Board of Professional Engineers of Queensland v Peter Knight [2016] QCAT 493
CITATION: Board of Professional Engineers of
Queensland v Peter Knight [2016] QCAT 493
PARTIES: Board of Professional Engineers of
Queensland
(Applicant)
v
Peter Knight
(Respondent)
APPLICATION NUMBER: OCR160-15
MATTER TYPE: Occupational regulation matters
HEARING DATE: 5 and 6 December 2016
HEARD AT: Brisbane
DECISION OF: Member P Roney QC
DELIVERED ON: 14 December 2016
DELIVERED AT: Brisbane
ORDERS MADE: The application is dismissed.
CATCHWORDS: Disciplinary proceedings against a structural
engineer – Professional Engineers Act 2002;
test to be applied for unprofessional conduct;
where conflicting expert evidence concerning
the adequacy of design; complex engineering
design making requiring the exercise of
judgement and design compromise to cater for
conflicting criteria; Relevance of the costs to
remedy failures to whether that has been
unprofessional conduct.
Professional Engineers Act 2002 – s 3, s 7, s
129, s 131
Adamson v Queensland Law Society
Incorporated [1990] 1 QdR 498
Board of Professional Engineers of
Queensland v Manwin [2009] QCCTE 1
BPEQ v Jutte [2005] QCCTE 2
Briginshaw v Briginshaw [1938] 60 CLR 336
Law Society of New South Wales v Harvey
[1976] 2 NSWLR 154
Law Society of New South Wales v Moulton
[1981] 2NSWLR 736
-- 1 of 19 --
2
Manwin v Board of Professional Engineers of
Queensland [2008] QDC 204
Re Seidler [1986] 1 QdR 486
Rejfek v McElroy (1965) 112 CLR 517
APPEARANCES:
APPLICANT: Ms P Morreau of Counsel instructed by Clarke
Kann Lawyers for the Applicant
RESPONDENT: Mr A Harding of Counsel instructed by Thynne
Macartney for the Respondent
REASONS FOR DECISION
Introduction – the principal issue .................................................................................. 2
Background .................................................................................................................. 3
Relevant legal principles .............................................................................................. 4
The notion of “unsatisfactory professional conduct” ...................................................... 6
The pier design issue and the evidence of the experts generally .................................. 9
Horizontal ground strains............................................................................................ 14
Drainage of the subfloor space ................................................................................... 16
The use of agg drains connected to the stormwater drainage system ........................ 17
Cost associated with remedying defects to the affected buildings .............................. 18
Introduction – the principal issue
[1] This is a disciplinary proceeding against an engineer who has more or less
retired from practice. It concerns the adequacy, principally of foundations
designed for a 17 building retirement accommodation facility in 2005. The
proceeding was contested and there were engineers called for each side in
an attempt to demonstrate the adequacy or otherwise of the relevant
engineering design but also going to the question of whether the design
showed a lack of adequate knowledge, skill, judgement or care in the
practice of engineering having regard to what might be reasonably
expected of a registered professional engineer.
[2] A principal point of interest which the proceeding throws up concerns the
proper methodology to be applied to deciding whether there has been
professional misconduct in circumstances where the engineer in question
contends that he sought to provide a considered engineering solution to a
difficult engineering problem with conflicting elements, and whether it is
enough to show in a proceeding such as this that another engineer, or
perhaps a body of them would not have adopted the particular methodology
adopted in that case, or would have applied a different, albeit perhaps
significantly more expensive solution to that which was provided. In other
-- 2 of 19 --
3
words, the question is whether it is demonstrated that there is a lack of
judgement or care in the practice of engineering where, although the expert
engineer called for the Board asserted a multiplicity of non-compliances
with what he regarded as the appropriate design methodology, there was
conflicting expert evidence to the effect that the adopted solution was within
the range of possible solutions a prudent engineer might have adopted.
Background
[3] The Respondent is a registered structural engineer with in excess of 35
years of experience in that role. He operated a structural engineering firm,
through his company Knight Consulting Pty Ltd from 1988. Knight
Consulting formally ceased operating in 2010 and the Respondent is now
transitioning to retirement.
[4] In 2002 Knight Consulting, and the Respondent, were engaged to provide
engineering services for what came to be a retirement village situated at
56A Moores Pocket Road, Moores Pocket, in an area adjacent to the
Bremer River in the Ipswich district. The builder engaged Mr Knight to
prepare a foundation and structural steel designs for some of the proposed
buildings. Other engineers with different organisations were involved to
prepare the road works, and bulk earthworks, and there is some evidence
that there may have been hydraulic engineering work done as well. In
consequence, the Respondent prepared 13 foundation and structural steel
designs for what came to be 17 buildings comprising the village, with each
building comprising multiple retiree units. This will also a recreation building.
The designs were based on architectural and preliminary building
application drawings prepared by “Project A Building Design and Drafting”.
The proposed builder for the development which engaged the Respondent
was Mark Middleton who conducted the company Qld Project
Developments Pty Ltd.
