Casey v Queensland Building and Construction Commission [2016] QCAT 424
CITATION: Casey v Queensland Building and
Construction Commission [2016] QCAT 424
PARTIES: Timothy Gavin Casey
(Applicant)
v
Queensland Building and Construction
Commission
(Respondent)
APPLICATION NUMBER: GAR043-14
MATTER TYPE: General administrative review matters
HEARING DATE: 18 February 2016
HEARD AT: Brisbane
DECISION OF: Dr Cullen, Member
DELIVERED ON: 10 November 2016
DELIVERED AT: Brisbane
ORDERS MADE: 1. The 17 May 2012 decision of the QBSA
that Mr Casey was an excluded
individual in relation to St Hilliers Ararat
Pty Ltd ‘Ararat’ and St Hilliers Pty Ltd
‘Construction’ is set aside.
2. The 13 June 2014 decision of the
Queensland Building and Construction
Commission (‘QBCC’) that Mr Casey
was an excluded individual in relation to
St Hilliers Pty Ltd ‘SHPL’ is set aside.
3. In substitution, the Tribunal decides
that pursuant to s 56AC of the
Queensland Building and Construction
Commission Act 1991 (Qld) (as it
applied on 15 May 2012), Timothy Gavin
Casey is an excluded individual
because he was a Director of St Hilliers
Ararat Pty Ltd at the time of liquidators
being appointed on 15 May 2012.
CATCHWORDS: OCCUPATIONAL REGULATION –
EXCLUDED INDIVIDUAL – STATUTORY
CONSTRUCTION – interpretation of s 56AC(6)
and what is meant by ‘consequences flowing
-- 1 of 10 --
2
from what is, in substance, the one set of
circumstances’.
Corporations Act 2001 (Cth)
Queensland Building and Construction
Commission Act 1991 (Qld), s 56AC, s 56AF
Alcan (NT) Alumina Pty Ltd v Commissioner of
Territory Revenue (Northern Territory) (2009)
239 CLR 27
Grey v Pearson (1857) 6 HLC 61
Project Blue Sky Inc. v Australian Broadcasting
Authority (1998) 194 CLR 355
REPRESENTATIVES:
APPLICANT: G D Beacham, QC instructed by M C Long of
TressCox Lawyers for the Applicant
RESPONDENT: M Robinson, Robinson Locke Litigation
Lawyers for the Respondent
REASONS FOR DECISION
[1] The Applicant in this matter, Mr Timothy Gavin Casey, is the founder of the
St Hilliers’ group of companies. In 2012, each of the companies that was
part of the group became subject to a form of external appointment under
the Corporations Act 2001 (Cth).
[2] At the time of the external appointments, Mr Casey was a director of each
of the companies. As a consequence, the Queensland Building Services
Authority (‘QBSA’ as it was then known) and subsequently the Queensland
Building and Construction Commission (‘QBCC’), notified him that he was
an “excluded individual” in relation pursuant to s 56AC(6) of the Queensland
Building Services Authority Act 1991 (Qld), as follows:
17 May 2012 decision of the QBSA that Mr Casey was an excluded
individual in relation to St Hilliers Ararat Pty Ltd (‘Ararat’) and St Hilliers
Construction Pty Ltd (‘Construction’).
13 June 2014 decision of the Queensland Building and Construction
Commission (‘QBCC’) that Mr Casey was an excluded individual in
relation to St Hilliers Pty Ltd (‘SHPL’).
-- 2 of 10 --
3
[3] The company arrangements for the St Hilliers’ group, decisions of the
QBSA/QBCC, and review by Mr Casey, can be summarised as follows:1
Company Date Form of
Appointment
Outcome of
Appointment
Decision
by
QBSA/
QBCC
Review in
the
Tribunal
St Hilliers Ararat
Pty Ltd (‘Ararat’)
15 May
2012
Liquidation Deregistered on
3 November
2013
Mr Casey
is an
Excluded
Individual
QCAT
Review
GAR043-
14
St Hilliers
Construction Pty
Ltd
(‘Construction’)
15 May
2012
Administration Deed of
company
arrangement,
wholly
effectuated on
28 July 2014
Mr Casey
is an
Excluded
Individual
QCAT
Review
GAR043-
14
St Hilliers Pty Ltd
(‘SHPL’)
6
September
2012
Administration Deed of
company
arrangement,
wholly
effectuated on
24 July 2013
Mr Casey
is an
Excluded
Individual
QCAT
Review
OCR148-
14
STH Holdings
Pty Ltd (‘SHH’)
6
September
2012
Administration Deed of
company
arrangement,
wholly
effectuated on
29 July 2013
QBCC did
not issue
a notice.
