Cherwell Creek Coal Pty Ltd v BHP Queensland Coal Investments Pty Ltd & Ors (No 8) [2017] QLC 7 (2017) 38 QLCR 24
* Pursuant to the Land Court Rules 2000, rule 21 (Power to correct mistakes), this is a corrected decision,
issued on 21 February 2017, and replaces the original decision issued on 17 February 2017.
LAND COURT OF QUEENSLAND
CITATION: Cherwell Creek Coal Pty Ltd v BHP Queensland Coal
Investments Pty Ltd & Ors (No. 8) [2017] QLC 7*
PARTIES: Cherwell Creek Coal Pty Ltd (ACN 063 763 002)
(applicant)
v
BHP Queensland Coal Investments Pty Ltd (ACN 098
876 825)
QCT Resources Pty Ltd (ACN 010 808 705)
BHP Coal Pty Ltd (ACN 010 595 721)
QCT Mining Pty Ltd (ACN 010 487 840)
Mitsubishi Development Pty Ltd (ACN 009 779 873)
QCT Investment Pty Ltd (ACN 010 487 831)
Umal Consolidated Pty Ltd (ACN 000 767 386)
(respondents)
FILE NO: MRA1332-08
DIVISION: General division
PROCEEDING: Hearing of application
DELIVERED ON: 17 February 2017
DELIVERED AT: Brisbane
HEARD ON: 10 February 2017
HEARD AT: Brisbane
PRESIDENT: FY Kingham
ORDERS: 1. The application to strike out the amendments is
refused.
2. The application to extend time for filing the Amended
Defence is allowed.
3. The dates allocated for trial of the Originating
Application are vacated.
4. The matter will be listed for further directions and
argument as to costs, on a date to be fixed, in
consultation with the parties.
-- 1 of 18 --
2
CATCHWORDS: CIVIL PROCEEDINGS IN STATE AND TERRITORY
COURTS – PLEADINGS – AMENDMENT – STRIKING
OUT – where the respondent filed an Amended Defence –
where the applicant applied to strike out the pleadings –
whether the applicant was taken by surprise – whether the
amendments disclose no reasonable defence – whether the
amendments delay the fair trial of the proceedings
CIVIL PROCEEDINGS IN STATE AND TERRITORY
COURTS – PLEADINGS– AMENDMENT – TIME,
EXTENSION AND ABRIDGMENT– where the respondent
sought an extension of the time fixed by directions to file
the Amended Defence – whether leave to amend was
required – whether the Court has power to vary a direction
to extend time – where the applicant opposed leave being
granted – where the respondent argued the amendments
were relevant, central to the proceedings, and responsive to
the applicant’s case – whether the applicant was taken by
surprise – whether the amendments lacked merit – whether
the amendments delay the fair trial of the proceedings –
whether the amendments result in additional and wasted
costs – whether the Court should exercise its discretion to
extend time.
Land Court Act 2000, s 7, s 22(2)
Land Court Rules 2000, r 4, r 19, r 45
Mineral Resources Act 1989, s 179, s 269(4), s 269(4)(m), s
279(1), s 281(3)(a)(vi), s 281(4)(b), s 281(4)(c), s 334ZJ, s
334ZJ(5)
Mineral Resources (Peak Downs Mine) Amendment Act
2008
Uniform Civil Procedure Rules 1999, r 5, r 7, r 171, r 378
Aon Risk Service Australia Ltd v Australian National
University (2009) 239 CLR 175 applied
Hartnett v Hynes [2009] QSC 225 followed
Monto Coal 2 Pty Ltd v Sanrus Pty Ltd (as Trustee of the
QC Trust) [2014] QCA 267 applied
The Beach Retreat P/L & Anor v Mooloolaba Marina Ltd &
Anor [2008] QCA 224 considered
Wills v Minerva Coal Pty Ltd [No. 2] (1998) 19 QLCR 297
considered
APPEARANCES: G Gibson QC and Ms J Chapple of Counsel (instructed by
Holding Redlich Lawyers) for the applicant
S Doyle QC and Mr A Stumer of Counsel (instructed by
Allens Linklaters) for the respondents
-- 2 of 18 --
3
[1] The parties have brought competing applications about an Amended Defence1 filed
by the respondent companies (“BMA”) 26 days after the date fixed by direction of
the Court. Although the applications are procedural, they have weighty consequences
for both parties. The outcome will determine the issues BMA may raise at trial and
will affect what further work each party must undertake to prepare the claim for a
trial listed to commence in a few weeks’ time.
