Annie Street JV Pty Ltd v MCC Pty Ltd & Ors [2016] QSC 268
SUPREME COURT OF QUEENSLAND
CITATION: Annie Street JV Pty Ltd v MCC Pty Ltd & Ors [2016] QSC
268
PARTIES: ANNIE STREET JV PTY LTD
ACN 160 994 016
(applicant)
v
MCC PTY LTD
ACN 002 243 263
(first respondent)
MAX TONKIN (ADJUDICATOR J1066620)
(second respondent)
MICHAEL HOPE CHESTERMAN
(Adjudication Registrar)
(third respondent)
FILE NO/S: SC No 9681 of 2016
DIVISION: Trial
PROCEEDING: Trial
ORIGINATING
COURT:
Supreme Court at Brisbane
DELIVERED ON: 21 November 2016
DELIVERED AT: Brisbane
HEARING DATE: 25 October 2016
JUDGE: Flanagan J
ORDER: 1. The applicant’s originating application filed
20 September 2016 is dismissed.
2. I will hear the parties as to costs.
CATCHWORDS: ADMINISTRATIVE LAW – DECLARATIONS – EXCESS
OR WANT OF JURISDICTION – PARTICULAR
INSTANCES OF JURISDICTIONAL ERROR – where the
applicant and the first respondent were parties to construction
contract – where the first respondent served a payment claim
under the Building and Construction Industry Payments Act
2004 (Qld) (the Act) – where the second respondent made an
adjudication decision under the Act – where the second
respondent determined, as part of the adjudication, that the
applicant was not entitled to set-off an amount for liquidated
damages – where the applicant alleges that this part of the
second respondent’s decision is affected by jurisdictional error
– whether the second respondent’s decision that the applicant
was not entitled to set-off an amount for liquidated damages
-- 1 of 24 --
2
was without foundation and illogical, with a deficient
reasoning process – whether the second respondent’s decision
that the applicant was not entitled to set-off an amount for
liquidated damages involved a failure to provide reasons or
adequate reasons in accordance with s 26(3)(b) of the Act –
whether the second respondent’s decision that the applicant
was not entitled to set-off an amount for liquidated damages
involved a denial, to the applicants, of natural justice
ADMINISTRATIVE LAW – DECLARATIONS – EXCESS
OR WANT OF JURISDICTION – PARTICULAR
INSTANCES OF JURISDICTIONAL ERROR – where the
applicant and the first respondent were parties to construction
contract – where the first respondent served a payment claim
under the Building and Construction Industry Payments Act
2004 (Qld) (the Act) – where the applicant served a payment
schedule under the Act – where the payment schedule did not
raise contractual time limitations as a basis for withholding
payment – where the second respondent did not consider
contractual time limitations in the adjudication – whether, in
not considering contractual time limitations, the second
respondent committed jurisdictional error
Building and Construction Industry Payments Act 2004 (Qld),
s 17, s 18, s 24, s 26(2)
Judicial Review Act 1991 (Qld), s 18(2)(b), Schedule 1, Part 2
Bauen Constructions v Westwood Interiors [2010] NSWSC
1359, cited
Camden v McKenzie [2008] 1 Qd R 39; [2007] QCA 136, cited
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd (2010)
78 NSWLR 393; [2010] NSWCA 190, cited
City of Ryde v AMDM Constructions Pty Ltd & Anor [2011]
NSWSC 1469, cited
Craig v South Australia (1995) 184 CLR 163; [1995] HCA 58,
cited
Holmwood Holdings Pty Ltd v Halkat Electrical Contractors
Pty Ltd [2005] NSWSC 1129, cited
John Holland Pty Limited v Roads & Traffic Authority (NSW)
[2007] NSWCA 19, applied
John Holland Pty Limited v TAC Pacific Pty Ltd & Ors [2010]
1 Qd R 30; [2009] QSC 205, cited
Minister for Commerce v Contrax Plumbing (NSW) Pty Ltd
[2005] NSWCA 142, cited
QCLNG Pipeline Pty Ltd v McConnell Dowell Constructors
(Aust) Pty Ltd and Consolidated Contracting Company
Australia Pty Ltd & Anor [2011] QSC 292, cited
Queensland Bulk Water Supply Authority v McDonald Keen
Group Pty Ltd & Anor [2009] QSC 165, cited
-- 2 of 24 --
3
Re Rich Rivers Pty Ltd and Independent FM Radio Pty Ltd v
Australian Broadcasting Tribunal & Goulburn Valley
Broadcasters Pty Limited [1989] FCA 132, cited
Roseville Bridge Mariner Pty Ltd v Bellingham Marine
Australia Pty Ltd [2009] NSWSC 320, cited
SSC Plenty Road Pty Ltd v Construction Engineering (Aust)
Pty Ltd [2015] VSC 631, cited
Sierra Property Qld Pty Ltd v National Construction
Management Pty Ltd & Ors [2016] QSC 108, considered
State Water Corporation v Civil Team Engineering Pty Ltd
[2013] NSWSC 1879, considered
COUNSEL: GD Beacham QC with M Martinez for the applicant
DG Clothier QC with M Hickey for the first respondent
SOLICITORS: McInnes Wilson for the applicant
Clayton Utz for the first respondent
Introduction
[1] The applicant, Annie Street JV Pty Ltd, seeks both declaratory and injunctive relief in
respect of an adjudication decision made by the second respondent pursuant to s 26(1) of
the Building and Construction Industry Payments Act 2004 (Qld) (the Act).
[2] The decision was made on 6 September 2016. The adjudication was that the applicant
pay the first respondent, MCC Pty Ltd, an amount of $528,505.09 (inclusive of GST),
together with interest at the rate of 7.75 per cent per annum, and that the date for payment
was 9 August 2016. The declaratory relief sought is a declaration that the decision is
void.1 The injunctive relief sought is an injunction to permanently restrain the third
respondent, in his role as Adjudication Registrar, from issuing an adjudication certificate
pursuant to s 30 of the Act in respect of the decision.2
[3] The first respondent opposes the granting of the relief sought.
[4] By Notices of Address for Service filed 26 September 2016 and 29 September 2016, the
second and third respondents submit to all orders of the Court save as to cost.
[5] The applicant seeks the relief on the basis that the decision is affected by jurisdictional
error in two respects. First, the applicant contends that the adjudicator’s decision not to
allow the applicant a set-off for liquidated damages in the amount of $164,160.00:
(a) was without foundation and illogical, with a deficient reasoning process;
1 Originating Application, [1].
2 Originating Application, [2].
-- 3 of 24 --
4
(b) involved a failure to provide reasons or adequate reasons in accordance with
s 26(3)(b) of the Act; and
(c) involved a denial to the applicant of natural justice.
Secondly, the applicant contends that the adjudicator committed jurisdictional error by
failing to consider the provisions of the relevant building contract in connection with
seven variations claimed by the first respondent (one of which was not allowed).3
[6] For the reasons which follow the applicant’s originating application for declaratory and
injunctive relief should be dismissed.
Background
[7] On 19 July 2016 the first respondent served a payment claim for $808,843.44.4 The claim
was made under a contract for a building project involving the construction of 18
residential units in New Farm, Brisbane.
[8] On 27 July 2016 the superintendent, Mr Dugan, on behalf of the applicant, served a
payment schedule in which it scheduled $nil.5
[9] On 8 August 2016 the first respondent served an adjudication application.6 The
adjudication application comprised 11 lever-arch folders, including a statutory
declaration of Mr Scroope, a director of the first respondent.7
[10] On 23 August 2016 the applicant served an adjudication response.8 The adjudication
response comprised one lever-arch file9 including a statutory declaration of Mr Dugan.