St Hilliers (SP)
Pty Ltd (‘SHSP’)
6
September
2012
Administration Deed of
company
arrangement,
wholly
effectuated on
29 July 2013
QBCC did
not issue
a notice.
[4] As indicated in the chart above, the Tribunal has been asked to review three
decisions made by the QBCC2 that Mr Timothy Gavin Casey is an ‘excluded
individual’ pursuant to the relevant legislation.3
1 Helpfully, these arrangements have been outlined in the Outline of Submissions filed
on behalf of Mr Casey in the Tribunal, at paragraphs [5]-[6].
2 And the QBCC’s predecessor, the Queensland Building Services Authority.
3 Queensland Building Services Authority Act 1991 (Qld), Part 3A; Queensland Building
Construction Commission Act 1991 (Qld) – (‘the Act’).
-- 3 of 10 --
4
[5] The effect of the QBCC’s decisions, if confirmed by the Tribunal, would be
that Mr Casey became a ‘permanently excluded individual’ by virtue of the
operation of Part 3B of the Act. Were this to happen, Mr Casey would be
prevented from participating in the Queensland building and construction
industry for the rest of his life.
[6] Mr Casey’s argument before the Tribunal relates to the proper interpretation
of s 56AC(6) of the Act. It is Mr Casey’s contention that s 56AC(6) applies
to each of the ‘relevant events’ that led to his becoming an excluded
individual with the end result that they should be considered a single
relevant event. He says that the ‘relevant events’ were, ‘consequences
flowing from what is, in substance, the one set of circumstances’.
Legislative Framework
[7] Section 56AC of the Act provides, relevantly:
(2) This section applies to an individual if-
(a) … a company, for the benefit of a creditor:
(i) has a provisional liquidator, liquidator, administrator or
controller appointed; or
(ii) is wound up, or is ordered to be wound up; and
(b) 5 years have not elapsed since the event mentioned in paragraph
(a)(i) or (ii) (relevant company event) happened; and
(c) the individual-
(i) was, when the relevant company event happened, a director
or secretary of, or an influential person for, the company; or
(ii) was, at any time after the commencement of this section and
within the period of 1 year immediately before the relevant
company event happened, a director or secretary of, or an
influential person for, the company.
…
(4) If this section applies to an individual because of subsection (2), the
individual is an excluded individual for the relevant company event.
…
(6) An excluded individual for a relevant company event (the first event) does
not also become an excluded individual for another relevant company
event (the other event) if the first event and the other event are both
consequences flowing from what is, in substance, the one set of
circumstances applying to the company.
[8] It is the case that these provisions of the Act have now been statutorily
modified, following passage of the Professional Engineers & Other
-- 4 of 10 --
5
Legislation Amendments Act 2014 (Qld). However, those amendments
commenced on 10 November 2014, and do not bear upon the law as it was
at the time of the relevant events in this matter.
[9] Simply put, the dispute about interpretation between the parties relates to
the way that the relevant events are counted. The parties agree that
s 56AC(6) applies to the relevant events for SHPL, SHH and SHSP. The
parties also agree that the QBCC did not issue any notices in relation to
SHH and SHSP.
[10] Despite the agreement about the application of s 56AC(6), the parties do
not agree about the way in which the section is to be interpreted. The
proper interpretation has an impact upon the Tribunal’s decision in relation
to the Applications before it, which are in relation to Ararat, Construction
and SHPL.
Interpretation of s 56AC(6)
[11] The QBCC asserts that the same set of circumstances applied to SHPL,
SHH and SHSP, such that s 56AC(6) applies and they are collectively one
‘relevant event’. Mr Casey contends that the effect of s 56AC(6) is not to
amalgamate those three company events into a single event, as the QBCC
suggests. Rather, Mr Casey says that each relevant company event
remains, but the correct interpretation of the legislation is that he is only an
excluded individual for the relevant event for SHPL.