[2] BMA sought an extension of time or, if required, leave to file the Amended Defence.
It argued the amendments relate to issues already raised by the pleadings, explicitly
or inferentially. It asserted they are relevant, central to the proceedings, and
responsive to the applicant’s case.
[3] The applicant, Cherwell Creek Coal Pty Ltd (“Cherwell Creek”), challenged the
Court’s power to vary the direction, opposed leave being granted and applied to strike
out the pleadings. It argued it was taken by surprise by the amendments, which
disclose no reasonable defence or lack merit, and which will delay the fair trial of the
proceeding, resulting in additional and wasted costs.
[4] Argument proceeded on the basis that similar factors were raised by both applications,
although the strike out application was brought under r 171 of the Uniform Civil
Procedure Rules 1999 (“UCPR”), which specifies particular grounds upon which a
strike out application might proceed.
[5] The issues raised by the parties can be dealt with by addressing the following
questions:
Does BMA need leave to file an Amended Defence or can the direction be varied
to extend time?
Was Cherwell Creek taken by surprise by the amendments?
Do the amendments disclose a reasonable defence?
Do the amendments delay the fair trial of the proceedings?
Will the amendments result in additional and wasted costs?
1 The document is entitled Defence to the Third Amended Annexure A (to the originating application)
but is referred to throughout these reasons as the Amended Defence.
-- 3 of 18 --
4
Should the Court allow the Amended Defence or should the amendments be struck
out?
[6] Those questions must be answered in the context of the background to, and history
of, the proceeding.
[7] Cherwell Creek claims compensation from BMA under s 334ZJ of the Mineral
Resources Act 1989 (“MRA”). That section sits in a special purpose part of the MRA
introduced by what the parties refer to as the Amending Act,2 which came in to force
in May 2008.
[8] The Amending Act brought to an end what was then a lengthy dispute between the
parties about their eligibility for mining and associated rights over land owned by
BMA near its Peak Downs Mine.
[9] Before the Amending Act commenced, Cherwell Creek and BMA held overlapping
and apparently inconsistent resource tenures. Cherwell Creek held an exploration
permit (EPC545). It had also applied for a mineral development licence over the land
(MDLA364). BMA held a special lease over the same area. The Amending Act
determined the matter in BMA’s favour, while providing Cherwell Creek a limited
opportunity to claim compensation from BMA for its loss of opportunity to
commercialise the MDLA364 coal resource.
[10] To make out its claim, Cherwell Creek must persuade the Court that compensation is
payable. In deciding whether it is, and in what amount, the Court must consider the
likelihood of a hypothetical proposition: that, but for the Amending Act, Cherwell
Creek would have been able to commercialise the MDLA364 coal resource, having
regard to factors including:
(a) the likely extent and quality of the MDLA364 coal resource;
(b) the likely mineability of the MDLA364 coal resource;
(c) the likely market for any coal mined from the MDLA364 coal
resource;
(d) the likely life of a mine for the MDLA364 coal resource;
(e) the likely coal revenue generated from the MDLA364 coal
resource;
(f) the likely coal revenue generation costs;
(g) the likelihood of a mining lease, appropriate for Cherwell Creek to
commercialise the MDLA364 coal resource, being granted under
this Act;
Note—
2 Mineral Resources (Peak Downs Mine) Amendment Act 2008.
-- 4 of 18 --
5
See sections 269(4) and 271 for matters that the Land Court and Minister
take into account in dealing with an application for the grant of a mining
lease.
(h) any other relevant matter.3
Against that background, I turn to the questions posed above.
Does BMA need leave to file an Amended Defence or can the direction be varied to
extend time?
[11] BMA’s primary position is that it does not need leave to file the Amended Defence.
[12] From the outset the parties agreed that the claim should proceed by way of pleadings
so the issues could be clearly defined for trial. Pleadings are not provided for in the
Land Court Act 2000 (“LCA”), the Land Court Rules 2000 (“LCR”) or a Practice
Direction issued under s 22(2) of the LCA. Rule 4 of the LCR applies the UCPR, with
necessary changes, if the LCR does not provide for a matter provided for by the
UCPR.