The first alleged jurisdictional error
[11] An adjudication decision is not reviewable under the Judicial Review Act 1991 (Qld).10
Both parties accept however that an adjudicator’s decision may be declared void if it is
affected by jurisdictional error.11
3 Variations 11A, 58, 60, 61A, 67, 69 and 72. The reasons for the adjudicator’s decision are Exhibit “ETB-6” to
the affidavit of Eden Tyler Bird, filed 28 September 2016, CD 6 (the Bird affidavit). Variation 11A was not
allowed: Exhibit “ETB-6” to the Bird affidavit, [119]-[126].
4 Exhibit “ETB-1” to the Bird affidavit. The payment claim was served pursuant to s 17 of the Act
5 Exhibit “ETB-2” to the Bird affidavit. The payment schedule was served pursuant to s 18 of the Act.
6 The adjudication application was served pursuant to s 21 of the Act.
7 The Bird affidavit, [4]; Exhibit “CS-1” to the affidavit of Christopher Scroope, filed 14 October 2016, CD8.
8 Pursuant to the regime set out in s 24 of the Act.
9 The Bird affidavit, [4]; Exhibit “ETB-5” to the Bird affidavit.
10 See s 18(2)(b) and Schedule 1, Part 2 of the Judicial Review Act 1991 (Qld).
11 Written Submissions for the Applicant, [11]. The proposition is implicitly accepted in the Outline of
Submissions of the First Respondent; Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd
[2012] 1 Qd R 525 at [6] per Margaret McMurdo P, at [33] per Chesterman JA and at [78] per White JA.
-- 4 of 24 --
5
[12] The applicant, through Mr Dugan, deducted $164,160.00 for liquidated damages in the
payment schedule. Such damages were able to be claimed pursuant to clause 34.7 of the
contract if the first respondent did not reach practical completion by the date for practical
completion. Item H of the Special Conditions provided, in effect, that the date for
practical completion was “35 weeks after the completion of the Basement (Definition
Basement Completion is the following:- Excavation, Retaining Walls and Basement
Slab).” The claim for liquidated damages was based on the applicant’s contention that
the superintendent, Mr Dugan, and Mr Scroope had made an agreement to amend or vary
the contract with effect that the 35 week period identified in item H commenced on
19 March 2015 rather than commencing after the completion of the basement.
[13] The adjudicator’s decision in respect of this issue is said to reveal jurisdictional error. It
is first necessary to consider the statutory framework in which the adjudicator was
required to give reasons for the decision.
[14] The procedure for recovering progress payments is outlined in Part 3 of the Act. The
procedure is commenced by the serving of a payment claim pursuant to s 17. A person
served with a payment claim may reply to the claim by serving a payment schedule
pursuant to s 18. Section 18(2) provides that a payment schedule –
(a) must identify the payment claim to which it relates; and
(b) must state the amount of the payment, if any, that the respondent proposes to
make (the scheduled amount).
[15] Section 18(3) provides that if the scheduled amount is less than the claimed amount, the
schedule must state why the scheduled amount is less and, if it is less because the
respondent is withholding payment for any reason, the respondent’s reasons for
withholding payment.
[16] An adjudication proceeding is commenced by an adjudication application under s 21. If
the adjudication application is accepted under s 23, there is a right to provide an
adjudication response under s 24. Section 24(4) provides that if the adjudication
application is about a standard payment claim, the adjudication response cannot include
any reasons for withholding payment unless those reasons were included in the payment
schedule when served on the claimant. It is common ground that the present case
concerns a standard payment claim. This is to be contrasted with s 24(5) which deals
with an adjudication application involving a complex payment claim. In those
circumstances the adjudication response may include any reasons for withholding
payment whether or not those reasons were included in the payment schedule when
served on the claimant. Section 24B(2) gives the claimant a right of reply to the
adjudication response. This right of reply is however, confined to an adjudication
response to a complex payment claim under s 24(5). The practical consequence of s 24(5)
and s 24B(2), for present purposes, is that the first respondent had no right of reply to the
applicant’s adjudication response which included Mr Dugan’s statutory declaration. The
first respondent therefore had no right under the Act to serve a further statutory
declaration of Mr Scroope responsive to the one given by Mr Dugan. By s 25(1)(a),
-- 5 of 24 --
6
subject to the time requirements under s 25A, an adjudicator must decide an adjudication
application “as quickly as possible”.
[17] The relevant provision in respect of an adjudicator’s decision is s 26:
“Adjudicator’s decision
(1) An adjudicator is to decide—
(a) the amount of the progress payment, if any, to be paid by the
respondent to the claimant (the adjudicated amount); and
(b) the date on which any amount became or becomes payable; and
(c) the rate of interest payable on any amount.
(2) In deciding an adjudication application, the adjudicator is to consider
the following matters only—
(a) the provisions of this Act and, to the extent they are relevant, the
provisions of the Queensland Building and Construction
Commission Act 1991, part 4A;
(b) the provisions of the construction contract from which the
application arose;
(c) the payment claim to which the application relates, together with
all submissions, including relevant documentation, that have been
properly made by the claimant in support of the claim;
(d) the payment schedule, if any, to which the application relates,
together with all submissions, including relevant documentation,
that have been properly made by the respondent in support of the
schedule;
(e) the results of any inspection carried out by the adjudicator of any
matter to which the claim relates.
(3) The adjudicator’s decision must—
(a) be in writing; and
(b) include the reasons for the decision, unless the claimant and the
respondent have both asked the adjudicator not to include the
reasons in the decision.”
[18] A decision under s 26(1) has three subjects, namely the adjudicated amount, the date for
payment and the rate of interest. The adjudicated amount is a single amount determined
as the amount of the progress payment to be made.12 An adjudication decision under the
12 Multiplex Constructions Pty Ltd v Luikens & Anor [2003] NSWSC 1140 at [92] per Palmer J; James Trowse
Constructions Pty Ltd v ASAP Plasterers Pty Ltd [2011] QSC 145 at [57]-[59] per Atkinson J; BM Alliance
Coal Operations Pty Ltd v BGC Contracting Pty Ltd [2012] QSC 346 at [48] per Applegarth J; Thiess Pty Ltd
v Warren Brothers Earthmoving Pty Ltd [2012] QSC 373 at [61]-[62] per A Lyons J.
-- 6 of 24 --
7
Act is, therefore, not a series of decisions as to amounts owing in respect of discrete
claims.13
[19] I consider s 26(2) in more detail below in dealing with the second alleged jurisdictional
error.
[20] As to s 26(3)(b), the only requirement is that the adjudicator “include the reasons for the
decision”. The relevant “decision” for which reasons must be included is the decision
identified in s 26(1).
[21] The procedures outlined in Part 3 and in sections 17 to 26 of the Act in particular, are
how the object of the Act stated in s 7 is to be achieved.14 That object is to ensure that a
person is entitled to receive, and is able to recover, progress payments if the person
relevantly undertakes to carry out construction work under a construction contract.
[22] In Craig v South Australia15 the High Court stated:16
“… jurisdictional error will occur where an inferior court disregards or takes
account of some matter in circumstances where the statute or other instrument
establishing it and conferring its jurisdiction requires that that particular
matter be taken into account or ignored as a pre-condition of the existence of
any authority to make an order or decision in the circumstances of the
particular case.”
