Cherwell Creek Coal Pty Ltd v BHP Queensland Coal Investments Pty Ltd & Ors (No. 6) [2017] QLAC 1 (2017) 38 QLCR 189
LAND APPEAL COURT OF QUEENSLAND
CITATION: Cherwell Creek Coal Pty Ltd v BHP Queensland Coal
Investments Pty Ltd & Ors (No. 6) [2017] QLAC 1
PARTIES: CHERWELL CREEK COAL PTY LTD
(ACN 063 763 002)
(appellant)
v
BHP QUEENSLAND COAL INVESTMENTS PTY LTD
(ACN 098 876 825), QCT RESOURCES PTY LTD
(ACN 010 808 705), BHP COAL PTY LTD
(ACN 010 595 721), QCT MINING PTY LTD
(ACN 010 487 840), MITSUBISHI DEVELOPMENT
PTY LTD (ACN 009 779 873), QCT INVESTMENT PTY
LTD (ACN 010 487 831) AND UMAL CONSOLIDATED
PTY LTD (ACN 000 767 386)
(respondents)
FILE NO/S: LAC001-17
LAC002-17
DIVISION: Land Appeal Court of Queensland
PROCEEDING: Appeal
ORIGINATING
COURT:
Land Court of Queensland, Brisbane
DELIVERED ON: 20 September 2017
DELIVERED AT: Brisbane
HEARING DATE: 15 May 2017
THE COURT: Dalton J
Mr W L Cochrane, Member of the Land Court
Mr W A Isdale, Member of the Land Court
ORDERS: 1. Grant leave to adduce further evidence;
2. Dismiss appeal number LAC001-17, and
3. Allow appeal number LAC002-17 and order that
BMA pay the costs thrown away by reason of its
having leave to file the amended defence dated
30 November 2016, such costs not to be assessed until
after the trial and determination of Proceeding
MRA1332-08;
4. Grant leave to the parties to make written submissions
as to costs of the appeal within 14 days of the delivery
of this judgment.
-- 1 of 24 --
2
CATCHWORDS: APPEAL AND NEW TRIAL – APPEAL – GENERAL
PRINCIPLES – INTERFERENCE WITH DISCRETION OF
COURT BELOW – IN GENERAL – WRONG PRINCIPLE
– PARTICULAR CASES – DECISION AFFECTING
PLEADINGS – where the respondents’ amended defence
was filed 26 days after the date ordered – where the primary
judge allowed the respondents’ application for an extension
of time to file the amended defence – where the primary
judge refused the appellant’s application to strike out the
amendments to the defence – whether the primary judge
acted on a wrong principle or misapplied the correct principle
– whether the primary judge failed to have any or adequate
regard to material considerations – whether the primary judge
made some error in exercising the discretion
PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – COSTS – APPEALS AS TO
COSTS – RELEVANT PRINCIPLES – WHERE WRONG
EXERCISE OF DISCRETION – where the respondents’
amended defence was filed 26 days after the date ordered –
where the primary judge allowed the respondents’ application
for an extension of time to file the amended defence – where
the primary judge accepted that the appellant would suffer
wasted costs in consequence of the grant of an extension of
time – where the primary judge reserved the question of the
appellant’s wasted costs until after the trial – whether the
primary judge made some error in exercising the discretion
Mineral Resources Act 1989 (Qld), s 281, s 334ZJ
Mineral Resources (Peak Downs Mine) Amendment Act 2008
(Qld)
Uniform Civil Procedure Rules 1999 (Qld), r 171
Adam P Brown Male Fashions Pty Ltd v Philip Morris Inc
(1981) 148 CLR 170, applied
Aon Risk Services Australia Ltd v Australian National
University (2009) 239 CLR 175, applied
General Steel Industries Inc v Commissioner for Railways
(NSW) (1964) 112 CLR 125, cited
House v The King (1936) 55 CLR 499, applied
McDowall v Reynolds [2015] QLC 32, cited
Wills v Minerva Coal Pty Ltd (No 2) (1998) 19 QLCR 297,
cited
Xstrata Coal Qld Pty Ltd & Ors v Keys & Ors (2013) 34
QLCR 186, cited
COUNSEL: G J Gibson QC, with J K Chapple, for the appellant
S Doyle QC, with A Stumer, for the respondents
SOLICITORS: Holding Redlich for the appellant
Allens for the respondents
-- 2 of 24 --
3
[1] DALTON J: This is an appeal from orders made by the President of the Land Court on
17 February 2017. Her orders extended time for filing an amended defence; refused an
application to strike out the amendments to the defence; vacated trial dates and listed
the matter for directions. There is also a separate appeal against the order which the
President made reserving costs thrown away by the amendments to the defence. The
decisions below were procedural and involved exercising discretion in a matter which
the President is supervising as it proceeds through the Land Court. The difficulty in
successfully challenging such a decision is considerable.1 The principles in Aon Risk
Services Australia Ltd v Australian National University2 apply, and were accepted as
applying, by the President, below.
[2] The President described the litigation in the Land Court as follows:
“[7] Cherwell Creek claims compensation from [the respondent companies
(BMA)] under s 334ZJ of the Mineral Resources Act 1989 (‘MRA’).
That section sits in a special purpose part of the MRA introduced by
what the parties refer to as the Amending Act,3 which came in to force
in May 2008.
[8] The Amending Act brought to an end what was then a lengthy dispute
between the parties about their eligibility for mining and associated
rights over land owned by BMA near its Peak Downs Mine.
[9] Before the Amending Act commenced, Cherwell Creek and BMA held
overlapping and apparently inconsistent resource tenures. Cherwell
Creek held an exploration permit (EPC545). It had also applied for a
mineral development licence over the land (MDLA364). BMA held a
special lease over the same area. The Amending Act determined the
matter in BMA’s favour, while providing Cherwell Creek a limited
opportunity to claim compensation from BMA for its loss of
opportunity to commercialise the MDLA364 coal resource.
[10] To make out its claim, Cherwell Creek must persuade the Court that
compensation is payable. In deciding whether it is, and in what
amount, the Court must consider the likelihood of a hypothetical
proposition: that, but for the Amending Act, Cherwell Creek would
have been able to commercialise the MDLA364 coal resource, having
regard to factors including:
(a) the likely extent and quality of the MDLA364 coal resource;
(b) the likely mineability of the MDLA364 coal resource;
(c) the likely market for any coal mined from the MDLA364 coal
resource;
(d) the likely life of a mine for the MDLA364 coal resource;
(e) the likely coal revenue generated from the MDLA364 coal resource;
1 House v The King (1936) 55 CLR 499; Adam P Brown Male Fashions Pty Ltd v Philip Morris Inc (1981)
148 CLR 170.
2 (2009) 239 CLR 175.
3 Mineral Resources (Peak Downs Mine) Amendment Act 2008.
-- 3 of 24 --
4
(f) the likely coal revenue generation costs;
(g) the likelihood of a mining lease, appropriate for Cherwell Creek to
commercialise the MDLA364 coal resource, being granted under this
Act;
Note—
See sections 269(4) and 271 for matters that the Land Court and Minister
take into account in dealing with an application for the grant of a mining
lease.
(h) any other relevant matter.4
…”
Progress of this Proceeding
[3] The President notes at paragraph [12] of her judgment below that the parties agreed
from the outset that there would be pleadings in this proceeding. Despite the fact that
neither the Land Court Act 2000, Rules, or Practice Directions make any provision for
pleadings, it seems to me impossible to conduct a case of the complexity of this case
without pleadings. Much of the background difficulty in supervising this case results
from the fact that, even though the parties have proceeded on the basis that there would
be pleadings, in reality it has been the expert reports which have identified, and
continue to identify, the issues and in effect drive the litigation.