[5] The retirement village came to be constructed based upon the
Respondent’s engineering design, and by which he certified on 5 January
2005. There were some adjustments made to the drawings after
certification which allowed for adjustment pockets on the tops of piers
supporting the buildings and the addition of some detail for sub-floor
ventilation. By 2008 some damage had become evident in some of the
buildings at the Tivoli Gardens Village and the Respondent inspected that
damage, although he did not recommend any adjustment or repair to the
floors which had been affected. In February 2011, the Building Services
Authority (as it then was) engaged a consultant engineer, NJA Consulting,
and it produced a report into the nature and cause of the damage in what
before me came to be known as the NJA report. The author of that report
was a Senior Structural Engineer, John Van de Hoef.
[6] Essentially, the NJA report concluded, after an examination of the design,
that the system design for the buildings did not comply with the “deemed to
comply” requirements of the Australian Standard 2870, and insofar as it
involved a design solution applying engineering considerations which were
-- 3 of 19 --
4
permissible under that standard, it was also unsuitable for site conditions
such as those which were present in this case.
[7] In July 2014, the QBCC issued a complaint to the Applicant Board about
the Respondent’s conduct in the preparation and certification of the designs
and in August 2014 the Applicant was invited to provide a submission
regarding the complaint. Through his solicitors he responded in October
2014. The Board then appointed an investigator who was another member
of NJA to investigate the complaint in November 2014, but that investigator
was replaced in February 2015 by Mr Peter Wright of Hughes Beal and
Wright Pty Ltd. Mr Wright conducted his principal inspection at the site in
February 2015, and on 24 February 2015 he conducted a record of
interview with Mr Knight. By August 2015 the Applicant Board had
determined to propose a disciplinary proceeding against the Respondent
arising out of his conduct in relation to the development and on
2 September a disciplinary application was filed. That application was
substituted with an amended application filed in this Tribunal on
1 December 2016.
[8] By the terms of the amended application, the Applicant applied for orders
from the Tribunal pursuant to section 131(1) of the Professional Engineers
Act 2002 (the PE Act) that a disciplinary ground is established that the
Respondent behaved in a way that constituted unsatisfactory professional
conduct, namely:
a) Conduct that is of a lesser standard than that which might reasonably
be expected of a registered professional engineer by the public or the
engineer’s professional peers;
b) Conduct that demonstrates incompetence or lack of adequate
knowledge, skill, judgement or care, in the practice of engineering.
[9] The Applicant sought that the Respondent be reprimanded and that a
penalty be imposed for other relief including payment of compensation and
costs.
Relevant legal principles
[10] It is well established that proceedings of a disciplinary nature such as the
present, albeit civil proceedings, with the requisite civil standard of proof
applying, that required to meet the standards of the so called Briginshaw
test; Briginshaw v Briginshaw [1938] 60 CLR 336; Rejfek v McElroy (1965)
112 CLR 517; Adamson v Queensland Law Society Incorporated [1990] 1
QdR 498; Re Seidler [1986] 1 QdR 486.
[11] The Briginshaw principle so-called is understood as requiring care in cases
where serious allegations have been made or a finding is likely to produce
grave consequences. Importantly, Briginshaw does not alter the standard
of proof, that is, on the balance of probabilities, as the High Court
emphasised in its authoritative re-statement of the Briginshaw principle in
Neat Holdings Pty Ltd v Karajan Holdings Pty Ltd [1992] HCA 66; (1992)
-- 4 of 19 --
5
110 ALR 449 at 449–50.Briginshaw does import some flexibility to the civil
standard by directing attention to the strength of the evidence required in
attaining the civil standard of proof, focusing on the probative value of such
evidence. Essentially, it goes to the degree of persuasion of the mind.
[12] Thus the High Court in Neat stated at ALR 449–50 that: “the strength of the
evidence necessary to establish a fact or facts on the balance of
probabilities may vary according to the nature of what it is sought to prove”.
[13] In short, the more serious the allegation, the more probative or stronger the
evidence needs to be. Having said this, in Neat the High Court cautioned
against generalisations about the need for ‘clear’ or ‘cogent’ evidence, even
where the standard of proof was correctly understood. These were ‘likely to
be unhelpful and even misleading’.
[14] The orders which are presently sought are enlivened if I am satisfied that
one of the disciplinary grounds set out in section 131 of the PE Act, but
relevantly the consideration here is whether the Respondent behaved in a
way that constitutes unsatisfactory professional conduct. That expression
is defined by section 7 and Schedule 2 of the PE Act as including, relevantly
for present purposes:
a) Conduct that is of a lesser standard that that which might be
reasonably be expected of a registered professional engineer by the
public or the engineer’s professional peers;
b) Conduct that demonstrates incompetence or lack of adequate
knowledge, skill, judgment or care, in the practice of engineering.
[15] There are other categories of misconduct which are defined in the schedule
to the PE Act, but they are not relevant for present purposes. Indeed
notwithstanding that the application focused in broad terms upon the two
above mentioned categories of unprofessional conduct, in the application
itself the basis on which it is contended that the Respondent’s designs were
defective focused upon the fact that in relevant respects “a competent
engineer, exercising proper skill, knowledge and judgment, would not have
prepared or issued the designs” because they contain specific defects.
[16] There were originally six categories of defects identified, by the conclusion
of the hearing these had been reduced to four and they were as follows:
a) The piers were not suitably designed to resist or otherwise
accommodate uplift forces from the sub-soil as recommended in
Supplement 1 section C4, Clause (d) of Australian Standard 2870-
1996 Residential Slabs and Footings and Clause 4.3.6 and Clause
4.5.4 of AS2159-1995 Piling Code - Structural Issues, or at all.
