Barry Pitt Constructions Pty Ltd v Queensland Building and Construction Commission [2016] QCAT 482
CITATION: Barry Pitt Constructions Pty Ltd v Queensland
Building and Construction Commission [2016]
QCAT 482
PARTIES: Barry Pitt Constructions Pty Ltd
(Applicant)
v
Queensland Building and Construction
Commission
(Respondent)
APPLICATION NUMBER: OCR208-15
MATTER TYPE: Building matters
HEARING DATE: 16 May 2016
HEARD AT: Brisbane
DECISION OF: Member Guthrie
DELIVERED ON: 8 December 2016
DELIVERED AT: Brisbane
ORDERS MADE: 1. The application filed on 30 March 2016 to
allow the application to review a decision
filed by the application on 24 November
2015 to proceed out of time is dismissed.
2. The application to extend time to lodge an
application for review of the Queensland
Building and Construction Commission’s
decision dated 29 September 2015 is
dismissed.
3. Time is not extended to lodge an
application for review of the Queensland
Building and Construction Commission’s
decision dated 26 August 2015 to give a
direction to rectify.
4. The application to review a decision is
dismissed.
CATCHWORDS: ADMINISTRATIVE REVIEW – BUILDING –
where extension of time to lodge review
requested – where issue of what it the
reviewable decision
-- 1 of 13 --
2
Queensland Building and Construction
Commission Act 1991 s 86, s 86F, s 87
Queensland Civil and Administrative Tribunal
Act 2009 (Qld), s 6, s 17, s 19, s 33, s 61
Queensland Civil and Administrative Tribunal
Regulation 2009 (Qld), Schedule 1
Queensland Civil and Administrative Tribunal
Rules 2009 (Qld), r 30, 31, 32
Kowalski v Repatriation Commission [2008]
AATA 903
Smith v Queensland Building Services Authority
[2010] QCAT 448
APPEARANCES:
This matter was partly heard and determined on the papers pursuant to s 32 of
the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
APPLICANT: Mr Barry Pitt
RESPONDENT: Ms Rojas and Mr Tan, in house lawyers with
the Queensland Building and Construction
Commission
REASONS FOR DECISION
Background
[1] The applicant in these proceedings is Barry Pitt Constructions Pty Ltd
(BPC). The application to be determined is an application to extend the time
for BPC to lodge an application for review of a decision of the Queensland
Building and Construction Commission (‘the QBCC’). The timeline of events
relevant to the application before me is important.
[2] On 26 August 2015, BPC was directed by the QBCC to rectify certain
building work at a particular site (‘the direction to rectify decision’):
1. Weep holes to the garage walls have been compromised by covering them
with the external concrete paths this contravenes the BCA Part 3.3.4
weatherproofing of masonry, AS 3660.1 3.6 Termite and Risk Management
AS4773.2 2010 Section 9.6.2 Damp-Proof Courses (DPC) – Pertains to Item
1 on the QBCC complaint form
2. Stormwater piping to shed does not comply with the local authority’s
requirement in that connection of stormwater is to be connected to existing
stormwater inlet – pertains to Item 3 on the QBCC complaint form.
[3] The rectification work was to be completed by 26 September 2015.
[4] On or about 29 September 2015, the QBCC carried out a further inspection
to determine whether BPC had complied with the direction to rectify. The
-- 2 of 13 --
3
QBCC effectively concluded that in relation to item 1 no works had been
carried out to rectify the issue to allow compliance with the relevant part of
the Building Code of Australia.
[5] The QBCC then sent a letter to BPC on 29 September 2015 notifying it that
it had not satisfactorily rectified item 1 (‘the failure to rectify decision’).