[4] The originating application in this proceeding is dated 8 August 2008. It made a claim
for compensation in an amount to be determined by the Land Court pursuant to (then)
s 722G of the Mineral Resources Act 1989 (the Act). Annexed to this claim were nine
pages said to contain the “facts, circumstances and other relevant matters” on which the
application was based. Compared to a pleading, this annexure was sketchy.
[5] The annexure to the claim pleaded the fact of the Amending Act and that but for it, “the
applicant would have applied for and been issued with a mining lease in respect of the
coal contained within MDLA364.” It continued that because of the Amending Act,
Cherwell Creek lost its opportunity to commercialise the MDLA364 coal resource by
mining and selling the coal or, alternatively, by selling its interest in the tenement. The
rest of the annexure was largely concerned with describing the scope and extent of the
coal resource Cherwell Creek contended was contained in MDLA364 and calculating
the likely price it said it would have obtained for that coal. It was said that the cost of
producing and selling the coal would be the subject of expert evidence, but would have
been approximately $75 per tonne. A list of the types of expenses necessary to produce
and sell the coal was provided.
[6] The scheme of the Act is that someone with ambitions to own a mining lease must first
hold an exploration permit. By s 179 of the Act it is necessary to hold an exploration
permit in order to be granted a mineral development licence. The holder of a mineral
development licence can be granted a mining lease. Cherwell Creek’s claim for
4 Section 334ZJ(5)(a)-(h) of the Mineral Resources Act 1989.
-- 4 of 24 --
5
compensation is premised on the fact that it held an exploration permit and would have
been granted first a mineral development licence, and then a mining lease.
[7] In the original annexure, it was pleaded that Cherwell Creek would have complied with
all conditions of the mineral development licence and all requirements of the Act in
order to obtain a mining lease. That is expanded somewhat at paragraphs 15 and 16 of
the annexure wherein it is said that Cherwell Creek would have been granted the mining
lease inter alia because there were no “applications for or holders of any exploration
permits or mineral development licences over the area comprised within the mining
lease”; the operations for the mining lease would have “conformed with sound land use
management”, and the mining lease was “an appropriate use of the land”. These
factors, it is said, would have caused the Land Court to have recommended to the
Minister that the application for the mining lease be granted, and that the Minister
would have recommended to the Governor in Council that the mining lease be granted.
[8] A defence was filed responding to Annexure A on 13 October 2008. BMA disputed
that Cherwell Creek would have been granted MDLA364 and said that its mineral
development licence application had been rejected by the Minister on 15 April 2008.
Separately, it pled that EPC545 had not been validly granted in 1994, and not been
validly renewed in 2003, so that no mineral development licence or mining lease could,
or would, have been granted to the applicant. In support of this plea it said that the
1994 grant of EPC545 was invalid either because the delegate who granted it did not
exercise his power pursuant to the instrument of delegation, or alternatively because the
delegate ought to have referred the application for grant of EPC545 to the Director
General or Minister for various reasons which are particularised. It followed that there
was no power to renew EPC545 in 2003, and consequently there was no power to grant
MDLA364. Alternatively it followed that the Land Court, considering these matters,
would not have recommended to the Minister that a mining lease be granted; nor would
the Minister have granted such a lease.
[9] Particulars of both Annexure A and the defence were delivered in 2009 and an amended
defence was filed on 28 August 2009. There was a reply and amended reply filed in
2009 and 2010. None of these documents touched on matters relevant to the issues
raised on this appeal. An amended Annexure A was delivered on 17 December 2012
pursuant to directions. The amendments concerned the quantum of compensation.
[10] Cherwell Creek filed a second amended Annexure A on 18 December 2015. This
document essentially re-pleaded the claim in its entirety and is in the form of a
conventional pleading. A fourth pleading was delivered on 6 May 2016. The
amendments in this version are less substantial and relate only to the calculation of the
quantum of the claim.
[11] The parties, and the Member managing this case, accepted that pleadings should be
amended after expert reports were obtained. This was accepted by the appellant’s
counsel below – t 1-44. Indeed it is clear from the transcripts of the review hearings
that the views of the experts were driving the case, rather than a conventional approach
in which expert opinion is sought within a framework established by pleadings.5
5 For example, Transcript 28 November 2014, tt 1-7, 1-8.
-- 5 of 24 --
6
[12] The Amending Act provided that if Cherwell Creek was to make an application for
compensation it was to be made within three months, and this might be some valid
reason why Annexure A, as initially filed, was sketchy. However it does not explain the
delay between that time and December 2015. The fact is that it was not until 18
December 2015 that Cherwell Creek filed a pleading which articulated its claim in an
appropriately detailed manner. The amended defence filed on 30 November 2016
contains the note on its first page that it entirely replaces the amended defence filed on
28 August 2009. Having regard to the fact that the second amended Annexure A filed
on 18 December 2015 entirely re-pleads the preceding two versions of Annexure A, this
is not surprising.
[13] Most unusually, in these circumstances, the Member supervising this matter made an
order on 5 December 2014 setting it down for trial. That is, well before the parties
obtained their expert reports and well before the issues were properly articulated by
Cherwell Creek in its pleading. The trial was set for four months starting in March
2017. The trial date allocation was prompted by the Member attempting to case manage
the matter, not the parties.6 At the time trial dates were allocated, the parties were not
able to say how long the trial would take, or when they would be ready for trial.7
[14] Several review hearings later, on 19 April 2016, a timetable was set to squeeze all
remaining interlocutory steps into the time remaining before trial. The Member, and
both parties, expressed serious reservations about whether these steps could be
accommodated in the time available or whether the trial dates ought be vacated.8 The
directions made on 19 April 2016 included: applicant to file and serve a further
amended pleading by 6 May 2016; respondent to file and serve its expert reports as to
the resource contained in MDLA364 by 28 October 2016, and respondent to file and
serve an amended defence by 4 November 2016. There was discussion about whether
amendments to the defence would be substantial, and clearly that was a possibility.9
BMA filed an amended defence on 30 November 2016. This was 26 days after the date
provided by the directions.
[15] Cherwell Creek’s protestations that the amendments to the defence of 30 November
2016 ought not to be allowed because they were late must be viewed in this context.
[16] The other important context to Cherwell Creek’s complaints on appeal is that Cherwell
Creek’s position, before the President below, was that even if BMA was not given leave
to file its amended defence, the trial could not proceed on the dates allocated to it, and
could not proceed until the second half of 2017. It was not the President’s allowing the
amended defence to be filed that meant that the trial dates had to be vacated – see [79]
of the judgment below, and see Appeal Transcript t 1-40. Indeed, when one looks at the
draft order submitted by Cherwell Creek below, one can see the considerable work
which was needed before this matter could be tried, all of which was quite independent
of BMA amending its defence.
6 Transcript 28 November 2014, tt 1-6, 1-8, 1-10.
7 Transcript 28 November 2014, t 1-9.
8 Transcript hearing 19 April 2016, tt 1-3, 1-4, 1-5, 1-14.
9 Transcript hearing 19 April 2016, t 1-22.
-- 6 of 24 --
7
Extension of Time to File Amended Defence
[17] Just in relation to this ground of appeal, Cherwell Creek made 26 separate complaints as
to the exercise of the President’s discretion. I deal with these in turn, by reference to
paragraph 4 of the Notice of Appeal.
[18] Paragraphs 4(h)(i) and (ii) complain that the President did not consider “adequately or at
all” that the amended defence was due on 4 November 2016 and not filed on that date.
[19] The complaint that the President did not consider this at all should not have been made.