Particulars
i) The depth of seasonal influence (1.5m to 1.8m) was less than
recommended in AS2870-1996 for Ipswich (2.3m);
-- 5 of 19 --
6
ii) There was a failure to either isolate the top of the pier from uplift
forces, or, alternatively anchor the piers sufficiently deep into the
sub-soil to resist the uplift forces on the top of the piers.
b) The floor framing was not designed to provide longitudinal continuity
or provided with a low friction slip layer to minimise or prevent damage
to the structures from large horizontal ground strains in the event of
subsidence of underground mines.
c) The sub-floor space was excavated into extremely reactive clay soil
and was not provided with any form of drainage to remove water,
should it enter the excavation, so as to prevent excessive reactive clay
soil swelling and damage to the building as recommended in Clause
B2.3(a) of AS2870-1996.
d) The area behind the perimeter walls to the basement spaces were
connected to stormwater drains which could potentially back up and
flood the extremely reactive sub-soil around the perimeter of the
basements causing excessive reactive clay soil swelling and damage
to the building.
The notion of “unsatisfactory professional conduct”
[17] The task of determining the meaning of the expression “unsatisfactory
professional conduct” of course requires a consideration of the language of
that expression in its context in the PE Act, and section 7, Schedule 2. In
submissions, neither party placed before me any authority which had dealt
with the way in which these statutory provisions were to be applied,
particularly in circumstances where there was a real conflict as between
purported engineering experts about whether conduct is unprofessional in
the relevant sense.
[18] Mr James Thomas QC, when sitting on the Queensland Commercial and
Consumer Tribunal, said in Board of Professional Engineers of Queensland
v Manwin [2009] QCCTE 1 at [55] that the term “unsatisfactory professional
conduct” under PE Act ... “is far wider in scope than earlier covers
professional misconduct, “unprofessional conduct” and “malpractice” and
seems to be designed to protect members of the public from incompetence
and other stated shortcomings on the part of professional practitioners”.
That it captures a broader category of unprofessional conduct may be
inferred from the fact that by section 3 of the PE Act, its objects are:
a) To protect the public from insuring professional engineering services
are provided by average to the professional engineer in a professional
and competent way; and
b) To maintain public confidence in the standard of services provided by
registered professional engineers; and
c) To uphold the standards of practice of registered professional
engineers.
-- 6 of 19 --
7
[19] Section 4 provides that the objects are to be achieved, inter alia, by
providing for the registration of engineers, and imposing obligations on
persons about the practice of engineering. Section 129 of the Act provides
that this Tribunal is to have regard to the Code of Practice for Registered
Professional Engineers in Queensland in considering whether an
engineer’s conduct constitutes unsatisfactory professional conduct.
[20] The preamble to the Code provides that engineers “combine detailed
technical and professional understanding and the wise application of that
understanding”. Clause 1.3 of the Code requires that engineers “take
reasonable steps to safeguard the health, welfare, and the safety of the
community”.
[21] Clause 3.1 of the Code requires that a registered professional engineer
bring to the engineering task “knowledge, skill, judgement and care that are
of a standard which might reasonably be expected by the public or the
registered professional engineer’s professional peers. In considering the
appropriate standards, registered professional engineers should have
regard to industry and performance standards”. There is some authority for
the view that there is a high standard expected of engineers because of the
often times critical nature of the responsibilities attaching to their decisions
when taken during the course of practice of their discipline because of the
potentially grave and serious repercussions where there is a lack of such
discipline.1
[22] Of course, the PE Act is not prescriptive, nor does it establish a code of
conduct to be applied to particular engineering problems, nor does it point
the engineer to only one appropriate engineering solution. It is axiomatic
that different engineers might arrive at differing, even conflicting
engineering solutions to the same engineering problems even when
applying appropriate knowledge, skill and judgment in the practice.
Moreover, even where there are accepted Australian Standards, for
example relevantly in this case, AS2870-1996 which concern the design of
residential slab and footings, there is of necessity a requirement for the
exercise of judgment by an engineer as to the manner and extent of its
application to a particular problem and as to whether even if applied, it is
an adequate or appropriate solution to a particular engineering problem.
[23] In Manwin v Board of Professional Engineers of Queensland [2008] QDC
204, Judge McGill made a number of remarks which are relevant to the
issues for considerations in the present case. First he took the view in the
context of a case where an engineer was alleged to have failed to nominate
the maximum permitted span for a continuous beam, that even if such was
a wrong conclusion, it does:
“Not necessarily follow that this error amounted to unsatisfactory
professional conduct”. In the area of negligence the mere fact that a
professional person makes a mistake or is shown to have given advice which
1 BPEQ v Jutte [2005] QCCTE 2 at [101]-[102].
-- 7 of 19 --
8
a Court is persuaded was wrong is not necessarily negligence; the question
is whether it was advice which no such professional exercising reasonable
care and skill would have given, which is really a different question. It seems
to me that there was a separate issue here as to whether the failure to give
correct advice actually amounted to unsatisfactory professional conduct in
one of the ways alleged. The definition of unsatisfactory professional
conduct may extend to negligence, but it does not extend to just making a
mistake”.2
[24] In Manwin there was an allegation as well, that the engineer had engaged
in unsatisfactory professional conduct in refusing to have certified the
designs in a way which the judge suggested amounted to the appellant
being criticised “for being too cautious”.