[13] BMA relied on r 378 of the UCPR which allows a party to amend its pleading without
leave at any time before it has filed a request for trial date. It argued the trial listing
in November 2014 cannot be equated to a request for trial date.
[14] Although Cherwell Creek accepts the listing was not due to a formal request, it said
BMA was not relieved from seeking leave.
[15] In The Beach Retreat P/L & Anor v Mooloolaba Marina Ltd & Anor4 Keane JA, as
he then was, observed there was some merit in the argument that if a matter is placed
on the Supervised Case List in the Supreme Court, r 378 of the UCPR no longer
applies.
[16] That observation was obiter. In Monto Coal 2 Pty Ltd & Ors v Sanrus Pty Ltd (as
Trustee of the QC Trust) & Ors,5 Flanagan J questioned, again without deciding,
whether all that is required to oust r 378 is for a matter to be placed on the supervised
case list.
3 Section 334ZJ(5)(a)-(h) of the Mineral Resources Act 1989.
4 [2008] QCA 224.
5 [2014] QCA 267.
-- 5 of 18 --
6
[17] In The Beach Retreat Keane JA referred to clause 19 of Practice Direction No 6 of
2000, which applies to supervised cases. It provides once the matter has been
allocated a trial date, a party who becomes aware of any proposal to amend a pleading
must notify the Supervised Case List Manager forthwith so that it can be dealt with
by the Court. There is no equivalent Practice Direction in this Court.
[18] I am not satisfied the trial listing ousted the operation of r 378. The trial listing was
instigated by the Member then case-managing the claim. It was done more than two
years prior to the dates allocated, when neither party was in a position to confirm they
would be ready for trial. Later directions made by the Court confirmed that amended
pleadings were expected. Those directions did not specify proposed pleadings or
require prior leave. They placed no restriction on the scope of the amendments.
[19] In those circumstances, I find BMA does not need leave to file an Amended Defence.
[20] BMA is, however, in breach of a direction of this Court to file the Amended Defence
by 4 November 2016. By making its application, BMA conceded some form of order
was necessary, whether to vary that date or extend time, so as to regularise its filing
of the Amended Defence.
[21] Cherwell Creek submitted the Court does not have power to vary the direction. It
appears to have been made under either s 22(3) of the LCA or r 19 of the LCR.
Nothing seems to turn on which head of power was used. Cherwell Creek argued the
direction is an order of the Court which can only be varied or set aside if the
circumstances specified in r 45 of the LCR apply. None of those circumstances apply
here.
[22] However, r 7 of the UCPR provides for extension of time fixed by order, a matter not
provided for by the LCR. Applying r 4 of the LCR r 7 of the UCPR confers power on
the Court to extend the time fixed by direction for the Amended Defence to be filed.
Was Cherwell Creek taken by surprise by the amendments?
[23] This question cannot be addressed without some exploration of the amendments and
the history of the pleadings.
[24] There are three groups of amendments which, for the sake of clarity, I will name:
-- 6 of 18 --
7
the JR issue;
the prospective use issue; and
the special loss issue.
[25] The JR issue is raised by paragraphs 2(f) and 2(g) of the Amended Defence and are
pleaded to support BMA’s denial of Cherwell Creek’s claim that, but for the
Amending Act, Cherwell Creek would have been granted MDL364. One aspect of that
claim is that, as the holder of EPC545, Cherwell Creek was eligible to apply for
MDL364.
[26] In paragraph 2(f), BMA alleges it commenced proceedings in the Supreme Court in
2003 to challenge the initial grant of EPC545 and the decision to renew it. In
paragraph 2(g) BMA alleges that, but for the Amending Act, it would have pursued
that proceeding, and any appeals, and would have obtained an order quashing or
setting aside the renewal of EPC545.
[27] It seems many issues were raised in those proceedings. Prior to the hearing, BMA
advised Cherwell Creek that it would deliver particulars to confine the arguments that
would be relied upon to further the JR issue to the allegations already pleaded in
paragraph 2.6 On that basis, the amendments are not as far reaching as they might
otherwise appear and do not raise new issues about the validity of that tenure. All
they do is assert that BMA would have pursued the proceeding in the Supreme Court
and been successful in challenging the renewal of EPC545. The arguments relied on
by BMA to establish the allegation would have succeeded in the proceeding were
already pleaded.