[6] The notice of the decision dated 29 September 2015, informed BPC of the
potential consequences of its failure to satisfactorily rectify the direction
items including that the failure may result in a claim for the owner under the
QBCC Home Warranty Insurance Policy. BPC was also notified that it had
a right to have the decision externally reviewed in this tribunal and that an
external review application must be lodged with the tribunal within 28 days
of the decision. Alternatively, BPC was notified that it could seek internal
review of the decision by a QBCC officer and that an internal review
application must be lodged within 28 days. The decision maker was Ms
Nicola White, Assessment Officer.
History of the applications now before the Tribunal
[7] According to the internal documents of the Tribunal’s registry, on 27
October 2015, BPC lodged in the Tribunal a Form 36 (Response and/or
counter application). The Tribunal stamped the form received on that date.
In that form, the QBCC was named as the respondent. That form was
initially inputted to another matter involving BPC before this Tribunal.
However, the case officer later considered, based on the content of the form
that it was perhaps intended to be a new application for review. In the
section of the form at Part D, “Details of Counter-application”, item 2 “The
reasons I consider the order/s sought should be made are;” BPC has stated:
“Nothing has been compromised and there is no structural defect. No
rectification is warranted/needed” and then reasons are offered as to why
that is so. BPC also lodged at that time, an “Alleged defective
work/incomplete work schedule” form. That is a form that must be lodged
with a Form 25 (Application for commercial building dispute) or a Form 26
(Application for domestic building dispute).
[8] On 30 October 2015, registry staff had a discussion with Mr Pitt and he
confirmed that he was seeking to review a decision of the QBCC and he
was correctly informed that the appropriate form for that purpose was a
Form 23. As Mr Pitt was to lodge a new application it was decided to hold
the Form 36 until 11 November with a view to possibly returning it to him
once the Form 23 was received and processed.
[9] On 24 November 2015, BPC filed in the Tribunal a Form 23, “Application to
review a decision”. The application was duly stamped by the registry, the
relevant fee is recorded as having been paid and the application was
allocated a case number. Part B of that form states:
“Details of decision to be reviewed…:
1151046-14
-- 3 of 13 --
4
When was the decision made?
? 29/09/2015
When did you receive the decision?
? 29/09/2015”
[10] In Part C of the Form 23, when asked to state briefly why the applicant thinks
the decision is wrong or not properly made, BPC states, amongst other
things, “Nothing has been compromised and there is no structural defect.
No rectification is warranted/needed” and then reasons are offered as to
why that is so. The Form 23 was thus in similar terms to the Form 36
previously lodged on 27 October 2015.
[11] Upon BPC lodging the application for review on 24 November 2015, it was
decided that there was no need to return the service copies of the Form 36
to BPC as it not relevant to an application for review.
[12] The application to review a decision was accepted by the registry and on
11 December 2015 directions were issued by the Tribunal for the future
progress of the matter.
[13] On 11 December 2015, BPC was notified by the QBCC that it was
proceeding with a claim for defective work under the Queensland Home
Warranty Scheme and that if any payment was made on the claim, the
QBCC may seek recovery from BPC under s 71 of the QBCC Act.
[14] On 17 December 2015, The QBCC served a notice on BPC advising that it
had approved a claim under the statutory insurance scheme.
[15] By letter dated 7 January 2016, the QBCC informed the Tribunal that the
application for review was not lodged within time and BPC had not applied
to extend the time limit for lodging the application for review.
The applications to extend time or proceed out of time
[16] Following an application for miscellaneous matters being filed by the QBCC,
the Tribunal made directions that BPC file and serve an application for an
extension of time together with submissions in support of the application by
a certain date. The QBCC was directed to file and serve submissions in
response and it was directed than the application for an extension of time
would be determined on the papers unless the parties requested an oral
hearing.
[17] On 30 March 2016, BPC made an application for miscellaneous matters
seeking directions that consideration be given to allowing BPC’s application
filed 24 November 2015 to proceed out of time because the principal
registrar accepted the application under s 35 of the QCAT Act and the
Tribunal had made directions in the proceeding.
[18] On 7 April 2016, BPC filed an application to extend or shorten a time limit
or for waiver of compliance with procedural requirement.