[25] Whilst expressing the view (Reasons par 24) that proving a case like that
might be difficult, and that in principle an overly cautious engineer might be
found to have engaged in unsatisfactory professional conduct, His Honour
concluded that:
“Such a question would require rather more evidence directly specifically to
those matters, and more consideration from the Tribunal, before such
conclusion could be reached. It may be that a suitably qualified expert would
be able to say that no reasonably competent professional engineer would
have refused to certify the beam. Such evidence if it were accepted would
provide a proper foundation for the finding of unsatisfactory professional
conduct on this basis”.
[26] The point to be observed about this, is that His Honour was, in my respectful
view correctly, identifying that the question to be considered did not merely
turn upon whether conduct by one engineer might be capable of being
criticised by another in a particular case, but whether the evidence went so
far as to provide a proper foundation for and finding of unsatisfactory
professional conduct, having regard to what competent professional
engineers do. If competent professional engineers might do different things
in the same context, even if it involved a different interpretation of or
application of an engineering standard, it does not follow that one or other
of those engineers has engaged in unsatisfactory professional conduct.
[27] In the course of oral submissions by Counsel for the Applicant, I was invited
to examine the evidence of the two engineers who were called (apart from
the Respondent himself) to speak to the adequacy of the design, and to
decide which was is “correct”. When I raised with Counsel the question of
what evidence there was of what the objective standards were for
reasonably competent professional engineers in this context, and referred
to the absence of direct evidence on this subject by the expert called for the
Applicant, the response implied that the establishment of what those
standards were could not conceivably require the calling of a multiplicity of
engineers who would each address the question of what they might have
2 At the Reasons par 18-19, and citing Brickhill v Cooke [1984] 3NSWLR 396 at 399;
“Professional Liability Australia” (Second Ed 2007) page 787.
-- 8 of 19 --
9
done in those circumstances in order to form a view about what were
objectively proper standards of conduct. Professional standards are the
subject matter of evidence before the Courts on a regular basis. The
standards are not proven by the weight of numbers of professionals who
claim to adopt them, but they are not to be inferred from the expressed
design preferences of a particular engineer.
[28] One of the other issues that arose in Manwin v Board of Professional
Engineers of Queensland concerned whether there was unsatisfactory
professional conduct in refusing to certify a strengthened beam. McGill DCJ
at [23] identified that what the engineer in that case had been asked to do
was express a professional opinion, as an engineer, as to whether the
particular structure was adequate. He concluded:
Whether his refusal to certify it as adequate amounted to conduct of a lesser
standard than that which might reasonably be expected of a registered
professional engineer, or conduct that demonstrated a lack of judgment or
care in the practice of engineering, did not depend on whether another
engineer disagreed with him, even if that engineer had been an experienced
structural engineer, but on whether his position was one which demonstrated
a lack of judgment or care, that is to say, was a position which would not
have been taken by any engineer demonstrating appropriate judgment or
care, or would not have been adopted by any engineer behaving in
accordance with the standard reasonably to be expected of him. It is by no
means clear that the respondent’s expert was even purporting to pronounce
on these matters, or that he would have been properly qualified to do so in
relation to an issue of structural engineering. Indeed, it seems to me that his
evidence on the point was appropriately cautious.
The pier design issue and the evidence of the experts generally
[29] The principal complaint against the Respondent that the concrete
reinforced piers designed to go beneath each building and vertically into the
earth for some distance were not suitably designed for the soil type and
other features of the building.
[30] On the Applicant’s case, there were two aspects of this complaint. The first
was that the Respondent, it has said, adopted the incorrect seasonal
influence level in determining the depth of the piers, having regard to what
it is said the Australian Standard 2870-1996 required. The second aspect
concerns an alleged failure to isolate the top of the pier from uplift forces or
anchor the piers sufficiently deep so as to protect them, and the structure
above from vertical pier movement associated with the reactivity of the
subsoil. The second aspect is in part an aspect of the first because it
concerns alternate methodology to constructing deeper piers, which might
have dealt with the consequences of seasonal reactivity in the soil.
[31] It was common ground that at the time the Respondent was engaged to
prepare his designs, that he was made aware that there were two critical
considerations which he was required to address. The first, although not in
his mind necessarily the most critical, was the fact that analysis had shown
that the soils on the site were reactive clay soils. The second was that the
-- 9 of 19 --
10
subject site was in an area in which there were old underground mine
workings, and there was a potential for mine subsidence under the site.
[32] Mr Peter Wright, the expert called for the Plaintiff and a structural and
technical engineer, provided three statutory declarations, with the primary
one dated 3 August 2016 exhibiting most of the historical documents, as
well as his own lengthy investigative report. Mr Wright was also a joint
author of a joint expert report written together with Mr Gould, who was the
structural and civil engineer called in the Respondent’s case.
[33] Apart from his role in providing the joint expert report, Mr Gould prepared
two reports, the first dated 28 May 2015, and the second 11 March 2016.