She plainly did; paragraphs [11]-[22] of her judgment are devoted to considering
whether or not the direction to deliver the defence could be varied, or whether BMA
needed to seek leave because it had not complied with the directions made on 19 April
2016. Later in the judgment when considering whether or not the amendments delayed
a fair trial of the proceedings, the President again turned to that issue – [70]ff.
[20] Her Honour considered the delay in complying with the direction of 19 April 2016, and
concluded, against BMA, that it could have “at least” flagged the issues it raised by way
of amended defence earlier than the date upon which it did deliver the amended
defence. She considered the evidence put before her by BMA as to when it recognised
the issues which are the subject of the amendments, and the steps it then took to
investigate and articulate them. She described the delay as unfortunate. Nonetheless
she considered it out-weighed by other matters, such as the fact that, with the consent of
both parties, the case had progressed through the Land Court on the basis that expert
reports would precede pleadings, and the unusual approach taken to allocating trial
dates. She considered the difficulties inherent in the timetable set on 19 April 2016
which allowed an amended defence to be filed only four months before a trial, in the
context of litigation which had been running for six years before that. She also
considered the fact that it would be necessary, whether or not amendments were
allowed, to vacate the trial dates.
[21] Having regard to all these matters, there is no error demonstrated in terms of paragraph
4(h) of the Notice of Appeal. Her Honour weighed relevant matters appropriately and
was clearly well aware that the delay in filing the amended defence took it outside the
period limited by directions in April 2016.
[22] Nor can it be said in my view that there is anything in the point raised at paragraph 4(j)
of the Notice of Appeal in which it is alleged that the President gave weight or undue
weight to the fact that the amended defence was only 26 days late, according to the
19 April 2016 direction. Indeed that ground of appeal sits uneasily not only with the
substance of her Honour’s reasons, but with the statements of counsel for Cherwell
Creek on appeal:
“It has not been Cherwell Creek’s intention to prevent BMA filing a – an
amended defence, albeit late. The 26 days is of no particular consequence
in itself.” – Appeal Transcript 1-5.
[23] At paragraph 4(k) of the Notice of Appeal, it is said that the President failed to
recognise that by reason of BMA having missed the 4 November 2016 date for filing an
-- 7 of 24 --
8
amended defence, her discretion was at large and she could consider all the
consequences and implications of the respondents having missed that date, not just
consequences which were confined to a delay of 26 days. In my view it is perfectly
plain in the discussion under the heading, “Do the Amendments Delay the Fair Trial of
the Proceedings?” in the judgment below, that the President did consider the question of
delay at large, and in particular considered the very relevant matter of how the
amendments would delay any trial of the matter.
[24] Grounds of appeal at paragraphs 4(l), (m), (n) and (o) complain that the President failed
to have regard to the fact that, were the amendments to the defence not allowed, a trial
could have taken place from July 2017 but, if the amendments were allowed, a trial was
likely to be delayed by a period of eight, or alternatively, 13 months. It is said that the
President failed to consider this, and the potential financial or other consequences to
Cherwell Creek of such a delay. At paragraph [79] of the judgment below the President
said:
“One final aspect of delay should be mentioned. The parties were asked to
propose directions for the further conduct of the matter, dealing,
alternatively, with the Amended Defence being allowed, or not. Cherwell
Creek’s proposed directions, assuming BMA could not file its Amended
Defence, assume the trial cannot proceed until the second half of 2017. The
trial could not have proceeded as listed and the delay attributable to the
amendments is some five months less than the 13 months Cherwell Creek
asserted.”
[25] The President clearly understood that allowing the amendments to the defence would
result in eight months’ delay of the trial, on Cherwell Creek’s view of things (as
revealed in its proposed directions).
[26] Her Honour then went on to consider, at paragraphs [81]-[84] below, the financial cost
of Cherwell Creek’s responding to the amendments which she assessed as
“considerable” and “substantial”. The President understood that this substantial cost
would include new expenditure but also be attributable to wasted expenditure. Quite
correctly she worked on the basis that the exact costs would be difficult to determine
until after a trial. Clearly enough the President also understood that payment of costs
did not necessarily entitle a party to procedural relief – [80] – that is, matters other than
costs are relevant to these questions. At [87]-[88] her Honour balanced the “prejudice
to Cherwell Creek by delay of the trial and additional or wasted costs” against prejudice
to BMA if the real issues in dispute were not determined at a trial. She came to the
conclusion that “it would inappropriate to hold out BMA from pleading matters which
are central to the claim. The prejudice to Cherwell Creek must be viewed in the context
of the proceedings as a whole and can be somewhat ameliorated by orders about costs.”
In my view, error is not shown as alleged at grounds 4(l)-(o) of the Notice of Appeal.
[27] Similarly, paragraphs 4(s), (t) and (x) complain that the President did not have “any or
adequate regard” to the substantial prejudice to Cherwell Creek in terms of costs and
consequences in terms of the future conduct of the proceeding if the amendments were
allowed. Again it is very difficult to see how lawyers could properly complain that the
-- 8 of 24 --
9
President did not have any regard to these matters. Particularly when paragraph 49 of
the written submissions filed on this appeal by Cherwell Creek says:
“Her Honour thereby recognised that Cherwell Creek would be prejudiced
by an extension of time to raise the Caval Ridge Mine allegations. Her
description, ‘substantial’ was apt to describe both the prejudice resulting to
Cherwell Creek from the additional and wasted expenditure, and from the
lengthy further delay to the trial of the proceeding.”
[28] That paragraph was the concluding paragraph in a section of the submissions which
acknowledged that her Honour noted and accepted Cherwell Creek’s argument about
incurring new costs; wasting past costs, and delay in a trial as consequences were the
amended defence allowed.
[29] Turning to the alternative contention that her Honour did not give adequate weight to
these matters, no error is demonstrated. As discussed above, her Honour appropriately
recognised and weighed these matters in an orthodox exercise of discretion.
[30] Associated with these grounds of appeal are those at paragraphs 4(y) and (z): that the
President failed to recognise that a costs order would not necessarily address all the
prejudice likely to be suffered by Cherwell Creek, and erred in concluding that BMA’s
assertion that it was “good for any costs order” was a consideration of significance in
the exercise of her discretion.
[31] As to the first of these complaints, nothing was raised either before the President below,
or on appeal, other than those matters already discussed above – wasted costs, extra
costs and delay in achieving a trial date – as being prejudice suffered by Cherwell Creek
as a consequence of allowing the amendments. The types of prejudice identified below,
and on appeal, were the types of prejudice which can be compensated by costs orders.
While her Honour recognised that a party was not entitled to procedural relief merely
upon its promise to pay costs – [80] of the judgment below – the ability of BMA to
meet a costs order was, as the President recognised, a weighty consideration in the
exercise of her discretion on the facts of this case. There is no error demonstrated.
[32] At paragraphs 4(f) and (g) of the Notice of Appeal, it was contended that the President
erred because she approached the exercise of her discretion on the basis that the April
order giving leave to amend did not constrain the nature of the amendments, or
alternatively, that she gave undue weight to this. The April order did not constrain the
nature of the amendments, and her Honour was right to approach the matter that way.
In the context where both parties had proceeded, and case management had proceeded,
on the basis that the parties’ cases could not be fully or finally articulated until expert
reports were received, it was a necessary corollary that substantial amendments might
be made pursuant to the leave granted in April. There is no error demonstrated.
[33] To understand the rest of the complaints about the President’s decision to allow BMA to
file its amended defence, it is necessary to understand more about three issues raised by
the amended defence: the JR Issue, the Prospective Use Issue, and the Special Loss
Issue.
