Baldwin & Anor v Icon Energy Ltd & Anor (No 3) [2016] QSC 18
SUPREME COURT OF QUEENSLAND
CITATION: Baldwin & Anor v Icon Energy Ltd & Anor (No 3) [2016]
QSC 18
PARTIES: RONALD WILLIAM BALDWIN
(first plaintiff)
SOUTHERN FAIRWAY INVESTMENTS PTY LTD
ACN 115 060 378
(second plaintiff)
v
ICON ENERGY LTD
ACN 058 454 569
(first defendant)
JAKABAR PTY LIMITED
ACN 058 454 765
(second defendant)
FILE NO/S: SC No 3667 of 2014
DIVISION: Trial Division
PROCEEDING: Application to amend pleadings
Application to strike out pleadings
ORIGINATING
COURT:
Supreme Court at Brisbane
DELIVERED ON: 18 February 2016
DELIVERED AT: Brisbane
HEARING DATE: Written submissions
JUDGE: Philip McMurdo JA
ORDER: The plaintiffs to pay the defendants’ costs of the plaintiffs’
application filed 12 May 2015 and the defendants’
application filed 15 May 2015.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – COSTS – GENERAL RULE:
COSTS FOLLOW EVENT – GENERAL PRINCIPLES AND
EXERCISE OF DISCRETION – where orders were made on
15 October 2015 giving the plaintiffs leave to amend their
statement of claim – where the defendants otherwise
succeeded on their cross-application by having significant
portions of the further amended statement of claim struck out
– where the plaintiffs argued that an order that the plaintiffs
pay 60 per cent of the defendants’ costs in both applications
would reflect the partial success enjoyed by both parties –
whether the defendants are entitled to all their costs of the
applications
-- 1 of 2 --
2
Baldwin & Anor v Icon Energy Ltd & Anor (No 2) [2015]
QSC 286, cited
COUNSEL: D A Skennar for the first and second plaintiffs
A Nicholas for the first and second defendants
SOLICITORS: Clayton Utz for the first and second plaintiffs
HopgoodGanim for the first and second defendants
[1] PHILIP McMURDO JA: This judgment determines questions of costs arising from last
year’s judgment when I made orders as to what parts of the plaintiffs’ claims should be
allowed to go forward.1 The plaintiffs were given leave to amend the claim and the
statement of claim to add claims for damages and exemplary damages for deceit. To that
extent their application succeeded. It was otherwise dismissed. The defendants
succeeded on their cross-application by having a great deal of the further amended
statement of claim struck out, although the plaintiffs were given leave to replead in certain
limited respects.
[2] The plaintiffs submit that each party enjoyed some success and that this would be
appropriately reflected in an order that the plaintiffs pay 60 per cent of the defendants’
costs of both the plaintiffs’ and defendants’ applications. For the defendants it is
submitted that they should have all of their costs.
[3] It is correct that the plaintiffs enjoyed some success. This was by their being allowed to
prosecute a claim for damages for deceit. However this was permitted by reference to a
draft statement of claim which was delivered by the plaintiffs only after the hearing.
During the hearing the plaintiffs’ counsel acknowledged that there were deficiencies in
an earlier draft which had been provided on the eve of the hearing. In turn that draft
acknowledged deficiencies in its predecessor, the Further Amended Statement of Claim
filed on 10 April 2015, which was the subject of the defendants’ strike out application.
So although the plaintiffs can claim some ultimate success, this resulted only from their
addressing deficiencies in several previous editions of the pleading. When this post
hearing pleading was delivered, the defendants conceded that their remaining concerns
could be addressed by a request for particulars. Therefore the defendants’ costs of
addressing this part of the plaintiffs’ case were incurred at times when there were
deficiencies in the pleading of it. With that in mind it would be unfair to deny the
defendants their costs in that respect.
[4] The defendants were otherwise successful. It is true that not every submission for the
defendants was accepted. But the other parts of the plaintiffs’ case which were challenged
by the defendants were either struck out or not permitted to go forward as additions to the
plaintiffs’ case.
[5] For these reasons the plaintiffs should pay the defendants’ costs of both applications.
1 Baldwin & Anor v Icon Energy Ltd & Anor (No 2) [2015] QSC 286
-- 2 of 2 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2016/018