-- 4 of 13 --
5
[19] On 16 May 2016, the Tribunal initiated a hearing in this application in order
to ensure that the parties were given a proper opportunity to make
submissions in relation to all potential issues for the tribunal’s determination.
Mr Barry Pitt attended that hearing on behalf of BPC. The QBCC was
represented by Ms Rojas. The Tribunal asked BPC whether in fact BPC
sought to have the direction to rectify decision in relation to item 1 reviewed
by the Tribunal. BPC informed the Tribunal that it did. It was also agreed
that BPC had not undertaken any rectification works in relation to item 1 of
the direction to rectify as it did not consider that the work was defective.
[20] The Tribunal also raised with the parties whether it was open for the Tribunal
to regard BPC’s application to review a decision as an application to review
the direction to rectify decision and BPC’s application to extend the time for
making the application as an application to extend the time to apply for a
review of the direction to rectify decision. Further, the Tribunal asked BPC
about the delay in filing the application to review a decision. Mr Pitt in
response informed the Tribunal of the documents he had previously filed in
October 2015. Out of that hearing, the Tribunal made further directions for
filing of further written submissions.
[21] Upon receipt of BPC’s submissions outlining that he had earlier lodged
incorrect forms with the tribunal and had waited for their return before filing
the application for review in these proceedings, the Tribunal conducted a
search for any such documents. The Tribunal located the Form 36 and
associated documents which are referred to in these reasons.
[22] The Tribunal provided the relevant documents to the QBCC following a
further directions hearing on 15 September 2016 and provided the parties
with an opportunity to lodge and further submissions. Mr Tan represented
the QBCC at the directions hearing.
[23] In determining the two applications made by BPC, the Tribunal has
considered the applications and all written submissions made by the parties
as well as the oral information provided to the parties at the hearing and
directions hearing.
What is the reviewable decision?
[24] This Tribunal’s review jurisdiction is the jurisdiction conferred on it by an
enabling Act to review a decision made by another entity under that Act
known as a “reviewable decision”.1 In this case, the enabling Act is the
Queensland Building and Construction Commission Act 1991 (Qld) (QBCC
Act).
[25] Section 86 of the QBCC Act lists each decision that is a “reviewable
decision”. Included in the list are the following decisions:
a decision to give a direction to rectify2
1 QCAT Act, s 17.
2 QBCC Act s 86(1)(e).
-- 5 of 13 --
6
a decision that building work undertaken at the direction of the
commission is or is not of a satisfactory standard.3
[26] The QBCC says that while BPC’s application for review states that it seeks
to review QBCC’s decision dated 29 September 2015 that building work
undertaken at the direction of the Commission is not of a satisfactory
standard, in fact, BPC seeks a review of QBCC’s decision to give the
direction to rectify on 25 August 2015, specifically item 1.
[27] It is common ground that BPC has not undertaken any building work in
compliance with the direction given in relation to item 1.
[28] The QBCC says that BPC is prevented from reviewing the decision to give
a direction to rectify because of s 86F(1)(b) of the QBCC Act which provides:
(b) a decision to give a person a direction to rectify or remedy, and any
finding by the commission in arriving at the decision if—
(i) 28 days have elapsed from the date the direction was served on a
person and the person has not, within that time, applied to the
tribunal for a review of the decision; and
(ii) the commission has—
(A) started a disciplinary proceeding against the person under
part 6A; or
(B) served a notice on the person advising a claim under the
statutory insurance scheme has been approved in relation to
the building work relevant to the direction; or
(C) started a prosecution, or served an infringement notice, for an
offence against section 73 in relation to the direction;
[29] BPC agreed at the hearing that it takes issue with the decision to give the
direction to rectify. The material it filed in the Tribunal prior the application
for extension of time clearly seeks to establish that there were no grounds
for the direction to be given. As the Tribunal has already said, it is common
ground that since the direction was given, no rectification work has been
carried out by BPC in relation to item 1 of the direction to rectify.