[28] The prospective use issue is raised by paragraphs 11(b)(iii), 14(f)(ii), 14(f)(iii),
14(f)(iv) and 14(f)(v)(C). These paragraphs are pleaded to advance BMA’s denial
that, by 1 July 2010, Cherwell Creek would have been granted a mining lease for the
disputed area, but for the Amending Act. That is one of the matters the Court must
consider in determining whether compensation is payable.7
[29] In making its recommendation on a disputed application for a mining lease, the Court
must consider the matters specified in s 269(4) of the MRA. They include the
6 Ex. 1, letter from Allens Linklater to Holding Redlich dated 9 February 2017.
7 Section 334ZJ(5)(g) of the Mineral Resources Act 1989.
-- 7 of 18 --
8
prospective use of that land.8 In deciding the application, the Minister must consider
the same matters, as well as the recommendation made by the Court.9
[30] BMA alleges the Court would not have recommended the grant of a mining lease
because of BMA’s plans to use the disputed area for infrastructure for the Caval Ridge
Mine. It alleges that was the most appropriate and economic use for that land and that
was a good reason to refuse to grant the mining lease.
[31] BMA said the prospective use of the land by BMA for the Caval Ridge Mine was
always in issue. BMA’s plans for the land and the impact of granting tenure to
Cherwell Creek was referred to in the Second Reading Speech given by the Minister
for Mines and Energy when he introduced the Amending Act.
[32] That speech was referred to in paragraph 2 of the Defence filed on 13 October 2008.
It was pleaded in support of an allegation that MDLA364 had already been rejected
by the Minister; not that it would have been rejected but for the Amending Act.
[33] However, by its particulars delivered on 24 April 2009 (at paragraph 7) BMA
squarely raised the prospective use as a reason the mining lease would not have been
granted. The particulars related to the allegation in paragraph 3(b)(v) of the Defence
that the Minister would not have granted the mining lease. It pleaded it could not be
more particular but the reasons are to be inferred from the Minister’s Second Reading
Speech.
[34] The prospective use of the land by BMA was clearly raised in the Minister’s Second
Reading Speech. Although the Amended Defence filed in November 2016 is much
more detailed in its particulars, Cherwell Creek was not taken by surprise by the issue.
[35] The special loss issue arises from paragraphs 11(c)(v), 11(c)(vi) and 11(c)(vii).10
BMA alleges Cherwell Creek would have withdrawn its application for a mining
lease because its compensation liability to BMA, as the owner of the land, would have
made the mining lease economically unviable. BMA alleges total compensation
payable by Cherwell Creek would have exceeded $180 million, which includes its
8 Section 269(4)(m) of the Mineral Resources Act 1989.
9 Section 271 of the Mineral Resources Act 1989.
10 Of the Defence to the third Amended Annexure, filed 30 November 2016.
-- 8 of 18 --
9
loss as a result of having to relocate the infrastructure for the Caval Ridge Mine onto
its mining lease ML1775.
[36] BMA conceded this issue has not been pleaded before; but argued the broader issue
of compensation was already raised, at least inferentially, on the pleadings. Cherwell
Creek alleged it would have complied with the requirements of the MRA for the grant
of tenure. That includes prior payment of compensation.11 The level of compensation
liability is relevant to the viability of the mine. However, neither party had identified
that, specifically, as an issue.
[37] Cherwell Creek did not contest its relevance. The economic viability of the mine, is
an important factor the Court must consider.12
[38] Cherwell Creek has had, for some years, information that BMA relies upon to make
this allegation: submissions made by BMA about the renewal of EPC545 and the
application for MDL364. Both submissions raise the prospective use issue and
estimate the loss BMA faced if held out from that use. So Cherwell Creek was aware
of the claimed loss, even if it had not identified precisely how it might be relied upon
in these proceedings.
[39] Neither, it appears, did BMA. It was one of their experts, Mr Eales, who brought this
matter to light. A solicitor for BMA, Ms Alana Maree Petty, explained how it came
to her attention and the steps then taken to investigate, calculate and then articulate
this allegation.13
[40] BMA also argued that Cherwell Creek seeks to use a special value assessment to
support its case, while trying to hold BMA out from running a positive argument
about it. Dr Rudenno, an expert engaged by Cherwell Creek, was asked to provide an
opinion on a fair market value for both the coal resource and the application for
MDL364.
