-dated the
decision of the Land Appeal Court namely: an addendum report to Mr Hamilton’s
compensation report of 4 November 2015,10 and a second addendum report to Mr
Hamilton’s compensation report dated 3 February 2016.11
[20] Similarly, the valuation reports of Mr Brett included an addendum report by him,
dated 3 December 2015.12
[21] Clearly, the documents in the agreed bundle were agreed subject to the entitlement
to object to the content of the document or the use proposed to be made of it.
[22] At the beginning of the remitted hearing Mr Gore QC, Counsel for the respondent,
dealt with the reports of Mr Hamilton referred to correspondence sent to the
applicant’s solicitors prior to the hearing. That correspondence said, inter alia;
“1.1 The respondent objects to the following aspects in both the body of the
report and the after resumption scenario cash-flows on the ground that the
changes are outside the scope of the remitter from the Land Appeal Court
or the Court of Appeal:
10 Ex R5.
11 Ex R6.
12 Ex R10.
-- 7 of 42 --
8
(a) the introduction of an 8 month delay between stages 2 and 3, with
construction commencing at months 29, 35 or 41;
(b) the use of an infrastructure charge of $3,000,000;
(c) an increase in the pre-construction phase from 12 months to 18 months.
1.2 The Respondent objects to Mr Hamilton’s challenge in Section 2 of the report to
Mr Brett’s piecemeal approach as being unreliable and not even a worthwhile check
method on the ground that Mr Hamilton did not express any disagreement with Mr
Brett’s evidence about those matters in the original hearing in 2011 and 2012, and
so this belated challenge is outside the scope of the remitter from the Land Appeal
Court or the Court of Appeal.” 13
[23] In supporting his objection, Mr Gore referred to the Land Appeal Court decision
wherein it is said:
“It follows that the reasons for judgment indicate that the learned Member
recognised the need to determine which rate of sales should be preferred;
he expressed a preference for that adopted by Mr Brett; and he gave brief
reasons for doing so. It cannot be said that he failed to determine the issue.
Although brief, his reasons provide some explanation for his conclusion on
this question…”14
[24] Mr Gore also referred to paragraphs 77, 78, 83 and 84 of the Land Appeal Court
reasons to point out that the eight-month difference between Mr Brett and Mr
Hamilton was an issue in my decision; secondly, that the rate of sales of lots in
stage three was a relevant issue; and thirdly, that the construction program for stage
three was a relevant issue. All of those matters were raised in ground three of the
appeal to the Land Appeal Court, and he further submitted that, given the Land
Appeal Court’s decision in respect of those grounds, there is no scope for any
further evidence or indeed for any further submissions.15
[25] With respect to the second objection (paragraph 1.2) which relates to the use of an
infrastructure charge of $3,000,000, Mr Gore referred to Mr Brett’s further
supplementary report.16 Mr Brett here gave consideration to the actual transport
infrastructure charges of $1,087,110,000, and to which I declined to give weight on
the basis that it reflected figures not available to the parties or known by them as at
the date of resumption. Mr Brett had utilised those figures in his check method to
confirm an earlier analysis carried out by him, and Mr Hamilton did not challenge
that part of the check method at the original hearing, which matter was referred to in
13 Ex R27.
14 Cidneo Pty Ltd v Chief Executive, Department of Transport and Main Roads [2014] QLAC 3 at [82].
15 T 1-7, line 35.
16 Ex R9.
-- 8 of 42 --
9
the two appellate Courts above, and which Mr Gore submits to Mr Hamilton is now
not entitled to do.
[26] Mr Gore’s basic point was that to do so would offend the basic rule about fresh
evidence; if there was evidence available at the time that they could have put in, but
did not.
[27] In support of his submissions, Mr Gore refers to the decision in Clarke v Japan
Machines (Australia) Pty Ltd,17 and in particular the observations of Thomas J (as
his Honour then was), where his Honour considered that special grounds were
needed before evidence which had otherwise been available at an earlier time that
should be received.
[28] His Honour stated:
“The classic statement of what amounts to “special grounds” for reception
of further evidence upon an appeal was approved recently by Lord Bridge
in Langdale v Danby [1982] 3 All E.R. 129 at 137-138. Three conditions
must be fulfilled. “First it must be shown that the evidence could not have
been obtained with reasonable diligence for use at the trial: second, the
evidence must be such that, if given, it would probably have an important
influence on the result of the case, although it need not be decisive: third,
the evidence must be such as is presumably to be believed, or in other
words, it must be apparently credible, though it need not be
incontrovertible.”” 18
[29] He also referred to the decision of the New South Wales Land and Environment
Court in Leichhardt Council v Roads and Traffic Authority of New South Wales,19
which considered an application for leave to adduce further evidence on the remitter
of a matter from the Court of Appeal.
[30] In the course of the decision, Lloyd J said as follows:
“The appeal rules relating to fresh evidence, whilst not determinative,
provide a useful guide as to the manner in which the discretion should be
exercised: Smith v New South Wales Bar Association [1992] 176 CLR 256
at 266-267, Carriage v Stockland Development Pty Ltd (No 5) [2004]
NSWLEC 674. Those principles have been correctly identified by the
council and noted in par [9](b) above.”
[31] The paragraph 9(b) referred to the submissions of the appellant local government
and stated as follows:
17 Clarke v Japan Machines (Australia) Pty Ltd [1984] 1 Qd R 404.
18 Ibid at [408].
19 Leichhardt Council v Roads and Traffic Authority (NSW) (No 2) [2008] NSWLEC 1.
-- 9 of 42 --
10
“Three conditions must be met before fresh evidence can be admitted on
appeal: (i) it must be shown that the evidence could not have been obtained
with reasonable diligence for use at the trial; (ii) the evidence must be such
that there must be a high degree of probability that there could be a
different verdict; and (iii) the evidence must be credible: Atkins v National
Australia Bank (1994) 34 NSWLR 155 at 160 per Clarke JA (Shelter JA
agreeing).”20
[32] As to the second ground of objections (paragraphs 1.1 to 1.2), Mr Gore conceded
that it overstated the actual position because reference to the transcript demonstrates
that Mr Hamilton did disagree with Mr Brett’s check method.21
[33] In attempting to clarify his position, Mr Gore said the following to the Court:
“I just wanted to add, for your Honour’s assistance and my learned friends
assistance … some more specificity in relation to paragraph 1.2 of exhibit
R27. Having acknowledged it’s too wide, I would like to be more specific,
and if your Honour would go to Mr Hamilton’s 2016 report … and if your
Honour goes to page 9 ... he is responding to parts of Mr Brett’s 2015
report. And if your Honour just reads the first sentence of paragraph 2.2 …
so in that first sentence he is clearly dealing with the figure of $4.3 million
that Mr Brett has referred to in all of his 2011 and 2012 reports and now
repeats in his 2015 reports and it’s that evidence of Mr Hamilton which is
fresh evidence that offends the fresh evidence rules. And that’s a clear
example, we respectfully submit, not for your Honour to rule on now, but
for ruling on at the end of the case in light of your Honour’s information of
what we intended to object to.”22
[34] Mr Gore also referred to paragraphs 2.7, 8, 9 and 16.23
[35] Lest it be thought that Mr Hinson for the applicant agreed, on the face of Mr Gore’s
submissions, Mr Hinson said as follows:
“And the respondent submits that the scope of the remitter includes the
approaches taken by Mr Brett and Mr Hamilton of their supplementary
reports. And both parties seek to expand upon the issues raised in those
reports, and, on the face of it that should be permitted. Now, part of that
exercise involves Mr Brett now saying, and this appears from paragraph 34
on the following page, subparagraph (a). This now involves Mr Brett
saying I now prefer the piecemeal method rather than the before and after
method. So that now is being put forward by Mr Brett as the primary
evaluation approach, not the before and after method, at the original
hearing where the piecemeal was described as a check.
And what the department is, in effect, saying is that now that Mr Brett
wants to put forward the piecemeal mode of assessment as the primary
assessment, not the check method, my side is not permitted to respond to
that in the way that Mr Hamilton responds in his February 2016 report. In
other words, while there is a change of Mr Brett’s preference in the
20 Ibid at [9].
21 T 1-13, line 8.
22 T 1-15, line 20 to T 1-16, line 23.
23 T 1-16, lines 10 to 22.
-- 10 of 42 --
11
appropriate method from before and after cash flow to piecemeal method
my side is not to be permitted to challenge that, and is only permitted to
challenge it on the basis that we did in the primary hearing where it wasn’t
the preferred method, but was simply said to be a check method.
