Actron Investments Queensland Pty Limited v D.D.S Project Management Pty Ltd & Ors [2016] QSC 306
SUPREME COURT OF QUEENSLAND
CITATION: Actron Investments Queensland Pty Limited v D.D.S Project
Management Pty Ltd & Ors [2016] QSC 306
PARTIES: ACTRON INVESTMENTS QUEENSLAND PTY
LIMITED ACN 124 426 455
(plaintiff)
v
D.D.S PROJECT MANAGEMENT PTY LTD
ACN 074 814 725
(first defendant)
DEQ CONSULTING PTY LTD ACN 065 711 248
(second defendant)
MICHAEL HENRY
(third defendant)
A1 EXPRESS PLAN APPROVAL SERVICES PTY
LIMITED ACN 082 452 499
(fourth defendant)
STACY KENNEDY
(fifth defendant)
FILE NO: BS2188 of 2012
DIVISION: Trial Division
PROCEEDING: Trial
DELIVERED ON: 22 December 2016
DELIVERED AT: Brisbane
HEARING DATE: 3-6, 9-11 May and 24 June 2016
JUDGE: Mullins J
ORDER: 1. The proceeding against the second and third
defendants is dismissed.
2. The question of the costs of the proceeding is
adjourned to a date to be fixed.
CATCHWORDS: TORTS – NEGLIGENCE – STATUTES, REGULATIONS,
ETC – APPLICABILITY AND EFFECT IN ACTIONS FOR
NEGLIGENCE – GENERALLY – where plaintiff purchased
a newly constructed industrial building where the floor was a
slab on ground – where site contained marine clays that
consolidated and caused the slab to settle – where defendant
engineer designed the slab on ground and certified the slab
complied with the Standard Building Regulation 1993 (Qld) –
where plaintiff’s use of the building as a warehouse was
affected by the uneven slab settlement – whether defendant
-- 1 of 37 --
2
owed plaintiff a duty of care in designing and certifying the
slab
TORTS – NEGLIGENCE – ESSENTIALS OF ACTION FOR
NEGLIGENCE – DUTY OF CARE – WHERE ECONOMIC
OR FINANCIAL LOSS – CARELESS ACTS OR
OMISSIONS – where plaintiff suffered economic loss caused
by replacing the floor of the industrial building – where
plaintiff was the subsequent purchaser of building – whether
plaintiff vulnerable in the sense described in Brookfield and
Woolcock – whether a duty of care should be imposed on the
defendant in designing the floor
Trade Practices Act 1974 (Cth), s 52, s 75B
Building Act 1975 (Qld), s 14, s 45
Building Regulation 2006 (Qld), s 17, s 18, s 46, s 48, s 56
Standard Building Regulation 1993 (Qld), s 23
Bamford v Albert Shire Council [1998] 2 Qd R 125; [1997]
QCA 462, considered
Brookfield Multiplex Ltd v Owners Corporation Strata Plan
61288 (2014) 254 CLR 185; [2014] HCA 36, considered
Bryan v Maloney (1995) 182 CLR 609; [1995] HCA 17,
considered
Chan v Acres [2015] NSWSC 1885, considered
Moorabool Shire Council v Taitapanui (2006) 14 VR 55;
[2006] VSCA 30, considered
Western Districts Developments Pty Ltd v Baulkham Hills
Shire Council (2009) 75 NSWLR 706; [2009] NSWCA 283,
considered
Woolcock Street Investments Pty Ltd v CDG Pty Ltd (2004)
216 CLR 515; [2004] HCA 16, considered
COUNSEL: A F Fernon for the plaintiff
A M Musgrave for the second and third defendants
SOLICITORS: Low Doherty & Stratford Lawyers for the plaintiff
HBM Lawyers for the second and third defendants
[1] The plaintiff is in a group of companies involved in the business of the design,
manufacture, sale, installation and service of residential and commercial air-conditioning
units. It purchased the property situated at 119 Benjamin Place, Lytton described as Lot
10 on SP174502 under contract dated 22 March 2007 (the contract) from Efstathis
Property Developments Pty Ltd (Efstathis) of which Mr Efstathis was a director. The
purchase was completed on 16 April 2007. The property is in a community title scheme
known as “Portlink” that was developed by Pradella Constructions which sold the
property as vacant land to Efstathis in late 2004.
-- 2 of 37 --
3
[2] The first defendant (DDS) and Efstathis had been involved in many commercial property
development projects where DDS would build for Efstathis under a Design and Construct
Contract. Mr McFadden who is the director of DDS and a licensed builder was involved
with Efstathis in doing the preliminary investigations for the development of the subject
property from around 2004. The development approval for use of the property for
industry and warehouse was obtained by Efstathis on 25 May 2006. Efstathis entered
into a Design and Construct Contract with DDS by or about August 2006 (the D&C
Contract) for the construction of a commercial warehouse building on the property.
Clause 1.7 of the D&C Contract provided that neither party may assign that contract
without the written consent of the other. (In fact, Mr McFadden made it clear in his
evidence that he would never have consented to the assignment by Efstathis of its rights
under the D&C Contract to the purchaser of the property.)
[3] The second defendant (DEQ) carried on the business of consultant civil, structural and
geotechnical engineers and had been first approached in about February 2005 by DDS to
quote for engineering fees on preliminary drawings for an industrial warehouse building
on the property, incorporating a concrete slab on ground. The quote covered the structural
and civil engineering works and inspections during construction. The third defendant Mr
Henry was at all material times a director of DEQ and a registered engineer with
experience in the structural, geotechnical and civil areas. DEQ was then retained by DDS
to do the structural drawings in about May 2006. The structural drawings S01 to S12 (the
S drawings) were prepared in June 2006 and issued on 5 July 2006 to DDS.
[4] Mr Henry on behalf of DEQ carried out a site investigation of the property and provided
DDS with a report dated 21 July 2006 (the first report) which Mr McFadden had requested
be the “bare minimum” to obtain building approval. The contractor engaged by DDS to
do the piling on site for the perimeter provided DDS with a geotechnical report for a
nearby site (about 200m away) referred to as Lots 29 to 31 undertaken in March 2006.
Mr Gillroy of DDS passed that geotechnical report onto DEQ and Mr Henry on 24 August
2006. As a result DEQ provided a further report (the second report) in the form of a letter
dated 25 August 2006 (exhibit 34) to DDS. There had been an issue between DDS and
DEQ, as to whether that report was sent by DEQ or received by DDS. The evidence
adduced by Mr Henry and Ms Reese and through Telstra employee Mr Miller was such
that DEQ and Mr Henry discharged the onus of proving the report was sent by DEQ to
DDS and received by DDS on 25 August 2006. Following the second report, drawing
S02 was amended to provide for the piling of that part of the slab that supported the
mezzanine office area.
[5] Mr Henry on behalf of DEQ issued the Form 15 Compliance Certificate – Design for the
property. The date on which it was originally issued is unclear, but consistent with the
metadata for the document (exhibit 43), it is likely it was issued on 18 August 2006. It
was re-issued on 22 April 2007. The Form 15 was issued when the Standard Building
Regulation 1993 (Qld) (SBR) was in force. It certified that the structural elements
detailed on DEQ’s drawings 06 0603 S01 to S12 P1, if installed and carried out in
accordance with the information contained in the certificate would comply with the SBR.
The following standards were listed as the basis of certification:
“AS1170.1 – Dead & Live Loads, AS1170.2 – Wind Loads, AS1170.4 –
Earthquake Loads,
-- 3 of 37 --
4
AS3600 – Concrete Structures Code, AS3700 – Masonry Code, AS1684 –
Timber Framing Code,
AS4100 – Steel Structures Code, BCA – Building Code of Australia Clause
C1.11
AS2870 – Residential Slabs & Footings-Construction.”
[6] DDS got oral approval from the fifth defendant in August 2006 to commence the building
works as a fast-track project, in anticipation of lodging with the fourth defendant all
engineering and architectural drawings for the project required to obtain the necessary
building approval.
[7] Mr Henry on behalf of DEQ issued the Form 16 Compliance Certificate - Construction
which purported to be under the SBR for the building constructed on the property,
certifying that the specified components had been built generally in accordance with the
development approval, DEQ’s drawings 060603 S01 to S12 Rev P and the SBR. The
certificate was originally dated 1 March 2007, but was re-issued with the correct
description of the property on 22 April 2007. (While the Form 16 was not in the approved
form under the Building Regulation 2006 (Qld) (the Regulation), it contained sufficient
information to assist the building certifier approve the building development and nothing
turns on the use of the wrong form.)
[8] The written approval with conditions in respect of the application for building works on
the subject site was issued by the fourth defendant on 2 March 2007 for a building with
the classification of class 8.
[9] A certificate of classification dated 4 April 2007 was issued for the ground and first floors
of the building constructed on the property. They were shown as class 8. The building
description was described as “industry”. The building certifier was the fifth defendant on
behalf of the fourth defendant.
[10] Mr Henry admits that he was a competent person within the meaning of the SBR and the
Regulation appointed to assist the building certifier by certifying works as described in
the Forms 15 and 16. The parties agree that s 56 of the Regulation provides that a properly
made building development application that has been made, but not yet determined,
before 1 September 2006 must still be resolved under the SBR, but as in this matter a
properly made application was not made until December 2006, it is the Regulation that
applies.
[11] The property was marketed on behalf of Efstathis for sale or lease and described as
“architecturally designed, single free-standing corporate headquarters/warehouse”
(exhibit 6). The marketing material provided to the plaintiff prior to entering into the
contract includes some of the George Group architectural drawings and a document
entitled “Lot 10 Benjamin Place, Lytton Schedule of Finishes”. Under the heading
“Floors”, it was noted:
“Warehouse floor has been designed for loading of 6 Ton rubber tyred
forklift.
-- 4 of 37 --
5
Refer to engineering design drawings for pallet racking requirements/
loadings.”
[12] The contract between the plaintiff and Efstathis is in the standard form contract for
Commercial Lots in a Community Title Scheme (first edition) with some amendments.
Relevantly, the standard clause 4 which made the contract conditional on building and
pest inspection reports was shown in the reference schedule as not applicable. The
property had been advertised for sale at a price of $3.3m (plus GST), but the plaintiff
offered to purchase for cash for $3.175m (plus GST) (exhibit 4) and that was the purchase
price in the contract.
[13] Special condition 2 of the contract dealt with completion of the improvements on the
property as contemplated by the plans in schedule 1 to the contract and the specifications
in schedule 2 to the contract. Clause 2.3 provided:
“During the Defects Liability Period the Buyer may on behalf of the Seller
notify the Builder in accordance with the Building Contract as to any defects
in the construction of the Improvements.”
[14] The term Defects Liability Period was defined in the special conditions as six calendar
months from the issue of the certificate of classification. The plaintiff’s solicitors sought
a letter from DDS acknowledging its obligations in relation to the defects liability period.
[15] A letter dated 20 March 2007 from DDS addressed to the purchaser of Lot 10 was
provided to the plaintiff’s solicitors that identified that DDS was the “contract builders of
the building works” on Lot 10 and was in these terms:
“There is a defects liability period of 6 calendar months from the date of issue
of the Certificate of Classification.
We acknowledge that we will be liable to any future purchaser to rectify any
defects in the building works notified to us during the defects liability period
in accordance with the attached clauses from the building contract.”
[16] Clause 2.4 of the special conditions of the contract provided:
“On completion the Seller assigns to the Buyer any rights of enforcement that
the Seller may have against the Builder. The Buyer:-
(i) May in the name of the Seller institute proceedings against
the Builder; and
(ii) Require the Seller not to release any retention
subject in both cases to appropriate indemnities and security for costs as are
reasonably required by the Seller being provided by the Buyer and the Buyer
executing a deed of indemnity in favour of the Seller in such form as the Seller
shall reasonably require.”