[41] Dr Rudenno cross-checked his valuation by considering BMA’s submission to
government in June 2006 opposing the renewal of EPC545.14 He said the clear
implication is that there was likely special value to BMA in using the area of EPC545.
11 Section 279(1) of the Mineral Resources Act 1989.
12 Section 334ZJ(5)(g) of the Mineral Resources Act 1989.
13 Affidavit of Alana Maree Petty, sworn on 30 January 2017, at paras 13-25.
14 Ex. 4, dated 22 June 2006.
-- 9 of 18 --
10
He noted BMA’s assessment of $180 million and, assuming no economic quantities
of coal on EPC545, he adopted a mid-point range of $90 million to show his valuation
of MDLA364 at $132 million15 was not unreasonable.16
[42] BMA wishes to contradict Dr Rudenno’s opinion. It argued Cherwell Creek seeks to
rely on a special value assessment against it, while denying BMA the opportunity to
run a positive case about its loss.
[43] Although the way in which that loss relates to these proceedings has taken Cherwell
Creek by surprise, BMA’s assertion that it would lose some $180 million if MDL364
was granted is not new to Cherwell Creek. Just as BMA could have recognised its
significance for this proceeding earlier, so could have Cherwell Creek. The surprise
is in the articulation of the issue.
Do the amendments disclose a reasonable defence?
[44] One ground for striking out a pleading is that it fails to disclose a reasonable cause of
defence.17 Cherwell Creek advanced that ground in relation to two issues: the JR issue
and the special loss issue.
[45] It questioned the utility of the JR issue as success in those proceedings would not
necessarily result in Cherwell Creek being disentitled to apply for or be granted
MDL364. Quashing EPC545 or setting aside its renewal would have no consequence
because Cherwell Creek held EPC545 at the time it made the application for
MDL364. This is all that was required.
[46] BMA argued the requirement for an exploration permit to apply for a mineral
development licence should be interpreted to mean “a valid exploration permit”. That
is a question of statutory interpretation best left to trial. Although the JR proceedings
would not necessarily result in a declaration that EPC545 was void ab initio, that is
one aspect of the relief sought in the Supreme Court proceeding and is directly
pleaded in the Defence.
[47] Cherwell Creek advanced a number of arguments about the special loss issue.
15 Expert report of Dr Rudenno, dated 15 February 2016, at [12].
16 Expert report of Dr Rudennos, dated 15 February 2016, at [66].
17 Rule 171(1)(a) of the Uniform Civil Procedure Rules 1999.
-- 10 of 18 --
11
[48] It referred to the report of Mr Eales, the valuer engaged by BMA. Cherwell Creek
construed BMA’s pleading regarding special loss as one made under both
s 281(3)(a)(vi) and s 281(4)(c) of the MRA. Section 281(3)(a)(vi) is a head of
compensation for all loss or expense that arises. Section 281(4)(c) allows a premium
to be applied if the owner of land proves the status and current use of the land justifies
it.
[49] BMA has advanced the special loss issue relying on s 281(3)(a)(vi).18 That may
counter Cherwell Creek’s argument the claim can only be made for a current not a
prospective use.
[50] The distinction between the two compensation provisions was recognised by Mr Scott
in Wills v Minerva Coal Pty Ltd [No. 2]19 when he found he could not allow a claim
for loss of a prospective use under s 281(4)(c) but could do so under s 281(3)(a)(vi).
That approach has been taken in other cases at first instance in this Court, and has not
been challenged on appeal.20
[51] Cherwell Creek also contended Mr Eales’ compensation assessment involves an
element of double dipping. He determined the highest and best use of the land affected
by MDLA364 was for infrastructure for the Caval Ridge Mine; yet also assessed the
loss of access to the land for that purpose as a special loss to BMA. If its value for
infrastructure purposes is accounted for in the market value of the land, it cannot also
be claimed as a special loss.
[52] Whether the loss can be claimed as a special loss and, also, the extent to which they
are already accounted for in the assessment of market value are issues for trial. It may
well be that BMA will have to elect one calculation or the other.
[53] Another argument raised by Cherwell Creek about the merit of the amendments is
that compensation cannot include any allowance for minerals; something it says the
special loss assessment appears to do. Certainly s 281(4)(b) of the MRA prohibits an
allowance being made for any minerals that are or may be on or under the surface of
the land concerned. The question is what is the land concerned.
18 Although paragraph 11(c)(iv) contains a typographical error noting the section as s 281(3)(vi).
19 (1998) 19 QLCR 297.