Now, your Honour might well understand a challenge to a check method
evaluation in a primary hearing might not be as complete and
comprehensive as a challenge to what was now said to be the preferred
method of assessment. It was very much a side issue in the first hearing,
because as there were – as your Honour will recall, there were joint reports
saying the before and after cash flow analysis is the best way to bring out
the differences. And Mr Brett simply put this up as a check method. And
if your Honour has the transcript could I trouble your Honour to go back to
the transcript to day six where at page 6-72 ---
…
This is Mr Brett’s examination-in-chief [indistinct] this isn’t meant to be
something that’s precise. It’s meant to be something that assists the court
in getting a feeling of a general level. So the first hearing – this was
described by Mr Brett as a check method. Your Honour might recall I
cross-examined Mr Brett about it, and he agreed that many of the figures
that he used in the check method were themselves taken out of the cash
flow. And I’ve put to him the proposition that if you use different outputs
from the different cash flow, Mr Hamilton’s, for example, you’d get a
different result. And he agreed. This was obviously correct.
So this was very much something which was not meant to be precise.
Meant to be something that assists the court in getting a feeling of a general
level, and was very much a check method as a check to the before and
after. Now, the department’s case is quite different. This is the preferred
method. This is the one that they urge upon you. And they want to argue
the before and after shouldn’t be --- the preferred method.”24
[36] The appeals above did not include any challenge to any of the reports or the
methodology adopted by any of the expert witnesses (including, in particular, those
of the valuers, Mr Hamilton and Mr Brett) in their various reports.
[37] The appeal points which resulted in this remitter all related to the view I had taken
(or in some cases failed to take) of some expert evidence.
[38] The main failure, as articulated by the Court of Appeal, was my disinclination to
permit use of the actual traffic infrastructure contribution of $1,087,110. Permitting
that figure to be utilised resulted in the fresh reports of Mr Brett and Mr Hamilton’s
response to the Court of Appeal remitter (which effectively disposed of the Land
Appeal Court’s decision in respect of appeal ground one).
The traffic engineering evidence
24 T 1-17, line 11 to T 1-18, line 21.
-- 11 of 42 --
12
[39] Mr Viney, who gave evidence at the original hearing, was called by the respondent.
[40] The Court had before it Mr Viney’s report of 4 November 2015.
[41] Mr Viney is a highly experienced traffic engineer well known to this Court, and has
been involved with the subject land since the mid to late 1990s.
[42] In his report he says: “the resolution of the TIC for this development has been the
most difficult and longest running dispute of its kind that I have been involved in.”
25
[43] He was critical of the respondent’s position saying:
“The respondent’s position seemed, from my perspective, driven more by
an apparent desire to obtain a large contribution from a party that it thought
it might be able to collect from rather than by a sensible and principled
traffic engineering basis.”26
[44] It is beyond dispute, and the matter frankly acknowledged by most of the witnesses,
that at all times up to the point at which a traffic infrastructure contribution of just in
excess of $1,000,000 (actually $1,087,110) was agreed, there was a high degree of
antagonism and antipathy between the applicant and DTMR.
[45] It is clear to me from the evidence that that antagonism and antipathy unnecessarily
extended the period of time taken to reach agreement about the appropriate
contribution for traffic infrastructure.
[46] It is clear on the evidence that there was a degree of suspicion by each side about
the motives and bona fides of the other.
[47] In his affidavit placed before the Court, Mr Viney gives a detailed outline of all of
the various steps that were taken regarding traffic engineering planning in respect of
the subject site, including steps that were taken to finally resolve the total amount of
the Transport Infrastructure Contribution (“TIC”).
[48] The evidence-in-chief and cross-examination of both Mr Viney and Mr Beard (to
whose evidence I will come shortly) focused on all of the various steps that were
taken by the various traffic consultants engaged with the project to try and get
agreement as to the appropriate TIC.
25 Ex R11, page 2, para 5.
26 Ex R11, para 8.
-- 12 of 42 --
13
[49] A careful reading of all of the evidence and the material contained within the reports
leads me to the conclusion that fault lay on both sides.
[50] As the respondent sets out in its supplementary submissions:
“Cidneo contends that the Land Court ought to take into consideration the
actual time taken by Metroplex between the lodging of its development
application for the western component of its proposed development in
November 2009 and the date of the agreement with DTMR about the TIC
on 6 December 2011 in the after resumption cash flows.” 27
[51] Unsurprisingly, the respondent objects to Metroplex being able to rely upon the
totality of the time and costs expended to achieve a reduction in the TIC.
[52] The evidence of Mr Viney, notwithstanding Mr Gore’s proposition put to him that
he had a fixation in relation to this subject development that DTMR had been trying
to “rip Cidneo off” provides, to me, some useful insights into the various fractures
or impediments to the ultimate decision of agreement being reached.
[53] The achievement of agreement with respect to the TIC had direct relevance to the
question of timing of works and staging of the ultimate development.
[54] For the respondent, the submissions contend that at least two of the factors which
impacted upon the timing of the development related to traffic matters.
[55] Those two factors were:
“(a) the standard of traffic material that supported the application and
was provided to DTMR during the assessment and negotiations
between Metroplex and DTMR (“the standard of material
factor”); and
(b) any unnecessary delays and the actual time taken between the
lodging of the development application and agreement with
DTMR (“the unnecessary delays factor”).”28
[56] The applicant, for its part, points to the following matters:
1. Timing of communications from DTMR, including the need to respond to an
information request issued on 31 March 2010;29
2. The information request on 31 March 2010;30
3. The slow response by DTMR in providing a concurrence agency response in
September 2010;31
4. Demands by DTMR expressed in a briefing note in September 201032
indicating or suggesting an inclination to seek contributions from the
27 Ex R39, para 20.
28 Ex R39, paras 27(a) and (b).
29 Ex R12, pages 23 to 25.
30 Ibid.
31 Ex R14, page 469.
-- 13 of 42 --
14
developer for their proportion of traffic on the planned upgrade to the
progress road and Ipswich Motorway exchange;
5. An appeal to the Planning and Environment Court by the applicant’s
associated company against the conditions of approval including the DTMR
concurrence agency condition.33
[57] All of those apparent delays and disruptions were, in my view, at least in part
caused by the belligerence that existed between the parties and were not indicative
of a timeframe that would be contemplated by the traditional hypothetical purchaser
and vendor.
[58] My view as to the blame for the time taken being visited on both parties being
somewhat out of the ordinary is confirmed by a reading of the report prepared in
December 2015 by Mr Beard.
[59] In the same way as Mr Viney was critical of the respondent’s conduct in the
negotiations for the transport infrastructure contribution, so is Mr Beard extremely
critical of the conduct of the applicant, and, in particular, critical of the quality of
the traffic engineering data and the analysis provided by the applicant to DTMR.
[60] In his report, Mr Beard observed as follows:
“This report does identify some significant impacts of generated traffic on
the State-controlled road network. However, directly contrary to the
Traffic Impact Information Request, it provides no recommendations on
works which might be considered necessary to ameliorate the impacts of
the generated traffic. Instead, on page 7 it simply states “as the land is
designated for industry uses and road safety is not compromised, the
application should be approved.”
That is, in terms of the four basic steps expected to be included in a traffic
impact assessment report (see paragraph 21), this report dealt with the first
step, partially dealt with the second step, but made no attempt to provide
information in respect of the third and fourth steps. Despite the very clear
guidance provided by the DTMR letter of 31st March 2010, this traffic
report submitted by the applicant was essentially still arguing that the
impacts of their traffic generations were not their responsibility.
Information relating to the third and fourth steps (necessary road network
upgrading) was not submitted until early December 2010, six months after
this report of May 2010.
In my opinion, the identification of the impacts of the proposed
development and the identification of works which would ameliorate those
impacts was never particularly complex. All of the information required
for a traffic impact assessment dealing with all relevant impacts was
32 Ex R17, pages 309 to 311.
33 Ex R14, para 171.
-- 14 of 42 --
15
available from mid-2010. From that time, there were no traffic engineering
issues which necessitated significant delays in the approval process.” 34
[61] In my view, there is no proper basis for regarding the period of time taken between
the applicant and the respondent to reach agreement on traffic infrastructure
contribution matters as indicative of what the prospective purchaser and prospective
vendor may have done in a Spencer-type situation.
[62] I am more comforted by the evidence of Mr Viney about the likely time that might
be taken to reach agreement.
[63] In his submissions, Mr Hinson says:
“now, there is a good deal of criticism in the respondent’s submissions
directed towards Metroflex saying “well, look, you sat on your hands. If
you’re acting reasonably, you could have done this.” It takes two people to
make an agreement and all I’m simply trying to identify is that on the
Department’s side there was an attitude, to, which was not necessarily
receptive to a meeting of the minds. Now a resolution did occur. It
occurred on the eve of the commencement of the appeal for the western
application.”35
The valuation evidence
[64] Consequent upon each of the appeals above, each of the parties to this matter
engaged their respective valuers to prepare supplementary reports.