-- 9 of 24 --
10
[34] The JR Issue. Cherwell Creek’s application for compensation has at all times
contained an allegation that it would have applied for, and been issued with, a mining
lease. In the third and fourth versions of the pleading, it pleads in a more detailed way
how it says the grant of a mining lease would have come about. This series of
allegations begins at paragraph 4(a) of the pleading with the allegation that in about
May 2008 Cherwell Creek would have been granted mineral development licence 364.
[35] The amended defence contains pleas similar to those in the original defence that
MDLA364 would have been rejected by the Minister, and that EPC545 was not validly
granted in 1994, and thus not validly renewed in 2003. The consequence is pleaded to
be that without a valid EPC, no mineral development licence could, or would, have been
granted to Cherwell Creek. The particulars of why the grant of EPC545 in 1994, and
renewal in 2003, were invalid are similar to those which were originally pleaded
(flawed delegation process; unusual circumstances or sensitive political nature requiring
referral to Director General or Minister).
[36] In addition, the amended defence pleads that in 2003 BMA challenged the grant of
EPC545 in judicial review proceedings in the Supreme Court. It is pleaded that, were it
not for the Amending Act, BMA would have pursued those proceedings and obtained
an order quashing or setting aside the renewal of EPC545. As the President concluded
below, the effect of this change to the pleading is less substantial than it might at first
appear, for BMA has undertaken to confine its case as to the judicial review
proceedings to reliance upon the same matters raised elsewhere in the Land Court
proceedings, ie., the invalid delegation and unusual circumstances or sensitive political
nature mentioned above – see [27] of the President’s reasons below.
[37] The Prospective Use Issue. The second of the contentious amendments is raised in
defence to the pleaded proposition that Cherwell Creek would have been granted a
mining lease. From the initial version of its claim in Annexure A, Cherwell Creek has
always pleaded that it would have been granted a mining lease because the Land Court
would have recommended to the Minister that a mining lease be granted, and the
Minister would have recommended this to the Governor in Council. That remains
Cherwell Creek’s case – see paragraphs 6, 7 and 8 of the current pleading. However, it
is only since the pleading delivered on 18 December 2015 that the hypothetical events
which Cherwell Creek says would have occurred between its being granted a mineral
development licence and the Land Court’s making a recommendation to the Minister
have been pleaded in any detail – see paragraphs 4 and 5 of the current pleading.
[38] BMA denies that a mining lease would have been granted by the Court or the Minister
on various grounds, one of which is that Cherwell Creek would not have been able to
demonstrate the economic viability of a mine in respect of the coal lying under the area
of MDLA364. The reason is pleaded to be that by May 2008, BMA had identified the
area of MDLA364 as the best place for the infrastructure for a proposed mine of its
own: Caval Ridge Mine. It is pleaded that this infrastructure was the most appropriate
and economic use for that land because, if BMA did not use the land contained in
MDLA364 for the infrastructure, it would have had to place the infrastructure on
Mining Lease 1775, thereby sterilising over 52 million tonnes of coking coal, which in
turn would have meant a loss of royalties to the State approaching an amount of $400
million.
-- 10 of 24 --
11
[39] The Special Loss Issue. The third area of contention raised by the amended defence is
conceptually related to the Prospective Use Issue. The pleading is that any mining lease
over the area comprised in MDLA364 would have extended over BMA’s freehold land.
The pleading proceeds to the effect that therefore, no mining lease would have been
granted to Cherwell Creek without an amount of compensation being paid to BMA as
the owner of the freehold. BMA pleads that the compensation would have included its
loss of the use of the land for infrastructure for the Caval Ridge Mine and consequent
sterilisation of coal resource in Mining Lease 1775. It is said that the total
compensation would have exceeded $180 million and thus rendered any mining lease
operated by Cherwell Creek on the area of MDLA364 uneconomic.
[40] I return to the remaining subparagraphs of paragraph 4 of the Notice of Appeal. Some
of these concern the President’s appreciation of the merits of the Prospective Use Issue
and the Special Loss Issue. Subparagraphs (a) and (b) contend that the President erred
in holding these issues were reasonably arguable (without considering Cherwell Creek’s
submissions to the contrary), and erred because she exercised her discretion on the basis
that, unless she found these issues were “self-evidently groundless”, their merits were
irrelevant. Subparagraphs (c) and (d) are not expressed to be in the alternative to
subparagraphs (a) and (b), but they must be, for they complain that the President
exercised her discretion on the basis of a conclusion that the amendments raised
important issues, and that she gave undue weight to that conclusion and specifically that
she thought the conclusion sufficient to outweigh “other countervailing considerations”.
In that same vein, it was contended at subparagraph (r), that the President failed to have
any, or any adequate, regard to the deficiencies which Cherwell Creek identified in
BMA’s expert report supporting the Special Loss Issue. This became relevant to the
merits of the claim pleaded, because the report is pleaded to contain the particulars of
the calculation of loss.
[41] It may be accepted that the merits of any case sought to be made by amendment are
relevant to a consideration of whether that amendment ought be allowed. On BMA’s
application before the President for an extension of time in which to amend its defence,
Cherwell Creek cross-applied to strike out the amendments which BMA sought to make
to its defence. The merits of the contentious amendments are considered by the
President in this context – [44]-[59] below. It was in this context that her Honour found
the contentious amendments were not unarguable and therefore ought not be struck out
– [59] below. This conclusion preceded her Honour’s weighing of discretionary matters
as to whether or not to allow the amendments, and I think it is clear that the President’s
conclusions about the merits of the issues raised by the amendments were part of her
discretionary exercise of judgment to extend time for the filing of the defence. At
paragraph [86] of the judgment below she refers to the importance of ensuring that the
real issues in the case are decided; at paragraph [89] of the judgment below she
describes the Prospective Use Issue as “fundamental” to the matters which the Court
will consider at trial, and at [90] she describes the Special Loss Issue as relating “to an
important factor for the claim”.
[42] It ought not to have been alleged that the President did not have any regard to the
deficiencies identified by Cherwell Creek in the expert report relied on by BMA as
supporting the Special Loss Issue. The President clearly did have regard to that set of
arguments – paragraphs [48]-[56] of the judgment below.
-- 11 of 24 --
12
[43] In my view, her Honour did not err in having regard to the merits of the claim sought to
be raised by the contentious amendments. I note that the written submissions filed on
behalf of the appellant, which extended well beyond the regulation 10 pages, did not
agitate this point as part of the argument that the President erred in allowing the
amendment. Nor was this pursued orally. Arguments about the merits were confined to
the strike out application. The same approach was taken below; paragraphs 88-107 of
written submissions, and t 1-65ff in oral argument. That is, neither in this Court, or
below, was there an argument that even if the new contentions were “not unarguable”,
and so should not be struck out, they were sufficiently lacking in merit that leave should
not be granted to amend to add them. Indeed, paragraph 37(h) of the appellant’s written
submissions before the President reads to the effect that in considering whether to allow
the amendments the President should consider whether they “raise an arguable case”.
[44] The points of law regarding the interpretation of the Act, and the case law dealing with
that Act, were discussed in the judgment below. Her Honour did not attempt to
determine these points of law but, having found that they were not unarguable, took the
view that they were matters for trial. With respect, I wholeheartedly agree. At the trial
the facts of the matter will be elucidated. The opinions of experts will have been
explored and tested and it is far more appropriate that these points of law be determined
then. They are by no means straightforward, and may well rise or fall upon factual
findings or expert evidence.
[45] At paragraph 4(e) of the Notice of Appeal it was contended that the President erred in
finding that Cherwell Creek was not taken by surprise, or ought not to have been taken
by surprise, by the inclusion of the Prospective Use Issue and the Special Loss Issue in
the amended defence. Paragraphs 5 and 6 of the Notice of Appeal in effect particularise
this complaint.