[12] Mr Casey argues that, properly applied, the test in s 56AC(6) should lead
to the Tribunal determining that the relevant events which led to Ararat,
Construction and SHPL are ‘consequences flowing from what is, in
substance, the one set of circumstances.’
[13] The QBCC contends that s 56AC(6) does not apply to Ararat and
Construction as ‘...whilst flowing from a related series of events, the
particular triggers were different’.4 The QBCC then contends that s 56AC(6)
does not apply to the relevant event for SHPL because:
The circumstances operating in May 2012 in relation to Ararat and
Construction do not appear to be the same set of circumstances that applied
to [SHPL] on 6 September 2012.
As a result, the particular triggers were different.
[14] The quandary in relation to the QBCC’s approach is that, if such a narrow
approach is taken in relation to the operation of s 56AC(6), Mr Casey has
tallied up three, rather than one, exclusions in relation to relevant events.
This would be without Mr Casey having had any opportunity for objective
review about whether the relevant events were consequences flowing from
what he says is the first event (Ararat).
4 Statement of Reasons for Decision, dated 27 February 2014, paragraph 13; Exhibit 16.
-- 5 of 10 --
6
SHH and SHSP are not relevant to the Applications now before the
Tribunal
[15] Mr Casey says that the correct and preferable decision is that the Ararat
relevant event is the ‘first event’ and that this had a domino effect in relation
to Construction and SHPL. He also contends that, for purposes of this
application, that SHH and SHSP are not relevant, and the Tribunal should
not consider evidence in relation to those companies. This is, in the
Tribunal’s view, the correct approach in these particular circumstances.
[16] The QBCC has not issued a written notice to Mr Casey in relation to either
SHH or SHSP, for the reason that they consider that s 56AC(6) applies,
such that they arose from the same set of circumstances at SHPL. As there
is no review before the Tribunal in relation to SHH and SHSP, there is
therefore no rational basis to consider evidence in relation to SHH and
SHSP.
[17] This view is further supported by the fact that the SHH and SHSP relevant
events were the last 2 cabs off the rank in the various company
arrangements made in relation to members of the St Hilliers group. On this
basis, it is difficult to see what impact the later demise of SHH and SHSP
could have had upon the demise of the earlier arrangements entered into
on behalf of Ararat, Construction and SHPL.
[18] As identified in the chart above, it is the QBCC decisions to exclude Mr
Casey in relation to Ararat, Construction and SHPL that are the reviewable
decisions now before the Tribunal. Section 56AF of the Act provides:
(1) This section applies if the authority considers that an individual who is a
licensee is an excluded individual for a relevant event.
(2) The commission must give the individual a written notice identifying the
relevant event and stating the following—
(a) why the commission considers the individual is an excluded
individual for the relevant event;
(b) the individual may apply to the commission to be categorised as
a permitted individual for the relevant event if the individual has
not already done so;
(c) the circumstances, stated in subsection (3), in which the
commission must cancel the individual’s licence.
[19] As a result of the QBCC making the decision that s 56AC(6) applies to SHH
and SHSP, Mr Casey cannot be considered to be an excluded individual in
relation to the SHH and SHSP relevant events.
[20] That the QBCC made the decision that it considers s 56AC(6) to apply to
SHPL, SHH and SHSP should not serve as a basis to now preclude Mr
Casey from arguing that, despite the QBCC’s view, the difficulties faced by
Construction and SHPL flow back to the first event, Ararat. To prevent this
-- 6 of 10 --
7
argument from being ventilated would prevent a genuine consideration by
the Tribunal of the factors that led to the challenges faced by Ararat,
Construction and SHPL. Where the resulting decision has the consequence
of preventing an ‘influential person’ in relation to a company from working
in the industry, taking such a narrow view of s 56AC(6) is unjust.
[21] The interpretation of s 56AC(6) contended for by Mr Casey is logical – after
all, Ararat was, in a temporal context, the ‘first event’ for the St Hilliers’ group
of companies. As such, it provides a sensible starting point for consideration
as to whether the circumstances that led to its liquidation had broader
reaching consequences for other companies in the group.