-- 5 of 37 --
6
[17] The plaintiff did not take any steps prior to or at settlement to perfect the assignment
provided for in clause 2.4. The plaintiff did not use the procedure provided for in clause
2.4 for pursuing any claim to enforce the D&C Contract against DDS.
[18] Clause 2.5 of the special conditions provided:
“Save as provided by this Special Condition the Seller does not warrant that
the Improvements have been constructed in a good and workmanlike manner
or are otherwise fit for any particular purpose.”
[19] Under clause 4.1 of the special conditions the date of completion of the contract was the
later of 16 April 2007 or seven days after the seller provided the buyer with a copy of the
certificate of classification.
[20] Clause 5.1 of the special conditions provided:
“If the Certificate of Classification shall not have issued by the Termination
Date either party may terminate this Contract and Standard Condition 2.3(3)
shall apply.”
[21] The termination date was defined in the special conditions to mean 30 September 2007.
On 16 April 2007 Efstathis sent a letter to the plaintiff accompanying a folder that
contained copies of the certificate of classification, the Forms 15 and 16, the engineering
drawings for job number 06-0603 S01 to S12 which were all version P1, except for
drawings S02 and S07 which were version P2, the schedule of colours and finishes and
other drawings. Efstathis did not send the two DEQ soil reports dated 21 July and 25
August 2006. By letter dated 26 April 2007, Efstathis sent the plaintiff copies of the
amended Forms 15 and 16 signed by Mr Henry and dated 22 April 2007. Apart from the
date of signing the forms, the only amendment in these forms related to the description
of the property, changing the suburb from Tingalpa to Lytton.
[22] After the plaintiff acquired the property, it installed pallet racking in about May/June
2007. The racking was up to four levels high, except the one bay which was six levels
high. The plaintiff then used the property as a warehouse for the storage of air-
conditioning units and parts, pending their sale and installation.
[23] Issues arose with respect to the failure of the concrete slab of the building. Investigations
as to the cause of the subsiding slab commenced in 2009. As a result of obtaining the
results of a geotechnical investigation of the slab, the plaintiff commenced this
proceeding on 9 March 2012 to pursue claims for pure economic loss arising from the
failure of the floating slab on which the warehouse was built on the property.
[24] In late 2013 the plaintiff relocated the warehousing part of its business to leased premises
at 142-150 Benjamin Place by pulling down the racking, storing some racking in the
carpark of the subject property, and reinstalling some racking at the temporary premises,
so that rectification works in respect of the concrete slab could be carried out. This
involved removing the floating slab and replacing it with a slab on piles. The plaintiff
then re-installed the pallet racking and was able to resume conducting its business fully
from the property. As a result of the rectification works undertaken by the plaintiff, the
-- 6 of 37 --
7
building classification for the ground floor of the property changed on 6 February 2014
from class 8 to class 7b.
[25] The plaintiff settled its claim against the fourth and fifth defendants for $100,000. On the
fifth day of the trial the plaintiff settled its claim against the first defendant on a
confidential basis.
Issues
[26] The plaintiff sues DEQ and Mr Henry for damages for breach of the duty of care owed in
tort for the design of the slab and the issue of the Form 15 and/or Form 16 and for damages
for misleading and deceptive conduct (in reliance on s 52 and s 75B respectively of the
Trade Practices Act 1974 (Cth)) (TPA) in respect of the issue of the Form 15 and/or Form
16. On 13 July 2016 the parties provided a further amended agreed statement of issues
(which will become exhibit 54).
[27] By the end of the trial, the list of what was truly in issue had reduced significantly. That
meant that some of the matters that were explored in evidence, such as whether there
should have been compaction of the existing fill on site before construction of the slab,
became irrelevant to the resolution of the claims. For that reason, I have endeavoured to
limit the recitation of the evidence to what is necessary to determine the outstanding
issues. As Mr Fernon of counsel for the plaintiff acknowledged during submissions
(Transcript 8-8), the ultimate issue is whether DEQ and Mr Henry should have designed
a floating slab at all, having regard to the range of potential uses for the structure, or
whether the design should take account of the owner’s subjective requirements and
instructions.
[28] The plaintiff’s claim against DEQ and Mr Henry based on representations was originally
based on the representation alleged to be implicit in the Form 16. It was alleged in
paragraph 45 of the statement of claim that the Form 16 represented that the building
works had been built generally in accordance with the development approval, the various
drawings prepared by DEQ and the SBR. The nature of the case based on representations
was expanded to include in paragraph 44A of the statement of claim the representation
implicit in the issue of the Form 15 that DEQ and Mr Henry represented that if the
building works described in the S drawings were installed and carried out in accordance
with the information contained in the Form 15, including any referenced documentation,
it would comply with the SBR. By the end of the trial, the representation case was
effectively limited to the Form 15 which was linked with the allegation in tort against
DEQ and Mr Henry that the design of a slab on ground for the subject building could
never comply with the Building Code of Australia (BCA).
[29] The principal issues to be decided are:
(a) identification of the standards that applied to the design of the concrete floor
slab;
(b) whether there was a breach by DEQ and Mr Henry of relevant design
standards;
(c) whether the issuing of the Form 15 constituted a breach of the SBR or
Regulation;
-- 7 of 37 --
8
(d) whether the plaintiff was vulnerable in any relevant sense to any want of
reasonable care by DEQ or Mr Henry in the design and/or certification of the
concrete slab;
(e) whether the representation that was implicit by the issue of the Form 15
amounted to misleading or deceptive conduct.
D&C Contract
[30] When Mr McFadden was undertaking preliminary discussions with Mr Efstathis about
the proposed development, Mr Efstathis provided him with a copy of the report from
engineers Weathered Howe Pty Ltd to Pradella Developments in respect of Lot 23 of the
Portlink Development, Lytton dated 28 June 2005 (exhibit 13) which dealt with the
placement and compaction of fill on Lots 22 and 23 from which Mr McFadden inferred
there had been no filling carried out on Lot 10, as the developer would have been obliged
pursuant to condition 13(c) of the development application to inform Efstathis of any
compaction testing results, if there had been filling on Lot 10. Mr Efstathis also provided
Mr McFadden with a copy of a report prepared by Soil Surveys dated 16 October 2002
prepared for Pradella Constructions in respect of the proposed industrial subdivision at
Lytton Road (Lot 1 on RP108559 and Lot 33 on S151833) (exhibit 14). Mr Efstathis
proposed to Mr McFadden a construction cost on a per square metre basis which gave Mr
McFadden some guidance for calculating the building contract lump sum. Mr McFadden
explained that at the end of any project he did with Mr Efstathis, they would share the
savings, if the project came in under budget, but that arrangement was not incorporated
into the formal building contract. It was an arrangement that applied to the subject
building.
[31] The D&C Contract is in the form of Decon 2-1998 produced by the Master Builders. The
Principal’s Project Requirements for the Works were limited to the architectural drawings
from the George Group being 2666/01 to 2666/09 set out in schedule 3. There is a
definition of “Contractor’s Design Deliverables” as “the design documents and other
documents prepared by the Contractor for the execution of the Project which are listed in
Schedule 4”. The only documents listed in schedule 4 is the schedule of finishes which
was incorporated into the D&C Contract. The contract sum was set out in schedule 6 as
$1,515,249 (inclusive of GST). A provisional sum of $85,000 was allowed for piling for
the perimeter wall on the basis that it was anticipated that subsurface and site conditions
might cause additional expense for piling of the perimeter, as piles were charged for by
the metre and not by the number.
[32] Clause 7.1.1 provides for the items of work in schedule 12 to be “expressly excluded from
the Works”. Schedule 12 refers to the schedule of finishes. In the section of the schedule
of finishes that is headed “Floors”, the following is noted:
“Warehouse floor has been designed for loading of 6 Ton rubber tired forklift.
No allowance has been made for pallet racking or punching, for further details
please refers (sic) to engineering design drawings.”
[33] The schedule of finishes in the marketing material for the property was obviously based
on the schedule of finishes in the D&C Contract, but omitted the express reference to “no
allowance has been made for pallet racking or punching”, while still making it clear that
-- 8 of 37 --
9
reference should be made to engineering design drawings for pallet racking
requirements/loadings.
[34] Mr McFadden described the building as constructed as comprising the tilt slab walls, the
roof and the steel framing structure which were all supported on deep piled foundations
as one element and the free floating floor slab that was constructed and moved
independently as the second element of the building.
[35] For the purpose of this proceeding, Mr Henry prepared a design for a fully piled slab
(exhibit 15) which Mr McFadden costed using 2006 figures which resulted in an
estimated additional cost of $400,812.20 (including a profit margin of $52,279.85
calculated at the rate applied to the project, but exclusive of GST) to construct a fully
piled slab (exhibit 16).
[36] After the plaintiff’s purchase, Mr McFadden was engaged by the plaintiff to fit out the
office area in the building. He noticed at the same time that some pallet racking was
delivered and he spoke to a person he described as one of the plaintiff’s employees in
relation to the pallet racking, observing “You need to make sure you’ve got the right feet
on there. Have you checked the engineering on the job? It’s a floating floor. There’s
going to be some movement.” Mr McFadden could not remember the name of the
employee to whom he spoke, but said it was an Italian sounding name and assumed from
the documents he read in connection with the proceeding that it must have been Mr Aldo
Borazio (Transcript 3-8).
[37] Mr Borazio was the national sales and marketing manager of the plaintiff in 2007 and
was involved in locating the subject building for purchase by the plaintiff. He has no
recollection whatsoever of the conversation which Mr McFadden suggested in his
evidence he had with Mr Borazio (Transcript 7-5).
[38] It was clearly supposition on Mr McFadden’s part that it was Mr Borazio with whom he
had the conversation. In light of his senior position within the plaintiff’s organisation and
his sporadic visits to Queensland, I do not accept Mr McFadden’s evidence that he had
that conversation with Mr Borazio or with any person with relevant authority in the
plaintiff’s organisation without such a conversation being reported to the plaintiff’s chief
executive officer which did not occur.
Drawings and reports prepared by DEQ
[39] Before Mr Henry did the fee proposal for DDS for the proposed development, he had
been told by Mr McFadden that he wanted him to design an industrial building with a
slab on grade floor. (The expression “slab on grade” was used by Mr Henry
interchangeably with “slab on ground”.) Mr Henry was aware that Mr McFadden had
knowledge of the ground conditions in the area, particularly that the area had settlement
issues and that there were fill and marine clays on site. Mr Henry was also familiar with
the area, anticipating the site conditions would be imported fill over marine clays. Mr
McFadden conveyed to Mr Henry the requirements of Efstathis that the building have six
metres of storage and that the portal frame accommodate a five tonne gantry frame.
-- 9 of 37 --
10
[40] The engineering drawings included in the trial bundle (exhibit 1, Tab 44) are those the
subject of the building approval and stamped by the fourth defendant.
[41] Drawing S01 contains the general notes for the proposed industrial building. Under the
heading “General”, there is a note to the effect that the structural work shown on the
drawings has been designed for a live load of 15 kPa in respect of the warehouse floor.
[42] There is the following note in the box headed “Floor Slabs”:
“The slabs have been designed as a floating slab. Hence movement in the
subgrade will result in vertical & curvature movements in the slab along with
some minor cracking. Expected movement to be in the range of ? 40-70mm.”
[43] The following note is found on drawing S01 under the heading “Concrete”:
“Concrete slab surface tolerance for internal slabs shall be the most stringent
of the following
- as required by the applied surface finish.
- 3mm over a 3000 straight edge.”