[23] Given the mandatory language of s 26(3)(b), absent the consent of both parties for the
adjudicator not to include the reasons in the decision, it may be accepted that a complete
failure on the part of an adjudicator to give reasons constitutes jurisdictional error. As
observed by Jackson J, when considering s 26(3) in Sierra Property Qld Pty Ltd v
National Construction Management Pty Ltd:17
“… something which is in writing but does not include the reasons for the
decision is not such a decision. Those conclusions are required by the use of
the word ”must” in the text.”
[24] The reasons for a decision under s 26(3)(b) should reflect a genuine consideration of the
matters identified in s 26(2). As observed by Palmer J, when considering the equivalent
provision to s 26(3) in the Building and Construction Industry Security of Payments Act
1999 (NSW) (the NSW Payments Act) in Brookhollow Pty Ltd v R & R Consultants Pty
Ltd:18
“The extent to which an adjudicator must give reasons for the determination
in accordance with s.22(3)(b) reflects the extent of his or her duty to give
consideration to the matters required by s.22(2). In a fully contested
adjudication in which several issues have been raised, the adjudicator’s
13 Outline of Submissions for the First Respondent, [16].
14 Section 8 of the Act.
15 (1995) 184 CLR 163.
16 (1995) 184 CLR 163, 177.
17 [2016] QSC 108 at [54].
18 [2006] NSWSC 1 at [66].
-- 7 of 24 --
8
reasons should demonstrate that he or she has endeavoured in good faith to
consider those issues, in compliance with the requirements of s.22(2)(c) and
(d).”19
[25] In SSC Plenty Road Pty Ltd v Construction Engineering (Aust) Pty Ltd20 Vickery J
identified that the requirement to give reasons for the decision means that an adjudicator
must proceed to make the critical findings: This process, according to his Honour
involves:
“ (j) The adjudicator must proceed to make critical findings by:
(i) fairly assessing and weighing the whole of the evidence which is
relevant to each issue arising for determination at the
adjudication;
(ii) drawing any necessary inferences from the evidence, or from the
absence of any controverting material provided by the
respondent, including an inference that if there is no controverting
material, no credible challenge can be made to the value of the
claim advanced by the claimant. Such an inference may be
considered in the context of the evidence as a whole;
(iii) arriving at a rational conclusion founded upon the evidence;
(iv) in so doing, is not called upon to act as an expert; and
(v) is not entitled to impose an onus on either party to establish a
sufficient basis for payment or a sufficient basis for withholding
payment.
(k) Pursuant to s 23(3) of the Act,21 the adjudicator must include in an
adjudication determination both the reasons for the determination and
the basis upon which any amount or date has been decided. In providing
these reasons the adjudicator must summarise the central reasons for
the making of the critical findings in the adjudication determination
with as much completeness as the time permitted under the Act will
allow.”22
[26] Jurisdictional error may also occur where findings or conclusions have no basis, are bare
conclusions and do not reveal due consideration. In such circumstances the decision
would be set aside –
“… being insufficiently supported by reason, they appear to be an improper
exercise of the power conferred or arbitrary or there was no evidence or other
material sufficient to justify the making of the decision or the decision was so
19 Section 22 referred to by Palmer J is the equivalent of s 26 of the Act.
20 [2015] VSC 631 at [101].
21 The equivalent to s 26(3) of the Act.
22 Cited with approval in Richard Crookes Constructions Pty Ltd v CES Projects (Aust) Pty Ltd [2016] NSWSC
1129 at [23] per McDougall J.
-- 8 of 24 --
9
unreasonable that no reasonable person would have so exercised the
power.”23
[27] Similarly, if one party’s evidence is rejected for no reason or on no other ground than a
bare conclusion that one party’s evidence is preferred over another does not constitute the
giving of reasons for a decision.24 As observed by Keane JA (as his Honour then was) in
Camden v McKenzie:25
“The appellants contend … that adequate reasons for judgment will refer to
the evidence which was important to the determination of the matter, and will
set out material findings of fact, giving the judge's reasons for his or her
findings of fact, and stating the basis on which the judge has come to prefer
one body of evidence over a competing body of evidence.
As a general rule, observance of these requirements is necessary to
demonstrate that litigation has been determined fairly and rationally.
Adherence to these requirements ensures that rights of appeal are not rendered
meaningless, and that a party affected by a decision adverse to his or her
interests is not left with a justified sense of grievance that the case has not
been properly considered. In short, these standards promote the conscientious
public discharge of the responsibilities of a judge to litigants, as well as to the
community, which has a vital interest in the integrity of the judicial process.”
(Citations omitted).
[28] Camden concerned reasons for judgment of a trial judge. The distinction between giving
reasons in a curial process rather than an adjudication process was noted by McDougall J
in Bauen Constructions v Westwood Interiors:26
“Although adjudicators work under significantly greater time pressures than
judges, and their reasons should not be scrutinised with the attention to detail
to which the reasons of trial judges and intermediate appellate courts are
subjected in ultimate courts of appeal, nonetheless the reasons must indicate
why it was that the adjudicator arrived at the determination given in
accordance with s 22(1). Just as there is with judges, so too with adjudicators
there is a presumption that the stated reasons are all of the reasons for coming
to the conclusion expressed.”
The jurisdictional error identified by McDougall J in Bauen was that the determination
revealed no intellectual justification for the decision that was made.27
[29] In considering the adjudicator’s reasons for decision in the present case, there is an
important distinction to keep in mind between an error committed within jurisdiction and
23 See Re Rich Rivers Pty Ltd and Independent FM Radio Pty Ltd v Australian Broadcasting Tribunal & Goulburn
Valley Broadcasters Pty Ltd [1989] FCA 132 at [49]-[50] per Davies J; Queensland Bulk Water Supply
Authority v McDonald Keen Group Pty Ltd & Anor [2009] QSC 165 at [32]-[33] per P Lyons J, cited with
approval in John Holland Pty Limited v TAC Pacific Pty Ltd & Ors [2009] QSC 205 at [21] per Applegarth.
24 W195/01A v Minister for Immigration & Multicultural Affairs [2002] FCA 396 at [34]-[36] per Lee J.
25 [2008] 1 Qd R 39, 47-48 at [30]-[31].
26 [2010] NSWSC 1359 at [23]; John Holland Pty Limited v TAC Pacific Pty Limited [2010] 1 Qd R 302, 323-
324 at [66]-[67] per Applegarth J
27 [2010] NSWSC 1359 at [40].
-- 9 of 24 --
10
jurisdictional error. As observed by Brereton J in City of Ryde v AMFM Constructions
Pty Ltd & Anor:28
“… the inadequacy, insufficiency, inconsistency or illogicality of reasons for
a decision, even when the governing statute requires a decision-maker to give
reasons in conjunction with and contemporaneously with the decision, does
not of itself amount to jurisdictional error. The significance of the reasons, or
their inadequacy, is that in the context of the surrounding material they may
reveal jurisdictional error, or that the adjudicator has not performed the task
of determining an adjudicated amount by reference to the specified relevant
factors in accordance with s 22 of the Act.”
[30] Where however, the reasons do not reveal any foundation or logical basis for the decision,
then there has been a failure to exercise jurisdiction.29
[31] A denial of natural justice may constitute jurisdictional error. Such a denial of natural
justice would occur where a decision is made on a basis not advanced by either party.30
[32] In determining the amount of the progress payment, if any, to be paid by the applicant to
the first respondent, the adjudicator had before him 12 binders of documents, including a
53 page statutory declaration (without annexures) of Mr Scroope31 and a 32 page statutory
declaration (without annexures) of Mr Dugan,32 together with 54 pages of submissions
from the first respondent33 and 29 pages of submissions from the applicant.34
[33] The reasons for decision extend over 79 pages and 297 paragraphs dealing with many
legal issues, including 55 variations as well as the liquidated damages claim.