[65] For the applicant, Mr Hamilton produced a report dated 4 November 201536 and a
second addendum report dated 3 February 2016.37
[66] For the respondent, Mr Brett produced a supplementary valuation report dated 23
November 2011, and what it described as an addendum report dated 3 December
2015 following the Land Appeal Court decision.38
[67] A starting point from the outset was that the valuers agreed, on the basis of what
they described as comparable en-globo sales, that the value of the land in the before
case was $60,877,800, which was based on a value of $60 per square metre of land
area.39
34 Ex R12, page 6, paras 30 to 33.
35 T 4-37, line 19.
36 Ex R5.
37 Ex R6.
38 Ex R10.
39 Ex 29, page 55; Ex 30, pages 16, 18 and 23; Ex 71, page 5 and T 3-46, lines 32 to 33.
-- 15 of 42 --
16
[68] That valuation was not the subject of any of the appeals above.
[69] For this appeal, Mr Brett has revisited the cash flow figures in the before case
contained in his December 2015 report.
[70] I cannot glean from the decisions of either the Land Appeal Court or the Court of
Appeal any basis upon which he is entitled to do this in respect of the before case.
[71] The applicant in their submissions say as follows:40
“The before value was an input to the before cash flow to derive an IRR
which was then used as an input to the after cash flow to derive the after
value. Mr Brett’s before cash flow in Ex 61 produced an IRR after interest
of 8.65% which was then input to his after cash flow.
Mr Brett revisits the before cash flow in his December 2015 report. That is
outside the scope of either remitter order. Ground 3 of the appeal to the
Land Appeal Court was solely concerned with the construction staging
period in the after case not the before case. The appeal to the Court of
Appeal related to the TIC in the after case, not the before case. The before
case was and remains hypothetical. No development application was made
for the before case highest and best use. The TIC was not agreed by
reference to the facts of the before case. The Land Court has determined
that the before TIC would
be $3 million and there is no reason to change that figure.
There is no basis to revisit the before cash flow by substituting $1.087
million for $3 million as the TIC. As Mr Brett acknowledged in his March
2012 report, the before TIC would not be less than the after TIC and would
likely be higher. That is the effect of Mr Beard’s evidence also.”41
[72] The remitter clearly permits the contemplation of the actual figure of the TIC, but
nowhere can I read into the reasons of either Court above a warrant for changing the
methodology that was used by either party.
[73] In his written submissions at the conclusion of the remitted hearing, Mr Gore
characterised the positon as follows:
“The basic issue remains – what is the impact of the decision of the Court
of Appeal on the assessment of compensation of $6,900,000 by this Court.
The specific sub-issues also remain as:
The Stage three issue
The Time and Cost issues
The Ground 2 issue
The Piecemeal issue
The Proper assessment of compensation.”42
40 Ex 38, paras 10 to 12.
41 See T 3-13 line 25; T 3-25 line 41 to T 3-26 line 15 and Ex R12, para 37. See also Cidneo Pty Ltd v
Chief Executive, Department of Transport and Main Roads [2013] QLC 47 at [215].
42 Ex 39, para 3.
-- 16 of 42 --
17
[74] With respect to those issues, a number of matters emerged from the opening
submissions filed by the parties on the remitter. The applicant identified its primary
case in the following terms:
“Cidneo’s primary case (Mr Hamilton’s Cash Flow 1) is that Mr Brett’s
cash flow should be adjusted in four respects:
“the TIC is reduced from $3,000,000 to $1.087 million;
the preconstruction phase is increased from 12 months to 24
months;
the cost of negotiating the TIC agreement is substituted for the
cost of a traffic network analysis;
construction of stage 3 commences at month 41 instead of eight
months earlier.” 43
[75] The reduction in TIC to $1.087 million is not contentious as between the parties,
and accordingly it becomes unnecessary to consider Mr Hamilton’s Cash Flows 3
and 5 in his 2016 report44 in that regard.
[76] Similarly, with respect to Mr Hamilton’s 2016 report, the applicant informs the
Court that “with a view to minimising the area of dispute and the issues to be
determined Cidneo will not pursue the sales rate issue. Mr Hamilton’s February
2016 Cash Flows adopt a sales rate of two sales per calendar month for Stage 3.”45
[77] As Mr Hinson informed the Court during his opening:
“To the rate of sales, and as I said, that’s now disappeared because in the
cash flows that Mr Hamilton has done, he said, look, let’s not have that
argument, I’ll just adopt Mr Brett’s rate of sales. I’ll try and keep them
simple. So that’s fallen by the wayside.”46
[78] In that regard, the Land Appeal Court in respect of ground 3 then before it said:
“These conclusions provide a sufficient basis on which to uphold the
appeal on Ground 3. It should, however, be said that there must be a real
doubt about the validity of Mr Brett’s approach to the rate of sales. As has
been mentioned, he proceeded on the basis that the speculative market of
2007 would continue, notwithstanding the increases in interest rates up to
February 2008, and the increased difficulty in obtaining finance.
Particularly against that background, there is a very real question whether
the hypothetical prudent vendor and purchaser would assume the
continuation of a speculative market for a further period approaching four
years. If Mr Brett’s rate of sales were not adopted, this could well have
implications for the assumed construction program. With slower sales, a
developer might be more inclined to delay construction for Stage 3 to
reduce its risks and its interest of liabilities.”47
43 Ex R24, page 3, para 14.
44 Ex R6.
45 Ex R24, page 4, para 26.
46 T 1-20 lines 22 to 26.
47 Cidneo Pty Ltd v Chief Executive, Department of Transport and Main Roads [2014] QLAC 3 at [88].
-- 17 of 42 --
18
[79] That apparent concession does arguably relieve me of the duty to give adequate
reasons as to why I accepted Mr Brett’s approach to the rate of sales since it is now
not contentious.
[80] In his opening submissions, Mr Hinson also told the Court:
“can I just mention, in that regard, to-Ground 2 of the Appeal to the Land
Appeal Court – your Honour may have seen, from the written submissions,
concerned this extra six months in the after case for traffic analysis. That’s
now disappeared and been subsumed in the issue canvassed in Mr
Hamilton’s supplementary March 2012 report about whether one needs to
take into account if one can have regard to a subsequent event, that being
the agreement about the amount of transport infrastructure contribution in
the after case – whether one can also have regard to the time and cost taken
in achieving that outcome in making the assessment of compensation, and
as I indicated earlier, paragraph 32 of the respondent’s submissions on the
remitted hearing, exhibit R26, appears to accept that the scope of the
remitter includes the approaches taken by Mr Brett and Mr Hamilton in
their supplementary reports.”48
[81] In his most recent report, Mr Brett explains why, in essence, he has changed courses
and now wants just to rely upon a piecemeal approach dependent on cash flow
analysis.49
[82] He says:
“Providing the before and after returns are consistent it is appropriate to
determine the compensable loss (apart from disturbance matters) by the
piecemeal addition of the per hectare value of the resumed land plus the per
hectare impacts on the retained land of the components identified in
paragraphs 2.6.1, 2.6.2 and 2.6.3 above. This is the basis of my assessment
on pages 25 and 26 of my valuation report dated 17 November 2011.
From the Court of Appeal decision it is clear that post-resumption events
impacting on the value of the retained land may be brought to account. On
this occasion post resumption changes have occurred, at least in respect of
identification of the TIC cost. In these circumstances the summation of the
value of the resumed land and of the value of injurious affects on the
retained land is my preferred method.”50
[83] The reference in paragraph 2.12 to Mr Brett’s valuation report dated 17 November
2011 (actually 15 November 2011) reveals that he did not in fact rely upon this
piecemeal approach as his basic valuation exercise. 51 Rather, it was contained in
the report as a “check valuation” and disposed of in one and a half pages.
48 T 1-20, lines 25 to 37.
49 Ex R10, page 5, paras 2.12 to 2.13.
50 Ex R10, page 5, para 2.12.
51 Ex R7.
-- 18 of 42 --
19
[84] I can see nothing in the Court of Appeal decision which entitles Mr Brett to do other
than to incorporate the actual TIC figures into his report and not to create a whole
new methodology for expressing his views.
[85] When questioned by Mr Hinson as to why he now contends that it is preferable to
do a piecemeal assessment rather than a before and after cash flow analysis, Mr
Brett responded as follows:
“I don’t mind the cash flow. It’s a reverse of what I’ve spoken of in the
past. The cash flow’s there certainly to quantify those holding charges.
The cash flow’s there to see what comes of the cash flow and if it differs
from the piecemeal, you need to reconcile the two and see which you prefer
to go with. But on this occasion, what triggers it really is the Court of
Appeal’s decision as a – something of a reminder to be somewhat more
flexible in these matters, not being wedded to the before and after approach
for the last 40 years and then treat something else as some kind of check
method. I revisit this one and there’s a good deal of clarity that can be
obtained from the piecemeal method in respect of the quantification of the
value of the resumed land and the quantification of the injurious effects or,
if there was, enhancement on the retained land.” 52
[86] His previous apparent disdain for that approach is apparent from a subsequent
answer given by him where he said:
“The use of the subsequent information made me realise that you can’t
close your mind to the piecemeal method. Here’s an occasion where, if
events have happened after the acquisition, you need to then revisit the
exercise to substitute those costs to bring those to account and that got me
thinking in respect of the means by which you could reasonably quantify
the components of the piecemeal method. Sot it was a reminder rather than
some dramatic event.”