[44] Mr Henry was cross-examined on whether that reference to “3mm over a 3000 straight
edge” was a reference to the standard set by the Cement and Concrete Association of
Australia’s “Industrial Floors and Pavements Guidelines for Design Construction and
Specification” known as T48. Mr Henry explained that it was not a reference to T48, but
instead it was a reference to construction installation tolerances and 3 mm in 3 metres is
the best practice that can be achieved with hand trowelling (Transcript 5-109). Mr Henry
did not use T48, but used the British version in designing concrete floors (Transcript 6-
14).
[45] Another version of the S drawings (exhibit 20) shows that “40-70mm” was preceded by
plus and minus signs. Evidence was given that these drawings were sent electronically
and that sometimes when they were printed out, the designation of the plus and minus
signs together was shown by a different symbol such as “?”. Mr Henry’s evidence was
that the difference arises, because some printers do not recognise different symbols in the
different versions of the Computer Aided Design software that are used. The fact that,
on the same page of the approved drawings where a question mark precedes “40-70mm”,
there is another dimension that is preceded by plus and minus signs that are printed out
as such does not preclude my acceptance of Mr Henry’s evidence based on his experience
in working with this software that the note was incorporated by him on the drawing with
the plus and minus signs preceding “40-70mm”, as shown in exhibit 20. This is supported
by Mr McFadden’s evidence who remembered seeing “a plus or minus” on the plan
(Transcript 3-72).
[46] One of the reasons that Mr Henry referenced AS 2870 even though it applies to residential
slabs, as it is the only code that describes seasonal surface movement and Mr Henry had
selected the H classification which applies to movement of 40 to 70mm.
[47] Drawing S02 which was the slab footing plan contained these notes under the heading
“Floor Design Loads For Slab”:
-- 10 of 37 --
11
“(a) Uniformly distribute loading of 2.0 kPa per m height applied evenly to
slab.
(b) 6 Tonne front axle load of solid rubber tyre fork lift trucks with single
wheel axles. ”
In calculating the live load of 15 kPa for the warehouse floor, Mr Henry used a height of
7.5m for the building at the “knee” where the roof meets the vertical member which
supports it.
[48] There is another note on this drawing in these terms:
“The slab has been designed as a floating slab. Thus the floor will under go
surface movement that occurs. The floor may also experience settlement due
to consolidation at compressible marine clays on site. Differential settlement
may occur.”
This note communicated the potential for the floor to undergo two types of movement,
namely the surface movement from the clays shrinking and swelling of 40 to 70mm and
settlement due to the consolidation of compressible marine clays.
[49] DDS was aware that DEQ had only a small rig for the purpose of doing a geotechnical
investigation where the auger could go to a maximum depth of only 4.5 metres. Five
boreholes were made and tested on Lot 10 on 13 June 2006 by an employee of DEQ and
the results were included in appendix A to the first report. Although the first report is
dated after the S drawings were first issued, Mr Henry had the results of borehole tests
and knowledge of the matters disclosed in the first report at the time he prepared these S
drawings.
[50] The scope of the site investigation that was undertaken for the first report is set out in
paragraph 1.0 as to determine the soil parameters for design purposes for the proposed
development, namely:
“(a) Identification of the soil profile.
(b) Shrink/swell potential of the subsoils.
(c) Allowable bearing capacity of the subsoils and identification of suitable
footing systems.”
[51] It was expressly noted that the site investigation did not include analysis of consolidation
of marine clays. As Mr Henry explained in his evidence, that service could not be
provided because of the limitation of the depth to which DEQ could drill with its
equipment. Paragraph 4.0 set out the extent of the site investigation as comprising five
boreholes with depths of up to 4.5m and the results of the boreholes were set out in
appendix A to the first report. It was recorded in paragraph 5.0 that filling operations had
taken place at the borehole locations and the subsoil profile encountered at the boreholes
consisted of fill overlaying clays to the depth of the boreholes. A description of the fill
was provided. Paragraph 7.1 of the first report noted that one shrink/swell test was
conducted from one of the samples and the test result was recorded. It was noted that
“the clayey fills encountered have a moderate potential for seasonal movement” and that,
due to the variability of the fill, the opinion was expressed “that the site surface movement
-- 11 of 37 --
12
of the order of 40-70mm be used with regard to seasonal surface movement” and that
“this value does not include the effects of consolidation of the marine clays which would
be in addition to these values”.
[52] Mr Henry clarified in his evidence (Transcript 5-6) that 40 to 70mm is the range of
movement from the condition of the surface when it is first measured and it is not a
movement from a fixed datum point as such. If the conditions are wet when measured,
then the movement can be downwards 40 to 70mm, but if the conditions are dry when
measured, then the movement can be 40 to 70mm upwards.
[53] In the conclusions and recommendations in paragraph 8.1 of the first report relating to
the foundations, the limitation that there was no investigation of the properties and depth
of the marine clays was repeated. It was pointed out that marine clays when loaded can
undergo consolidation which results in settlement of the surface. It was then stated:
“More advanced investigations in these areas have calculated typical surface
settlement of over 100mm could be expected to sites that have not been
preloaded. The magnitude of the settlement is dependent on loadings, depth
of marine clay and whether any preloading has been applied to the site to
cause consolidation prior to building construction. Loadings include any
filling, applied live loads and building weight. Typical differential
settlements are of the order of 50% of the total deflection.”
[54] Mr Henry explained that his reference to more advanced investigations was to projects
where such advanced investigations were undertaken in the vicinity of the subject land
by himself or a fellow director. Mr Henry explained that he described the magnitude of
this settlement in the first report as “over 100mm” as that would be a “red flag” to
“someone doing a due diligence review of these drawings”.
[55] It was then noted that floor design was dependent on the proposed use of the building and
the sensitivity to floor movement and also construction budget, and the proposed use of
the building was unknown.
[56] Three structural options were canvassed, one of which was the free floating slab on
ground option (option 1). Option 2 was partial floating slab on ground with relieving
slabs to perimeter and option 3 was suspended slab supported on piles. It was noted that
as options 1 and 2 have the floor constructed on the ground, the floor is subject to the
settlement of the subsoils. There was advice on methods for managing this movement by
either or a combination of two specified methods. The drawback associated with these
methods that had the lowest construction cost was noted as “settlements and associated
damage, floor cracking and floor curvatures would be high, resulting in higher
maintenance costs for the buildings”. Option 3 was noted as the most expensive option
with respect to construction cost.
[57] This section of the report then concluded:
“The client should be fully informed of the above scenarios and made aware
of the cost implications of the different methods of construction and
-- 12 of 37 --
13
expectations of the building performance associated with each floor design
option.
Where settlements of the floor can be tolerated, options 1 & 2 may be the
most economic in construction, however, the client and/or future owners and
tenants must be made aware of the increased maintenance costs associated
with this type of construction.
If the warehouse slab settlements cannot be tolerated, or increased
maintenance costs and potential damage associated with the slab settlements
and movements are unacceptable, then Option 3 should be the preferred
method of construction.
Where settlement can be accommodated a floor live load of 15 kPa could be
used in the existing fill.”
[58] Paragraph 8.2 of the first report set out recommendations for limiting effects of reactive
clays due to the high potential for movement with moisture content fluctuations. One
recommendation was:
“Internal slabs should be kept independent of the main structure and be
allowed to float with surface movement. Floating pavements are the most
economical pavement system for expansive clay sites. It should be noted
however that the levelness of the pavement will not be maintained due to the
surface movement. The end user of the building should be advised that
movement of the pavement could occur.”
[59] In the second report, DEQ used the Soil Surveys soil report dated March 2006 to quantify
the possible settlement that could occur due to the compressible material encountered on
site. The relevant conclusions in the second report were:
“We refer you to Section 4.4 Settlement Behaviours of the soil report. The
report advises that settlement figures of between 150 and 200mm could be
expected for a loading of 20 kPa. A loading of 20 kPa is applicable for a
building of this height. Another 50mm of secondary creep could also occur.
Your client should be made aware that the slab-on-ground as presently
designed will experience similar magnitude movements. This magnitude of
movement may severely restrict the possible usage of the building.
Relevelling of the floor can be expected to be required in heavily loaded zones
of floor throughout the life of the building.
Your client should be made aware also that the use of a floating slab-on-
ground is a minimum construction cost option and the construction saving
made should be weighed against the possible economic costs with regard to
future maintenance costs and lack of compatibility with building use of future
purchasers.”
[60] Mr Henry was cross-examined on his statement that “A loading of 20 kPa is applicable
for a building of this height” on the basis he was asserting that the subject building had
been designed for a load of 20 kPa. Mr Henry explained that he wrote the second report
in light of the content of the Soil Surveys report that had been forwarded by DDS. That
-- 13 of 37 --
14
report in section 4.4 referred to a slab loading of 20 kPa and he just adopted that figure
for the subject building without referring back to his drawings (Transcript 6-8). It is
apparent from the urgency with which the second report was provided that it was likely
that was the case. The loose reference by Mr Henry to 20 kPa as applicable for the subject
building did not alter what was, in fact, the relevant loading of 15 kPa disclosed in the S
drawings and the advice given in the second report was not affected by the error which
he made in recording the relevant loading as 20 kPa instead of 15 kPa. (I reject the
plaintiff’s submission that Mr Henry’s explanation was that the loading for the building
was 20 kPa.)
[61] Mr Henry explained that the reference to “relevelling” was to undertake maintenance to
make the floor level by replacement or grout injection. As a result of his consideration
of the Soil Surveys soil report dated March 2006, Mr Henry considered that an office fit-
out on the mezzanine floor would not handle the movement of a floating slab and
recommended replacing the flooring of the mezzanine level with a product called Hebel.
It is at this time Mr Henry produced the P2 version of drawing S02 and the P2 version of
drawing S07.
[62] Mr Henry explained (Transcript 5-9) that the S drawings did not include a schematic
diagram that provided for the floor design loads for the slab where pallet racking was to
be installed. He produced DEQ’s standard details for a floor that shows the locations
where the slab is capable of resisting the punching load form pallet racking feet (exhibit
33). It was Mr Henry’s experience that if a slab on ground had been designed for racking,
he would have expected to see such a schematic diagram in the engineering drawings.
[63] Mr Henry accepted that the anticipated design life of the building was 40 years (Transcript
5-60). He also anticipated that the expected settlement of the slab throughout the life of
the building would require it to be replaced as least once (Transcript 5-91). He made the
point that his client was happy to have a warehouse with a floor that settled and, he was
designing to meet his client’s expectations (Transcript 5-109). Although DEQ was
retained by DDS, I infer that Mr Henry’s reference to client was to Efstathis, as Mr Henry
knew that DDS who had contracted with DEQ was building for Efstathis.
[64] Mr Henry was cross-examined on the application of clause 16.2.1 of AS 3600-2001 which
gives additional design considerations for in situ concrete slabs cast on the ground and
extending to industrial, commercial and residential usage. Clause 16.2.1 provides:
“The foundation shall be investigated and suitably modified, where
necessary, to ensure that the sustained and any intermittent service loads, can
be resisted by the slab without undue differential or uniform settlement.”
[65] Mr Henry’s response to the proposition that an anticipated settlement over time of over
100mm was "undue" for the purpose of clause 16.2.1 was that it depended on what the
client wanted, as the slab is designed for what the client wanted (Transcript 6-23).
[66] For the purpose of the trial Mr Henry inspected and obtained copies of plans for other
constructions in the vicinity of the subject building which showed that none of these
industrial buildings had been built with a piled slab. These included the building on the
adjoining Lot 9 Benjamin Place (exhibit 21), the warehouse at 114 Benjamin Place
-- 14 of 37 --
15
(exhibit 22), the building at Lot 11 Lytton Road, Hemmant (exhibit 23), the warehouse at
130 Benjamin Place (exhibit 24), the warehouse at Lot 12 Benjamin Place (exhibit 25),
the building at Lot 2 Canberra Street, Hemmant (exhibit 26), and the industrial building
at 43 Export Drive, Lytton (exhibit 40). Mr Henry expressed the opinion it was likely the
warehouse at 30 Anton Road, Hemmant (exhibit 39) was a slab on ground.