Both experts gave oral testimony in addition to what was contained in their
reports or statements and each was cross-examined, albeit in neither case
in a way which made any direct or substantial challenge to the conclusions
that each of them had reached in their written material.
[34] For the Applicant it was submitted that I should prefer the opinions
expressed about the adequacy of the design elements by Mr Wright
because he had “extensive apposite experience” and had, since obtaining
his formal qualifications in 1976, undertaken design work in respect of small
buildings, including designing footing and framing systems as well as being
involved in laboratory testing of soils and the classification of sites. He has,
as he swore in his oral testimony, investigated small building failures
including numerous foundation failures, water penetration, foundation
movement and drying of subsoils. I accept that Mr Wright was well qualified
to speak about the design practices that he adopted, and perhaps those of
other engineers with whom he worked and he presented as a careful and
credible witness although, as I have said, cross-examination of him scarcely
challenged the conclusions that he sought to reach that were in conflict with
those reached by Mr Gould.
[35] On the other hand, Mr Gould also had considerable consulting engineering
experience, with a Bachelor of Engineering Degree with Honours from the
University of Queensland in 1978. As with Mr Wright, he had acted as an
expert witness in many Courts over time and had engineering design
experience.
[36] For the Applicant it was submitted that I should prefer the opinions of
Mr Wright over those of Mr Gould because Mr Wright had been more
actively involved in residential design and that Mr Gould had some
experience in that regard but that it was much more dated. Both had had
some professional experience in mine subsidence issues. In his oral
testimony in cross-examination Mr Gould said that he had not recently been
involved in residential footing design, or at least not since 2012. He had
worked on an indigenous housing project across the Northern Territory
where he had been involved in extremely reactive soils. He swore that
before that for many years he had been involved in slab and footing design
for houses, and had also been involved in mining subsidence in areas in
the Ipswich district. He conceded he had not worked on a site where there
were the two features, mine subsidence issues and reactive soil.
-- 10 of 19 --
11
[37] I found Mr Gould to be a careful and objective witness, who was, if anything,
restrained in the way that he expressed his opinions, and overall gave the
impression of being a conservative witness who was careful in the
expressions of opinion he gave.
[38] In each of his reports, Mr Gould set out the basis of the complaints which
were made against the Respondent, dealt with those respects in which
there was a level of judgement and expertise required to reach an
engineering conclusion and expressed a view in terms of whether the
design aspects which were being criticised were to a suitable standard and
in respect of which appropriate skill and judgement had been applied. He
was also careful to identify in a number of ways those respects in which the
Respondent was forced to adopt design criteria imposed upon him by
others involved in the project, to make a decision which involved some
compromise in design judgement.
[39] On the other hand, whilst Mr Wright did not in the way in which he presented
at the hearing room, suggest that he was in any way partial, or advocating
for the position of the Applicant, the same cannot be said of some of the
statements which made their way into his reports. For example, in his report
to the Applicant dated 17 March 2015, in the executive summary thereto,
after expressing opinions that were within his area of expertise, he then
swore the issue in asserting that the Respondent’s conduct in providing the
design for the buildings was in his opinion “of a lesser standard than that
which might reasonably be expected by the public and by his professional
peers”. He also made the assertion that the Respondent’s conduct
demonstrated “a lack of adequate knowledge, skill and judgment in the
practice of engineering”.
[40] I would ordinarily have placed no weight whatsoever upon assertions which
swear the issue which I am to determine, and I have not done so here, as
Counsel for both parties accept I ought not. It is, however, significant that
these statements of opinion were not substantiated in the body of the report
itself by identifying what the relevant Standards were, why they might be
reasonably expected by professional engineers or what the basis was for
the conclusion that the Respondent demonstrated a lack of adequate
knowledge, skill and judgment in his practice.
[41] One of the reasons that may be inferred drove Mr Wright to state these
matters was his interpretation of things that were said to him by Mr Knight
in an interview conducted by Mr Wright on 24 February 2015. Mr Wright’s
first report which contained the aforementioned opinions was produced
within three weeks of that interview. At page 23 of Mr Wright’s first report
he said he took into account the following matters, which he said he derived
from that interview:
a) That the Respondent was aware that mine subsidence could cause
both vertical and lateral movement, possibly in the order of 100mm,
and also that reactive clay soil movement could generate 100mm of
vertical movement;
-- 11 of 19 --
12
b) That the footing piers’ founding depth was selected by adding about
1 metre to the seasonal movement on the subsoil;
c) That the depth of seasonal influence was 1.5-1.8 metres and higher
in Ipswich;
d) That no provision was made in the Respondent’s design drawings to
drain the holes created beneath the buildings;
e) That drains behind the perimeter rat walls were intended to be
connected to the stormwater drainage system and that no
consideration was given to the stormwater drainage surcharging those
drains and saturating the subsoils they were intended to drain;
f) That little consideration was given to uplift forces that could be exerted
on the piers by swelling reactive clay subsoil;
g) That some thought was given to, and the facility designed in order to
re-level the floors should ground movement cause distress and
damage to the superstructure;
h) That some consideration was also given to the necessity to re-adjust
external paving when the floors were re-levelled;
i) That little consideration was given to uplift on the surrounding paths
and rat walls beneath the external walls of the building from swelling
reactive clay subsoil;
j) That some consideration “may have been” given to potential lateral
forces generated by mine subsidence early in the design phase;
k) That “little consideration” was given to the durability of the timber floor;
l) That subfloor ventilation details were included on the drawings in
order to satisfy the building certifier.