[87] Notwithstanding his strident support for the piecemeal assessment as the preferred
approach, Mr Brett acknowledged in cross-examination that he could not recall a
case where he had used a piecemeal assessment as his preferred method of
assessment of compensation.53
[88] Prior to that concession by Mr Brett, he had confirmed to Mr Hinson that, in respect
of the before and after cash flow methodology, which involves putting material into
the cash flow, amongst the things to go into that cash flow were:
1. The development yield;
2. Construction costs; and
3. Construction periods.
52 T 3-41, lines 23 to 34.
53 T 3-44, line 37.
-- 19 of 42 --
20
All of which matters were subject of agreement between him and Mr Hamilton.54
[89] Mr Brett agreed with the proposition put to him by Mr Hinson in cross-examination
that by comparison with a lot of other cases there are far fewer uncertainties
involved in doing a cash flow analysis in this case, but he added that “those
outstanding uncertainties can have a big impact on the conclusion reached.”55
[90] One of those uncertainties had been taken out of the equation because in Mr
Hamilton’s February 2016 report,56 he had adopted the sales rates contended for by
Mr Brett.57
[91] There remained differences between Mr Brett and Mr Hamilton about when stage
three construction should start, and whether the appropriate period was a 12 month
period or a 24 month period.
[92] The following passage of cross-examination, to my mind, subsequently summarises
the position exclusive of Mr Brett’s inclination to use a piecemeal approach:
“And on the approach that you and Mr Hamilton took in this case you said
that a before and after cash flow analysis was the appropriate way to go
because – and the appropriate way to deal with that was to put yourself in
the position of the hypothetical prudent purchase as at the date of
resumption, February 2008 --- Correct.
All right. And on that basis you and Mr Hamilton received different advice
from traffic engineers about what an input into the cashflow, a transport
infrastructure contribution, would be? --- Yes, yes.
Yes? --- Sorry.
And now each of you are putting in a different figure, 1.087 million ---? ---
Yes.
--- at least in the after case. That’s common to both of you? --- Correct.
And Mr Hamilton doesn’t revisit the before case and I’ll come to that
shortly? --- Yes.
But you use the same figure in the before case? --- I do.”58
[93] Following that, Mr Brett conceded the fact that he put in a different input figure for
the transport infrastructure contribution based upon a subsequent event, as opposed
54 T 3-42, lines 20 to 38.
55 T 3-43, lines 15-16.
56 Ex R6.
57 T 3-43 line 21.
58 T 3-45, lines 26 to 44.
-- 20 of 42 --
21
to a figure based upon foresight at the time of resumption, did not mean that the
before and after cash flow analysis method ceased to be an appropriate method.59
[94] Mr Brett conceded that those propositions did not drive the decision about whether
to use the piecemeal or the cash flow approach.
[95] Invited to explain why he chose a piecemeal approach rather than a before and after
cash flow analysis for the current remitted hearing Mr Brett told us as follows:
“Well, it’s what I touched on before, the reminder from the Court of
Appeal’s decision that there are the occasions where it’s appropriate to look
at the piecemeal because a subsequent event might affect the value, but that
was only a trigger to – as a reminder that you do not need to look at both
the piecemeal and the cash flow, so I look at the piecemeal and the cash
flow, and then re-looking at the piecemeal approach it seems to me there is
considerable transparency and considerable ability to quantify each of the
relevant components and leave somewhat unclear and unexplained what
drives all of the issues in the uncertainty of the cash flow.”
[96] Mr Brett conceded that there was nothing in the Court of Appeal decision which
gave him comfort to revert to using the piecemeal approach.
[97] He also confirmed that he remained comfortable with the before figure for value of
$60 million (or more correctly, $60,877,800).
[98] By way of clarification, Mr Brett told Mr Hinson that he had worked on a $60
million figure but that if they were doing a current valuation exercise then they were
looking at a before figure of $60,877,800 then everything would come up by
$877,800.60
[99] Having regard to what transpired in the Land Appeal Court and in the Court of
Appeal I can find no basis for Mr Brett to now change his primary approach to a
piecemeal approach, and accordingly do not propose to rely upon that particular part
of his evidence in respect of the before case.
[100] I do, however, have the view that his approach is responsive to the observations of
Dalton J in the Court of Appeal.
[101] Her Honour said:
“A decision needs to be made as to the matters raised by Mr Hamilton in
his March 2012 report. Quite apart from that, the matters decided by the
59 T 3-45, line 46 to T 3-46 line 3.
60 T 3-48, line 21.
-- 21 of 42 --
22
Land Appeal Court as to appeal ground 2 and appeal ground 3 are not
resolved by an agreement as to the amount of TIC. They need to be
determined by the Land Court. As well, it seems to me that the valuers will
need to revisit their evidence, and that the parties will need to spend some
time ensuring that the evidence which is presented to the Land Court is
coherent and in a framework consistent with s 20 of the Act.”61
[102] I am satisfied that both Mr Hamilton and Mr Brett have attempted to do that in
respect of the after case.
[103] The before case was not the subject of any appeal point, and I do not propose to
revisit it. Nothing in the Land Appeal Court decision nor in the Court of Appeal
decision suggests I should do so.
[104] Mr Hinson’s final submissions on behalf of the applicant set out how that before
case was calculated and it is unnecessary to recite everything that he says here.62
[105] Mr Brett’s report of December 2015 seems to anticipate the objections taken against
him. 63 He says:
“My approach and valuation are unchanged from the Alternative (b) check
valuation on page 5 of my March 2012 Further Supplementary Report.
These proceed on the basis of a 12 month approval period and a $100,000
traffic network study both before and after the resumption. It excludes Mr
Hamilton’s 8 month delay in the release of stage 3. The approach
separately quantifies the value of the resumed land and that of the various
injurious affects calculated as:
Injurious affect $1,530,405
Value of resumed land $4,533,954
Total $6,064.359
Rounded to $6,100,000” 64
[106] Mr Brett’s December 2015 report was prepared after the Court of Appeal made its
decision. It addressed the incorporation of the traffic infrastructure charge of
$1,087,110.
[107] Mr Brett’s December 2015 report moves away from the approach he adopted
earlier. He explains his use of the piecemeal approach this way:
“2.5 Before and after cash flow exercises are necessary on this
occasion because the direct comparison approach is not
sufficiently sensitive to quantify the resumptions impacts on the
retained land. The size and nature of this property, with its
potential for industrial subdivision, means comparison with prices
61 Chief Executive, Department of Transport and Main Roads v Cidneo Pty Ltd [2015] QCA 96 at
[87].
62 Ex R38, page 2, paras 8-12.
63 Ex R10.
64 Ibid, page 8, para 5.1.
-- 22 of 42 --
23
paid elsewhere cannot account for all variables relevant to each
site’s development characteristics and costs. Adverse impacts on
the retained land are best brought to account by accommodating
each within the post resumption cash flow.
2.6 For this property the resumption’s affects on the retained land,
best
expressed as a rate per hectare of developable land, are:
2.6.1 lower net realisations from allotment sales
2.6.2 high development costs, including holding costs (council rates
and government land tax), over the life of the project, and
2.6.3 lower interest costs over the life of the project.” 65
[108] True it is to say, however, that he did use a piecemeal cash flow approach by way of
a check valuation.66
[109] In his supplementary report of 23 November 2011,67 he amended that report to
reflect the calculation of goods and services tax and both the before and after cash
flows and to accommodate a 40-metre tree retention and rehabilitation buffer.68
[110] In his yet further supplementary report,69 he then incorporated the figure of
$1,087,110 and produced calculations in the before and after utilising the
$1,087,110 figure.
[111] In that report of 14 March 2012, he calculated the loss in value as $6,377,800.70
[112] To some extent, Mr Brett’s approach in March 2012 was prophetic of the decision
of the Court of Appeal.
[113] In the March 2012 report, Mr Brett adopted two different approaches with respect to
the before situation.
[114] The first alternative was to contemplate a pre-resumption contribution of $2 million
and a post resumption contribution of $1,087,110.71
65 Ibid, page 4, paras 2.5. to 2.6.3.
66 Ex R7, page 19.
67 Ex R8.
68 Ibid, page 2.
69 Ex R9.
70 Ibid, page 5.
71 Ibid, page 3.
-- 23 of 42 --
24
[115] The second alternative embraced by him was to contemplate the contribution of
$1,087,110 in both the pre- and post-resumption situations.