Does the Principal Registrar’s acceptance of the application cure any issue
regarding the application being lodged outside the relevant time limit?
[30] Section 33 of the Queensland Civil and Administrative Tribunal Act 2009
(Qld) (QCAT Act) sets out how a proceeding is started. Section 33(3)
provides that if the application is for the review of a reviewable decision, the
application must be made, by filing it in the registry, within 28 days after the
relevant day. “Relevant day” in this case means the day the applicant is
notified of the decision.4
[31] Section 35 of the QCAT Act upon which BPC relies provides that the
principal registrar may accept the application without imposing any
3 QBCC Act s 86(1)(f).
4 S 33(4)(a).
-- 6 of 13 --
7
condition and may reject an application if it is made after the expiry of the
period within which it is required to be made under the QCAT Act. While this
provision gives the principal registrar a discretion not to reject an application
made after the expiry of a time period, it must be read in the context of Part
3 of the QCAT Act which relates to starting proceedings.
[32] Section 36 provides that a proceeding starts when the principal registrar
accepts an application or referral whether or not on conditions.
[33] Section 33(3) is plain and specifically refers to applications for review of a
reviewable decision; the application must be made by filing it in the registry
within 28 days of the relevant day. Under s 61 of the QCAT Act, the Tribunal
can extend the a time limit fixed for the start of a proceeding by the QCAT
Act or an enabling Act or waive compliance with another procedural
requirement under the QCAT Act or the enabling Act or the rules. The
Tribunal considers it worthwhile setting out the terms of s 61:
61 Relief from procedural requirements
(1) The tribunal may, by order—
(a) extend a time limit fixed for the start of a proceeding by this Act or
an enabling Act; or
(b) extend or shorten a time limit fixed by this Act, an enabling Act or
the rules; or
(c) waive compliance with another procedural requirement under this
Act, an enabling Act or the rules.
(2) An extension or waiver may be given under subsection (1) even if the
time for complying with the relevant requirement has passed.
(3) The tribunal can not extend or shorten a time limit or waive compliance
with another procedural requirement if to do so would cause prejudice or
detriment, not able to be remedied by an appropriate order for costs or
damages, to a party or potential party to a proceeding.
(4) The tribunal may act under subsection (1) on the application of a party or
potential party to the proceeding or on its own initiative.
(5) The tribunal’s power to act under subsection (1) is exercisable only by—
(a) the tribunal as constituted for the proceeding; or
(b) a legally qualified member, an adjudicator or the principal
registrar.
[34] As s 33(3) is the more specific provision to ss 35 and 36, the Tribunal is
satisfied that the principal registrar’s acceptance of the application filed 24
November 2015 cannot supersede the requirement for BPC to apply for an
extension of time in order for its application for review to be considered
properly filed in the registry under s 33(3).5
Has BPC applied within time to review a reviewable decision?
5 Also see the notes to s 33(3).
-- 7 of 13 --
8
[35] The application for review lodged with the Tribunal on 24 November 2015
appears to substantially comply with the Queensland Civil and
Administrative Tribunal Rules 2009 (Qld). In accordance with rule 31 it was
filed as the principal registrar stamped it with the tribunal’s seal. It also
states the reasons for the application so that it satisfied s 33(2) of the QCAT
Act. It is in the appropriate form, a Form 23.
[36] BPC does not say with any specificity when it was notified of the failure to
rectify decision made 29 September 2015. BPC submits that the Tribunal
should determine that the notice was sent by letter and received in the
ordinary course of the post i.e. two business days later on 1 October 2015.
Therefore, any application for review was required to be lodged by no later
than 29 October 2015. The Tribunal finds accordingly.
[37] Applying that same calculation to the direction to rectify decision made 25
August 2015, any application for review was required to be lodged by no
later than 24 September 2015. The Tribunal finds accordingly.
[38] Therefore, the application for review filed 24 November 2015 was filed more
than 28 days after notice of both the direction to rectify decision and the
failure to rectify decision was given to BPC.