[34] The adjudicator’s consideration of the liquidated damages claim commences at paragraph
[57] and continues through to paragraph [77]. At paragraph [57] the adjudicator
commences his analysis by noting that the payment schedule shows that $164,160.00 has
been deducted for liquidated damages.
[35] In paragraph [58] the adjudicator identifies the relevant parts of the first respondent’s
adjudication application that dealt with the applicant’s liquidated damages claim. These
included sections 12 and 13 of the submissions in the adjudication application and
paragraphs [467] to [497] of Mr Scroope’s statutory declaration.
[36] In paragraph [59] the adjudicator notes the first respondent’s primary position, namely
that the date for practical completion was 35 weeks from the date of Basement
Completion, which was 16 October 2015.
28 [2011] NSWSC 1469 at [9].
29 State Water Corporation v Civil Team Engineering Pty Ltd [2013] NSWSC 1879 at [126] per Sackar J; Chase
Oyster Bar Pty Ltd v Hamo Industries Pty Ltd (2010) 78 NSWLR 393 at [177] per McDougall J.
30 John Holland Pty Limited v TAC Pacific Pty Ltd [2010] 1 Qd R 302, 321 at [57] per Applegarth J; Caltex
Refineries (Qld) v Allstate Access (Australia) Pty Ltd [2014] QSC 223 at [38] per Philip McMurdo J.
31 Exhibit “CS-1” to the affidavit of Christopher Scroope, filed 14 October 2016, CD8.
32 Exhibit “ETB-5” to the Bird affidavit.
33 Exhibit “ETB-3” to the Bird affidavit.
34 Exhibit “ETB-4” to the Bird affidavit.
-- 10 of 24 --
11
[37] In paragraph [60] the adjudicator summarises and considers in some detail (extending
over three pages) the first respondent’s submissions in support of its primary position.
This includes, in paragraphs [60(a)] and [60(b)], the first respondent’s understanding that
the date for practical completion was to be calculated on the basis of 35 weeks after the
first respondent had completed the basement. The first respondent’s understanding of the
date for practical completion was accepted by the adjudicator upon the adjudicator’s
construction of the contract outlined in paragraphs [64] to [66] of the decision. The
adjudicator’s analysis in this respect refers to clause 34.7 of the contract which deals with
liquidated damages, together with clause 1, Item 7(a), Item 7(b) and Item H on page 27
of 29 in the Schedule of Amendments to the contract. The adjudicator’s conclusion as to
the construction of the contract in this respect is found at paragraph 67:35
“My construction of these contract provisions is that the date of practical
completion is the last day of the period of 35 weeks commencing on the date
of basement completion where basement completion as defined in item H of
the Special Conditions is completion of excavation, retaining walls and
basement slab.”
[38] The adjudicator in considering the first respondent’s primary submission that the date for
practical completion was 35 weeks from the date of the completion of the basement, refers
to contemporaneous documents from Mr Dugan consistent with this position. These
documents include an email of 17 July 2016 from Mr Dugan, whose advice regarding
practical completion was: 36
“35 weeks after completion of basement (which includes the excavation,
retaining walls and basement slab).”
[39] In summarising and considering the relevant submissions of the first respondent in the
adjudication application and Mr Scroope’s statutory declaration, the adjudicator makes
reference to a number of other contemporaneous documents, including an email from
Mr Dugan dated 11 December 2014, the first respondent’s email of 2 February 2015 and
an email from Mr Dugan dated 30 September 2015.
[40] At paragraphs [60(i)] and [60(j)] the adjudicator refers to a “Notice of Start and
Completion” dated 25 March 2015 sent by Mr Dugan to the first respondent on or about
6 May 2015:
“We confirm that the official start date for the project after the wet season has
been completed and basement works substantially complete has been agreed
between MCC Representative and The Superintendent John Dugan and as per
MCC programme is 19/03/2015 and Official completion date is 19/11/15.”
[41] The first respondent’s submission in the adjudication application in relation to the notice
of 6 May 2015 is recorded by the adjudicator in paragraph 60(j):
“The Claimant agrees that the project was significantly disrupted by
inclement weather in the period December 2014 to February 2015, for which
the claimant erroneously claimed an EOT. However, it was never agreed that
35 Exhibit “ETB-6” to the Bird affidavit, page 190.
36 Exhibit “ETB-6” to the Bird affidavit, page 183, [60(c)].
-- 11 of 24 --
12
the definition of the date for practical completion was modified to the extent
that the trigger for the 35 weeks commenced other than after basement
completion as defined by the Contract. The basement was not substantially
complete either on 25 March 2015 or 6 May 2015.”
[42] In paragraph [60(s)] the adjudicator records the first respondent’s submission in the
adjudication application that it had completed the basement on or about 16 October 2015.
Accordingly, the original date for practical completion was 17 June 2016, being 35 weeks
after basement completion.
[43] The adjudicator summarises and considers the applicant’s adjudication response from
paragraphs [61] to [63], which extend over approximately four and one-half pages. At
paragraph [61(f)] the adjudicator notes the matters set out in Mr Dugan’s statutory
declaration for his proposition that the date for practical completion was varied between
Mr Dugan on behalf of the applicant and the first respondent in March 2015.
[44] The adjudicator’s reasoning for concluding that the date for practical completion had not
been varied in March 2015 is found in paragraphs [68] to [72]:
“68. The Respondent’s and Superintendent’s submissions indicate that the
Respondent and Superintendent consider the Respondent and Claimant
agreed to change the terms of the Contract such that the 35 week period
commenced on 19 March 2015. The Superintendent referred to this as
“the official start date for the project” in his notice dated 25 March
2015. Mr Scroope acknowledged that he received the Superintendent’s
notice on 6 May 2015. I found no submission in the Superintendent’s
statutory declaration, that indicates where in the contract the
Superintendent is given the power to determine the start date of the 35
week period. In the adjudication response, the Respondent submitted
that the Superintendent acted on behalf of the Respondent.
69. The Superintendent’s submissions and the materials he provided
indicate that the Revised Program issued by Mr Scroope on 27 March
2015 indicated 19 March 2015 as day zero in the program, however the
submissions and materials to support the proposition that the Claimant,
or Mr Scroope on behalf of the Claimant, agreed to amend item H in
the Special Conditions have been generated by the Superintendent.
Given that Mr Scroope submitted in his statutory declaration that it was
never agreed expressly or otherwise to change the start date of the
35 week period, and given that Mr Scroope also submitted and provided
substantial back up evidence that the basement works were not
completed by 25 March 2015 or 6 May 2015, I am not satisfied that the
submissions and materials provided by the Superintendent are sufficient
to substantiate that the parties agreed to amend what is a fundamental
provision in the Contract.
70. In these circumstances I am not satisfied that the contract terms that
define the date for practical completion have been amended.
71. Mr Scroope submitted that he proposed to the Superintendent to
proceed with the building works before completing the basement
-- 12 of 24 --
13
instead of undertaking the basement and building works in sequence as
originally planned. In any case, Mr Scroope submitted that basement
completion was achieved on 16 October 2015. I found no submission
in the adjudication response submissions or the Superintendent’s
statutory declaration that challenges this contention.