Section 56AC(6) should not be narrowed
[22] In his written submissions, Mr Casey’s Counsel draws the Tribunal’s
attention to the usual authorities cited in relation to statutory interpretation.
The Tribunal acknowledges that, in considering the correct approach to be
taken in relation to s 56AC(6), it is to have regard to the context and
legislative purpose of s 56AC(6). The Tribunal must give the words their
ordinary meaning; the section should not be read in isolation.5
[23] As mentioned earlier, the outcome of this matter will have life-altering
consequences for Mr Casey, his family, and potentially other persons such
as employees and contractors. It is clear that s 56AC(6) is intended to
countermand the profound effect of permanent exclusion where relevant
company events are consequences flowing from the one set of
circumstances.
[24] The approach taken by the QBCC in deciding whether s 56AC(6) applies is
to identify the ‘trigger’ that led to the relevant event happening. The reason
for this, presumably, is because of the chain of events that flows from the
QBCC making a decision that an individual is an ‘excluded individual’. As
the legislation applied at the relevant time, a licensee who wanted to
continue to work in the industry, despite being an excluded individual,
needed to then apply to be a ‘permitted individual’ in relation to the relevant
event. In order to be a permitted individual, the licensee needed to establish
that they took all reasonable steps in accordance with s 56AD of the Act to
avoid the coming into existence of the circumstances that resulted in the
happening of the relevant event. It is understandable that the QBCC would
then try to determine whether the licensee took ‘all reasonable steps’ by
identifying what it was that led to the happening of the relevant – i.e. ‘the
trigger’.
[25] However, whilst this is the approach that has been applied for some time in
reviews of this nature by the QBCC, the effect of same is to add an
additional test to the legislation, which has the effect, as demonstrated in
5 Alcan (NT) Alumina Pty Ltd v Commissioner of Territory Revenue (Northern Territory)
(2009) 239 CLR 27 at 31 and 46-7; Grey v Pearson (1857) 6 HLC 61 at 106; Project
Blue Sky Inc. v Australian Broadcasting Authority (1998) 194 CLR 355 at 381.
-- 7 of 10 --
8
Mr Casey’s circumstances, of narrowing the legislation. If applied in the
manner suggested by the QBCC, the Tribunal would be firstly required to
identify ‘the trigger’ (not part of the legislative provisions) and then go on to
consider whether the events are part of the ‘one set of circumstances’.
[26] Conceivably, the Tribunal may take a more global view as to the ‘one set of
circumstances’ that led to the demise of a group of related companies,
rather than identifying the specific trigger that led to the demise of one
member of the group. On its face, the legislation does not contain any
further tests that must be considered in deciding what the ‘one set of
circumstances’ is.
[27] Here, the preferable approach, and the only one that affords Mr Casey the
benefit of an unconstricted application of s 56AC(6) is to look at Ararat first,
and consider the impact its failure had on Construction and SHPL. The
Tribunal should ‘Begin at the beginning,’ and consider the fallout from
Ararat and when it has ‘come to the end: then stop.’6
The failure of the Ararat project, and its impact on Construction and SHPL
[28] The liquidation of Ararat was the ‘first event’ for purposes of s 56AC(6). The
Ararat event occurred at 7.55pm on 15 May 2012, just prior to the
Construction event at 8.30pm the same day.7 Ararat was a wholly owned
subsidiary of Construction. It was incorporated for purposes of an
unincorporated joint venture project with another construction project, the
purpose of which was to build the Ararat Prison in Victoria.
[29] The Ararat Prison project did not proceed according to plans, for many
reasons. The State of Victoria had contracted with Aegis Correctional
Partnership Pty Ltd (Aegis). Ararat failed after negotiations between the
State of Victoria and Aegis failed, resulting in the advice to Ararat that Aegis
would not be paying progress payments that had been certified, and which
totalled $4,649,564.
[30] Construction, as part of the Ararat project, provided a guarantee of Ararat’s
performance of the construction contract. Additionally, there were bonds
issued by Swiss Re under the Ararat Prison construction contract, in
relation to performance of the construction work by Ararat. These bonds
were guaranteed by Ararat, Construction and SHPL.