[67] Mr Henry identified that the warehouse inspected at 10 Anton Road, Hemmant (exhibit
38) was a suspended concrete slab which was explained by its use as a coldroom
warehouse.
The plaintiff’s purchase of the property
[68] The plaintiff’s head office was in New South Wales where its chief executive officer and
director Mr Mundy was and is based. Prior to purchasing the property, the plaintiff’s
business in Queensland operated from leased premises at Morningside and used a third
party to distribute its product. The plaintiff decided that the Queensland business should
operate like the business in New South Wales and undertake its own distribution. The
subject property was located. Mr Mundy inspected the building before it was completed.
The plaintiff did not engage an engineer to assist in its purchase.
[69] The plaintiff did not attempt to inspect any engineering drawings for the building prior to
completion of the purchase and did not organise for any building inspection by a builder
or engineer or undertake any inquiries about the suitability of premises for the plaintiff’s
proposed use.
[70] Mr Mundy was aware that pallet racking on which air-conditioning units were stored
placed a downward force on the concrete slab but did not consider it necessary to inquire
about the engineering specifications for the concrete slab, because he assumed that the
building would be built to “the proper design” and he had never encountered a problem
before with racking in buildings (Transcript 1-57).
[71] The plaintiff obtained a quote from Elbowroom (Aust) Pty Ltd dated 26 April 2007 for
the supply, delivery and installation of racking and shelving to the building (exhibit 9).
Elbowroom used the product Colby shelving. The quote dealt with floor strength and
differential settlement in these terms:
“Colby fixing standards assume that the racks are directly fixed to concrete
floors with a minimum strength of 25 MPa. It is recommended to use 32 MPa
or higher concrete strength if floors are subjected to medium to heavy
pneumatic-tyred traffic.
Differential settlement is the condition encountered in a warehouse where one
part of the floor slab settles relative to another. While the floor slab may have
been level when it was initially constructed, the occurrence of differential
settlement will result in an out-of-level floor. From the point of view of rack
performance, the impact of floor slab differential settlement is that the non-
verticality of the rack may be increased to the point where it exceeds the
tolerances specified in AS 4084-1993.
-- 15 of 37 --
16
Please be aware of these limits and the effect of differential settlement. The
typical settlement encountered in most warehouses is span/360 over a 6 m x
6 m grid. This would normally be acceptable for most manually served racks
up to 6 m high.
Please consult your engineer to confirm suitability of your floor for the above
installation.”
[72] The plaintiff did not consult any engineer about the suitability of the floor of the building
for the installation of the racks and shelving by Elbowroom.
[73] The set out of the racks that were installed is shown in exhibit 5.
Problems experienced with the slab
[74] Mr Poole was employed by the plaintiff between May 2007 and October 2012 as the
warehouse logistics coordinator. The plaintiff commenced operating out of the subject
property within two or three weeks of the start of Mr Poole’s employment with the
plaintiff. There were two forklifts in use, an electric high reach forklift which was the
main forklift used that reached the high levels of the racking and a gas forklift used for
bulkier items and low level operations from the ground. Mr Poole first noticed an issue
with the slab within about one year of the commencement of his employment when the
forklift exited through the roller doors to the carpark area and it would get stuck in certain
areas of the ramp exit. Mr Poole noticed uniform falls across the exit to the carpark area
and then along the back wall of the warehouse. It worsened over the few months
following his first observations. Between 12 to 18 months after first noticing the problem,
the stabilisers on the bottom of the electric high reach forklift were getting stuck mainly
on the joins in the concrete at the back of the warehouse. Mr Poole also observed the
racking on the back wall leaning forward towards the roller doors and there was also a
problem with racks D and E where shims had to be placed under them to address the lean.
By the time Mr Poole left the plaintiff in October 2012, he considered the state of the slab
to be “absolutely totally unsafe”.
[75] Mr Poole recalled that the smaller to mid-range air-conditioning units weighed between
160 and 230 kilograms per unit and four of the 160 kilogram units could fit on each level
per bay. The larger units were 230 to 240 kilograms per unit and would be packed three
units on each level per bay. Smaller indoor units that weighed about 60 kilograms per
unit would be packed 12 units per level per bay.
[76] Mr McKinnon commenced employment with the plaintiff in September 2012 and took
over as warehouse manager from Mr Poole. He observed the expansion joints in the
warehouse were lifting and in one spot the slab had dropped up to 200mm. It got to the
stage where the electric forklift could not be driven over any of the expansion joints,
whether loaded or unloaded. Some of the racking was leaning out of plumb and had to
be packed up by at least 50mm with metal shims. It got to the point where five or six
bays of racking (out of 40 or 50 bays) had to be taped off, as they were not useable.
[77] Mr McKinnon explained that two standard sized Chep pallets fit into each bay and the
loading for the racking is two tonne per bay, ie 2,000 kilograms per bay, but on average
-- 16 of 37 --
17
they did not go over 1,020 kilograms per bay which comprised two of the heaviest units
at 510 kilograms per unit. The units that were heavier than 510 kilograms were not stored
on the racking, but on the floor.
[78] Mr Craig Loughlin was employed by the plaintiff as Queensland sales manager between
August 2010 and August 2015. The state of the floor of the warehouse was of concern
from the time Mr Loughlin commenced his duties. He observed severe cracking and
chunks taken out of the concrete from the forklifts. There was a severe lean on the racking
at the rear of the warehouse. There was a massive movement in the slab after the 2011
floods.
[79] Mr Loughlin had to respond to an incident report in 2011, as a result of the lean on the
racking. Elbowroom was engaged to repeg the legs on the racking. This was undertaken
in February/March 2011.
[80] Mr Gillroy of DDS sent a facsimile to Ms Melissa Soldatos of the plaintiff on 30 January
2008 which included a copy of the DEQ drawing S02(P2) and part of the note on drawing
S01 including the section on “Floor Slabs”. The coversheet merely stated “Following
find Copy of Plan with Notes as Discussed”.
[81] Mr Mundy first became aware in the middle of 2009 there was a problem with the
concrete slab, when the Queensland manager reported that the supports on the side of one
of the forklifts were hitting the concrete (Transcript 1-32).
[82] The plaintiff’s solicitors sent a letter to Mr Efstathis dated 13 October 2011 advising the
plaintiff had encountered difficulties with the slab of the building and requesting a copy
of the building contract and development approval and whether any instructions were
given directly to DEQ by the builder. By letter dated 28 October 2011 the plaintiff’s
solicitors advised Efstathis’ solicitors that the plaintiff was relying on the assignment
under the purchase contract in its favour of any rights that the seller may have had against
the builder, in view of the problems with the concrete slab in the warehouse. In response,
Efstathis’ solicitors submitted a deed of indemnity for the plaintiff’s signature, as
contemplated by the contract. The deed included a provision that the plaintiff would
indemnify Efstathis from all or any liabilities, costs or expenses that Efstathis may incur
or be liable for in respect of any proceedings and/or demand made upon the builder. It
does not appear that the deed was ever signed by the plaintiff.
[83] A contour survey of the concrete slab was undertaken by surveyor RPS on 6 June 2013.
Relevant statutory provisions
[84] It was common ground that at the relevant time the Building Act 1975 (Qld) required
building assessment work to be carried out by reference to the BCA. Under s 14(2) of
the Building Act, building work complies with the BCA only if it complies with the
relevant performance requirements under the BCA. It was also common ground that the
2006 version of the BCA was the applicable version for the purpose of considering
whether the subject building complied with the BCA. Section 45 of the Building Act
provides generally for building assessment work to be carried out by a building certifier.
-- 17 of 37 --
18
[85] Section 23(1) of the SBR was in force when the Form 15 was originally issued. There is
no material difference between that regulation and the equivalent provisions under the
Regulation.
[86] Section 17 of the Regulation provided:
“(1) Subject to section 18, a building certifier may decide an individual—
(a) is, or has from a particular day been, competent to perform
functions that help (design/specification help) the certifier
perform building certifying functions for building design or
specification; or
(b) is, from the making of the decision, competent to perform
functions that help (inspection help) the certifier perform
building certifying functions for the inspection of assessable
building work.
(2) The decision may be that the individual may give the building
certifier—
(a) design/specification help or inspection help generally; or
(b) help limited to a particular aspect of design/specification help
or inspection help; or
(c) design/specification help or inspection help only for
particular assessable building work.
(3) An individual the subject of a decision under subsection (1) is a
competent person.
(4) A competent person decided under subsection (1)(a) is a competent
person (design/specification).
(5) A competent person decided under subsection (1)(b) is a competent
person (inspections).
(6) A person may be decided to be a competent person
(design/specification) and a competent person (inspections) at the same
time or for the same matter.”
[87] Section 18 of the Regulation required that if a relevant law required the individual to be
licensed or registered give the help to the building certifier, then the individual must be
so licensed or registered. It was common ground that Mr Henry had the appropriate
registration to be qualified as a competent person to give both design/specification help
and inspection help to the builder and certifier.
[88] In order for a competent person to give a certificate that a building design or specification
will (if installed or carried out under the certificate) comply with the building assessment
provisions, s 46 of the Regulation required the certificate to comply with s 48 which
provides:
“A certificate by a competent person must—
(a) be in the approved form; and
-- 18 of 37 --
19
(b) be signed by the competent person; and
(c) state in detail—
(i) the basis for giving the certificate; and
(ii) the extent to which the person has relied on tests,
specifications, rules, standards, codes of practice or other
publications.”
Building Code of Australia
[89] The structure of the BCA is set out in clause A0.3. Each part comprises objectives,
functional statements, performance requirements with which all building solutions must
comply and the building solutions. Under clause A0.4 a building solution will comply
with the BCA if it satisfies the performance requirements. Clause A0.6 provides the
objectives and functional statements may be used as an aid to interpretation.
[90] Part B1 covers structural provisions. The objective of Part B1 is set out in clause BO1:
“(a) safeguard people from injury caused by structural failure; and
(b) safeguard people from loss of amenity caused by structural behaviour;
and
(c) protect other property from physical damage caused by structural
failure; and
(d) safeguard people from injury that may be caused by failure of, or impact
with, glazing.”
[91] The relevant functional statement is found in clause BF1.1:
“A building or structure is to withstand the combination of loads and other
actions to which it may be reasonably subjected.”
[92] The performance requirement is then set out in clause BP1.1(a) in these terms:
“A building or structure, to the degree necessary, must-
(i) remain stable and not collapse; and
(ii) prevent progressive collapse; and
(iii) minimise local damage and loss of amenity through excessive
deformation, vibration or degradation; and
(iv) avoid causing damage to other properties, by resisting the actions
to which it may reasonably be subjected.”
[93] Under clause BP1.1, a list of actions to be considered to satisfy paragraph (a) are then set
out including imposed actions (live loads from occupancy and use), differential
movement, time dependent effects (including creep and shrinkage) and ground movement
caused by swelling, or shrinkage of the subsoil.
[94] Clause BP1.2 then provides:
“The structural resistance of materials and forms of construction must be
determined using five percentile characteristic material properties with
appropriate allowance for-
(a) known construction activities; and
(b) type of material; and
-- 19 of 37 --
20
(c) characteristics of the site; and
(d) the degree of accuracy inherent in the methods used to assess the
structural behaviour; and
(e) action effects arising from the differential settlement of foundations,
and from restrained dimensional changes due to temperature, moisture
shrinkage, creep and similar effects.”