72. Given the lack of challenge and given Mr Scroope’s submission that the
Claimant commenced building works before basement completion, and
given the status of basement construction in March 2015 as outlined in
sub-paragraphs (c) to (f) of paragraphs 488 of Mr Scroope’s statutory
declaration; I accept Mr Scroope’s contention that basement completion
as defined in item H occurred on 16 October 2015. Adding 35 weeks
to that date as provided in item H of the Special Conditions means that
the date for practical completion was 17 June 2016 as submitted by
Mr Scroope, not 24 December 2015 as submitted by the
Superintendent.”
[45] By reference to the sentence in paragraph 68, “I found no submission in the
Superintendent’s statutory declaration, that indicates where in the contract the
Superintendent is given the power to determine the start of the 35 week period”, the
applicant submits that this observation constitutes a denial of natural justice. This is
because neither party had referred to nor made submissions concerning the
superintendent’s power to determine the start date of the 35 week period. The applicant
submits that not only does this sentence suggest “a misunderstanding of the debate”37 but
the inclusion of this sentence in the reasons for decision is “opaque”: 38
“It is unclear to what extent this issue, not raised by either party, frames the
Adjudicator’s mind when he approached the liquidated damages claim. To
the extent that it informed his decision, it amounts to a breach of natural
justice, as the Adjudicator was required to give the parties notice of intention
so that they could put submissions on it. ASJV was given no opportunity to
deal with it.” (Citations omitted).
[46] I do not accept this submission. The applicant’s use of the word “opaque” is a reference
to the decision of Jackson J in Sierra Property Qld Pty Ltd v National Construction
Management Pty Ltd & Ors.39 In Sierra his Honour stated:40
“In my view, the reasons of the second respondent in the adjudication
decision for the original contract works claim are opaque.”
[47] The use of the word “opaque” by his Honour, in context, does not suggest that
jurisdictional error occurs where the reasoning of an adjudicator is opaque. His Honour’s
use of the word “opaque” should not be taken out of context. As explained by his
Honour:41
37 Written Submissions for the Applicant, [38].
38 Written Submissions for the Applicant, [40].
39 [2016] QSC 108.
40 [2016] QSC 108 at [44].
41 [2016] QSC 108 at [44]-[45].
-- 13 of 24 --
14
“Although the second respondent referred to having “carefully” considered
the applicant’s material, the only particular reference made was to paragraph
119 of the adjudication response. Paragraph 119 was concerned with the
dispute as to how the amount originally included in the schedule for the
deleted swimming pools should be allocated. No reference was made to the
extent of the work completed in any of the nine relevant contract categories,
either as claimed by the first respondent or as disputed by the applicant.
In my view, the statement of reasons did not adequately discharge the
obligation to “include the reasons for the decision” under s 26(3)(b) of the
Payments Act.”42
[48] Properly understood, his Honour found the reasoning to be “opaque” in the sense that no
reasons for decision were revealed. This of course is a recognised basis for finding
jurisdictional error.
[49] The adjudicator’s reference to the superintendent not having the power to unilaterally
determine the start date of the 35 week period is not, in my view, opaque. The statement
was made in the context of a written contract which expressly identified in item H the
date for practical completion. What the adjudicator had to decide was whether this date
had been varied. The adjudicator had already made reference to a document dated
25 March 2015 sent by the superintendent entitled “Notice of Start and Ccompletion”
which was received by the first respondent on or about 6 May 2015. By this notice Mr
Dugan, as superintendent, had purported to determine the start date. The adjudicator’s
observation in paragraph [68] is to the effect that this could not be done unilaterally. This
observation was made in the context where the adjudicator was deciding whether there
had in fact been an agreed change to the date for practical completion. I accept the first
respondent’s submission that the adjudicator simply recorded what was not contended as
well as what was. Rather than revealing a misunderstanding of the issue, the comment
represents an accurate statement about the limited nature of the relevant issue before
him.43 The adjudicator’s statement isolated the true issue, namely whether an agreement
had been reached to vary the date for practical completion from that which was expressed
in the written contract. No breach of natural justice arises as a result of this statement.
[50] The applicant submits that the sentence in paragraph [69] of the decision, “… however
the submissions and materials to support the proposition that the Claimant, or Mr
Scroope on behalf of the Claimant, agreed to amend item H in the Special Conditions
have been generated by the Superintendent” reveals reasoning that is “internally
inconsistent”.44 The internal inconsistency is said to arise because in the same paragraph
the adjudicator refers to a revised program issued by Mr Scroope on 27 March 2015,
which indicated 19 March 2015 as day zero in the program. According to the applicant,
the adjudicator does not explain how he found that this program is a document “generated
by the Superintendent” or otherwise how or why he discounts it.45 The revised program
showed a completion date of 19 November 2015.
42 [2016] QSC 108 at [44]-[45].
43 Outline of Submissions for the First Respondent, [43](b).
44 Written Submissions for the Applicant, [44].
45 Written Submissions for the Applicant, [44].
-- 14 of 24 --
15
[51] The adjudicator referred to the revised program in paragraph [69]. The fact that a revised
program was issued by Mr Scroope on 27 March 2015 does not detract from the
adjudicator’s finding that the material supportive of the alleged agreement to amend item
H in the special conditions was generated by the superintendent. That is, an arrangement
or agreement as between Mr Dugan and Mr Scroope for the issuing of a revised program
does not, in itself, evidence an agreed variation to the date for practical completion. The
documents said to evidence this variation were in fact all sent by Mr Dugan. The
adjudicator had already referred to the Notice of Start and Completion dated 25 March
2016 sent by Mr Dugan on 6 May 2015. As previously observed, this notice referred to
the “basement works substantially complete”. The first respondent’s case was that as at
25 March 2015 or 6 May 2015 the basement works had not been substantially completed.
It was also Mr Dugan who sent the email dated 30 September 2015. This was referred to
by the adjudicator in paragraph [60(k)]. In that email Mr Dugan referred to the new start
date as being 15 March 2015 rather than 19 March 2015. He further stated in this email:
“This was a bonus because you already completed the bulk excavation.”
The adjudicator accepted that the basement completion was not actually achieved until
16 October 2015.46 There is in my view no internal inconsistency, as submitted by the
applicant. To the extent that any inconsistency may be identified, it does not constitute
jurisdictional error because there are contemporaneous documents that support the
adjudicator’s finding.
[52] The applicant submits that the adjudicator’s reasoning in paragraph 69 amounts to a
conclusion that the agreement relied upon by the applicant could not be accepted, because
all of the evidence was produced by Mr Dugan. The applicant therefore submits that on
this reasoning, a party propounding an agreement at adjudication could never win, no
matter how cogent the evidence was, unless the agreement was admitted or evidenced in
the other party’s documents.47 The submission is in effect, that jurisdictional error
occurred because the adjudicator failed to identify a proper basis for rejecting Mr Dugan’s
evidence as to an agreement to vary the date for practical completion. The applicant
submits that the rejection of Mr Dugan’s evidence by the adjudicator on the basis that it
has been generated by Mr Dugan was irrational and without foundation.48 This
submission was further explained in oral submissions by Senior Counsel for the applicant:
“The jurisdictional error that we argue is that he never got to the point of
considering that evidence and whether or not it made out the agreement
altered the date for practical completion because he rejected it, and it was the
rejection that constituted the jurisdictional error, because we accept that we
have to get to the point where he rejected it without reason, for want of a
better word, and we accept that he said something about it in his reasons.”49
[53] I do not accept that the adjudicator’s reasoning in this respect reveals jurisdictional error.