[39] BPC relies on its lodgement of the Form 36 on 27 October 2015 and further
that part of the reason for its failure to lodge the Form 23 until 24 November
2015 was that BPC was awaiting the return of the Form 36 documents by
the Tribunal. While BPC’s submissions about when the earlier incorrect
forms were lodged was somewhat inconsistent with the documents located
by the Tribunal, further searches by the Tribunal of other files relating to
BPC failed to locate any other documents. At the last directions hearing,
BPC accepted that the forms located by the Tribunal were likely the forms
referred to in its submissions. Based on the evidence before me, in
particular, the location of the documents filed on 27 October 2015; the
searches conducted by the Tribunal for any other documents; Mr Pitt’s
description of his interaction with the Tribunal’s registry in relation to the
documents he filed in error being largely consistent with what is recorded
by the registry in relation to those documents filed on 27 October 2015, the
Tribunal finds that the only other documents filed by the BPC which
purported to challenge the decisions of the QBCC were the Form 36 and
other documents lodged on 27 October 2015.
[40] The Form 36 was lodged within 28 days of the failure to rectify decision
made 29 September 2015. However, it was not lodged within 28 days of the
direction to rectify decision made on 25 August 2015.
Can the Form 36 be regarded as an application for review of a reviewable
decision?
[41] Section 33 of the QCAT Act sets out the requirements for making an
application. Section 33(2) provides that the application must be in a form
substantially complying with the rules and state the reasons for the
application and be filed in the registry.
-- 8 of 13 --
9
[42] Rule 30 of the QCAT Rules provides that a document filed by post must be
accompanied by a stamped envelope for return post. It is unclear to the
Tribunal whether a stamped envelope for return post was included with the
Form 36.
[43] Rule 31 of the QCAT Rules provides that a document is filed when the
principal registrar records the document and stamps the tribunal’s seal on
it. The Form 36 does not bear the Tribunal’s seal.
[44] Rule 32 of the QCAT Rules provides that the principal registrar may refuse
to file a document if it does not comply with the rules or it cannot otherwise
be filed. If the principal registrar refuses to file a document a person filed by
post, the principal registrar must return the document to the person in the
envelope accompanying the document under rule 30. It is clear that the
Form 36 was not returned to BPC.
[45] In Smith v Queensland Building Services Authority6 it was held that an
application was not filed for the purposes of s 33 if the tribunal seal was not
stamped on the document. However, the Tribunal was prepared to exercise
its power under s 61(1)(c) of the QCAT Act to waive this procedural
requirement in circumstances where, although the application had been
lodged and accepted, the filing fee had not been paid.
[46] While it is clear that BPC in fact lodged the Form 36 within the relevant time
limit for seeking review of the failure to rectify decision made 29 September
2015, BPC does not seek to review that decision. It is clear that it seeks to
review the decision to give the direction to rectify made 25 August 2015.
[47] Further, and in any event, it is common ground that BPC has not undertaken
any building work in relation to item 1 of the direction of the QBCC.
Therefore, any application to review the failure to rectify decision made 29
September 2015 is without merit.
[48] For those reasons, the Tribunal does not consider there is any utility in
waiving the procedural requirements to enable the Form 36 to be regarded
as an application for review of the failure to rectify decision made by the
QBCC on 29 September 2015.
[49] For the same reasons, the Tribunal will not exercise its discretion to extend
the time for the lodging of the application for review filed 24 November 2015
insofar as it can be taken to be an application for a review of the QBCC’s
decision dated 29 September 2015.
Can the Form 36 or the application for review lodged 24 November 2015 be
regarded as an application for review of the decision to give the direction
to rectify?
[50] The QBCC says that the application for review lodged 24 November 2015
identifies the decision under review as the decision that the building work
6 [2010] QCAT 448 at [13].