[46] BMA’s original defence, filed on 13 October 2008, contended that the Minister “had
accepted his Department’s recommendations and had rejected [Cherwell Creek’s]
application” – paragraph 2(c). The basis for this allegation was pleaded to be the
statements made by the Minister in the Second Reading Speech which introduced the
Amending Act. At paragraph 3(b)(v) of the original defence it was pleaded, “further,
the Minister would not have granted a mining lease in whole or in part to the applicant.”
Particulars of that allegation were provided on 24 April 2009. They were to the effect
that the Minister would have considered each of the matters in s 271(1) of the Act and
“otherwise, the best particulars they can give until the completion of interlocutory steps
are that it is to be inferred from the Minister’s Second Reading Speech that a Mining
Lease would not have been granted in whole or in part”.
[47] The Second Reading Speech was made in May 2008. It contained the following:
“…
The Peak Downs Coal Mine is a premium coking coal mine, producing nine
million tonnes of coal per annum. The total coal reserve size is 1,915
million tonnes. The value of its exports last financial year was $1.28 billion
and its coal royalty payments were $86.8 million. As at June 2007, the mine
had a work force of 1,085 employees and contractors.
-- 12 of 24 --
13
…
BMA is proposing a major expansion of the Peak Downs Mine and the
surrounding area. It is investigating the feasibility of developing and
constructing a new Greenfield mine in the northern part of Mining Lease
1775, to be known as the Caval Ridge Mine.
The Caval Ridge Mine could result in over 1200 construction-based jobs
and 550 operational jobs and the construction of over $1 billion worth of
infrastructure.
It might also result in up to a further 12 million tonnes of coal production
per annum. To put this into context, 12 million tonnes per annum is more
than the current capacity of the Peak Downs Mine (which is nine million)
and more than the combined annual production capabilities of the
Millennium, Poitrel and Isaac Plains Mines.
…
The Government accepts that the land currently held by Cherwell Creek
under Exploration Permit for Coal 545 and its application for Mineral
Development License 364 is the optimal location for the infrastructure
needed for the Caval Ridge Mine.
If BMA is unable to locate its expansion infrastructure off the mining lease
and in this particular area, most of which I understand it owns freehold, the
infrastructure would need to be placed within Mining Lease 1775. This
would be problematic firstly because operating costs would generally be
significantly higher because of the geophysical features of the land.
Secondly, it would require the placement of infrastructure on top of reserves
of premium hard coking coal. BMA has suggested that approximately 52.5
million tonnes of coking coal would be sterilised by this, which could have
a revenue value of approximately $2.2 billion and a royalty value to the
State of approximately $146 million.
Thirdly, while BMA might be able to avoid sterilising some coal by
progressively relocating its infrastructure, this would further increase
operating costs and lastly, the placement of infrastructure on the eastern
boundary would move the infrastructure closer to the Moranbah Township,
which might require significant steps to be taken (and higher costs incurred)
to reduce the noise, dust, vibration and visual impact on the local
community and township.
…
In an attempt to resolve the dispute, the Department of Mines and Energy
facilitated a mediation between the parties between February and September
2007. The mediation was unsuccessful. There appears to be no prospect of
BMA and Cherwell Creek resolving their dispute on a commercial basis and
it is for this reason that the Government has had to step in and make these
decisions in the public interest.
Since the mediation, Cherwell Creek’s outstanding applications and all
submissions received from both parties in relation to those submissions have
-- 13 of 24 --
14
been reviewed by a small multi-disciplinary team within the Department of
Mines and Energy, comprising an experienced geologist, a coal mining
engineer and a former senior mining registrar.
On the basis of that review, my Department has recommended to me that all
of Cherwell Creek’s applications be rejected for the following reasons.
Cherwell Creek has had 131/2 years to prove up and develop any coal
resource within the area of its exploration permit, but has been unable to do
so.
In the past 131/2 years, Cherwell Creek has only drilled in the reporting
years 1994, 2004, 2005 and possibly 2007. While my Department is aware
that Cherwell Creek proposed to drill in 2007, it has not yet had to report
back to the Department and it is not known whether it did drill in 2007.
As far as the Department is currently aware, Cherwell Creek has only drilled
in the area subject to the application for Mineral Development License 364.
This means that Cherwell Creek applied for Mineral Development License
366 over an area it had never drilled.
In the absence of any sizeable, economically viable coal resource, the most
appropriate and economic use of the land subject to the application for
Mineral Development License 366 is for the Peak Downs Mine’s current
infrastructure.
Cherwell Creek has defined only a relatively small coal resource in the area
subject to its application for Mineral Development License 364 which is at a
very preliminary stage of assessment and which it is considered might only
be marginally viable.
In the absence of any sizeable, economically viable coal resource, the most
appropriate and economic use of the land subject to the application for
Mineral Development License 364 is for infrastructure to support the Caval
Ridge Mine.
I have accepted my Department’s recommendations to reject all four of
Cherwell Creek’s current outstanding applications.
…
This will enable BMA to secure that land for its infrastructure. This is
arguably what was always intended when the Special Lease was granted
back in the 1970s.
…” (my underlining)
[48] The current contentious amendments are to the effect that, had Cherwell Creek applied
for a mining lease, the Land Court and the Minister would not have granted it because
doing so would mean that the infrastructure for the Caval Ridge Mine would need to be
placed within BMA’s Mining Lease 1775, thus sterilising coal; causing loss of profit
and royalties, and delaying production at the Caval Ridge Mine. In effect, what was
incorporated by reference to the Second Reading Speech in the particulars of 24 April
2009 is now, by virtue of the amendments, express in the pleading. In my view the
-- 14 of 24 --
15
President was correct in concluding that Cherwell Creek was not taken by surprise by
this inclusion – paragraph [34] of the judgment below.
[49] While the Special Loss Issue is associated with the Prospective Use Issue, it had never
been raised in the pleadings by Cherwell Creek or BMA before the contentious
amendments to the defence of 30 November 2016. Nonetheless, the issue was not new
to either party. BMA had raised it in opposition to both the renewal of EPC545 and
Cherwell Creek’s application for MDL364.
[50] Against that background, it is somewhat surprising that both parties overlooked the
issue as far as the pleadings in this matter are concerned. Part of Cherwell Creek’s
pleading is that it would have complied with the requirements of the Act for the grant of
a mining lease. Quite some detail of what that might include is pleaded, but not the
payment of compensation to BMA. Of course, it was not in Cherwell Creek’s interest
to raise the Special Loss Issue in this matter. However, payment of compensation to the
land owner is one of the matters the Act requires as a condition of granting a mine lease,
and Cherwell Creek have known since 200610 that BMA asserts that its losses arising
from any grant of MDLA364 included the need to locate infrastructure on ML1775 and
consequently to sterilise part of its own coal resource. One of Cherwell Creek’s expert
reports, that from Mr Knight, does raise the issue that Cherwell Creek would be
required to compensate BMA if granted a mining lease over the area of MDLA364. Mr
Knight says that compensation should be assessed on the basis that the best use of the
land was as pasture for cattle. This report was given to BMA in 2015 even though
Cherwell Creek’s pleadings still do not plead that to obtain a mining lease over the area
of MDLA364 it would have paid compensation to the freehold owner, BMA.
[51] Further, the Special Loss Issue, or its mirror image, has emerged in Cherwell Creek’s
case, at least in the expert report of Dr Rudenno.11 He values MDLA364 at $132
million. He relies on comparative sales, but as a check, relies partly upon the fact that
BMA claimed a special value to it in the area of EPC545 when opposing Cherwell
Creek’s renewal of that permit in 2006. As discussed in Dr Rudenno’s report, BMA’s
assessment of loss at that stage was $180 million, based upon its inability to use the area
for infrastructure and the sterilisation of its own coal as a consequence.