[116] The utilisation of the $2 million contribution was premised upon estimated figures
for a pre-resumption contribution to both the Progress Road intersection and the
Centenary Highway intersection.
[117] The first alternative presented by Mr Brett resulted in the loss being quantified as
$5,400,000 based upon the check valuation approach, and $5,877,800 based upon
the cash flow approach.
[118] Pursuant to the second alternative approach, that resulted in quantification of the
loss based upon the check valuation in his report of $6,100,000 and a loss of
$6,377,800 if reliance is placed upon the cash flow approach.72
[119] In his report of 3 December 201573 Mr Brett prepared four cash flows each of which
adopted a 24-month approval period both pre- and post-resumption but which
excluded the eight-month stage 3 delay. (That being the delay contended for by Mr
Hamilton). Those four alternative cash flows produce the following values in each
case:74
A table summarising these values follows. The cash flows are contained in
Attachments One to Four of this report.
BRETT MARCH 2012 REPORT
(Based on 12 month approval period and
$100,000 traffic network analysis)
Land Value
IRR
Before Resumption $60,877,800
9.12%
After Resumption $54,500,000
9.03%
Difference $ 6,377,800
Piecemeal assessment $ 6,064,359
CASHFLOW 1
(Based on the $60,000,000 pre-resumption value,
24 month approval period and
$100,000 traffic network analysis)
Land Value
72 Ibid, page 5.
73 Ex R10.
74 Ibid, page 7.
-- 24 of 42 --
25
IRR
Before Resumption $60,000,000
5.97%
After Resumption $53,000,000
5.98%
Difference $ 7,000,000
Piecemeal assessment $ 5,071,766
CASH FLOW 2
(Based on the $60,000,000 pre-resumption value,
24 month approval period and
$241,236 litigation cost)
Land Value
IRR
Before Resumption $60,000,000
5.92%
After Resumption $53,000,000
5.93%
Difference $ 7,000,000
Piecemeal assessment $ 5,074,345
CASH FLOW 3
(Based on a pre-resumption return of about 9.04%,
24 month approval period and
$100,000 traffic network analysis)
Land Value
IRR
Before Resumption $52,350,000
9.06%
After Resumption $46,500,000
9.05%
Difference $ 5,850,000
CASH FLOW 4
(Based on a pre-resumption return of about 9.04%,
24 month approval period and
$241,236 litigation cost)
Land Value
IRR
Before Resumption $52,275,000
9.04%
After Resumption $46,425,000
9.04%
Difference $ 5,850,000
The traffic engineering evidence
[120] In his closing submissions Mr Gore said:
“and it’s really, at bottom, your Honour’s acceptance of the Department’s
case that in terms of traffic impacts there was no material difference
-- 25 of 42 --
26
between the before and after case. There was significant impacts in the
before case there was significant impacts in the after case, and your Honour
accepted that in the result, the amount of time taken in the before-case to
obtain the relevant preconstruction approvals would be the same as in the
after case, and that, in effect, in both cases there would be a need for a
traffic study, which was the thrust of Mr Beard’s evidence.” 75
[121] For the remitted hearing, Mr Hamilton prepared a report dated 3 February 2016.76
[122] In explaining the genesis of his report he wrote:
“… I have been instructed to prepare post resumption cash flows adopting
adjustments to Mr Brett’s after resumption cash flow contained in his
supplementary report dated 23 November 2011. The purpose of this report
is to:
(1) Provide an after resumption cash flow that takes into account a
correction to Peter McGregor’s evidence as to the cost of the litigation
required to resolve the TIC;
(2) Provide the Court of post resumption cash flows that take into account
possible alternative findings which it might make if my assessment is
not preferred or is preferred only in part;
(3) Provide a reply to Mr Brett’s addendum report dated 3 December
2015.”
[123] In his report, Mr Hamilton presents three alternative cash flows (cash flow 3, 4 and
5) which adopt a traffic infrastructure charge of $3,000,000.77
[124] In light of the Court of Appeal findings with respect to the TIC charge, I do not
propose to consider those cash flows where Mr Hamilton has ignored the apparent
preference of the Court of Appeal for the $1,087,110 TIC, and sought comfort in the
$3,000,000 figure opined by him.
[125] Both cash flows 1 and 2 adopted an internal rate of return of 8.68 percent and
applied a cost to litigate the TIC of $214,497 as per Mr McGregor’s 4 February
2016 affidavit.78
[126] As to that $214,497 figure, in her cross-examination of Mr McGregor, about the
figures advanced by him in his affidavits Ms Brien was able to elicit from Mr
McGregor numerous concessions that the figures which she had used were, to
express it colloquially, “a little rubbery.”
75 T 4-9, lines 1 to 10.
76 Ex R6.
77 Ex R6, pages 4 to 7.
78 Ex R16.
-- 26 of 42 --
27
[127] There were really two important aspects of her cross-examination which lead me to
the view that the figure of $241,236 contended for as the actual cost incurred by
Cidneo in achieving resolution of the TIC issue are unreliable.
[128] The first of those is the amount claimed by Mr McGregor in his role as a consultant
and town planner, as opposed to his assertion in his evidence that he stood in the
shoes of the developer because Mr Pradella had lived overseas for some years.79
[129] The claim by Mr McGregor was a figure of just over $80,000. It was the biggest
single figure in the calculation.
[130] In their submissions to the Court, the respondent asserted as follows:
“The hypothetical exercise necessitated by the resumption does not assume
that the hypothetical prudent purchaser is an overseas resident. Rather, it
assumes that the hypothetical prudent purchaser is a “johnny-on-the-spot”
– who would not factor into his costs in the cash analysis some costs
referable to a consultant engaged by an overseas purchaser. All of Mr
McGregor’s claimed amount of $80,000 fails on this ground alone.”80
[131] In aid of that proposition, the respondent refers to a line of authority in Queensland
to the effect that costs attributable to the time spent by an owner in preparing a
compensation claim are not recoverable.81
[132] The second ground upon which the respondent challenges the figures contended for
in Mr McGregor’s affidavit is his inability to justify some of the amounts, and the
frequent response that he either “did not know, had no idea, had made a complete
guess, did not understand what had happened here, and I don’t maintain it” were
unconvincing.82
[133] The respondent also points to the applicant’s final submissions. The applicant
submitted the schedule of deductions which had been conceded by Mr McGregor in
cross-examination totalled $36,600.83.83
79 T 1-90, lines 22 to 36.
80 Ex R39, page 22, para 77.
81 Ex R39, page 2,2 para 78. See Heavey Lex No 64 Pty Ltd v Chief Executive, Department of
Transport [1999] QLC 133 at [451] to [453]; Heavey Lex No 64 Pty Ltd v Chief Executive,
Department of Transport (2001) 22 QLCR 177 at [184].
82 T 1-44 to T 1-64.
83 Ex R38.
-- 27 of 42 --
28
[134] It is unnecessary to identify those items acknowledged by the applicant individually,
but most of them relate to work that was unrelated to the subject claim or
constituted doubling up.
[135] That concession by the respondent would reduce the amount claimed from $214,497
to $177,400.
[136] As to the claim by Mr McGregor for a figure of just over $80,000 for his
consultancy work, I am of the view that there is merit in the respondent’s
submissions. Mr McGregor’s evidence was to the effect that he effectively became
the alter ego of the developer, Mr Pradella, who lived overseas. There was, to my
recollection, no evidence at all of any involvement by Mr Pradella as the principal,
and while Mr McGregor was paid for his efforts, a lot of what he was doing was
clearly work that Mr Pradella would otherwise have done himself and for which, in
my view, he is not entitled to claim.
[137] If one was to take a strict view of the documentary evidence advanced to support the
$214,000 claim, much of it would fall by the wayside because of the lack of
specificity for detail in the documentation. Clearly, some figure has to be allowed
for the negotiation efforts which achieve the reduction in the TIC.
[138] The respondent also points to the absence of any documentary support for the
figures contended for by Mr McGregor,84 and Mr McGregor’s concession in
response to a question from me that even if the Department had not sought any
contribution, many of the invoices would relate to work that would have inevitably
have to have been done in any event.85
[139] To some extent, concerns about the precision of Mr McGregor’s evidence are
mitigated by the evidence given by Mr Hamilton as to what the effect would be on
his modelling exercise if the TIC was, for example, reduced from $214,000 to say
$100,000.86
[140] When asked to assume that reduction from $214,000 to $100,000 Mr Hamilton said:
“Because the cost is up at the beginning of the cash flow, it will have an
impact, but because the project takes over many many years it’s not the
84 T 1-68, lines 36 to 40.
85 T 1-81, lines 12 to 18.
86 T 2-45, lines 1 to 10
-- 28 of 42 --
29
case where you deduct $100,000 or $200,000 from the actual land value.