[31] Following the non-completion of the prison project, Ararat became liable for
non-completion damages. The Swiss Re bonds were called upon, leading
to Ararat, Construction and SHPL becoming liable for the amounts paid out
under the Swiss Re bonds.
[32] Construction, now having incurred liability in relation to the Ararat non-
completion and Swiss Re bonds, was in jeopardy in relation to some of its
6 Lewis Carroll, ‘Alice in Wonderland’.
7 Annexure A, Extension of Time Application filed 31 January 2014 in GAR043-14;
Minutes of Meetings, pages 21 and 23 of “Annexure 3”.
-- 8 of 10 --
9
own building projects. Construction’s own projects were secured by bonds
provided by Vero Insurance Limited. As a consequence of the fragility of
Construction’s own projects, occasioned by the demise of the Ararat prison
project, there were calls made on some of the Vero bonds.
[33] When the Ararat prison project failed, the value of Vero bonds issued in
relation to Construction was approximately $39 million. Of this amount,
approximately $13.7 million had been encashed. The calls on the Vero
bonds, and potential for further calls, led to a liability by both Construction
and SHPL to Vero.
[34] The QBCC acknowledge that the insolvency and liquidation of Ararat was
the catalyst for the administration of Construction. But, the QBCC says that:
The liquidation of Ararat was caused by its insolvency resulting from the
blow-out of the costs to complete the project, which were such that Ararat
could not complete and would breach the contract.8
The administration of Construction was because it gave a guarantee of
Ararat, the limit of which exceeded its net assets (and if related entity loans
are considered, the shortfall is substantial).
[35] The QBCC acknowledges that Ararat and Construction flow from a ‘related
series’ of events. Similarly, the administration of SHPL was the result of the
Swiss Re and Vero liabilities. The approach to determining the ‘trigger’ and
then narrowing the application of s 56AC(6) is not, for the reasons set out
above, the correct and preferable approach.
[36] The evidence before the Tribunal demonstrates that the Ararat,
Construction and SHPL events are ‘consequences flowing from what is, in
substance, the one set of circumstances’. The liquidation of Ararat had a
direct impact upon Construction and SHPL and arose from the failure of the
Ararat prison project.
[37] The difficulty with the argument that the QBCC makes in relation to Ararat,
Construction and SHPL can be illustrated with the following analogy.
Assume that Ararat, Construction and SHPL are, instead of companies, all
buildings located on a city block, which are destroyed following an
earthquake. The obvious common factor in their destruction is the
earthquake. The buildings may have been, depending on their structural
underpinnings, damaged in slightly different ways and to different degrees.
But, it could not logically be argued that the cause of any one of the
buildings falling related to the manner in which it was designed and built,
even if that may have had some impact on the level of destruction. Here,
the ‘earthquake’ was the failure of the Ararat prison project. Rather than
looking only at the detail referable to each company, the appropriate, and
fair approach, requires looking at the overarching genesis of the ‘one set of
circumstances’.
8 QBCC Statement of Reasons GAR043-14, 27 February 2014, para [12].
-- 9 of 10 --
10
[38] The Tribunal determines that s56AC(6) applies to the Ararat, Construction
and SHPL relevant events, such that Mr Casey is an excluded individual in
relation to the Ararat event.
Orders
1. The 17 May 2012 decision of the QBSA that Mr Casey was an
excluded individual in relation to St Hilliers Ararat Pty Ltd ‘Ararat’ and
St Hilliers Pty Ltd ‘Construction’ is set aside.
2. The 13 June 2014 decision of the Queensland Building and
Construction Commission (‘QBCC’) that Mr Casey was an excluded
individual in relation to St Hilliers Pty Ltd ‘SHPL’ is set aside.
3. In substitution, the Tribunal decides that pursuant to s 56AC of the
Queensland Building and Construction Commission Act 1991 (Qld) (as
it applied on 15 May 2012), Timothy Gavin Casey is an excluded
individual because he was a Director of St Hilliers Ararat Pty Ltd at the
time of liquidators being appointed on 15 May 2012.
-- 10 of 10 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2016/424