-- 9 of 13 --
10
undertaken at the direction of the Commission is not of a satisfactory
standard. The identifying information is the following:
Details of decision to be reviewed…:
1151046-14
When was the decision made?
? 29/09/2015
When did you receive the decision?
? 29/09/2015
[51] However, the Tribunal notes that the QBCC also relies on the fact that the
grounds for the review referred to by BPC clearly reference his objection to
the giving of the direction to rectify in the first place.7 Indeed, the QBCC
argues that BPC’s application to review has no merit for that reason. BPC
also confirmed at the hearing that it is the giving of the direction to rectify in
relation to item 1 that it says was not correct and seeks to challenge.
[52] Even allowing a week for the receipt of the direction to rectify decision, BPC
had until the end of September 2015 to apply for review. The Form 36 was
not lodged with the Tribunal within the 28 days period.
[53] Therefore, BPC can only proceed to have the direction to rectify decision
reviewed if the Tribunal:
a) Treats the application for review filed 24 November 2015 as an
application to review the direction to rectify decision made 25 August
2015; and
b) Extends the time for the making of the application to review under s
61(1) of the QCAT Act.
[54] The QBCC submits that it is clear from BPC’s application to review that BPC
sought to review the failure to rectify decision and has not applied to review
the direction to rectify decision. The QBCC further submits that the Tribunal
cannot ‘substitute’ the direction to rectify decision for the failure to rectify
decision to allow BPC to review the direction to rectify decision. The QBCC
submits that s 86F of the QBCC Act applies so that since 11 December
2015 the direction to rectify decision is not a reviewable decision.
[55] The Tribunal does not seek to substitute the direction to rectify decision for
the failure to rectify decision but it has considered whether the application
to review a decision filed on 24 November 2015 can be taken to be an
application to review the direction to rectify decision. It is the Tribunal’s view
that it can. It is clear from the grounds of the application that BPC sought to
review the direction to rectify decision. The Tribunal has been guided by the
following reasoning of the Administrative Appeal Tribunal constituted by
7 Respondent’s submission in response to application to extend time dated 21 April 2016
at [20] to [24] inclusive.
-- 10 of 13 --
11
Deputy President Jarvis in the decision of Kowalski v Repatriation
Commission8:
…Instruments should be construed in accordance with the maxim falsa
demonstratio non nocet, that is, an imperfect or inaccurate description will
not vitiate an instrument. …
I think that the application of the falsa demonstratio maxim in the present
circumstances is also supported by Minister for Immigration and Multicultural
Affairs v Eshetu (1999) 197 CLR 611 where Gaudron and Kirby JJ, after
referring to a provision similar to s 119(1)(g) of the VE Act, said at, [76], that
it would be an error of law for the Refugee Review Tribunal to decline
jurisdiction because of some technical error in the application for review.
Section 119(1)(g) requires the Commission (and this tribunal standing in its
shoes) to act according to substantial justice and substantial merits of the
case without regard to legal form and technicalities.
The above common law maxim applies where the intention of the person who
made the instrument is clear. In the present case, Mr Kowalski clearly
intended to invoke the jurisdiction of this tribunal because he was dissatisfied
with the decision of the VRB. The error he made in referring to the wrong
decision was an obvious error, and should not render his application for
review ineffective.
[56] That means that BPC’s application to review the direction to rectify decision
was filed on 24 November 2015 and was filed prior to the notice issued by
the QBCC on 17 December 2015. While s 86F(1)(b)(i) was met at the time
of filing the application to review as 28 days had elapsed since the direction
to rectify decision was made, s 86F(1)(b)(ii)(B) of the QBCC Act was not at
that time satisfied. The direction to rectify decision remained a reviewable
decision subject to the granting of an extension of time in which to file the
application.
[57] In determining whether to extend the time for making the application to
review the Tribunal must consider a number of matters. Section 61(3) of the
QCAT Act is relevant and has already been set out above.