[52] It is difficult to understand why BMA had not raised the matter before 30 November
2016. It apparently did not occur to the lawyers or those instructing them. It was not
until one of their experts brought the matter to the attention of the lawyers that the
matter was articulated in the pleading. The solicitor acting for BMA swore to this
having been the case.12 The parties had proceeded on the basis that pleadings would not
be finalised until expert reports had been obtained. Directions made on 19 April 2016
for expert reports and pleadings put these steps very close before the trial dates. It is
obvious, with hindsight, how this situation has arisen.
10 The issue of compensation was raised, and quantified at $180 million, in BMA’s objection to Cherwell Creek
being granted EPC545 in 2006. Cherwell Creek’s solicitors also had notice of the claim in a letter copied to
them in 2007. These were exhibits 4 and 5 before the President.
11 15 February 2016.
12 Affidavit of Alana Maree Petty, 30 January 2017, paragraphs 13-25.
-- 15 of 24 --
16
[53] The President was cognisant of the fact that the Special Loss Issue was relevant to
issues which were already raised in the case: Cherwell Creek’s willingness to comply
with the provisions of the Act about paying compensation in order to obtain a mining
lease, and (on Dr Rudenno’s report) the fair market value for the coal resource in
MDL364 – [36], [43], [65] and [66] below.
[54] These matters were considered and weighed by the President in considering the
submission that the Special Loss Issue had taken Cherwell Creek by surprise. In fact,
the President considered that the articulation of the issue in the Land Court proceedings
did take Cherwell Creek by surprise – [43] below. However, weighing this matter
against the explanation for the late pleading; the likelihood that such an issue would
emerge because of the way the case had proceeded and been managed, and the close
connection between this issue and other issues in the litigation, the President concluded
that the fact that Cherwell Creek was taken by surprise was not determinative of the
outcome of the application to amend. There is no error demonstrated; what is evident in
the judgment below is a conventional and, with respect, perfectly sound exercise of
discretion.
[55] At paragraph 4(v) of the Notice of Appeal it was contended by Cherwell Creek that
Dr Rudenno’s report did not raise the Special Loss Issue and was not relevant to the
President’s consideration. The President did not find that Dr Rudenno’s report did raise
the Special Loss Issue, but found that it raised an issue closely connected with it.
[56] It is further asserted at paragraph 4(v)(ii) of the Notice of Appeal that the President’s
decision was based on a notion that BMA ought not be held out from raising the Special
Loss Issue in response to Dr Rudenno’s report. This mischaracterises the reasoning in
the judgment below. The President properly recognises the close connection between
part of Dr Rudenno’s report and the Special Loss Issue. There is nothing in paragraph
4(v) of the grounds of appeal.
[57] Cherwell Creek complains at paragraph 4(i) of the Notice of Appeal that the President
erred in finding BMA’s explanation for the delay in pleading the JR Issue, Prospective
Use Issue and Special Loss Issue was adequate. The explanation given for raising the
Special Loss Issue late has already been discussed – [52] above. I am not sure that the
President did find the explanation adequate; I do not see this expressly in her judgment.
In fact at [64] the President is critical of BMA for failing to identify and plead the
Special Loss Issue earlier. She is generally critical of BMA’s delay – eg., [72].
However, BMA swore to an explanation which was not challenged, and was accepted as
true,13 on the application before the President, and which was the type of unfortunate
result which the progress of the matter, and the directions made in it were likely to
produce.
[58] Cherwell Creek agitates the point that BMA knew of the Special Loss Issue
independently of its experts. That is, to say that the parties agreed that pleadings would
follow expert reports, does not explain why BMA did not raise the matter earlier; it did
not need its expert to tell it about the point; it already knew. This is correct, but needs
to be seen in the context of the matters discussed at [50] and [54]. There is nothing to
13 Transcript below, 10 February 2017, t 1-44.
-- 16 of 24 --
17
indicate that the President did not consider this in exercising her discretion – see [64]
and [71] of the judgment below. She was certainly cognisant of all the relevant facts.
[59] As to the other two issues, their articulation in the pleading of 30 November 2016 is
certainly more precise, and more in the form of a proper pleading, than their articulation
in previous versions of the defence. However, when the progress of pleadings is
considered, one can understand why they were articulated precisely for the first time
only on 30 November 2016. There is no rule that a party cannot make a late
amendment to a pleading unless it has a completely meritorious explanation for the
delay. The explanations here were understandable against the way the proceeding had
been run by both parties, and supervised by the Court. The explanations were relevant
to an exercise of discretion; the President did consider them – [68]-[70] and [74]-[77].
In my view no error is shown in her consideration.
[60] Paragraphs 4(p) and (q) of the Notice of Appeal assert that the President failed to have
any regard to the fact that BMA knew the facts now pleaded and had the opportunity to
plead these matters earlier than it did. Again, it is difficult to see how the assertion that
the President failed to have any regard to these matters could properly be made. The
President clearly did have regard to these matters and weighed them, as I have
discussed, at paragraphs 20 and [46]-[54] above. Her Honour took into account that the
Prospective Use Issue and the JR Issue had always been apparent on the pleadings, if
not articulated in the most lawyerly fashion. As just discussed, her Honour took some
time to understand exactly how it was that the Special Loss Issue had escaped the notice
of BMA’s lawyers until it emerged in the 30 November 2016 pleading. Once again, her
Honour weighed these matters in her discretion in an orthodox and, respectfully, sound
manner. Error is not demonstrated.
[61] Lastly, so far as the exercise of discretion to allow the amended pleading dated
30 November 2016 is concerned, paragraphs 4(u) and (w) of the Notice of Appeal assert
error on the part of the President in accepting BMA’s submission that it would not be
necessary for Cherwell Creek’s mining engineer to consider and develop a mine plan
for the coal resource within ML1775 as a result of the addition of the Special Loss
Issue. Unfortunately, once again these grounds of appeal are not based on an accurate
statement of the findings below.
[62] At [81]-[84] of the judgment below the President discussed the parties’ differing
contentions as to the additional cost to which Cherwell Creek would be put in
responding to the contentious amendments. Her Honour notes Cherwell Creek’s
estimate at $2 million and eventually finds that it is difficult to determine the amount of
additional and wasted costs. That will be better done after trial. Nonetheless her
Honour accepted that there would be considerable cost consequences for both Cherwell
Creek and BMA and remarked, “Even discounting Cherwell Creek’s assessment by
50%, the figure is substantial.” – [84]. In the course of that discussion about the
quantum of additional and wasted costs, the President noted that Cherwell Creek
contended its mining engineer would be required to develop a practical mine plan for
the coal resource within ML1775 and that BMA did not accept that was necessary. Her
Honour did not decide that issue. There is no basis for Cherwell Creek’s complaint in
this regard.
-- 17 of 24 --
18
Failure to Strike Out Contentious Parts of Amended Defence 30 November 2016
[63] Paragraphs 1, 2 and 3 of the Notice of Appeal assert that the President erred in failing to
strike out those parts of the 30 November defence which raised, respectively, the
Special Loss Issue, the Prospective Use Issue and the JR Issue. I will deal with each of
these in turn.
[64] The JR Issue. It will be recalled that BMA contends that EPC545 was never valid – its
grant in 1994 having been invalid, the decision to renew it in 2003 was also flawed.