[42] The Respondent swore an affidavit dated 3 August 2016 and he was cross-
examined. His explanations for why he did that which he did in the designs
for the subject structure differ significantly both as to their content and their
context in that affidavit and in his evidence from the conclusions which I
have summarised above as having founded the opinions of Mr Wright.
While some attempt was made in cross-examination of the Respondent to
suggest that the differing version he had given in response to the questions
in the interview was accurate, during final addresses, Counsel for the
Applicant conceded that the Tribunal should act upon what the Respondent
said in his affidavit and in his oral testimony, where it conflicted with what
was said in the record of interview. In other words it was not being
suggested that the Respondent is not telling the truth about his state of
knowledge and his design intent, and what he sought to achieve in that
design, in his evidence before me.
-- 12 of 19 --
13
[43] A reading of the conclusions expressed by Mr Gould, demonstrates that
they more consistently adopt the interpretation of the facts described by the
Respondent in the interview, rather than those expressed by Mr Knight in
his testimony.
[44] In general, I prefer the opinions of Mr Gould where they differ with those
expressed by Mr Wright, although they are by no means in conflict on a
wide range of issues, as the topic areas showing the areas of agreement
which appear in the joint expert report reveal.
[45] Against that background, I turn to the first issue, namely the question of
whether the pier design, and their depth manifested unsatisfactory
professional conduct in the relevant sense.
[46] Both experts acknowledge that the Respondent’s design called for piers to
be embedded 2 metres below the blinding layer at a minimum, and that as
Mr Knight had said, some piers were imbedded to a greater depth where a
different soil type was encountered during the drilling. It came to pass
during the evidence-in-chief of Mr Gould that he placed a different
interpretation upon where it was that the depth of influence was to be
calculated, and in his case he would have included the 600mm length of
the piers in the void. In other words, Mr Wright counted only the pillar depth
below ground. Mr Gould counted the length above as well.
[47] Mr Wright expressed his conclusions in terms of what he considered to be
“the more appropriate design solution”, which would have been to embed
the piers no less than 4.6 metres below the blinding level because the
reactive clay soils were more active nearer the ground surface. Hence a
pier imbedded deeper would be more resistant to the heaving of the upper
layers because it was anchored in more stable soil. On the other hand
Mr Wright acknowledged that in the event of mine subsidence, a deeper
pier of the length he proposed may have undergone greater lateral
movement than a shallower pier of 2 metres of depth. He preferred a
solution with a deeper pier because, in his view, mine subsidence was a
less frequent occurrence than movement from reactive clay soil changes
and because in his view, the reactive clay soil movement ought to have
been the dominant design consideration.
[48] On the other hand, Mr Gould gave careful consideration also the
background information and contemporaneous documentation that was
available to the Respondent at the time that he was charged with
conducting his design. His interpretation of that material, which I accept as
more reasoned than that which founded the view of Mr Wright, is that the
dominant design criteria advanced by other engineers, the mining
subsidence engineer and the local authority as set out in the development
approval was to consider the potential for mine subsidence. Hence, whilst
he accepted that imbedding the piers to the greater depth Mr Wright
referred to might have reduced movement from reactive clay soil, it would
not have achieved the objective of having the piers closer to the surface to
minimise the impact of mine subsidence. He identified, consistently with the
unchallenged evidence of the Respondent, that the Respondent had
-- 13 of 19 --
14
designed the structure in a way such that there would be an ability to jack
up the floor to level it. The design specified that this was to occur by
including jacking points and adjustable tie down rods on the piers. Hence
the engineer designed his footings in a way which contemplated, indeed
required floor levels being adjusted periodically to ensure that any
movement was levelled. I accept that it was an intentional design feature of
this engineering solution that the floor was expected to move to some
degree and would have to be adjusted from time to time as it became
necessary. In his view, which I accept, the jacking system was a reasonable
design solution to deal with both mine subsidence and reactive clay soil
movement.
[49] Mr Wright did not agree that allowing for the provision of jacking was an
“appropriate means of managing” reactive clay soil movement issues due
to the frequency of such movement”. There was criticism by the Applicant
of the Respondent for failing to insert something specifically on the
drawings which recognised the need for regular inspection and the
necessary levelling of the floor. Whilst this criticism has some justification,
I accept the unchallenged evidence of the Respondent that he described
the necessity for those inspections to occur in timely meetings he had with
the developer and its representatives.
[50] There was evidence that there would have been considerable additional
expense associated with constructing the piers to the depth that Mr Wright
contended for, and I accept that additional costs would have been
substantial. Mr Gould calculated it at an extra $400,000.00. Mr Wright did a
rough calculation which brought it in at $202,000.00. I prefer Mr Gould’s
evidence as to what that additional cost would have been. Had there been
proper monitoring of levels by the owner the necessary adjustments ought
not have involved significant expense. Mr Gould opined that if he had been
doing the design himself, he would not have adopted the practice which
Mr Wright suggested was “the more appropriate design solution”.