20 Xstrata Coal Queensland Pty Ltd & Ors v Keys & Anor; Xstrata Coal Queensland Pty Ltd v Sky
Grove Pty ltd; Xstrata Coal Queensland Pty Ltd v Erbacher; Xstrata Coal Queensland Pty Ltd v
Edmonds & Anor [2013] QLC 34; McDowall v Reynolds [2015] QLC 32.
-- 11 of 18 --
12
[54] BMA wears two hats in this respect. It is the owner of the land affected by the
hypothetical proposed mining lease (over MDLA364). It appears to be common
ground that s 281(4)(b) would preclude compensation for the minerals on that land.
[55] However, BMA also holds a mining lease over adjacent land (ML1775). The special
loss calculation involves the sterilisation of the coal resource on ML1775, not on
Cherwell Creek’s proposed mining lease area (MDLA364). Whether s 281(4)(b)
precludes an allowance for minerals on ML1775 is a matter of statutory construction,
and an issue for trial.
[56] Cherwell Creek raised a number of other issues about Mr Eales’ methodology and
proof of the assumptions he has made in his assessment. Questions of methodology
can be determined at trial. However, Cherwell Creek has questioned whether all the
expert and other evidence upon which Mr Eales will rely has been disclosed or
included in the existing expert reports. Further directions may be needed about such
matters.
[57] Finally, Cherwell Creek claims BMA is prevented from claiming special loss because
it could not demonstrate it could have secured a mining lease for infrastructure
purposes due to EPC545, held by Cherwell Creek. Whether EPC would have
precluded BMA from becoming eligible to apply depends on at least two issues:
firstly; the validity of EPC545, a live issue on the pleadings; and secondly,
construction of the relevant provisions regarding eligibility. Again these are questions
for trial.
[58] Cherwell Creek has raised numerous arguments about the special loss issue
amendments. Some appear to misconceive BMA’s case. Others raise issues for trial.
[59] The discretion to strike out pleadings should only be exercised in clear cases. I am
not persuaded BMA’s amendments regarding either the JR or the special loss issues
are unarguable. I am not satisfied they should be struck out for failing to disclose a
reasonable defence.
-- 12 of 18 --
13
Do the amendments delay the fair trial of the proceedings?
[60] Unnecessary delay can constitute sufficient irreparable prejudice.21 Cherwell Creek
argued the amendments will significantly delay the proceeding; holding out Cherwell
Creek from potential compensation.
[61] As I understand the submissions, the parties agree amendments raising the JR issue,
at least as clarified by BMA before the hearing, would not, alone, delay the fair trial
of the proceedings.
[62] The focus of Cherwell Creek’s submissions about prejudice arising from delay (and
cost) relate to the amendments raising the prospective use and the special loss issues.
It said these raise significant new issues that must be considered by its experts for the
first time. BMA must provide substantial further disclosure. Cherwell Creek’s experts
will need to revise their expert reports.
[63] Although BMA contested the prospective use issue was new, it did not seriously
contest any of the other propositions or challenge the deponents of the affidavits that
Cherwell Creek relied upon to advance them.22
[64] BMA could, and arguably should, have identified and pleaded the special loss issue
earlier. Against that, BMA is defending Cherwell Creek’s claim.
[65] Cherwell Creek alleged it would comply with all requirements for grant of the mining
lease. That inferentially raised compensation. Neither party addressed in their
pleadings how compensation would be calculated.
[66] Economic viability is central to the likelihood of commercialisation of the coal
resource. Its compensation liability is an aspect of that assessment. Cherwell Creek
had some information from BMA which identified and indeed sought to quantify a
loss that, arguably, may be compensated for.
[67] When BMA delivered its previous Amended Defence (August 2009) and its
particulars (February 2010) Cherwell Creek’s case was not fully particularised. In its
21 Aon Risk Service Australia Ltd v Australian National University (2009) 239 CLR 175 (‘Aon’) at para
[5].
22 See 1st affidavit of Toby Michael Boys; 1st affidavit of John Stapleton; 1st affidavit of Jamie Ivan
Freeman; 1st affidavit of Jeffrey lewis Hall; affidavit of Alana Maree Petty; Affidavit of Kenneth
Edward Stapleton sworn 6 February 2016; and affidavit of Geoffrey Charles Streeton.