Cherwell Creek responds that even if the initial grant and renewal of EPC545 were to
have been set aside by the Supreme Court, it does not change the fact that at the time of
the application for the mineral development licence it was the holder of an exploration
permit. It relies upon cases to the effect that it is very rare that an administrative act
will be of no effect whatsoever, even if it is later declared to have been beyond power.
There are nice questions of law involved in this issue, and in particular its determination
will involve a consideration of the cases dealing with the consequence of a finding that
an administrative act was beyond power. The question of what remedy the Supreme
Court was likely to fashion in the 2003 judicial review proceedings will depend upon an
understanding of the facts proved as to the initial grant of the exploration permit; its
renewal, and the consequences of any order made. In my view, the President was
correct in concluding that these matters are best determined after a trial. The President
correctly understood that these were the parties’ positions – [44]-[46] below. Her
Honour was well aware of the stringent test which applies before a court will strike out
a pleading at an interlocutory stage, thus denying a party the chance to try a case which
is not on its face unarguable.14
[65] The Prospective Use Issue. Cherwell Creek’s point about this issue is found at
paragraph 2 of the Notice of Appeal. It centres upon the fact that BMA did not have a
mining lease, or a mining infrastructure lease, which would allow it to place
infrastructure on the area of MDLA364. It is said the President failed to address this
submission and further erred by either not considering the merits of Cherwell Creek’s
argument, beyond concluding that BMA’s claim was not groundless, or erred in
thinking that BMA’s claim was sufficiently meritorious to warrant its determination at
trial. Presumably all three of these points were in the alternative, although they are not
expressed to be in the Notice of Appeal.
[66] It was quite wrong to assert that the President did not consider the issue. At paragraph
[57] of the judgment below she said:
“Finally, Cherwell Creek claims BMA is prevented from claiming special
loss because it could not demonstrate it could have secured a mining lease
for infrastructure purposes due to EPC545, held by Cherwell Creek.
Whether EPC would have precluded BMA from becoming eligible to apply
depends on at least two issues: firstly; the validity of EPC545, a live issue
on the pleadings; and secondly, construction of the relevant provisions
regarding eligibility. Again these are questions for trial.”
14 General Steel Industries Inc v Commissioner for Railways (NSW) (1964) 112 CLR 125, and r 171(1)(a)
UCPR 1999.
-- 18 of 24 --
19
[67] The claim that BMA would be granted the necessary licences and permissions to
establish infrastructure associated with the Caval Ridge Mine on the area, or part of the
area, comprised in MDLA364 could not possibly be regarded as without merit having
regard to the fact that BMA owned the land; had Mining Lease 1775 on adjacent land;
had Supreme Court proceedings on foot challenging the grant of EPC545, and having
regard to the statements by the Minister in the Second Reading Speech extracted at [47]
above.
[68] Because the amended defence pleads that any compensation payable to BMA
consequent on the grant of a mining lease to Cherwell Creek over the area of MDLA364
would have been in an amount of over $180 million as particularised by its expert Mr
Eales,15 Cherwell Creek attacked the expert report delivered by BMA’s expert Mr Eales
on the applications below. Mr Eales’ report was said to assume use of the area of
MDLA364 by BMA from 2010, when that was not realistic having regard to BMA’s
case about when Cherwell Creek would be denied a mining lease over the area of
MDLA364. I do not necessarily read Mr Eales’ report that way; see paragraph 50 of the
report. In any case, this is a factual matter which Cherwell Creek will no doubt advance
at trial through cross-examination, and perhaps through its own expert.
[69] The President correctly recognised the test to be applied when an application to strike
out a pleading was made – [59]. Cherwell Creek has not demonstrated that the
judgment below shows error in this respect; to the contrary.
[70] Special Loss Issue. BMA relies on s 281(3)(a)(vi) of the Act to claim that
compensation in an amount of $180 million would have been due to it, had Cherwell
Creek been granted a mining lease over the area of land on MDLA364. Cherwell Creek
submits that no compensation is payable pursuant to this section for prospective, as
opposed to current, use of land. The President noted that there are several single
Member decisions of the Land Court which are against Cherwell Creek’s contention in
this respect.16
[71] Cherwell Creek raises another argument, saying that s 281(4)(b) of the Act prohibits
compensation being made for minerals on or under “the land concerned”. There will be
a question of statutory construction as to whether the land concerned is that comprised
in MDLA364, or that comprised in Mining Lease 1775. While recognising that this was
a matter of statutory construction, the President thought it was a determination which
was better made after a trial. I agree, and I must say the view I have of the issue
(without full argument, of course) is that BMA has a good arguable case. There is also
an arguable question in my view whether BMA is claiming “for any minerals” or is
claiming economic loss.
[72] Further, it was contended that BMA’s case, so far as it appeared in Mr Eales’ report,
claimed the same loss twice. This was said to be because Mr Eales determined the
highest and best use of the freehold land which BMA owned as being for infrastructure
for the Caval Ridge Mine and also assessed, in effect, the same matters to produce the
15 Paragraph 11(c)(vi).
16 Wills v Minerva Coal Pty Ltd (No 2) (1998) 19 QLCR 297; ie, Xstrata Coal Qld Pty Ltd & Ors v Keys & Ors
(2013) 34 QLCR 186 and McDowall v Reynolds [2015] QLC 32.
-- 19 of 24 --
20
special loss BMA claims. BMA did not concede that its position was logically
unsustainable. However, it did make a submission that if it were wrong as to this, it
would claim the two different calculations in the alternative. I agree with the President
that this matter ought to be determined after a trial. The factual matters on which the
expert opinions are based, and the experts’ reasoning, will be much clearer after a trial
and cross-examination of experts for both sides. Other criticisms which Cherwell Creek
makes of Mr Eales’ methodology: failure to discount for contingencies, for example, are
also best determined after a trial.
[73] In all the circumstances, I think the President was correct not to determine these issues
but to reserve them to the trial judge. I think BMA certainly has an arguable case.
Application to Adduce Further Evidence on Appeal
[74] Cherwell Creek applied to admit an affidavit which exhibited a request for particulars,
and further and better particulars of the 30 November 2016 defence on the hearing of
this appeal. The request was dated 22 February 2017 and the particulars were dated 17
March 2017. I would grant that leave, and also allow a responsive affidavit from the
respondent which exhibits correspondence between the solicitors and directions which
have been made below since the decision under appeal. I now turn to consider the
matters which Cherwell Creek urged upon the Court arising from this further material.
[75] The JR Issue. It will be recalled that the respondent took the position before the
President that in its proceeding in the Land Court it would advance only those factual
matters already pleaded at paragraphs 2(b)-(e) of the defence to contend that it would
have been successful in the judicial review proceeding – see [36] above. At paragraph
4(c) of the request, Cherwell Creek’s solicitors ask by what date BMA would have
obtained an order quashing or setting aside the renewal of EPC545 in the judicial
review proceedings. The answer is that the respondent thought it likely that it would
have obtained such an order between May 2008 and the end of 2009. At paragraph 4(a)
of the request, Cherwell Creek’s solicitors ask for every factual and legal allegation
which BMA would have pursued in the judicial review proceedings. Consistently with
what the President was told below, the response to that was confined to the matters set
out in paragraphs 2(b)-(e) of the defence.
[76] In that context, by paragraph 4(d) of the request, Cherwell Creek’s solicitors asked for
particulars of the effect which an order quashing or setting aside the renewal of EPC545
would have had on the grant of MDLA364. The answer to this request was that the
effect of an order quashing or setting aside the renewal of EPC545 was that the Minister
could not have, or alternatively would not have, granted the application for MDL364.