[51] Putting all cost issues aside, and even accepting that a more appropriate
design solution albeit one which involved significantly greater cost than the
one the Respondent adopted, namely to have imbedded the piers at no less
than 4.6 metres, I do not consider that the Applicant has discharged the
onus of demonstrating that the methodology and design philosophy which
the Respondent described in his evidence as having been adopted,
constituted unsatisfactory professional conduct.
Horizontal ground strains
[52] This aspect of the complaint concerned the fact that each of the 17 buildings
consisted of eight separate units set in a row and that they were kept
separate by firewalls to prevent the spread of fire. It was common ground
that in the event of mine subsidence, there could have been resultant
horizontal forces in the soil acting on the buildings and that this was a factor
that needed to be taken into account in the design.
-- 14 of 19 --
15
[53] For the Applicant, via Mr Wright, it was contended that there was a lack of
longitudinal restraint on the floor system to prevent the lateral movement of
one or more units away from the adjoining units. In this opinion, if such a
movement had occurred it could or would result in damage to the walls and
roof framing and cladding. He suggested that “the design solution to this
problem would have been to provide a longitudinal restraint in the form of
rods or beams running the full length of the building, together with slip joints
between the bearers and the concrete piers to allow the piers to move
horizontally without dragging the building’s superstructure with them”.
[54] It is to be observed that the problem which such a design solution might
have existed to prevent, has not in fact occurred. There has not been lateral
movement of any of the units away from adjoining units, nor any mine
subsidence. Hence this is a design problem simpliciter, which has had no
consequence to date.
[55] One of the matters that Mr Wright had originally expressed a view about,
was to the effect that there was no low friction slip layer provided to the pier
framing interface, however it was conceded for the Applicant that such a
slip layer was in fact provided by ant capping, although the Applicant
continued to assert there was still insufficient longitudinal restraint on the
floor system.
[56] There was much debate between the experts as to whether some or other
of the features of the building, as designed, did in fact provide for sufficient
horizontal restraint in the form of edge beams, wall framing and roof
structure, sufficient to resist the horizontal forces if they were mobilised.
According to Mr Gould, since this was a lightweight structure, it had the
ability to move across the top of the piers, and that would relieve the lateral
forces. He did not consider slip joints to be necessary due to the lightweight
nature of the structure. In his oral testimony, Mr Gould gave evidence,
which I accept, that:
a) The Respondent’s design did provide sufficient longitudinal and
latitudinal support because as a rectangular frame it was sufficiently
rigid to hold it together;
b) There were firewalls between each of the units, and these provided
some strength, with the floor being fixed to the bearers and the wall
running down the long side of each building being continuous;
c) The nature of the buildings being lightweight timber structures was to
allow for flexibility, and they were repairable in the event of any
damage;
d) Being lightweight structures they had the ability to move across the
top of the piers which would relieve the lateral forces.
[57] Whilst I accept Mr Wright’s evidence that a better design detail would have
been to provide additional longitudinal support, the fact that it did not do so
does not lead to the conclusion that:
-- 15 of 19 --
16
a) The Respondent did not specifically turn his mind to what lateral
restraints were necessary and design for them accordingly; or
b) In adopting the design that he did, having regard to the considerations
that he took into account, that his design evidenced unsatisfactory
professional conduct in the relevant sense.
Drainage of the subfloor space
[58] Beneath the floor space and adjacent to the piers and rat walls which
surrounded each building was a 600mm void or air space below the floors.
At the foot of that void was a thin concrete layer which went over the
exposed soil and which was generally described as a “blinding layer”. As
particularised, the complaint was that the subfloor space had been
excavated into reactive clay, and that there had not been provided any form
of drainage to remove water should it enter the excavation so as to prevent
excessive movement of the dwelling due to the reactive clay soil, and
consequent damage to the building.
[59] Mr Wright’s conclusion, which came perilously close to swearing the issue,
if it did not actually do so, was that “a prudent engineer would have
designed a drainage system for the subfloor voids to avoid the risk that any
water that should end up in the void space remains trapped, and then soaks
through cracks in the blinding layer to the extremely reactive subsoil”.
[60] I accept the Respondent’s evidence that he did give consideration to the
manner in which these areas would drain, should they be exposed to water.
A critical feature of the opinions expressed by Mr Wright in his report on this
issue as appears at paragraph 3.8.4 of his report, is that the Respondent
did not design drainage systems to remove free water that might enter and
be trapped in the deep excavations beneath the underfloor spaces. He also
insisted that no apparent consideration was given to the possibility that agg
drains, or subsoil drains were designed to be connected to the stormwater
drainage system and that these might cause backflow up the drains into
reactive subsoil. Both of these conclusions are inconsistent with the
unchallenged sworn testimony of the Respondent, that he did give
consideration to this matter. I accept the Respondent’s evidence in that
regard.
[61] As Mr Gould explained, and which I accept, the void was protected from
moisture entering into that area by the fact that there was a fully enclosed
roof over the building, and the surrounding areas around the building had a
fall away from the building so that there might be a minimum or no surface
water entering the void. The rat walls around the perimeter of the building
were designed to protect the void space because there was an agg drain
constructed on the outside of the rat wall which ought to have taken water
away. Thus there was minimal or no requirement for drainage to the void
space. There is no suggestion that there has in fact been any flooding of
the void spaces.