So if you reduce that TIC contribution from $214,000 to $100,000, all other
matters remain the same, the value would increase, but not to the same
extent as the $100,000.”87
[141] While Mr Hamilton was unable to give an accurate answer off the top of his head,
he did inform the Court that the increase in the value would be less than the
$114,000 difference between the two figures. 88 Doing the best I can with the
evidence that was before me, and putting aside some serious doubts about the lack
of substantiation of some of the claims, I think it would be fair to allow a figure of
$100,000 for those negotiations in lieu of the $214,000 claim.
[142] I observe that a $100,000 reduction in a value of $67 million dollars represents less
than one percent (by my calculation, 0.149 percent).
[143] In his most recent report Mr Hamilton assessed:
“I consider that Mr Brett’s cash flow four – after resumption most closely
reflects the actual after resumption scenario. His after resumption
valuation is $46,425,000.
Mr Brett’s after resumption valuation of $46,425,000 is relatively similar to
my after resumption valuation of $45,750,000 based on a delay of 24
months. The difference in value would reflect what I consider an error in
Mr Brett’s valuation in that he commenced construction of Stage 3 well
before it would have been prudent to do so.” 89
[144] Based on the agreed pre-resumption valuation of $60 million and Mr Brett’s cash
flow 4 after resumption valuation of $46,425,000, the compensation payable would
be $13,575,000.
[145] That cash flow 4 calculation of Mr Brett’s, it should be noted, includes an
infrastructure charges item of $1,087,000, and a cost of litigation to reduce the
DTMR contribution of $241,236.90
[146] Mr Hamilton attributes the difference in Mr Brett’s valuation to what he described
as an error insofar as Mr Hamilton contends that Mr Brett commenced construction
of stage three before it would have been prudent to do so, and that constitutes the
overlapping construction period which is a point of difference between Mr
Hamilton and Mr Brett.
87 T 2-45, lines 4 to 9.
88 T 2-45.
89 Ex R6, page 13.
90 Ex R10, attachment 4, page 43.
-- 29 of 42 --
30
[147] In his February 2016 report Mr Hamilton explains his approach this way:
“In my 4 November 2015 Addendum report I adopted Mr Brett’s post-
resumption cash flow with a number of amendments. These amendments
were included in the cash flow in order to take into consideration comments
within the judgement of the Court of Appeal. These included:
Delay of 8 months for commencement of construction of Stage 3
after completion of Stage 2 – See the Land Appeal Court Judgement
at [83].
Pre-construction approval period of 24 months.
Provision of $241,236 for the cost of litigation to reduce DTMR
contributions.
Removal of the traffic network analysis cost of $100,000.
In order for my post-resumption cash flow, which was based on Mr Brett’s
post resumption cash flow to reflect the same level of return that Mr Brett
had selected, it was necessary for my cash flow to deliver an IRR of
approximately 8.68%.”91
[148] Mr Hamilton agrees that the $60 million value should remain as the pre-resumption
land value, but disagrees that that figure of $60 million should be the primary
determinant of the value of the land resumed.92
[149] Mr Hamilton states:
“what is required in my opinion to fairly assess compensation in this case is
to assess the value of the property before resumption and the value of the
land after resumption. The difference between the two figures reflects not
only the land taken but severance, injurious affection and enhancement.
The exercise undertaken by Mr Brett does not satisfy this approach.”
[150] In making that observation, it might be inferred that he was influenced by the
observations of Dalton J in the Court of Appeal decision where her Honour
observed:
“… the matters decided by the Land Appeal Court as to appeal ground 2
and appeal ground 3 are not resolved by an agreement as to the amount of
TIC. They need to be determined by the Land Court. As well, it seems to
me that the valuers will need to revisit their evidence, and that the parties
will need to spend some time ensuring that the evidence which is presented
to the Land Court is coherent and in a framework consistent with s 20 of
the Act.”93
[151] Accepting as Mr Hinson said, by Mr Hamilton adopting Mr Brett’s rates of sales,
ground of appeal 2 has evaporated but there still remains to be considered ground of
91 Ex R6, page 8, paras 1.4 to 1.5.
92 Ex R6, page 9, para 2.3
93 Chief Executive, Department of Transport and Main Roads v Cidneo Pty Ltd [2015] QCA 96 at [87].
-- 30 of 42 --
31
appeal 3, which dealt with the eight month delay for the commencement of
construction of stage 3 after completion of stage 2.
[152] In my original decision I accepted the view taken by Mr Brett.
[153] The Land Appeal Court loosely pointed out that it appeared I had not properly
contemplated the evidence given by Mr Whitelaw, a chartered accountant
specialising in property development finance.
[154] Mr Whitelaw’s evidence based upon the Gantt chart prepared by him was to the
effect that the early commencement of stage 3 assumed by Mr Brett was
uncommercial and not the action of a prudent developer.
[155] In his affidavit tendered before the Land Appeal Court, Mr Hamilton expressed the
following:
“Mr Brett and Mr Hamilton differ in their ‘before’ and ‘after’ construction
timeframes by a total of 21 months.
Mr Brett opines the construction timeframe in the ‘after’ will be completed
10 months earlier than the ‘before’ development (47 months in the ‘before’
including gaps between stages and 37 in the ‘after’). Mr Hamilton opines
the construction timeframe in the ‘after’ will be completed 5 months later
than the ‘before’ development (43 months in the ‘before’ including gaps
between stages and 48 months in the ‘after’).
Mr Hamilton also takes the view that the commencement of construction
will be delayed by 6 months as a result of the severance and injurious
affection in the after case.
Apart from the six month delay, the main differences between Mr Brett and
Mr Hamilton are –
Mr Brett starts Stage 4 one month later
than Mr Hamilton in the ‘before’
1 month
Mr Brett starts Stage 1 three months later
than Mr Hamilton in the ‘before’
3 months
Mr Brett starts Stage 3 five months
earlier than Mr Hamilton in the ‘after’
5 months
Mr Brett starts Stage 4 six months earlier
than Mr Hamilton in the ‘after’
6 months
At Mr Hamilton’s request, I have prepared Gant charts illustrating the
staging of each valuer which are located at pages 1 and 2 of the bundle.
A prudent developer who relies on bank funding to undertake development
would, in my experience, usually only commence the next stage of a
construction once they had achieved sufficient pre-sales of the prior stage
and settlements of most lots in the stage prior to that.
-- 31 of 42 --
32
Page 5 of the bundle is entitled ‘Lots Sold and Settled before
commencement of next stage’ and shows that in the cash flow models
prepared by Mr Brett and Mr Hamilton there is one significant item which
does not meet these principles (highlighted) blue, namely Mr Brett’s model
whereby he suggests Stage 3 in the ‘after’ would commence so early that
there would probably be no pre-sales and certainly no settlements of Stage
1. In my opinion that is ‘unbankable’, uncommercial and not the action of
a prudent developer.
By the term ‘unbankable’ I mean that such a position would not be
acceptable, in my opinion, to a financier lending to fund the construction of
any given stage on generally accepted practices.
Based in my experience in property finance, I would concur with Mr
Hamilton’s view that construction of stage 3 in the ‘after’ case would
commence 5 months later than Mr Brett’s timing.
With any four stage land development, I would normally expect there to be
three peaks in stock on hand as construction of new stock is undertaken.
On occasions, I have seen developments with four peaks – this arises when
the second stage is not commenced prior to any settlements from the first
stage. In this case, both valuers have proceeded on the basis (in both the
‘before’ and ‘after’ case) that commencement of the second stage will
proceed prior to any settlements in the first stage.”94
[156] The “bundle” to which Mr Hamilton referred in that affidavit was a bundle of
documents attached to that affidavit and included a series of graphs comparing the
consequences of the staging contended for by each of the valuers.
[157] Those graphs show the peaks and the availability of land stock created by the land
developer coming on to the market. The graphs show that in the before case, each
of Mr Brett and Mr Hamilton had three peaks of stock of land.
[158] In the after case, Mr Hamilton’s proposed staging had three peaks whereas Mr Brett
had only two.
[159] Mr Hamilton relied upon that as demonstrating, in his opinion, “that Mr Brett’s
model brings on stock of land too early and is not the action of a prudent
developer.”
[160] Mr Whitelaw said, clearly having regard to cash flows being achieved form earlier
stages of development, said that Mr Brett’s “two peak” scenario was
disadvantageous for a number of reasons:95
94 Ex R36.
95 Ex R36, page 5, para 25.
-- 32 of 42 --
33
“(a) It would be difficult to attract finance to construct stage 3 while
no settlements have occurred in stages 1 and 2.
(b) If finance was obtained, the effect of this construction timetable is
that stock on hand levels are significantly higher than the level
held by a prudent developer and therefore interest costs would
also be significantly higher.
(c) Developers, in my experience, do not want to have an oversupply
of stock, particularly in a period of rising interest rates.