[95] The specific conditions of the fourth defendant’s development application decision notice
showed that DEQ’s Form 15 certifying compliance with Parts B1.1, B1.2, B1.3, B1.4 and
C1.11 had been relied upon.
Expert structural engineering evidence
[96] The plaintiff engaged structural and civil engineer Mr Stephen Healey of New South
Wales based Eclipse Consulting Engineers Pty Ltd to provide a number of expert reports
for the proceeding. These reports are dated 1 August 2013, 20 November 2014 and 6
May 2016 (exhibit 45). DEQ and Mr Henry engaged structural and geotechnical engineer
Mr Peter Wright of Hughes, Beal & Wright Pty Ltd as their expert engineer for the
purpose of the proceeding. Mr Wright’s reports are dated 11 July 2013, 17 November
2013, 28 November 2013 (exhibit 46), 23 March 2015 and 10 June 2015 (exhibit 47). Mr
Healey and Mr Wright prepared a joint report dated 26 March 2014 and a supplementary
joint report dated 17 April 2015. They gave evidence concurrently.
[97] By the time the joint report was prepared, there was much common ground. Both
engineers proceed on the basis that DEQ had general knowledge of the site conditions of
“a thickness of marine clay overlying stronger strata” and was not aware of the intended
use of the building, when designing the slab. Mr Healey is of the view that a floating slab
was not appropriate due to the anticipated total and differential settlements. Mr Wright
considers that the decision to use a floating slab was made by others, in light of the
warnings issued by DEQ regarding settlement and differential settlement, and that DEQ’s
actions were that of a competent engineering practice. Whereas Mr Wright considers that
it was competent engineering practice to inform the client of the risks associated with the
floating slab option, as well as offering more robust and stable options, Mr Healey
considers that DEQ should have insisted that the floating slab design was not suitable due
to the lack of tolerance to vertical movement. In the supplementary joint report Mr
Healey considers that the magnitude of the differential settlements nominated meant that
both options 1 and 2 in the first report could not result in compliance with the BCA. Both
experts agree that DEQ did everything that was reasonable to advise the client of the risks
associated with the floating slab design.
[98] The experts agree that the slab settlement was due to consolidation of the underlying
marine clays. They also agree that compaction, or the lack of compaction, if any fill were
placed on the site, was largely irrelevant to the settlement.
[99] One issue on which these experts disagree is whether there has been compliance with the
BCA for the design of the building. Mr Healey is of the view that the lack of piling to
the floor slab and allowing it to settle and move demonstrates a lack of compliance with
the BCA.
-- 20 of 37 --
21
[100] Mr Healey starts in part B1 of the BCA with the objective, functional statement and
performance requirements that applied generally to a building or structure. Mr Wright
agrees with Mr Healey’s views about these statements reminding a structural engineer of
the overall aim in relation to safeguarding people and property from injury caused by
structural failure, but that the guidance in implementing the aims of the BCA is obtained
from the Australian standards.
[101] Both experts agree that the BCA provided for reference to the loading code of AS 1170.1
and the requirements of this standard were complied with.
[102] Both experts agree that AS 3600-2001 relating to concrete structures applied to the
project. Mr Wright notes that that standard makes no reference to T48 and that DEQ was
not bound to follow the recommendations in T48, but Mr Healey considers that, if the
design method in accordance with T48 were not used, the engineer would need to
demonstrate that Australian Standard and BCA compliance could be achieved without
following the T48 recommendations. His view is that, due to the excess settlement
predicted on this site, the structural design of the slab would not have been possible using
T48, so that the only appropriate slab design would be a suspended slab supported by
piles founded in the deep stable material.
[103] Mr Healey relies on the introductory comments in T48:
“Many industrial pavement projects are part of a property-development
package the designer of which often having little or no knowledge of future
tenants and their operating requirements. Selecting the lowest-initial-cost
solution may provide short-term performance and meet normal operating
requirements in the first few years. However, a change of tenancy and the
introduction of mechanical equipment may cause sufficient distress to disrupt
the use of the building until repairs have been completed. It is recommended
that the designer considers the life-cycle cost of the pavement, including
initial construction costs, maintenance and disruption costs to the business,
when selecting the payment system.
The designer should always ask to be made aware of the pavement operating
requirement and state this on the pavement layout drawing. Also, the designer
will need to consider construction loading, and that the pavement may be
subjected to semi-trailers and fork lift trucks during and after the completion
of the building.”
[104] Mr Healey considers that a structural engineer provides expert advice and guides the
client in the direction that it needs to go to find an appropriate structural solution
(Transcript 6-105). By way of contrast, Mr Wright explains that the structural engineer
gives the client sensible options, but that it is ultimately the client who decides, because
he is the one “with the purse strings” and has to make a decision as to low cost
construction with high maintenance or high cost construction with low maintenance
(Transcript 6-105). In fact Mr Wright’s comments are consistent with the dichotomy
contemplated in the introductory comments to T48 between lower construction costs and
higher maintenance costs on the one hand and higher construction costs that may
accommodate a variety of uses and have lower maintenance costs on the other hand.
-- 21 of 37 --
22
[105] Mr Wright and Mr Healey also differ on whether section 2 of AS 3600-2001 applied to
the design of a floating slab on ground. Clause 2.1.1 sets out the aim of structural design,
namely to provide a structure that is “durable, serviceable and has adequate strength
whilst serving its intended function and that satisfies other relevant requirements such as
robustness, ease of construction and economy”. Clause 2.4.1 then states that the structure
and its component members shall be designed for serviceability by controlling or limiting
the deflection, lateral drift, cracking and vibration in accordance with the requirements of
clauses 2.4.2 to 2.4.5. Mr Healey considers that table 2.4.2 which sets out limits for
calculated deflection of beams and slabs had some general relevance to the design of a
slab on ground, although he concedes that the table applies to suspended members and
was not strictly applicable to slabs on ground. Mr Healey considers that, by reference to
serviceability, the slab in this building failed (Transcript 6-95). Mr Wright considers that
a slab on ground is not part of the structure as such and table 2.4.2 does not set deflection
requirements for a slab on ground.
[106] Both Mr Wright and Mr Healey agree that clause 16.2.1 was the most relevant clause of
AS 3600 for the design of the slab on ground. They differ, however, on how they interpret
clause 16.2.1 in its application to the design of a slab on ground. Mr Healey is of the
view that the designer must take into account a variety of possible uses for the slab over
the life of the building. Mr Wright considers the designer is bound to act on the
instructions of the owner, as to the performance of the slab. Mr Wright considers that if
the owner deems the amount of settlement as acceptable to the owner, then the designer
will have satisfied the obligations under section 16 (Transcript 6-86). Mr Healey did
concede that the owner’s requirement in the form of budgetary constraint would not be
irrelevant, but the engineer would still need to make decisions based on the BCA as to
what type of floor system would be suitable to be constructed (Transcript 6-88).
[107] Consistent with Mr Healey’s view that the slab of the building should be designed for the
different uses of the building over its life, his view is that the engineer would take into
account a variety of racking layouts in designing the slab (Transcript 6-121). For that
reason he would not have expected a schematic diagram such as exhibit 33 to be included
in the engineering drawings. When challenged on that, he explains (Transcript 6-122)
that he expected the purchaser would make inquiries as to whether the slab could take the
loads required for their racking “and that would be typically nominated on the structural
drawings provided with the sale documents, I assume”.
[108] Mr Wright attended the site on 8 November 2013 to witness the boring of a 150mm
diameter core hole through the floor slab near a column in the back right hand corner of
the building. Mr Wright formed the view from that inspection that void formers were not
provided beneath the slab where it sat above the pile headstock at this column, as required
on drawing S03. Mr Wright subsequently resiled from that opinion, when he saw
remnants of void formers when the slab was removed which are shown in the photographs
he took (exhibit 18). Mr Wright in his report dated 17 November 2013 recorded his
observation at the location at which the hole was bored that:
“The floor slab at this location is distorted in a manner similar to a number of
locations around the building, namely at the base of each column. The slab
is ‘hung up’ on the pile headstocks. By ‘hung up’ I mean the slab over the
headstocks has not been allowed to settle to the same degree as the slab
supported on the ground surface.”
-- 22 of 37 --
23
[109] Mr Wright explains (Transcript 6-116) that there were localised high spots on the back
wall and on the left hand wall where the slab was hung up on the pile caps and the bulk
of the rest of the slab was reasonably flat. Mr Healey and Mr Wright agree that the void
formers failed to perform their function and that in the process of casting the slab,
concrete was allowed to flow down behind the plastic membrane and reach the gap
between the top of the pile cap and the underside of the slab (Transcript 6-117).
Valuation evidence
[110] The valuer Mr Craig Ehlers was briefed by DEQ and Mr Henry to investigate sales of
comparable industrial buildings similar to the subject property to ascertain whether there
was any demonstrable difference in values for buildings with varying floor types. For the
purpose of his report (exhibit 48), he researched all sales of industrial buildings in the
suburbs of Hemmant and Lytton between January 2006 and January 2008. Mr Ehlers
noted that the plaintiff’s purchase of the property was at a value of $1,677 per square
metre of the building area which was at the lower end of values for modern industrial
buildings in the locality during that period.
[111] Mr Ehlers relied on input from Mr Henry as to the nature of the slab construction for the
industrial buildings which he selected as the most comparable to the subject property for
type and size of building. Mr Ehlers concluded that there is little or no difference in the
per square metre value of properties with buildings of varying floor types, such as slab
on ground, supported slab floors, or buildings with piered floors. During cross-
examination Mr Ehlers conceded that there was limited sales evidence of constructions
other than slab on ground on which to base his conclusion, but he was satisfied that, on
the sales evidence, if two industrial buildings looked the same, but one had a suspended
slab and the other a slab on ground, that was unlikely to result in a different market price,
as his research showed the market price was based on the floor area.
Expert geotechnical evidence
[112] The plaintiff engaged geotechnical engineer Mr Michael Riley of Morrison Geotechnic
Pty Ltd to give evidence on a number of aspects relevant to the settlement of the concrete
slab. Mr Riley’s reports are dated 8 July 2013, 27 August 2013 and 28 April 2016 (exhibit
50). Geotechnical engineer Dr Philip Shaw of Shaw Urquhart Pty Ltd prepared a report
dated 5 December 2013 for DEQ and Mr Henry. Mr Riley and Dr Shaw prepared a joint
report dated 1 April 2014 and gave evidence concurrently.
[113] The experts agree that the site is located on the Brisbane floodplain in an area known to
be underlain by deep alluvial deposits which may be sufficiently soft and compressible
to settle under the expected development loads.
[114] These experts agree that the actual measured floor slab settlement of 160mm is more than
the settlement of 100mm advised in the first report, but is less than the settlement of
250mm advised in the second report.
Expert evidence on the role of the building certifier
-- 23 of 37 --
24
[115] Three witnesses gave concurrent evidence relevant to the role undertaken by the building
certifier. Mr Wright gave evidence again. The plaintiff called Mr Michael Moran, an
accredited building certifier, whose report was dated 2 August 2013. The third witness
was Mr Mark Catchpole whose report dated 13 December 2013 (exhibit 51) had been
prepared when he was engaged by the solicitors acting for the fourth and fifth defendants.
Mr Catchpole was called in the trial by DEQ and Mr Henry. The three witnesses had also
prepared a joint report dated 27 March 2014. Mr Catchpole and Mr Moran had also
prepared a joint report dated 27 March 2014 (exhibit 52).
[116] Mr Moran and Mr Catchpole agree that the development application decision notice dated
2 March 2007 was an approval for the proposed use of a commercial warehouse building
in class 8 which is for an industry/factory type usage, rather than a warehouse which is
class 7B (Transcript 7-65). The approval did not extend to fit out works and Mr Moran
and Mr Catchpole agree that a further building development approval would have been
required to fit out the building with racking, office layout or internal partitions (Transcript
7-69).