The delay
[58] BPC has not explained why it did not seek review of the decision to give a
direction to rectify within the 28 days of receiving the decision. This weighs
against exercising the discretion to extend the time. The delay in this case
is a month. It is not a lengthy delay.
Is it fair and reasonable?
[59] BPC has filed material to support its contention that there was no defective
work. The direction to rectify decision has ramifications for BPC’s licence. A
notation of the decision will appear on any search of BPC’s licence.
[60] From the QBCC’s point of view, its administrative decision making process
has moved on, as it was of the view that BPC wished to review the decision
8 [2008] AATA 903 at [133] to [135] inclusive.
-- 11 of 13 --
12
of the QBCC that BPC had not satisfactorily carried out rectification work as
directed. The QBCC has processed a claim under the statutory insurance
scheme. The QBCC argues that if the extension of time is granted it will be
significantly disadvantaged as it would have lost the ability to withhold
payment pursuant to the statutory insurance scheme. The QBCC further
submits that will be deprived of the opportunity to reject the insurance claim
on the basis of matters now sought to be agitated by BPC after the claim
has been approved. The QBCC submits that throughout the dispute
resolution process, BPC had plenty of opportunity to raise the reasons as
to why the defects were alleged by it not to be defects but it did not do so.9
[61] The QBCC further submits that now that it has made a payment under the
insurance scheme, if time were extended and BPC successful it would have
to recover the amounts already paid under the insurance scheme. That
would impact others. It submits that granting of an extension of time will
have implications in relation to the recovery of the insurance claim. The
homeowner will be impacted. It is further submitted that this would be
contrary to the justice of the case.10
[62] The Tribunal accepts the prejudice to the QBCC and others as submitted
by the QBCC. In addition to the arguments raised by the QBCC the Tribunal
considers that there is a public interest in finality of administrative decision
making.
[63] The Tribunal considers that the prejudice to the QBCC and others and
taking into account the public interest outweighs the prejudice to BPC. The
Tribunal considers that those matters weigh in favour of finding that it is not
fair and reasonable to extend time.
Prejudice
[64] The matters relating to whether it is fair and reasonable to extend time are
also relevant to a consideration of the prejudice to the parties.
[65] The Tribunal considers that the prejudice to the QBCC and third parties if
the extension of time is granted outweighs the prejudice to BPC if the
extension of time is not granted. Further as I have already found, the public
interest weighs against extending the time to file the application to review.
Prospects of success
[66] BPC has filed material in the Tribunal including from an engineer and PHD
Timber Importers and provided his own evidence as to the work he carried
out and the work carried out by others. It is not for the Tribunal in considering
this application to make any findings in relation to the issues for the
determination in the substantive review should the extension of time be
granted. However, based on the material filed by BPC and the QBCC I
consider that BPC’s case is not without some merit.
9 Submissions of the QBCC dated 6 October 2016 [28] and [29].
10 Submissions of the QBCC dated 6 October 2016 [30]-[32] inclusive.
-- 12 of 13 --
13
Conclusion
[67] The Tribunal concludes that BPC’s failure to properly explain its reasons for
not seeking review of the direction to rectify decision within time, the
prejudice to the QBCC and third parties and the public interest all weigh
against extending the time for BPC to apply for review of the direction to
rectify decision.
[68] The Tribunal has also concluded that as there is no merit to an application
by BPC to review the failure to rectify decision, it will not exercise the
discretion in s 61(1) to waive compliance with the rules for starting
proceedings. Further, the Tribunal will also not extend the time for the
application to review lodged 24 November 2015 to review the failure to
rectify decision.
[69] The application to extend or shorten a time limit or for waiver of compliance
with procedural requirement filed 7 April 2016 by BPC is dismissed.
[70] The application for miscellaneous matters filed 30 March 2016 by BPC is
also dismissed.
[71] It follows that the application for review filed 24 November 2015 must also
be dismissed the application filed by BPC cannot start a proceeding under
s 33 as it was filed out of time.
-- 13 of 13 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2016/482