-- 13 of 18 --
14
March 2009 response to BMA’s request for particulars of the claim, Cherwell Creek
repeatedly stated it could not give particulars regarding matters of substance until it
had obtained expert reports.
[68] That is understandable, given the hypothetical nature of the exercise it had to engage
in and the need for experts in various disciplines to rely on the work of others before
they could express their opinion. It seems this was accepted by the Member managing
the matter, as well as the parties.
[69] Cherwell Creek did not deliver its fully particularised case until 18 December 2015.
The Court has granted Cherwell Creek a number of indulgences regarding late
delivery of its material.
[70] BMA did not deliver amended pleadings until 30 November 2016; and then only 26
days after it had been directed to do so.
[71] I am not persuaded BMA could not raise the issue until it had Cherwell Creek’s fully
documented mine plan. I accept that it was open to BMA to flag potential
amendments during reviews or in correspondence with Cherwell Creek.
[72] Nevertheless, the directions did not constrain BMA in what amendments it could
make. It has put on evidence about how and when it recognised this issue was open
and the steps taken to investigate and articulate it. Although the further delay is
unfortunate, it must be assessed in the context of the consensus that expert reports
should precede pleadings.
[73] Arguably, that approach to case management is justified by what has transpired. The
experts played the role the Court and the parties anticipated. It was the process of
preparing and, in BMA’s case, responding to the expert reports that brought to light
an important issue which had been overlooked by both parties. In reviewing and
responding to Mr Knight’s report, Mr Eales clarified a matter likely to be in dispute.
Better that was identified then than after the trial had commenced.
[74] The question of delay is also coloured by the circumstances in which the trial was
listed. Dates were allocated in late 2014. That listing was prompted by the Member
managing the matter, not the parties.23 It was well intentioned to advance the case and
23 Transcript of proceedings 5/12/2014, at pp 1-2.
-- 14 of 18 --
15
secure time in the Court calendar. It is clear, though, that the directions were
retrofitted to meet the trial listing.
[75] In hindsight the trial listing was premature. Neither party had delivered final
pleadings. Neither could then confirm they would be ready for trial. Neither could say
the period allocated was sufficient or excessive.
[76] The later directions allowed both parties to deliver amended pleadings after they had
obtained their expert reports, but before the experts had jointly conferred. That is an
unusual way to proceed, but is explained by the unusual nature of the proceedings.
Without detailed expert evidence about the criteria in s 334ZJ(5), the parties were
unable to distil disputed issues with sufficient particularity.
[77] However, the timetable allowed an Amended Defence only four months before trial.
It set a compressed timetable for joint conferencing by the experts only two and a half
months before trial; a period which included the Christmas and New Year vacation.
Given the history of the proceedings, these features made the directions to trial
inherently risky.
[78] Although the listing and the later directions appear to have been largely by consent,
this cannot be equated to a case where a party has pressed for trial on dates later
abandoned because of their conduct.
[79] One final aspect of delay should be mentioned. The parties were asked to propose
directions for the further conduct of the matter, dealing, alternatively, with the
Amended Defence being allowed, or not. Cherwell Creek’s proposed directions,
assuming BMA could not file its Amended Defence, assume the trial cannot proceed
until the second half of 2017. The trial could not have proceeded as listed and the
delay attributable to the amendments is some five months less than the 13 months
Cherwell Creek asserted.
Will the amendments result in additional and wasted costs?
[80] The payment of costs does not necessarily entitle a party to procedural relief.
However, the efficacy of a costs order is a relevant factor in exercising discretion.
BMA argued it is good for any costs order made on the application.
-- 15 of 18 --
16
[81] Cherwell Creek estimates the additional costs of responding to the amendments could
be in the order of $2 million. Although BMA did not cross-examine the experts who
estimated their further costs, it does not accept all the costs are attributable to the
amendments. It challenged an underlying assumption about the scope of the work
required by Cherwell Creek’s Mining Engineer, Mr Stapleton. He said he would be
required to develop a practical mine plan for the coal resource within ML1775 based
upon geological data and modelling. He also said he would need to investigate
alternative mine plans for both Caval Ridge Mine and the Cherwell Creek Mine to
deal with infrastructure and mining options.24
[82] BMA does not accept that is a necessary exercise and, therefore, cost. BMA had
already developed its own mine plan for Caval Ridge in the period between 2008 and
2010. If that work is not required that also has implications for the argument about
delay as Mr Stapleton said he would need 13 months to undertake the exercise.