[117] Mr Catchpole notes that a class 8 factory type building would typically have work
benches and places for assembling or processing things, rather than storing equipment
stacked seven or eight metres high. That is in contrast to a warehouse building where the
expectation is for use for storage. Mr Moran is of the opinion that, from the certifier’s
perspective, there is a design for the building which the certifier accepts and approves the
application on the basis of that design and it does not necessarily follow from the fact that
a building will be classified as class 8 that the slab will not be able to bear significant
loads. Mr Wright agrees that a class 8 building does not define a specified live load, but
if the floor was to bear very heavy machinery, that would be a matter for the engineer to
take into account in designing the building.
The standards applicable to the design of the slab
[118] Before evaluating whether a duty of care was owed by DEQ and Mr Henry to avoid
economic loss to the subsequent purchaser of the building arising out of the design of the
slab on ground, it is necessary to consider the nature of the design flaw alleged by the
plaintiff which is otherwise expressed as whether a slab on ground should ever have been
considered as a feasible option for this building. I proceed on the basis of the expert
evidence of Mr Wright and Mr Healey that the settlement of the slab was due to
consolidation of the underlying marine clays.
[119] This is a curious building case. As was submitted by Mr Musgrave, this is not a case
where the slab was not constructed in accordance with the drawings. It was also not a
case where the design fault alleged by the plaintiff resulted in failure of the building
structure, apart from the problems arising from the settlement of the slab. The plaintiff’s
problems with the building were confined to the uneven levels of the floor slab and
consequent chipping and cracking of the concrete. As designed, the slab on ground was
intended to move independently of the walls of the building which were on piles. The
settlement of the concrete slab was unsatisfactory for the plaintiff’s use of the building,
but that does not answer the question whether the design of the slab as a slab on ground
failed to conform with the applicable standards.
-- 24 of 37 --
25
[120] In undertaking the structural design, DEQ and Mr Henry had to comply with the BCA
and the codes that were incorporated which relevantly included AS 1170.1 and AS 3600-
2001. (Although T48 may be in common use and is an industry standard, it is not
mandated by AS 3600-2001 and other references, such as the British version of T48 used
by Mr Henry, are also in use in designing concrete floors. In any case T48 addresses
surface finishes and not ground movement issues due to consolidation.)
[121] An industrial building can be contrasted with a house which has one use. An industrial
building may have many uses, as canvassed in the evidence of Mr Healey and Mr Wright.
Sometimes an industrial building may be purpose built for a use that requires a
performance outcome that may not be necessary for other uses, such as a floor that will
support a coldroom (exhibit 38).
[122] The plaintiff sought to make much in the cross-examination of Mr Henry and submissions
of the use of the term “warehouse” to describe the subject building such as in DEQ’s fee
proposal, the description of the slab in the Form 16 and the development application
decision notice. The use of such term, however, is not definitive of the quality of the
construction or the range of uses for which the building was designed. This is illustrated
by the fact that development application decision notice was for building work for
“industry/warehouse” that had been assessed with building classification class 8. Table
3.1 in AS 1170.1 sets out different imposed actions appropriate to the type of activity or
occupancy for which the floor area will be used. A class 8 building includes factories,
workshops and similar buildings (general industrial) and Table 3.1 provides for a
reference value of 5.0 kPa, whereas the use of a class 7b building for warehousing and
storage areas with areas subject to accumulation of goods attracts in Table 3.1 the
reference value of imposed actions of 2.4 kPa for each metre of storage height.
[123] Mr Healey’s approach to what is required of an engineer in designing a concrete slab for
an industrial building would result in a building built for all possible industry or
warehouse purposes, irrespective of the anticipated use or the owner’s requirements. I
accept that, if the owner’s requirements were so ridiculous that the building as constructed
would not comply with the BCA for the least intensive use appropriate for that type of
building within the relevant BCA classification, the engineer could not rely on the
owner’s requirements to absolve the engineer from exercising the professional skill and
judgment in designing the building to comply with the BCA. Mr Fernon’s submission
that Mr Henry’s evidence that in this case the client could have the slab on ground, if that
was what it wanted after the advice given by Mr Henry, amounts to the client rather than
the BCA or the statutory requirements dictating the design overstates the effect of Mr
Henry’s evidence which was given in the context of the circumstances of DEQ’s design
of the slab on ground for the subject building.
[124] There must be some scope for what amounts to “undue … settlement” for the purpose of
clause 16.2.1 of AS 3600-2001, as the description “undue” is itself not one of precision.
Mr Healey’s strict view that the magnitude of the anticipated settlements and differential
settlements precluded DEQ’s options 1 and 2 in the first report from demonstrating
compliance with the BCA is difficult to reconcile with the evidence of numerous other
industrial buildings in the vicinity also being slab on ground constructions. I am
persuaded by Mr Wright’s evidence which supports Mr Henry that, in the circumstances
in which Mr Henry designed the slab on ground, including the warnings in the first and
-- 25 of 37 --
26
second reports, the design was of a slab, “without undue differential or uniform
settlement” and therefore compliant with the BCA.
[125] It follows from this conclusion that there was no breach by DEQ and Mr Henry of relevant
design standards in designing the slab for the subject building as a slab on ground. That
conclusion has the consequence that the issuing of the Form 15 was not a breach of either
the SBR or the Regulation.
Did DEQ and/or Mr Henry owe any duty of care to the plaintiff in respect of the
design and/or certification of the floor slab?
[126] If DEQ and Mr Henry were shown to have designed a slab which was not consistent with
the standard of skill reasonably expected of a professional engineer, the submissions in
the trial focussed on the issue of whether any duty of care was imposed on DEQ and/or
Mr Henry and owed to the plaintiff in respect of the design and/ or certification of the
concrete floor slab. This raises the issue of whether the plaintiff was affected by
vulnerability in the sense referred to in Woolcock Street Investments Pty Ltd v CDG Pty
Ltd (2004) 216 CLR 515 and Brookfield Multiplex Ltd v Owners Corporation Strata Plan
61288 (2014) 254 CLR 185.
[127] Woolcock concerned whether a subsequent purchaser of a warehouse and office complex
had a cause of action in negligence against the engineers who designed the foundations,
when it was discovered by the purchaser that the building suffered substantial structural
distress due to settlement of the foundations. The purchaser alleged the engineers owed
it a duty to take reasonable care in designing the foundations for the building. A case had
been stated for the Court of Appeal on the basis of agreed facts to determine as a
substantive question of law whether the statement of claim disclosed a cause of action in
negligence against the respondents. It was held by the majority in the High Court that the
engineers did not owe to the purchaser a duty to take reasonable care on the facts alleged
in the statement of claim and agreed in the case stated. The damage which the appellant
alleged it had suffered was pure economic loss. The concept of vulnerability was
explained by the plurality at [23]:
“Since Caltex Oil, and most notably in Perre v Apand Pty Ltd, the
vulnerability of the plaintiff has emerged as an important requirement in cases
where a duty of care to avoid economic loss has been held to have been owed.
‘Vulnerability’, in this context, is not to be understood as meaning only that
the plaintiff was likely to suffer damage if reasonable care was not taken.
Rather, ‘vulnerability’ is to be understood as a reference to the plaintiff's
inability to protect itself from the consequences of a defendant's want of
reasonable care, either entirely or at least in a way which would cast the
consequences of loss on the defendant.” (footnotes omitted)
[128] In Woolcock, the original owner of the land refused to pay for geotechnical investigations,
so that it was noted at [25] that the relationship was one “in which the original owner
asserted control over the investigations which the engineer undertook for the purposes of
performing its work”, at [26] that “the appellant did not allege that the relationship
between the respondents and the original owner was characterised by that assumption of
responsibility by the respondents, and known reliance by the original owner on the
-- 26 of 37 --
27
respondents, which is referred to in the joint reasons in Bryan v Maloney”, and at [27]
that the anterior step of demonstrating that the respondents owed a duty of care to the
original owner was not made out. The plurality also noted at [28] that the terms of the
contract between the original owner and the respondents “is not an irrelevant
circumstance” in considering what duty the engineers owed others.
[129] The plurality made the following observations on the issue of vulnerability at [31]:
“Neither the facts alleged in the statement of claim nor those set out in the
Case Stated show that the appellant was, in any relevant sense, vulnerable to
the economic consequences of any negligence of the respondents in their
design of the foundations for the building. Those facts do not show that the
appellant could not have protected itself against the economic loss it alleges
it has suffered. It is agreed that no warranty of freedom from defect was
included in the contract by which the appellant bought the land, and that there
was no assignment to the appellant of any rights which the vendor may have
had against third parties in respect of any claim for defects in the building.
Those facts describe what did happen. They say nothing about what could
have been done to cast on the respondents the burden of the economic
consequences of any negligence by the respondents. The appellant’s pleading
and the facts set out in the Case Stated are silent about whether the appellant
could have sought and obtained the benefit of terms of that kind in the
contract.”
[130] This issue of vulnerability was revisited by the High Court in Brookfield. The appellant
builder had constructed a 22 storey building under a design and construct contract with
an owner/developer for a contract price of more than $57 million. There was provision
in the contract for a defects liability period of 52 weeks which commenced upon practical
completion. Under the contract, a final certificate was evidence that the works had been
completed in accordance with the contract, subject to an exception in cl 42.6(b) of the
contract that applied to any defect in the works that was not apparent at the end of the
defects liability period or which would not have been disclosed upon reasonable
inspection at the time of the issue of the final certificate. A strata scheme was registered
in respect of levels one to nine which comprised serviced apartments. The developer
entered into a master agreement with an operator pursuant to which the apartments were
leased to the operator to be operated collectively as a serviced apartment hotel. The
developer onsold the strata-titled apartments to purchasers who were investors, using a
standard form contract annexed to the design and construct contract, and those purchases
were subject to the lease to the operator. Under the relevant legislation for strata schemes,
the first respondent as the body corporate held the common property as agent for the
owners of the individual lots as tenants in common in shares proportional to the unit
entitlements of the respective lots. The first respondent sued the appellant for the cost of
rectifying latent defects in the common property, on the basis the appellant owed a duty
to take reasonable care to avoid a reasonably foreseeable economic loss to the first
respondent in having to repair the consequences of the latent defects caused by the
defective design and/or construction. These defects were not alleged to have caused any
damage to person or property, but the first respondent’s claim was for damages for pure
economic loss. The issue on appeal was whether the appellant owed the first respondent
a duty of care. Woolcock was applied by the High Court and there was found to be no
duty of care owed by the appellant to the first respondent.
-- 27 of 37 --
28
[131] Relevant conditions of the standard form contract were summarised at [16]-[17],
including that the developer had to cause the property and the common property to be
finished in accordance with the schedule of finishes and in a proper and workmanlike
manner, the developer was obliged to repair defects in the common property due to faulty
materials or workmanship of which written notice was served on it by the first respondent
within seven months after the date of the registration of the strata plan. There was also
provision for a purchaser of a lot to serve a notice of special faults which were structural
or required urgent attention or might cause danger to persons in the property or make the
property uninhabitable.
[132] French CJ observed in Brookfield at [22] that in the context of determining the existence
of a duty of care for pure economic loss, the notion of vulnerability refers to “the
plaintiff’s incapacity or limited capacity to take steps to protect itself from economic loss
arising out of the defendant’s conduct”. According to French CJ at [30], the
determination of the appeal required consideration of the relationship between the first
respondent and the appellant, including whether the appellant owed the developer a
relevant duty of care and whether the first respondent was vulnerable.