(d) By bringing on stage 3 without experiencing the results of stages
1 and 2 the developer loses the flexibility to alter lot sizes or
otherwise adapt the design to meet the market or changes in
market conditions.”
[161] In her decision in the Court of Appeal, Justice Dalton drew attention to the decision
in Mio Art:96
“The decision of this Court in Mio Art recognised that s 20 of the Act deals
with two separate elements of compensation: the value of the land taken,
and damage caused by severance, injurious affection and disturbance. The
decision recognised that the Act requires that the value of the land taken be
assessed as at the date of the acquisition. Further, that damage caused by
the other three matters will often be quantified by reference to post-
acquisition events – [51], [75].
Where the entirety of a land-owner’s lot is resumed, the only relevant
enquiry for the Court is the value of the land taken. However if part of a
land-owner’s lot is resumed, the Court may in addition need to enquire as
to: damage caused by severance, injurious affection, disturbance and
enhancement. In cases of the latter type, a short-hand method of assessing
compensation known as the ‘before and after method’ has been used
regularly. It is described by Spigelman CJ in Mir Bros Unit Constructions
Pty Ltd v Roads & Traffic Authority of New South Wales:
“… That method involves subtracting the market value of the
residue land (i.e. the part of the property that was not acquired
and remains the property of the Appellant) from the market value
of the entire property prior to acquisition.”” 97
[162] As was made clear in the cross-examination of Mr Whitelaw by Mr Gore, Mr
Whitelaw was by no means an entirely aloof witness. He is Director of Brescia
Investments, a registered shareholder in Cidneo.
[163] He is also a Director of Metroplex Management Pty Ltd, a company associated with
Mr Pradella and Cidneo.98
[164] Mr Whitelaw conceded that at the time of the stage 4 construction the “cash flow
would be in the black and the developer would be, in a sense, self-financing”.99
96 Brisbane City Council v Mio Art Pty Ltd [2011] QCA 234.
97 Chief Executive, Department of Transport and Main Roads v Cidneo Pty Ltd [2015] QCA 96 at [56]
and [57].
98 Initial Land Court hearing transcript, T 7-64, lines 20 to 45.
-- 33 of 42 --
34
Those concessions by Mr Whitelaw effectively, to my satisfaction, dispose of any
reservations about the start of construction of stage 3 because on all of the evidence
available by the time stage 3 was developed, the project had sold. The project
would be cash flow positive, and reservations about financing would be
substantially diminished.
[165] He said “he wouldn’t have the constraints placed on him by his financier.” The
differences between the valuers were canvassed at some length in the first instance
before me.
[166] Each of the valuers find some support in the others’ calculations.
[167] Mr Hamilton says in his 2016 report:
“I consider that Mr Brett’s cash flow 4 – after resumption most closely
reflects the actual resumption scenario. His after resumption valuation is
$46,425,000.
Mr Brett’s after resumption valuation of $46,425,000 is relatively similar to
my after resumption valuation of $45,750,000 based on a delay of 24
months. The difference in value would reflect what I consider an error in
Mr Brett’s valuation in that he commenced construction of Stage 3 well
before it would have been prudent to do so.
Based on the agreed pre-resumption valuation of $60,000,000 and Mr
Brett’s Cash Flow 4 after-resumption valuation of $46,425,000 the
compensation payable would be $13,575,000.”100
[168] Mr Brett, in a similar way in his December 2015 report observes, speaking of Mr
Hamilton’s November 2015 addendum report:
“Mr Hamilton’s 4 November 2015 Addendum Report contains a post-
resumption cash flow which adopts my post-resumption cash flow
including a return of 9.04% as per Attachment 2 of my Further
Supplementary Report dated 14 March 2012 but changed by the following:
1.4.1 Stage 3 construction is delayed for 8 months after the completion
of stage 2 whereas I do not include a delay.
1.4.2 Development approval period is extended by 12 months to 24
months.
1.4.3 Provision of a $241,236 cost of litigation to reduce DTMR
contribution.
1.4.4 Exclusion of a traffic network analysis cost of $100,000.”101
99 Initial Land Court hearing transcript, T 7-66, line 20.
100 Ex R4, page 13.
101 Ex R10, page 3, para 1.4.
-- 34 of 42 --
35
[169] In their closing submissions, Counsel for the respondent highlighted the manner in
which the applicant’s case with respect to litigation cost had been something of a
moving feast.
[170] Those submissions conceded that “of itself, the dispute about the amount is not
significant.”
[171] Because of my scepticism as to the accuracy of the $241,236 litigation cost, I am
not prepared to contemplate those modelling outcomes which relied upon that
figure.
[172] I am firmly of the view that the figure of $100,000 contemplated by DTMR is an
adequate allowance for that.
[173] As Mr Gore points out, the dispute about the amount is not significant.
[174] Mr Hamilton’s revised cash flow, which assumed the departmental figure of
$100,000, resulted in an increase in the after case land value of only $100,000, up to
$45,850,000.102
[175] Mr Brett’s cash flows 1 and 2 demonstrate something similar.103
[176] While the issue of the cost of achieving transport condition may result in relatively
minor differences amounting to less than say, one percent of the total value, the
issue of the time taken to achieve agreement is a different matter.
[177] In the present case, for the reasons I have already articulated, there was fault on both
sides which resulted in achievement of agreement taking much longer than it should
have. It is unnecessary to attempt to apportion blame but a number of factors led to
delays including:
(a) Changes in the western development application prompted by the
Brisbane City Council and unrelated to resumption issues104and
delays in responding to information request from concurrence
agencies and Brisbane City Council.105
(b) Difficulties in communication between the department and experts
engaged by the applicant.
102 Ex R35.
103 Ex R10, page 7
104 Ex R14, paras 83, 84, and 91(b).
105 Ex R12, para 24 and Ex R14, para 112.
-- 35 of 42 --
36
(c) Delays in the Brisbane City Council issuing its decision notice.106
(d) Delays occasioned by the appeal to the Planning and Environment
Court including the involvement of unrelated submitters.107
(e) Delays between March and September clarifying cost sharing
arrangements.108
(f) The various requirements in the Brisbane City Council in connection
with the planning application requiring expert input into other
matters including hydraulics, storm water drainage and quality
management and ecological matters.
[178] In all of the circumstances I am satisfied that the contention by the respondent for a
period of 12 months ought be preferred over the contention of the applicant for a
period of 24 (or 25 months).
[179] Accordingly, that leads to a position where the most acceptable recourse or
approaches from Mr Brett are his March 2012 report. I come to the view that so far
as Mr Brett’s work is concerned the preferable approach is that contained in his
March 2012 report which contemplated a 12 month approval period and $100,000
for a traffic network analysis.109
[180] That report generated an internal rate of return of 9.12 percent in the before situation
and 9.03 percent in the after.
[181] Mr Hamilton on the other hand, in his report of February 2016, remains vetted to
the figure of $241,236 for the cost of litigation to reduce the DTMR contributions.
He says in a quote, which is already referred to above,110 that he sought to achieve
the valuation exercise that would reflect not only the land taken but severance,
injurious affection and enhancement and asserts that Mr Brett does not satisfy an
approach.
[182] In his report, Mr Hamilton produces two cash flows which adopt the parameters
contained within Mr Brett’s after resumption cash flow in his 23 November 2011
report.111
[183] The parameters which he adopts in both cash flow cases are:
(a) Development yield
106 Ex R14, paras 166 to 171.
107 Ex R14, para 171.
108 Ex R17, para 9.
109 Ex R9.
110 Ex R6, page 9.
111 Ex R8.
-- 36 of 42 --
37
(b) Gross realisation
(c) Rate of sale
(d) Construction Costs
(e) Selling Costs
(f) Treatment of GST
(g) Internal Rate of Return (IRR) of 8.68 percent.
[184] In addition, his cash flow 2 adopts Mr Brett’s commencement date for construction
of Stage 3.
[185] In his case flow 1 he makes a number of adjustments to Mr Brett’s cash flow
modelling.
[186] Those adjustments are:112
Infrastructure charges reduced from $3,000,000 to $1,087,000.
Pre-construction phase increased from 12 months to 24 months.
Replaced the Traffic Network Analysis cost of $100,000 with the
cost to litigate the TIC of $214,497 (as per Mr McGregor’s 4
February 2016 affidavit).
Construction of Stage 3 to commence at month 41 whereas Mr
Brett’s cash flow has Stage 3 construction commencing eight months
earlier (as per Cidneo’s appeal ground 3 referred to in the Land
Appeal Court’s Judgment at [84] to [88]).
[187] In the cash flow 2 he makes the following adjustments to Mr Brett’s cash flow:113
Infrastructure charges reduced from $3,000,000 to $1,087,000.
Pre-construction phase increased from 12 months to 24 months.
Replaced the Traffic Network Analysis cost of $100,000 with the
cost to litigate the TIC of $214,497.