The first respondent, through Mr Scroope, had no right to reply to the adjudication
response, including Mr Dugan’s statutory declaration.50 The adjudicator’s starting point
46 Exhibit “ETB-6” of the Bird affidavit, page 191, [71]-[72].
47 Written Submissions for the Applicant, [46].
48 Written Submissions for the Applicant, [45].
49 T1-7, line 46 to T1-8, line 4.
50 See [16] above.
-- 15 of 24 --
16
in his consideration of whether there was a variation, was the express provision of the
written contract. This provision identified the date for practical completion as being 35
weeks after the completion of the basement. The adjudicator was therefore deciding
whether there had been a variation to an express term of the contract. It is implicit in this
proposition that the adjudicator would have required cogent evidence that the parties had
actually agreed to such a change, particularly where such a variation exposed the first
respondent to liquidated damages from an earlier date. This is in circumstances where
Mr Scroope had stated in his statutory declaration that not only were the basement works
not completed by 25 March 2015 or 6 May 2015, but that it was never agreed, expressly
or otherwise, to change the start date of the 35 week period from being the completion of
the basement. It was by reference either expressly or implicitly to all these matters that
the adjudicator concluded:51
“… I am not satisfied that the submissions and materials provided by the
Superintendent are sufficient to substantiate that the parties agreed to amend
what is a fundamental provision in the Contract.”
This does not constitute a rejection of Mr Dugan’s evidence simply on the basis that the
evidence was generated by him. Even if the reasoning was inadequate, insufficient,
inconsistent or illogical, at least some process of reasoning for arriving at the decision is
revealed. No jurisdictional error is therefore established.
[54] The first respondent submits that if this aspect did involve jurisdictional error, it did so
only to the extent of the adjudicator’s consideration of a set-off of $164,160.00. By
reference to s 100(4) of the Act the first respondent submits that the part of the
adjudicator’s decision not affected by jurisdictional error is the part which is not affected
by the claim for set-off.52 Section 100(4) is a remedial provision that applies where the
Court is able to identify “the part of the decision” affected by the error and “allow the
part of the decision not affected by the error to remain binding on the parties to the
proceeding”. The applicant submits however, that the discretion in s 100(4) cannot be
exercised because if jurisdictional error was found the liquidated claim does not relate to
a particular part of the decision in that it does not relate to a discrete claim under the
contract.53 As I have found that the reasons for decision are not affected by jurisdictional
error, it is not necessary to decide whether the set-off amount of liquidated damages of
$164,160.00 could be severed in accordance with s 100(4).
The second alleged jurisdictional error
[55] The applicant submits that the adjudicator committed jurisdictional error by failing to
consider the provisions of the contract relevant to time limitations in respect of claims for
certain variations. These time bar issues had not been raised by the applicant in its
payment schedule.
[56] This jurisdictional error concerns the adjudicator’s decision in respect of six variations,
11A, 58, 60, 61A, 67, 69 and 72. The adjudicator found against the first respondent in
51 Exhibit “ETB-6” to the Bird affidavit, page 191, [69].
52 Outline of Submissions for the First Respondent, [7].
53 Applicant’s Written Submissions, [74].
-- 16 of 24 --
17
respect of variation 11A.54 The sum allowed by the adjudicator for the variations, apart
from variation 11A, was $64,354.40 (inclusive of GST).
[57] In the adjudication application at paragraph 8.1(b)(i) the first respondent raised the issue
of whether it had complied with the contractual time requirements in respect to
variation 024. The decision of the adjudicator in relation to this variation is not the subject
of any complaint concerning jurisdictional error. In paragraph 8.1(b)(i) of the
adjudication application the relevant time requirements in the contract are identified as
follows:55
“(A) Clause 8.1(c) of the Schedule of Amendments – that is, the claimant
failed to make a variation claim within 10 days of receiving the
direction and in any case prior to the commencement of the Work to
which the direction relates; or
(B) Clause 13(d) of the Schedule of Amendments – that is, the claimant
failed to make a variation claim within 15 days after receipt of the
Superintendent’s instruction, or prior to commencement of the work,
whichever is the earlier.”
[58] Paragraph 8.1(b)(ii) of the adjudication application referred to a number of variations
which had not been approved by the superintendent, including variations 60 and 72 which
are the subject of complaint. Variation 58 is referred to in paragraph 8.1(b)(iii) of the
adjudication application but not in the context of any time requirements under the
contract. The adjudication application in paragraphs 8.3 to 8.6 specifically raised the
operation of s 24(4) of the Act which provides that the adjudication response cannot
include any reasons for withholding payment unless those reasons were included in the
payment schedule when served on the claimant.
[59] The contractual time requirements were raised by the applicant in its adjudication
response in paragraphs 3.16 to 3.24.56
[60] It was in that context that the adjudicator considered the issue of variations at paragraphs
[84] to [283]. The adjudicator dealt with the submissions in respect of s 24(4) of the
Act:57
“Each party also included submissions in respect of s 24(4) of the Act. I am
satisfied that this section is relevant where submissions in the adjudication
response and the Superintendent’s statutory declaration submitted with the
adjudication response attributable to a variation include reasons for
withholding money that are not included in the submissions in the payment
schedule that are attributable to the variation.
The parties have provided extensive submissions dealing with conditions
precedent to the Claimant’s entitlement to make claims for unapproved
variations. I have read the submissions in detail and have taken them into
54 Exhibit “ETB-6” to the Bird affidavit, pages 203-204, [119]-[126].
55 Exhibit “ETB-3” to the Bird affidavit, page 34.
56 Exhibit “ETB-4” to the Bird affidavit, pages 79-81.
57 Exhibit “ETB-6” to the Bird affidavit, page 195, [86]-[87].
-- 17 of 24 --
18
account where appropriate and where the Respondents’ and Superintendent’s
submissions in the adjudication response attributable to individual variations
do not contravene s 24(4) of the Act.”
[61] The adjudicator applied this reasoning to the relevant variations. For example, in relation
to variation 58 the adjudicator stated:58
“I found no reference to a time bar in the reasons in the payment schedule
associated with V058. On that basis, the Superintendent’s submission in the
adjudication response that the claim is time barred contravenes s 24(4) of the
Act. I am not satisfied that the submissions are submissions that had been
properly made for the purpose of s 26(2) of the Act.”
[62] Pursuant to s 26(2) in deciding an adjudication application the adjudicator is to consider
specified matters only. These matters include the provisions of the Act, the provisions of
the construction contract from which the application arose and the payment schedule, if
any, to which the application relates, together with all submissions, including relevant
documentation, that have been properly made by the respondent in support of the
schedule. As submitted by the first respondent, s 26(2) both defines and confines the
matters to be considered by the adjudicator: 59
“The section does not impose a jurisdictional requirement that the
adjudicator’s consideration of the listed matters be exhaustive or free of legal
or factual error. What is required is for the adjudicator to genuinely (in good
faith) consider the list of matters. Provided that they have done that, an error
in the consideration of those matters will not affect the validity of the
decision.”