[133] After noting at [34] that the purchasers of lots from the developer were “effectively
investors in a hotel venture under standard form contracts which were an integral part of
the overall contractual arrangements”, French CJ stated:
“The standard form contract contained specific provisions relating to the
construction of the building and [the developer’s] obligations to undertake
repairs. Those provisions have already been mentioned. This is not a case in
which, for the purposes of the subsistence of a duty of care, the subsequent
owners could be regarded as vulnerable. Nor, therefore, could the Corporation
as their statutory ‘agent’. The position of the subsequent owners and the
interaction of the contractual and statutory frameworks are antithetical to the
proposition that Brookfield owed the Corporation the duty of care found to
exist by the Court of Appeal.”
[134] French CJ concluded at [35] that the relationship between the appellant and the first
respondent was not analogous to the relationship in Bryan v Maloney (1995) 182 CLR
609, but analogous, although not identical to the position of the purchase of the complex
in Woolcock.
[135] Hayne and Kiefel JJ at [57] noted that reliance of the purchasers of the lots and the first
respondent on the appellant doing its work properly may be a necessary element in
demonstrating vulnerability, but it is not a sufficient element, and expressed that
“vulnerability is concerned with a plaintiff’s inability to protect itself from the
defendant’s want of reasonable care, either entirely or at least in a way which would cast
the consequences of loss on the defendant”. Hayne and Kiefel JJ concluded at [58]:
“It is neither necessary nor profitable to attempt to define what would or
would not constitute vulnerability. It is enough to observe that both the
developer and the original purchasers made contracts, including the standard
contracts, which gave rights to have remedied defects in the common property
vested in the [first respondent]. The making of contracts which expressly
provided for what quality of work was promised demonstrates the ability of
-- 28 of 37 --
29
the parties to protect against, and denies their vulnerability to, any lack of care
by the builder in performance of its contractual obligations. It was not
suggested that the parties could not protect their own interests. The builder
did not owe the [first respondent] a duty of care.” (footnote omitted)
[136] Crennan, Bell and Keane JJ also emphasised at [67] that it was of critical importance to
the success of the appellant on the appeal that the first respondent’s claim was “based on
the failure of the purchasers of the apartments to get value for money from the developer
rather than on the appellant’s causing damage to the [first] respondent’s property”.
[137] They stated at [69]:
“This Court's decision in Bryan v Maloney does not sustain the proposition
that a builder that breaches its contractual obligations to the first owner of a
building is to be held responsible for the consequences of what is really a bad
bargain made by subsequent purchasers of the building. To impose upon a
defendant builder a greater liability to a disappointed purchaser than to the
party for whom the building was made and by whom the defendant was paid
for its work would reduce the common law to incoherence. Moreover, to hold
that a subsequent purchaser of a building is vulnerable to the builder so far as
the risk of making an unfavourable bargain for its acquisition is concerned
would involve a departure from what was held by this Court in Woolcock
Street Investments.” (footnotes omitted)
[138] Crennan, Bell and Keane JJ explained in Brookfield at [130]:
“Vulnerability, in this field of discourse, is concerned not only with the
reasonable foreseeability of loss if reasonable care is not taken by the
defendant, but also, and importantly, with the inability of the plaintiff to take
steps to protect itself from the risk of the loss.”
[139] After quoting passages from [31] and [96] in Woolcock, they further explained at [132]:
“These passages accord with the primacy of the law of contract in the
protection afforded by the common law against unintended harm to economic
interests where the particular harm consists of disappointed expectations
under a contract. The common law has not developed with a view to altering
the allocation of economic risks between parties to a contract by
supplementing or supplanting the terms of the contract by duties imposed by
the law of tort.” (footnote omitted)
[140] The remaining member of the court in Brookfield, Gageler J explained at [185] the
rationale for not imposing a duty of care in tort on a builder in carrying out building work
to a subsequent purchaser for defective building in these terms:
“Absent any application that Bryan v Maloney should be overruled, and
absent data which might permit the making of a value judgment different from
that made in Woolcock Street Investments, the view expressed by McHugh J
in Woolcock Street Investments should in my opinion be accepted. The
continuing authority of Bryan v Maloney should be confined to a category of
-- 29 of 37 --
30
case in which the building is a dwelling house and in which the subsequent
owner can be shown by evidence to fall within a class of persons incapable
of protecting themselves from the consequences of the builder's want of
reasonable care. Outside that category of case, it should now be
acknowledged that a builder has no duty in tort to exercise reasonable care,
in the execution of building work, to avoid a subsequent owner incurring the
cost of repairing latent defects in the building. That is because, by virtue of
the freedom they have to choose the price and non-price terms on which they
are prepared to contract to purchase, there is no reason to consider that
subsequent owners cannot ordinarily be expected to be able to protect
themselves against incurring economic loss of that nature.”
[141] The plaintiff relies on the fulfilment of a statutory function by Mr Henry in issuing the
Form 15 as relevant to the issue of vulnerability of the plaintiff in the circumstances. In
particular, the plaintiff relies on the series of cases of Bamford v Albert Shire Council
[1998] 2 Qd R 125, Moorabool Shire Council v Taitapanui (2006) 14 VR 55, and Western
Districts Developments Pty Ltd v Baulkham Hills Shire Council (2009) 75 NSWLR 706.
[142] In Bamford, the Court of Appeal at 126-127 and 131 applied Sutherland Shire Council v
Heyman (1985) 157 CLR 434 to hold that a local authority in exercising its statutory
function of considering whether or not to grant approval of an application for a
subdivision of land owed a duty of care to a subsequent purchaser of one of the subdivided
lots not to carry out that function negligently.
[143] One of the considerations for the council’s exercise of its statutory function was whether
the subject land was fit for residential purposes. When the council approved the
subdivision, there was a risk of land slipping on the lot in question. The house that the
purchaser built on the land became uninhabitable and valueless because of movement of
earth and rock on the lot. The council’s appeal against the finding of liability on its part
was unsuccessful. One of the members of the court, McPherson JA, noted at 126:
“The effect of exercising its power of approving an application for
subdivision is to create a series of new allotments that would otherwise not
be available for purchase and use by members of the public for residential
purposes.”
[144] Bamford was therefore concerned with the council’s exercise of the statutory function
that was an integral step in the creation of the lot that was then available for purchase for
the purpose of constructing a house for which it was not suitable. Once the stock of land
was available through subdivision for sale, there was no opportunity for a purchaser of
the subdivided lot to propose any conditions for the contract pursuant to which the
subdivided lot was purchased that could protect the purchaser against the risk that
eventuated. The subject matter of Bamford was a residential property where the
purchasers fell within the category of having no capacity to protect themselves against
the risk that would have been addressed, if the council had not been negligent in
exercising its statutory function, making the approach in Bryan v Maloney applicable.
[145] Moorabool concerned whether a building surveyor who was employed by Moorabool
Shire Council, authorised by the relevant legislation, and permitted by his employer (for
-- 30 of 37 --
31
which the employer was remunerated) to act as a private building surveyor in other
council areas to issue building permits owed a duty of care to Mr and Mrs Taitapanui as
subsequent purchasers of a house built pursuant to a building permit granted by him
outside the Moorabool Shire Council area. It was subsequently ascertained, after Mr and
Mrs Taitapanui purchased the property, that there were serious structural deficiencies
with the house. The wrong type of footing system was specified on the plans submitted
to the building surveyor with the application for the building permit. It was found that
the building permit should never have issued on the basis of the plans and other
documents lodged with the building surveyor (at [65]).
[146] The court held that the building surveyor and his employer owed a duty of care to Mr and
Mrs Taitapanui and were liable for pure economic loss. Maxwell P largely agreed with
the joint judgment of Ormiston and Ashley JJA, but also gave additional reasons.
[147] Mr and Mrs Taitapanui were held to be vulnerable, in the sense described in the judgment
of the plurality in Woolcock. The relevant law was summarised in the joint judgment of
Ormiston and Ashley JJA as follows:
“[70] Over the past 30 years, there has been recurrent, intensive, consideration
– at the highest judicial levels in Australia and elsewhere – of the
circumstances in which a duty of care will arise to avoid causing pure
economic loss. No occasion arises in this appeal to rehearse at any length the
chain of case law through which the principles have been developed and
refined. It is sufficient for present purposes if we identify what appear to us
to be pertinent considerations, as the law now stands in Australia.
[71] The categories of case in which a duty of care with respect to pure
economic loss is to be found are properly to be seen as special. Foreseeability
of loss, and an unbroken chain of causation, are necessary elements, but by
themselves are not sufficient. An additional element which must be present
has been variously described as involving one or more of known reliance or
dependence of the plaintiff; the assumption of responsibility by the defendant;
or the control exercised, or exercisable, by the defendant over the
circumstances affecting the plaintiff’s interests. What ultimately determines
whether a duty of care arises is the character of the relationship between the
plaintiff and the defendant. Matters such as those which we have just
mentioned, and others, bear upon the resolution of that question in the
particular circumstances of particular cases; though not all of those matters
will be at the forefront in every case. The question to be answered is whether,
having regard to the salient features of the particular case, the connection
between the parties is sufficiently close – though not necessarily physically
close – as to give rise to a duty of care. When the defendant’s acts or
omissions arise in connection with the discharge of statutory duties or the
performance of statutory functions, the statutory framework is itself a salient
feature to which consideration must be given.
[72] To those considerations should be added the following: Three policy
considerations are pertinent in every case. First, that the effect of a decision
should not lay a defendant open to claims which are indeterminate as to the
class or number of potential claimants, time or amount. Second, that the effect
of a decision should not be to unduly hinder ordinary commercial transactions
-- 31 of 37 --
32
(or, be inconsistent with normal business standards). Third, that a decision
should not have the effect of intruding into another area of the law.”
[148] The Victorian legislative scheme in relation to building permits, including a permit
register that was able to be searched by a purchaser and a requirement that the vendor of
a residential property must before the purchaser signs the contract give the purchaser a
statement particularising any building permit in the preceding seven years in relation to
the property, was relevant to the determination by Ormiston and Ashley JJA of the
purchaser’s vulnerability to the negligence of the building surveyor in issuing the permit
for the subject house that had the effect of conveying that the building work would comply
with the relevant building legislation and regulations. The relevance was also noted at
[156] that “for most people the purchase of a home is a major personal decision, that the
structural soundness of the home is of first importance, and that homes are often enough
the subject of resale”.
[149] The position of Mr and Mrs Taitapanui as subsequent purchasers of a residential home is
very different to the position of the plaintiff in purchasing a building for the purpose of
conducting its commercial enterprise.
[150] Western Districts also concerned the exercise by a local council of a statutory power as
the principal certifying authority appointed by the developer under s 109E of the
Environmental Planning and Assessment Act 1979 (NSW) (EPA). It was held that a duty
of care was owed by the council to a purchaser of an allotment from the subdivision of
land that was created, as a result of the issue of the subdivision certificate by the council
that authorised the registration of the plan of subdivision.
[151] In exercising the power to issue the subdivision certificate, s 109J of the EPA precluded
the issue of the certificate unless the certifying authority was satisfied of each of the
specified matters, including that the applicant had complied with all conditions of the
development consent which were required to be complied with before the subdivision
certificate may be issued in relation to the plan of subdivision and, where the land was
within a water supply authority’s area of operations, that the applicant had obtained a
certificate of compliance from the water supply authority with respect to the subdivision
of the land. The developer had not applied for a certificate of compliance from the
relevant water supply authority. Notwithstanding that failure, the council issued a
subdivision certificate for the subdivision. After the purchaser completed the purchase,
it was ascertained that $47,511 was owed to the relevant water supply authority which
the purchaser had to pay to that authority.
[152] Preston CJ of LEC, with whom the other members of the court agreed, observed:
“84 There is also an anterior problem. Prospective purchasers are entitled to
assume that if the principal certifying authority exercises the statutory
power to issue a subdivision certificate, it has satisfied itself that all of
the applicable requirements in s 109J(1) and (2) have in fact been
complied with. Prospective purchasers ought not be required to assume
that the principal certifying authority has exercised the statutory power
improperly or to make inquiries to ascertain whether it has exercised the
statutory power properly or improperly.