[188] His cash flow 1 produces an after resumption land value of $45,750,000, so that on
that basis compensation would be $14,250,000.114
[189] His cash flow 2 produces an after resumption land value of $47,250,000 which
generates a compensation figure of $12,750,000.
[190] The respondent in its submissions identifies two relevant differences between Mr
Hamilton’s 2015 report and his 2016 report.115
112 Ex R6, page 4.
113 Ex R6, page 5.
114 Ex R6, page 4.
115 Ex R39, paras 6 and 7.
-- 37 of 42 --
38
[191] As can be seen, Mr Hamilton utilised the cash flow from Mr Brett’s 2011 report
(which generated an internal rate of return of 8.68 percent) as the base cash flow,
which change is embraced by the respondent.
[192] The second difference identified relates to Mr Hamilton’s support for the litigation
cost of $214,497 focusing on cash flow 1.
[193] The respondent’s submissions contend, I think correctly, that within Mr Hamilton’s
cash flow 1 in his 2016 report there are two significant errors.
[194] The respondent in its written submissions submits as follows:
“The first mistake relates to the adjustment described as “pre-construction
phase increased from 12 months to 24 months.” It was common ground
between the 2 valuers in the original hearing that it was possible to start
construction in the last month of the pre-construction phase; for both
valuers that was month 12 in the before case; in the after case, it remained
month 12 for Mr Brett, but Mr Hamilton used month 18, to allow for the
extra 6 months to allow for the obtaining of a traffic report; applying the
same logic to the new period of 24 months, construction should commence
in month 24, not month 25.”116
[195] Those contentions are borne out by a review of the transcript on the remitted
hearing.117
[196] In cross-examination, Mr Gore put to Mr Hamilton that applying that same logic
that he had applied in his before and after cases in 2011 he would have started his
cash flow 1, true civil costs in month 24 not month 25 and Mr Hamilton agreed with
that proposition.118
[197] Because the respondent goes on to contend that it is outside the remitter for Cidneo
to contend for any other approach then that conceded on that occasion by Mr
Hamilton, because the logic was an area of common ground between the valuers at
the original hearing and so beyond the reach of any complaint of the Land Appeal
Court.
[198] I think that is correct.
[199] Shortly after that dialog, Mr Hamilton conceded that the impact on value of simple
interest for one month was of the order of $310,000 with the consequence that the
116 Ex R39, page 5, para 9.
117 T 2-56 to T 2-57.
118 T 2-56, lines 25 to 27.
-- 38 of 42 --
39
after value was reduced, thereby providing an opportunity to increase the
compensation contended for.
[200] The second mistake relates to Mr Hamilton’s adjustment to commit construction of
Stage 3 to commence at month 41 compared to Mr Brett’s construction
commencing eight months earlier.
[201] The respondent says in respect of that adjustment
“while it is true that the LIC did refer to a difference of eight months
between the two valuers in this discussion of Ground 3, Mr Hamilton has
taken that reference out of context in his decision to delay the start of
construction of Stage 3 for eight months after the time assumed by Mr
Brett.”
[202] The respondent contends that the eight months referred to by the Land Appeal Court
was in the context of its identification of the overall difference in the valuers total
development and sales periods in the after case where Mr Brett’s period was 62
months, whereas Mr Hamilton’s period was for 76 months, a difference of 14
months.
[203] Six months of that 14 months is accounted for by the period the subject of ground 2
which by the amended approach of Mr Hamilton as referred to by Mr Hinson in his
opening has now evaporated.
[204] The balance of eight months was referred to by the Land Appeal Court in its
discussion of ground 3 and, says the respondent:
“it was never identified as a period that separated the start of construction
of Stage 3 in the valuers different cash flows. Mr Whitelaw had identified
that as a period of five months and reference to the relevant cash flows
confirms that that was the correct period.”
[205] Reference to the transcript for the remitted hearing in his affidavit, Mr Whitelaw, in
seeking to describe the main differences between himself and Mr Brett, said “Mr
Brett starts Stage 3 five months earlier than Mr Hamilton in the ‘after’”. 119
[206] The respondent contends that the consequence of that is that in cash flow 1, Mr
Hamilton has started construction of Stage 3 some three months later than he should
have which lengthens the total period and so has the effect of reducing the after case
119 Ex R36, para 18.
-- 39 of 42 --
40
land value. This is because net realisations are occurring later, and interest is being
incurred for a longer period of time.120
[207] In cross-examination by Mr Gore, Mr Hamilton said as follows:
“Mr Brett’s preconstruction phase is 12 months, but with the true civil
works commencing in month 12. We’ve established that? --- Mmm.
Right? So if it is valid to adjust that 12 months by adding on an extra 12
months, that takes you to month 24. We discussed that before lunch,
correct? --- Yes, I’m following you.
And if you add on the five months’ difference, which was – we can see was
between you and Mr Brett for the commencement of stage 3, whatever you
use as the indicator of commencement, you get a total of 17 months to add
on to Mr Brett’s 12 months, so if he started phase – stage 3 in 2011 – let’s
go back to ---? --- At month 20, yes.
At 20, to use the trigger that you’ve used here. Then the adjustment would
be to month 37. Just let me think about that? --- Yes.
You’ve got to add on 17, so it’ll be to month 37. Yes. Correct? --- Yes.
Whereas you have added on four months. You’ve taken it to month 41? ---
Yes.
And that is a mistake? --- I’d have to think through why I adjusted it. It’s
inconsistent.
I’ll give you – I concede that.”
[208] Later, Mr Gore put to Mr Hamilton “now, the difference you and I have established
that, in truth emerged from that factor is five months, not eight months: correct?” to
which Mr Hamilton responded, “yes and then subsequently accepted that his use of
month 41 as the start of construction was incorrect.”121
[209] The consequence of all of those mistakes and concessions is that Mr Hamilton’s
cash flow analysis contained in his 2016 report122 is incorrect and that makes it very
difficult to act upon the conclusions of that report.
Conclusion
[210] For the reasons set out above, I remain of the view that the approach and reports of
Mr Brett are to be preferred to the approach and reports of Mr Hamilton, and have
attempted to set out above the reasons why I believe that is so.
120 T 2-65, lines 19 to 40.
121 T 2-68, lines 1 to 5.
122 Ex R10.
-- 40 of 42 --
41
[211] As I estimated above, I have come to the view that by relying on a 12-month
approval period and a $100,000 traffic network analysis as opposed to the $241,236
litigation cost, Mr Brett’s report of March 2012123 provides the appropriate basis
upon which to assess the compensation which is due to the applicant. Save that it is
premised upon a before resumption valuation of $60,877,800, which is some
$877,800 higher than the before resumption value that was agreed between the
valuers on the basis of the before valuation of $60 million dollars. The after value
calculated by Mr Brett was $54,500,000.124
[212] Accepting and relying upon that valuation exercise of course involved the adoption
of the figure of a pre-resumption contribution of $1,087,100. That figure is of
course applied in the pre- and post-resumption scenarios and the figures within that
report are not significantly inconsistent with any of the cash flow analyses done.
[213] I propose to utilise the more accurately calculated before land value of $60,877,800
for the purpose of trying to properly quantify the pre-resumption value.
[214] That was a figure contended for by the respondent and, in his evidence-in-chief in
the Land Court previously, Mr Hamilton acknowledged that he had, on the basis of
a direct comparison, valued the land at $60 a square metre, which on a precise
calculation produced a figure of $6,377,800, but had rounded it down.125
[215] To do so is consistent with the liberal estimate principle, well established, that in a
resumption case doubts are resolved in favour of a more liberal estimate.126
[216] Accordingly I order that compensation is payable by the respondent to the applicant
for the taking on 22 February 2008 of an area of 8.385 hectares being Lot 1 on SP
218520 being part of the land contained in title reference 50553649, County of
Stanley, Parish of Oxley in the sum of $6,377,800.
Orders:
123 Ex R9.
124 Ibid, page 5.
125 Initial Land Court hearing transcript, T 5-5.
126 Commissioner of Succession Duties (SA) v Executor Trustee and Agency Company of South
Australia Ltd [1947] 74 CLR 358 at [373]-[374]; Gregory v FCT [1971] 123 CLR 547; and Boland v
Yates Property Corporation Pty Ltd [1999] 74 ALJR 209 at [279].
-- 41 of 42 --
42
Compensation is payable by the respondent to the applicant for the taking on
22 February 2008 of an area of 8.385 hectares being Lot 1 on SP 218520 being
part of the land contained in title reference 50553649, County of Stanley,
Parish of Oxley in the sum of Six Million Three Hundred and Seventy-Seven
Thousand Eight Hundred Dollars ($6,377,800).
WL COCHRANE
MEMBER OF THE LAND COURT
-- 42 of 42 --
Official source: https://www.sclqld.org.au/caselaw/QLC/2017/045