[63] The applicant however submits that an adjudicator may be obliged to take into account
the provisions of the contract that are relevant to the sums claimed in the payment claim,
even if those provisions are not raised in the payment schedule; and that a failure to do so
amounts to jurisdictional error.60
[64] The submission proceeds on the basis that the applicant accepts that an adjudicator
cannot, pursuant to s 26(2)(d), consider any submission not properly made. Here, the
time requirement submissions in the adjudication response were not properly made
because they were not included as a reason for withholding payment in the payment
schedule as required by s 24(4). The applicant’s submission is not that the contractual
time requirements had to be taken into account by the adjudicator pursuant to s 26(2)(d)
but rather the adjudicator should have taken these contractual time requirements into
consideration because of s 26(2)(b).61
58 Exhibit “ETB-6” to the Bird affidavit, page 229, [224].
59 Outline of Submissions for the First Respondent, [18] citing Holmwood Holdings Pty Ltd v Halkat Electrical
Contractors Pty Ltd [2005] NSWSC 1129 at [34]-[49]; Brookhollow Pty Ltd v R & R Consultants Pty Ltd
[2006] NSWSC 1 at [56]; McNab Developments (Qld) Pty Ltd v MAK Construction Services Pty Ltd [2015]
1 Qd R 250.
60 Written Submissions for the Applicant, [68].
61 T1-19, lines 14-21.
-- 18 of 24 --
19
[65] The applicant seeks to make good this submission by reference to a number of authorities,
none of which are directly on point.
[66] In Roseville Bridge Mariner Pty Ltd v Bellingham Marine Australia Pty Ltd62 Brereton J
had to consider whether an alleged agreement said to constitute an accord and satisfaction
and which sought to preclude a claim in respect of variations, was void by operation of
s 34 of the NSW Payments Act. His Honour observed:63
“The Act does not create a right to remuneration for construction work – that
right is created by the construction contract. What the Act does is to create
and regulate a right to obtain a progress payment. It is inherent in the concept
of a progress payment that it be a payment on account of the amount
ultimately due. The contract provides the starting point for the determination
of rights under the Act …”
[67] In State Water Corporation v Civil Team Engineering Pty Ltd64 Sackar J accepted that,
for the purposes of the NSW equivalent to s 26(2)(d) of the Act, a submission was not
“duly made” as it “clearly and obviously advanced reasons for non-payment which were
not included in State Water’s payment schedule”.65 His Honour however accepted that
the adjudicator was still permitted to consider the submission even if not duly made
provided it was relevant to issues arising under s 22(2)(a) or (b): 66
“However, it must be remembered that the claimant’s and respondent’s
submissions (duly made) are only two of a number of matters that the
adjudicator is required to consider. Accordingly, an adjudicator should not
ignore something of real relevance to issues arising under s 22(2)(a) or (b) (or
both), simply because the matter was not raised in submissions duly made by
the parties (John Holland Pty Ltd v RTA at [47]-[48]).That applies even where
the adjudicator only gained an awareness of those particular matters (i.e. of
particular provisions of the relevant construction contract or the Act, as
opposed to the facts and circumstances of the particular case) from having
come into contact with submissions not duly made (Minister for Commerce v
Contrax Plumbing (NSW) Pty Ltd [2005] NSWCA 142 at [35] per Hodgson
JA). But where that situation arises, the adjudicator must bear in mind the
need to afford natural justice to the parties. To address that problem, the
adjudicator may wish to call for further submissions (s 21(4)(a)) or arrange a
conference (s 21(4)(c)).”
[68] The applicant submits by reference to the above quoted passage that even though the
adjudicator was not required to consider the contractual time requirements in the context
of s 26(2)(d) as submissions “properly made”, the contractual provisions, having been
brought to his attention, should have been considered by him as required by s 26(2)(b).
The failure to consider the contractual time requirements therefore constitutes
jurisdictional error.
62 [2009] NSWSC 320.
63 [2009] NSWSC 320 at [43].
64 [2013] NSWSC 1879.
65 [2013] NSWSC 1879 at [66]. The NSW Payments Act uses the term “duly made” rather than “properly made”
as used in s 26(2)(d) of the Act.
66 [2013] NSWSC 1879 at [70].
-- 19 of 24 --
20
[69] The relevant challenge to the adjudication decision in State Water was that in arriving at
his determination the adjudicator, contrary to the New South Wales equivalent to s 24(4)
of the Act, took into account a number of submissions for non-payment advanced by State
Water in its adjudication response, which were not included in its payment schedule.
These “impermissibly considered” submissions all concerned the proper construction of
clause 12 of the contract and included:
(a) the relevance of the parol evidence rule to the construction of the contract;
and
(b) the effect of Codelfa Constructions Pty Ltd v State Railway Authority (NSW)
on the permissible use of extrinsic evidence when construing the contract.67
[70] State Water submitted that even if the submissions had not been “duly made” the
adjudicator was still permitted to consider them provided they were relevant to issues
arising under the New South Wales equivalent of s 26(2)(b) of the Act.
[71] Sackar J was therefore considering whether an adjudicator was permitted to take into
account submissions that had not been raised in the payment schedule. The issue in the
present case is the reverse. It is whether an adjudicator, having decided that a submission
contravened s 24(4) and was not properly made for the purposes of s 26(2)(d), is
nonetheless required to consider the submission if it raises for consideration provisions
of the contract. This is quite a different issue to that considered in State Water and raises
different considerations. There is, for example, a tension, on the applicant’s case,
between the requirement of the adjudicator to consider the provisions of the Act under
s 26(2)(a) which include s 24(4) and s 26(2)(d) (which specifically limit the reasons for
withholding payment which may be included in the adjudication response), and the
requirement in s 26(2)(b) for the adjudicator to consider the provisions of the contract.
[72] Under s 26(2)(d) it is the role of the adjudicator to determine whether submissions are or
are not properly made and whether a submission contained in an adjudication response is
one that should not be considered because of the effect of s 24(4).68
[73] In State Water Sackar J decided that the adjudicator’s consideration of State Water’s
submissions on the proper construction of clause 12 of the contract was permissible
pursuant to the New South Wales equivalent to s 26(2)(b) of the Act. This was on the
basis that the submissions were “of real relevance”.69 His Honour was not dealing with
a case such as the present, where an adjudicator, aware that the payment schedule raises
time bar issues under the contract, refuses to deal with such issues on the basis they
contravene s 24(4).
[74] The applicant referred to two further authorities. In Holmwood Holdings Pty Ltd v Halkat
Electrical Contractors Pty Ltd & Anor70 Brereton J had to consider jurisdictional error in
67 [2013] NSWSC 1879 at [41]-[42] per Sackar J.
68 John Holland Pty Limited v Roads & Traffic Authority (NSW) [2007] NSWCA 19 at [63] per Hodgson JA
(with whom Beazley JA agreed) and at [71] per Basten JA.
69 [2013] NSWSC 1871 at [70]-[71].
70 [2005] NSWSC 1129.
-- 20 of 24 --
21
the context of a failure by an adjudicator to have regard to a contractual provision relevant
to the adjudication. Unlike the present case the payment schedule had raised as an issue
how the claim as put could be justified, having regard to the percentage works to be
complete, which supported a significantly lower figure than that claimed by the
claimant.71 His Honour concluded:
“Accordingly, I conclude that a failure by an adjudicator to have regard to a
provision of the construction contract which is relevant to the adjudication
under consideration is jurisdictional error, resulting in invalidity of the
determination.”72
[75] Holmwood was not concerned with whether an adjudicator is required to consider the
provisions of the contract where those provisions are not raised in a payment schedule as
a reason for withholding payment. As observed by Brereton J, the requirement for
consideration in accordance with the NSW Payments Act equivalent to s 26(2)(b)) is not
a requirement to consider each and every provision of the contract:
“… that does not mean that the requirement in s 22(2)(b) to consider the
provisions of the contract has the effect that in each adjudication the
adjudicator must consider every provision of the contract – any more than the
requirement in s 22(2)(a) to consider the provisions of the Act has the effect
that in each adjudication the adjudicator must consider every provision of the
Act; both the paragraphs are to be read as requiring consideration of the
provisions only to the extent that they relevant to the adjudication application
in question. In other words, the adjudicator is not required to consider
provisions of the Act or the contract which had no bearing on, or relationship
to, the adjudication application under consideration. This follows from the
stated function of the considerations required by s 22(2) – which is, as its
opening words express, “in determining an adjudication application” – and
from the great inconvenience without utility which any other construction
would involve.”73
[76] In QCLNG Pipeline Pty Ltd v McConnell Dowell Constructors (Aust) Pty Ltd & Ors,74
QCLNG sought a declaration that the adjudicator’s decision was void as a result of, inter
alia, the adjudicator’s failure to consider the contractual requirements in clause 32.4(a)
for the contractor to provide estimates within a specified period, notwithstanding
submissions in the adjudication response relying on this provision. Peter Lyons J
determined that the failure on the part of the adjudicator to consider submissions in
respect of the effect of this clause constituted a failure by the adjudicator to comply with
an essential requirement of the Act for a valid decision.75 QCLNG did not however,
concern a failure to consider a contractual provision in circumstances where the provision
was not raised in a payment schedule as a reason for withholding payment.