-- 16 of 19 --
17
[62] Ultimately, Mr Wright’s opinions about what should have been done to drain
this area are expressed in terms of what, in his opinion, “ought to have been
done”. He does not express that view by reference to what was common or
usual experience by professional engineers. This is an example of criticism
of a design which might have been improved, but which notwithstanding the
absence of those improved features, did not evidence unsatisfactory
professional conduct in failing to give consideration to the extent to which
there would be prevention of water or moisture access to the void area.
The use of agg drains connected to the stormwater drainage system
[63] The Applicant’s complaint in this regard is that the Respondent designed
the use of agg drains outside the rat walls to the exterior of the building
such that those agg drains were connected to the stormwater drainage.
This is said to be unprofessional conduct where this design was intended
to ensure groundwater from the perimeter of the building, and under the
perimeter pathways, was taken away from the building and minimise the
risk of it penetrating the reactive soil below the building where the footings
were.
[64] Once again, in his original report, Mr Wright’s criticism was that the
Respondent gave no apparent consideration to the possibility that the agg
drains connected to the stormwater drainage system could allow water to
flow back up the drains and into the extremely reactive subsoil adjacent to
the perimeter piers.
[65] In his record of interview with Mr Wright, the Respondent said that the
circumstances by which the design included that design detail was that it
occurred at the request of the certifier. The certifier had approved the
drawings and had the opportunity to review the detail which had been
included by Mr Knight and the certifier had the responsibility to review the
solution that he had nominated. According to Mr Gould’s evidence, which I
accept, it is not unusual for a structural engineer to include requirements
such as ventilation which would ordinarily be taken from architect’s
drawings.
[66] In the joint expert report, Mr Wright’s criticism of the fact that the agg drains
were connected to stormwater was not referenced to any particular
engineering practice or to what might be described as what might
reasonably be expected of a professional engineer in relation to such
issues. His opinion in criticising the drawings was referenced to the fact that
stormwater drains can back up overflow during high intensity rain events
and introduce a risk of soaking the reactive soil. According to Mr Gould,
whose evidence I prefer, the inclusion of perimeter agg drains were a typical
engineering detail intended to provide protection to the void space, and that
the connection of an agg pipe to the stormwater drain was “normal
practice”, particularly as here where the stormwater drain to the north with
reasonable fall. I accept his evidence that likely backup from a stormwater
drain was an insignificant issue and that even if there was a backing up
event, that as designed, the water would eventually drain away at the
conclusion of the event without negative consequences. The Applicant has
-- 17 of 19 --
18
not established that to have included such a detail was unprofessional
conduct.
Cost associated with remedying defects to the affected buildings
[67] In the expert reports, and in the oral testimony before me, there was a body
of conflicting evidence about what the likely cost would be to remedy what
were said to be consequences of the Respondent’s alleged unsatisfactory
professional conduct. Estimates ranged from a figure identified by
Mr Wright as $317,000.00 just in respect of the five of the 17 buildings which
had hitherto been inspected, but extended to an estimated cost of $3.5 to
$4 million to demolish and reconstruct those five buildings. Inferentially, if
all 17 were to be demolished and reconstructed, one would be looking at a
very large sum indeed.
[68] I expressed the view in the course of the hearing that I struggled to see that
the issue of whether those costs were involved or not, was a relevant
consideration to determining whether there had been unsatisfactory
professional conduct. I was assured by Counsel for the Applicant that I
could usefully have regard to those sums in determining whether there had
been unsatisfactory professional conduct. Notwithstanding that assurance,
in a case such as this where the Respondent is not alleged to have failed
to give consideration to relevant issues in the design process, but the
resultant design is criticised, it is difficult to see what these cost estimates
do to assist a resolution of the issues before me. It is common ground that
the Respondent intended the levels of these buildings to be monitored to
ensure that they were re-levelled so that there was no resultant damage.
The fact that the developer or operator of the site did not do this, leading to
an accumulation of problems, does not mean that these costs were in some
way a foreseeable consequence of the design that he developed.
[69] Moreover, it has been well accepted, albeit in an environment in which
Courts were considering whether a solicitor had been guilty of professional
misconduct, that in considering the gravity of the misconduct that the fact
that the client, in the ultimate event, suffered no loss is of little, if any,
relevance.3 As the Court in Moulton said:
“If the acts or omissions of a solicitor constitute professional misconduct,
they do so at the time when they occur. Their character is not changed by
the fact that subsequently a loss, or no loss is sustained. The presence or
absence of loss may throw light on the propriety of action taken to ensure
the adequacy of a security for a loan, but that propriety is to be found
primarily in the steps taken at the time the loan is made, and not by what
happens some years later.”
[70] The Court made reference to the fact that these propositions were not new
law and had been stated much earlier in the decision in Law Society of New
3 Law Society of New South Wales v Moulton [1981] 2NSWLR 736 at [740].
-- 18 of 19 --
19
South Wales v Harvey [1976] 2 NSWLR 154, although having read that
discussion it is less clear on the point that what was said in Moulton.
[71] It follows from the findings that I have made that the application is
dismissed, and I so order.
-- 19 of 19 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2016/493