-- 32 of 37 --
33
85 Prospective purchasers who have entered a conditional contract to
purchase an allotment to be created by the subdivision, such as the
applicants in this case, cannot withhold from purchasing the subdivided
allotment once the plan of subdivision has been registered if they
discover that the principal certifying authority issued the subdivision
certificate without being satisfied that each of the applicable
requirements in s 109J(1) and (2) had in fact been met. They are obliged
to complete the contract upon registration of the plan of subdivision.
They cannot renegotiate the price or the terms of the contract.
86 It is also not reasonable to expect that prospective purchasers should
protect themselves, before the principal certifying authority exercises the
statutory power to issue a subdivision certificate, against the
consequences of any potential misexercise of the power.”
[153] Preston CJ of LEC noted that theoretically a prospective purchaser could seek protection
against misexercise of the statutory power by the principal certifying authority by
negotiating a provision in the contract entitling the purchaser to decline to complete the
contract or to be compensated by the vendor, if there were such a misexercise of the
statutory power. Preston CJ of LEC considered at [88]-[89] that such a contractual
provision would not provide adequate protection against economic loss for the
prospective purchaser and the burden of loss remained either on the purchaser or the
vendor of the lot and therefore concluded that at [90] that in that case the purchasers were
vulnerable.
[154] Western Districts can be distinguished on the facts, as it was concerned with the
negligence of the principal certifying authority that preceded the creation of the
subdivided lot which produced the subject matter of the contract.
[155] Mr Fernon relies on the distinction drawn by McDougall J in Chan v Acres [2015]
NSWSC 1885 between the position of the engineers MHE (which prepared the structural
drawings for extensions to a dwelling house and carried out inspections of the structural
work) and the local council that issued the occupation certificate for the dwelling house.
The plaintiff had purchased the dwelling house from the owner builder who did the
extensions. The council was the principal certifying authority of the building work under
the EPA. There was no problem with the design of the extensions to the dwelling house,
but the contractors who carried out the relevant building work failed to comply with the
design and that was not detected on the inspections by MHE’s employed engineer.
[156] Applying Woolcock and Brookfield, McDougall J weighed up the factors relevant to
imposing a duty of care on the engineers and concluded, at [255], that taken together they
were insufficient to justify the imposition of the duty of care. The conclusion was
otherwise in relation to the council. McDougall J stated at [360]:
“In the case of the Council, and quite unlike the case of MHE, it is in my view
clear that there was both the expectation of reliance (i.e., the Council, through
the certifier, knew or understood that prospective purchasers would rely on
the occupation certificate) and actual reliance. I do not understand it to have
been submitted that the reliance of which [the purchaser] gave evidence was
unreasonable. It is plain from the evidence of the certifier that the Council
-- 33 of 37 --
34
knew of the likelihood of that reliance. In those circumstances, it is easy to
infer, and I do, that the Council, knowing that intending purchasers would
rely on its work as summarised in occupation certificates, assumed the
responsibility of certifying accurately. One might well ask, accordingly, why
should it not also bear the consequences of certifying inaccurately?”
[157] The plaintiff submits that the fact that Mr Henry was fulfilling a statutory function in
issuing the Form 15 and/or Form 16 was of particular significance on the issue of
vulnerability. The plaintiff did not actually plead in the statement of claim the matters of
fact relied on to allege that the plaintiff was affected by vulnerability that gave rise to the
duty of care alleged to be owed by DEQ and Mr Henry to the plaintiff. At least DEQ and
Mr Henry in paragraph 19 of the defence pleaded the factual matters on which they rely
to show that the plaintiff was in a position to protect itself prior to, and at the time of, its
entry into the contract and therefore to preclude the imposition of such a duty of care and
these factual matters were largely established by the evidence as follows.
[158] The plaintiff knew what its intended use was of the building, including the installation of
racking to store air-conditioning units which would exert a downward force on the
concrete slab, and yet the plaintiff made no inquiries before entering into the contract,
when exhibit 6 alerted the plaintiff to the fact that “No allowance has been made for pallet
racking or punching”. Not only did the plaintiff not engage an engineer to inspect the
building and the engineering drawings to ascertain whether the building was suitable for
the plaintiff’s intended commercial use (for which maintaining a level floor was
important) prior to entering into the contract, the plaintiff agreed to the deletion of the
standard clause 4 which would have otherwise made the contract conditional on a
building report. It is submitted on behalf of the plaintiff that a building inspection prior
to completion would not have disclosed the design issues in respect of the slab. This
overlooks the fact that any inspection done in conjunction with inspecting the S drawings,
would have revealed the nature of the construction of the concrete slab, the floor design
loads for the slab, and the express qualifications about anticipated settlement.
[159] Subject to clause 2.3 of the special conditions of the contract that permitted the plaintiff
during the defects liability period under the D&C Contract to notify DDS on behalf of
Efstathis as to any defects in the construction of the improvements and the assignment of
rights of enforcement in clause 2.4 of the special conditions, the plaintiff entered into a
contract under which Efstathis expressly did not warrant that the improvements had been
constructed in a good and workmanlike manner or were otherwise fit for any particular
purpose. It is not irrelevant that despite clause 2.4 of the special conditions, the plaintiff
did not seek to perfect the assignment of Efstathis’ rights against DDS at the same time
as the completion of the purchase. It is not to the point that DDS would never have
consented to the assignment by Efstathis of its rights under the D&C Contract to the
plaintiff, but the plaintiff’s failure to pursue its rights under clause 2.4 of the special
conditions meant that the position in respect of being able to pursue DDS for any defects
in the building works discovered after the expiry of the defects liability period was not
resolved before completion of the purchase.
[160] In addition, the imperative consideration for the plaintiff in its negotiations with Efstathis
prior to entering the contract was achieving a discount in the purchase price, rather than
taking all steps that would have otherwise been available to ensure that the building was
-- 34 of 37 --
35
of a suitable construction for its intended use. The submission is well made by Mr
Musgrave of counsel on behalf of DEQ and Mr Henry that there were many opportunities
for this plaintiff to protect itself from the risk of settlement of the slab that it did not take,
so that it could not be found to be vulnerable in the sense described in Woolcock and
Brookfield.
[161] Another important consideration is that neither DDS nor Efstathis would have been able
to take action against DEQ and Mr Henry for designing a slab on ground, when that was
what DDS contracted DEQ to do and what I infer was Efstathis’ requirement in
minimising the construction costs to maximise the profit on the sale of the building. As
explained in Brookfield at [69] and [132], the coherence of the common law would be
undermined if a duty of care in tort were imposed on a party in respect of the performance
of an obligation under contract for which that party had no liability to the other contracting
party.
[162] The plaintiff emphasises the statutory role that DEQ and Mr Henry had in issuing the
Form 15 and the Form 16. The submission that they should be characterised as equivalent
to the prescribed certifying authority under the EPA in New South Wales is not accurate.
Under the Regulation their role was to help the building certifier in their area of
professional skill to enable the building certifier to carry out its role. Issuing the Form 15
was incidental to the role of DEQ and Mr Henry in designing the slab on ground for which
DEQ was paid by DDS and has no significant effect on the characterisation of the role of
DEQ and Mr Henry as designing the slab. The plaintiff had advanced an alternative
argument in respect of the application of vulnerability on the basis that the presence of a
statutory function on the part of DEQ and Mr Henry dispensed with the requirement of
vulnerability as an essential condition for founding a duty of care. Apart from the fact
that argument is inconsistent with the approach in Woolcock and Brookfield, there is no
foundation for it in the light of the true nature of the role of Mr Henry on behalf of DEQ
as a competent person under the Regulation.
[163] If there had been negligence by DEQ and Mr Henry in designing the slab as a slab on
ground, the plaintiff has failed to establish vulnerability in the sense explained in
Woolcock and Brookfield to permit the imposition of a duty of care owed by DEQ and Mr
Henry in respect of the design and/or certification of the slab for the subject building.
TPA claim
[164] In view of my conclusion that there was no breach of the design standards under the BCA
in respect of the design of the slab, it follows that the claims based on misleading and
deceptive conduct in respect of the issuing of the Forms 15 and 16 cannot succeed.
Limitation periods
[165] The manner in which the claims are currently formulated against DEQ and Mr Henry in
tort and under the TPA first appeared in the statement of claim in the version that was
filed on 30 July 2014. No leave of the court was obtained for these amendments. DEQ
and Mr Henry plead that the conduct alleged to comprise the breach of duty occurred
before January 2008 and the loss or damage the subject matter of the claim was evident
-- 35 of 37 --
36
no later than January 2008 and therefore plead the limitation period as a defence against
the plaintiff. If necessary, the plaintiff applies for leave under r 376 of the Uniform Civil
Procedure Rules 1999 (Qld) in respect of the amendments that include new causes of
action after the expiry of the relevant limitation period. In view of my conclusion on the
question of liability, it is not necessary to deal with the application for leave or the
limitation defence.
[166] I observe, however, that the preponderance of evidence indicates the loss or damage was
evident in a relevant sense later than January 2008. The mere fact that one of the
plaintiff’s employees had requested DDS provide a copy of the engineering drawings that
dealt with the floor slab in late January 2008 without any further evidence about the
circumstances is not enough to enable a finding to be made that the damage was sustained
by January 2008. It would also be inconsistent with Mr Poole’s observations.
Other matters
[167] It is unnecessary to consider other issues raised on the pleadings of contributory
negligence and proportionate liability.
Quantum of damages
[168] It is also not necessary to consider the issue of quantum.
[169] The plaintiff claims damages in the sum of $1,067,203.50 as the cost of the rectification
work to replace the floating slab and associated costs. The plaintiff submits that it was
not unreasonable for the plaintiff to replace the slab rather than undertake slab jacking. It
is argued that slab jacking was temporary and with repeated treatments is likely to result
in similar costs to the replacement of the slab and, in addition, slab jacking would not fix
the other slab problems of cracking and gouging.
[170] If DEQ and Mr Henry were liable to the plaintiff, they dispute the quantum of damages
on the basis that the plaintiff failed to mitigate its damages and also on the basis that the
plaintiff’s method of rectification resulted in the plaintiff obtaining a benefit, namely a
warehouse floor of greater load bearing capacity and longer useful life than that which
the plaintiff contracted to purchase. On the basis of Mr McFadden’s estimate that the
additional costs of constructing the building as a piled slab construction would have been
$400,812.20 (excluding GST), the benefit is calculated on the basis of the difference
between the actual purchase price of $3.175m and the total of the purchase price that was
sought by Efstathis of $3.3m plus $400,812.20. The benefit is therefore calculated as
$505,809.
[171] Alternatively, it is submitted by DEQ and Mr Henry that the plaintiff should be limited
to the rectification costs necessitated by reason of the negligence, if damages are
calculated on the basis of slab jacking which DEQ calculates to be $505,809.
[172] There is substance in the betterment argument. Either basis for calculating damages
results in much the same figure. It is academic to decide the point.
-- 36 of 37 --
37
Orders
[173] On the publication of these reasons, I will give the parties an opportunity to agree on an
appropriate order for costs or, failing an agreement, on a timetable for submissions on
what costs order should be made in the proceeding. In the meantime, I will adjourn the
question of costs to a date to be fixed to accommodate the parties either agreeing on the
costs order or agreeing on the timetable for costs submissions.
[174] In the meantime, I will make the following orders:
1. The proceeding against the second and third defendants is dismissed.
2. The question of the costs of the proceeding is adjourned to a date to be fixed.
-- 37 of 37 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2016/306