71 [2005] NSWSC 1129 at [14].
72 [2005] NSWSC 1129 at [51].
73 [2005] NSWSC 1129 at [50].
74 [2011] QSC 292.
75 [2011] QSC 292 at [123]; City of Ryde v AMFM Constructions Pty Ltd & Anor [2011] NSWSC 1469 at [22]
per Brereton J and State Water Corporation v Civil Team Engineering Pty Ltd [2013] NSWSC 1879 at [71]-
[72] per Sackar J.
-- 21 of 24 --
22
[77] The first respondent submits that the extent to which an adjudicator is required to consider
the provisions of the contract is affected by the payment claim and payment schedule, and
the adjudication application and adjudication response in relation to those matters,
because they, in turn, frame the scope of the dispute. Necessarily an adjudicator is not
obliged to address provisions of a contract which are not raised as a reason for
withholding payment in a payment schedule.76
[78] The first respondent referred to the following sections of the Act as framing the scope of
the dispute. Section 18(3) requires a payment schedule to state the reasons for
withholding payment. Such reasons may include contractual provisions limiting the
claimant’s right to payment.77 As observed by Hodgson JA in John Holland at [33], the
plain purpose (of s 24(4)) is “to avoid new submissions being introduced late in a process
going ahead on a brief and strict timetable”. The introductory words of s 26(2) “in
deciding an adjudication application” are significant in construing s 26(2)(b) which
requires the adjudicator to consider the provisions of the contract from which the
application arose. From these introductory words it is evident that what the adjudicator
decides is the adjudication application, not whether a progress payment should be made
under the relevant contract. As stated by Mason P in Clarence Street Pty Ltd v ISIS
Projects Pty Limited:78
“The joinder of issue thus achieved sets the parameters for the matters that
may be contested if an adjudication under the Act ensues …”
[79] Senior counsel for the first respondent submits that the decision of the New South Wales
Court of Appeal in John Holland governs the present case.79 In that case the adjudicator’s
reasons referred to submissions made in the adjudication response that had not been
included in the payment schedule and would not therefore be considered.80 Similarly in
the present case, the adjudicator, being aware of the time bar submissions, turned his mind
to that issue and decided they should not be considered because of the operation of
s 24(4).
[80] Similar to the applicant’s submission in the present case, in John Holland it was submitted
that the adjudicator was obliged to consider the substance of the submission, because it
concerned the Act, the contract and the payment claim, all of which the adjudicator was
required to consider under s 22(2) of the NSW Payments Act.81
[81] Hodgson JA at [47] adhered to the views that his Honour had expressed in the Minister
for Commerce v Contrax Plumbing (NSW) Pty Ltd82 at paragraphs [33]-[36].83 In Contrax
his Honour stated:84
76 Outline of Submissions for the First Respondent, [57].
77 John Holland Pty Limited v Roads & Traffic Authority of NSW [2007] NSWCA 19 at [33] per Hodgson JA
(with whom Beazley JA agreed).
78 (2005) 64 NSWLR 448, 455 at [30].
79 T1-43, lines 4-5.
80 [2007] NSWCA 19 at [17] per Hodgson JA (with whom Beazley JA agreed).
81 [2007] NSWCA at [21] per Hodgson JA (with whom Beazley JA agreed).
82 [2005] NSWCA 142.
83 T1-43, lines 4-5.
84 [2005] NSWCA 142 at [35].
-- 22 of 24 --
23
“However, paragraphs (a) and (b) of s.22(2) require the adjudicator to
consider the provisions of the Act and the provisions of the construction
contract; and in my opinion, that entitles and indeed requires the adjudicator
to take into account any considerations (other than considerations arising
from facts and circumstances of the particular case not otherwise before him
or her) that he or she thinks relevant to the construction of the Act, the
construction of the contract, and the validity of terms of the contract having
regard to provisions of the Act. Thus, in my opinion, if an adjudicator comes
to know of submissions of a respondent that he or she thinks to be relevant to
these questions (not being submissions based on facts and circumstances of
the particular case not otherwise before him or her), he or she can take them
into account under paragraphs (a) and (b), even if they cannot be considered
under paragraph (d).”
[82] His Honour clarified the effect of what he had said in Contrax at [48] of John Holland:
“… I was saying that the adjudicator should not ignore something which he
or she is aware of and also believes is of real relevance to issues arising under
paras (a) and (b), simply because the matter was not raised in submissions
duly made by a respondent.”
Nothing in his Honour’s observations as clarified suggest that the adjudicator in the
present case was required to have regard to the time bar issue in circumstances where it
had not been raised in the payment schedule. By reference to s 24(4), the adjudicator
decided that he would not have regard to the time bar issue. It was not jurisdictional error
for the adjudicator, being aware of the time bar issue, not to consider it because of his
view of the operation of s 24(4). If the adjudicator erred in the application of s 24(4), this
is an error committed within jurisdiction. This is because the adjudicator has not failed
to consider the time bar issue but rather refused to consider the issue because of the
operation of s 24(4).
[83] As stated by Hodgson JA in John Holland:85
“Thus, in my opinion, any requirement to consider such matters which were
not raised in submissions duly made arises only after a threshold is crossed,
involving both awareness of the matters in question and a belief that they are
of real relevance. In this case, I would infer that the adjudicator became aware
of the submissions to the extent necessary for forming a view that they were
affected by s.20(2B), but there is no basis for any conclusion that the
adjudicator believed they were of substantial relevance to issues arising under
pars. (a) and (b) of s.22(2).
In those circumstances, in my opinion the adjudicator was not required to
consider RTA’s jurisdiction submissions by reason of par.(a) and/or par.(b)
of s.22(2).”
[84] The distinction that should be made is between a failure to consider a relevant contractual
provision which may constitute jurisdictional error and an adjudicator’s decision not to
85 [2007] NSWCA 19 at [49]-[50].
-- 23 of 24 --
24
consider such a provision because of the operation of s 24(4) which, if erroneous, would
constitute an error within jurisdiction.86 No jurisdictional error has been identified.
[85] The parties accept that had this jurisdictional error been established, the affected part of
the decision, namely $64,354.40, could have been severed pursuant to s 100(4).
Disposition
1. The applicant’s originating application filed 20 September 2016 is dismissed.
2. I will hear the parties as to cost.
86 [2007] NSWCA 19 at [57] per Hodgson JA (with whom Beazley JA agreed) and at [71]-[72] per Basten JA.
-- 24 of 24 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2016/268