[77] The particulars continue, at paragraph 4(f), to say that if the Minister had already dealt
with the application for MDL364 before the judicial review proceeding had concluded,
and if in so dealing with the application for MDL364, the Minister had granted
MDL364 to Cherwell Creek, BMA would have amended the application in the judicial
review proceeding to seek an order that the grant of MDL364 to Cherwell Creek be
quashed or set aside. It is pleaded that the Supreme Court would have granted that
order.
-- 20 of 24 --
21
[78] Cherwell Creek submitted to this Court that as a consequence of the further and better
particulars which I deal with at [77] above, BMA would have to file a new pleading.
Further, it was submitted that BMA has departed from the basis on which it presented
its case for an extension of time to file the amended defence of 30 November 2016 to
the President. It was said that these matters would influence this Court to take a
different view of the application to amend the defence to add the JR Issue than the
President took.
[79] I do not accept these submissions on behalf of Cherwell Creek. I cannot see the need
for a new pleading. BMA has not departed from the basis upon which it presented its
case to the President below. No new factual matters are being introduced into the case.
Nothing in this new material could sensibly be regarded as bringing about a different
result to that which the President reached below. This point was not fairly arguable in
my view.
[80] The Special Loss Issue. The amended defence filed 30 November 2016 quantifies the
compensation which BMA says Cherwell Creek would have been required to pay it in
order to obtain a mining lease over the area of MDLA364 as exceeding $180 million –
paragraph 11(c)(vi) of the defence. The particulars in the defence are, “The
Respondents will deliver an expert report assessing the compensation that would have
been payable by the applicant to the Respondents.” It was accepted that the report
referred to in the particulars was Mr Eales’ report of 2 December 2016, discussed
above.
[81] Paragraph 20 of the request for particulars asked BMA to specify each material fact in
support of the allegation that the compensation would have exceeded $180 million,
including a description of every item comprising that amount, and the method of
calculation. The response at paragraph 20 of the further and better particulars was that
the respondents were reviewing the calculation of the compensation and were not able
to provide further particulars until the completion of that review. That remained the
respondents’ position as at the time of the hearing of this appeal.
[82] Cherwell Creek complains that at the hearing before the President BMA only relied on
facts contained in Mr Eales’ report but it now anticipated that there were more or
different facts. With respect, that is not the only logical conclusion to be drawn from
the response at paragraph 20 of the particulars. It is equally possible that BMA will rely
upon some of the facts in Mr Eales’ report but seek to confine them, or indeed recast
them. Further, the request asks for more details of matters in Mr Eales’ report. A
response that contains what is asked will not necessarily give rise to any legitimate
complaint in Cherwell Creek. In these circumstances there is nothing to cause this
Court to come to a different conclusion than that reached by the President below as to
BMA having an extension of time in which to file the amended defence of 30
November 2016.
[83] The Prospective Use Issue. At paragraph 14(f)(iii) of the amended defence filed
30 November 2016 it is pleaded that the grant of a mining lease to Cherwell Creek over
the area of MDLA364 would have resulted in infrastructure for the Caval Ridge Mine
being placed on Mining Lease 1775 with the results that: 52.5 million tonnes of coking
coal in Mining Lease 1775 would have been sterilised; a profit of $178.4 million would
-- 21 of 24 --
22
have been lost to BMA; production of coal from the Caval Ridge Mine would have been
delayed, and royalties of $392 million would have been lost to the State. Paragraph 27
of the request for particulars asks, in a very detailed way, what items of infrastructure
would have been located where; why it would have been necessary to place
infrastructure within the boundaries of Mining Lease 1775; what coal would have been
sterilised, and how the loss of profit, delay and royalties are calculated. The response
was that BMA was reviewing the allegations and not currently able to provide
particulars. The same situation obtained at the time of hearing this appeal.
[84] Cherwell Creek submitted that this showed how erroneous it was for the President to
have concluded that the Prospective Use Issue had been raised in the pleading from the
outset. Further, it was submitted that the response showed that, “BMA does not know
whether it intends to rely on the facts pleaded in paragraph 14(f)(iii) of the Amended
Defence”. I do not accept either of those submissions. They overstate the position to
the point of inaccuracy. There is nothing on the further material before this Court
which would cause it to come to a different result in relation to the extension of time to
plead the Prospective Use Issue.
Costs Decision
[85] By a separate Notice of Appeal to this Court, Cherwell Creek challenged the decision of
the President of 15 March 2017 reserving the question of costs thrown away by the
amendments to the 30 November 2016 defence and the vacation of trial dates, to the
Land Court Member hearing the trial. This was a separate decision of the President
delivered after a hearing on the papers. The President made the following costs orders:
“1. The following are costs in the cause:
(a) the costs of the Respondents’ application for an extension of
time to file its amended defence; and
(b) the costs of the Applicant’s application to strike out parts of the
amended defence.
2. The question of costs thrown away either by the amendments to the
defence or the vacation of the trial dates is reserved.”
[86] It is only the second of those orders which is challenged by Cherwell Creek. So far as
these costs were concerned the President said:
“Turning to costs thrown away, any prejudice Cherwell Creek has suffered
can still be ameliorated by a costs order. Cherwell Creek wants an order in
its favour which is not enforceable until the conclusion of the proceedings.
If Cherwell Creek is, in fact, prejudiced by the amended defence or the trial
dates being vacated, they will be in no worse position by an order reserving
that question. The Court will be in a better position to assess prejudice after
the trial.” – [14]
[87] Cherwell Creek’s point on appeal is that the President had, in her decision of 17
February 2017, accepted that Cherwell Creek would suffer some wasted costs in
consequence of the extension of time granted to the respondents to file the amended
-- 22 of 24 --
23
defence, and it was wrong in those circumstances to hold that the question of who
should pay the costs thrown away should be reserved until after the trial.
[88] As to additional costs and wasted costs, the President said this at [84] of her judgment
of 17 February 2017:
“It is difficult to determine the scale of additional and wasted costs at this
stage of the proceedings. That is better done after trial. However, I accept
there will be considerable cost consequences for both Cherwell Creek and
BMA; some additional and some wasted. Even discounting Cherwell
Creek’s assessment by 50%, the figure is substantial.”
[89] Before the President, Cherwell Creek submitted that the appropriate costs order was,
“BMA pay Cherwell Creek’s legal and expert costs thrown away as a result of the
amendments [which] ought to be calculated following the trial and not be enforceable
until that time”.17 It contends for the same order on appeal.
[90] In my view the President’s discretion as to costs did miscarry. She found that there
would be costs wasted as a result of the late amendments to the defence. The fact that
no calculation of the amount of these wasted costs can sensibly be performed until after
trial, does not mean that the question of BMA’s liability to pay the costs should not be
determined now. In my view Cherwell Creek should have an order in the terms it
sought below.
Disposition
[91] The orders I would make are:
1. Grant leave to adduce further evidence;
2. Dismiss appeal number LAC001-17, and
3. Allow appeal number LAC002-17 and order that BMA pay the costs thrown away
by reason of its having leave to file the amended defence dated 30 November
2016, such costs not to be assessed until after the trial and determination of
Proceeding MRA1332-08;
4. Grant leave to the parties to make written submissions as to costs of the appeal
within 14 days of the delivery of this judgment.
[92] MEMBER COCHRANE: I concur with the reasoning of Dalton J and the orders she
proposed.
[93] MEMBER ISDALE: I agree with the reasons of Dalton J and with the orders
proposed.
17 Written submissions, paragraph 8.
-- 23 of 24 --
24
DALTON J
WL COCHRANE
MEMBER OF THE LAND COURT
WA ISDALE
MEMBER OF THE LAND COURT
-- 24 of 24 --
Official source: https://www.sclqld.org.au/caselaw/QLAC/2017/001