[83] There is also the argument that BMA’s opposition to Cherwell Creek having access
to its drilling data resulted in unnecessary costs. BMA’s position that the data was not
relevant, although open given the state of the pleadings at the time, is now inconsistent
with its Amended Defence. Had BMA identified the special loss issue earlier, those
costs might have been reduced or avoided altogether.
[84] It is difficult to determine the scale of additional and wasted costs at this stage of the
proceedings. That is better done after trial. However, I accept there will be
considerable cost consequences for both Cherwell Creek and BMA; some additional
and some wasted. Even discounting Cherwell Creek’s assessment by 50%, the figure
is substantial.
Should the Court allow the Amended Defence or should the amendments be struck
out?
[85] I have already stated my reasons for concluding that leave to file the Amended
Defence was not required. However I have approached both the application to extend
time and the application to strike out the amendments in light of the principles
24 Stapleton affidavit at [4](b)(i) and (iii).
-- 16 of 18 --
17
enunciated in Aon Risk Services Pty Ltd v ANU.25 They would guide my decision on
an application for leave, if that was required.
[86] That is consistent with the philosophy of the UCPR expressed in r 5 and the
requirement in s 7 of the LCA that the Court act according to equity, good conscience
and the substantial merits of the case. Where the Court is called upon to exercise its
discretion in relation to amended pleadings, the Aon principles are accepted to be
generally applicable, whether or not leave to amend is required.26 They provide useful
guidance in ensuring the rules are applied to facilitate the just and expeditious
resolution of the real issues at a minimum expense. Respectfully, I adopt the
compendious distillation of relevant factors in the judgment of Applegarth J in
Hartnett v Hynes.27
[87] The application to strike out the amendments is made on particular grounds canvassed
in these reasons. I am not satisfied any of the amendments should be struck out
because they fail to disclose a reasonable defence. The remaining grounds raise
considerations common to both applications. I have sufficiently canvassed whether
Cherwell Creek was taken by surprise by the amendments and the prejudice to
Cherwell Creek by delay of the trial and additional or wasted costs.
[88] The rules require a balancing of factors specific to the case at hand. As well as the
considerations advanced by Cherwell Creek, the Court must consider any prejudice
to BMA if it cannot raise the real issues canvassed by the amendments at trial.
[89] BMA is entitled to a proper opportunity to plead its case. The JR issue does not rest
on new factual allegations; except about BMA’s allegation that it would have
persisted in the proceedings. The prospective use issue further particularises a live
question on the former pleadings, which is fundamental to the matters the Court must
consider at trial of the claim.
[90] Although the special loss issue is newly pleaded, it relates to an important factor for
the claim. BMA has provided some explanation for the delay. Although Cherwell
Creek considers the explanation is not adequate, BMA’s failure to identify and
articulate the special loss argument earlier is not surprising given the unique and
25 (2009) 239 CLR 175 at [5].
26 Monto Coal 2 Pty Ltd v Sanrus Pty Ltd (as Trustee of the QC Trust) [2014] QCA 267 at [73].
27 [2009] QSC 225 at [27].
-- 17 of 18 --
18
complex nature of the claim. Cherwell Creek did not identify it either, although being
seized of relevant information.
[91] Neither party advocated for the trial dates. The directions left clarification of the
issues for trial until the 11th hour. The compressed timetable for final pleadings and
expert conferences presented an appreciable risk that the trial might not proceed as
listed. As matters have transpired, Cherwell Creek is not ready to proceed even if the
amendments are not allowed.
[92] Balancing all the factors canvassed, it would be inappropriate to hold out BMA from
pleading matters which are central to the claim. The prejudice to Cherwell Creek must
be viewed in the context of the proceedings as a whole and can be somewhat
ameliorated by orders about costs.
Orders
[93] Having regard to all those factors, I make the following orders:
1. The application to strike out the amendments is refused.
2. The application to extend time for filing the Amended Defence is allowed.
3. The dates allocated for trial of the Originating Application are vacated.
4. The matter will be listed for further directions and argument as to costs,
on a date to be fixed, in consultation with the parties.
FY KINGHAM
PRESIDENT OF THE LAND COURT
-- 18 of 18 --
Official source: https://www.sclqld.org.au/caselaw/QLC/2017/007